JPS63247423A - Underground continuous wall usable as structure base and its construction - Google Patents

Underground continuous wall usable as structure base and its construction

Info

Publication number
JPS63247423A
JPS63247423A JP7958987A JP7958987A JPS63247423A JP S63247423 A JPS63247423 A JP S63247423A JP 7958987 A JP7958987 A JP 7958987A JP 7958987 A JP7958987 A JP 7958987A JP S63247423 A JPS63247423 A JP S63247423A
Authority
JP
Japan
Prior art keywords
tube
underground continuous
concrete
steel
injected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7958987A
Other languages
Japanese (ja)
Other versions
JPH0511166B2 (en
Inventor
Toshiyuki Ujiie
Yoshikiyo Fukushima
Original Assignee
Seiko Kogyo Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seiko Kogyo Kk filed Critical Seiko Kogyo Kk
Priority to JP7958987A priority Critical patent/JPH0511166B2/ja
Publication of JPS63247423A publication Critical patent/JPS63247423A/en
Publication of JPH0511166B2 publication Critical patent/JPH0511166B2/ja
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PURPOSE: To effectively utilize the area of construction site by a method in which various shapes of steel materials as stress supports are driven until they reach the bearing ground or its neighbor of the main part of a underground continuous wall and their lower ends are fixed to permit the foundation of a structure to be supported.
CONSTITUTION: An underground continuous wall is constructed with the process as follows: i.e. while the ground is excavated, cement milk, etc., is injected to fill the excavated pit with soil cement 12, and a square steel tube 3, together with H-steel 2, is driven into the pit and its head is struck until its lower end reaches the bearing ground 13, or, cement milk 7 is injected to the lower part of the tube 3 to form a concrete block. The upper soil cement 12 in the tube 3 may be drawn out and substituted with concrete, and reinforcing materials are set and connected with the superstructure. A concrete wall 6 is then constructed in close contact with the wall 1 along the inside of the tube 3, and a column 8 and a beam 7 are set in the inside space.
COPYRIGHT: (C)1988,JPO&Japio
JP7958987A 1987-04-02 1987-04-02 Expired - Lifetime JPH0511166B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7958987A JPH0511166B2 (en) 1987-04-02 1987-04-02

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7958987A JPH0511166B2 (en) 1987-04-02 1987-04-02

Publications (2)

Publication Number Publication Date
JPS63247423A true JPS63247423A (en) 1988-10-14
JPH0511166B2 JPH0511166B2 (en) 1993-02-12

Family

ID=13694181

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7958987A Expired - Lifetime JPH0511166B2 (en) 1987-04-02 1987-04-02

Country Status (1)

Country Link
JP (1) JPH0511166B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08284152A (en) * 1995-04-12 1996-10-29 Sumikin Kozai Kogyo Kk Reinforcements for soil cement continuous underground wall
CN106968257A (en) * 2017-03-09 2017-07-21 中国建筑第八工程局有限公司 The concrete assembled shaped steel mixing support system of super-sized foundation pit and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08284152A (en) * 1995-04-12 1996-10-29 Sumikin Kozai Kogyo Kk Reinforcements for soil cement continuous underground wall
CN106968257A (en) * 2017-03-09 2017-07-21 中国建筑第八工程局有限公司 The concrete assembled shaped steel mixing support system of super-sized foundation pit and its construction method

Also Published As

Publication number Publication date
JPH0511166B2 (en) 1993-02-12

Similar Documents

Publication Publication Date Title
JPH0393923A (en) Connection method of steel pillar of cast-in-place pile and connection structure
JPS63247423A (en) Underground continuous wall usable as structure base and its construction
JPS55159024A (en) Construction method for structure foundation
JPS59126821A (en) Erection work of foundation pile
JPS615125A (en) Foundation of building
JPS6397712A (en) Soil cement composite pile
JPS62268423A (en) Construction work of underground pile used in common for earth anchor
JPS56111725A (en) Constructing method for strip footing by using existing concrete pile
JPS641826A (en) Lay-out method of wide-headed pile
JPH01250541A (en) Construction of main structural column
JPH04131428A (en) Construction of underground structure
JPS61254716A (en) Setting of in-place concrete pile
JPH03202511A (en) Liquefaction-proof construction
JPH0376929A (en) Steel-framed foundation
RU28499U1 (en) Enclosing wall
JPS6272822A (en) Construction work of underground structure
JPS63176530A (en) Construction of foundation of underground continuous wall
JPS61266731A (en) Foundation formwork for column and its application
JPS62197526A (en) Trussed pile and its construction
JPH03132520A (en) Construction method of basement and column and beam joining body used therefor
JPS637416A (en) Construction of hollow concrete structure under ground
JPH03250112A (en) Continuous underground wall
JPS63280124A (en) Construction work for retaining wall
JPS61261527A (en) Side wall structure for round underground type structure
JPH0381500A (en) Method for constructing big space for building in great depth underground