Installation structure of septic tanks

Info

Publication number
JPH0626395Y2
JPH0626395Y2 JP12030987U JP12030987U JPH0626395Y2 JP H0626395 Y2 JPH0626395 Y2 JP H0626395Y2 JP 12030987 U JP12030987 U JP 12030987U JP 12030987 U JP12030987 U JP 12030987U JP H0626395 Y2 JPH0626395 Y2 JP H0626395Y2
Authority
JP
Japan
Prior art keywords
septic tank
slab
plate
slab plate
installation structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP12030987U
Other languages
Japanese (ja)
Other versions
JPS6425397U (en
Inventor
勲 伊藤
求 末方
栄一 堀田
Original Assignee
株式会社イナックス
大成プレハブ株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社イナックス, 大成プレハブ株式会社 filed Critical 株式会社イナックス
Priority to JP12030987U priority Critical patent/JPH0626395Y2/en
Publication of JPS6425397U publication Critical patent/JPS6425397U/ja
Application granted granted Critical
Publication of JPH0626395Y2 publication Critical patent/JPH0626395Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【考案の詳細な説明】 (産業上の利用分野) この考案は、し尿排水と生活排水とを同時に浄化処理す
ることのできる浄化槽等を設置するための設置構造に関
するものである。
DETAILED DESCRIPTION OF THE INVENTION (Industrial field of application) The present invention relates to an installation structure for installing a septic tank or the like capable of simultaneously purifying human waste water and domestic waste water.

(従来技術及びその問題点) 従来、浄化処理手段を内蔵した浄化槽等を設置するにあ
たり、例えば第9図に示すように、地面Eに埋設溝Hを
形成させておき、この埋設溝Hの底面に砂利石またはコ
ンクリート等により基礎部51を造形し、この基礎部5
1の上面にコンクリートベース52を構築し、このコン
クリートベース52上に浄化槽C本体に一体化されてい
る架台53を介し浄化槽Cを載置固定した後、埋設溝H
を埋めて浄化槽Cを地中に埋設状に設置することが行な
われており、従来においては、設置現場において埋設溝
Hを掘削後、その底面に基礎部51とともにコンクリー
トベース52をコンクリートの流込工法等により構築し
ており、又、浄化槽Cの上面部を駐車場として利用する
場合には、浄化槽Cの上方にスラブ層を形成させ、この
スラブ層を支持するための補強柱を埋設溝H内にコンク
リートの流込工法等により構築していたため、現場にお
いてコンクリート打ち作業が必要となり、浄化槽Cを設
置するための前作業が多く、相当の工期を必要とし、か
つ基礎となるコンクリートベース52及び補強柱等のコ
ンクリートの強度を十分に確保するためにコンリートの
品質管理を厳重に行なう必要があり、土木作業及び品質
管理に多大な労力を要するという問題点があった。
(Prior Art and Problems Thereof) Conventionally, when installing a septic tank or the like having a built-in purifying means, as shown in FIG. 9, for example, a buried groove H is formed in the ground E, and the bottom surface of this buried groove H is formed. The foundation part 51 is made of gravel stone or concrete, and the foundation part 5
After constructing a concrete base 52 on the upper surface of 1 and mounting and fixing the septic tank C on the concrete base 52 via a pedestal 53 integrated with the main body of the septic tank C, the embedded groove H
The septic tank C is buried in the ground and installed in the ground. Conventionally, after the buried groove H is excavated at the installation site, the concrete base 52 is poured into the bottom surface of the concrete base 52 together with the foundation part 51. When the upper surface of the septic tank C is used as a parking lot, the slab layer is formed above the septic tank C, and the reinforcing column for supporting the slab layer is embedded in the buried groove H. Since it was constructed by the method of pouring concrete into it, concrete work was required at the site, there was a lot of pre-work to install the septic tank C, a considerable construction period was required, and the concrete base 52 and It is necessary to perform strict quality control of the concrete to secure sufficient strength of concrete such as reinforcement columns, and a great deal of labor is required for civil engineering work and quality control. There is a problem that it requires.

(問題点を解決するための手段) 本考案は上記従来の問題点に鑑み案出したものであっ
て、浄化槽等を設置するにあたり簡易迅速に設置作業を
完了し得る設置構造を提供せんことを目的とし、その要
旨は、基礎面を形成するプレキャストコンクリート版
(PC版)にて平板状に形成したスラブ板上に浄化槽等
の地下埋設物を設置する構造であって、前記地下埋設物
の下部には適数個の架台を設けるとともに、前記スラブ
板には、その長手方向に沿って適宜間隔をおいてレベル
調整用のグラウト穴を形成したことである。
(Means for Solving Problems) The present invention has been devised in view of the above-mentioned conventional problems, and does not provide an installation structure capable of completing installation work simply and quickly when installing a septic tank or the like. For the purpose, the gist thereof is a structure in which an underground buried object such as a septic tank is installed on a slab plate formed in a flat plate shape by a precast concrete plate (PC plate) forming a foundation surface, and the lower part of the underground buried object. Is provided with an appropriate number of mounts, and the slab plate is formed with grout holes for level adjustment at appropriate intervals along the longitudinal direction thereof.

(作用) 現場に構築された埋設溝の底面にスラブ板を敷設し、ス
ラブ板のグラウト穴にモルタル等を注入してスラブ板の
レベル調整を行ない、そのスラブ板の上部に架台を介し
浄化槽等を設置して設置作業を完了することができ、現
場において従来のようにコンクリート打ちを行なう必要
がなく、浄化槽等の設置を容易かつ短時間に行なうこと
ができる。
(Operation) A slab board is laid on the bottom of the buried groove constructed on the site, mortar etc. is injected into the grout hole of the slab board to adjust the level of the slab board, and a septic tank, etc. is placed on the top of the slab board via a stand. Can be installed and the installation work can be completed, there is no need to perform concrete pouring at the site as in the past, and the septic tank and the like can be installed easily and in a short time.

又、浄化槽等の上面部を駐車場として利用する場合に
は、浄化槽等の上方に上部スラブを鉄筋コンクリート等
により形成するが、この上部スラブを支持するための補
強柱をも工場生産にて造形された部材とすれば、これら
を現場で組み付ける作業により浄化槽等を設置し得る。
When using the upper surface of the septic tank as a parking lot, the upper slab is made of reinforced concrete or the like above the septic tank, but reinforcement columns to support the upper slab are also manufactured by factory production. If such members are used, a septic tank or the like can be installed by assembling them on site.

(実施例) 以下、本考案の実施例を図面に基づいて説明する。Embodiment An embodiment of the present invention will be described below with reference to the drawings.

第1図〜第5図において、浄化槽CはFRP等の素材に
て円筒状に形成されたものであり、その上面部には突出
状に上方が開口したマンホールCaが一体形成されてお
り、この浄化槽Cの内部には、し尿排水と生活排水を浄
化処理することのできる沈殿分離槽,接触曝気槽,沈殿
槽等が内蔵されている。この浄化槽Cは工場にて造形さ
れたものであり、この浄化槽Cを現場に埋設状に設置す
るにあたり、本例においては同様に工場生産にて造形さ
れたスラブ板1と架台2,3を使用する。
1 to 5, the septic tank C is formed of a material such as FRP into a cylindrical shape, and a manhole Ca having a projecting upper opening is integrally formed on the upper surface thereof. Inside the septic tank C, a sedimentation separation tank, a contact aeration tank, a sedimentation tank, and the like capable of purifying human waste water and domestic waste water are incorporated. This septic tank C is molded at the factory, and when installing the septic tank C in a buried state on the site, in this example, the slab plate 1 and the pedestals 2 and 3 that are similarly manufactured at the factory are used. To do.

即ち、スラブ板1は第2図に拡大して示すように、PC
版(プレキャストコンクリート版)にて板状に形成され
たものであり、その表面側の両側部には長手方向に沿っ
て一対の断面凹状の係合溝1a,1bが形成されてお
り、又、両側縁部には長手方向に沿って適宜間隔をおい
て切欠部1cが形成されており、この欠切部1c内には
フック鉄筋1dが突出されている。又、スラブ板1の短
手方向にも適宜間隔をおいて凹状の連結溝1fが形成さ
れており、この連結溝1f内にもフック鉄筋1dが突出
形成されている。このスラブ板1を複数長手方向に連結
溝1f内のフック鉄筋1dを介して連結することにより
前記浄化槽Cと同等寸法のスラブ板が形成される。その
連結状態を第3図及び第4図に拡大して示す。図中J
は、対向するフック鉄筋1dを連結する連結金具であ
る。
That is, the slab plate 1 is a PC as shown in FIG.
It is formed into a plate shape by a plate (precast concrete plate), and a pair of engaging grooves 1a and 1b having a concave cross section is formed along the longitudinal direction on both sides of the surface side thereof. Notches 1c are formed at appropriate intervals along the longitudinal direction on both side edge portions, and hook rebars 1d project into the notches 1c. Further, concave connecting grooves 1f are formed at appropriate intervals also in the lateral direction of the slab plate 1, and hook reinforcing bars 1d are formed to project in the connecting grooves 1f. By connecting a plurality of the slab plates 1 in the longitudinal direction via hook rebars 1d in the connecting groove 1f, a slab plate having the same size as the septic tank C is formed. The connected state is enlarged and shown in FIG. 3 and FIG. J in the figure
Is a connecting fitting for connecting the opposing hook rebars 1d.

又このスラブ板1には長手方向に沿って適宜間隔をおい
てグラウト穴1eが形成されている。スラブ板の長手方
向長さが例えば9m必要な場合は、4mのスラブ板1
と、5mのスラブ板1とを組み合わせば良く、その他3
m,4m,5m等の各長さに形成したスラブ板1を用意
しておけば、適宜組み合わせにより、必要長さのスラブ
板を得ることができる。
In addition, the slab plate 1 is formed with grout holes 1e at appropriate intervals along the longitudinal direction. If the length of the slab plate in the longitudinal direction is, for example, 9 m, a slab plate of 4 m 1
And 5m slab 1 can be combined, and other 3
If the slab plate 1 formed in each length of m, 4 m, 5 m, etc. is prepared, the slab plate of the required length can be obtained by appropriately combining.

一方、架台2及び3は対称形に工場生産にて造形された
ものであり、それぞれその上面側には浄化槽Cの下面と
当接可能な円弧面2b,3bが形成されており、円弧面
2b,3bと対向状に下方に係止凸部2a,3aが一体
状に形成されている。この架台2の係止凸部2aは前記
スラブ板1の係合溝1bに嵌入可能な形状に形成されて
おり、又、架台3の係止凸部3aは前記スラブ板1の係
合溝1aに嵌入可能な形状に形成されたものである。こ
の架台2及び3は、例えばPC版等により工場生産され
たものである。
On the other hand, the pedestals 2 and 3 are symmetrically shaped by factory production, and arc surfaces 2b and 3b capable of contacting the lower surface of the septic tank C are formed on the upper surface side of the pedestals 2 and 3, respectively. , 3b are formed integrally with locking projections 2a, 3a below. The engaging protrusion 2a of the gantry 2 is formed in a shape that can be fitted into the engaging groove 1b of the slab plate 1, and the engaging protrusion 3a of the gantry 3 is the engaging groove 1a of the slab plate 1. It is formed into a shape that can be fitted into. The mounts 2 and 3 are factory-produced using, for example, a PC version.

このようなスラブ板1と架台2及び3を用いて第5図の
ように浄化槽Cを設置するにあたり、設置現場にて予め
埋設溝Hの底面側に砂利等により基礎部51を構築して
おき、その状態において上方より前記連結されたスラブ
板1を敷設し、スラブ板1のグラウト穴1eにモルタル
等を注入してレベル調整を行ない、又スラブ板1の連結
溝1f内にもモルタル等を注入して各スラブ板1を接合
し、敷設されたスラブ板1の上方より架台2と3をスラ
ブ板1の長手方向に沿って適宜間隔をおいて適宜個数を
設置する。その時に架台2及び3の各係止凸部2a,3
aをスラブ板1の係合溝1a,1bに嵌入させてスラブ
板1と架台2及び3を一体化させる。その場合に接着剤
等を介し強固に両者を固着させることもできる。
When installing the septic tank C using the slab plate 1 and the pedestals 2 and 3 as shown in FIG. 5, the foundation part 51 is previously constructed on the bottom surface side of the embedding groove H by gravel or the like at the installation site. In that state, the connected slab plate 1 is laid from above and mortar or the like is injected into the grout hole 1e of the slab plate 1 to adjust the level, and the mortar or the like is also placed in the connecting groove 1f of the slab plate 1. The slab plates 1 are injected and joined to each other, and the pedestals 2 and 3 are placed from above the laid slab plate 1 along the longitudinal direction of the slab plate 1 at appropriate intervals and in an appropriate number. At that time, the respective locking projections 2a, 3 of the pedestals 2 and 3
By fitting a into the engaging grooves 1a and 1b of the slab plate 1, the slab plate 1 and the pedestals 2 and 3 are integrated. In that case, it is also possible to firmly fix the both via an adhesive or the like.

このようにスラブ板1の上面側に適数個の架台2,3が
それぞれ対向状に配設された後に、上方より浄化槽Cを
架台2及び3の円弧面2b,3b上に載置し、架台2,
3上に浄化槽Cを固定させることができる。その時に架
台2,3は係止凸部2a及び3aがスラブ板1の係合溝
1a,1b内に嵌入されているため、浄化槽Cの上方か
らの押圧力により横ズレすることがなく強固に浄化槽C
を支えることができる。この状態で更に前記スラブ板1
の欠切部1cに突設されたフック鉄筋1dに浮上防止ワ
イヤー等を掛け、ワイヤーを浄化槽Cの上周面に掛け渡
し、対向側のフック鉄筋1dにワイヤーの端部を結び付
けることにより、ワイヤーを介し更に強固に浄化槽Cを
固定させることができ浄化槽Cの浮上防止を図ることが
できる。浄化槽Cが固定された後に埋設溝Hを埋め、浄
化槽Cの上面側に突出したマンホールCaのみを地表に
開口させて、浄化槽Cの設置作業を完了することができ
る。
In this way, after a suitable number of pedestals 2 and 3 are arranged facing each other on the upper surface side of the slab plate 1, the septic tank C is placed on the arc surfaces 2b and 3b of the pedestals 2 and 3 from above, Stand 2,
It is possible to fix the septic tank C on the surface of the container 3. At that time, since the locking projections 2a and 3a of the pedestals 2 and 3 are fitted into the engaging grooves 1a and 1b of the slab plate 1, the pedestals 2 and 3 are firmly fixed without lateral displacement due to the pressing force from above the septic tank C. Septic tank C
Can support. In this state, the slab plate 1 is further
By hooking a float prevention wire or the like on the hook rebar 1d protruding from the notch portion 1c of the wire, the wire is laid over the upper peripheral surface of the septic tank C, and the end of the wire is tied to the hook rebar 1d on the opposite side. The septic tank C can be fixed more firmly via the via, and the septic tank C can be prevented from floating. After the septic tank C is fixed, the buried groove H is filled, and only the manhole Ca projecting to the upper surface side of the septic tank C is opened to the surface of the ground, and the installation work of the septic tank C can be completed.

このように本例においては、工場生産にて造形されたス
ラブ板1と架台2,3をそれぞれ現場に搬入して、所定
位置に配設させるのみの作業により浄化槽Cを簡易に設
置することができ、浄化槽Cの設置作業を短時間にて完
了することができる。しかもスラブ板1及び架台2,3
は工場にて厳格な品質管理のもとに造形することができ
るため、強度上等の品質が良好に確保されるものであ
り、従来のように現場においてコンクリート打ちされた
ベース部52等の品質管理を行なう必要がなく、強固に
浄化槽Cを設置することができる。
As described above, in this example, the septic tank C can be easily installed by simply carrying in the slab plate 1 and the pedestals 2 and 3 that have been modeled by factory production and arranging them at predetermined positions. Therefore, the installation work of the septic tank C can be completed in a short time. Moreover, the slab 1 and the pedestals 2 and 3
Can be molded in a factory under strict quality control, so quality such as strength can be secured satisfactorily. The septic tank C can be firmly installed without the need for management.

第6図には埋設溝Hの幅長を増大させて、その埋設溝H
内に二連に浄化槽Cを並設した例を示す。
In FIG. 6, the width of the buried groove H is increased so that the buried groove H
An example in which two septic tanks C are installed side by side inside is shown.

本例においてもスラブ板1及び架台2及び3は工場生産
にて造形されたものであるため設置が極めて簡易に行な
われる。本例においては各浄化槽Cのスラブ板1のフッ
ク鉄筋1dにそれぞれ浮上防止ワイヤーを掛け、各ワイ
ヤーを各浄化槽Cの上面に掛け渡し、対向側のフック鉄
筋1dに各ワイヤーの端部を結び付けることにより、各
浄化槽Cを固定させることができる。
Also in this example, since the slab plate 1 and the pedestals 2 and 3 are modeled by factory production, the installation is extremely easy. In this example, the anti-floating wire is hung on the hook rebar 1d of the slab plate 1 of each septic tank C, each wire is laid over the upper surface of each septic tank C, and the end of each wire is tied to the hook rebar 1d on the opposite side. Thereby, each septic tank C can be fixed.

さらに第7図には浄化槽C上の地表を駐車場等に利用す
る場合の設置構造を示す。
Further, FIG. 7 shows an installation structure when the surface of the septic tank C is used for a parking lot or the like.

本例においては、設置現場にて予め埋設溝Hの底面側に
砂利等により基礎部51を形成させておき、その上面に
工場生産されたスラブ板1と架台2,3を設置させ、そ
の上面に浄化槽Cを載置するものであり、さらに浄化槽
Cの側縁に上部スラブ6の補強用の柱を配置したもので
ある。即ち、敷設されたスラブ板1の両側縁部に工場生
産にて造形された支持ベース4,4をスラブ板1の長手
方向に沿って所定間隔に適数個配置させ、この支持ベー
ス4には凹み状の係合凹部が形成されているため、この
係合凹部内に嵌入可能な係止凸部を形成した補強柱5を
それぞれ支持ベース4上に立設させボルト7にて固定す
る。この補強柱5の上端部に上部スラブ6を鉄筋コンク
リート等により形成させ、上部スラブ6にて車重等を支
える。この補強柱5及び支持ベース4も工場生産にて造
形することができるため、設置が容易に行なわれ短時間
にて設置作業が完了するものである。
In this example, the foundation part 51 is formed on the bottom surface side of the buried groove H in advance by gravel or the like at the installation site, and the factory-produced slab plate 1 and the pedestals 2 and 3 are installed on the top surface thereof. The septic tank C is mounted on the column, and a column for reinforcing the upper slab 6 is arranged on the side edge of the septic tank C. That is, a suitable number of support bases 4 and 4 shaped by factory production are arranged at predetermined intervals along the longitudinal direction of the slab plate 1 on both side edges of the slab plate 1 that has been laid. Since the recessed engaging recesses are formed, the reinforcing columns 5 having the engaging protrusions that can be fitted into the engaging recesses are erected on the support bases 4 and fixed by the bolts 7. An upper slab 6 is formed on the upper ends of the reinforcing columns 5 by using reinforced concrete or the like, and the upper slab 6 supports the vehicle weight and the like. Since the reinforcing column 5 and the support base 4 can also be formed by factory production, the installation can be easily performed and the installation work can be completed in a short time.

第8図には埋設溝Hの幅長を増大させて、その埋設溝H
内に二連に浄化槽Cを並設した例を示す。
In FIG. 8, the width of the buried groove H is increased so that the buried groove H
An example in which two septic tanks C are installed side by side inside is shown.

本例においては、補強柱5を幅方向に3本使用し、その
上方に上部スラブ6を形成する。中央の補強柱5は二連
の浄化槽C,Cに兼用されるものである。尚、上部スラ
ブ6は適宜寸法に調整することができる。
In this example, three reinforcing columns 5 are used in the width direction, and an upper slab 6 is formed above them. The central reinforcement column 5 is also used as the two septic tanks C, C. The upper slab 6 can be adjusted to a suitable size.

尚、上記実施例にあっては、埋設溝H内に浄化槽Cを設
置する場合について述べたが、浄化槽Cに限らず、他の
地下埋設物(例えば地下タンク等)においても同様な構
造部材を採用し同様に設置を容易に行なうことができ
る。
In addition, in the said Example, although the case where the septic tank C was installed in the burial groove H was described, the same structural member is not limited to the septic tank C but other underground buried objects (for example, an underground tank etc.). It can be installed easily as well.

(考案の効果) 本考案は、基礎面を形成するプレキャストンクリート版
(PC版)にて平板状に形成したスラブ板上に浄化槽等
の地下埋設物を設置する構造であって、前記地下埋設物
の下部には適数個の架台を設けるとともに、前記スラブ
板には、その長手方向に沿って適宜間隔をおいてレベル
調整用のグラウト穴を形成したことにより、構造部材を
現場に搬入し、現場に構築された埋設溝の底面にスラブ
板を敷設し、グラウト穴にモルタル等を注入してスラブ
板のレベル調節を行ない、そのスラブ板上に架台を介し
浄化槽等を設置でき、現場において従来のようにコンク
リート打ちを行なう必要がなく、浄化槽等の設置を容易
かつ短時間に行なうことができ、設置のための労力が軽
減されて、設置コストを低減し得る効果を有する。
(Effects of the Invention) The present invention is a structure in which an underground buried object such as a septic tank is installed on a slab plate formed in a flat plate shape by a precast Ncleet plate (PC plate) forming a foundation surface, In addition to providing a suitable number of pedestals in the lower part of the slab, by forming grout holes for level adjustment at appropriate intervals along the longitudinal direction of the slab plate, the structural member is carried into the site, A slab plate is laid on the bottom of the buried groove constructed on the site, mortar etc. is injected into the grout hole to adjust the level of the slab plate, and a septic tank etc. can be installed on the slab plate via a stand, which is the conventional method on site. Since it is not necessary to pour concrete as described above, the septic tank can be installed easily and in a short time, the labor for installation is reduced, and the installation cost can be reduced.

【図面の簡単な説明】[Brief description of drawings]

図は本考案の実施例を示し、第1図は第1実施例の設置
構造部材の分解斜視図、第2図は第1図のスラブ板の拡
大平面図、第3図はスラブ板の連結状態を示す要部拡大
平面図、第4図は第3図の側面図、第5図は第1図の構
造部材にて浄化槽を設置した状態を示す断面図、第6図
は二連型の浄化槽の設置状態を示す断面図、第7図は浄
化槽上の地表を駐車場等に利用する場合の設置構造を示
す断面図、第8図は第7図のものを二連型に設置した状
態を示す断面図、第9図は従来の浄化槽の設置状態を示
す断面図である。 1……スラブ板、1a,1b……係合溝 1c……欠切部、1f……連結溝 1d……フック鉄筋、1e……グラウト穴 2……架台、2a……係止凸部 2b……円弧面、3……架台 3a……係止凸部、3b……円弧面 4……支持ベース 5……補強柱 6……上部スラブ、51……基礎部 C……浄化槽、Ca……マンホール H……埋設溝
FIG. 1 shows an embodiment of the present invention, FIG. 1 is an exploded perspective view of an installed structural member of the first embodiment, FIG. 2 is an enlarged plan view of the slab plate of FIG. 1, and FIG. 3 is a connection of slab plates. FIG. 4 is a side view of FIG. 3 showing the state, FIG. 4 is a side view of FIG. 3, FIG. 5 is a sectional view showing a state in which the septic tank is installed by the structural member of FIG. 1, and FIG. Sectional view showing the installed state of the septic tank, Fig. 7 is a sectional view showing the installation structure when the surface of the septic tank is used for a parking lot, etc. FIG. 9 is a cross-sectional view showing an installed state of a conventional septic tank. 1 ... Slab plate, 1a, 1b ... Engagement groove 1c ... Notch, 1f ... Connection groove 1d ... Hook rebar, 1e ... Grout hole 2 ... Stand, 2a ... Locking protrusion 2b …… Arc surface, 3 …… Stand 3a …… Locking convex part, 3b …… Arc surface 4 …… Support base 5 …… Reinforcing column 6 …… Upper slab, 51 …… Foundation C …… Septic tank, Ca… … Manhole H… Buried groove

───────────────────────────────────────────────────── フロントページの続き (72)考案者 堀田 栄一 愛知県名古屋市中村区名駅4丁目5番26号 大成プレハブ株式会社中部営業所内 (56)参考文献 特開 昭61−232193(JP,A) 実開 昭55−163351(JP,U) 実開 昭60−22541(JP,U) 実公 昭61−28797(JP,Y2) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Eiichi Hotta 4-5-26, Mei Station, Nakamura-ku, Nagoya, Aichi Taisei Prefab Co., Ltd. (56) Reference JP-A-61-232193 (JP, A) ) Actually open 55-163351 (JP, U) Actually open 60-22541 (JP, U) Actually open 61-28797 (JP, Y2)

Claims (4)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】基礎面を形成するプレキャストコンクリー
ト版(PC版)にて平板状に形成したスラブ板1上に浄
化槽C等の地下埋設物を設置する構造であって、前記地
下埋設物の下部には適数個の架台2を設けるとともに、
前記スラブ板1には、その長手方向に沿って適宜間隔を
おいてレベル調整用のグラウト穴1eを形成したことを
特徴とする浄化槽等の設置構造。
1. A structure in which an underground buried object such as a septic tank C is installed on a slab plate 1 formed in a flat plate shape by a precast concrete plate (PC plate) forming a foundation surface, and the lower part of the underground buried object. In addition to installing a suitable number of mounts 2,
An installation structure for a septic tank or the like, wherein the slab plate 1 has grout holes 1e for level adjustment formed at appropriate intervals along the longitudinal direction thereof.
【請求項2】スラブ板と架台とが一体化可能な嵌合手段
を備え、架台上に浄化槽等が載置された時に架台の横ズ
レが防止されるように構成した実用新案登録請求の範囲
第1項記載の浄化槽等の設置構造。
2. A utility model registration claim comprising a fitting means capable of integrating a slab plate and a gantry so as to prevent lateral displacement of the gantry when a septic tank or the like is placed on the gantry. The installation structure of the septic tank, etc. described in paragraph 1.
【請求項3】基礎面を形成するスラブ板と、該スラブ板
上に適数個配設される架台と、該架台上に載置される浄
化槽等と、該浄化槽等の上部に設置され地表面を形成す
る上部スラブと、該上部スラブを補強するために前記浄
化槽等の側縁に立設された補強柱とを主体として構成さ
れ、前記スラブ板,架台,補強柱がそれぞれ別体にて工
場生産にて造形されたものである実用新案登録請求の範
囲第1項記載の浄化槽等の設置構造。
3. A slab plate forming a base surface, an appropriate number of pedestals arranged on the slab plate, a septic tank mounted on the pedestal, and a ground installed on the septic tank or the like. Mainly composed of an upper slab that forms a surface and a reinforcing column that is erected upright on the side edge of the septic tank or the like to reinforce the upper slab, and the slab plate, pedestal, and reinforcing column are separate bodies. The installation structure of the septic tank etc. according to claim 1 of the utility model registration that was modeled by factory production.
【請求項4】スラブ板の側縁に補強柱を立設支持可能な
ベース板を配設し、該ベース板と補強柱とが一体化可能
な嵌合構造に構成されている実用新案登録請求の範囲第
3項記載の浄化槽等の設置構造。
4. A utility model registration request wherein a base plate capable of standing and supporting a reinforcing column is provided on a side edge of the slab plate, and the base plate and the reinforcing column are integrated into a fitting structure. The installation structure of the septic tank, etc. described in the section 3 above.
JP12030987U 1987-08-04 1987-08-04 Installation structure of septic tanks Expired - Lifetime JPH0626395Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12030987U JPH0626395Y2 (en) 1987-08-04 1987-08-04 Installation structure of septic tanks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12030987U JPH0626395Y2 (en) 1987-08-04 1987-08-04 Installation structure of septic tanks

Publications (2)

Publication Number Publication Date
JPS6425397U JPS6425397U (en) 1989-02-13
JPH0626395Y2 true JPH0626395Y2 (en) 1994-07-20

Family

ID=31366300

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12030987U Expired - Lifetime JPH0626395Y2 (en) 1987-08-04 1987-08-04 Installation structure of septic tanks

Country Status (1)

Country Link
JP (1) JPH0626395Y2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2504360Y2 (en) * 1990-12-12 1996-07-10 株式会社クボタ Septic tank equipped with formwork device
JP2009185601A (en) * 2009-04-27 2009-08-20 Irie Shunsuke Septic tank foundation structural body and its construction method
JP5000771B2 (en) * 2011-01-31 2012-08-15 株式会社カンケン Septic tank installation structure

Also Published As

Publication number Publication date
JPS6425397U (en) 1989-02-13

Similar Documents

Publication Publication Date Title
JPH0626395Y2 (en) Installation structure of septic tanks
JPS609178B2 (en) How to install garden or boundary wall panels
JPH037449Y2 (en)
JP3429230B2 (en) Construction methods for building concrete structures from concrete blocks
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
JPH0218123Y2 (en)
JPH07279184A (en) Floating underground beam foundation for building
JP3399924B2 (en) Seawall protection structure
JPS5941209Y2 (en) Precast assembly walkway
JPS6215349Y2 (en)
JP2963613B2 (en) Foundation structure and construction method
JP3002026B2 (en) Structure of residential continuous foundation
JPH04117040U (en) Building foundation structure
JPH0743177Y2 (en) Mounting structure of concrete cloth foundation and precast concrete wall slab
JPH0421874Y2 (en)
JPH026896A (en) Structure for installation of underground buried matter such as cleaning tank
JP3095417U (en) Large assembled culvert constructed of precast concrete and cast-in-place concrete
JP2547497Y2 (en) Precast foundation material for rectangular section concrete cloth foundation
JPS5812917Y2 (en) Foundation formwork support structure
JP2004143849A (en) Spacer, variable gradient type side ditch using the spacer and its construction method
JP2522712B2 (en) Foundation slab construction method
JPH067075Y2 (en) Building foundation
JPS6029292Y2 (en) Semi-prefabricated conduit for underground cable pipes
JPH02300423A (en) Form panel and sump water-disposing structure therewith
JP2643760B2 (en) How to build foundation beams