JPH041363A - Construction method of prestressed concrete structure - Google Patents

Construction method of prestressed concrete structure

Info

Publication number
JPH041363A
JPH041363A JP10382590A JP10382590A JPH041363A JP H041363 A JPH041363 A JP H041363A JP 10382590 A JP10382590 A JP 10382590A JP 10382590 A JP10382590 A JP 10382590A JP H041363 A JPH041363 A JP H041363A
Authority
JP
Japan
Prior art keywords
concrete
concrete structure
prestressed
reaction
prestressed concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10382590A
Other languages
Japanese (ja)
Inventor
Takenori Kumagai
武紀 熊谷
Yasuo Kuno
雍夫 久野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP10382590A priority Critical patent/JPH041363A/en
Publication of JPH041363A publication Critical patent/JPH041363A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To lighten a structure, and to shorten the term of work by forming reaction supporters unified with posts at both end sections of a girder while disposing PC steel in two vertical rows, introducing prestress and placing concrete to residual sections. CONSTITUTION:Reaction supporters 2 as one parts of a girder 1 unified with posts 10 are formed at both end sections of the girder 1 constituting a concrete structure A. PC steel 5 in two vertical rows are arranged between the reaction supporters 2 at both ends while reinforcing bars 4 are installed to connecting sections with each post 10. Prestress is introduced to upper and lower PC steel 5a and 5b, and concrete is placed to residual sections between the reaction supporters 2, thus shaping the girder 1. Accordingly, operating efficiency can be improved.

Description

【発明の詳細な説明】 「産業上の利用分野 本発明は、コンクリート構築物を築造するにあたり、既
に形成されたコンクリート構造体に、このコンクリート
構造体間にわたるプレストレストコンクリート構造物を
築造する方法に関するしのである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a prestressed concrete structure extending between already formed concrete structures when constructing a concrete structure. be.

「従来の技術」 周知のとおり、プレストレストコンクリート構造物を製
作する際のプレス)・レス導入方法としては、従来より
、プリテンンヨン法とボス)・テンノヨン法とかある。
``Conventional technology'' As is well known, there are conventional methods for introducing presses and presses when manufacturing prestressed concrete structures, such as the preten-yon method, the boss), and the ten-no-yon method.

前者は、PCI!i材の引張力を与えておいてコンクリ
ートを打ち込み、コンクリートの硬化後、P C鋼材に
与えておいた引張力をP C鋼材とコンクリートの付着
によりコンクリートに伝えてプレストレスを与える方法
であり、また複台は、コンクリート打ち込みに際し、P
CM材を通す位置にソースを埋め込み、コンクリートの
硬化後、このノースにPCM材を通して一端を定着し、
他端は水圧または油圧ツヤツキにより緊張し、その反力
でコンクリートに強力な圧縮を与えてから、くさび、ね
し等を用いて定着ζる、というしのである。この場合に
はさらに、鋼材の保護と部材の安全性のために、引き通
しの孔にモルタルを注入して鋼材とソースとを付着させ
る(ポンド工法)ことが望ましい。
The former is PCI! This is a method of applying prestress to the concrete by applying tensile force to the I material and pouring concrete, and after the concrete hardens, the tensile force applied to the PC steel material is transferred to the concrete by the adhesion of the PC steel material and concrete. Also, when using multiple units, P
Embed the source at the position where the CM material will pass, and after the concrete hardens, pass the PCM material through this north and fix one end,
The other end is tensioned by water pressure or oil pressure, and the reaction force applies strong compression to the concrete, which is then fixed using wedges, screws, etc. In this case, in order to protect the steel material and ensure the safety of the members, it is desirable to inject mortar into the lead-through hole to adhere the steel material and the source (pond construction method).

「発明か解決しようとする問題点J しかしながら、上記二つの方法にあってはそれぞれ次の
ような問題点があった。
``Problems to be Solved by the Invention'' However, each of the above two methods had the following problems.

すなわち、ブリテンション法においては、定着部の費用
かかからず、グラウト注入などの施工も不要であるか、
PCM材を予め緊張するための頑丈な反力台(アバ、l
ト)を必要とし、また、ボストテンノヨン法においては
、緊張設備などにあまり大型のものを必要とせず現場で
のプレストレスの導入作業は比較的容易であるがノース
の配設、およびグラウト充填など?二手間を要していた
。さらに、プレストレスの導入つまりPCM材の配設は
部材に生ずる応力を打ち消すことができるような形態に
行う必要があるが、このためにPCfl材の所定箇所を
その形態に合致するように屈曲させなければならず、そ
のPCj14材の屈曲配設は、上記ブリテンンヨン、ボ
ストテンンヨンいずれにおいても手間の掛かる作業であ
った。
In other words, in the britension method, there is no cost for the fixing part, and there is no need for construction such as grout injection.
A sturdy reaction table (ABA, l) for pre-tensioning the PCM material.
In addition, in the Bost Tennoyon method, it is relatively easy to introduce prestressing on site because it does not require very large tension equipment. It required two efforts. Furthermore, the introduction of prestress, that is, the arrangement of the PCM material, must be done in a form that can cancel out the stress generated in the member, and for this purpose, predetermined parts of the PCfl material must be bent to match the form. Therefore, bending and arranging the PCj14 material was a labor-intensive work in both the bulletin board and the boss board.

本発明は上g己の事情に鑑みてなされfこもので、大型
て運搬やセソティンクに手間を要する反力台を必要とせ
ず、PC1li材の屈曲配設をなくすと共に、シースの
配設およびグラウト充填などの作業を排除せしめるプレ
ストレス導入法、すなわち、工期短縮およびコスト低減
を実現するプレストレスの導入方法を提供することをそ
の目的とするものである。
The present invention has been made in view of the above circumstances, and eliminates the need for a large reaction force table that requires time and effort for transportation and sesotin, eliminates the need for bending the PC1li material, and eliminates the need for sheath placement and grout filling. The purpose of this invention is to provide a method for introducing prestress that eliminates the above operations, that is, a method for introducing prestress that shortens the construction period and reduces costs.

「問題点を解決するための手段。“A means to solve problems.

本発明は、コンクリート構築物を構築するにあたり、予
め形成された既成コンクリート構造体に瓦いに平行なる
二面を存して前記既成コンクリート構造体間にわたるプ
レストレストコンクリート構造物を築造するにおいて、
築造すべきプレストし・ストコンクリート構造物の両端
部に前記既成コンクリート構造体と一体となる反力支持
体を形成する工程と、該反力支持体間にPC鋼材を、築
造オへきブし・ストレストコンクリート構造物の内部に
位置4−るようにかつ前記平行なる二面にそれぞれ近接
するように二列に配設してこれを緊張する工程と、築造
すべきプレストレストコンクリート構造物の、前記既成
コンクリート構造体との接合部に前記二列のI)CM材
間にわrコる補強筋を設ける工程と、前記PCjlji
材の緊張後に目的とするプレストレストコンクリート構
造物を形成するためのコンクリートを打設する工程と、
この打設されたコンクリートの硬化後に前記PCM材の
緊張を解除することによりコンクリ−1・にプレストレ
スを導入する工程とを有することを特徴としている。
In constructing a concrete structure, the present invention provides a pre-stressed concrete structure in which a pre-formed concrete structure is provided with two surfaces parallel to tiles and spans between the pre-formed concrete structures.
A process of forming reaction force supports that are integrated with the pre-formed concrete structure at both ends of the prestressed concrete structure to be constructed, and placing a PC steel material between the reaction force supports in the construction oven. a step of arranging the prestressed concrete structures in two rows so as to be located inside the stressed concrete structure and in proximity to the two parallel surfaces and tensioning them; A step of providing reinforcing bars between the two rows of I) CM materials at the joint with the precast concrete structure, and
a step of pouring concrete to form the desired prestressed concrete structure after the material is tensioned;
The method is characterized in that it includes a step of introducing prestress into the concrete 1 by releasing the tension of the PCM material after the cast concrete has hardened.

「作用 」 築造すべきプレストレストコンクリート構築物の両端1
ラーメンまたは複数ラーメン構造等の架橋を利用して反
力支持体を形成する。PC鋼材を緊張するために、従来
のプリテンノヨン法による大掛かりな反力台を使用せず
現場でのpca材の緊張か可能となる。また、築造され
るプレストレストコンクリート構造物はその厚さ方向に
PCjllji材か二列(二段)に配設されたものとな
り剛性が高いものとなる。さらに、形成されたプレスト
レストコノクリート構造物の大部分は、いわゆるプノテ
ンンヨン法によるプレストレスの導入か行なわれるため
、ノースの配設、グラウト充填なとの作業のほとんどを
削除することができる。
"Action" Both ends of the prestressed concrete structure to be constructed 1
Cross-linking, such as a rigid frame or multiple rigid frame structure, is utilized to form a counterforce support. In order to tension the PC steel material, it is possible to tension the PCA material on-site without using the large-scale reaction table of the conventional pre-tension method. Furthermore, the prestressed concrete structure to be constructed will have high rigidity because the PCJllji materials will be arranged in two rows (two stages) in the thickness direction. Furthermore, since most of the prestressed conocrete structures formed are prestressed by the so-called punching method, most of the work such as arranging the north and filling with grout can be eliminated.

[実施例」 以下、本発明の実施例を図を参照しながら説明する。第
1図ないし第4図は、本発明をRC(鉄筋コンクリート
)構造物を構成する梁に適用したものである。
[Example] Hereinafter, an example of the present invention will be described with reference to the drawings. 1 to 4 show the present invention applied to beams constituting an RC (reinforced concrete) structure.

図中、全体として符号1て示すものが目的とするプレス
トレストコレンクリート粱(以下、単に粱と略す)であ
る。粱Iは、これを支持する柱10と共にコンクリート
構築物Aを構成するもので、この梁lを支持すべき柱1
0は既に地盤Gに立設されている。そして、これらの既
成コンクリート構造体すなわち前記柱IOに粱1を築造
するには次の方法による。なお、図において、鉄筋は第
4図を除いて省略してあり、また柱lOには、これら柱
10にわたる粱1を形成するf二めの型枠か付設されて
いるものとしている。
In the figure, what is indicated as a whole by reference numeral 1 is the target prestressed corencrete (hereinafter simply abbreviated as "kat"). The beam I constitutes the concrete structure A together with the pillar 10 that supports it, and the pillar 1 that should support this beam I
0 has already been erected on the ground G. The following method is used to construct the casings 1 on these prefabricated concrete structures, that is, the pillars IO. In addition, in the figures, reinforcing bars are omitted except in FIG. 4, and it is assumed that a second formwork f for forming a frame 1 extending over these columns 10 is attached to each column 10.

まず始めに、築造すべき粱1の両端、1スパン分または
複数スパン分にあたる部分にコンクリートを打って、前
記柱10と一体となる反力支持体2をそれぞれ形成する
。この際、コンクリ−1・を打設する部分には、第2図
に示すように、ノース3を上下二段に埋設する。ノース
3は、反力支持体2よりも若干長めに設定し、その開口
端か反力支持体2により塞かねないようにする。
First of all, concrete is poured at both ends of the fence 1 to be constructed, at a portion corresponding to one span or a plurality of spans, to form reaction force supports 2 that are integrated with the pillars 10, respectively. At this time, as shown in FIG. 2, norths 3 are buried in two stages, upper and lower, in the area where concrete 1 is to be poured. The north 3 is set to be slightly longer than the reaction support 2 so that its open end may not be blocked by the reaction support 2.

反力支持体2か形成されたならば、第3図に示すように
、二〇反力支持体2に二段に埋設されて対向する前記ノ
ース3の上段に上部PCIIil材5aを、同しくノー
ス3の下段には下部P CflA N5bをそれぞれ挿
通させて、rj記反力支持体2間に架設する。これらP
c綱材5としてはPCC枠棒たよPC鋼線のともらでし
よいか、本実施例ではPCC縁線している。
Once the reaction force support 2 is formed, as shown in FIG. The lower parts P CflA N5b are respectively inserted into the lower part of the north 3 and installed between the reaction force supports 2 shown in rj. These P
c The rope material 5 may be a PCC frame rod or the top of a PC steel wire; in this embodiment, a PCC edge wire is used.

Pc綱材5が架設されf二ら、第3図または第4図に拡
大して示すように、築造すべき梁1の柱10との接続部
に補強筋4を設置する。この補強筋・1よ、本実施例で
は山型をなすしのであり、その山型の頂部を形成する部
分が前記上部PCQ材5aの架設された位置に、かつ底
部を形成する部分か前記下部Pc綱材5bの架設され1
こ位置にほぼ対応するように設置される。
After the Pc ropes 5 are erected, reinforcing bars 4 are installed at the connection portions of the beams 1 to be constructed with the columns 10, as shown in an enlarged view in FIG. 3 or 4. This reinforcing bar 1 is formed into a mountain shape in this embodiment, and the portion forming the top of the mountain shape is located at the position where the upper PCQ material 5a is constructed, and the portion forming the bottom portion is located at the position where the upper PCQ material 5a is constructed. Erection of Pc rope material 5b 1
It will be installed to approximately correspond to this position.

補強筋4か設置されたならば、第3図なとに示すように
、前記それぞれのP(44材5の一端に定着装置6を取
り付け、他端に緊張ツヤツキ7をセットした後PC,M
材5を、この緊張ジヤツキ7を作動させることによって
緊張する。反力支持体2かそれぞれ定着装置6および緊
張ツヤツキ7の反力台として作用するわけである。この
時、反力台のさらに大きな支持力を必要とするなら、通
常の構造体に架設される地中梁13やプレース材14、
さらにはプレース材14と同一面の壁(耐震壁ならさら
によい)で強化することができる。
Once the reinforcing bars 4 have been installed, as shown in Fig. 3, the fixing device 6 is attached to one end of the P (44 material 5) and the tension gloss 7 is set to the other end, then the PC, M
The material 5 is tensioned by operating the tensioning jack 7. The reaction support 2 acts as a reaction force base for the fixing device 6 and the tension gloss 7, respectively. At this time, if a larger supporting force of the reaction platform is required, underground beams 13 or place materials 14 installed in a normal structure,
Furthermore, it can be reinforced with a wall on the same plane as the place material 14 (even better if it is a seismic wall).

Pc綱材5を緊張するにあたっては、上部Pc綱材5a
の緊張力は下部Pc綱材5bの緊張ノ〕よりも小さいも
のとする。これは、このように梁にプレストレスを導入
する本来の主旨、すなわち粱の下弦に加わる引張り力を
Pc綱材によって負担するということ、に沿うよう1こ
するノニめである。
When tensioning the Pc rope 5, the upper Pc rope 5a
The tension of the lower Pc rope 5b shall be smaller than the tension of the lower Pc rope 5b. This is done in accordance with the original purpose of introducing prestress into the beam, that is, the tensile force applied to the lower chord of the beam is borne by the Pc rope.

緊張ジヤツキ7としては、ボストテンノヨン法によるプ
レストレス導入の際に従来より現場で用いられているも
のでよい。また、このとき、緊張したP C,綱材5を
、ナツトまたはクサビ等で仮定着させて緊張ジヤツキ7
を外してもよい。
The tension jack 7 may be one that has been conventionally used in the field when introducing prestress by the Bosttennoyon method. In addition, at this time, the tensioned PC and rope material 5 are temporarily attached with nuts or wedges, etc., and tensioned jacks 7
may be removed.

PCII材5が緊張されたならば、次いで、型枠内の2
つの反力支持体2の間に位置する部分に、目的とオる粱
1を形成するためのコンクリート8(図示せず)を打設
する。2つの反力支持体2の間には既にPCm材5が緊
張状態で架設されているから、これらPCB材5はコン
クリート8の中に埋設された状態となる。また、このコ
ンクリートを打設する前に、前記上部Pc綱材5aおよ
び下部pcg材5bをスターラップ筋11て接続しても
よい。なお符号12は柱lOのためのフープ筋である。
Once the PCII material 5 has been tensioned, it is then
Concrete 8 (not shown) is poured into a portion located between the two reaction force supports 2 to form a concrete 1. Since the PCM materials 5 are already installed under tension between the two reaction force supports 2, these PCB materials 5 are buried in the concrete 8. Moreover, before pouring this concrete, the above-mentioned upper Pc rope material 5a and lower PCG material 5b may be connected using stirrup bars 11. Note that the reference numeral 12 is a hoop muscle for the column IO.

打設したコンクリートか硬化した時点で、前記緊張ツヤ
ツキ7またはす・ノド、クサビによるP C綱材5の緊
張を解くと共に定着装置6を外す。これにより、打設し
たコンクリート8には、いわゆるプリテノンコン法によ
りコンクリートにプし・ストしスか導入されるのと同し
原理てブしスl−Lスか導入される。つまり、前記Pc
綱材5はその緊張を解かれることにより圧縮しようとす
る力が作用し、Pc綱材5にはコンクリート8か付着し
ているた島にこの圧縮力かコンクリート8に導入される
、つまりプレストレスか導入されるわけである。また、
Pc綱材5の賢張後、前記ノース3内にグラウト充填す
れば、Wj記反力支持体2にも、いわゆるボストテンノ
ヨン・ボントエ法によるブしストレスが導入される。反
力支持体2は、コンクリート8の硬化後、このコンクリ
ート8と一体となって梁lを構成するものとなる。
When the poured concrete has hardened, the tension on the PC rope 5 caused by the tension gloss 7 or the slots and wedges is released, and the fixing device 6 is removed. As a result, bush l-l-s is introduced into the poured concrete 8 on the same principle that push-strain is introduced into concrete by the so-called Pritenoncon method. In other words, the Pc
When the tension is released, a compressive force acts on the rope 5, and this compressive force is introduced into the concrete 8 to which the concrete 8 is attached to the Pc rope 5, that is, prestress. It will be introduced. Also,
After the Pc rope material 5 is stretched, grout is filled in the north 3, and the reaction force support 2 is also subjected to a bushing stress by the so-called Bosttennoyon-Bontoet method. After the concrete 8 hardens, the reaction support 2 becomes integral with the concrete 8 to form the beam l.

上1己方法により築造され1こ粱lは、その厚さ方向に
上下二段にPC触材か配設されたものであるから、午に
粱1の耐力を増加せしめてその9梁1の軽量化を図れる
ばかりでなく、粱iの剛性を高め、集中荷重、あるいは
地震等による振動に対する強度を高めろことができ、特
に、直下地震にも対応できる。また、PCM材の配設は
、プし・ストし・ス導入の主旨からいって、部材Iこ発
生する応力に対応するように、すなわち部材に発生ずる
応力を打ち消すような形に行うことが望まれ、たとえば
部材を単純梁とした場合、中央部で曲げモーメントが大
きく端(支持端)では/]Xさしため、PC鋼材を梁の
中央部では梁の丁端に、梁の端部つまり柱付近では上端
に位置するように配設するのが理想的であるわけである
か、上記実施例によれば、Aij記」一部P CI4材
5aおよび下部PC,M材5bは共に直線でたがいに平
行に配設されているものの、粱1の柱IOとの接続部に
は、前述したような補強筋4が設けられているから、上
記の主旨7こ沿ったものとなっている。
The 1st beam constructed using the above 1st method has PC contact materials arranged in upper and lower layers in the thickness direction, so the yield strength of the 1st beam was increased in order to increase the strength of the 9 beams 1. Not only can the weight be reduced, but the rigidity of the wire can be increased to increase its strength against concentrated loads or vibrations caused by earthquakes, etc., and in particular, it can also be used to withstand direct earthquakes. In addition, in keeping with the idea of introducing pressure, stress, and stress, the PCM material should be arranged in a manner that corresponds to the stress generated in the member, that is, in a manner that cancels out the stress generated in the member. For example, if the member is a simple beam, the bending moment is large at the center and the end (supporting end) is In other words, in the vicinity of the pillar, it is ideal to arrange it so that it is located at the upper end.According to the above embodiment, both the part PCI4 material 5a and the lower PC and M materials 5b are in a straight line. Although they are arranged parallel to each other, reinforcing bars 4 as mentioned above are provided at the connection part of 籱 1 with the pillar IO, so the above-mentioned seven points are followed. .

なお、本実施例ではRC構造物の梁について説明したが
、本発明はこの例に限らず、5RC(鉄骨鉄筋コンクリ
ート)構造物でも勿論よく、さらに、梁の他?こスラブ
、外壁、耐震壁、必要によっては柱にも適用することが
できる。
Although this embodiment has been described with respect to a beam of an RC structure, the present invention is not limited to this example, and may of course be applied to a 5RC (steel reinforced concrete) structure. This can be applied to slabs, exterior walls, shear walls, and if necessary, columns.

まfコ、ii?j記補強筋4の設置は、実施例ではPC
鋼材5の配設後としているが、これに限定されるもので
はなく、PC馴材5を架設する前工程であってもよいも
のである。
Mafco, ii? In the embodiment, the reinforcing bars 4 are installed using PC
Although the process is performed after the steel material 5 is installed, the present invention is not limited to this, and may be performed before the PC material 5 is installed.

「発明の効果」 以上説明したとおり、本発明によれは、大掛かりな反力
台を使用せずに現場でのPCM材の緊張を実施すること
ができる。しかも、築造されたプレストレストコンクリ
−)・構造物は、その厚さ方向にPC鯛材か二!i1]
に配設されたものとなって剛性が高められ、構造物自体
の軽量化を閲れると同時に集中荷重および振動に対する
強度を高めることかでき、r7C鋼材の屈曲配設を必要
としな1)。
"Effects of the Invention" As explained above, according to the present invention, tensioning of PCM material can be carried out on site without using a large-scale reaction force table. Moreover, the prestressed concrete (prestressed concrete) structure that was built is made of PC sea bream material or two in the thickness direction! i1]
This increases the rigidity of the structure, reduces the weight of the structure itself, and at the same time increases the strength against concentrated loads and vibrations, eliminating the need for bent R7C steel1).

さらに構造物の大部分は、いわゆるブリテンンヨン法に
J、るブトストレスの導入が行なわれるために、シース
の配設、グラウト充填なとの手間か省1す、PCQ材と
フンクリートとの一体化による構造強度向上およびそれ
に伴うコンクリートボリュームの軽減化といった相乗効
果の活用を図れ、これにより工期短縮およびコスト低減
を実現するなと優れた効果を奏する。
Furthermore, in most of the structures, buttostress is introduced using the so-called Britten-yon method, which eliminates the hassle of installing a sheath and filling it with grout. It is possible to take advantage of the synergistic effect of improving structural strength and reducing concrete volume, which has an excellent effect of shortening construction period and reducing costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図ないし第4図は本発明の一実施例を示すもので、
第1図はプ「スト1ノストコンクリート粱1が築造途中
にあるコンクリート構造物Aの正面断面図、第2閲は反
力支持体2を拡大して示す部分正面断面図、第3図はプ
レストし・ストコンクリ−)−粱1の築造過程を示す正
面断面図、第4図はブ[ストレストコンクリート梁1と
柱10との接合部を拡大して示す部分正面断面図である
。 2・・・反力支持体、   3・・・・シース、4 ・ 補強筋、 5 ・・・PCp材、 緊張ジヤツキ、 10・ 柱。
1 to 4 show an embodiment of the present invention,
Figure 1 is a front sectional view of a concrete structure A in which a concrete structure 1 is in the middle of construction, the second view is a partial front sectional view showing an enlarged reaction force support 2, and Figure 3 is a front sectional view of a concrete structure A in the middle of construction. Fig. 4 is a partial front sectional view showing an enlarged view of the joint between the stressed concrete beam 1 and the column 10.2. ... Reaction force support body, 3. ... Sheath, 4. Reinforcement bar, 5. ... PCp material, tension jack, 10. Column.

Claims (1)

【特許請求の範囲】[Claims] コンクリート構築物を構築するにあたり、予め形成され
た既成コンクリート構造体に、互いに平行なる二面を有
して前記既成コンクリート構造体間にわたるプレストレ
ストコンクリート構造物を築造する方法であって、築造
すべきプレストレストコンクリート構造物の両端部に前
記既成コンクリート構造体と一体となる反力支持体を形
成する工程と、該反力支持体間にPC鋼材を、築造すべ
きプレストレストコンクリート構造物の内部に位置する
ようにかつ前記平行なる二面にそれぞれ近接するように
二列に配設してこれを緊張する工程と、築造すべきプレ
ストレストコンクリート構造物の、前記既成コンクリー
ト構造体との接合部に前記二列のPC鋼材間にわたる補
強筋を設ける工程と、前記PC鋼材の緊張後に目的とす
るプレストレストコンクリート構造物を形成するための
コンクリートを打設する工程と、この打設されたコンク
リートの硬化後に前記PC鋼材の緊張を解除することに
よりコンクリートにプレストレスを導入する工程とを有
することを特徴とするプレストレストコンクリート構造
物の築造方法。
In constructing a concrete structure, a method of constructing a prestressed concrete structure having two mutually parallel surfaces on a pre-formed concrete structure and extending between the pre-formed concrete structures, the prestressed concrete structure to be constructed a step of forming reaction force supports that are integrated with the pre-fabricated concrete structure at both ends of the structure, and placing a PC steel material between the reaction force supports so as to be located inside the prestressed concrete structure to be constructed. and a step of arranging and tensioning the PCs in two rows so as to be close to the two parallel surfaces, respectively, and placing the PCs in the two rows at the joint of the prestressed concrete structure to be constructed with the prefabricated concrete structure. A step of providing reinforcing bars between the steel materials, a step of placing concrete to form the intended prestressed concrete structure after tensioning the prestressed steel materials, and a step of placing reinforcement bars between the prestressed steel materials after the cast concrete has hardened. 1. A method for constructing a prestressed concrete structure, comprising the step of introducing prestress into concrete by releasing the prestress.
JP10382590A 1990-04-19 1990-04-19 Construction method of prestressed concrete structure Pending JPH041363A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10382590A JPH041363A (en) 1990-04-19 1990-04-19 Construction method of prestressed concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10382590A JPH041363A (en) 1990-04-19 1990-04-19 Construction method of prestressed concrete structure

Publications (1)

Publication Number Publication Date
JPH041363A true JPH041363A (en) 1992-01-06

Family

ID=14364192

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10382590A Pending JPH041363A (en) 1990-04-19 1990-04-19 Construction method of prestressed concrete structure

Country Status (1)

Country Link
JP (1) JPH041363A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105370046A (en) * 2015-12-01 2016-03-02 中国建筑第七工程局有限公司 Beam steel bar installation tool and using method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105370046A (en) * 2015-12-01 2016-03-02 中国建筑第七工程局有限公司 Beam steel bar installation tool and using method thereof

Similar Documents

Publication Publication Date Title
KR102187993B1 (en) Prefabricated Bridge Structure and Construction Method
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR20020011706A (en) Fabricated pier and Fabricated pier construction method
JP3660647B2 (en) Girder construction method using concrete receiving beams
JP2011149265A (en) Beam member and building structure
JP3877995B2 (en) How to build a string string bridge
JPH041363A (en) Construction method of prestressed concrete structure
JP2831934B2 (en) How to build substructure
JPH1096210A (en) Method of executing enlargement of bridge pier
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP5128569B2 (en) Prestressed concrete beam
KR102585728B1 (en) Prestressed precast module with integrated girder and column and construction method using the same
JPH01255507A (en) Manufacture of prestress introduction semi-precast concrete component for long span slab
CN113026994B (en) Assembly type double-connecting-beam combined shear wall component, structure and manufacturing and construction method thereof
JP2600531B2 (en) Foundation structure for steel column and its construction method
KR20120030206A (en) A precast concrete deck and construction method for slab structure by using it
JPH06146472A (en) Precast ferro-concrete beam
JP2003161041A (en) Aseismatic reinforcing structure of existing building and execution method therefor
JP2579944Y2 (en) Load-bearing wall assembly structure
JP2006118226A (en) Construction method of floor board with precast concrete slab
JPS6351529A (en) Construction of reinforced concrete underground beam and slab
JPH0469268B2 (en)
JPS6355234A (en) Construction of prestressed concrete
JPH05156605A (en) Arch concrete constructing method by arched form timbering
JPH08193336A (en) Foundation structure