JP4248716B2 - Caisson top end construction method - Google Patents

Caisson top end construction method Download PDF

Info

Publication number
JP4248716B2
JP4248716B2 JP36175199A JP36175199A JP4248716B2 JP 4248716 B2 JP4248716 B2 JP 4248716B2 JP 36175199 A JP36175199 A JP 36175199A JP 36175199 A JP36175199 A JP 36175199A JP 4248716 B2 JP4248716 B2 JP 4248716B2
Authority
JP
Japan
Prior art keywords
caisson
retaining wall
earth retaining
top plate
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP36175199A
Other languages
Japanese (ja)
Other versions
JP2001172983A (en
Inventor
敏文 南
実 池田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP36175199A priority Critical patent/JP4248716B2/en
Publication of JP2001172983A publication Critical patent/JP2001172983A/en
Application granted granted Critical
Publication of JP4248716B2 publication Critical patent/JP4248716B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、上端部が地表下に位置するケーソンの上端部の施工方法に関するものである。
【0002】
【従来の技術】
ケーソン工法には、オープンケーソン工法等のように、鉄筋コンクリート等で構築した筒状構造物を地盤上に据え、筒状構造物の下部の地盤を掘削し、筒状構造物の自重または載荷重により、筒状構造物を地中に沈下させる工法があり、筒状構造物の打ち足しと地盤の掘削を繰り返すことにより、筒状構造物を所定の支持地盤に到達させた後、底盤コンクリートと頂版コンクリートを施工し、基礎構造体を構築する。この構築された基礎構造体は、地上構造物の基礎や地下構造体の駆体となる。
このようなケーソン工法では、筒状構造物が、常に地表まで達しているようになるため、筒状構造物自体が、筒状構造物内に周囲の土等がなだれ込むのを防ぐ土留め壁となっている。
【0003】
【発明が解決しようとする課題】
ところで、地下に構造物を構築する際に、地下構造物上の地表を、たとえば、公園や宅地として、地下の構造物とは関係ない利用目的に使用するような場合には、地表から一定の深さに構造物や仮設材等を残置しないようにする必要がある。そこで、上述したように、地表まで筒状構造物が達しているケーソン工法では、このような場合、地表付近の筒状構造物を撤去しなくてはならない。
【0004】
しかし、上述したケーソン工法においては、地上構造物の基礎や地下構造体の駆体となるため、筒状構造物は強固な構造になっている。そのため、筒状構造物の一部(上部)を撤去するのに手間がかかるという問題がある。
【0005】
そこで、本発明の目的は、上端部が地表下に位置し、頂版上が埋め戻された構造を有するケーソンにおいて、ケーソンの頂版より上の構造物を容易に撤去して埋め戻すことができるケーソン上端部の施工方法を提供することにある。
【0006】
【課題を解決するための手段】
以上の課題を解決すべく本発明は、ケーソン内部を掘削して、ケーソンを沈下させる工程を含むケーソン工法によって、地表下に設置されるケーソンのうちの、上端部の位置が地表部分の下とされるとともに前記上端部に設けられた頂版の上が埋め戻された構造を有するケーソンにおけるケーソン上端部の施工方法であって、前記地表部より下に沈設させられる前記ケーソン(1)上端部から地表部に至るように、前記ケーソン上に前記ケーソンとほぼ同様の筒状で、かつ、複数に分割自在な仮設土留め壁(4)を設けておき、上記仮設土留め壁内において、前記ケーソン上端部に前記頂版(8)を設けた後に、前記頂版上を埋め戻すとともに頂版より上の仮設土留め壁を分割して撤去することを特徴としている。
【0007】
ここで、ここで仮設土留め壁は、該土留め壁と交差する垂直な複数の面で切断されて、分割された形状となっていることが好ましい。
【0008】
以上のように、本発明によれば、地表部より下に沈設されたケーソン上端部から地表部に至る部分において、ケーソン上に、ケーソンとほぼ同様の筒状で、複数に分割自在な仮設土留め壁を設け、この仮設土留め壁内で、ケーソンの頂版を形成後、頂版上を埋め戻し、仮設土留め壁を分割して撤去することになる。従って、ケーソン上端部から地表部に至る部分を仮設土留め壁で土留めを行うことにより、地表部より下に沈設されたケーソン上端部に頂版を設けることができる。また、仮設土留め壁は、ケーソンを沈設する際のように、加重をかけられることがなく、かつ、基礎や地下構造物の駆体として用いられることがなく、土留めを行えるだけの強度があればよいので、ケーソンよりも厚さを薄くすることができる。そして、このような仮設土留め壁は、更に複数に分割自在であるので、埋め戻し後、引抜き易く、容易に撤去できる。
なお、ケーソンの沈設に際しては、ケーソンの上端部となる筒状構造物を地上から地下に沈める際に、あらかじめ、筒状構造物上に仮設土留め壁を作成しておき、最後の筒状構造物の上端が地表より下に沈められても、仮設土留め壁により筒状構造物上を土留めできるようにしておく必要がある。また、この際には、仮設土留め壁に荷重をかけることなく、ケーソンの自重や、ケーソンの上端に荷重をかけることにより、ケーソンを地表部より深く沈設するようにする必要がある。
【0009】
また、本発明は、上記のケーソン上端部の施工方法において、前記仮設土留め壁が、コンクリートを打設して頂版を設ける際の頂版の外周部分の型枠となる土留め壁下部(5)と、該土留め壁下部の上に設けられ、該土留め壁下部から取り外し自在で、かつ、複数に分割自在な土留め壁上部(6)とを備え、前記頂版上を埋め戻す際に上記分割自在な土留め壁上部を分割して撤去することを特徴としている。
【0010】
このように、本発明によれば、仮設土留め壁が、コンクリートを打設して頂版を形成する際の頂版の外周部分の型枠となる土留め壁下部と、土留め壁下部の上に設けられ、土留め壁下部から取り外し自在で、複数に分割自在な土留め壁上部とを備えたことにより、頂版の型枠を新たに設ける必要がなく、コストを削減できる。また、土留め壁上部は、土留め壁下部から取り外し自在であるので、土留め壁下部内にコンクリートを打設後も容易に撤去することができる。
【0011】
また、本発明は、上記のケーソン上端部の施工方法において、前記仮設土留め壁の内周側で周方向に沿って設けられた環状の梁(例えばリングビーム3)と、前記仮設土留め壁の内周に沿って上下に延在する柱(例えばHビーム2)とを備えた支保工で前記仮設土留め壁を支持し、前記頂版上を埋め戻す際に前記環状の梁を撤去するとともに、前記柱を前記頂版の上端部に対応する位置で切断して、前記柱を撤去することを特徴としている。
【0012】
このように、本発明によれば、仮設土留め壁の内周側で周方向に沿って設けられた環状の梁と、仮設土留め壁の内周に沿って上下に延在する柱とを備えた支保工で仮設土留め壁を支持することにより、仮設土留め壁の強度を高めることができるので、仮設土留め壁自体は、たとえば、薄くするなどして軽量化を図ることができ、撤去しやすくすることができる。また、頂版上を埋め戻す際に環状の梁を撤去し、柱を頂版の上端部に対応する位置で切断しておくことにより、頂版上を埋め戻し後、柱を容易に撤去することができる。
【0013】
また、本発明は、上記のケーソン上端部の施工方法において、前記支保工の前記柱を撤去するに際し、頂版上の埋め戻しを行う前に、前記柱を頂版の上端部に対応する位置で切断するとともに、切断に際し、柱の上端部と柱の切断位置より下の部分とを、ボルト(10)で締結しておき、頂版上の埋め戻しを行った後に、柱の上端部側から前記ボルトの締結を解除して前記柱を引き抜くことを特徴としている。
【0014】
このように、本発明によれば、頂版上の埋め戻しを行う前に、頂版の上端部に対応する位置で柱を切断して、柱の上端部と柱の切断位置より下の部分とを、ボルトで締結しておき、頂版上の埋め戻し完了後に、柱の上端部側からボルトの締結を解除して、柱を引き抜くことにより、埋め戻し前の柱が露出している状態で容易に切断でき、かつ、ボルトにより切断後も柱を立てた状態に保持することができる。また、支保工の柱に仮設土留め壁上部の各分割部分が接合されることにより、仮設土留め壁下部に仮設土留め壁上部の各分割部部分が接合された状態となっていれば、柱の切断部分を上記ボルトで締結することで、埋め戻しの際に、仮設土留め壁上部の各分割部分を仮設土留め壁下部に接合した状態に保つことができ、かつ、上述のボルトによる締結を解除した後に、仮設土留め壁上部の各分割部分を容易に取り外すことができる。
【0015】
【発明の実施の形態】
以下に、本発明に係るケーソン上端部の施工方法の実施の形態例を図1から図6に基づいて説明する。
なお、本発明を応用して構築された地下構造物は、たとえば、地下鉄用の二つのトンネル21,22から排水管23,23が接続され、地上からの通路を有する立抗であり、該立抗がオープンケーソン26から構成されている。しかし、オープンケーソン26上の地表は、この地下構造物と異なる目的で使用されるため、オープンケーソン26からなる地下構造物は、地表より下方の位置までとされ、オープンケーソン26上が埋め戻された状態となっている。
そして、地上までの通路を確保するために、オープンケーソン26から離れた位置に地上に至るオープンケーソン24からなる立抗が設けられ、オープンケーソン26とオープンケーソン24とが、地下で通路25により接合されている。これにより、オープンケーソン26の下部と地上との通行が確保できるようになっている。
【0016】
ここで、オープンケーソン上端部の施工方法を説明する前に、オープンケーソン上端部にもうけられる仮設構造について説明する。図1はオープンケーソン上端部の側面図であり、図2は図1中のA部分の拡大図である。図中、1は円形ケーソン、2はHビーム(柱)、3はリングビーム(環状の梁)、4は仮設土留め壁である。仮設土留め壁4は、土留め壁下部5と、土留め壁上部6から構成されている。Hビーム2およびリングビーム3は、仮設土留め壁4の支保工となるものである。Hビーム2はケーソン1に一部埋め込まれており、ケーソン1の上端部から上方に、ケーソン1の長さ方向(上下方向)と平行に突出している。Hビーム2は、ケーソン1の上端部に複数本設けられている。Hビーム2の内側には、周方向に沿って環状のリングビーム3,3が設置されている。このリングビーム3,3はHビームの上部に上下方向に間隔を空けて設けられている。
【0017】
ケーソン1の上端部上には、Hビーム2,2…の外側に、ケーソン1の周にそって円筒状の土留め壁下部5が設けられている。この土留め壁下部5は、たとえば、厚さ200mmのコンクリートで形成されている。なお、土留め壁下部5(土留め壁4)は、ケーソン1より薄くされており(ケーソン1は、たとえば、厚さ700mm)、ケーソン1の上端面の外周側に載るように形成されている。従って、ケーソン1の上端面の内周側は、露出した状態となっており、ケーソン1を沈設する際に土留め壁4の内側において、ケーソン1に荷重をかけられるようになっている。
【0018】
土留め壁下部5の上には、土留め壁上部6が、土留め壁下部5と同様にHビーム2,2…の外側になるよう設置されている(図3参照)。土留め壁上部6は、土留め壁下部と同様に厚さ200mmのコンクリートで形成された円筒状であるが、縦に10分割できるようになっている。すなわち、10個の円弧板状の分割体を円周に沿って並べて接合することにより、円筒上の土留め壁上部6が構築されるようになっている。なお、土留め壁上部6となる各分割体は、プレキャストコンクリートからなるものとしても良いし、分割された状態に現場でコンクリートを打設して構築するものとしても良い。
【0019】
また、分割体同士の接合は、周知の方法で行うことができ、たとえば、周知の各種の継ぎ手を用いて接合するものとしても良い。また、土留め壁下部5と土留め壁上部6との接合も周知の方法により行うことができる。また、土留め壁上部6の各分割体同士の接合と、土留め壁下部5と土留め壁上部6との接合を上記Hビーム2およびリングビーム3からなる支保工を介して行うものとしても良い。すなわち、土留め壁上部6の各分割体を支保工に接合することにより、土留め壁上部6の各分割体同士の接合と、土留め壁下部5と土留め壁上部6との接合を行うようにしても良い。
【0020】
また、土留め壁上部6は、図4に示すように、各分割体同士の接合部分がHビーム2の背後に来るように配置する。また、土留め壁下部5からの取り外しも容易に行うことができるようになっている。
ここで、地表からある深さまでは構造物等を残置してはならない制約がある場合は、この土留め壁上部6の長さを制約で定められた深さと等しい長さ以上にする。例えば、地表から地下2.5mまでは構造物等を残置してはいけない場合は、土留め壁上部6の長さを2.5m以上とする。
【0021】
次に、上述のような仮設構造物を有するケーソン上端部の施工方法を説明する。
一般的なオープンケーソン工法と同様に、ケーソン1の下の地盤を掘削し、ケーソン1の自重または圧入により、ケーソン1を地中に埋入していく。
次いで、ケーソン1の上端部となる筒状構造部を構築する際に、上述のようなHビーム2およびリングビーム3からなる支保工と、仮設土留め壁下部5と仮設土留め壁上部6とからなる仮設土留め壁4を構築する。
そして、さらに、ケーソン1を地中に沈設していき、土留め壁上部6の上端が地表とほぼ等しい高さになるまで埋入する。ケーソン1の埋入が完了した後、ケーソン1の上端部に、ケーソン1を塞ぐように頂版の型枠の底部となるプレキャストコンクリート7を敷き並べ、その上へコンクリートを打設し頂版8を形成する。このとき、土留め壁下部5は、土留め行うと同時に頂版8の型枠となっている。また、頂版8の上端は、土留め壁下部5と土留め壁上部6との接合部より下になるように打設する。なお、ケーソン1内に水等が浸入しないようにするため、頂版8とHビーム2,2…との接触面には、防水シート12が挟み込まれている。
【0022】
次に、この頂版8上に、図5(a)に示すようにカバーモルタル9を打設し、Hビーム2,2…をカバーモルタル9の上方で切断する。カバーモルタルも頂版8と同様に土留め壁下部5と土留め壁上部6との接合部より下になるように打設する。
Hビーム2,2…の切断する際には、長いボルト10,10…でHビーム2,2…の上端部とHビーム2,2…の切断すべき位置より下の部分とを締結しておく(図5(b)参照)。
さらに、カバーモルタル9上にコンクリート11を打設した後(図5(c)参照)、リングビーム3,3をHビーム2,2…から取り外し(図5(d)参照)、ケーソンの頂版8上を土砂13等で埋め戻す(図5(e)参照)。
そして、Hビーム2,2…の上端側からボルト10,10…の締結を解除し(図5(f)参照)、Hビーム2,2…を引抜くとともに、土留め壁上部を引抜くことにより、図6に示すように、地表から一定の深さに構造物等を残さないよう、オープンケーソンの上端部を施工することができる。
【0023】
このように、上記実施の形態のケーソン上端部の施工方法によれば、ケーソン1の上端部から地表に至る部分を、土留め壁下部5及び土留め壁上部6で土留めを行うことにより、地表より下に沈設されたケーソン1の上端部に頂版8を容易に打設することができる。また、土留め壁上部6はケーソン1よりも厚さが薄く、10分割可能であるので、ケーソン1頂版上を埋め戻し後、容易に撤去することができる。土留め壁下部5は、土留めをするだけでなく、頂版8の外周部分の型枠となるので、新たに型枠を設ける必要がなく、コストを削減することができる。
また、頂版8及びカバーモルタル9は土留め壁下部5と土留め壁上部6との接合部より下に打設されるので、土留め壁上部6は容易に引抜き可能である。
Hビーム2,2…とリングビーム3,3とで、土留め壁下部5及び土留め壁上部6を支持することにより、土留め壁下部5及び土留め壁上部6の強度を高めることができる。
また、頂版8上の埋め戻しを行う前に、Hビーム2,2…が露出している状態で、Hビーム2,2…を切断するとともに、Hビーム2,2…の上端部とHビーム2,2…の切断位置より下の部分とを、ボルト10,10…で締結し、頂版上の埋め戻し完了後に、ボルト10,10…の締結を解除して、Hビーム2,2…を引き抜くことにより、切断後もHビーム2,2…を立てた状態に保持することができる。切断、引抜き作業も容易に行うことができる。
【0024】
なお、以上の実施の形態例においては、適用するケーソンとしてオープンケーソンを挙げたが、本発明はこれに限定されるものではなく、ケーソン内を掘削することによって、地表下に沈設させられるケーソンであれば良く、例えばニューマチックケーソンや圧入ケーソン等にも適用することができる。
また、土留め壁上部を10分割可能としたが、これに限定されるものではなく、分割することによって土留め壁上部が容易に引抜ける大きさになればよく、いくつに分割しても良い。
土留め壁の厚さ、Hビームやリングビームの数等も任意であり、その他、具体的な細部構造等についても適宜に変更可能であることは勿論である。
【0025】
【発明の効果】
以上のように、本発明に係るケーソン上端部の施工方法によれば、地表部より下に沈設されたケーソン上端部から地表部に至る部分に、ケーソン上に、ケーソンとほぼ同様の筒状で、複数に分割自在な仮設土留め壁を設けたことにより、仮設土留め壁でケーソン上端部から地表部に至る部分の土留めを行うことができ、地表部より下に沈設されたケーソン上端部に頂版を設けることができる。また、仮設土留め壁内で、ケーソンの頂版を形成後、頂版上を埋め戻し、仮設土留め壁を分割して撤去することにより、仮設土留め壁はケーソンよりも厚さが薄く、更に複数に分割自在であるので、埋め戻し後に引抜き易く、容易に撤去できる。
【0026】
また、本発明に係るケーソン上端部の施工方法によれば、仮設土留め壁は、頂版を形成する際の頂版の外周部分の型枠となる土留め壁下部と、この土留め壁下部の上に設けられ、土留め壁下部から取り外し自在で、複数に分割自在な土留め壁上部とを備えている。これにより、頂版の型枠を新たに設ける必要がないのでコストを削減できる。また、土留め壁下部内にコンクリートを打設後も土留め壁上部を容易に撤去することができる。
【0027】
また、本発明に係るケーソン上端部の施工方法によれば、仮設土留め壁の内周側に、周方向に沿って設けた環状の梁と、内周に沿って上下に延在する柱とからなる支保工を設け、仮設土留め壁を支持することにより、仮設土留め壁の強度を高めることができる。そして、これにより仮設土留め壁の軽量化を図ることができ、仮設土留め壁の撤去をさらに容易にすることができる。また、頂版上を埋め戻す際に環状の梁の撤去し、柱を頂版の上端部に対応する位置で切断することにより、頂版上を埋め戻し後の柱の撤去を容易に行うことができる。
【0028】
また、本発明に係るケーソン上端部の施工方法によれば、頂版上の埋め戻しを行う前に、頂版の上端部に対応する位置で柱を切断して、柱の上端部と柱の切断位置より下の部分とを、ボルトで締結しておき、頂版上の埋め戻し完了後に、ボルトの締結を解除して、柱を引き抜くので、柱が露出している状態、容易に柱を切断し、埋め戻し後に柱を撤去できる。また、柱を切断後もボルトにより立てた状態に保持できるので、たとえば、支保工に接合された状態の仮設土留め壁上部を支えることができるので、仮設土留め壁で土留めを行うことができる。
【図面の簡単な説明】
【図1】本発明を適用した一例としてのオープンケーソン上端部の側面図である。
【図2】図1におけるオープンケーソン上端部の、図中のA部分の拡大図である。
【図3】図1におけるオープンケーソン上端部の上面図である。
【図4】図3におけるオープンケーソン上端部の上面図の一部拡大図である。
【図5】オープンケーソン上端部の施工順序を示す、オープンケーソン上端部の概略側面図である。
【図6】上端部の施工完了後のオープンケーソンの状態を示す、概略側面図である。
【符号の説明】
1 ケーソン
2 Hビーム
3 リングビーム
4 仮設土留め壁
5 土留め壁下部
6 土留め壁上部
8 頂版
10 ボルト
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method for an upper end portion of a caisson whose upper end portion is located below the ground surface.
[0002]
[Prior art]
In the caisson method, as in the open caisson method, a tubular structure constructed of reinforced concrete is placed on the ground, the ground below the tubular structure is excavated, and the weight or load of the tubular structure is There is a method of sinking the cylindrical structure into the ground, and by repeatedly adding the cylindrical structure and excavating the ground, the cylindrical structure reaches the predetermined supporting ground, and then the bottom concrete and the top Construction of slab concrete and construction of foundation structure. The constructed foundation structure serves as the foundation of the ground structure and the main body of the underground structure.
In such a caisson method, since the cylindrical structure always reaches the ground surface, the cylindrical structure itself has a retaining wall that prevents the surrounding soil from flowing into the cylindrical structure. It has become.
[0003]
[Problems to be solved by the invention]
By the way, when building a structure in the basement, when the ground surface on the underground structure is used for a purpose of use unrelated to the underground structure, for example, as a park or residential land, a certain amount of It is necessary not to leave a structure or temporary material in the depth. Therefore, as described above, in the caisson method in which the cylindrical structure reaches the ground surface, in such a case, the cylindrical structure near the ground surface must be removed.
[0004]
However, in the above-described caisson method, the cylindrical structure has a strong structure because it serves as the foundation of the ground structure and the base of the underground structure. Therefore, there is a problem that it takes time to remove a part (upper part) of the cylindrical structure.
[0005]
Accordingly, an object of the present invention is to easily remove the structure above the top plate of the caisson and backfill in a caisson having a structure in which the upper end portion is located below the ground surface and the top plate is backfilled. The object is to provide a method for constructing the upper end of the caisson.
[0006]
[Means for Solving the Problems]
In order to solve the above problems, the present invention provides a caisson method including a step of excavating the caisson and sinking the caisson, so that the position of the upper end of the caisson installed below the ground surface is below the surface part. The caisson upper end portion in the caisson having a structure in which the top of the top plate provided on the upper end portion is backfilled, the caisson (1) upper end portion being submerged below the ground surface portion A temporary earth retaining wall (4) that is substantially the same as the caisson and can be divided into a plurality of pieces is provided on the caisson so as to reach the ground surface portion, and in the temporary earth retaining wall, After the top plate (8) is provided at the upper end of the caisson, the top plate is refilled and the temporary earth retaining wall above the top plate is divided and removed.
[0007]
Here, it is preferable that the temporary earth retaining wall is cut and cut into a plurality of vertical surfaces intersecting the earth retaining wall.
[0008]
As described above, according to the present invention , in the portion extending from the upper end portion of the caisson, which is sunk below the ground surface portion, to the ground surface portion, a temporary soil that is substantially the same cylindrical shape as the caisson and can be divided into a plurality of pieces. A retaining wall is provided, and after the caisson top plate is formed in the temporary earth retaining wall, the top plate is refilled and the temporary earth retaining wall is divided and removed. Therefore, the top plate can be provided at the upper end portion of the caisson submerged below the ground surface portion by retaining the portion from the upper end portion of the caisson to the ground surface portion with the temporary earth retaining wall. In addition, the temporary earth retaining wall is not subjected to weighting as when caisson is sunk, and is not used as a foundation or basement structure, and has sufficient strength to allow earth retaining. Since it is sufficient, the thickness can be made thinner than the caisson. Such a temporary earth retaining wall can be further divided into a plurality of parts, so that it can be easily pulled out after being backfilled and easily removed.
When the caisson is laid, a temporary earth retaining wall is created on the cylindrical structure in advance when the cylindrical structure that becomes the upper end of the caisson is submerged from the ground to the basement. Even if the upper end of the object is submerged below the ground surface, it is necessary to be able to retain the top of the cylindrical structure with the temporary retaining wall. In this case, it is necessary to sink the caisson deeper than the ground surface by applying a load to the caisson's own weight or the upper end of the caisson without applying a load to the temporary earth retaining wall.
[0009]
In the construction method of the caisson upper end portion according to the present invention, the temporary earth retaining wall is a lower part of the earth retaining wall that serves as a mold for the outer peripheral portion of the top plate when the concrete is placed and the top plate is provided. 5) and a retaining wall upper portion (6) provided on the lower part of the retaining wall, removable from the lower part of the retaining wall and detachable into a plurality of parts, and refilling the top plate In this case, the upper part of the separable earth retaining wall is divided and removed.
[0010]
As described above, according to the present invention , the temporary earth retaining wall is a lower part of the earth retaining wall that forms the outer peripheral portion of the top plate when the concrete is cast to form the top plate. By providing the upper part of the retaining wall upper part, which is detachable from the lower part of the retaining wall and can be divided into a plurality of parts, it is not necessary to newly provide a form plate for the top plate, and the cost can be reduced. Further, since the upper part of the retaining wall can be removed from the lower part of the retaining wall, it can be easily removed even after placing concrete in the lower part of the retaining wall.
[0011]
In the construction method of the caisson upper end , the present invention provides an annular beam (for example, ring beam 3) provided along the circumferential direction on the inner peripheral side of the temporary earth retaining wall, and the temporary earth retaining wall. The temporary earth retaining wall is supported by a support having a column (for example, an H beam 2) extending vertically along the inner periphery of the ring, and the annular beam is removed when the top plate is refilled. In addition, the column is cut at a position corresponding to the upper end of the top plate, and the column is removed.
[0012]
Thus, according to the present invention , the annular beam provided along the circumferential direction on the inner peripheral side of the temporary earth retaining wall, and the column extending vertically along the inner circumference of the temporary earth retaining wall. By supporting the temporary earth retaining wall with the supporting structure provided, the strength of the temporary earth retaining wall can be increased, so that the temporary earth retaining wall itself can be reduced in weight, for example, by reducing the thickness, It can be made easier to remove. Also, when the top plate is backfilled, the circular beam is removed, and the column is cut at a position corresponding to the upper end of the top plate, so that the column is easily removed after the top plate is backfilled. be able to.
[0013]
Further, in the construction method of the caisson upper end portion according to the present invention, the position of the column corresponding to the upper end portion of the top plate before the backfilling on the top plate when removing the column of the support work. At the time of cutting, the upper end portion of the column and the portion below the cutting position of the column are fastened with bolts (10) and backfilled on the top plate, and then the upper end portion side of the column From the above, the fastening of the bolt is released and the column is pulled out.
[0014]
Thus, according to the present invention , before performing backfilling on the top plate, the column is cut at a position corresponding to the upper end portion of the top plate, and the upper end portion of the column and the portion below the cutting position of the column And after the backfilling on the top plate is completed, the bolts are released from the upper end side of the column, and the column before the backfilling is exposed by pulling out the column. Can be easily cut, and can be held in an upright state even after cutting with a bolt. Further, by the divided parts of the temporary設土fastening wall upper pillars of shoring is bonded, if a state where each divided portion of the temporary earth retaining wall upper is joined to temporary earth retaining wall lower By fastening the column cutting portion with the above bolts, when the backfilling is performed, the divided portions of the upper part of the temporary earth retaining wall can be kept joined to the lower part of the temporary earth retaining wall, and the above bolt After releasing the fastening by, each divided portion of the upper part of the temporary earth retaining wall can be easily removed.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
Below, the embodiment of the construction method of the caisson upper end part which concerns on this invention is described based on FIGS.
The underground structure constructed by applying the present invention is, for example, a resistance that has drainage pipes 23 and 23 connected from two tunnels 21 and 22 for a subway and has a passage from the ground. The resistance is composed of an open caisson 26. However, since the ground surface on the open caisson 26 is used for a purpose different from this underground structure, the underground structure composed of the open caisson 26 is set to a position below the ground surface, and the top of the open caisson 26 is backfilled. It is in the state.
In order to secure a passage to the ground, a resistance composed of the open caisson 24 reaching the ground is provided at a position away from the open caisson 26, and the open caisson 26 and the open caisson 24 are joined by the passage 25 in the basement. Has been. Thereby, the passage between the lower part of the open caisson 26 and the ground can be secured.
[0016]
Here, before explaining the construction method of the upper end portion of the open caisson, a temporary structure provided at the upper end portion of the open caisson will be described. FIG. 1 is a side view of the upper end portion of an open caisson, and FIG. 2 is an enlarged view of a portion A in FIG. In the figure, 1 is a circular caisson, 2 is an H beam (column), 3 is a ring beam ( annular beam), and 4 is a temporary earth retaining wall. The temporary earth retaining wall 4 is composed of an earth retaining wall lower part 5 and an earth retaining wall upper part 6. The H beam 2 and the ring beam 3 serve to support the temporary earth retaining wall 4. The H beam 2 is partially embedded in the caisson 1 and protrudes upward from the upper end of the caisson 1 in parallel with the length direction (vertical direction) of the caisson 1. A plurality of H beams 2 are provided at the upper end of the caisson 1. Inside the H beam 2, annular ring beams 3 and 3 are installed along the circumferential direction. The ring beams 3 and 3 are provided above the H beam with an interval in the vertical direction.
[0017]
On the upper end of the caisson 1, a cylindrical earth retaining wall lower part 5 is provided along the circumference of the caisson 1 outside the H beams 2, 2,. The retaining wall lower portion 5 is made of, for example, concrete having a thickness of 200 mm. The earth retaining wall lower part 5 (earth retaining wall 4) is thinner than the caisson 1 (the caisson 1 has a thickness of 700 mm, for example) and is formed so as to be placed on the outer peripheral side of the upper end surface of the caisson 1. . Therefore, the inner peripheral side of the upper end surface of the caisson 1 is in an exposed state, and a load can be applied to the caisson 1 inside the earth retaining wall 4 when the caisson 1 is laid down.
[0018]
On the earth retaining wall lower part 5, the earth retaining wall upper part 6 is installed so as to be outside the H beams 2, 2... Like the earth retaining wall lower part 5 (see FIG. 3). The earth retaining wall upper part 6 has a cylindrical shape made of concrete having a thickness of 200 mm, like the earth retaining wall lower part, but can be divided vertically into 10 parts. That is, the retaining wall upper part 6 on the cylinder is constructed by arranging and joining ten arc-plate-like divided bodies along the circumference. In addition, each division | segmentation body used as the earth retaining wall upper part 6 is good also as what consists of precast concrete, and is good also as what constructs by placing concrete in the field in the divided | segmented state.
[0019]
Moreover, joining of division bodies can be performed by a known method, for example, it is good also as what joins using a well-known various coupling. Moreover, joining of the retaining wall lower part 5 and the retaining wall upper part 6 can also be performed by a known method. Moreover, it is also possible to perform the joining of the respective divided bodies of the retaining wall upper part 6 and the joining of the retaining wall lower part 5 and the retaining wall upper part 6 through the supporting work composed of the H beam 2 and the ring beam 3. good. That is, by joining each divided body of the retaining wall upper part 6 to the support work, joining of each divided body of the retaining wall upper part 6 and joining of the retaining wall lower part 5 and the retaining wall upper part 6 are performed. You may do it.
[0020]
Further, the earth retaining wall upper portion 6 is arranged so that the joint portion between the divided bodies comes behind the H beam 2 as shown in FIG. 4. Moreover, the removal from the earth retaining wall lower part 5 can also be performed now easily.
Here, when there is a restriction that a structure or the like should not be left at a certain depth from the ground surface, the length of the earth retaining wall upper part 6 is set to be equal to or longer than a depth determined by the restriction. For example, when a structure or the like should not be left from the ground surface to 2.5 m underground, the length of the retaining wall upper part 6 is set to 2.5 m or more.
[0021]
Next, the construction method of the caisson upper end part which has the above temporary structures is demonstrated.
Similar to the general open caisson method, the ground below the caisson 1 is excavated, and the caisson 1 is buried in the ground by its own weight or press-fitting.
Then, when constructing the cylindrical structure part which becomes the upper end part of the caisson 1, the supporting work composed of the H beam 2 and the ring beam 3 as described above, the temporary earth retaining wall lower part 5 and the temporary earth retaining wall upper part 6 A temporary earth retaining wall 4 is constructed.
Further, the caisson 1 is further submerged in the ground, and the caisson 1 is buried until the upper end of the earth retaining wall upper part 6 becomes almost equal to the ground surface. After the caisson 1 is completely embedded, the precast concrete 7 serving as the bottom of the form plate of the top plate is laid on the upper end portion of the caisson 1 so as to close the caisson 1, and the concrete is placed on the top plate 8 Form. At this time, the earth retaining wall lower part 5 becomes a formwork of the top plate 8 simultaneously with earth retaining. Further, the top end of the top plate 8 is placed so as to be below the joint between the retaining wall lower part 5 and the retaining wall upper part 6. In order to prevent water or the like from entering the caisson 1, a waterproof sheet 12 is sandwiched between contact surfaces of the top plate 8 and the H beams 2, 2,.
[0022]
Next, a cover mortar 9 is placed on the top plate 8 as shown in FIG. 5A, and the H beams 2, 2... Are cut above the cover mortar 9. Similarly to the top plate 8, the cover mortar is also placed so as to be below the joint between the retaining wall lower part 5 and the retaining wall upper part 6.
When cutting the H beams 2, 2,..., Fasten the upper ends of the H beams 2, 2,... With the long bolts 10, 10,. (See FIG. 5B).
Further, after placing the concrete 11 on the cover mortar 9 (see FIG. 5 (c)), the ring beams 3, 3 are removed from the H beams 2, 2,... (See FIG. 5 (d)), and the top plate of the caisson. 8 The top is refilled with earth and sand 13 or the like (see FIG. 5E).
Then, the fastening of the bolts 10, 10... Is released from the upper end side of the H beams 2, 2... (See FIG. 5 (f)), and the H beams 2, 2. Thus, as shown in FIG. 6, the upper end portion of the open caisson can be constructed so as not to leave a structure or the like at a certain depth from the ground surface.
[0023]
Thus, according to the construction method of the caisson upper end part of the above embodiment, by carrying out the earth retaining with the earth retaining wall lower part 5 and the earth retaining wall upper part 6 from the upper end part of the caisson 1 to the ground surface, The top plate 8 can be easily driven on the upper end portion of the caisson 1 set below the ground surface. Moreover, since the retaining wall upper part 6 is thinner than the caisson 1 and can be divided into 10 parts, it can be easily removed after the top of the caisson 1 is backfilled. Since the earth retaining wall lower part 5 is not only earth retaining but also a mold frame of the outer peripheral portion of the top plate 8, it is not necessary to newly provide a mold frame, and the cost can be reduced.
Moreover, since the top plate 8 and the cover mortar 9 are driven below the joint between the retaining wall lower part 5 and the retaining wall upper part 6, the retaining wall upper part 6 can be easily pulled out.
The strength of the earth retaining wall lower part 5 and the earth retaining wall upper part 6 can be increased by supporting the earth retaining wall lower part 5 and the earth retaining wall upper part 6 with the H beams 2, 2. .
Further, before the back-filling on the top plate 8, the H beams 2, 2... Are cut with the H beams 2, 2. The parts below the cutting position of the beams 2, 2 ... are fastened with bolts 10, 10 ..., and after the back-filling on the top plate is completed, the fastening of the bolts 10, 10 ... is released, and the H beams 2, 2 ... By pulling out ..., the H beams 2, 2, ... can be kept upright even after cutting. Cutting and drawing operations can be easily performed.
[0024]
In the above embodiment, an open caisson is cited as an applied caisson. However, the present invention is not limited to this, and a caisson that is submerged under the ground surface by excavating the caisson. For example, it can be applied to a pneumatic caisson or a press-fitting caisson.
In addition, although the upper part of the retaining wall can be divided into ten parts, the present invention is not limited to this, and it is only necessary that the upper part of the retaining wall can be easily pulled out by dividing, and may be divided into any number of parts. .
The thickness of the earth retaining wall, the number of H beams and ring beams, and the like are arbitrary, and it is needless to say that other specific detailed structures can be appropriately changed.
[0025]
【The invention's effect】
As described above, according to the construction method of the caisson upper end portion according to the present invention , the caisson upper end portion submerged below the ground surface portion to the ground surface portion, on the caisson, in a cylindrical shape substantially similar to the caisson. By providing a temporary earth retaining wall that can be divided into a plurality of pieces, the temporary earth retaining wall can retain the part from the upper end portion of the caisson to the surface portion, and the upper end portion of the caisson set below the surface portion. A top plate can be provided. In addition, after forming the top plate of the caisson in the temporary earth retaining wall, by refilling the top plate, dividing the temporary earth retaining wall and removing it, the temporary earth retaining wall is thinner than the caisson, Furthermore, since it can be divided into a plurality of parts, it can be easily pulled out after backfilling and can be easily removed.
[0026]
Moreover, according to the construction method of the caisson upper end part according to the present invention , the temporary earth retaining wall includes an earth retaining wall lower part which becomes a mold of an outer peripheral part of the top plate when the top plate is formed, and the earth retaining wall lower part. And an upper part of the retaining wall that is detachable from the lower part of the retaining wall and can be divided into a plurality of parts. As a result, it is not necessary to newly provide a form plate for the top plate, so that the cost can be reduced. Further, the upper part of the retaining wall can be easily removed even after the concrete is placed in the lower part of the retaining wall.
[0027]
Moreover, according to the construction method of the caisson upper end portion according to the present invention , an annular beam provided along the circumferential direction on the inner peripheral side of the temporary earth retaining wall, and a column extending up and down along the inner periphery The strength of the temporary earth retaining wall can be increased by providing the support work made of and supporting the temporary earth retaining wall. Thus, the temporary earth retaining wall can be reduced in weight, and the temporary earth retaining wall can be removed more easily. Also, when the top plate is backfilled, the circular beam is removed, and the column is cut at a position corresponding to the upper end of the top plate, so that the top plate can be easily removed after backfilling. Can do.
[0028]
Moreover, according to the construction method of the caisson upper end portion according to the present invention , before refilling the top plate, the column is cut at a position corresponding to the upper end portion of the top plate, and the upper end portion of the column and the column The part below the cutting position is fastened with bolts, and after the backfilling on the top plate is completed, the bolts are released and the pillars are pulled out. The pillar can be removed after cutting and backfilling. Moreover, since it can hold | maintain in the state stood with the volt | bolt after cut | disconnecting a pillar, for example, since the temporary earth retaining wall upper part state in which it was joined to the support work can be supported, earth retaining with a temporary earth retaining wall can be performed. it can.
[Brief description of the drawings]
FIG. 1 is a side view of an upper end portion of an open caisson as an example to which the present invention is applied.
FIG. 2 is an enlarged view of a portion A in the drawing at the upper end portion of the open caisson in FIG. 1;
3 is a top view of the upper end portion of the open caisson in FIG. 1. FIG.
4 is a partially enlarged view of a top view of the upper end portion of the open caisson in FIG. 3;
FIG. 5 is a schematic side view of the upper end portion of the open caisson showing the construction sequence of the upper end portion of the open caisson.
FIG. 6 is a schematic side view showing the state of the open caisson after completion of the construction of the upper end portion.
[Explanation of symbols]
1 Caisson 2 H beam 3 Ring beam 4 Temporary earth retaining wall 5 Earth retaining wall lower part 6 Earth retaining wall upper part 8 Top plate 10 Bolt

Claims (3)

ケーソン内部を掘削して、ケーソンを沈下させる工程を含むケーソン工法によって、地表下に設置されるケーソンのうちの、上端部の位置が地表部分の下とされるとともに前記上端部に設けられた頂版の上が埋め戻された構造を有し、
前記地表部より下に沈設させられる前記ケーソン上端部から地表部に至るように、前記ケーソン上に前記ケーソンとほぼ同様の筒状で、かつ、複数に分割自在な仮設土留め壁を設けておき、
上記仮設土留め壁内において、前記ケーソン上端部に前記頂版を設けた後に、前記頂版上を埋め戻すとともに頂版より上の仮設土留め壁を分割して撤去するケーソン上端部の施工方法であって、
前記仮設土留め壁が、コンクリートを打設して頂版を設ける際の頂版の外周部分の型枠となる土留め壁下部と、該土留め壁下部の上に設けられ、該土留め壁下部から取り外し自在で、かつ、複数に分割自在な土留め壁上部とを備え、
前記頂版上を埋め戻す際に上記分割自在な土留め壁上部を分割して撤去することを特徴とするケーソン上端部の施工方法。
By the caisson method that includes the step of excavating the caisson and sinking the caisson, the position of the upper end of the caisson installed below the ground surface is set below the ground surface and the top provided at the upper end It has a structure where the top of the plate is backfilled ,
A temporary earth retaining wall having a cylindrical shape substantially the same as the caisson and separable into a plurality of pieces is provided on the caisson so as to reach the ground surface from the upper end of the caisson that is submerged below the ground surface. ,
In the temporary earth retaining wall, said after providing the top plate to the caisson upper end, the construction method of the caisson upper end with backfill on the top plate to be removed by dividing the temporary earth retaining wall above the top plate Because
The temporary earth retaining wall is provided on the earth retaining wall lower part to be a formwork of the outer peripheral part of the top plate when the concrete is placed and the top plate is provided, and on the earth retaining wall lower part, the earth retaining wall It has a retaining wall upper part that is removable from the lower part and can be divided into a plurality of parts,
The caisson upper end construction method characterized in that when the top plate is backfilled, the separable earth retaining wall upper part is divided and removed .
請求項1記載のケーソン上端部の施工方法において、
前記仮設土留め壁の内周側で周方向に沿って設けられた環状の梁と、前記仮設土留め壁の内周に沿って上下に延在する柱とを備えた支保工で前記仮設土留め壁を支持し、前記頂版上を埋め戻す際に前記環状の梁を撤去するとともに、前記柱を前記頂版の上端部に対応する位置で切断して、前記柱を撤去することを特徴とするケーソン上端部の施工方法。
In construction methods caissons upper portion of claim 1 Symbol placement,
The temporary soil is a support structure comprising an annular beam provided along the circumferential direction on the inner peripheral side of the temporary earth retaining wall and a column extending vertically along the inner circumference of the temporary earth retaining wall. The retaining beam is supported, and the annular beam is removed when the top plate is refilled, and the column is cut at a position corresponding to the upper end portion of the top plate to remove the column. The caisson top end construction method.
請求項2記載のケーソン上端部の施工方法において、
前記支保工の前記柱を撤去するに際し、頂版上の埋め戻しを行う前に、前記柱を頂版の上端部に対応する位置で切断するとともに、切断に際し、柱の上端部と柱の切断位置より下の部分とを、ボルトで締結しておき、
頂版上の埋め戻しを行った後に、柱の上端部側から前記ボルトの締結を解除して前記柱を引き抜くことを特徴とするケーソン上端部の施工方法。
In construction methods caisson upper end of claim 2 Symbol placement,
When removing the column of the support, before performing backfilling on the top plate, the column is cut at a position corresponding to the upper end portion of the top plate, and at the time of cutting, the upper end portion of the column and the column are cut. Fasten the part below the position with bolts,
A caisson upper end construction method characterized by releasing the fastening of the bolt from the upper end side of the column and then pulling out the column after backfilling the top plate.
JP36175199A 1999-12-20 1999-12-20 Caisson top end construction method Expired - Fee Related JP4248716B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP36175199A JP4248716B2 (en) 1999-12-20 1999-12-20 Caisson top end construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP36175199A JP4248716B2 (en) 1999-12-20 1999-12-20 Caisson top end construction method

Publications (2)

Publication Number Publication Date
JP2001172983A JP2001172983A (en) 2001-06-26
JP4248716B2 true JP4248716B2 (en) 2009-04-02

Family

ID=18474747

Family Applications (1)

Application Number Title Priority Date Filing Date
JP36175199A Expired - Fee Related JP4248716B2 (en) 1999-12-20 1999-12-20 Caisson top end construction method

Country Status (1)

Country Link
JP (1) JP4248716B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695447B (en) * 2015-03-13 2017-01-25 朱奎 deep basement support

Also Published As

Publication number Publication date
JP2001172983A (en) 2001-06-26

Similar Documents

Publication Publication Date Title
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
JP4881555B2 (en) Construction method of underground structure
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
KR102223856B1 (en) Foundation structure of waste landfill site and construction method thereof
KR20130021952A (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JP5480744B2 (en) Foundation for structure and its construction method
JP4226954B2 (en) Underpinning method and viaduct
JP4248716B2 (en) Caisson top end construction method
JPH1136338A (en) Construction method of underground structure
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
JPH11152762A (en) Structure and its construction method
JP3919852B2 (en) Method for construction of cast-in-place pile
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
JPH07243269A (en) Method of building underground parking lot
JP4475116B2 (en) Vertical shaft structure and its construction method
JPH07197473A (en) Structure of open caisson
JP4344733B2 (en) Seismic reinforcement structure for existing pile foundation structures
KR200375610Y1 (en) Cast in place concrete pile using vibro magnetic shovel hammer
JP3646698B2 (en) Construction method for underground structures
CN219261048U (en) Working well
JP4132320B2 (en) Foundation construction method
KR20120032368A (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
JP4146561B2 (en) Construction method of shaft

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060809

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080916

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080924

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081114

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090106

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090114

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120123

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150123

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees