JPH026896A JP6679388A JP6679388A JPH026896A JP H026896 A JPH026896 A JP H026896A JP 6679388 A JP6679388 A JP 6679388A JP 6679388 A JP6679388 A JP 6679388A JP H026896 A JPH026896 A JP H026896A
Authority
JP
Japan
Prior art keywords
plates
slab
septic tank
version
laid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6679388A
Other languages
Japanese (ja)
Inventor
Isao Ito
勲 伊藤
Motomu Suekata
末方 求
Eiichi Hotta
堀田 栄一
Yoshiaki Koishihara
小石原 義明
Hideo Murayama
村山 秀生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ISUZU SHOKAI KK
TAISEI PREFAB KK
Inax Corp
Original Assignee
ISUZU SHOKAI KK
TAISEI PREFAB KK
Inax Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ISUZU SHOKAI KK, TAISEI PREFAB KK, Inax Corp filed Critical ISUZU SHOKAI KK
Priority to JP6679388A priority Critical patent/JPH026896A/en
Publication of JPH026896A publication Critical patent/JPH026896A/en
Pending legal-status Critical Current

Links

Landscapes

  • Treatment Of Biological Wastes In General (AREA)

Abstract

PURPOSE:To allow the easy execution of operations by making factory production of lower slab plates, lower stand plates, upper stand plates, and upper slab plates in such a manner that these plates can be assembled respectively separately. CONSTITUTION:The lower slab plates 1, 2, the lower stand plates 3, the upper stand plates 4, and the upper slab plates 5, 6 are respectively separately produced in a factory and, therefore, these members can be accurately produced under strict quality control and be carried to site. The lower slab plates 1, 2 are laid on the base side of a burying ditch on site and the lower stand plates 3 are erected atop these plates. The cleaning tank C is mounted on the receiving surfaces 3a of the plates 3 and further, the receiving surfaces 4a of the upper stand plates 4 are mated and integrated with the surfaces 3a. The tank C is fixed by the plates 3 and the plates 4. The upper slab plates 5, 6 are laid atop the plates 4. The tank C or the like is installed to the rear surface side of the plates 5, 6 in the well buried state in such a manner and the operations thereof are extremely easily carried out.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、浄化槽等の地下埋設物を地中に埋設状に設
置するための設置構造に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to an installation structure for installing an underground object such as a septic tank underground.

(従来技術及びその問題点) 従来、床法わト水と生活排水とを同時に浄化処理するこ
とのできる浄化槽等を地中に埋設状に設置するにあたり
、例えば第2図に示すように、地面の所定位置に埋設溝
Hを構築し、その埋設溝Hの底面に砂利又はコンクリー
ト等により基礎部Kを形成し、その基礎部にの上面側に
スラブ版51を敷設し、スラブ版51の側面側に沿って
支持ベース54を配設するとともに、スラブ版51の上
面側には分割可rlとな一対の架台52.53を固定さ
せて、この架台52.53上に円筒状の浄化槽Cを設置
し、この浄化槽Cの側面側の前記支持ベース54.54
上に補強柱55.55を立設させ、この補強柱55.5
5の上面側に鉄筋コンクリート等により上部スラブ56
を形成させ、この上部スラブ56の上面が地表に露出し
て、例えは駐車場等を構成することができ、浄化槽Cの
マンホールCaがこの上部スラブ56に突出して設置さ
れる。
(Prior art and its problems) Conventionally, when installing a septic tank or the like underground that can purify water and household wastewater at the same time, for example, as shown in Figure 2, A buried groove H is constructed at a predetermined position, a foundation part K is formed at the bottom of the buried groove H with gravel or concrete, etc., a slab version 51 is laid on the upper surface side of the foundation part, and the side surface of the slab version 51 is A support base 54 is arranged along the side, and a pair of splittable frames 52.53 are fixed to the upper surface side of the slab version 51, and a cylindrical septic tank C is mounted on these frames 52.53. Install the support base 54, 54 on the side of this septic tank C.
A reinforcing column 55.55 is erected above, and this reinforcing column 55.5
Upper slab 56 is made of reinforced concrete etc. on the upper surface side of 5.
The upper surface of the upper slab 56 is exposed to the ground surface to form a parking lot, for example, and the manhole Ca of the septic tank C is installed so as to protrude from the upper slab 56.

このような従来の設置構造においては、基礎部K及びス
ラブ版51.支持ヘース54.補強柱55及び上部スラ
ブ56等を現場にてコンクリートの7M込方法により構
築するものであるため、現場においてコンクリート打作
業が必要となり、浄化槽Cを設置するための前作業が多
く、相当の工期を必要とし、又、基礎部K及びスラブ版
51等の強度を十分に確保するために、流し込まれるコ
ンクリートの品質管理を厳重に行なう必要があり、土木
作業及び品質管理上に多大な労力を要するという問題点
があった。
In such a conventional installation structure, the foundation part K and the slab plate 51. Support heath54. Since the reinforcing columns 55, upper slab 56, etc. are constructed on site using the 7M concrete method, concrete pouring work is required on site, and there is a lot of pre-work to install the septic tank C, which takes a considerable amount of time. In addition, in order to ensure sufficient strength of the foundation part K and the slab 51, etc., it is necessary to strictly control the quality of the poured concrete, which requires a great deal of effort in terms of civil engineering work and quality control. There was a problem.

又、別途外部にて造形されたスラブ版51.支持ベース
54.補強柱55等を現場に持ち込んで浄化槽Cを設置
する場合においても部品点数が多く、それぞれの部材の
配置状態を良好に確保しなから構築する必要があり、現
場作業に多大な労力を要するという問題点があった。
In addition, a slab version 51. which is separately modeled externally. Support base 54. Even when the reinforcement columns 55 and the like are brought to the site and the septic tank C is installed, there are a large number of parts, and it is necessary to ensure the proper placement of each component before construction, which requires a great deal of labor on site. There was a problem.

(問題点を解決するだめの手段) 本発明は上記従来の問題点に鑑み案出したものであって
、簡易に浄化槽等を設置することのできる設置構造を提
供せんことを目的とし、その要旨は、構築された埋設置
mの底面側に敷設される下部スラブ版と、該下部スラブ
版上に立設され上方に開口状に形成された受け面に浄化
槽等を載置可能な下架台版と、該上架台版上に一体状に
立設され浄化槽等の上面部に当接し得る下方に開口した
受け面を有する上架台版と、該上架台版上に敷設される
上部スラブ版とを正体として構成され、前記下部スラブ
版、下架台版、上架台版、上部スラブ版がそれぞれ別体
にて組付可能に工場生産されたことである。
(Means for Solving the Problems) The present invention has been devised in view of the above-mentioned conventional problems, and its purpose is to provide an installation structure in which a septic tank or the like can be easily installed. consists of a lower slab slab to be laid on the bottom side of the constructed buried installation m, and a lower mounting frame on which a septic tank, etc. can be placed on the receiving surface which is erected on the lower slab slab and has an opening in the upper part. , an upper pedestal plate that is integrally erected on the upper pedestal plate and has a receiving surface that opens downward and can come into contact with the upper surface of the septic tank, etc., and an upper slab plate that is laid on the upper pedestal plate. The lower slab version, the lower mount version, the upper mount version, and the upper slab version are manufactured in a factory so that they can be assembled separately.

(作用) 下部スラブ版、下架台版、上架台版、上部スラブ版がそ
れぞれ別体にて工場生産されたものであるため、工場に
て厳格な品質管理のもとにこれらの部材を精度よく造形
して現場に運び込むことができ、現場にて埋設溝の底面
側に下部スラブ版を敷設し、その上面側に下架台版を立
設させて、この上架台版上に浄化槽等を截置させ、さら
に上架台版を下架台版に一体化させて、下架台版と上架
台版にて浄化槽を固定し、かつ上架台版の上面に上スラ
ブ版を敷設する工程により、上部スラブ版の下面側に良
好に埋設状に浄化槽等を設置することができ、その作業
が極めて簡易に行なえるものである。
(Function) Since the lower slab version, lower mount version, upper mount version, and upper slab version are manufactured separately in the factory, these parts are precisely manufactured under strict quality control at the factory. It can be shaped and transported to the site, where a lower slab slab is laid on the bottom side of the burial trench, a lower pedestal slab is erected on the top side, and a septic tank, etc. is cut on top of this upper pedestal slab. Then, the upper slab plate is integrated with the lower frame plate, the septic tank is fixed by the lower frame plate and the upper frame plate, and the upper slab plate is laid on the upper surface of the upper frame plate. A septic tank or the like can be installed in a well-buried manner on the lower surface side, and the work can be done very easily.

(実施例) 以下、本発明の一実施例を図面に基づいて説明する。(Example) Hereinafter, one embodiment of the present invention will be described based on the drawings.

第1図は浄化槽Cを各構成部材により設置した設置状態
の斜視図であり、図において、現場に構築された埋設溝
Hの底面側には予め砂利等により基礎部Kを形成してお
き、この基礎部にの上面側に一対の下部スラブ版1及び
2を敷設することができる。この下部スラブ版1,2は
PC版(プレキャストコンクリート版)にて工場生産さ
れたものであって、相当の長さを有する長方形状に形成
され、中央部に溝状の嵌合溝部1a、2aがそれぞれ形
成されている。
Fig. 1 is a perspective view of a septic tank C installed with each constituent member. A pair of lower slabs 1 and 2 can be laid on the upper side of this foundation. These lower slab plates 1 and 2 are factory-produced PC plates (precast concrete plates), and are formed into a rectangular shape with a considerable length, with groove-shaped fitting grooves 1a and 2a in the center. are formed respectively.

下部スラブ版1及び2が敷設された後に、この下部スラ
ブ版1,2上に複数の下架台版3,3゜3.3が適宜間
隔をおいて立設される。即ら、下部スラブ版1及び2の
嵌合溝部1a、2a内に上方より下架台版3の下面に突
設された嵌合突部3c l 3 C’、−rlff1人
さけて、下架台版3,3.3を立設することができる。
After the lower slab plates 1 and 2 are laid, a plurality of lower stand plates 3 and 3.3 are erected on the lower slab plates 1 and 2 at appropriate intervals. That is, the fitting protrusions 3c l 3 C', -rlff provided in the fitting grooves 1a, 2a of the lower slab plates 1 and 2 and protruding from above onto the lower surface of the lower pedestal plate 3 are placed in the lower pedestal plate, avoiding one person. 3, 3.3 can be erected.

この各下架台版3,3.3の中央部には上方に開口した
円弧状の円弧受面3a、3a、3aがそれぞれ形成され
ており、この円弧受面3a、3a、3aは設置!する浄
化槽Cの下面外周形状に適合して予め形成されたもので
あり、複数個の下架台版3,3.3が適宜間隔に立設さ
れた後に、この複数個の下架台版3,3.3上に浄化槽
Cが截置されて、各架台版3,3.3の円弧受面3a。
In the center of each of the lower mount plates 3, 3.3, upwardly opened arcuate receiving surfaces 3a, 3a, 3a are formed, respectively. It is formed in advance to match the outer peripheral shape of the lower surface of the septic tank C, and after the plurality of lower mount plates 3, 3.3 are erected at appropriate intervals, the plurality of lower mount plates 3, 3. A septic tank C is placed on the circular arc receiving surface 3a of each frame plate 3, 3.3.

3a、3a内に浄化槽Cが底台状に截置される。A septic tank C is placed in the shape of a base in 3a and 3a.

又、各下架台版3の上端両側面には上方に段状に開口し
た連結凹部3b、3b、3bが形成されている。
In addition, connecting recesses 3b, 3b, 3b are formed on both sides of the upper end of each lower pedestal plate 3 and open upward in a stepped manner.

浄化槽Cが截置された後に前記下架台版3に一体状に上
方より上架台版4が立設固定される。即ち、L架台版4
は下架台版3と対称形状をなし、その下端部には前記連
結凹部3bに嵌合可能な連結凸部4bが突出形成されて
おり、連結凹部3b内に連結凸部4bが嵌入することに
より、下架台版3の上方に上架置版4が一体状に立設さ
れる。
After the septic tank C is installed, an upper frame plate 4 is erected and fixed integrally with the lower frame plate 3 from above. That is, L mount version 4
has a symmetrical shape with the lower pedestal plate 3, and a connecting protrusion 4b that can be fitted into the connecting recess 3b is formed protruding from its lower end. , an upper mounting plate 4 is integrally erected above the lower mounting plate 3.

この時に上架置版4の中央部に円弧状に形成された円弧
受面4aは、設置された浄化槽Cの上面外周面に沿って
当接し、下架台版3と上架台版4間に挾まれた状態で浄
化槽Cは固定される。
At this time, an arcuate receiving surface 4a formed in an arc shape at the center of the upper mounting plate 4 comes into contact along the outer peripheral surface of the upper surface of the installed septic tank C, and is sandwiched between the lower mounting plate 3 and the upper mounting plate 4. The septic tank C is fixed in this state.

尚、上架置版4は全ての下架台版3上に立設されなくて
も良く、強度的に必要な数を下架台版3上に立設するも
のである。
Incidentally, the upper mounting plates 4 do not have to be erected on all the lower mount plates 3, and the number of upper mount plates 4 required for strength is erected on the lower mount plates 3.

上架置版4,4.4が設置された後に、その上面側に上
部スラブ版5,6が敷設される。上部スラブ版5,6は
前記下部スラブ版1,2とほぼ同様な形状に形成された
ものであって、上部スラ:ノ版5及び6には浄化槽Cの
上部に突出されたマンポールCa 、Ca 、Caが1
1梃入し得る開口部が形成されており、この開口部より
マンホールCa。
After the upper mounting plates 4, 4.4 are installed, upper slab plates 5, 6 are laid on the upper surface side thereof. The upper slab plates 5 and 6 are formed in substantially the same shape as the lower slab plates 1 and 2, and the upper slab plates 5 and 6 have a manpole Ca protruding from the top of the septic tank C, Ca, Ca is 1
An opening is formed into which the manhole Ca can be inserted.

Caを地表側に開口させて設置することができ、各マン
ホールCaには上方より蓋部材が取り付けられて設置が
完了される。この状態で上部スラブ版5,6は上面側が
地表面に露出して、例えば駐車場等に利用することがで
きる。
The manhole Ca can be installed with its opening facing the ground surface, and the installation is completed by attaching a cover member to each manhole Ca from above. In this state, the upper surfaces of the upper slabs 5 and 6 are exposed to the ground surface, and can be used, for example, in a parking lot.

本例においては、下部スラブ版1.2及び下架台版3及
び上架置版4及び上部スラブ版5,6がそれぞれPC版
等の素材により別体で正確な寸法に工場生産されたもの
で、現場にて簡易に組み付けることができるものであり
、各部材を現場に運び込んで順次組付けることにより、
浄化槽Cの設置工事が完了する。
In this example, the lower slab version 1.2, the lower mounting version 3, the upper mounting version 4, and the upper slab versions 5 and 6 are each made of a PC board or other material and manufactured separately in a factory with accurate dimensions. It can be easily assembled on site, and by transporting each component to the site and assembling it in sequence,
Installation work for septic tank C is completed.

又、本例においては構成部材が少ないため、現場への搬
入が簡易に行なλるとともに現場での組付工事が簡単に
行なえ、シ/フ)も、組付状態が部材・、気散が少ない
た)り正確な設置状態を呈し、強固か一つ正確に所定位
置に浄化槽Cを設置することができる。又、各部材の嵌
合部には接着材部を塗布(7て、その嵌合状態を強固な
ものとすることもできる。
In addition, since this example has fewer components, it can be easily transported to the site, and the assembly work on site can be easily performed. Since there are few problems, the installation state is accurate, and the septic tank C can be firmly and accurately installed in a predetermined position. Furthermore, the fitting state can be made stronger by applying an adhesive to the fitting portion of each member (7).

尚、前記下部スラブ版1,2及び上部スラブ版5.6の
長手方向寸法は適宜変更が可R1であり、設置すべき浄
化槽Cの長手寸法に対応させて種々のものを造形させて
おくことができ、又、現場にて長手方向に何枚か継ぎ合
わせて設置することができる。又、下架台版3及び上架
置版4の配置枚数も浄化槽Cの長さ等に対応して増減さ
せることができる。
Note that the longitudinal dimensions of the lower slab plates 1, 2 and the upper slab plates 5.6 can be changed as appropriate R1, and various shapes may be formed in accordance with the longitudinal dimensions of the septic tank C to be installed. It is also possible to connect several sheets in the longitudinal direction and install them on site. Further, the number of lower mounting plates 3 and upper mounting plates 4 arranged can be increased or decreased depending on the length of the septic tank C, etc.

又、本例においては浄化槽CL:r)R置例を示したが
、浄化槽Cに限らず他の地下埋設物(例えば地下タンク
等)の埋設時にも、同様な工場生産された構成部材によ
り良好に埋設工事を完了することができるものである。
In addition, although this example shows an example of installing a septic tank CL:r)R, similar factory-produced structural members can be used not only for septic tank C but also for other underground objects (for example, underground tanks). The burial work can be completed within 24 hours.

(発明の効果) 本発明の浄化槽等の設置構造は、構築された埋設溝の底
面側に敷設される下部スラブ版と、該下部スラブ版上に
立設され上方に開口状に形成された受面に浄化槽等を載
置可能な下架台版と、該上架台版上に一体状に立設され
浄化槽等の上面部に当接し得る下方に開口した受面を有
する上架置版と、該上架台版上に敷設される上部スラブ
版とを主体として構成され、前記下部スラブ版、下架台
版、上架台版、上部スラブ版がそれぞれ別体にて組付可
能に工場生産されたものであることにより、各部材を現
場に搬入して現場にて順次組付けることにより正確かつ
強固に浄化槽等を設置することができ、設置工事が極め
て短時間で完了し得る効果を有する。
(Effects of the Invention) The installation structure of a septic tank, etc. of the present invention includes a lower slab laid on the bottom side of the constructed burial trench, and a receiver that is erected on the lower slab and formed in an upwardly opening shape. A lower mounting plate on which a septic tank or the like can be placed; an upper mounting plate that is integrally erected on the upper mounting plate and has a downwardly opening receiving surface that can come into contact with the upper surface of the septic tank, etc.; It is mainly composed of an upper slab installed on a base plate, and is factory-produced so that the lower slab, lower mount, upper mount, and upper slab can be assembled separately. This has the effect that a septic tank or the like can be installed accurately and firmly by carrying each member to the site and assembling them one after another on site, and the installation work can be completed in an extremely short time.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例を示す浄化槽の設置構成部材
の配置状態を示す斜視図、第2図は従来の設置状態を示
す正面断面図である。 1.2・・・下81;スラブ版   3 ・・下架台版
4・・・上架置版    3a、4a・・・円弧受面5
.6・・・上部スラブ版
FIG. 1 is a perspective view showing the arrangement of installed components of a septic tank according to an embodiment of the present invention, and FIG. 2 is a front sectional view showing the conventional installation state. 1.2...Lower 81; Slab version 3...Lower mounting version 4...Upper mounting version 3a, 4a...Circular receiving surface 5
.. 6...Top slab version

Claims (1)

【特許請求の範囲】[Claims] 構築された埋設溝の底面側に敷設される下部スラブ版と
、該下部スラブ版上に立設され上方に開口状に形成され
た受け面に浄化槽等を載置可能な下架台版と、該下架台
版上に一体状に立設され浄化槽等の上面部に当接し得る
下方に開口した受け面を有する上架台版と、該上架台版
上に敷設される上部スラブ版とを主体として構成され、
前記下部スラブ版、下架台版、上架台版、上部スラブ版
がそれぞれ別体にて組付可能に工場生産されたものであ
ることを特徴とする浄化槽等の地下埋設物の設置構造。
A lower slab slab is laid on the bottom side of the constructed burial trench, a lower mounting platform is erected on the lower slab slab, and a septic tank or the like can be placed on a receiving surface formed with an opening at the top; Mainly composed of an upper pedestal plate which is integrally erected on the lower pedestal plate and has a downwardly opened receiving surface that can come into contact with the upper surface of the septic tank, etc., and an upper slab plate which is laid on the upper pedestal plate. is,
An installation structure for an underground object such as a septic tank, characterized in that the lower slab version, the lower mount version, the upper mount version, and the upper slab version are manufactured in a factory so that they can be assembled separately.
JP6679388A 1988-03-19 1988-03-19 Structure for installation of underground buried matter such as cleaning tank Pending JPH026896A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6679388A JPH026896A (en) 1988-03-19 1988-03-19 Structure for installation of underground buried matter such as cleaning tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6679388A JPH026896A (en) 1988-03-19 1988-03-19 Structure for installation of underground buried matter such as cleaning tank

Publications (1)

Publication Number Publication Date
JPH026896A true JPH026896A (en) 1990-01-11

Family

ID=13326100

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6679388A Pending JPH026896A (en) 1988-03-19 1988-03-19 Structure for installation of underground buried matter such as cleaning tank

Country Status (1)

Country Link
JP (1) JPH026896A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0478995U (en) * 1990-11-14 1992-07-09
US5254068A (en) * 1990-08-17 1993-10-19 Yamazaki Mazak Kabushiki Kaisha Automatic setup apparatus

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5254068A (en) * 1990-08-17 1993-10-19 Yamazaki Mazak Kabushiki Kaisha Automatic setup apparatus
JPH0478995U (en) * 1990-11-14 1992-07-09

Similar Documents

Publication Publication Date Title
JPH026896A (en) Structure for installation of underground buried matter such as cleaning tank
JPH0782753A (en) Constructing method for continuous footing
JPH0626395Y2 (en) Installation structure of septic tanks
JPH0751534Y2 (en) Floor slab with concrete dam
JPH03199528A (en) Steel frame foundation of construction
JP3656873B2 (en) Foundation construction method
JP2002356853A (en) Anchor bolt location setting jig
JPH026901B2 (en)
JP2002088775A (en) Foundation structure equipped with anchor bolt and method for constructing the same
JPH028466A (en) Fixed structure of concrete plate
JPH07113240A (en) Housing long-strip footing and construction method thereof
JP2002364139A (en) Steel stair mounting hardware, mounting device and mounting method
JP2001107498A (en) Precast floor board laying structure and method
JPH0711630A (en) Method of underground continuous wall used for precast prestressed concrete slab wall
JP2843880B2 (en) Wall construction method
JPS6138028A (en) Construction of foundation
JPH11343628A (en) Footing/retaining wall construction material and construction method therefor
JPH07216906A (en) Building foundation and building method
KR200383451Y1 (en) Method Carried out a Freeway utilizing PS Concrete wide Post
JPH1181485A (en) Artificial land and its construction method
JPS61257536A (en) Construction of building
JPH1018588A (en) Support for concrete form
JPS60168822A (en) Form paneling work for structure-burying ground
KR20050037441A (en) Method carrying out a freeway utilizing ps concrete wide post
JPH04143322A (en) Forming method for concrete foundation