JPH03277886A - Integral suspended construction for piping - Google Patents

Integral suspended construction for piping

Info

Publication number
JPH03277886A
JPH03277886A JP7406690A JP7406690A JPH03277886A JP H03277886 A JPH03277886 A JP H03277886A JP 7406690 A JP7406690 A JP 7406690A JP 7406690 A JP7406690 A JP 7406690A JP H03277886 A JPH03277886 A JP H03277886A
Authority
JP
Japan
Prior art keywords
surface plate
floor
piping
lifting
supporting pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7406690A
Other languages
Japanese (ja)
Other versions
JP2551192B2 (en
Inventor
Masato Gunji
郡司 正人
Yusuke Ishikawa
祐助 石川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Plant Technologies Ltd filed Critical Hitachi Plant Technologies Ltd
Priority to JP2074066A priority Critical patent/JP2551192B2/en
Publication of JPH03277886A publication Critical patent/JPH03277886A/en
Application granted granted Critical
Publication of JP2551192B2 publication Critical patent/JP2551192B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE:To secure the suspending construction for piping, etc., at high working efficiency and in high safety by erecting a supporting pillar rod on a surface plate for assembling a single article on a floor surface, connecting the supporting pillar rod with a hoisting rope, suspending the surface plate by hoisting a hoisting roll after assembling pipings previously and fixing the supporting pillar rod. CONSTITUTION:A supporting pillar rod 16 is erected upward on a surface plate 12 for assembling single article which is placed on the surface of a floor 10. On a floor board 18 on the upper part stage which constitutes a ceiling part, a penetration sleeve 20 is embedded in correspondence with the supporting pillar rod 16, and a hoisting wire rope 26 is installed, together with a winch 22 and a guide pulley. After pipings 14 are assembled on the surface plate 12, the surface plate 12 is hoisted by winding the wire rope 26, and the supporting pillar rod 16 is fixed through the penetration of the floor panel 18 on the upper part stage, and connected with the pipings 14 on the surface plate 12. Accordingly, the working efficiency and safety can be improved, and the manhour can be reduced.

Description

【発明の詳細な説明】[Detailed description of the invention] 【産業上の利用分野】[Industrial application field]

この発明、は、配管類の吊り上げ工法に係り、特に床上
で一体化組立てた製品を定盤ごと吊り上げる一体化吊り
上げ工法に関する。
The present invention relates to a method for hoisting piping, and more particularly to an integrated hoisting method for hoisting a product that has been integrally assembled on a floor together with a surface plate.

【従来の技術】[Conventional technology]

従来、建屋の各階の天井部に配管を設備したり、あるい
はダクトを設備する作業においては、次のような作業工
程となっていた。すなわち、予め製品の吊り上げ設定位
置に木組足場あるいは吊り足場を構築し、天井部床下面
に埋め込んだ埋込金物に吊り金具を取り付け、チェーン
ブロックなどの揚重手段を用いて、単品ずつ足場上に吊
り上げ、足場上で単品を継ぎ合わせ一体化していた。
Conventionally, the work process for installing piping or ducts in the ceiling of each floor of a building was as follows. In other words, a wooden scaffold or hanging scaffold is constructed in advance at the location where the product is to be lifted, the hanging fittings are attached to the embedded hardware embedded in the underside of the ceiling floor, and each item is lifted onto the scaffold one by one using a lifting means such as a chain block. The pieces were hoisted up, and the individual parts were pieced together on scaffolding.

【発明が解決しようとする課題】[Problem to be solved by the invention]

しかし、このような従来工法にあっては、床上からの足
場構築作業が発生するのみならす、せっかく構築した足
場が、製品の吊り上げおよび足場上への引き込み時に、
干渉したり障害となったりして、足場の一部解体作業が
発生したりする。 また、この工法では、製品の吊り上げごとに多くの作業
員を必要とするばかりでなく、仮設資材、設備か必要と
なり、それを操作するのに多大な労力を費やしていた。 更に、足場の組立て作業及び製品の一体化作業が、高所
作業となるため、安全性においても危険的要素が高いな
どの欠点があった。 この発明の目的は、前記従来工法の欠点を解消し、作業
効率が良く、かつ安全性の高い配管やダクト類の一体化
吊り上げ工法を提供するにある。
However, with such conventional construction methods, not only does scaffold construction work occur from the floor, but also the scaffolding that has been constructed can be damaged when lifting products and pulling them onto the scaffolding.
Interference or obstruction may occur, requiring partial dismantling of the scaffolding. Furthermore, this construction method not only requires a large number of workers for each lifting of the product, but also requires temporary materials and equipment, which requires a great deal of effort to operate. Furthermore, since the work of assembling the scaffolding and the work of integrating the products are performed at heights, there is a drawback in terms of safety, such as a high degree of risk. An object of the present invention is to provide a method for integrally lifting piping and ducts, which eliminates the drawbacks of the conventional method, has good working efficiency, and is highly safe.

【課題を解決するための手段】[Means to solve the problem]

この工法は配管、ダクト類を床上で継ぎ合わせ一体化と
した製品を吊り上げることが効率的と考え、この吊り上
げ手段として、天井部床下面に埋込金物の代りに、上部
階床を貫通するスリーブ内にワイヤローブを通し上部階
床上より吊り上げる工法としたものである。 すなわち、本発明に係る配管類の一体化吊り上げ工法は
、建屋内に配管やダクト類を吊り上げ設定する工法にお
いて、床面に載置した単品組立用定盤に支柱ロッドを立
設してこれを上部階床盤を貫通して垂下された吊り上げ
ロープに連結し、前記定盤上にて予め配管類の単品相互
を組み付けた後に前記吊り上げロープを巻上げることに
より定盤を吊り上げ、前記支柱ロッドを上部階床盤に貫
通されてこれを固定することにより定盤上にて既設配管
類との接続を行なうように構成したものである。
This construction method is thought to be efficient in hoisting a product in which pipes and ducts are joined together on the floor, and as a means of lifting, instead of metal fittings embedded in the underside of the ceiling floor, a sleeve that penetrates the upper floor is used. The construction method was to pass a wire rope through the inside and lift it from above the upper floor. In other words, the integrated lifting method for piping according to the present invention is a method for lifting and setting piping and ducts inside a building, in which a support rod is erected on a single-item assembly surface plate placed on the floor. It is connected to a lifting rope hanging down through the upper floor panel, and after assembling individual pieces of piping to each other in advance on the surface plate, the surface plate is hoisted by winding up the lifting rope, and the support rod is It is constructed so that it is connected to the existing piping on the surface plate by penetrating the upper floor panel and fixing it.

【作用】[Effect]

建設現場の建屋内の配管、ダクト類の吊り上げ設定作業
を行なう場合、予め床面には足場兼用の定盤が載置され
ているので、この定盤上では定盤長さの範囲内で配管類
の単品を予め一体化に組立てることができる。一方、天
井部の吊り上げ位置には、その上部隅の床盤をスリーブ
等を貫通させて吊り上げ用ワイヤローブを数本下げ、こ
れを定盤に設けた支柱ロッドの先端に連結しておく。床
上で一体化した配管、ダクト類を定盤ごと上部隅の床面
上に据え付けたウィンチ等によりワイヤローブを巻取り
、吊り上げる。そして、支柱ロッドを上部隅のローブ貫
通部に差込み、これを固定支持することにより定盤は上
部隅の床盤に固定される。この状態では定盤は固定保持
されているので既設の配管類への接続を安定かつ安全に
行なうことができる。作業終了後は、前記設定作業の逆
手順により定盤のみを吊り降ろせばよい。
When lifting and setting piping and ducts inside a building at a construction site, a surface plate that also serves as a scaffold is placed on the floor in advance. Single items of the same type can be pre-assembled into one piece. On the other hand, at the lifting position of the ceiling, several lifting wire lobes are lowered by passing sleeves or the like through the floor plate at the upper corner thereof, and these are connected to the tips of support rods provided on the surface plate. The pipes and ducts integrated on the floor are wound around the wire robe using a winch installed on the floor in the upper corner along with the surface plate, and lifted up. Then, the support rod is inserted into the lobe penetration portion at the upper corner and fixedly supported, thereby fixing the surface plate to the floor plate at the upper corner. In this state, the surface plate is held fixed, so that connections to existing piping can be made stably and safely. After completing the work, it is sufficient to suspend only the surface plate by reversing the setting work described above.

【実施例】【Example】

以下に本発明に係る配管類の一体化吊り上げ工法の具体
的実施例を図面を参照して詳細に説明する。 第1図は、床上での組立図を、第2図は吊り上げ図を、
第3図は吊り上げの断面図を示す。これらの図に示すよ
うに、この工法を実施するために、最初床10面上に載
置される定盤12が使用される。この定盤12は作業台
と作業用足場を兼用するもので、形鋼等をトラス組みし
た矩形平板状に形成Nれたものである。そして作業対象
の単品ダクト(または配管)14が複数同時に配列でき
るような平面サイズをもっている。このような定盤12
の外周縁の四隅部には上方に向けて立設させた支柱ロッ
ド16が接続クランプ17を介して固定されており、こ
れは定盤12上に載置される前記単品ダクト14より充
分高い位置に達する長さをもっている。そしてロッド端
には雄ねじが切られている。 一方、定盤12が載置されている階層の天井部を構成し
ている上部隅の床盤18には前記支柱ロッド16に対応
して、コンクリート打設時に予め貫通スリーブ20か埋
設されている。上部隅の床面上には巻き上げウィンチ2
2および案内滑車24が設置されており、これらを介し
て繰り出される右き上げ用ワイヤーローブ26を前記貫
通スリーブ20を通して定盤12の上方に垂れ下げ、前
記支柱ロッド16の先端に連結している。支柱ロッド1
6とロープ26の連結に際して、ロープ26にはロット
16先端の雄ねじに螺着可能なナツト28を貫通させて
いる。 なお、定盤12の上面両側部には足場板30が取り付け
られ、また、保護柵となる手摺り32を設けるようにし
ている。 このような器材を用いて行なわれる作業は次のようにな
る。すなわち、床10上に載置した定盤12上に単品ダ
クト14を並べ、定盤12上でボルト、溶接などにて積
載可能な範囲で一体化する。 上部隅の床盤18に設けた貫通スリーブ20を通じて上
階床面に設置された案内滑車24を介七て巻き上げ用ワ
イヤーロープ26が垂れ下げられているので、これを各
支柱ロッド16の先端に連結する。このとく、ロープ2
6にはナツト28を通しておく。 下階床10上において定盤12上で複数の単品ダクト1
4を一体化に組み上げたならば、定盤12に必要な安全
設備、足場板30、手摺り32を設け、上部階の床上に
設置した巻上ウィンチ22にて、定盤12ごと一体にて
吊り上げる。そして、上部階の床盤18の貫通スリーブ
20内に支柱ロッド16を差込み、先端を上部階床面か
ら突出させる。 所定の設定レベルまで吊り上げたなら、予め、ワイヤロ
ープ26内に貫通させた締付ナツト28と、分割構造と
した押えプレート34にて支柱ロッド16を押え込み、
ワイヤーロープ26切り離す。 この状態で、サポートなどの取付作業を行ない、ダクト
、配管などの上部作業を終了させる。 上部での取付作業が終了したら、吊り上げ作業の逆手順
も行ない解体するが、設置した配管、ダクト14は上部
に残し、定盤12のみを床上10に吊り降ろす。 上部階床に埋め込んだ貫通スリーブ20は、使用後はグ
ラウトを充填して閉塞する。これにより設置建屋が原子
力設備用の場合であっても放射能に対する影響は無い。 なお、前記実施例においては、製品と一体で吊り上げる
工法について説明したが、これは単に数段の足場を組合
せた足場設備のみの吊り上げ工法としても良い。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Specific embodiments of the method for integrally lifting piping according to the present invention will be described in detail below with reference to the drawings. Figure 1 shows the assembly diagram on the floor, Figure 2 shows the lifting diagram.
FIG. 3 shows a sectional view of the lift. As shown in these figures, in order to carry out this construction method, a surface plate 12 that is initially placed on a floor 10 is used. This surface plate 12 serves both as a workbench and a scaffold for work, and is formed into a rectangular flat plate made of trussed steel sections. The planar size is such that a plurality of single ducts (or piping) 14 to be worked on can be arranged simultaneously. Such a surface plate 12
Support rods 16 are fixed to the four corners of the outer periphery via connection clamps 17, and are placed at a position sufficiently higher than the single duct 14 placed on the surface plate 12. It has a length that reaches . A male thread is cut at the end of the rod. On the other hand, a penetration sleeve 20 is buried in the upper corner floor plate 18 constituting the ceiling of the floor on which the surface plate 12 is placed, corresponding to the support rod 16, in advance at the time of concrete pouring. . There is a winch 2 on the floor in the upper corner.
2 and a guide pulley 24 are installed, and a wire lobe 26 for lifting to the right that is fed out through these is suspended above the surface plate 12 through the penetration sleeve 20 and connected to the tip of the support rod 16. . Strut rod 1
6 and the rope 26, a nut 28 which can be screwed onto the male thread at the tip of the rod 16 is passed through the rope 26. Scaffolding boards 30 are attached to both sides of the upper surface of the surface plate 12, and handrails 32 serving as a protective fence are also provided. The operations performed using such equipment are as follows. That is, the individual ducts 14 are arranged on a surface plate 12 placed on the floor 10, and are integrated on the surface plate 12 by bolts, welding, etc. to the extent that they can be loaded. A hoisting wire rope 26 is suspended from a guide pulley 24 installed on the upper floor through a through-sleeve 20 provided on the floor panel 18 at the upper corner, and is attached to the tip of each support rod 16. Link. In this case, rope 2
Pass nut 28 through 6. Multiple single ducts 1 on the surface plate 12 above the lower floor 10
4 is assembled into one unit, the necessary safety equipment, scaffolding board 30, and handrail 32 are installed on the surface plate 12, and the surface plate 12 is assembled together with the hoisting winch 22 installed on the floor of the upper floor. lift. Then, the support rod 16 is inserted into the penetrating sleeve 20 of the floor board 18 on the upper floor, and the tip thereof is made to protrude from the upper floor surface. Once it has been lifted to a predetermined setting level, the support rod 16 is held down using the tightening nut 28 passed through the wire rope 26 in advance and the holding plate 34 which has a split structure.
Cut off wire rope 26. In this state, installation work such as supports is carried out, and upper part work such as ducts and piping is completed. When the installation work at the upper part is completed, the lifting work is reversed and dismantled, but the installed pipes and ducts 14 are left at the upper part, and only the surface plate 12 is lowered to the floor 10. The penetration sleeve 20 embedded in the upper floor is filled with grout and closed after use. As a result, even if the installation building is for nuclear equipment, there is no effect on radioactivity. In the above embodiments, a method of lifting the product together with the product has been described, but this may also be a method of lifting only the scaffolding equipment, which is a combination of several stages of scaffolding.

【発明の効果】【Effect of the invention】

以上説明したように、本発明に係る工法は、床面に載置
した単品組立用定盤に支柱ロッドを立設してこれを上部
階床盤を貫通して垂下された吊り上げロープに連結し、
前記定盤上にて予め配管類の単品相互を組み付けた後に
前記吊り上げロープを巻上げることにより定盤を吊り上
げ、前記支柱ロッドを上部階床盤に貫通されてこれを固
定することにより定盤上にて既設配管類との接続を行な
うようにしたので、作業効率および安全性に優れ、かつ
、工数低減が可能な吊り上げ工法とすることができる。
As explained above, the construction method according to the present invention involves installing support rods upright on a surface plate for assembling single items placed on the floor, and connecting the support rods to a lifting rope that passes through the upper floor board and hangs down. ,
After assembling individual pieces of piping on the surface plate in advance, the surface plate is lifted by winding up the lifting rope, and the support rods are passed through the upper floor board and fixed, thereby lifting the pipes onto the surface plate. Since the connection to the existing piping is made at , it is possible to use a lifting method that is superior in work efficiency and safety and can reduce the number of man-hours.

【図面の簡単な説明】[Brief explanation of drawings]

図面は実施例に係る一体化吊り上げ工法を実施する設備
構成を示すもので、第1図は吊り上げ前の床面上での組
立て状態を示す側面図、第2図は同吊り上げ状態の側面
図、第3図は第2図の断面図である。 10・・・・・・床、12・・・・・・定盤、14・・
・・・・単品ダクト(または配管)、16・・・・・・
支柱ロッド、18・・・・・・上部階床盤、20・・・
・・・貫通スリーブ、22・・・・・巻き上げウィンチ
The drawings show the configuration of equipment for carrying out the integrated lifting method according to the embodiment. Figure 1 is a side view showing the assembled state on the floor before lifting, Figure 2 is a side view of the same lifting state, FIG. 3 is a sectional view of FIG. 2. 10...Floor, 12...Surface plate, 14...
...Single duct (or piping), 16...
Support rod, 18... Upper floor board, 20...
... Penetration sleeve, 22 ... Hoisting winch.

Claims (1)

【特許請求の範囲】[Claims] 1)、建屋内に配管やダクト類を吊り上げ設定する工法
において、床面に載置した単品組立用定盤に支柱ロッド
を立設してこれを上部階床盤を貫通して垂下された吊り
上げロープに連結し、前記定盤上にて予め配管類の単品
相互を組み付けた後に前記吊り上げロープを巻上げるこ
とにより定盤を吊り上げ、前記支柱ロッドを上部階床盤
に貫通されてこれを固定することにより定盤上にて既設
配管類との接続を行なうことを特徴とする配管類の一体
化吊り上げ工法。
1) In the method of lifting and setting piping and ducts inside a building, a support rod is erected on a surface plate for single assembly placed on the floor, and the rod is suspended by penetrating the upper floor panel. After connecting to a rope and assembling individual pieces of piping to each other on the surface plate in advance, the surface plate is hoisted by winding up the lifting rope, and the support rod is passed through the upper floor board and fixed. An integrated lifting method for piping, which is characterized by connecting existing piping on a surface plate.
JP2074066A 1990-03-23 1990-03-23 Integrated lifting method for piping Expired - Lifetime JP2551192B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2074066A JP2551192B2 (en) 1990-03-23 1990-03-23 Integrated lifting method for piping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2074066A JP2551192B2 (en) 1990-03-23 1990-03-23 Integrated lifting method for piping

Publications (2)

Publication Number Publication Date
JPH03277886A true JPH03277886A (en) 1991-12-09
JP2551192B2 JP2551192B2 (en) 1996-11-06

Family

ID=13536445

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2074066A Expired - Lifetime JP2551192B2 (en) 1990-03-23 1990-03-23 Integrated lifting method for piping

Country Status (1)

Country Link
JP (1) JP2551192B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635732A (en) * 2012-04-13 2012-08-15 中国海洋石油总公司 Process for mounting relatively long pipeline

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269928A (en) * 2017-05-16 2017-10-20 广西建工集团第五建筑工程有限责任公司 A kind of construction method of large-scale Pipe installing arranged side by side

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02168090A (en) * 1988-12-22 1990-06-28 Hitachi Ltd Installation method for piping, valve, and support and support structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02168090A (en) * 1988-12-22 1990-06-28 Hitachi Ltd Installation method for piping, valve, and support and support structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635732A (en) * 2012-04-13 2012-08-15 中国海洋石油总公司 Process for mounting relatively long pipeline

Also Published As

Publication number Publication date
JP2551192B2 (en) 1996-11-06

Similar Documents

Publication Publication Date Title
JPH0220354Y2 (en)
JPH03277886A (en) Integral suspended construction for piping
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JP2669254B2 (en) Side wall panel mounting method
JPH09177070A (en) Method and device for placing of steel bar cage for deep foundation
JPH0637159Y2 (en) Hanging scaffolding
JP3015229B2 (en) Construction method of vertical pipe of high-rise building
JP2843042B2 (en) Steel framing unit scaffolding method
JPH0430213Y2 (en)
JPH0546425B2 (en)
JPH1179602A (en) Work floor device for installing elevator
JPH02305785A (en) Elevator installation process and working floor device for elevator installation
JPH09296610A (en) Outside curing unit
JP6868342B2 (en) Effective use of vertical hole space in the construction process of multi-story buildings
JPH09310484A (en) Large space applicable suspended scaffold constructing system
JPH01127585A (en) Method of installation construction of elevator
JPH04153460A (en) Constructing method for building, and its equipment
JPS5940374Y2 (en) Elevator installation equipment
JPH06229116A (en) Construction of suspended scaffold in steel frame structure
JPH04237761A (en) Method for constructing high place facility
JPS647149Y2 (en)
JPH0423710B2 (en)
JPH035547A (en) Outer wall half pc plate and mounting method thereof
JPH06248803A (en) Construction method of external facing panel in structure
JPH01275860A (en) Scaffold for wire control-type inside operation of furnace