Construction of sheathing and cut-off wall

Info

Publication number
JPH03217515A
JPH03217515A JP980390A JP980390A JPH03217515A JP H03217515 A JPH03217515 A JP H03217515A JP 980390 A JP980390 A JP 980390A JP 980390 A JP980390 A JP 980390A JP H03217515 A JPH03217515 A JP H03217515A
Authority
JP
Japan
Prior art keywords
constructed
piles
ground
underground
vertical holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP980390A
Other languages
Japanese (ja)
Other versions
JPH0541766B2 (en
Inventor
Chikashi Kusumoto
楠本 千賀志
Teruyoshi Baba
馬場 照世志
Yutaka Tanaka
裕 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP980390A priority Critical patent/JPH03217515A/en
Publication of JPH03217515A publication Critical patent/JPH03217515A/en
Publication of JPH0541766B2 publication Critical patent/JPH0541766B2/ja
Granted legal-status Critical Current

Links

Abstract

PURPOSE:To make execution of work easy by a method wherein vertical holes are drilled into the ground, then mud columns are constructed with bentonite milk poured therein and agitated there and after erecting underground piles, soil mortar columns are constructed with cement milk poured therein and agitated there. CONSTITUTION:Vertical holes 1, 2, 3 are drilled into the ground with a triple- shafted earth auger. Mud columns are then constructed in the vertical holes 1, 2, 3 with slow-hardening bentonite milk injected into the holes and agitated there. Underground piles 4 are erected in every other or in every third vertical holes 1, 2, 3. Installation intervals of the underground piles 4 depend on the scale of a sheathing and cut-off wall to be constructed. In the case where the ground is hard, the installation intervals can be extended so that the materials can be saved, requiring less piles. Mortar piles 5 are then constructed between the underground piles 4 with materials containing cement milk injected with a boring machine by high-pressure jet agitation method. Thereby water stop works can be executed without fail.

Description

【発明の詳細な説明】 〔産業上の利用分野] この発明は土留め止水壁の施工方法に関するものである
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method of constructing an earth retaining water-stop wall.

(従来の技術及び解決しようとする課題〕従来、土留め
止水璧の施工方法として三軸オカーを使用したいわゆる
SMW工法が一般に知られている。
(Prior Art and Problems to Be Solved) Conventionally, the so-called SMW construction method using a triaxial drill is generally known as a construction method for earth retaining and water stop walls.

この種の施工方法は三軸オーガーを使用して地盤に縦孔
を削孔し、続いて当該縦孔内にベントナイトセメントミ
ルクを注入撹拌してソイルモルタルを作り、その中にH
鋼等の地中杭を立て込んで土留め壁を連続的に施工する
ものである。
This type of construction method uses a triaxial auger to drill a vertical hole in the ground, then injects and stirs bentonite cement milk into the vertical hole to create a soil mortar.
An earth retaining wall is constructed continuously using underground piles made of steel or other materials.

ところで、この施工方法を橋桁の下等のような上に障害
物がある場所で行おうとすると、大型三軸オーガーの使
用が困難となる。
By the way, if this construction method is attempted in a place where there are obstacles above, such as under a bridge girder, it will be difficult to use a large three-shaft auger.

この為、小型の三軸オ−ガー機を使用せざるを得す、ま
た土留壁が深い場合には土留の深さに応してオーガーを
適宜継ぎ足す必要かあり、さらに、ガード下等の作業は
列車の往来のない夜間帯を利用して行う必要がある為、
作業性が著しく低下し、一区画の施工が数日に及ぶこと
がよくある。
For this reason, it is necessary to use a small three-shaft auger machine, and if the retaining wall is deep, it is necessary to add more augers depending on the depth of the retaining wall. The work must be carried out at night when there is no train traffic, so
Work efficiency is significantly reduced, and construction of a single section often takes several days.

ところが、この施工にはヘントナイト泥水として比較的
硬化の早いベントナイトセメントミルクが使用される為
、施工が数日にも及ぶと地中杭の立て込みが出来なくな
ってしまうことがある。
However, because bentonite cement milk, which hardens relatively quickly, is used in this construction, it may become impossible to drive underground piles if the construction lasts several days.

この発明はこのような前記従来の課題を解消する為に提
案されたもので、地盤中の縦孔にヘントナイトミルク製
造後、数日経過してもH形鋼等の地中杭をM無く立て込
むことが可能な土留め止水壁の施工方法を提供すること
を目的とするものである。
This invention was proposed in order to solve the above-mentioned conventional problems, and it is possible to install underground piles such as H-section steel without M even after several days have passed after producing hentonite milk in a vertical hole in the ground. The purpose of the present invention is to provide a construction method for an earth-retaining water-stop wall that can be built up.

〔課題を解決する為の手段〕[Means to solve problems]

この発明は土留め止水壁の施工方法に関するもので、地
盤中に縦孔を削孔し、続いて当該縦孔内にヘントナイト
ミルクを注入攪拌して泥土柱を施工し、続いて前記縦孔
内に複数本の地中杭を立て込み、続いて前記地中杭間に
セメントミルクを注入攪拌してソイルモルタル柱を施工
することにより前記目的を達成するものである。
This invention relates to a method for constructing an earth retaining water cutoff wall, in which a vertical hole is drilled in the ground, then hentonite milk is poured into the vertical hole and stirred to construct a mud pillar, and then a mud column is constructed in the vertical hole. The above object is achieved by driving a plurality of underground piles into the hole, then pouring and stirring cement milk between the underground piles and constructing a soil mortar column.

〔実施例] 以下、この発明を図示する一実施例に基づいて説明する
[Example] The present invention will be described below based on an illustrative example.

:軸オーガーによって地盤中に図のように紀孔1、2、
3をこの順序で削孔する。
: Holes 1, 2, and 2 are drilled into the ground by the shaft auger as shown in the figure.
Drill holes 3 in this order.

かかる場合、削孔及びミキシングに用いる注入材には比
較的硬化の遅いベントナイトミルクを使用する。
In such cases, bentonite milk, which hardens relatively slowly, is used as the injection material for drilling and mixing.

尚、ヘントナイトミルクは工事日程に応して、材料の調
合を適当に変えることにより硬化時間を調整するものと
する。
The curing time of the hentonite milk shall be adjusted by appropriately changing the mixture of materials according to the construction schedule.

縦孔3の削孔が終了したら、縦孔1、2、3に1つおき
乃至2つおきに地中杭4,4を立て込む。
After drilling of the vertical holes 3 is completed, underground piles 4, 4 are driven into every other or every two vertical holes 1, 2, and 3.

尚、地中杭4には原則としてH形鋼を使用するものとす
るが、ほかにI形鋼を使用しても良い。
In principle, H-section steel is used for the underground pile 4, but I-section steel may also be used.

また、地中杭4の設置間隔は土留め止水壁の規模によっ
て異なるが、深くて軟弱地盤の場合には設置間隔を狭く
且つ多く立て込むことにより強度を高め、逆に浅くて硬
質地盤の場合には設置間隔を広く且つ少なめに立て込む
ことにより材料の節約を回るものとる。
In addition, the installation interval of the underground piles 4 varies depending on the scale of the earth retaining water cutoff wall, but in the case of deep and soft ground, the strength is increased by narrowing the installation interval and increasing the number of installations, and conversely, in the case of shallow and hard ground In some cases, it is possible to save material by widening the installation interval and making the installation space a little smaller.

地中杭4の立て込みが終了したら紹孔1、2及び3に立
て込まれた地中杭4と4との間にボノングマシンを用い
て注入材にセメントミルクを用いた高圧ジェット撹拌工
法によってモルタル抗5を施工する。
After the installation of the underground piles 4 is completed, mortar is placed between the underground piles 4 and 4 installed in the introduction holes 1, 2, and 3 using a Bonong machine using a high-pressure jet stirring method using cement milk as the injection material. Construct resistor 5.

モルタル抗5は左右地中杭4,4の溝部4a,4 aに
確実に達するように施工する。
The mortar shaft 5 is constructed so as to surely reach the grooves 4a, 4a of the left and right underground piles 4,4.

以下、同様な方法で地中連続壁を連続的に施工する。Thereafter, underground walls will be constructed continuously using the same method.

尚、注入材にはセメントミルク以外に薬液注入材の使用
が可能である。
Note that, in addition to cement milk, a chemical injection material can be used as the injection material.

〔発明の効果〕〔Effect of the invention〕

この発明は以上の構成からなるので以下の効果を有する
Since the present invention has the above configuration, it has the following effects.

■ この発明に係る土留め止水璧の施工方法は基本的に
は従来のS M W工法と同しであるが、縦孔内Cこ最
初Cこ注入撹拌するのは、硬化の早いセメントミルクで
はなく、比較的硬化の遅いベントナイトミルクである為
、数日経過後でも縦孔内に地中杭を簡単に立て込むこと
ができる。
■ The construction method of the earth retaining water stop wall according to this invention is basically the same as the conventional SMW construction method, but the method of injecting and stirring the fast-hardening cement milk into the vertical hole is C. Instead, bentonite milk hardens relatively slowly, so underground piles can be easily driven into vertical holes even after several days have passed.

また、地中杭の立て込み後、H形ロ間にセメントミルク
を用いた高圧ジェyトPA拌工法でソイルモルタル柱を
連続的に施工する為、止水施工も確実に行うことができ
る。
In addition, after installing the underground piles, soil mortar columns are continuously constructed using the high-pressure jet PA stirring method using cement milk between the H-shaped holes, making it possible to reliably perform water-stop construction.

したがって、ガード下等といった、数日にまたがって施
工せざるを得ないような場所においても容易に施工する
ことができる。
Therefore, the construction can be easily carried out even in places such as under a guard where construction must be carried out over several days.

【図面の簡単な説明】[Brief explanation of drawings]

図はこの発明にかかる土留め止水壁の施工方法を示す平
面図である。 1,2.3・・・樅孔、4・・・地中杭、5・・・モル
タル杭。
The figure is a plan view showing a method of constructing an earth retaining water stop wall according to the present invention. 1, 2. 3...Fir hole, 4...Underground pile, 5...Mortar pile.

Claims (1)

【特許請求の範囲】[Claims] (1)地盤中に縦孔を削孔し、続いて当該縦孔内にベン
トナイトミルクを注入撹拌して泥土柱を施工し、続いて
前記縦孔内に複数本の地中杭を立て込み、続いて前記地
中杭間にセメントミルクを注入撹拌してソイルモルタル
柱を施工することを特徴とする土留め止水壁の施工方法
(1) Drill a vertical hole in the ground, then inject and stir bentonite milk into the vertical hole to construct a mud column, and then drive a plurality of underground piles into the vertical hole, A method for constructing an earth retaining and water-stopping wall, which comprises subsequently injecting and stirring cement milk between the underground piles and constructing soil mortar columns.
JP980390A 1990-01-19 1990-01-19 Construction of sheathing and cut-off wall Granted JPH03217515A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP980390A JPH03217515A (en) 1990-01-19 1990-01-19 Construction of sheathing and cut-off wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP980390A JPH03217515A (en) 1990-01-19 1990-01-19 Construction of sheathing and cut-off wall

Publications (2)

Publication Number Publication Date
JPH03217515A true JPH03217515A (en) 1991-09-25
JPH0541766B2 JPH0541766B2 (en) 1993-06-24

Family

ID=11730349

Family Applications (1)

Application Number Title Priority Date Filing Date
JP980390A Granted JPH03217515A (en) 1990-01-19 1990-01-19 Construction of sheathing and cut-off wall

Country Status (1)

Country Link
JP (1) JPH03217515A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013127189A (en) * 2011-12-19 2013-06-27 Takenaka Komuten Co Ltd Lattice ground improvement body, impervious wall, and construction method for the same

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS524846A (en) * 1975-06-13 1977-01-14 Hoechst Ag Device for electrostatically charging recording material
JPS59145821A (en) * 1983-02-09 1984-08-21 Sanwa Kizai Co Ltd Method and apparatus for construction of pillar-row pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS524846A (en) * 1975-06-13 1977-01-14 Hoechst Ag Device for electrostatically charging recording material
JPS59145821A (en) * 1983-02-09 1984-08-21 Sanwa Kizai Co Ltd Method and apparatus for construction of pillar-row pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013127189A (en) * 2011-12-19 2013-06-27 Takenaka Komuten Co Ltd Lattice ground improvement body, impervious wall, and construction method for the same

Also Published As

Publication number Publication date
JPH0541766B2 (en) 1993-06-24

Similar Documents

Publication Publication Date Title
US5378085A (en) Methods for in situ construction of deep soil-cement structures
JPH10325138A (en) Method for constructing earth retaining wall and earth auger device
US20020071725A1 (en) Earth support and permanent structural foundation wall
KR100415809B1 (en) precast pile for braced wall and the method using the same
US6241426B1 (en) Method for forming an interconnected underground structure
JPH08311864A (en) Earth retaining wall and construction method therefor
JPH03217515A (en) Construction of sheathing and cut-off wall
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
RU2209267C1 (en) Process of earth fixing
JPH0978571A (en) Execution method for soil cement pile
JP2698768B2 (en) Method of forming underground continuous wall
JPH0734449A (en) Self standing type landslide protection wall construction method
JPS58120918A (en) Burying method for pile
JP2020143467A (en) Construction method of earth retaining wall
JPH0351415A (en) Constructing method for underground continuous wall
RU2204656C1 (en) Process of erection of enclosing wall in ground
JPS626049B2 (en)
JPS6117973B2 (en)
JP2001164550A (en) Improvement method of construction ground for underground structure
JPH0336370B2 (en)
JPS5972319A (en) Underground continuous wall work utilizing soil pillar-row wall
JPH018587Y2 (en)
JPH0442493B2 (en)
JP2601140B2 (en) Independent mountain retaining wall method
JPS63247423A (en) Underground continuous wall usable as structure base and its construction