JPH0337632B2 - - Google Patents

Info

Publication number
JPH0337632B2
JPH0337632B2 JP60148960A JP14896085A JPH0337632B2 JP H0337632 B2 JPH0337632 B2 JP H0337632B2 JP 60148960 A JP60148960 A JP 60148960A JP 14896085 A JP14896085 A JP 14896085A JP H0337632 B2 JPH0337632 B2 JP H0337632B2
Authority
JP
Japan
Prior art keywords
release agent
concrete
coating layer
base layer
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60148960A
Other languages
Japanese (ja)
Other versions
JPS6210366A (en
Inventor
Hirofumi Aoki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP14896085A priority Critical patent/JPS6210366A/en
Publication of JPS6210366A publication Critical patent/JPS6210366A/en
Publication of JPH0337632B2 publication Critical patent/JPH0337632B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、コンクリート構造物を所定の形状、
寸法に作るために仮設される打設型枠に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention provides concrete structures with a predetermined shape,
It relates to a pouring formwork that is temporarily installed to make it to a certain size.

〔従来の技術とその問題点〕[Conventional technology and its problems]

従来、打設型枠として鋼製、合板製などのもの
が多用されたが、コンクリート打込後所定日数経
過したとき行なう型枠解体時に、コンクリートと
の離型を良くするために、打込みに先だち剥離材
を塗付していた。このときの剥離材の塗付が不充
分であると、打設型枠表面にコンクリートが付着
してとり除かねばならない不具合があつた。また
この塗付作業を完全に行なう為に、コンクリート
構造物によつては、大組みした打設型枠を組立状
態のままレツカー等で移動させた後、組立てたり
解体したりする余分な工程を要し、人が入れない
程の狭い空間で塗付作業を行なう必要があつた
り、トンネル工事などでは非常に危険を伴う作業
となつた。
Conventionally, molds made of steel, plywood, etc. were often used as pouring formwork, but in order to improve the release from the concrete when dismantling the formwork after a predetermined number of days have passed after concrete pouring, molds made of steel or plywood were often used. A release agent was applied. If the release material was not sufficiently applied at this time, concrete would adhere to the surface of the pouring form and had to be removed. In addition, in order to completely perform this coating work, depending on the concrete structure, the extra process of assembling and dismantling is required after the large-scale casting form is moved with a retoucher etc. in the assembled state. In short, painting work had to be carried out in spaces too narrow for people to enter, and work such as tunnel construction was extremely dangerous.

打設型枠を水平な平板状に設けたスラブ面に於
ては、塗付された剥離剤によつて作業者が足を滑
らせることによる墜落事故が絶えなかつた。
On the slab surface where the pouring formwork is placed in the form of a horizontal flat plate, there have been frequent falls due to workers slipping due to the applied release agent.

本発明は、上記問題点が解決された打設型枠を
提供することを目的としている。
An object of the present invention is to provide a casting formwork in which the above-mentioned problems are solved.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は、生コンクリート用打設型枠本体の基
板の表面に、ポリオレフイン系樹脂等のフイルム
状下地層を形成し、さらに該下地層の表面に、微
小ピンホールを多数有するポリオレフイン系樹脂
等の被覆層を形成し、かつ、該被覆層の表面に、
固形又は半固形で熱膨張係数が該被覆層より大き
い剥離剤を押圧した状態で摺動することにて上記
微小ピンホール内に該剥離剤を含浸して構成され
た打設型枠によつて、上記問題点を解決する。
The present invention involves forming a film-like base layer of polyolefin resin or the like on the surface of the substrate of the casting form body for ready-mixed concrete, and further forming a film-like base layer of polyolefin resin or the like on the surface of the base layer with a large number of micro pinholes. forming a coating layer, and on the surface of the coating layer,
By sliding a solid or semi-solid release agent with a coefficient of thermal expansion larger than that of the coating layer while pressing the release agent, the micro pinholes are impregnated with the release agent. , solves the above problems.

〔作用〕[Effect]

打設型枠内部にコンクリートが打込まれること
により、被覆層内部で生コンクリートが水和反応
熱を発生する。該水和反応熱にて被覆層と微小ピ
ンホール内の剥離剤が熱膨張し、熱膨張係数の大
きな剥離剤が浸出してきて、被覆層とコンクリー
トの間に剥離剤の薄膜が形成されるため、上記被
覆層と打込みコンクリートとは直接触することは
なく、打込みコンクリートが被覆層に付着するこ
とはない。従つて、打設枠本体の取外し作業は容
易に行なえる。
When concrete is poured into the pouring form, the fresh concrete generates heat of hydration reaction inside the coating layer. The heat of the hydration reaction thermally expands the coating layer and the release agent in the tiny pinholes, and the release agent with a large coefficient of thermal expansion leaches out, forming a thin film of release agent between the coating layer and the concrete. The covering layer and the poured concrete do not come into direct contact, and the poured concrete does not adhere to the covering layer. Therefore, the work of removing the casting frame body can be easily performed.

〔実施例〕〔Example〕

図面に基いて本発明を詳説すると、第1図、第
2図に於て、1はコンクリート2を打込むときに
仮設される打設型枠であつて、3は該型枠1を構
成する型枠本体であるる。該型枠本体3の基板3
a表面3bには熱可塑性を有するポリオレフイン
系樹脂等による下地層4が、該下地層4の表面に
は同じくポリオレフイン系樹脂等の被覆層5がそ
れぞれ設けられている。また、該被覆層5に打設
型枠1の打込みコンクリート2からの離型(分離
させる)を良くする為の剥離剤6が含浸された多
数の微小ピンホール7が形成されている。型枠本
体3の上記基板3aは木製、鋼製、アルミ製等の
何れであつてもよい。
To explain the present invention in detail based on the drawings, in FIGS. 1 and 2, 1 is a pouring formwork temporarily installed when pouring concrete 2, and 3 constitutes the formwork 1. This is the formwork body. Substrate 3 of the form body 3
A base layer 4 made of thermoplastic polyolefin resin or the like is provided on the a surface 3b, and a covering layer 5 similarly made of polyolefin resin or the like is provided on the surface of the base layer 4. Further, a large number of minute pinholes 7 are formed in the coating layer 5 and are impregnated with a release agent 6 to improve the release (separation) of the pouring formwork 1 from the poured concrete 2. The substrate 3a of the form body 3 may be made of wood, steel, aluminum, or the like.

そこで、上記型枠本体3の製造方法を第3図に
ついて説明すると、8は鉄、鋼、銅等の薄板から
なる受け盤であり、該受け盤8上には上記型枠本
体3の基板3aが載置されている。基板3aが載
置された受け盤8は、まず高温加熱工()に於
て200℃〜250℃程度の雰囲気の炉内で高温に加熱
される。次の初期静電塗装工程()では、陰極
である塗料噴射装置9と陽極である受け盤8との
間には高電圧がかけられているので、上記噴射装
置9から基板3a表面に向けて噴射される粉末状
塗料Pは飛散中に帯電され、基板3aの表面に吸
引されて融着を開始する。上記粉末状塗料Pとし
てはポリオレフイン系樹脂と総称されるポリエチ
レンやポリプロピレンが好ましい。
Therefore, the manufacturing method of the form body 3 will be explained with reference to FIG. is placed. The receiving plate 8 on which the substrate 3a is placed is first heated to a high temperature in a furnace with an atmosphere of about 200°C to 250°C in a high-temperature heating process. In the next initial electrostatic coating step (), a high voltage is applied between the paint spraying device 9, which is a cathode, and the receiving plate 8, which is an anode. The powdered paint P that is sprayed is electrically charged during scattering, is attracted to the surface of the substrate 3a, and starts fusing. As the powder coating P, polyethylene and polypropylene, which are collectively referred to as polyolefin resins, are preferable.

次に()の中温加熱工程では、受け盤8及び
基板3aを粉末状塗料Pの融着に必要な温度に維
持すべく加熱炉(図示せず)内で150℃〜200℃好
ましくは180℃〜190℃の雰囲気により20分程度加
熱され乾燥される。このようにして層厚100μ〜
200μ程度のフイルム状に形成された下地層4の
表面に、液剤吹付工程()では液剤噴射装置1
1によつて水若しくはシンナー等の液剤Wを吹き
付ける。次に、これらを室温程度に冷却した後、
上記液剤Wの乾燥しないうちに後期静電塗装工程
()に於ては、前記粉末状塗料Pを塗料噴射装
置10から上記下地層4の表面に噴射して静電塗
装を行なう。この場合にも前記同様に飛散中に帯
電された粉末状塗料Pは下地層4の表面に吸引さ
れる。この後の高温加熱工程()では炉内温度
が180℃〜220℃好ましくは200℃〜210℃の雰囲気
中で20分間程度の加熱が行なわれ、この間粉末状
塗料Pの融着が進行しているが、層厚300〜400μ
程度フイルム状の被覆層5が形成され、下地層4
に固着する迄の過程において上記液剤Wは、融着
が進行している粉末状塗料P内部を上方向に放散
するように蒸発する。このときの液剤W粒子の融
着状態の粉末状塗料P内での移動軌跡によつて上
記被覆層5内に微小ピンホール7が形成される。
そして型枠本体3は炉外において受け盤8から取
出される。なお、上記下地層4及び被覆層5の各
表面は全体が均一で表面仕上がりの優れた塗装面
に形成されている。第3図()に示すように、
上記被覆層5の微小ピンホール7に剥離剤6を含
浸させるには、固形或いは半固形の剥離剤6を被
覆層5表面に押圧した状態で摺動することによつ
て行なう。このようにして基板3a表面3bに下
地層4が、該下地層4表面に微小ピンホール7を
有する被覆層5がそれぞれ固着されて形成された
型枠本体3は、打設型枠1内部にコンクリート2
が打込まれることにより、上記被覆層5内部では
生コンクリートが発生する水和反応による熱によ
つて次の現象が生じる。即ち、一般的に80℃以内
といわれる上記水和反応熱によつて被覆層5並び
にピンホール7内の剥離剤6の温度も同時に上昇
するが、被覆層5を構成する前記ポリオレフイン
系樹脂と剥離剤6との熱膨張係数の差異により、
剥離剤6がピンホール7から浸出する。このとき
の剥離剤6のピンホール7からの浸出過程につい
て説明すると、打込みコンクリート2からの上記
発生熱に感応して、一部のピンホール7内の剥離
剤6はコンクリート2と被覆層5とが接触する以
前に、残りのピンホール7内の剥離剤6は接触後
に、それぞれ剥離剤6を浸出する。なお、打込み
コンクリート2の側圧による荷重により弾性を有
する被覆層5が圧縮されることによつてもピンホ
ール7内から剥離剤6が浸出する。このようにし
て浸出してくる剥離剤6は被覆層5表面に拡散し
て分子膜(図示せず)ないしはそれに近い程度の
厚さの薄膜12を形成するに到る。上記被覆層5
と打込みコンクリート2とは、微視的には、直接
は接触せず両者間には上記薄膜12が介存するこ
とになる。したがつて打込みコンクリート2と型
枠本体3とが離型の極めて容易に行なわれる。ピ
ンホール7内に含浸された剥離剤6はコンクリー
ト2の1度の打込みでは各ピンホール7内の剥離
剤6の一部が所定量浸出するだけであるから打込
み回数にして5〜6回程度の転用が可能である。
したがつて、打込み5〜6回につき1度だけ剥離
剤6を含浸すればよく従来の打設型枠のようにコ
ンクリートの打込み毎に塗付する必要はない。
Next, in the medium temperature heating step (), the receiving plate 8 and the substrate 3a are heated at 150°C to 200°C, preferably 180°C, in a heating furnace (not shown) in order to maintain the temperature necessary for fusing the powdered paint P. It is heated and dried in an atmosphere of ~190°C for about 20 minutes. In this way, the layer thickness is 100μ~
In the liquid spraying process (), a liquid injection device 1 is applied to the surface of the base layer 4 formed in a film shape of about 200μ.
1, spray a liquid agent W such as water or thinner. Next, after cooling these to about room temperature,
In the latter electrostatic coating step (), before the liquid agent W has dried, the powdered paint P is sprayed onto the surface of the base layer 4 from the paint spraying device 10 to perform electrostatic coating. In this case as well, the powdered paint P charged during scattering is attracted to the surface of the base layer 4 in the same manner as described above. In the subsequent high-temperature heating step (), heating is performed for about 20 minutes in an atmosphere with a furnace temperature of 180°C to 220°C, preferably 200°C to 210°C, during which time the powdered paint P is fused. However, the layer thickness is 300~400μ
A film-like covering layer 5 is formed, and a base layer 4 is formed.
In the process of adhering to the powder coating material P, the liquid agent W evaporates upwardly inside the powdered coating material P where fusion is progressing. At this time, minute pinholes 7 are formed in the coating layer 5 due to the locus of movement of the liquid agent W particles within the fused powder paint P.
The form body 3 is then taken out from the receiving plate 8 outside the furnace. Note that the surfaces of the base layer 4 and the coating layer 5 are formed into coated surfaces that are uniform throughout and have an excellent surface finish. As shown in Figure 3 (),
The micro pinholes 7 of the coating layer 5 are impregnated with the release agent 6 by sliding the solid or semi-solid release agent 6 onto the surface of the coating layer 5 while being pressed. In this way, the formwork main body 3 formed by fixing the base layer 4 to the surface 3b of the substrate 3a and the coating layer 5 having minute pinholes 7 to the surface of the base layer 4 is placed inside the casting form 1. concrete 2
When concrete is poured, the following phenomenon occurs inside the coating layer 5 due to the heat generated by the hydration reaction of the fresh concrete. That is, the temperature of the coating layer 5 and the release agent 6 in the pinholes 7 rise at the same time due to the heat of hydration reaction, which is generally said to be within 80°C, but the temperature of the release agent 6 in the coating layer 5 and the polyolefin resin constituting the coating layer 5 are increased at the same time. Due to the difference in thermal expansion coefficient with agent 6,
Release agent 6 oozes out from pinhole 7. To explain the leaching process of the release agent 6 from the pinholes 7 at this time, in response to the heat generated from the poured concrete 2, the release agent 6 in some of the pinholes 7 separates from the concrete 2 and the coating layer 5. The release agent 6 in the remaining pinholes 7 exudes the release agent 6 after the contact, respectively. The release agent 6 also oozes out from the pinholes 7 when the elastic coating layer 5 is compressed by the lateral pressure of the poured concrete 2. The release agent 6 leached out in this way diffuses onto the surface of the coating layer 5 to form a molecular film (not shown) or a thin film 12 having a thickness close to it. The above coating layer 5
Microscopically, the poured concrete 2 and the cast concrete 2 do not directly contact each other, but the thin film 12 exists between them. Therefore, the poured concrete 2 and the form body 3 can be released from the mold very easily. Since only a predetermined amount of the release agent 6 impregnated into the pinholes 7 is leached out of each pinhole 7 when the concrete 2 is placed once, the number of times the release agent 6 is placed is approximately 5 to 6 times. diversion is possible.
Therefore, it is only necessary to impregnate the release agent 6 once every 5 to 6 times of pouring, and there is no need to apply it every time concrete is poured as in conventional pouring forms.

別の実施例として、第4図、第5図のように多
数の針状突出部14が外周部に設けられた針布ロ
ーラ13を被覆層5の表面上で転動させることに
よつて微小ピンホール7を形成するようにしても
よい。なお、この場合下地層4及び被覆層5は、
前記粉末状塗料Pによつて形成されたフイルムを
型枠本体3の基板3a表面に熱圧着することによ
つて、或いは接着剤等を使用して固着し、または
下地層4を形成した後、さらに該下地層の表面に
同様な方法によつて前記粉末状塗料Pのフイルム
を固着するようにしてもよい。
As another example, as shown in FIG. 4 and FIG. A pinhole 7 may also be formed. In addition, in this case, the base layer 4 and the covering layer 5 are
After the film formed of the powdered paint P is thermocompressed onto the surface of the substrate 3a of the form body 3, or is fixed using an adhesive or the like, or the base layer 4 is formed, Furthermore, a film of the powdered paint P may be fixed to the surface of the base layer by a similar method.

本発明においては、既述のように熱可塑性樹脂
であるポリプロピレンやポリエチレンを下地層4
及び被覆層5の材料としてそれぞれ採用したが、
これは、該樹脂がアルカリや酸等に対して極めて
安定しており、また表面硬度が高くてキズがつき
にくい、低温域での離型性が秀れている、或いは
ピンホールが形成されても弾性率が低下しないな
どの性質に基づくものである。
In the present invention, as mentioned above, thermoplastic resin such as polypropylene or polyethylene is used as the base layer 4.
and were respectively adopted as the material of the coating layer 5,
This is because the resin is extremely stable against alkalis and acids, has a high surface hardness and is difficult to scratch, has excellent mold releasability at low temperatures, or has no pinholes. This is also based on properties such as the fact that the modulus of elasticity does not decrease.

〔発明の効果〕〔Effect of the invention〕

以上のように、本発明に於ては、生コンクリー
トの水和反応による発生熱及び圧力等によつて微
小ピンホール7内の剥離剤6が浸出し、被覆層5
の表面が剥離剤6の薄膜12によつておおわれて
いるので、微視的には被覆層5と打込みコンクリ
ート2とは接触することはなく、打設型枠1解体
時におけるコンクリート2と型枠本体3との離型
が容易に行なわれる。したがつて、他の型枠材料
と比較すればコンクリート2との剥離性がかなり
良好な合成樹脂本来の特性に加えて、上記効果が
相乗的に働くので型枠1取外し作業を極めて容易
に行ない得る効果がある。
As described above, in the present invention, the release agent 6 in the micro pinholes 7 leaches out due to the heat and pressure generated by the hydration reaction of fresh concrete, and the coating layer 5
Since the surface of is covered with a thin film 12 of the release agent 6, there is no microscopic contact between the coating layer 5 and the poured concrete 2, and the concrete 2 and the formwork when the poured formwork 1 is dismantled. The mold release from the main body 3 is easily performed. Therefore, in addition to the inherent properties of the synthetic resin, which has fairly good peelability from concrete 2 compared to other formwork materials, the above effects work synergistically, making it extremely easy to remove formwork 1. There are benefits to be gained.

また、本発明の打設型枠1は何度も連続して使
用することが可能であるから、従来のように型枠
1組立毎に剥離剤を塗付する必要がない。
Further, since the casting form 1 of the present invention can be used continuously many times, there is no need to apply a release agent each time the form is assembled, unlike the conventional method.

さらに、従来、床版上に水平に取付けられた型
枠本3に剥離剤が塗付された後は、打設型枠1表
面に剥離剤が浮いた状態となり、作業者が滑りや
すく、このような型枠1上での作業は危険を極め
たが、本発明においてはコンクリート2との分離
をコンクリート2打込みに伴なつて型枠本体3表
面に形成される剥離剤6の薄膜12によつて行な
うことにしたので、上を歩いても作業者が滑るよ
うなことはなく、打設型枠1からの落下事故を防
止することができる。さらに、被覆層5をフイル
ム状下地層4の表面に形成しているため、微小ピ
ンホール7内の剥離剤6が基板3a側へ浸出する
のを防げる。
Furthermore, conventionally, after the release agent is applied to the formwork 3 installed horizontally on the floor slab, the release agent floats on the surface of the pouring formwork 1, making it easy for workers to slip. Working on such a formwork 1 was extremely dangerous, but in the present invention, separation from the concrete 2 is achieved by a thin film 12 of release agent 6 formed on the surface of the formwork body 3 as the concrete 2 is poured. Since it is decided to do this by holding the mold, the worker will not slip even if he or she walks on it, and an accident of falling from the pouring formwork 1 can be prevented. Furthermore, since the coating layer 5 is formed on the surface of the film-like base layer 4, the release agent 6 in the minute pinholes 7 can be prevented from seeping out to the substrate 3a side.

以上、本発明は、建設業の省力化及び安全管理
上において極めて顕著な効果を奏するものであ
る。
As described above, the present invention has extremely significant effects in terms of labor saving and safety management in the construction industry.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例を示す拡大断面図、
第2図は打設型枠内部にコンクリートが打設され
た状態を示す縦断面図、第3図は本発明の打設型
枠の製造方法を工程順に示す断面図、第4図は他
の実施例を示す拡大断面図、第5図はその製造方
法における微小ピンホールの形成方法を示す断面
図である。 3…型枠本体、3a…基板、3b…表面、4…
下地層、5…被覆層、6…剥離剤、7…微小ピン
ホール。
FIG. 1 is an enlarged sectional view showing an embodiment of the present invention;
Fig. 2 is a vertical cross-sectional view showing concrete poured inside the pouring form, Fig. 3 is a cross-sectional view showing the method of manufacturing the casting form according to the present invention in the order of steps, and Fig. 4 is a vertical cross-sectional view showing concrete poured inside the pouring form. FIG. 5 is an enlarged cross-sectional view showing an example, and FIG. 5 is a cross-sectional view showing a method of forming minute pinholes in the manufacturing method. 3...Form body, 3a...Substrate, 3b...Surface, 4...
Base layer, 5... Covering layer, 6... Release agent, 7... Minute pinhole.

Claims (1)

【特許請求の範囲】[Claims] 1 生コンクリート用打設型枠本体3の基板3a
の表面3bに、ポリオレフイン系樹脂等のフイル
ム状下地層4を形成し、さらに該下地層4の表面
に、微小ピンホール7を多数有するポリオレフイ
ン系樹脂等の被覆層5を形成し、かつ、該被覆層
5の表面に、固形又は半固形で熱膨張係数が該被
覆層5より大きい剥離剤6を押圧した状態で摺動
することにて上記微小ピンホール7内に該剥離剤
6を含浸して構成したことを特徴とする打設型
枠。
1 Substrate 3a of pouring form body 3 for fresh concrete
A film-like base layer 4 made of a polyolefin resin or the like is formed on the surface 3b of the base layer 4, and a coating layer 5 made of a polyolefin resin or the like having a large number of micro pinholes 7 is formed on the surface of the base layer 4. The release agent 6, which is solid or semi-solid and has a coefficient of thermal expansion larger than that of the coating layer 5, is pressed and slid onto the surface of the coating layer 5, thereby impregnating the micro pinholes 7 with the release agent 6. A pouring formwork characterized by being constructed with.
JP14896085A 1985-07-05 1985-07-05 Casting mold frame Granted JPS6210366A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14896085A JPS6210366A (en) 1985-07-05 1985-07-05 Casting mold frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14896085A JPS6210366A (en) 1985-07-05 1985-07-05 Casting mold frame

Publications (2)

Publication Number Publication Date
JPS6210366A JPS6210366A (en) 1987-01-19
JPH0337632B2 true JPH0337632B2 (en) 1991-06-06

Family

ID=15464508

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14896085A Granted JPS6210366A (en) 1985-07-05 1985-07-05 Casting mold frame

Country Status (1)

Country Link
JP (1) JPS6210366A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT518244A2 (en) * 2017-03-02 2017-08-15 Pro-Coaching E U Shuttering element with theft protection

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59203673A (en) * 1983-05-02 1984-11-17 Kobunshi Giken Kk Manufacture of concrete form board and apparatus therefor

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59203673A (en) * 1983-05-02 1984-11-17 Kobunshi Giken Kk Manufacture of concrete form board and apparatus therefor

Also Published As

Publication number Publication date
JPS6210366A (en) 1987-01-19

Similar Documents

Publication Publication Date Title
JP2625580B2 (en) Tool and method for stamping a composite layer consisting of a layer of conductive material and a layer of non-conductive insulating material
KR960702388A (en) PATTERNED ABRASIVE MATERIAL AND METHOD
JPH0215365B2 (en)
JPH0337632B2 (en)
US3427178A (en) Method for coating a mold with a polyurethane release agent
JPH0342213A (en) Preparation of split mold
EP0255940B1 (en) Base for coating material made of synthetic resin
JP2525995B2 (en) Building material manufacturing method
JPH06144824A (en) Production of polycrystalline silicon
JP2667470B2 (en) Press die manufacturing method
CN109502993A (en) A kind of porous structure processing method in material surface
JPS6146347A (en) Production of casting mold
JPH01219259A (en) Crack-preventing work for concrete
JPH0332673B2 (en)
JPH05340093A (en) Concrete molding form
JPS63151692A (en) Surface finishment for cement set body
JPH05309632A (en) Concrete shuttering for molding of concrete block
JPH02267177A (en) Aging of concrete body
JPH01245958A (en) Production of fiber reinforced composite material
JPS62170325A (en) Manufacture of resin mortar products
JPH01226313A (en) Preparation of resin molded item
JP2000303685A (en) Form for concrete
JPS6315137B2 (en)
JPS59124805A (en) Preparation of mold
JPH0114378Y2 (en)