JPH03262836A - Underground structure and its construction - Google Patents

Underground structure and its construction

Info

Publication number
JPH03262836A
JPH03262836A JP2063813A JP6381390A JPH03262836A JP H03262836 A JPH03262836 A JP H03262836A JP 2063813 A JP2063813 A JP 2063813A JP 6381390 A JP6381390 A JP 6381390A JP H03262836 A JPH03262836 A JP H03262836A
Authority
JP
Japan
Prior art keywords
underground
continuous wall
bottom plate
constructing
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2063813A
Other languages
Japanese (ja)
Inventor
Hiroshi Kazama
風間 広志
Yoshinobu Inoue
井上 嘉信
Yoshiaki Negami
根上 義昭
Noriji Miyake
紀治 三宅
Atsushi Denda
傳田 篤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2063813A priority Critical patent/JPH03262836A/en
Publication of JPH03262836A publication Critical patent/JPH03262836A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To reduce cost by conducting construction in water in which the bottom part of an underground continuous wall is blocked with a bottom plate, downward protrudedly and curvedly formed, and the bottom plate is fixed with plural anchors. CONSTITUTION:A part, surrounded with close-ringed tubular underwater continuous wall 10 in the natural ground G is underwater-excavated, and moreover a part lower than the lower end of the wall 10 is bowllikely excavated. Next a bottom plate 20, curvedly formed so as to be a downwardly protruded state, is intergratedly constructed with the continuous wall 10 in water to improve the bearing force of the bottom plate 20 against buoyancy. Then plural anchors, for supporting the bottom plate 20 with their upper end parts fixed to the bottom plate 20, are provided in water on the natural ground G under the bottom plate 20. This permits low-cost construction.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は地中構造物およびその構築方法に係わり、特に
、地下水により地中構造物の底版(底部床版)に作用す
る浮力に有効に対処し得る地中構造物およびその構築方
法に関する。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to an underground structure and a method of constructing the same, and in particular, to an underground structure that effectively reduces the buoyant force acting on the bottom slab (bottom slab) of an underground structure due to groundwater. Concerning underground structures that can be used and their construction methods.

〔従来の技術〕[Conventional technology]

従来、地中構造物の構築方法のごく一般的なものとして
ケーソン工法が知られている。ケーソン工法により地中
構造物を構築する場合には、例えばコンクリート製の函
体を、該函体の設置部分の地山を掘削しながら地中に沈
設していく方法が採られる。
Conventionally, the caisson method has been known as a very common method for constructing underground structures. When constructing an underground structure using the caisson construction method, a method is adopted in which, for example, a concrete box is sunk into the ground while excavating the ground where the box will be installed.

しかしながら、上記ケーソン工法による地中構造物の構
築方法にあっては、ケーソンが大型となると沈設が難し
くなり、大径・大深度の地中構造物に適用した場合コス
トが嵩み、かつ工期も長くなるといった問題がある。
However, in the method of constructing underground structures using the caisson construction method, as the caisson becomes larger, it becomes difficult to sink it, and when applied to large-diameter, deep-seated underground structures, the cost increases and the construction period is also shortened. There is a problem with the length.

そこで、構築すべき地中構造物が大型であったり、ある
いは大深度である場合には、地中構造物を地中連続壁に
より構築するのが一般的である。
Therefore, when the underground structure to be constructed is large-sized or located at a great depth, it is common to construct the underground structure using an underground continuous wall.

地中連続壁は、地山内にコンクリート構造体を構築して
いくものであるため、既製の構造体を沈設するケーソン
工法に比べ、地下構造物の大型化・大深度化への適用が
容易である。
Because underground continuous walls are constructed as a concrete structure within the ground, they are easier to apply to larger and deeper underground structures than the caisson construction method, which involves sinking a ready-made structure. be.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

ところで、上記のように地中連続壁工法により地中構造
物を構築するする場合においても下記の如き問題があっ
た。
By the way, even when constructing an underground structure using the underground continuous wall construction method as described above, there are the following problems.

すなわち、第9図に示すように、通常、他山G内には地
下水か存在する (図中ラインWは地下水位を示す)た
め、一般に地中構造物lの底版20にはこの地下水によ
る浮力を受ける。この浮力を減するためには、構造物底
部に湧水処理層を設けるなどして積極的に地下水を排水
する手段があるが、この地下水の排水により周辺地山が
変形あるいは崩壊を起こし、周辺環境に悪影響を及ぼす
おそれがある。このため従来は、同第9図に示すように
、地中連続壁lOを地山G内の不透水層4まで根入れす
ることにより止水壁を形成し、これによって地下水の侵
入を防ぐとともに、浮力に対する抵抗力を持たせた構造
としていた。
In other words, as shown in Fig. 9, there is usually groundwater within the mountain G (line W in the figure indicates the groundwater level), so the bottom slab 20 of the underground structure I generally has buoyancy due to this groundwater. receive. In order to reduce this buoyancy, there are methods to actively drain groundwater, such as installing a spring water treatment layer at the bottom of the structure, but this drainage of groundwater causes deformation or collapse of the surrounding ground, causing May have a negative impact on the environment. For this reason, conventionally, as shown in Fig. 9, a water-stop wall was formed by embedding an underground continuous wall lO up to the impermeable layer 4 in the ground G, thereby preventing the intrusion of groundwater and The structure was designed to resist buoyancy.

しかしながら、上記構造の地中構造物lにあっては、地
中連続壁10を、地中構造物の実際上の底部より遥か下
方にまで延出させて構築する必要があり、コスト高にな
るといった不都合があった。
However, in the underground structure I having the above structure, it is necessary to construct the underground continuous wall 10 extending far below the actual bottom of the underground structure, which increases the cost. There were some inconveniences.

本発明は上記の事情に鑑みてなされたもので、底版に作
用する浮力を有効に抑えることができ、しかも底版の肉
厚を極力小さくしてコストダウンが図れ、大形・大深度
の地中構造物にも有効に適用することのできる、地中構
造物およびその構築方法を提供することを目的とするも
のである。
The present invention has been made in view of the above circumstances, and it is possible to effectively suppress the buoyant force acting on the bottom plate, reduce the thickness of the bottom plate as much as possible, and reduce costs. It is an object of the present invention to provide an underground structure and a method for constructing the same, which can be effectively applied to structures.

〔課題を解決するための手段〕[Means to solve the problem]

本発明の請求項1に係る地中構造物は、地山中に筒状に
形成され構造物の外殻を成す地中連続壁と、該地中連続
壁の底部を閉塞して形成された底版と、上端部を該底版
に定着されて該底版よりも下方の地山内に設けられた複
数のアンカーとを有して構成され、しかも前記底版は下
向きに凸となる如く湾曲形成されていることを特徴とす
るものである。
The underground structure according to claim 1 of the present invention includes an underground continuous wall formed in a cylindrical shape in the earth and forming the outer shell of the structure, and a bottom plate formed by closing the bottom of the underground continuous wall. and a plurality of anchors whose upper ends are fixed to the bottom plate and provided in the ground below the bottom plate, and the bottom plate is curved so as to be convex downward. It is characterized by:

本発明の請求項2に記載した発明は請求項1記載の地中
構造物の構築方法であって、地山中に水平面内において
閉環された筒状の地中連続壁を構築する工程と、水中掘
削により前記地山の前記地中連続壁により囲まれた部分
を掘削するとともに地中連続壁下端よりさらに下方部分
を椀型に掘削する工程と、前記工程により形成された掘
削穴底部に、該底部に沿った椀型を成し前記地中連続壁
と一体となる底版を水中にて構築する工程と、前記底版
の下方地山に、上端部を前記底版に定着されて該底版を
支持するためのアンカーを水中にて設ける工程と、を有
することを特徴とするものである。
The invention described in claim 2 of the present invention is a method for constructing an underground structure according to claim 1, which includes the step of constructing a closed cylindrical underground continuous wall in a horizontal plane in the ground, and a step of excavating a portion of the ground surrounded by the underground continuous wall and excavating a portion further below the lower end of the underground continuous wall into a bowl shape; A step of constructing a bottom slab in water that forms a bowl shape along the bottom and is integrated with the underground continuous wall, and supporting the bottom slab by fixing its upper end to the bottom slab in the ground below the bottom slab. The method is characterized by comprising a step of providing an anchor for the purpose underwater.

さらに、本発明の請求項3に記載した発明は請求項2記
載の地中構造物の構築方法において、前記底版を構築す
るに際し、該底版を構成する鉄筋篭を椀型に形成すると
ともに、該鉄筋篭の上部には予め該鉄筋篭の上面形状に
沿う上部型枠を付設しておき、これら鉄筋篭および上部
型枠を一体として前記掘削穴底部に設置することを特徴
とするものである。
Furthermore, the invention described in claim 3 of the present invention is the method for constructing an underground structure according to claim 2, in which, when constructing the bottom slab, a reinforcing bar cage constituting the bottom slab is formed into a bowl shape, and The present invention is characterized in that an upper formwork that follows the shape of the upper surface of the reinforcing bar cage is attached in advance to the upper part of the reinforcing bar cage, and the reinforcing bar cage and the upper formwork are installed as one at the bottom of the excavation hole.

〔作用 〕 請求項1記載の地中構造物によれば、底版に作用する上
向きの力がアンカーにより支持され、底版の浮力に対す
る抵抗力が増す。また、底版を下方に湾曲させたいわゆ
る椀型に形成したので、浮力に対する底版の耐力が向上
する。
[Function] According to the underground structure according to the first aspect, the upward force acting on the bottom slab is supported by the anchor, and the resistance of the bottom slab to the buoyancy force is increased. Moreover, since the bottom plate is formed into a so-called bowl shape that is curved downward, the resistance of the bottom plate against buoyancy is improved.

また、請求項2記載の地中構造物の構築方法によれば、
水中にて底版を構築し、しかもこの底版をアンカーにて
定着した後に地中連続壁内の水を排水するため、構築中
にあっても底版に浮力を生じさせることなく施工するこ
とができる。
Further, according to the method for constructing an underground structure according to claim 2,
Since the bottom slab is constructed underwater and the water in the underground continuous wall is drained after the bottom slab is fixed with anchors, construction can be carried out without creating buoyancy in the bottom slab even during construction.

そして、請求項3記載の地中構造物の構築方法によれば
、掘削穴の底部にて煩わしい位置決め操作等を行いなが
ら型枠を鉄筋篭に付設する必要がなく、特に、底版の構
築を水中にて行うものにおいて極めて有効となる。
According to the method for constructing an underground structure according to claim 3, there is no need to attach the formwork to the reinforcing bar cage while performing troublesome positioning operations at the bottom of the excavated hole. It is extremely effective when used in

〔実施例〕〔Example〕

以下、本発明の実施例を図面を参照しながら説明する。 Embodiments of the present invention will be described below with reference to the drawings.

第1図は本発明に係る地中構造物の一例を示したもので
ある。該地中構造物lは地山G中に構築されたもので、
この場合は全体として有底筒状に形成されたものとなっ
ている。該地中構造物二は、例えば建築物の基礎、ある
いは建築物地階、地下工場、地下駐車場等の地下施設を
構成するものである。図中地山G内において、ラインW
は地下水位を、また、符号4は不透水層を表わしている
FIG. 1 shows an example of an underground structure according to the present invention. The underground structure l is constructed in the ground G,
In this case, the whole is formed into a cylindrical shape with a bottom. The underground structure 2 constitutes, for example, the foundation of a building, or an underground facility such as a building basement, an underground factory, or an underground parking lot. Line W within Mt. G in the map
represents the groundwater level, and numeral 4 represents the impermeable layer.

前記地中構造物(以下、“構造物”と略称する)1にお
いて、符号lOは該構造物1の側壁部を構成する地中連
続壁(以下、“連続壁°と略称する)、符号20は該構
造物lの底版、符号30は上端部を該底版20に定着さ
れ、該底版20の下方地山内に打設されたアンカーであ
る。なお、該構造物lを例えば地下施設として利用する
場合には、底版20の上に本設の床版(図示時)を施工
する。
In the underground structure (hereinafter abbreviated as "structure") 1, reference numeral 10 denotes an underground continuous wall (hereinafter abbreviated as "continuous wall °") 20 that constitutes the side wall of the structure 1. is a bottom plate of the structure 1, and reference numeral 30 is an anchor whose upper end is fixed to the bottom plate 20 and is driven into the ground below the bottom plate 20.The structure 1 may be used, for example, as an underground facility. In this case, a permanent floor slab (as shown) is constructed on top of the bottom slab 20.

ここで、前記底版20は下向きに凸となる如く湾曲に形
成され、いわゆる椀型に形成されたものとなっている。
Here, the bottom plate 20 is curved so as to be convex downward, and is formed in a so-called bowl shape.

また、この底版20は図示の如く、その椀型を呈す内径
部が前記連続壁10の内径よりも若干小径に形成されて
おり、この場合その連続!!L10の内面10aよりも
内側に入り込んだ部分が内面10aに沿って若干上方に
延出したものとなっている。
Further, as shown in the figure, the inner diameter portion of the bottom plate 20 is formed to have a bowl shape with a slightly smaller diameter than the inner diameter of the continuous wall 10. In this case, the bottom plate 20 is continuous! ! A portion of L10 that goes inside the inner surface 10a extends slightly upward along the inner surface 10a.

上記構造物lは下記の工程により構築される。The above structure 1 is constructed by the following steps.

、地中連続壁の構築 前記地中連続壁10を地山G内に構築する。この地中連
続壁IOは、従来一般の地中連続壁工法により構築すれ
ばよい。
, Construction of underground continuous wall The underground continuous wall 10 is constructed within the ground G. This underground continuous wall IO may be constructed by a conventional common underground continuous wall construction method.

この地中連続壁■0はFi記構造遺物の外殻を成すもの
であるから、その断面形状は構造物lに応じて任意に決
定すればよい。本実施例では、この地中連続壁10を、
断面円形を呈した円筒状に形成している。
Since this underground continuous wall (20) forms the outer shell of the Fi structure relic, its cross-sectional shape may be arbitrarily determined depending on the structure (1). In this embodiment, this underground continuous wall 10 is
It is formed into a cylindrical shape with a circular cross section.

、水中掘削 地中連続壁lOが構築されたら、地山Gにおける前記連
続壁10により囲まれた部分、さらには連続壁lOの下
端よりさらに下方の部分を掘削する。この掘削作業は、
掘削部に水を貯留しながら水中掘削法により行う。この
水中掘削法も、従来一般に実施されているものに準じて
行えばよい。
, Underwater excavation Once the underground continuous wall 10 is constructed, the part of the ground G surrounded by the continuous wall 10 and further the part further below the lower end of the continuous wall 10 is excavated. This excavation work
This is done using the underwater drilling method while storing water in the excavation area. This underwater excavation method may also be carried out according to the method generally practiced in the past.

貯留する水3は清水であっても泥水であってもよい。こ
のとき、連続壁10より下方部分の掘削は、掘削面が下
向きに湾曲する如くいわゆる椀型に掘削する。その際、
連続壁IOに対応した部分の掘削は、通常一般のクラム
シェル等により行うことができ、また、連続壁lOの下
端部よりも下方部の掘削は、例えば第2図に示す如くブ
ームカッタ装置50を用いることにより、連続壁lOの
内径よりも大径となる掘削穴を形成することが可能であ
る。
The water 3 to be stored may be fresh water or muddy water. At this time, the portion below the continuous wall 10 is excavated in a so-called bowl shape so that the excavated surface is curved downward. that time,
Excavation of the portion corresponding to the continuous wall IO can be carried out using a general clamshell or the like, and excavation below the lower end of the continuous wall IO can be carried out using a boom cutter device 50, for example, as shown in FIG. By using this, it is possible to form an excavated hole having a diameter larger than the inner diameter of the continuous wall IO.

iii 、底版の施工 次いで、上記水中掘削により形成された掘削穴2の底部
に、前記底版20を施工する。
iii. Construction of bottom slab Next, the bottom slab 20 is constructed at the bottom of the excavated hole 2 formed by the underwater excavation.

1ii−■ 地中連続壁の底版構築部のケレン形成すべ
き底版20と地中連続壁lOとの一体化が図れるように
、地中連続壁IOの内面10aにおける、前記底版、2
0が形成されるべき下端部のケレンを行う。
1ii-■ In order to integrate the bottom slab 20 to be formed in the bottom slab construction part of the underground continuous wall with the underground continuous wall IO, the bottom slab, 2 on the inner surface 10a of the underground continuous wall IO is installed.
Carve the bottom edge where 0 is to be formed.

本実施例においては、このケレン作業を第3図および第
4図に示すケレン装置60により行うものとしている。
In this embodiment, this cleaning work is performed using a cleaning device 60 shown in FIGS. 3 and 4.

ここで、このケレン装置60の構成について説明する。Here, the configuration of this cleaning device 60 will be explained.

該ケレン装置60は、地上に設置された揚重手段により
懸吊支持され、前記掘削穴2の上方開口部より掘削穴2
内に挿入される。該ケレン装置60は、リング状に形成
されたフレーム61と、該フレーム61から放射状に延
びた少なくとも3本のガイドアーム62 (図示例のも
のは4本)と、同じくフレーム61から放射状に延びた
軸部65の先端に設けられた噴射ノズル66とを主要構
成要素として備えたものとなっている。
The cleaning device 60 is suspended and supported by a lifting means installed on the ground, and is opened from the upper opening of the excavation hole 2.
inserted within. The keren device 60 includes a ring-shaped frame 61, at least three guide arms 62 (four in the illustrated example) extending radially from the frame 61, and at least three guide arms 62 (four guide arms 62 in the illustrated example) extending radially from the frame 61. The main component includes an injection nozzle 66 provided at the tip of a shaft portion 65.

前記フレーム6Iは、そのリング体の中心部を回転中心
として、センターボール(支持部材)67の軸線回りに
回動自在に懸吊支持される。前記ガイドアーム62は、
この場合油圧ジヤツキ68の作動により長手方向伸縮自
在に構成され、かつ、地中連続壁lOの壁面と当接する
先端部には車輪64が設けられている。そして、前記フ
レーム61は、このガイドアーム62が地中連続壁lO
内面に突っ張ることにより水平方向の移動が規制される
。また、前記噴射ノズル66は、その先端部が前記ガイ
ドアーム62の先端部より若干引っ込んだ位置にセット
されている。
The frame 6I is suspended and supported so as to be rotatable around the axis of a center ball (support member) 67, with the center of the ring body as the center of rotation. The guide arm 62 is
In this case, it is configured to be extendable and retractable in the longitudinal direction by the operation of a hydraulic jack 68, and a wheel 64 is provided at the tip that comes into contact with the wall surface of the underground continuous wall IO. The frame 61 has this guide arm 62 connected to the underground continuous wall lO.
Horizontal movement is restricted by tensioning the inner surface. Further, the injection nozzle 66 is set at a position where its tip is slightly retracted from the tip of the guide arm 62.

上記構成となるケレン装置60を用いて、前記噴射ノズ
ル66より水および空気を勢い良く噴射させながら、該
ケレン装置60全体を回転させると、噴射ノズル66か
らの噴流が地中連続壁lOの内面10aの下端部および
下端面10bの付着土砂等を除去し、コンクリート面を
露呈させることができる。
Using the cleaning device 60 having the above configuration, when the entire cleaning device 60 is rotated while injecting water and air vigorously from the injection nozzle 66, the jet from the injection nozzle 66 flows into the inner surface of the underground wall lO. Adhering soil and the like on the lower end portion 10a and the lower end surface 10b can be removed to expose the concrete surface.

山−■ 鉄筋篭の組み立て 地中連続壁10の下端内面のケレンが終了したならば、
床版20を構築するための鉄筋篭21の組立てを行う。
Mountain - ■ Assembling the reinforcing bar cage Once the inner surface of the lower end of the underground continuous wall 10 has been cleaned,
The reinforcing bar cage 21 for constructing the floor slab 20 is assembled.

鉄筋篭21は、例えば、掘削穴2内に貯留されている水
3の水面上に台船を浮かべ、それら台船上にて組み立て
る。
The reinforcing bar cage 21 is assembled on a barge, for example, by floating a barge on the surface of water 3 stored in the excavated hole 2.

ここで、この鉄筋篭21は第5図に示すように、全体に
椀型に形成され、たちのとなっている。また、この鉄筋
21の上部には、予め該鉄筋篭21の上面形状に沿うよ
うに椀型に形成した型枠(上部型枠)29を鉄筋篭21
と一体に固定しておく。
Here, as shown in FIG. 5, this reinforcing bar cage 21 is formed into a bowl shape as a whole, and has a vertical shape. Further, on the upper part of the reinforcing bar 21, a formwork (upper formwork) 29 previously formed in a bowl shape so as to follow the top surface shape of the reinforcing bar cage 21 is installed.
Fix it together.

さらに、本実施例においては、前記鉄筋篭21に、図示
の如く後述するトレミー管25をつなぐためのトレミー
管用補助管26、および後述するアンカーガイド管31
をつなぐためのアンカーガイド管用補助管32をそれぞ
れ予め一体に設けておく。これらトレミー管用補助管2
6およびアンカーガイド管用補助管32は共に、前記型
枠29および鉄筋篭21を鉛直方向に貫通して設けられ
たもので、所定間隔をおいて鉄筋篭21の複数箇所に配
設されている。前記トレミー管用補助管26は、例えば
、図示の如くその下端が鉄筋篭21下端より僅かに上方
にて終端する一方、上端は型枠29より上方に突出した
ものとなっている。また、前記アンカーガイド管用補助
管32は、その下端が鉄筋篭21の下端とほぼ同じ位置
となり、かつ上端が型枠29よりも上方に突出したもの
となっている。
Furthermore, in this embodiment, the reinforcing bar cage 21 is provided with an auxiliary tremie tube 26 for connecting a tremie tube 25, which will be described later, as shown in the drawing, and an anchor guide tube 31, which will be described later.
An auxiliary anchor guide tube 32 for connecting the anchor guide tubes is provided integrally in advance. Auxiliary tube 2 for these tremie tubes
6 and the anchor guide pipe auxiliary pipe 32 are both provided vertically penetrating the formwork 29 and the reinforcing bar cage 21, and are arranged at a plurality of locations on the reinforcing bar cage 21 at predetermined intervals. The tremie tube auxiliary pipe 26 has, for example, its lower end terminating slightly above the lower end of the reinforcing bar basket 21 as shown in the figure, while its upper end projects upward from the formwork 29. Further, the anchor guide pipe auxiliary pipe 32 has its lower end positioned approximately at the same position as the lower end of the reinforcing bar cage 21, and its upper end protrudes above the formwork 29.

また、このアンカーガイド管用補助管32の下端開口部
には、該開口部を仮閉塞するための栓材33が詰め込ま
れている。栓材33は、例えばゴム栓、木材1モルタル
等である。さらに、前記両補助管26.32の上端には
、例えばネジ等の図示しない接続手段が構成されている
。なお、符号27は、該鉄筋篭21による形成される底
版20と、この底版20の上部に後打ちされる本設の床
版との一体化を図るためのアンカー鉄筋である。
Moreover, a plug material 33 for temporarily closing the opening is packed in the lower end opening of this anchor guide tube auxiliary tube 32. The plug material 33 is, for example, a rubber plug, wood mortar, or the like. Furthermore, connection means (not shown) such as screws are provided at the upper ends of both of the auxiliary pipes 26.32. Incidentally, reference numeral 27 is an anchor reinforcing bar for integrating the bottom slab 20 formed by the reinforcing bar basket 21 with the main floor slab installed later on the upper part of the bottom slab 20.

111−■ 鉄筋篭の沈設 上記の如き型枠29と一体となった鉄筋篭21が組み上
がったならば、その鉄筋篭21を一旦上方に吊り上げ、
上述の台船を取り除く。
111-■ Sinking the reinforcing bar cage Once the reinforcing bar basket 21 integrated with the formwork 29 as described above is assembled, the reinforcing bar cage 21 is once lifted upward,
Remove the barge mentioned above.

その後、鉄筋篭21を徐々に掘削穴2内に吊り下げてい
き、掘削穴2底部に着底させるが、その際、該鉄筋篭2
1を吊り下げていく途中で、第6図に示す如く、コンク
リート打設用のトレミー管25の分管25a、25a、
・・・およびアンカーガイド管31の分管31a、31
a、・・・を順次水上にて継ぎ足していく。つまり、ト
レミー管25の分管25a、25a、・・・のうち最初
のものは、前記鉄筋篭21に予め設けられた前記トレミ
ー管用補助管26に、また、アンカーガイド管31の分
管31a、31a。
Thereafter, the reinforcing bar basket 21 is gradually suspended into the excavated hole 2 and is brought to the bottom of the excavated hole 2. At this time, the reinforcing bar cage 2
1, as shown in FIG. 6, the branch pipes 25a, 25a,
... and branch tubes 31a, 31 of the anchor guide tube 31
A, ... will be added one after another on the water. That is, the first of the branch pipes 25a, 25a, .

・・の最初のものは、同じく鉄筋篭21に設けられた前
記アンカーガイド管用補助管32に接続されるものとな
る。なお、トレミー管25およびアンカーガイド管31
は、鉄筋篭21が掘削穴2の底部まで沈設された状態に
おいて、その上端が少なくとも水面上に突出するところ
まで延出させる。
The first one is connected to the anchor guide pipe auxiliary pipe 32 which is also provided in the reinforcing bar cage 21. In addition, the tremie tube 25 and the anchor guide tube 31
In the state where the reinforcing bar cage 21 is sunk to the bottom of the excavated hole 2, its upper end is extended at least to the point where it protrudes above the water surface.

11−■ 底版コンクリート打設 上記の如く鉄筋篭21が掘削穴2の底部に着底されたな
らば、前記トレミー管25により、前記型枠29の内部
すなわち掘削穴2底部にコンクリ−)28  (第7図
に図示)を水中打設する。打設コンクリート28はトレ
ミー管25の下端、すなわちこの場合は前記トレミー管
用補助管26の下端開口より排出される。このとき、コ
ンクリート28が型枠29内に充填されていくのに伴い
、型枠29にはこの型枠29を上方へ追いやろうとする
力が働くため、その力を前記アンカーガイド管31 3
1、・・・により支持する。なお、この場合、アンカー
ガイド管31は地上部(水上部)にて支持しである。
11-■ Placing concrete on the bottom slab Once the reinforcing bar cage 21 has been placed at the bottom of the excavated hole 2 as described above, concrete is placed inside the formwork 29, that is, at the bottom of the excavated hole 2, using the tremie pipe 25. (shown in Figure 7) is poured underwater. The poured concrete 28 is discharged from the lower end of the tremie pipe 25, that is, in this case, from the lower end opening of the auxiliary pipe 26 for the tremie pipe. At this time, as the concrete 28 is being filled into the formwork 29, a force is applied to the formwork 29 that tries to push the formwork 29 upward, so that force is transferred to the anchor guide pipe 31 3.
1, supported by... In this case, the anchor guide pipe 31 is supported on the ground (aquatic part).

前記鉄筋篭21は、打設されたコンクリート28内に埋
設される。また、コンクリート28は連続壁10の内面
10a側にも珊り込むものとなるが、連続壁IOの内面
10aおよび下端面10bは上述のケレン装置60によ
りケレンされているので、打設されたコンクリート28
と地中連続壁10の内面10aおよび下端面10bとが
完全に密着され、該地中連続壁IOとコンクリート28
との接続面の構造的な一体化とともに確実な遮水が図ら
れる。前記コンクリート28が硬化した時点で椀型の底
版20が完成する。なお、前記トレミー管25は、コン
クリート28の打設が終了した時点で撤去して良い。
The reinforcing bar cage 21 is buried in poured concrete 28. Further, the concrete 28 also sinks into the inner surface 10a side of the continuous wall 10, but since the inner surface 10a and the lower end surface 10b of the continuous wall IO are smeared by the above-mentioned smearing device 60, the poured concrete 28
The inner surface 10a and the lower end surface 10b of the underground continuous wall 10 are completely in contact with each other, and the underground continuous wall IO and the concrete 28
Reliable water shielding is achieved by structurally integrating the connection surface with the Once the concrete 28 has hardened, the bowl-shaped bottom plate 20 is completed. Note that the tremie pipe 25 may be removed when the concrete 28 is finished being poured.

iv 、アンカーの設置 底版20が構築されたならば、該底版20を固定するた
めの前記アンカー30を、形成された底版20の下方地
山内に設置する。アンカー20の設置作業自体は、一般
に行なわれているアースアンカー工法と同様であるが、
本実施例(本発明)においては、これを水中にて実施す
るものである。
iv. Installation of anchors Once the bottom slab 20 has been constructed, the anchors 30 for fixing the bottom slab 20 are installed in the ground beneath the formed bottom slab 20. The installation work of the anchor 20 itself is similar to the commonly used earth anchor construction method, but
In this example (the present invention), this is carried out underwater.

1v−■ 削孔 アンカー30を設置するには、まず、該アンカー30を
埋設するための削孔を行うが、この削孔作業は第7図に
示す如く前記アンカーガイド管31を利用することによ
り水面上より行うことが可能である。すなわち、前記ア
ンカーガイド管31内に削孔用のケーシングドリル34
を挿入し、前記アンカーガイド管用補助管32を介して
該ケーシングドリル34を底版20下面の地山Gに至ら
しめ、その状態から下方への削孔を開始する。アンカー
ガイド管用補助管32の下端部に設けられた前記栓材3
3は、この削孔の際に取り除かれる。
1v-■ To install the hole-drilling anchor 30, first, a hole is drilled to bury the anchor 30, but this hole-drilling work is performed by using the anchor guide pipe 31 as shown in FIG. It is possible to do this from above the water surface. That is, a casing drill 34 for drilling holes is installed in the anchor guide pipe 31.
is inserted, and the casing drill 34 is brought to the ground G on the lower surface of the bottom plate 20 via the auxiliary pipe 32 for the anchor guide pipe, and from this state, downward drilling is started. The plug material 3 provided at the lower end of the auxiliary pipe 32 for anchor guide pipe
3 is removed during this drilling.

上述の如く、底版20を構成する前記鉄筋篭21および
型枠29には、予め、前記ケーシングドリル34を挿通
させるための前記アンカーガイド管用補助管32を設け
、かつこのアンカーガイド管用補助管32からアンカー
ガイド管31を水面上にまで延出させたので、底版20
構築後における削孔作業、しかも掘削穴2内に水3を貯
留させた状態での削孔作業を容易に行うことができるわ
けである。
As described above, the reinforcing bar cage 21 and the formwork 29 constituting the bottom plate 20 are provided with the anchor guide pipe auxiliary pipe 32 for inserting the casing drill 34 in advance, and from this anchor guide pipe auxiliary pipe 32 Since the anchor guide pipe 31 extends above the water surface, the bottom plate 20
This makes it possible to easily perform the drilling work after construction, and moreover, the drilling work can be easily performed while water 3 is stored in the excavated hole 2.

1v−■ PC材設置およびモルタル充填所定深さの削
孔が形成されたならば、前記ケーシングドリル34内に
PC材36 (第8図)を挿入する。その後、削孔底部
に例えばモルタル等の硬化充填材37を注入しなからケ
ーシングドリル34を引き抜く。
1v-■ Installation of PC material and filling of mortar Once a hole of a predetermined depth has been formed, a PC material 36 (FIG. 8) is inserted into the casing drill 34. Thereafter, a hardened filler 37 such as mortar is injected into the bottom of the drilled hole, and then the casing drill 34 is pulled out.

1v−■ PC材への緊張力導入 前記硬化充填材37が硬化した後、下記の要領により前
記PC材36を緊張する。
1v-■ Introducing tension to the PC material After the cured filler 37 has hardened, the PC material 36 is tensioned in the following manner.

まず、アンカーガイド管31をアンカーガイド管用補助
管32より取り外し、撤去する。この状態においては、
既にコンクリート28は完全に硬化し、型枠29もコン
クリート28と一体となっているので、アンカーガイド
管31を撤去してもコンクリート28の打設時のように
型枠29が浮き上がることはない。これらアンカーガイ
ド管31と、アンカーガイド管用補助管32との切り離
しは、例えば、アンカーガイド管用補助管32と該補助
管32に直接接続される前記分管31aとを結合するネ
ジを、各分管31a、31a、・・・どうしを接続する
ネジに対して逆ネジに構成しておけば、アンカーガイド
管31を所定方向にねじ回すだけでアンカーガイド管3
1がアンカーガイド管用補助管32より外れるから、水
上部にて行うことができる。
First, the anchor guide tube 31 is removed from the anchor guide tube auxiliary tube 32 and removed. In this state,
Since the concrete 28 has already completely hardened and the formwork 29 is also integrated with the concrete 28, even if the anchor guide pipe 31 is removed, the formwork 29 will not be lifted up unlike when the concrete 28 is poured. The anchor guide tube 31 and the anchor guide tube auxiliary tube 32 can be separated by, for example, screwing the screws connecting the anchor guide tube auxiliary tube 32 and the branch tube 31a directly connected to the auxiliary tube 32 into each branch tube 31a, 31a, . . . If the screws connecting them are configured with opposite threads, the anchor guide tube 31 can be removed by simply turning the anchor guide tube 31 in a predetermined direction.
1 is removed from the anchor guide pipe auxiliary pipe 32, so it can be carried out above the water.

アンカーガイド管31が撤去されたならば、まず初めに
第8図に示すアンカ一定着プレート38を、水上部より
、前記PC材36をガイドとして水3中に沈め、底版2
0 (型枠29)の上面に着底させる。ただし、この場
合、型枠29の上面からは前記アンカーガイド管用補助
管32の上端部が突出しており、滑り落とした前記アン
カ一定着プレート38はこのアンカーガイド管用補助管
32に当接した位置で止まり型枠29まで達しないため
、ここでは、該アンカ一定着プレート38の下部に脚部
38aを設け、この脚部38aが型枠29の上面に当接
するものとなっている。また、前記アンカ一定着プレー
ト38には、この場合PC材36に下向きの移動が生じ
たときに、くさび作用によりPC材36を咬むことので
きるチャック39が備えられたものとなっている。
After the anchor guide pipe 31 is removed, first, the anchor fixing plate 38 shown in FIG.
0 (The bottom of the mold 29). However, in this case, the upper end of the anchor guide tube auxiliary tube 32 protrudes from the upper surface of the formwork 29, and the anchor fixing plate 38 that has slipped down is at a position where it abuts on the anchor guide tube auxiliary tube 32. Since the anchor plate 38 does not reach the stop form 29, a leg 38a is provided at the lower part of the anchor fixing plate 38, and this leg 38a abuts against the upper surface of the form 29. Further, the anchor fixing plate 38 is provided with a chuck 39 that can grip the PC material 36 by a wedge action when the PC material 36 moves downward.

次いで、前記アンカ一定着プレート38と同様にPC材
36をガイドとしてセンターホールツヤツキ40を水中
に沈め、前記アンカ一定着プレート38上に到達させる
。符号41は、水上部まで延びこのセンターホールドジ
ヤツキ40を作動させるための油圧ホースである。その
後、このセンターホールジヤツキ40にて前記PC材3
6に緊張力を導入すればよい。センターホールジヤツキ
40の操作は水上部にて行うことができる。よって、セ
ンターホールジヤツキ40によりPC材36を緊張した
後、引張り力を解除すると、PC材36は前記アンカ一
定着プレート38の前記チャック39の作用により弛緩
動作を拘束され(すなわち緊張力が導入され)、該緊張
力が該アンカ一定着プレート38を介して底版20に導
入される。
Next, similarly to the anchor fixing plate 38, the center hole gloss 40 is submerged in water using the PC material 36 as a guide, and is made to reach the anchor fixing plate 38. Reference numeral 41 is a hydraulic hose that extends to the upper part of the water and operates the center hold jack 40. After that, using this center hole jack 40, the PC material 3 is
It is sufficient to introduce tension force in step 6. The center hole jack 40 can be operated above the water. Therefore, when the tensile force is released after tensioning the PC material 36 with the center hole jack 40, the PC material 36 is restrained from relaxing by the action of the chuck 39 of the anchor fixing plate 38 (that is, the tension force is introduced). ), and the tension force is introduced into the bottom plate 20 via the anchor fixation plate 38.

V、排水その他 上記の如くアンカー30が設置されたならば、掘削穴2
内の水3を排水する。その後PC材36を前記アンカ一
定着プレート38の上部で切断すれば、目的とする地中
構造物1が完成する。
V, drainage, etc. Once the anchor 30 is installed as described above, the excavated hole 2
Drain the water 3 inside. Thereafter, by cutting the PC material 36 above the anchor fixing plate 38, the intended underground structure 1 is completed.

そして、該地中構造物lを、例えば居住空間としての地
下施設等として利用する場合には、前記底版20の上部
に本設の床版を打設すればよい。
When the underground structure 1 is to be used, for example, as an underground facility serving as a living space, a permanent floor slab may be placed on top of the bottom slab 20.

また例えば、前記地中構造物1内をさらに複数階層に形
成する、あるいは該地中構造物lの上方に建築物の地上
部を構築する等、該地中構造物lをそれぞれの目的に応
じてさらに発展させた構造とすることは任意である。
Furthermore, for example, the underground structure 1 may be further formed into multiple layers, or the above-ground part of a building may be constructed above the underground structure 1, etc., depending on the purpose of the underground structure 1. It is optional to further develop the structure.

上記構造となる地中構造物1によれば、アンカー30に
より、地下水の影響で底版20に作用する浮力を支持す
ることができ、底版20の浮き上がりあるいは変形等を
防止することができる。これにより、地中連続壁により
構築される従来の地中構造物の如く、地中連続壁IOを
底版20のはるか下方まで必要以上に延出構築する必要
がなく、根入れ深さを短くして施工上の低コスト化と、
工期の短縮を図れる。
According to the underground structure 1 having the above structure, the anchor 30 can support the buoyant force acting on the bottom slab 20 due to the influence of groundwater, and can prevent the bottom slab 20 from floating or deforming. As a result, there is no need to extend the underground continuous wall IO far below the bottom slab 20 more than necessary, unlike conventional underground structures constructed using underground continuous walls, and the penetration depth can be shortened. to reduce construction costs,
The construction period can be shortened.

また、底版20を椀型となるよう下向きに湾曲形成した
ので、該底版20の浮力に対する耐力を高めることがで
きる。
Further, since the bottom plate 20 is formed to be curved downward so as to have a bowl shape, the resistance of the bottom plate 20 to buoyancy can be increased.

さらに、実施例のものでは、掘削穴2を連続壁lOより
も下方において連続壁IOの内径よりも大径に形成する
ことにより、底版20を構成するコンクリート28が連
続壁lOの下部に廻り込むような構造とし、底版20か
連続壁IOの下端面10bに係止される如く構成したの
で、底版20に作用する浮力が連続壁lOによっても支
持されるものとなり、底版20に作用する浮力をより確
実に支持できる。
Furthermore, in the example, by forming the excavated hole 2 below the continuous wall IO to have a larger diameter than the inner diameter of the continuous wall IO, the concrete 28 constituting the bottom plate 20 can go around the lower part of the continuous wall IO. Since the structure is such that the bottom plate 20 is locked to the lower end surface 10b of the continuous wall IO, the buoyant force acting on the bottom plate 20 is also supported by the continuous wall IO, and the buoyant force acting on the bottom plate 20 is reduced. It can be supported more reliably.

また、上記構築方法によれば、上記地中構造物1を確実
に実現することができるのは無論であるが、さらに下記
の如き効果がある。すなわち、掘削穴2内に水3を満た
した状態で底版20を構築し、しかも前記水3が存在し
た状態において底版20をアンカー30にて定着してか
ら水3を排水するため、底版20の完全定着後に底版2
0への載加荷重(水3)が除かれるものとなり、底版2
0は、施工中においても地下水による浮力の影響を受け
ることがない。
Moreover, according to the construction method described above, it goes without saying that the underground structure 1 described above can be reliably realized, but also has the following effects. That is, the bottom plate 20 is constructed with the excavated hole 2 filled with water 3, and the bottom plate 20 is fixed with the anchor 30 in the state where the water 3 is present, and then the water 3 is drained. Bottom plate 2 after complete fixation
The applied load (water 3) to 0 is removed, and the bottom plate 2
0 is not affected by the buoyancy of groundwater even during construction.

さらに、上記構築方法にあっては、床版20を構成する
鉄筋篭21において、該鉄筋篭21を掘削穴2の底部に
設置する際、これに予め型枠29を一体に取り付けたの
で、型枠29を別途設置する必要がなく作業の効率化を
図ることができる。
Furthermore, in the above construction method, when installing the reinforcing bar cage 21 at the bottom of the excavated hole 2, the formwork 29 is integrally attached to the reinforcing bar cage 21 constituting the floor slab 20, so that the mold There is no need to separately install the frame 29, and work efficiency can be improved.

このことは特に、これら鉄筋篭21等が水中に設置され
るものであり、型枠29を鉄筋篭21の設置後にしかも
水中にて前記鉄筋篭21の所定位置に固定することが極
めて困難であることを考慮したときは極めて効果的であ
る。
This is especially true because these reinforcing bar cages 21 and the like are installed underwater, and it is extremely difficult to fix the formwork 29 at a predetermined position of the reinforcing bar cage 21 after the reinforcing bar cages 21 are installed and underwater. It is extremely effective when taking this into account.

また、上記実施例では連続壁lOにおける底版20との
接合部、すなわち連続壁IOの内面lOa下部および下
端面10bのケレン作業を前記ケレン装置60により確
実に行えるため、底版20と地中連続壁10との一体化
および密着度を高め確実なる遮水性が望める、等の優れ
た効果を奏する。
In addition, in the above embodiment, since the cleaning device 60 can reliably clean the joint portion of the continuous wall IO with the bottom slab 20, that is, the lower part of the inner surface IOa and the lower end surface 10b of the continuous wall IO, the bottom slab 20 and the underground continuous wall can be cleaned by the cleaning device 60. It has excellent effects such as increased integration and adhesion with 10 and reliable water-blocking properties.

C発明の効果〕 以上説明したとおり、本発明の請求項1に記載した地中
構造物によれば、アンカーにより、底版に作用する浮力
を支持することができ、底版の浮き上がりあるいは変形
等を防止することができ、これにより、地中連続壁によ
り構築される従来の地中構造物の如く地中連続壁を底版
のはるか下方まで必要以上に延出構築する必要がなく、
根入れ深さを短くして施工上の低コスト化と、工期の短
縮を図れる。しかも、底版を椀型となるよう下向きに湾
曲形成したので、該底版の浮力に対する耐力を大きく高
めて床版の薄肉化を実現することができ、特に大形・大
深度の地中構造物に有効に適用できる。
C Effect of the Invention] As explained above, according to the underground structure described in claim 1 of the present invention, the anchor can support the buoyant force acting on the bottom slab, and prevent the bottom slab from lifting or deforming. This eliminates the need to extend the underground continuous wall far below the bottom slab unnecessarily, unlike conventional underground structures constructed using underground continuous walls.
By shortening the penetration depth, it is possible to reduce construction costs and shorten the construction period. Moreover, since the bottom plate is curved downward to form a bowl shape, it is possible to greatly increase the bottom plate's resistance to buoyancy and make the wall thinner, making it especially suitable for large and deep underground structures. Can be applied effectively.

また、請求項2に記載した地中構造物の構築方法によれ
ば、上記地中構造物を確実に実現することができること
に加え、掘削穴内に水を満たした状態で底版を構築し、
しかも前記水が存在した状態において底版をアンカーに
て定着してから水を排水するため、底版の完全定着後に
底版への戦地荷重(水)が除かれるものとなり、底版を
、施工中においても地下水による浮力の影響を受けるこ
とがなく構築することができる。
Further, according to the method for constructing an underground structure described in claim 2, in addition to being able to reliably realize the above-mentioned underground structure, the bottom slab is constructed with the excavation hole filled with water,
Moreover, since water is drained after fixing the bottom slab with anchors in the presence of water, the battlefield load (water) on the bottom slab is removed after the bottom slab is completely fixed, and even during construction can be constructed without being affected by buoyancy.

さらに、請求項3に記載した地中構造物の構築方法によ
れば、上記請求項2の地中構造物の構築方法を実施する
際、床版を構成する鉄筋篭を掘削穴の底部に設置する際
、鉄筋篭に予め型枠を一体に取り付けたので、型枠を別
途設置する必要がなく、特に水中作業にあって大幅な効
率化を図れる、等の効果を奏することができる。
Furthermore, according to the method for constructing an underground structure according to claim 3, when carrying out the method for constructing an underground structure according to claim 2, a reinforcing bar cage constituting the floor slab is installed at the bottom of the excavation hole. Since the formwork is integrally attached to the reinforcing bar cage in advance, there is no need to separately install the formwork, and it is possible to achieve effects such as greatly improving efficiency, especially in underwater work.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係る地中構造物の一実施例を示す全体
側面図、第2図ないし第8図は本発明の地中構造物の構
築方法の一実施例を示すもので第2図は掘削穴の形成状
態を示す部分側断面図、第3図はケレン装置を地中連続
壁と共に示す平面図、第4図は第3図の側断面図、第5
図は鉄筋篭を示す部分側面図、第6図は鉄筋篭の設置状
態を示す部分側断面図、第7図はアンカーの設置状態を
示す部分側断面図、第8図はPC鋼棒の緊張状態を示す
部分側断面図、第9図は従来技術を説明するもので地中
構造物の全体側断面図である。 21・・・・・・鉄筋篭、 29・・・・型枠(上部型枠)、 30・・・・・・アンカー
FIG. 1 is an overall side view showing one embodiment of an underground structure according to the present invention, and FIGS. 2 to 8 show an embodiment of the method for constructing an underground structure according to the present invention. The figure is a partial side sectional view showing the formation state of the excavation hole, Figure 3 is a plan view showing the Keren device together with the underground continuous wall, Figure 4 is a side sectional view of Figure 3, and Figure 5
The figure is a partial side view showing the reinforcing bar cage, Fig. 6 is a partial side sectional view showing the installed state of the reinforcing bar cage, Fig. 7 is a partial side sectional view showing the installed state of the anchor, and Fig. 8 is the tension of the PC steel bar. FIG. 9 is a partial side sectional view showing the state, and is a side sectional view of the entire underground structure for explaining the prior art. 21...Reinforced cage, 29...Formwork (upper formwork), 30...Anchor

Claims (3)

【特許請求の範囲】[Claims] (1)地山中に筒状に形成され構造物の外殻を成す地中
連続壁と、該地中連続壁の底部を閉塞して形成された底
版と、上端部を該底版に定着されて該底版よりも下方の
地山内に設けられた複数のアンカーとを有して構成され
、しかも前記底版は下向きに凸となる如く湾曲形成され
ていることを特徴とする地中構造物。
(1) An underground continuous wall formed in a cylindrical shape in the earth and forming the outer shell of the structure, a bottom slab formed by closing the bottom of the underground continuous wall, and a top end fixed to the bottom slab. An underground structure comprising a plurality of anchors provided in the ground below the bottom slab, and the bottom slab is curved so as to be convex downward.
(2)請求項1記載の地中構造物の構築方法であって、
地山中に水平面内において閉環された筒状の地中連続壁
を構築する工程と、水中掘削により前記地山の前記地中
連続壁により囲まれた部分を掘削するとともに地中連続
壁下端よりさらに下方部分を椀型に掘削する工程と、前
記工程により形成された掘削穴底部に、該底部に沿った
椀型を成し前記地中連続壁と一体となる底版を水中にて
構築する工程と、前記底版の下方地山に、上端部を前記
底版に定着されて該底版を支持するためのアンカーを水
中にて設ける工程と、を有することを特徴とする地中構
造物の構築方法。
(2) A method for constructing an underground structure according to claim 1, comprising:
A step of constructing a closed cylindrical diaphragm wall in a horizontal plane in the ground, and excavating a portion of the ground surrounded by the diaphragm wall by underwater excavation, and further excavating the area from the bottom end of the diaphragm wall. a step of excavating the lower part into a bowl shape; and a step of constructing underwater a bottom slab that forms a bowl shape along the bottom of the excavation hole formed by the step and is integrated with the underground continuous wall. A method for constructing an underground structure, comprising the steps of: providing an anchor in the ground below the bottom slab, the upper end of which is fixed to the bottom slab to support the bottom slab.
(3)請求項2記載の地中構造物の構築方法において、
前記底版を構築するに際し、該底版を構成する鉄筋篭を
椀型に形成するとともに、該鉄筋篭の上部には予め該鉄
筋篭の上面形状に沿う上部型枠を付設しておき、これら
鉄筋篭および上部型枠を一体として前記掘削穴底部に設
置することを特徴とする地中構造物の構築方法。
(3) In the method for constructing an underground structure according to claim 2,
When constructing the bottom plate, the reinforcing bar basket constituting the bottom slab is formed into a bowl shape, and an upper formwork that follows the top surface shape of the reinforcing bar cage is attached in advance to the top of the reinforcing bar cage, and these reinforcing bar cages are and a method for constructing an underground structure, comprising installing the upper formwork as one piece at the bottom of the excavation hole.
JP2063813A 1990-03-14 1990-03-14 Underground structure and its construction Pending JPH03262836A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2063813A JPH03262836A (en) 1990-03-14 1990-03-14 Underground structure and its construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2063813A JPH03262836A (en) 1990-03-14 1990-03-14 Underground structure and its construction

Publications (1)

Publication Number Publication Date
JPH03262836A true JPH03262836A (en) 1991-11-22

Family

ID=13240186

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2063813A Pending JPH03262836A (en) 1990-03-14 1990-03-14 Underground structure and its construction

Country Status (1)

Country Link
JP (1) JPH03262836A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014134054A (en) * 2013-01-11 2014-07-24 Taisei Corp Pile center positioning member and pile construction method
JP2016194247A (en) * 2016-07-21 2016-11-17 大成建設株式会社 Construction method of underwater pile

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4894911A (en) * 1972-03-18 1973-12-06
JPS5091113A (en) * 1973-12-15 1975-07-21
JPS54118633A (en) * 1978-03-06 1979-09-14 Taisei Corp Underground tank and its constructing method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4894911A (en) * 1972-03-18 1973-12-06
JPS5091113A (en) * 1973-12-15 1975-07-21
JPS54118633A (en) * 1978-03-06 1979-09-14 Taisei Corp Underground tank and its constructing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014134054A (en) * 2013-01-11 2014-07-24 Taisei Corp Pile center positioning member and pile construction method
JP2016194247A (en) * 2016-07-21 2016-11-17 大成建設株式会社 Construction method of underwater pile

Similar Documents

Publication Publication Date Title
JP5282541B2 (en) How to prevent lifting of the lining body
JP5502538B2 (en) Pile construction method and pile construction device
JP4451553B2 (en) Buoyancy prevention structure and construction method thereof
JPH03262836A (en) Underground structure and its construction
JPH06146305A (en) Underwater foundation and installation method thereof
JP2855156B2 (en) How to build underground structures
JP2718241B2 (en) Foundation construction method on soft submarine ground
JP3893052B2 (en) Joint structure of manhole for propulsion pipe and its construction method
JP4465808B2 (en) Construction method for underwater foundation
JP5282542B2 (en) Ground deformation prevention method and ground deformation prevention structure
JPS5936058B2 (en) How to construct a structure using underground continuous walls
KR100989380B1 (en) Vertical tunnel constructions for a underwater tunnel
JPS61109822A (en) Construction work of pile
KR20190019530A (en) Retaining wall method by using the precast house(PC house) of bridge building
JP2874906B2 (en) Shaft construction method
JP7057582B1 (en) Underground construction method for large pipes and bottomed buried pipes
CN216446925U (en) Reinforcing construction device for entrance and exit of heavy-caliber jacking pipe in silt stratum
JPH0525828A (en) Final excavation level lift-preventive construction
JP4248716B2 (en) Caisson top end construction method
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer
JP3600990B2 (en) Connection method between side wall and underground continuous wall in underground structure
KR100631362B1 (en) Dependant basement wall supported to the protecting structure
JPH04339916A (en) Sealing construction for steel pipe adding caisson foundation
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JP5526532B2 (en) Shielding machine settlement prevention method and settlement prevention structure