JPH0243874B2 - - Google Patents

Info

Publication number
JPH0243874B2
JPH0243874B2 JP58039094A JP3909483A JPH0243874B2 JP H0243874 B2 JPH0243874 B2 JP H0243874B2 JP 58039094 A JP58039094 A JP 58039094A JP 3909483 A JP3909483 A JP 3909483A JP H0243874 B2 JPH0243874 B2 JP H0243874B2
Authority
JP
Japan
Prior art keywords
pressure
face
mud
pipe
muddy water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58039094A
Other languages
Japanese (ja)
Other versions
JPS59165797A (en
Inventor
Chojiro Endo
Osamu Morikawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP3909483A priority Critical patent/JPS59165797A/en
Publication of JPS59165797A publication Critical patent/JPS59165797A/en
Publication of JPH0243874B2 publication Critical patent/JPH0243874B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】 この発明は、泥水シールド工法に関し、特に切
羽面圧力の変動を防止し、切羽面の圧力を常に一
定に維持できる泥水シールド工法における切羽圧
力保持方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a muddy water shield construction method, and more particularly to a face pressure maintaining method in a muddy water shield construction method that prevents fluctuations in face pressure and can always maintain the pressure on the face constant.

泥水シールド工法は、砂質あるいは砂礫のよう
な地盤地の掘削において採用され、この工法で
は、地盤の性質上、切羽面の圧力を常時一定に保
持することが地盤の崩壊・沈下を防止する上で最
も重要な条件である。
The mud shield method is used when excavating sandy or gravelly ground. Due to the nature of the ground, it is important to keep the pressure on the face constant at all times in order to prevent ground collapse and subsidence. This is the most important condition.

しかしながら、従来の工法では切羽面の圧力を
常時一定に保つ上で問題があつた。
However, conventional construction methods have had problems in keeping the pressure on the face constant at all times.

すなわち、従来の工法で使用されていた掘進機
は、泥水を供給する送泥管を掘進機の近傍で伸縮
管と称する二重管とし、掘削に伴つてこれを延長
していたが、二重管が伸びきつてしまうと掘進機
をそれ以上前進させることができないため、送泥
を一時中断し新たな管材を継ぎ足して掘削を行な
つていた。
In other words, with the excavators used in the conventional construction method, the mud pipe that supplies mud water was constructed as a double pipe called a telescopic pipe near the excavator, and this was extended as the excavation was carried out. Once the pipe was stretched, the excavator could no longer move forward, so mud feeding was temporarily suspended and new pipe material was added to continue digging.

従つて、この継ぎ足し作業時に、当然切羽面の
圧力は低化し、地盤が崩壊・沈下する恐れが極め
て大きかつた。
Therefore, during this replenishment work, the pressure on the face naturally decreased, and there was an extremely high risk that the ground would collapse and subside.

また、この種の工法では、通常掘削後の土砂と
ベントナイトを分離し、ベントナイトの再使用を
行つているが、これを土砂から完全に分離するこ
とは不可能であり、若干の土砂が混在していた。
In addition, in this type of construction method, the bentonite is usually separated from the bentonite after excavation, and the bentonite is reused. was.

従つて、長時間掘削作業を中止すると、切羽面
内の泥水は、時間の経過とともに地盤中に浸透し
圧力低化をきたすとともに、良質な泥水よりも土
砂が混入していると沈澱速度が早くなり、さらに
圧力低化を促進し、地盤崩壊の危険性が大きくな
り、また長期間の中止は、上記送泥管内にベント
ナイトが沈澱・堆積し、再開時にこれを排除しな
ければならず、掘削作業の再開にかなりの手間と
時間を費していた。
Therefore, if excavation work is stopped for a long period of time, the muddy water within the face surface will penetrate into the ground over time and cause a decrease in pressure, and if the muddy water is mixed with earth and sand, the sedimentation rate will be faster than with good quality muddy water. This will further promote a pressure drop and increase the risk of ground collapse.Also, long-term suspension will cause bentonite to precipitate and accumulate in the mud pipe, which must be removed when excavation is resumed. It took a lot of time and effort to restart work.

このような問題に対して、例えば、特開昭50−
61853号公報には、圧力調整用の送泥管を既設の
送、排泥管とは別に設ける技術が開示されてい
る。
For such problems, for example,
Publication No. 61853 discloses a technique in which a mud feeding pipe for pressure adjustment is provided separately from the existing mud feeding and mud draining pipes.

しかしながら、この公報に示されている技術で
は、送泥管に小容量の可変吐出ポンプを設置し、
このポンプを圧力検出器の大きさに応じて制御し
ているので、切羽が複数ある場合には個別にこれ
らを設けなければならず、構成が複雑になるとと
もに、作動の確認には坑道に入らなければならな
いので、取扱いも煩雑なものとなつていた。
However, in the technology shown in this publication, a small-capacity variable discharge pump is installed in the mud pipe,
Since this pump is controlled according to the size of the pressure detector, if there are multiple faces, these must be installed individually, which complicates the configuration and requires entry into the tunnel to confirm operation. As a result, handling has become complicated.

この発明は、上述のような問題点に鑑みなされ
たもので、その目的とするところは、掘削作業の
中断・中止等のように切羽面の圧力が低化する際
に、比較的簡単な構成によりこれを有効且つ確実
に防止することで、地盤の崩壊・沈下を妨げる泥
水シールド工法における切羽圧力保持方法を提供
するところにある。
This invention was made in view of the above-mentioned problems, and its purpose is to provide a relatively simple structure that can be used when the pressure on the face decreases, such as when excavation work is interrupted or stopped. Therefore, it is an object of the present invention to provide a method for maintaining face pressure in a muddy water shield construction method that prevents collapse and subsidence of the ground by effectively and reliably preventing this.

上記目的を達成するため、この発明は、ベント
ナイトを含有した泥水を切羽面に供給しながら掘
削し、この後に前記泥水と掘削土砂との混濁物を
排出しトンネル等の坑道を掘削する泥水シールド
工法において、一端に圧力調整用のバイパス管を
有し、他端が前記切羽面に連通される伸長可能な
複数の切羽圧力調整用送泥管を備えた送泥装置を
地上に設置し、前記切羽圧力調整用送泥管を前記
切羽面に接続して、前記バイパス管内に泥水を充
満させて前記切羽圧力調整用送泥管に常時一定圧
力の泥水を送出することで、掘削作業の中断・中
止時に前記切羽面の圧力を所定圧に維持すること
を特徴とする。
In order to achieve the above object, the present invention provides a mud water shield construction method in which excavation is carried out while supplying mud water containing bentonite to the face, and after that, the turbidity of the mud water and excavated soil is discharged to excavate a shaft such as a tunnel. A mud feeding device is installed on the ground and includes a plurality of extensible mud feeding pipes for regulating face pressure, one end of which has a bypass pipe for regulating pressure, and the other end communicating with the face surface, Interruption/stopping of excavation work by connecting a mud feeding pipe for pressure adjustment to the face surface, filling the bypass pipe with muddy water, and constantly sending muddy water at a constant pressure to the mud feeding pipe for regulating face pressure. The pressure on the face is sometimes maintained at a predetermined pressure.

以下に、この発明の好適な実施例を添付図面に
基づいて説明する。
Preferred embodiments of the present invention will be described below with reference to the accompanying drawings.

図は、この発明に係る泥水シールド工法におけ
る切羽圧力保持方法の一実施例を示すものであ
る。
The figure shows an embodiment of a face pressure maintaining method in the muddy water shield construction method according to the present invention.

同図に示す切羽圧力保持方法は、タンク等に貯
留されたベントナイトを含有した泥水を切羽面1
2にポンプ等を介して供給する既設送泥管14
と、泥水シールド掘進機16でもつて掘削した土
砂と泥水の混濁物を排出する排泥管18とを備
え、泥水を供給しながら掘進機を駆動し、トンネ
ル等の坑道を掘削するいわゆる泥水シールド工法
に適用した場合を示すものである。
The method of maintaining pressure at the face shown in the same figure involves pumping muddy water containing bentonite stored in a tank or the like onto the face of the face.
Existing sludge pipe 14 that supplies sludge to 2 via a pump, etc.
and a mud discharge pipe 18 for discharging the muddy soil and muddy water excavated by a mud water shield excavator 16, and the so-called mud water shield construction method in which the excavator is driven while supplying mud water to excavate a shaft such as a tunnel. This shows the case where it is applied to.

そして、同図に示す方法は、以下に示すような
特徴を有するものである。
The method shown in the figure has the following characteristics.

すなわち、同図に示す方法では、上記既設送泥
管14とは別個に切羽圧力調整用送泥管20を設
けており、この送泥管20を備えた送泥装置は、
地上に設置されている。
That is, in the method shown in the figure, a mud feeding pipe 20 for adjusting the face pressure is provided separately from the existing mud feeding pipe 14, and a mud feeding device equipped with this mud feeding pipe 20 is as follows:
It is installed on the ground.

送泥装置は、良質な泥水10、つまり回収した
ベントナイトを一切含有しない新規なベントナイ
トを混合した泥水10を貯蔵したタンク24と、
第1の送泥バルブ26と、サンドポンプ28とを
有し、このサンドポンプ28の出力側は、二叉状
に分岐され、一方は、圧力調整用バルブ30を介
して前記タンク24にリターンする圧力調整用バ
イパス管32であり、他方は、エアー抜きバルブ
34と圧力ゲージ36を備えた圧力タンク38と
なつている。
The mud feeding device includes a tank 24 storing good quality muddy water 10, that is, muddy water 10 mixed with new bentonite that does not contain any recovered bentonite;
It has a first mud feeding valve 26 and a sand pump 28, and the output side of this sand pump 28 is branched into two branches, one of which returns to the tank 24 via a pressure adjustment valve 30. One end is a bypass pipe 32 for pressure adjustment, and the other end is a pressure tank 38 equipped with an air bleed valve 34 and a pressure gauge 36.

この実施例では、圧力タンク38には一対の第
2の送泥バルブ40が設けられ、この送泥バルブ
40にはそれぞれを圧力調整用送泥管20が接続
されている。
In this embodiment, the pressure tank 38 is provided with a pair of second mud feeding valves 40, each of which is connected to a pressure regulating mud feeding pipe 20.

圧力調整用送泥管20の他端は、上記従来工法
で使用する伸縮管やフレキシブルチユーブ等を、
上記掘進機16の近傍に配置し伸長可能としそれ
ぞれ別の切羽面12に連通している。
The other end of the pressure regulating slurry pipe 20 is a telescopic pipe or flexible tube used in the conventional construction method.
It is disposed near the excavator 16, is extendable, and communicates with different face surfaces 12, respectively.

なお、図中42は注水バルブ、44は圧力確認
ゲージを示すものである。
In addition, in the figure, 42 indicates a water injection valve, and 44 indicates a pressure confirmation gauge.

以上の構成において、例えば掘削作業の中断・
中止時に先ず掘進機16を停止し既設送泥管14
および排泥管18のバルブを閉じた後、圧力確認
ゲージ44により圧力を確認して、切羽面12に
直結された圧力計46の支持圧力の低化にあわせ
て送泥バルブ42を開閉して、切羽面12の圧力
が一定になるよう調節する。
In the above configuration, for example, interruption of excavation work,
When stopping, first stop the excavator 16 and open the existing mud pipe 14.
After closing the valve of the sludge drain pipe 18, the pressure is checked using the pressure confirmation gauge 44, and the sludge feeding valve 42 is opened and closed in accordance with the decrease in the supporting pressure of the pressure gauge 46 directly connected to the face 12. , the pressure on the face 12 is adjusted to be constant.

このとき、既設の送、排泥管14,18とは別
に設けた切羽圧力調整用送泥管20には、その一
端にバイパス管32が設けられているので、この
送泥管20に常時一定圧力の泥水10を送出する
ことができ、常時一定圧力の泥水10を送泥管2
0に送出しておけば、送泥管20の他端が切羽面
12に連通しているので、切羽面12の圧力が低
下すると、送泥管20から泥水10が送り込まれ
て、その圧力を上昇させ、また、切羽面20の圧
力が高くなると、バイパス管32の通過量が多く
なつて、切羽面12の圧力を低下させ、自動的に
切羽面12の圧力を所定圧に維持できる。
At this time, since a bypass pipe 32 is provided at one end of the mud feeding pipe 20 for adjusting the face pressure, which is provided separately from the existing mud feeding and mud removal pipes 14 and 18, the mud feeding pipe 20 always has a constant pressure. Mud water 10 at a constant pressure can be sent out through the mud pipe 2.
0, the other end of the mud feeding pipe 20 is in communication with the face surface 12, so when the pressure on the face surface 12 decreases, the muddy water 10 is sent from the mud feeding pipe 20, and the pressure is reduced. When the pressure on the face 20 increases, the amount of passage through the bypass pipe 32 increases, reducing the pressure on the face 12 and automatically maintaining the pressure on the face 12 at a predetermined pressure.

従つて、長時間作業を中止する場合でも、上述
のように上記圧力調整用バイパス管32の作用に
より切羽面12は、常時一定圧力に保持されるた
め、地盤中に泥水10が浸透しても圧力が低化す
ることがなく、また掘削作業の中止前に切羽面1
2を良質の泥水10で充填しておけば、回収ベン
トナイトを含有する泥水よりも分離速度を遅くで
き、切羽面12がより安定し望ましいところであ
る。
Therefore, even when the work is stopped for a long time, the face surface 12 is always maintained at a constant pressure by the action of the pressure regulating bypass pipe 32 as described above, so even if the muddy water 10 penetrates into the ground, The pressure does not drop and the face 1
If 2 is filled with good quality muddy water 10, the separation speed can be made slower than muddy water containing recovered bentonite, and the face 12 will be more stable, which is desirable.

また、上記圧力調整用送泥管20を設置するこ
とは緊急用の切羽圧力保持系統が二系統となり安
全度が増加するだけでなく、例え既設送泥管14
内にベントナイトが沈澱・滞積した場合でも新設
送泥管20を使用して掘削作業ができるため、長
時間停止後の作業の再開はスムーズに行うことが
できる。
In addition, by installing the pressure regulating slurry pipe 20, there are two emergency face pressure holding systems, which not only increases safety, but also increases the safety level even if the existing mud pipe 14
Even if bentonite is precipitated and accumulated in the excavation work, the newly installed mud pipe 20 can be used to carry out the excavation work, so work can be resumed smoothly after a long stoppage.

以上のように本発明方法は、泥水シールド工法
において、一端に圧力調整用のバイパス管を有
し、他端が前記切羽面に連通される伸長可能な複
数の切羽圧力調整用送泥管を備えた送泥装置を地
上に設置し、前記切羽圧力調整用送泥管を前記切
羽面に接続して、前記バイパス管内に泥水を充満
させて前記切羽圧力調整用送泥管に常時一定圧力
の泥水を送出することで、掘削作業の中断・中止
時に前記切羽面の圧力を所定圧に維持するもので
あり、これにより、掘削作業を長時間中止した場
合や、既設送泥管の継ぎ足し時等においても切羽
面の崩壊を確実に防止できる。
As described above, the method of the present invention is a mud shield construction method, which includes a plurality of extensible mud feeding pipes for adjusting face pressure, each having a bypass pipe for regulating pressure at one end and communicating with the face surface at the other end. A mud feeding device is installed on the ground, the mud feeding pipe for adjusting the face pressure is connected to the face surface, the bypass pipe is filled with mud water, and the mud feeding pipe for adjusting the face pressure is constantly supplied with mud water at a constant pressure. By sending out the pressure, the pressure on the face is maintained at a specified pressure when excavation work is interrupted or stopped.This allows the pressure to be maintained at a specified pressure when excavation work is stopped for a long time, when adding to an existing mud pipe, etc. Also, collapse of the face can be reliably prevented.

また、切羽面の圧力を維持する圧力調整用の送
泥管は、その一端にバイパス管が設けてあればよ
いので、構成が簡単で操作が容易に行えるととも
に、作動の確認も簡単にできる。
In addition, the mud feeding pipe for pressure adjustment that maintains the pressure on the face surface only needs to be provided with a bypass pipe at one end, so that the structure is simple, the operation is easy, and the operation can be easily confirmed.

【図面の簡単な説明】[Brief explanation of the drawing]

図はこの発明の一実施例を示す概略図である。 10……泥水、12……切羽面、16……泥水
シールド掘進機(掘進機)、20……圧力調整用
送泥管、30……圧力調整用バルブ、32……圧
力調整用バイパス経路。
The figure is a schematic diagram showing an embodiment of the present invention. DESCRIPTION OF SYMBOLS 10... Mud water, 12... Face surface, 16... Mud water shield excavation machine (excavation machine), 20... Mud feeding pipe for pressure adjustment, 30... Valve for pressure regulation, 32... Bypass path for pressure regulation.

Claims (1)

【特許請求の範囲】[Claims] 1 ベントナイトを含有した泥水を切羽面に供給
しながら掘削し、この後に該泥水と掘削土砂との
混濁物を排出しトンネル等の坑道を掘削する泥水
シールド工法において、一端に圧力調整用のバイ
パス管を有し、他端が該切羽面に連通される伸長
可能な複数の切羽圧力調整用泥管を備えた送泥装
置を地上に設置し、該切羽圧力調整用送泥管を該
切羽面に接続して、該バイパス管内に泥水を充満
させて該切羽圧力調整用送泥管に常時一定圧力の
泥水を送出することで、掘削作業の中断・中止時
に該切羽面の圧力を所定圧に維持することを特徴
とする泥水シールド工法における切羽圧力保持方
法。
1 In the mud shield method, in which muddy water containing bentonite is supplied to the face while excavating, and then the muddy water and excavated soil are discharged to excavate a tunnel or other shaft, a bypass pipe is installed at one end for pressure regulation. A mud feeding device having a plurality of extendable mud pipes for adjusting face pressure, the other ends of which are connected to the face, is installed on the ground, and the mud feeding pipes for adjusting face pressure are connected to the face. By connecting and filling the bypass pipe with muddy water and constantly sending muddy water at a constant pressure to the face pressure adjustment mud feeding pipe, the pressure on the face surface is maintained at a predetermined pressure when excavation work is interrupted or stopped. A method for maintaining face pressure in the muddy water shield method.
JP3909483A 1983-03-11 1983-03-11 Face pressure holding method in muddy water shield construction method Granted JPS59165797A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3909483A JPS59165797A (en) 1983-03-11 1983-03-11 Face pressure holding method in muddy water shield construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3909483A JPS59165797A (en) 1983-03-11 1983-03-11 Face pressure holding method in muddy water shield construction method

Publications (2)

Publication Number Publication Date
JPS59165797A JPS59165797A (en) 1984-09-19
JPH0243874B2 true JPH0243874B2 (en) 1990-10-01

Family

ID=12543487

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3909483A Granted JPS59165797A (en) 1983-03-11 1983-03-11 Face pressure holding method in muddy water shield construction method

Country Status (1)

Country Link
JP (1) JPS59165797A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5061835A (en) * 1973-10-05 1975-05-27

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5061835A (en) * 1973-10-05 1975-05-27

Also Published As

Publication number Publication date
JPS59165797A (en) 1984-09-19

Similar Documents

Publication Publication Date Title
JP5425855B2 (en) Muddy water type shield machine
JP7449633B2 (en) Mud water shield excavator
JP7449634B2 (en) Mud water type shield excavator and its excavation method
JPH0243874B2 (en)
US4848963A (en) Earth pressure shield
JP7427342B2 (en) Mud water type shield excavation machine and compressed air pressure adjustment method in muddy water type shield excavation machine
JP2696396B2 (en) Mud pressurized shield machine
JP7449637B2 (en) Mud water type shield excavator and its excavation method
JP7412860B2 (en) Mud water type shield excavation machine and compressed air pressure adjustment method in muddy water type shield excavation machine
JPH08218771A (en) Sludge type tunnel excavator
JPS5824599B2 (en) Mud water pressurized shield drilling equipment
JP2737826B2 (en) Face-limited underground wall excavator
JP7449636B2 (en) Mud water shield excavator
JP7449635B2 (en) Mud water shield excavator
JP7430026B2 (en) Mud water shield excavator
JP7493887B2 (en) Slurry shield tunneling machine
JP2022072378A (en) Slurry shield machine and segment assembly method
JP7481080B2 (en) Slurry shield tunneling machine
JPH1077784A (en) Tunnel excavator and tunnel excavation method
JPS5923828Y2 (en) Slurry transportation device for excavated soil
JPH06307186A (en) Pit construction by vertical shield
JPH0596194U (en) Mud pressure shield automatic machine mud pressure controller
JPH0235839B2 (en) SHIIRUDOSHIKITONNERUKUTSUSAKUKI
JPS602301Y2 (en) Sediment fluid transport device for shield excavator
JPH02112525A (en) Muddy water caisson technique