JPH04114929U - Mounting hardware for suspended scaffolding for construction work - Google Patents
Mounting hardware for suspended scaffolding for construction workInfo
- Publication number
- JPH04114929U JPH04114929U JP2662791U JP2662791U JPH04114929U JP H04114929 U JPH04114929 U JP H04114929U JP 2662791 U JP2662791 U JP 2662791U JP 2662791 U JP2662791 U JP 2662791U JP H04114929 U JPH04114929 U JP H04114929U
- Authority
- JP
- Japan
- Prior art keywords
- chain
- scaffolding
- construction work
- mounting
- mounting hardware
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 11
- 238000004804 winding Methods 0.000 claims 1
- 239000000725 suspension Substances 0.000 abstract description 4
- 229910000831 Steel Inorganic materials 0.000 description 7
- 239000010959 steel Substances 0.000 description 7
- 101500021084 Locusta migratoria 5 kDa peptide Proteins 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Landscapes
- Movable Scaffolding (AREA)
Abstract
(57)【要約】 (修正有)
【目的】 建設工事における吊足場の構築工事に際して
足場下地用単管と吊用チェーンを容易に、しかも確実に
取り付けることのできる取付金具を提供すること。
【構成】 クランプ金具1とチェーン支持金具2とを回
動可能に結合して構成する。
(57) [Summary] (with amendments) [Purpose] To provide a mounting bracket that can easily and reliably attach a single pipe for a scaffold base and a suspension chain when constructing a suspended scaffold in construction work. [Structure] A clamp fitting 1 and a chain support fitting 2 are rotatably connected.
Description
【0001】0001
この考案は、建設工事において、S造、SRC造等の吊足場構築の際の足場下 地用単管と吊用チェーンの取付金具に関する。 This idea was developed for use under scaffolding when constructing suspended scaffolding such as S construction and SRC construction in construction work. Concerning mounting hardware for underground pipes and hanging chains.
【0002】0002
従来、S造、SRC造等の作業足場を構築する方法として、鉄骨材として使用 するH型鋼の建方後、H型鋼のほぼ2m下に足場下地用単管をH型鋼に巻着した 吊用チェーンにより吊設し、その単管の上に足場板を架設して足場を構築する吊 足場の工法が開示されている。 Conventionally, it is used as a steel frame material to construct work scaffolds such as S construction and SRC construction. After the H-shaped steel was erected, a single tube for the scaffold base was wrapped around the H-shaped steel approximately 2m below the H-shaped steel. A suspension system in which a scaffold is constructed by suspending a suspension chain and constructing a scaffolding board on top of the single pipe. A construction method for scaffolding is disclosed.
【0003】0003
上記従来の方法では、H型鋼の下方に吊設する足場下地用単管を吊用チェーン で直接巻着するために、吊足場の構築後の作業員の通行等により振動が生じ、単 管がチェーンから滑り抜けるなどの問題点を有する。 In the above conventional method, the single pipe for the scaffolding base, which is suspended below the H-shaped steel, is connected to the suspension chain. Because it is wrapped directly around the suspended scaffold, vibrations occur due to the passage of workers after the suspended scaffolding is constructed, and There are problems such as the pipe slipping out of the chain.
【0004】0004
この考案は上記従来の課題に鑑みなされたもので、その目的は、足場下地用単 管を確実に握着し、チェーンと単管の取付けが簡単な吊足場の取付金具を提供す るものである。 This idea was devised in view of the above-mentioned conventional problems, and its purpose was to We provide hanging scaffold mounting hardware that securely grips pipes and makes it easy to attach chains and single pipes. It is something that
【0005】 その手段として、単管支持用のクランプ金具と、チェーンを巻着して支持する チェーン支持具とを回動可能に結合したことを特徴とする。[0005] As a means of achieving this, a clamp fitting for supporting the single tube and a chain are wrapped around and supported. It is characterized by being rotatably coupled to a chain support.
【0006】 上記構造により、単管支持用のクランプ金具により足場下地用単管を支持する ために確実に握着し、取付けも容易である。 また、 チェーン支持具に吊用チェーンの先端に付属するフック部を巻き通し、 チェーンの所要の位置に掛止するだけで取付けられるために、容易に作業が行え るなど、前記従来の課題を解消するものである。[0006] With the above structure, the single pipe for scaffolding base is supported by the clamp fitting for supporting the single pipe. It has a secure grip and is easy to install. In addition, wind the hook attached to the end of the hanging chain through the chain support. Easy to install as it can be installed by simply hooking it onto the chain at the desired position. This solves the conventional problems mentioned above.
【0007】[0007]
第1図は本考案の取付金具の実施例を示す斜視図であり、第2図は実施例の構 成要素を示す斜視図である。 第2図に示すように、クランプ金具1とチェーン支持具2から構成され、クラ ンプ金具1の底面にチェーン支持具2の取付ボルト2dを螺入できる程度の孔1 aを穿設する。 チェーン支持具2は、コの字部2aとそのコの字部2aの対辺の内側に摺設で きるU型部2bを連結軸2cにより結合し、その場合、U型部2bは連結軸2c を軸に任意の角度に摺動するように螺合する。 第1図に示すように、クランプ金具1の孔1aに、チェーン支持具2の取付ボ ルト2dを螺入し、さらに、取付用ナット2eをその取付ボルト2dに螺入して クランプ金具1と回動可能に結合して構成する。 FIG. 1 is a perspective view showing an embodiment of the mounting bracket of the present invention, and FIG. 2 shows the structure of the embodiment. It is a perspective view showing a component. As shown in Fig. 2, it consists of a clamp fitting 1 and a chain support 2. A hole 1 large enough to screw the mounting bolt 2d of the chain support 2 into the bottom of the pump fitting 1. Drill a. The chain support 2 can be slid on the inside of the U-shaped portion 2a and the opposite side of the U-shaped portion 2a. The U-shaped portions 2b that can be connected are connected by a connecting shaft 2c, and in that case, the U-shaped portions 2b Screw together so that it slides at any angle around the axis. As shown in FIG. 1, the mounting bolt of the chain support 2 is inserted into the hole 1a of the clamp fitting 1. Screw in the bolt 2d, and then screw the mounting nut 2e into the mounting bolt 2d. It is configured to be rotatably coupled to the clamp fitting 1.
【0008】 第3図は、本考案の実施例に係る取付金具のの使用状態を示す一部断面図であ り、H型鋼Aに巻着した吊用チェーンBの先端をチェーン支持具2のU型部2b に通して巻着すると共に、クランプ金具1で足場下地用単管Dを握着した後、フ ック部Cを吊用チェーンBに引掛けて固定する。 同様にして、吊用チェーンBを単管支持用クランプ金具に取り付け、その後、 足場下地用単管Dを組み立て、足場板Eを所要の位置に配置して、吊足場を構築 するものである。[0008] FIG. 3 is a partial sectional view showing how the mounting bracket according to the embodiment of the present invention is used. Then, attach the tip of the hanging chain B wrapped around the H-shaped steel A to the U-shaped part 2b of the chain support 2. At the same time, after gripping the single tube D for scaffolding base with the clamp fitting 1, Hang the hook part C on the hanging chain B and fix it. In the same way, attach the hanging chain B to the single pipe support clamp, and then Assemble the single pipes D for the scaffolding base, place the scaffolding boards E in the required positions, and construct the suspended scaffolding. It is something to do.
【0009】[0009]
以上詳細に説明したようにこの考案の建設工事用吊足場の取付金具によれば、 単管支持用のクランプ金具により足場下地用単管を支持するために確実に握着し 、取付けも容易であり、安全性の確保、作業能率の向上に効果がある。 また、チェーン支持具に吊用チェーンの先端に付属するフック部を巻き通し、 チェーンの所要の位置に掛止するだけで取付けられるために、容易に作業が行え 、上記と同様に作業能率の向上が期待できるなど実用上有益な建設工事用吊足場 の取付金具を得ることができる。 As explained in detail above, according to the mounting bracket for suspended scaffolding for construction work of this invention, Clamp fittings for supporting single pipes ensure secure grip to support single pipes for scaffolding. It is easy to install, and is effective in ensuring safety and improving work efficiency. In addition, wind the hook attached to the end of the hanging chain through the chain support, Easy to install as it can be installed by simply hooking it onto the chain at the desired position. , a suspended scaffold for construction work that is practically useful and can be expected to improve work efficiency as well as the above. You can get the mounting hardware.
【提出日】平成3年4月11日[Submission date] April 11, 1991
【手続補正1】[Procedural amendment 1]
【補正対象書類名】明細書[Name of document to be amended] Specification
【補正対象項目名】0007[Correction target item name] 0007
【補正方法】変更[Correction method] Change
【0007】 第1図は本考案の取付金具の実施例を示す斜視図であり、第2図 は実施例の構成要素を示す斜視図である。 第2図に示すように、クランプ金具1とチェーン支持具2から構成され、クラ ンプ金具1の底面にチェーン支持具2の取付ボルト2dを挿入できる程度の孔1 aを穿設する。 チェーン支持具2は、コの字部2aとそのコの字部2aの対辺の内側に摺設で きるU字部2bを連結部2cにより結合し、その場合、U字部2bは連結部2c を軸に任意の角度に摺動するように結合する。 第1図に示すように、クランプ金具1の孔1aに、チェーン支持具2の取付ボ ルト2dを挿入し、さらに、取付用ナット2eをその取付ボルト2dに螺入して クランプ金具1と回動可能に結合して構成する。FIG. 1 is a perspective view showing an embodiment of the mounting bracket of the present invention, and FIG. FIG. 2 is a perspective view showing the components of the embodiment. As shown in Fig. 2, it consists of a clamp fitting 1 and a chain support 2. The hole 1 is large enough to insert the mounting bolt 2d of the chain support 2 into the bottom of the pump fitting 1. Drill a. The chain support 2 can be slid on the inside of the U-shaped portion 2a and the opposite side of the U-shaped portion 2a. In this case, the U-shaped portion 2b is connected to the connecting portion 2c. Connect so that it can slide at any angle around the axis. As shown in FIG. 1, the mounting bolt of the chain support 2 is inserted into the hole 1a of the clamp fitting 1. Insert the bolt 2d, and then screw the mounting nut 2e onto the mounting bolt 2d. It is configured to be rotatably coupled to the clamp fitting 1.
【図1】 実施例の取付金具を示す斜視図[Figure 1] Perspective view showing the mounting bracket of the example
【図2】 実施例の構成要素を示す斜視図[Figure 2] Perspective view showing the components of the embodiment
【図3】 実施例に係る取付金具の使用状態を示す一部
断面図[Figure 3] Partial cross-sectional view showing how the mounting bracket according to the example is used
1 クランプ金具 1a 孔 2 チェーン支持具 2a コの字部 2b U型部 2c 連結軸 2d 取付ボルト 2e 取付用ナット A H型鋼 B 吊用チェーン C チェーンのフック部 D 足場下地用単管 E 足場板 1 Clamp fittings 1a hole 2 Chain support 2a U-shaped part 2b U-shaped part 2c connection shaft 2d mounting bolt 2e Mounting nut A H type steel B Hanging chain C chain hook part D Single pipe for scaffolding base E Scaffolding board
Claims (1)
を巻着して支持するチェーン支持具とを回動可能に結合
したことを特徴とする建設工事用吊足場の取付金具。1. A mounting fixture for a suspended scaffold for construction work, characterized in that a clamping fixture for supporting a single pipe and a chain supporter for winding and supporting a chain are rotatably coupled.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2662791U JPH04114929U (en) | 1991-03-26 | 1991-03-26 | Mounting hardware for suspended scaffolding for construction work |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2662791U JPH04114929U (en) | 1991-03-26 | 1991-03-26 | Mounting hardware for suspended scaffolding for construction work |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH04114929U true JPH04114929U (en) | 1992-10-12 |
Family
ID=31911063
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2662791U Pending JPH04114929U (en) | 1991-03-26 | 1991-03-26 | Mounting hardware for suspended scaffolding for construction work |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH04114929U (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0258548B2 (en) * | 1985-06-07 | 1990-12-10 | Taisei Corp |
-
1991
- 1991-03-26 JP JP2662791U patent/JPH04114929U/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0258548B2 (en) * | 1985-06-07 | 1990-12-10 | Taisei Corp |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3197748U (en) | Single pipe hanging bracket | |
KR200417712Y1 (en) | A cable hanger have a pipe cramps | |
KR20100005397U (en) | Attaching devise of cable hanger | |
JPH04114929U (en) | Mounting hardware for suspended scaffolding for construction work | |
CN112252591A (en) | Connecting piece for reinforcing steel bar framework with deviation rectifying function | |
JP2005290786A (en) | Hanging fixture | |
JP3209707U (en) | Square steel pipe reinforcing material universal coupler | |
JPH0683047U (en) | Sprinkler attachment | |
JP2000230315A (en) | Pipe clamp and scaffold hanger making the same | |
JP3081653U (en) | Baseboard panel fixture | |
JP3119181B2 (en) | Hanging bracket | |
JP3008053U (en) | Handrail equipment for building framework scaffolding | |
JPH0633104Y2 (en) | Hanging scaffold mounting bracket | |
JP3069424U (en) | Scaffolding hanging brackets that can simultaneously suspend both the suspended under the bridge girder and the two-stage scaffold between the bridge girder | |
CN210720832U (en) | Multifunctional mounting bracket for erecting optical cable | |
JP7409780B2 (en) | Hanging equipment for hanging scaffolds and hanging scaffolding | |
JP6843451B1 (en) | Tightening bracket and how to attach the binding bracket | |
JP2525987Y2 (en) | Construction support bracket | |
JP2513480Y2 (en) | Assembly scaffolding | |
JP2538491Y2 (en) | Scaffolding hanger | |
JPH0440353Y2 (en) | ||
JPS587886Y2 (en) | scaffolding equipment | |
JPH0640773Y2 (en) | Temporary scaffolding equipment | |
JPH0614663U (en) | Piping jig | |
JPH058740Y2 (en) |