JPH0321777A - Construction method of iron-frame pillar - Google Patents

Construction method of iron-frame pillar

Info

Publication number
JPH0321777A
JPH0321777A JP15445889A JP15445889A JPH0321777A JP H0321777 A JPH0321777 A JP H0321777A JP 15445889 A JP15445889 A JP 15445889A JP 15445889 A JP15445889 A JP 15445889A JP H0321777 A JPH0321777 A JP H0321777A
Authority
JP
Japan
Prior art keywords
column
steel
iron
frame pillar
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15445889A
Other languages
Japanese (ja)
Inventor
Yoshiaki Takao
高尾 善卿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP15445889A priority Critical patent/JPH0321777A/en
Publication of JPH0321777A publication Critical patent/JPH0321777A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To construct an iron-frame pillar efficiently in a short period by lifting up a tube-form iron-frame pillar body by using a basic pillar erected on the ground as a guide, adding the next iron-frame pillar body below the first pillar body, and constructing the iron-frame pillar in order. CONSTITUTION:A tube-form upper iron-frame pillar body 12 to be the top iron- frame pillar body is loaded on the upper stoppers 11a and 11b at the top end of a base pillar 2, and the second iron frame pillar bodies 13a and 13b added to the lower end of the upper iron-frame pillar body 12 are incorporated between the upper iron-frame pillar body 12 and a lower stopper 10 covering the base pillar 2. The iron-frame pillar bodies 13a and 13b are welded or bolted to connect to the lower end of the upper iron-frame pillar body 12 to make into the second iron-frame pillar body 13. Then, a hook 9 is fixed to the lower end, and a winch 6 is driven to lift a wire 7 so as to make the added iron-frame pillar bodies 12 and 13 incorporated. They are lifted up further to add the next iron frame pillar body in the same procedure, and an iron-frame pillar is constructed.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は立体駐車場の如き塔状建築物を埋設する際に用
いる鉄骨社の構築方法に関づるものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for constructing a steel frame used when burying a tower-shaped building such as a multi-story parking lot.

[従来の技術] 立体駐車場の如き塔状建築物を建設するために、鉄骨柱
体と梁やトラス等の構造材とから建築物の骨組構造をな
す建屋構造体を構築する場合、大型クレーンを用いて鉄
骨柱体を建て、且つ大型の作業足場を利用して上記構造
材を鉄骨柱体に取り付けて行き、下部から順次上方へと
作業を進めて行くことが従来一般的に行われている。
[Prior Art] In order to construct a tower-like building such as a multi-story parking lot, a large crane is used to construct a building structure that forms the frame structure of the building from steel columns and structural materials such as beams and trusses. Conventionally, it has been common practice to erect a steel column using a large work scaffold, attach the structural materials to the steel column using a large work scaffold, and proceed with the work from the bottom upwards. There is.

[発明が解決しようとする課題] ところが、上記従来一般的に行われている建屋構造体の
構築方法の場合には、大型クレーンを用いて鉄骨柱体を
吊り上げる必要があり、又、構築時に風等の影響を受け
ると柱倒壊の虞があるため、安全性に問題があり、史に
、大型の作業足場を利用しての高所作業となるため、作
業能率が悪く且つ多くの人手を必要とし、工期が長くか
かる問題があった。
[Problems to be Solved by the Invention] However, in the case of the conventional building structure construction method described above, it is necessary to lift the steel column using a large crane, and there is There is a safety issue as there is a risk of pillars collapsing if they are affected by such things. However, there was a problem with the long construction period.

そこで、本発明は、大型クレーンを用いることなく、し
かも風等の影響を受けることなく安全に鉄骨柱を構築で
きる鉄骨柱の構築方法を提供し、以て、建屋構造体の如
き構造物を作業足場を利用することなく能率よく短期間
にて構築できるようにしようとするものである。
Therefore, the present invention provides a method for constructing a steel frame column that can be safely constructed without using a large crane and without being affected by wind, etc., and allows construction of a structure such as a building structure. The aim is to enable efficient construction in a short period of time without the use of scaffolding.

[課題を解決するための手段] 本発明は、上記課題を解決するために、所要の長さとし
た筒状の鉄骨柱体を、地上に立設した基礎柱をガイドと
して該鉄骨柱体の長さと同じ高さ分持ち上げ、次いで、
該持ち上げた鉄骨柱体と地上との間に2つ割れの鉄骨柱
体を上記基礎柱を抱くように配した後、該2つ割れの鉄
骨柱体を持ら上げた鉄骨柱体との接合、2つυ1れ鉄骨
4I自体の接合を行って継ぎ足し、しかる後、上記継ぎ
足した鉄骨柱体をほぼその高さ分持ち上げ、以後同様な
作業を繰り返して所定高さの鉄骨柱を構築することを特
徴とする鉄骨社の構築方法である。
[Means for Solving the Problems] In order to solve the above-mentioned problems, the present invention provides a method for measuring the length of a cylindrical steel column with a required length using a foundation column erected on the ground as a guide. Lift it up to the same height as the
A two-piece steel column is placed between the lifted steel column and the ground so as to embrace the foundation column, and then the two-piece steel column is joined to the lifted steel column. , the two υ1 steel frames 4I are joined and joined together, and then the added steel column body is lifted by approximately that height, and the same work is repeated thereafter to construct a steel frame column of a specified height. This is the construction method of the steel frame company.

又、鉄骨柱体の持ち上げを、基礎柱上のシブにかけて先
端を該鉄骨柱体に係止させたワイヤロープを巻き取るこ
とにより行うとよい。
Further, lifting of the steel frame column may be carried out by winding up a wire rope whose tip is secured to the steel frame column by passing it through a shib on the foundation column.

更に、地上に少なくとも2本の基礎柱を立て、少なくと
も2本の鉄骨柱体を用いて構築した鉄骨構造体を上記基
礎柱をガイドとして持ち上げた後継ぎ足して行くように
してもよい。
Furthermore, at least two foundation columns may be erected on the ground, and a steel frame structure constructed using at least two steel frame columns may be added to the steel structure by lifting it up using the foundation columns as a guide.

[作  用] 筒状の鉄骨柱体を、地上に立てた基礎柱をガイドとして
リフトアップさせてその下に次の鉄骨柱体を継ぎ足した
後、再びリフトアップさせて行くようにするので、リフ
トアップ時は基礎柱にガイドされていることから風等の
影響を受けることなく安全にリフトアップできて鉄骨柱
体を所要高ざまで構築することができる。又、建屋構造
体の如き構造物の構築作業に採用して、少なくとも2本
の鉄骨柱体を用いて構築した構造体を、少なくとも2本
の基礎柱に沿いリフトアップさせるようにすることによ
り、構造物の構築を作業足場を用いることなく能率よく
行うことができるようになる。
[Operation] The cylindrical steel column is lifted up using the foundation column erected on the ground as a guide, the next steel column is added below it, and then it is lifted up again. Since it is guided by the foundation columns when it is lifted up, it can be lifted up safely without being affected by wind, etc., and the steel column body can be built to the required height. In addition, by adopting it in the construction work of structures such as building structures, and lifting up the structure constructed using at least two steel columns along at least two foundation columns, Structures can be constructed efficiently without using scaffolding.

[実 施 例] 以下、本発明の実施例を図面を参照して説明ずる。[Example] Embodiments of the present invention will be described below with reference to the drawings.

第1図乃至第7図は本発明の鉄骨社の構築方法の一実施
例による作業手順を示すもので、本発明の方法は、基本
的には、所要長さとした筒状の鉄骨柱体を、地上に立て
た角型断面又は丸型断面で中空の基礎柱の外側を沿わせ
てリフトアップさせて、その下に別の鉄骨柱体を継ぎ足
しながら高さの高い鉄骨柱を上から下へ構築して行くも
のである。
Figures 1 to 7 show the working procedure according to an embodiment of the steel frame construction method of the present invention. , Lift up a hollow foundation column with a square or round cross section erected on the ground along the outside, and add another steel column below it to move the taller steel column from top to bottom. It is something that will be built.

具体的に説明すると、先ず、第1図に示プ如く、地上1
に、角パイプ又は丸パイプからなる所要高さの基礎柱2
をアンカーボルト3を用いて立設し、且つ該基礎柱2内
の下端部にガイドシーブ4aを設置すると共に、上記基
礎柱2の頂部にガイドシーブ4bを設買し、地上1に設
備したウインチ6のワイヤロー17を、上記基礎柱2の
下端部に穿設した孔8を通して基礎柱2内に導入して、
上記ガイドシーブ4a, 4bの順に掛けた後、基礎柱
2外へ導出して地上1付近に位置させ、その先端にフッ
ク9を取り付けておく。
To explain specifically, first, as shown in Figure 1,
2 foundation columns of the required height made of square or round pipes.
is erected using anchor bolts 3, a guide sheave 4a is installed at the lower end of the foundation pillar 2, a guide sheave 4b is installed at the top of the foundation pillar 2, and a winch is installed on the ground 1. 6 of the wire row 17 is introduced into the foundation pillar 2 through the hole 8 drilled in the lower end of the foundation pillar 2,
After the guide sheaves 4a and 4b are hung in this order, they are led out of the foundation pillar 2 and positioned near the ground 1, and a hook 9 is attached to the tip.

又、上記基礎柱2の下端部には、上記孔8の位置よりも
上部位置の相対する側に、下部ストツパ10を設けると
共に、上端部の相対する位置に、上部ストツパlla,
 llbを、ピン5の抜き差しにより着脱自在となるよ
うに取り付けておく。
Further, at the lower end of the foundation column 2, a lower stopper 10 is provided on the opposite side above the position of the hole 8, and an upper stopper 10 is provided at the opposite position on the upper end.
llb is attached so that it can be attached and detached by inserting and removing the pin 5.

かかる状態において、塔状鉄骨柱を構築するために所要
長さとした多数の鉄骨柱体を継ぎ足しながら上記基礎柱
2をガイドとして上昇させて行くようにする。先ず、第
2図に示す如く、鉄骨社を構成するときの頂部の鉄骨柱
体となる筒状の上部鉄骨柱体12を、上記基礎柱2の外
径よりも大きい内径のものとして、基礎柱2の上端部に
取り付けてある上部ストツパlla, llb上に戟置
させる。次に、上記上部鉄骨柱体2の下端に継ぎ足すた
めの2段目の鉄骨柱体となる径方向に2つ割れとした鉄
骨柱片13aと13bとからなる下段(2段目〉の銖骨
柱体13を、第3図の状態から第4図に示す如く上部鉄
骨柱体12と下部ストツパ10との間に組み入れ、基礎
柱2を包むようにする。この場合は、先ず、上記基礎柱
2に取り付けてある上部ストツパlla,llbのうら
、たとえば、llaを取り外して上部鉄骨柱体12を他
方の上部ストツパ11bに支持させた状態としておき、
次いで、上記上部ストツパllaを取り外した側に配置
させるように用意させた上記鉄骨柱体13の一方の鉄骨
柱片13aを下部ストツパ10上に搬入し、該鉄骨柱片
13aの上端と上部鉄骨柱体12の下端とを溶接又はボ
ルト締めにより接合する。この接合により上部鉄骨柱体
12は鉄骨柱片13aを介して下部ストツパ10上に支
持させた状態にすることができるので、続いて、他方の
上部ストツパ1lbを取り外してその位置に他方の鉄骨
社片13bを搬入して下部ストッパ10上に戟せ、同様
に、該鉄骨柱片13bの上端と上部鉄骨柱体12の下端
とを接合し、更に、鉄骨社片13aと13bとを接合し
て2段目の鉄骨柱体13とし、第4図に示す如く、該2
段目の鉄骨柱体13を上部鉄骨柱体12に継ぎ足した状
態とする。
In such a state, in order to construct a tower-shaped steel column, a large number of steel frame columns each having a required length are added and raised using the foundation column 2 as a guide. First, as shown in FIG. 2, the cylindrical upper steel column 12, which will be the top steel column when constructing the steel frame building, has an inner diameter larger than the outer diameter of the foundation column 2. Place it on the upper stoppers lla and llb attached to the upper end of 2. Next, a lower tier (second tier) column consisting of radially split steel column pieces 13a and 13b, which will become a second tier of steel columns to be added to the lower end of the upper steel column 2, is constructed. The frame column body 13 is assembled between the upper steel frame column body 12 and the lower stopper 10 from the state shown in FIG. 3 as shown in FIG. 4, so as to wrap around the foundation column 2. The backs of upper stoppers lla and llb attached to 2, for example, lla, are removed and the upper steel column body 12 is left supported by the other upper stopper 11b,
Next, one steel column piece 13a of the steel column body 13 prepared so as to be placed on the side from which the upper stopper lla has been removed is carried onto the lower stopper 10, and the upper end of the steel column piece 13a and the upper steel column The lower end of the body 12 is joined by welding or bolting. By this connection, the upper steel column 12 can be supported on the lower stopper 10 via the steel column piece 13a, so next, the other upper stopper 1lb is removed and the other steel column is placed in that position. The piece 13b is brought in and placed on the lower stopper 10, and in the same way, the upper end of the steel column piece 13b and the lower end of the upper steel column body 12 are joined, and then the steel frame pieces 13a and 13b are joined. As shown in FIG. 4, the second stage steel column body 13 is
The steel column 13 of the second stage is added to the upper steel column 12.

次に、地上1まで垂れ下げたワイヤロー77の先端のフ
ック9を上記継ぎ足した2段目の鉄骨柱体13の下端に
係止させ、第5図に示す如く、ウインチ6を巻き取り駆
動させて、ワイヤロー17を介しフック9を上昇させる
ことにより上記鉄骨柱体13を基礎柱2をガイドとして
上昇させ、上記継ぎ足した鉄骨柱体12と13を一体と
してリフトアップさせる。上記2段目の鉄骨柱体13の
下端が基礎柱2の上部ストツパ11a,11b取付位置
よりも高い位置までリフトアップされると、この位置で
基礎柱2に片方の上部ストツパ11bを取り付け、該上
部ストツパ11b上に上記鉄骨柱体13の下端を降して
支持させ、フック9を鉄骨柱体13の下端より外して再
び地上1の近くまで下げておくようにする。
Next, the hook 9 at the tip of the wire row 77 hanging down to the ground level 1 is locked to the lower end of the added second stage steel column 13, and as shown in FIG. 5, the winch 6 is wound and driven. By raising the hook 9 via the wire row 17, the steel column 13 is raised using the foundation column 2 as a guide, and the joined steel columns 12 and 13 are lifted up as one. When the lower end of the second stage steel column 13 is lifted up to a position higher than the upper stopper 11a, 11b attachment position of the foundation column 2, one of the upper stoppers 11b is attached to the foundation column 2 at this position. The lower end of the steel column 13 is lowered and supported on the upper stopper 11b, and the hook 9 is removed from the lower end of the steel column 13 and lowered again to near the ground 1.

しかる後、第6図に示す如く、2つ割れとした鉄骨柱片
13a,13bからなる次の段の鉄骨柱体13を用意し
、上述した作業手順と同様な作業手順で、順次上段に位
置する鉄骨柱体13に下段の鉄骨柱体13を接合する作
業とこれらをリフトアップする作業とを行い、順次鉄骨
柱体13を長手方向に所定段数継ぎ足すことにより第7
図に示す如く、地上1に所定高さの鉄骨柱14を上部よ
り下部へと構築して行き、最後に、最下部に最下段の鉄
骨柱体13を基礎柱2の周りに組み込んで、基礎柱2を
残したまま鉄骨柱14を構築する。
Thereafter, as shown in Fig. 6, the next stage of the steel column body 13 consisting of the two pieces of steel column pieces 13a and 13b is prepared, and the steel column pieces 13a and 13b are successively placed in the upper stage using the same procedure as described above. The lower steel column 13 is joined to the lower steel column 13 and the lower steel column 13 is lifted up, and a predetermined number of steps are sequentially added to the steel column 13 in the longitudinal direction.
As shown in the figure, steel columns 14 of a predetermined height are constructed on the ground 1 from the top to the bottom, and finally, the lowest steel column body 13 is assembled around the foundation column 2 at the bottom, and the foundation A steel frame column 14 is constructed while leaving column 2.

このように、本発明においては、鉄骨柱体13を、地上
1に立てた基礎柱2をガイドとして順次リフトアップさ
せて継ぎ足して行くようにするので、風等の影響を受け
ることなく安全に鉄骨柱14を構築することができる。
In this way, in the present invention, the steel frame columns 13 are sequentially lifted up and added using the foundation columns 2 erected on the ground 1 as a guide, so the steel frames can be safely installed without being affected by wind etc. Pillars 14 can be constructed.

したがって、本発明の方法を塔状建築物の建屋構造体を
構築する作業に採用すると、大型クレーンや大型の作業
足場を不要にできると共に、施工期間を短くすることが
できるようになる。
Therefore, when the method of the present invention is employed in the work of constructing the building structure of a tower-like building, it becomes possible to eliminate the need for large cranes and large-scale work scaffolding, and to shorten the construction period.

本発明の方法を採用して塔状建築物の建屋構造体を構築
する場合の作業手順の概要は第8図乃至第12図に示す
如くである。すなわち、先ず、第8図に示す如く、地上
1に前記と同様に上下にストツパHa,llbと10を
有する少なくとも2本の基礎柱2を立設し、次いで、第
9図に示す如く、該各基礎柱2の数に対応する数の上部
鉄骨柱体12に梁やトラス等の構造材15を取り付けて
上部鉄骨構造体16を構或し、この上部鉄骨構造体16
をクレーンで吊って上記鉄骨柱体12の下端部を基礎柱
2上に嵌め、上部ストツパ11a,fib上に支持させ
る。次いで、第10図に示す如く、各基礎柱2部に、前
記した第3図及び第4図について説明したと同様に2つ
割れ構造としてある鉄骨柱片13aと13bをそれぞれ
配置して、鉄骨社片13aと13bを片方ずつ上段に位
置する上部鉄骨構造体16の上部鉄骨柱体12の下端に
接合すると共に、鉄骨柱片13a,13b同士も接合し
た後、第11図に示す如く下段の〈2段目の〉鉄骨柱体
13間にも構造考A15を取り付けて2段目の鉄骨構造
体17を構戊する。しかる後、一体化させた鉄骨構造体
16.17を前記した第5図の場合と同様に1段分リフ
トアップさせ、以後、同様な作業手順で下段の鉄骨構造
体17の継き′足し作業とリフトアップ作業とを順次行
うことにより、第12図に示寸知く、地上1に所定高さ
の建屋構造体18を構築寸る。
The outline of the work procedure when constructing the building structure of a tower-shaped building by employing the method of the present invention is as shown in FIGS. 8 to 12. That is, first, as shown in FIG. 8, at least two foundation columns 2 having upper and lower stoppers Ha, Ilb and 10 are erected on the ground 1 in the same manner as described above, and then, as shown in FIG. An upper steel structure 16 is constructed by attaching structural members 15 such as beams and trusses to upper steel columns 12 in a number corresponding to the number of foundation columns 2.
is lifted by a crane, the lower end of the steel column 12 is fitted onto the foundation column 2, and supported on the upper stoppers 11a and fib. Next, as shown in FIG. 10, steel column pieces 13a and 13b having a two-piece structure are respectively arranged on the two parts of each foundation column in the same manner as explained in FIGS. 3 and 4 above, and the steel frame After joining the steel frame pieces 13a and 13b one by one to the lower end of the upper steel column body 12 of the upper steel frame structure 16 located at the upper level, and also joining the steel frame pieces 13a and 13b to each other, as shown in FIG. <Second tier> Structural considerations A15 are also attached between the steel frame columns 13 to construct the second tier steel structure 17. Thereafter, the integrated steel structures 16 and 17 are lifted up one level in the same manner as in the case of FIG. By sequentially performing the lift-up work and the lift-up work, a building structure 18 of a predetermined height above the ground 1 is constructed as shown in FIG. 12.

なお、本発明は上記実施例にのみ限定されるものではな
く、鉄骨柱体12.13をリフトアップさせるための手
段としては、ウインチ6による場合以外に、たとえば、
ジャッキやシリンダ等を用いるようにしてもよいこと、
又、実施例では、本発明の方法を塔状建築物の建屋構造
体18を構築する作業に採用して上部鉄骨構造体16に
各段の鉄骨構造体17を継ぎ足してリフトアップさせる
場合を示したが、他の構造物をリフトアップさせながら
継ぎ足して行く場合にも採用できること、更に、前記の
各実施例では、基礎柱2に下端部に下部ストツパ10を
固定して、この上に、継ぎ足すべき2つ割れ構造とした
鉄骨柱片13a,13bを戟せて支持させる場合を示し
たが、これに代えて、地上に固定台を設置し、この固定
台の上面をストツパとして使用できるようにし、最下段
の鉄骨柱体13を組み込んだとき、該鉄骨柱体13を固
定台にボルトなどで固定させるようにしてもよいこと、
その他本発明の要旨を逸脱しない範囲内において種々変
更をDIえ得ることは勿論である。
It should be noted that the present invention is not limited to the above-mentioned embodiments, and means for lifting up the steel column bodies 12, 13 may include, for example, other than the winch 6.
that jacks, cylinders, etc. may be used;
Further, in the embodiment, a case is shown in which the method of the present invention is applied to the work of constructing the building structure 18 of a tower-like building, and each stage of the steel structure 17 is added to the upper steel structure 16 to lift it up. However, it can also be used when adding parts while lifting up other structures.Furthermore, in each of the above embodiments, the lower stopper 10 is fixed to the lower end of the foundation column 2, and the parting material is placed on top of the lower stopper 10. The case where the steel frame column pieces 13a and 13b with the two-piece structure to be added are supported by turning them is shown, but instead of this, it is possible to install a fixed stand on the ground and use the top surface of this fixed stand as a stopper. and when the lowermost steel column 13 is installed, the steel column 13 may be fixed to a fixing base with bolts or the like;
It goes without saying that various other changes may be made within the scope of the invention.

[発明の効果1 以上jボベた如く、本発明の鉄骨柱の構築方法によれば
、鉄骨柱体を地上に立てた基礎柱をカイドとしてリフト
アップさせた後、その下端に次段の鉄骨柱体を継ぎ足し
、しかる後、該継ぎ足した下段の鉄骨柱休を同様にリフ
トアップさせ、以後、同様な作業を繰り返して行き鉄骨
社を上部から下部へ構戒して行くようにするので、風等
の影響を受けることなく安全に鉄骨社を構築でき、従来
用いていた大型クレーンの使用を不要にできると共に、
塔状建築物の建屋構造体の如き構造物の構築作業に採用
しても同様に地上で組んで上昇させて構築できて、作業
足場を利用しての高所作業を行うことなく能率よく短期
間に構造物の構造を行うことができるようになる、等の
優れた効果を発揮する。
[Effect of the invention 1 As described above, according to the steel column construction method of the present invention, after lifting up a foundation column with a steel column body erected on the ground as a guide, the next stage steel column is attached to the lower end of the foundation column. After adding the body, lift up the added lower steel frame column in the same way, and repeat the same operation from now on so that the steel frame column is guarded from the top to the bottom, so that wind etc. It is possible to safely construct a steel frame without being affected by
Even if it is used in the construction work of structures such as tower-like building structures, it can be assembled on the ground and raised, and can be constructed efficiently and in a short period of time without having to work at heights using scaffolding. It exhibits excellent effects such as being able to construct structures in between.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第7図は本発明の鉄骨社の構築方法の一実施
例を示す作業手順の概要図、第8図乃至第12図は本発
明の方法を採用して塔状建築物の建@構造体を構築する
場合の一例を示す作業手順の概要図である。 1・・・地上、2・・・基礎柱、4a,4b・・・シー
ブ、6・・・ウインチ、7・・・ワイヤ口ープ、10・
・・下部ストッパ、lla,1lb・・・上部ストツパ
、12・・・上部鉄骨柱体、13・・・下段の鉄骨柱体
、13a,13b・・・鉄骨柱片、14・・・鉄骨性、
15・・・構造材、16・・・上部鉄骨構造体、17・
・・下段の鉄骨構造体、18・・・建摩構造体。 第1図 第2図 第3図 第4図 第7図
Figures 1 to 7 are schematic diagrams of work procedures showing one embodiment of the method for constructing a steel frame building of the present invention, and Figures 8 to 12 are diagrams for constructing a tower-shaped building using the method of the present invention. FIG. 2 is a schematic diagram of a work procedure illustrating an example of constructing an @ structure. 1... Ground, 2... Foundation pillar, 4a, 4b... Sheave, 6... Winch, 7... Wire mouth, 10...
... Lower stopper, lla, 1lb... Upper stopper, 12... Upper steel column body, 13... Lower steel column body, 13a, 13b... Steel column piece, 14... Steel frame,
15... Structural material, 16... Upper steel structure, 17.
... Lower steel structure, 18... Kenma structure. Figure 1 Figure 2 Figure 3 Figure 4 Figure 7

Claims (3)

【特許請求の範囲】[Claims] (1)所要の長さとした筒状の鉄骨柱体を、地上に立設
した基礎柱をガイドとして該鉄骨柱体の長さと同じ高さ
分持ち上げ、次いで、該持ち上げた鉄骨柱体と地上との
間に2つ割れの鉄骨柱体を上記基礎柱を抱くように配し
た後、該2つ割れの鉄骨柱体を持ち上げた鉄骨柱体との
接合、2つ割れ鉄骨柱自体の接合を行つて継ぎ足し、し
かる後、上記継ぎ足した鉄骨柱体をほぼその高さ分持ち
上げ、以後同様な作業を繰り返して所定高さの鉄骨柱を
構築することを特徴とする鉄骨柱の構築方法。
(1) Lift a cylindrical steel column of the required length to a height equal to the length of the steel column using a foundation column erected on the ground as a guide, and then connect the lifted steel column to the ground. After arranging the two-split steel column so as to hold the foundation column between them, the two-split steel column is joined to the lifted steel column, and the two-split steel column itself is joined. A method for constructing a steel frame column, which comprises: adding a steel frame column to a predetermined height, and then lifting the added steel column body by approximately the same height, and thereafter repeating the same operation to construct a steel column of a predetermined height.
(2)鉄骨柱体の持ち上げを、基礎柱上のシーブにかけ
て先端を該鉄骨柱体に係止させたワイヤロープを巻き取
ることにより行う請求項(1)に記載の鉄骨柱の構築方
法。
(2) The method for constructing a steel frame column according to claim (1), wherein the steel frame column is lifted by winding up a wire rope whose tip is secured to the steel frame column by passing it through a sheave on the foundation column.
(3)地上に少なくとも2本の基礎柱を立て、少なくと
も2本の鉄骨柱体を用いて構築した鉄骨構造体を上記基
礎柱をガイドとして持ち上げた後継ぎ足して行く請求項
(1)に記載の鉄骨柱の構築方法。
(3) The method according to claim (1), wherein at least two foundation columns are erected on the ground, and the steel frame structure constructed using at least two steel columns is lifted up using the foundation columns as a guide and then added to the subsequent structure. How to construct a steel column.
JP15445889A 1989-06-19 1989-06-19 Construction method of iron-frame pillar Pending JPH0321777A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15445889A JPH0321777A (en) 1989-06-19 1989-06-19 Construction method of iron-frame pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15445889A JPH0321777A (en) 1989-06-19 1989-06-19 Construction method of iron-frame pillar

Publications (1)

Publication Number Publication Date
JPH0321777A true JPH0321777A (en) 1991-01-30

Family

ID=15584674

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15445889A Pending JPH0321777A (en) 1989-06-19 1989-06-19 Construction method of iron-frame pillar

Country Status (1)

Country Link
JP (1) JPH0321777A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0518132A (en) * 1991-07-12 1993-01-26 M Ii C Eng Service Kk Jack-up type construction method for steel structure such as tower type stereoscopic parking lot
US8240051B2 (en) * 2008-05-07 2012-08-14 Babcock & Wilcox Power Generation Group, Inc. Method for erection of a solar receiver and support tower
CN106996196A (en) * 2017-05-19 2017-08-01 中国五冶集团有限公司 A kind of large diameter pipeline integral hoisting construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0518132A (en) * 1991-07-12 1993-01-26 M Ii C Eng Service Kk Jack-up type construction method for steel structure such as tower type stereoscopic parking lot
US8240051B2 (en) * 2008-05-07 2012-08-14 Babcock & Wilcox Power Generation Group, Inc. Method for erection of a solar receiver and support tower
CN106996196A (en) * 2017-05-19 2017-08-01 中国五冶集团有限公司 A kind of large diameter pipeline integral hoisting construction method

Similar Documents

Publication Publication Date Title
JP2016145477A (en) Demolition system and demolition method
JPH09302919A (en) Transfer platform for columnar body
JPH0321777A (en) Construction method of iron-frame pillar
JPH10140872A (en) Roof constructing method for tower structure
JP2618171B2 (en) Telescopic strut
JP3532161B2 (en) Tower construction machine and tower construction method
JPH09177070A (en) Method and device for placing of steel bar cage for deep foundation
JPH06101348A (en) Method for constructing tower
JP6950041B1 (en) Structure dismantling system and structure dismantling method
JP2704446B2 (en) Lift-up method using temporary columns
JPH10152981A (en) Vertically moving scaffold
JPH0718743A (en) Construction method for large span domelike roof
JP3230012B2 (en) Building construction equipment
JP3785742B2 (en) Steel tower construction method for steel tower supported chimney
JPH05263531A (en) Automatic construction method and lifting-up device of structure
JP2023131474A (en) Steel tower disassembling and assembling device, steel tower disassembling method, and steel tower assembling method
JP3021199B2 (en) Construction method of chimney inner cylinder and pull jack up device for the construction
JP2796448B2 (en) Building construction method and building construction equipment used for the construction method
JP2572642B2 (en) Scaffolding disassembly method
JPH0827903A (en) All weather type building method
JP2021038645A (en) Tent setting method
JPH1037527A (en) Method for constructing inner and outer cylinder of chimney simultaneously
JP2843042B2 (en) Steel framing unit scaffolding method
JP2687000B2 (en) Jib crane assembly equipment
JPH03212564A (en) Jacking up method and device