JPH02311620A - Underground structure construction method - Google Patents

Underground structure construction method

Info

Publication number
JPH02311620A
JPH02311620A JP1132453A JP13245389A JPH02311620A JP H02311620 A JPH02311620 A JP H02311620A JP 1132453 A JP1132453 A JP 1132453A JP 13245389 A JP13245389 A JP 13245389A JP H02311620 A JPH02311620 A JP H02311620A
Authority
JP
Japan
Prior art keywords
water
retaining wall
ground
excavated
excavator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1132453A
Other languages
Japanese (ja)
Other versions
JP2876076B2 (en
Inventor
Hideo Omura
秀雄 大村
Hiroshi Horie
博 堀江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP1132453A priority Critical patent/JP2876076B2/en
Publication of JPH02311620A publication Critical patent/JPH02311620A/en
Application granted granted Critical
Publication of JP2876076B2 publication Critical patent/JP2876076B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To shorten a construction term as well as to permit easy construction by collecting water in the inner part of an earth retaining wall and excavating the ground in the water, while constructing a structure as balancing buoyancy in parallel with the progress, and installing it in a specified position. CONSTITUTION:An earth retaining wall 1 is set up in the ground, and the inner ground is excavated, setting up an earth anchor 2 there. Next, an assembling pit 3 of an excavator is excavated on the excavating ground, constructing the lower part of an underground structure 4. Then, a pipe body 5 is set up on a bottom part of the structure 4, and water is poured in an inner part of the earth retaining wall, floating the structure on the water. Successively, a lower ground of the structure 4 is excavated in the water by a sand pump excavator 6 with a cutter, and in parallel with progress of this excavation, each upper part of the structure 4 is built up in a series in order on a lower part of the structure 4. In addition, mud produced by excavation at this time is discharged to the outside by a mud discharge pipe 7 and, after it is excavated as far as specified depth, the excavator 6 is removed and the structure 4 is installed. Finally, water is drained and a consolidation material is charged in and around the structure 4.

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、地下構造物あるいはその上に地上部建屋を
有する構造物などの地中構造物を構築する工法、特に構
造物を浮体として山留壁の内部に溜めた水上に浮かべた
上で沈設するようにした工法に関するものである。
Detailed Description of the Invention "Field of Industrial Application" This invention relates to a construction method for constructing an underground structure such as an underground structure or a structure having an above-ground building on top of the underground structure, and in particular, a construction method for constructing an underground structure such as an underground structure or a structure having an above-ground building. This relates to a construction method in which the retaining wall is floated on water stored inside the retaining wall and then submerged.

[従来の技術、発明が解決せんとする問題点」従来、地
中に構造物を築造する工法として、山留支保工による開
削工法や、ニューマチックケーソン、あるいはオーブン
ケーソンによる築造工法などが一般的に知られている。
[Prior art and problems to be solved by the invention] Traditionally, common methods for constructing underground structures include the cut-and-cover method using mountain retaining supports, construction methods using pneumatic caisson, or oven caisson. known to.

しかしながら、山留支保工による開削工法においては、
山留壁外部の地下水圧および土圧によって山留壁へ荷重
が加わるため、山留壁を強固なものとしなければならず
、そのための山留にかかわる工費が嵩むという問題があ
った。
However, in the cut-and-cover method using mountain retaining shoring,
Since groundwater pressure and earth pressure outside the mountain retaining wall apply loads to the retaining wall, the retaining wall must be made strong, which poses a problem in that the construction costs associated with the retaining wall increase.

また、ニューマチックケーソンによる築造工法において
は、圧気内作業による作業者に対する安全性の問題、沈
設に伴って構造物へ偏荷重が作用するという施工の不安
定性、周辺摩擦による沈設不能、高度な掘削精度の要求
、さらには施工時の条件によって定まる作業室スラブと
しての下床版の過大設計など、地中構造物の構築に当っ
て種々の問題があった。
In addition, in the construction method using pneumatic caissons, there are safety issues for workers due to work in pressurized air, instability of construction due to uneven load acting on the structure as it is sunk, impossibility of sinking due to surrounding friction, and advanced excavation. There were various problems when constructing underground structures, such as the requirement for accuracy and over-design of the sub-slab as the work room slab, which was determined by the conditions at the time of construction.

さらに、オーブンケーソン工法においては、掘削中の姿
勢制御、位置制御、掘削が完了してからの耐水圧底版の
地中施工などに問題があった。
Furthermore, the oven caisson construction method had problems with attitude control and position control during excavation, and with underground construction of the hydraulic bottom slab after excavation was completed.

「問題点を解決するための手段」 この発明は前記従来の課題を解決するために、山留壁の
内部に水を溜めて山留壁外部の地下水圧と土圧の一部を
打ち消すことによって、山留壁を簡易化すると共に、築
造しようとする構造物の下部を前記山留壁の内部の水上
に浮かべ、この構造物の下方の地盤を掘削機によって水
中掘削し、この掘削の進行と併行して前記構造物の下部
上に順次構造物の上部を一連に建ち上げ、この構造物の
重量あるいはその内部に注水した水荷重などによって所
定の位置に沈設することにより、ニューマチックケーソ
ン工法の種々の問題を解決することを可能とした地下構
造物の構築工法を提案するものである。
"Means for Solving the Problems" This invention solves the above-mentioned conventional problems by storing water inside the retaining wall and canceling out part of the groundwater pressure and earth pressure outside the retaining wall. In addition to simplifying the mountain retaining wall, the lower part of the structure to be constructed is floated on water inside the mountain retaining wall, the ground below this structure is excavated underwater with an excavator, and the progress of this excavation is monitored. At the same time, the upper part of the structure is built one after another on top of the lower part of the structure, and the pneumatic caisson construction method is carried out by erecting the upper part of the structure one after another and sinking it into a predetermined position by the weight of this structure or the load of water poured into the structure. This paper proposes a construction method for underground structures that can solve various problems.

「実施例j 以下この発明を図面に示す実施例について説明すると、
第1図に示すように構築計画地盤の周辺に鋼矢板、鋼管
あるいは連続地中壁などを打設して山留壁1を設置し、
その内部の地盤を所要深さ掘削してアースアンカー2を
設置すると共に、掘削地盤上に掘削機の組立て用のビッ
ト3を掘削する。
``Example j'' An example of the present invention shown in the drawings will be described below.
As shown in Figure 1, a retaining wall 1 is installed by pouring steel sheet piles, steel pipes, or continuous underground walls around the planned construction ground.
The ground inside the ground is excavated to a required depth and an earth anchor 2 is installed, and a bit 3 for assembling an excavator is excavated on the excavated ground.

この時、周囲の環境が許せば、山留壁を地盤上部に突出
させることにより、上記掘削は省略することができる。
At this time, if the surrounding environment permits, the above-mentioned excavation can be omitted by making the retaining wall protrude above the ground.

ついで、第2図に示すように、掘削地盤上において地中
構造物4の下部を築造し、第3図に示すように構造物4
の底部に掘削機組立て・修理用の管体5を底部下方に連
通して設置し、このなかにカッター付サンドポンプ掘削
機6の組立て部材を通して下方のビット4内で組立てた
後、山留壁1の内部に水を注入して外部の地下水位より
も高く溜め、構造物4を浮かべる。
Next, as shown in FIG. 2, the lower part of the underground structure 4 is constructed on the excavated ground, and the structure 4 is constructed as shown in FIG.
A pipe body 5 for assembling and repairing an excavator is installed at the bottom of the pipe body 5 so as to communicate with the lower part of the bottom, and after passing the assembly member of the sand pump excavator 6 with a cutter through the pipe body 5 and assembling it in the bit 4 below, the mountain retaining wall is installed. Water is injected into the interior of the structure 1 and stored higher than the groundwater level outside, and the structure 4 is floated.

この山留壁内部の水圧によって山留壁1の外部の地下水
圧と土庄の一部を打ち消し、山留壁1を簡易なものとす
ることができる。
This water pressure inside the mountain retaining wall cancels out the groundwater pressure outside the mountain retaining wall 1 and a part of the soil, making it possible to simplify the mountain retaining wall 1.

次に、第4図に示すように、構造物4の下方の地盤を掘
削機6によって水中掘削し、この掘削の進行と併行して
構造物4の下部上に順次構造物4の上部を一連に建ち上
げる。
Next, as shown in FIG. 4, the ground below the structure 4 is excavated underwater using an excavator 6, and as this excavation progresses, the upper part of the structure 4 is successively placed over the lower part of the structure 4. erected in

なお、このとき掘削した泥土は、排泥管7により外部に
排出する。
Note that the mud excavated at this time is discharged to the outside through a mud drain pipe 7.

所定深さ掘削して掘削機6を解体撤去した後、この構造
物の重量あるいはその内部に注水した水荷重等の付加荷
重によって浮力と均衡させながら所定の位置に沈設し、
第5図に示すように浮力が上回る場合には構造物4の底
部をアースアンカー8に緊結して浮力に対抗する。
After excavating to a predetermined depth and dismantling and removing the excavator 6, the structure is sunk in a predetermined position while balancing the buoyancy by the weight of the structure or an additional load such as the water load poured into the structure,
As shown in FIG. 5, if the buoyant force exceeds the buoyant force, the bottom of the structure 4 is tied to the earth anchor 8 to counteract the buoyant force.

最後に、山留壁1内の水を排水しながら、構造物4の周
囲に水中コンクリート等の固結材9を充填して施工を完
了する。
Finally, while draining the water in the retaining wall 1, a consolidation material 9 such as underwater concrete is filled around the structure 4 to complete the construction.

なお、この発明で構築する構造物4は、第5図の地下部
に連続して地上部建屋を建ち上げた構造物を構築する場
合も同様に施工できることはいうまでもない。
It goes without saying that the structure 4 constructed according to the present invention can be similarly constructed in the case of constructing a structure in which an above-ground building is erected continuously to an underground part as shown in FIG.

「発明の効果」 以上の通りこの発明によれば、山留壁の内部に水を溜め
て山留壁外部の地下水圧と土圧の一部を打ち消すので、
山留壁を簡易化してその工費を削減することができると
共に、築造しようとする構造物の下部を山留壁の内部の
水上に27かべ、この構造物の下方の地盤を掘削機によ
って水中掘削し、この掘削の進行と併行して構造物の下
部上に順次構造物の上部を一連に建ち上げるための工期
の短縮を図ることができ、またこの構造物の重量あるい
はその内部に注水した水荷重によって所定の位置に沈設
するので、沈設に伴なって構造物へ偏荷重や周辺摩擦が
作用することもなく、また高度な掘削精度も要求される
ことな(、さらには施工時の条件によって定まる作業室
スラブとしての下床版の過大設計などもなく比較的簡易
に安全に施工できる。
"Effects of the Invention" As described above, according to the present invention, water is stored inside the retaining wall to cancel out part of the groundwater pressure and earth pressure outside the retaining wall.
In addition to simplifying the mountain retaining wall and reducing its construction cost, the lower part of the structure to be constructed is placed 27 times above water inside the mountain retaining wall, and the ground below this structure is submerged using an excavator. It is possible to shorten the construction period for excavating and erecting the upper part of the structure one after another on the lower part of the structure in parallel with the progress of this excavation. Since the structure is sunk into a predetermined position by the water load, there is no uneven load or surrounding friction acting on the structure as it is sunk, and a high degree of excavation precision is not required (and there is no need to worry about the conditions at the time of construction). It can be constructed relatively easily and safely without over-designing the sub-slab as the workroom slab determined by the above.

【図面の簡単な説明】[Brief explanation of drawings]

第1〜6図はこの発明の施工工程を順に示す縦断側面図
である。 ■・・山留壁、2・・アースアンカー、3・・ビット、
4・・構造物、5・・管体、6・・掘削機、7・・排泥
管、 8・・アースアンカー、9・・固結剤。
1 to 6 are longitudinal sectional side views sequentially showing the construction steps of the present invention. ■...Mountain retaining wall, 2...Earth anchor, 3...Bit,
4. Structure, 5. Pipe body, 6. Excavator, 7. Sludge removal pipe, 8. Earth anchor, 9. Consolidation agent.

Claims (1)

【特許請求の範囲】[Claims] 1)山留壁の内部に水を溜めて山留壁外部の地下水圧と
土圧の一部を打ち消し、築造しようとする構造物の下部
を前記山留壁の内部の水上に浮かべ、この構造物の下方
の地盤を掘削機によって水中掘削し、この掘削の進行と
併行して前記構造物の下部上に順次構造物の上部を一連
に建ち上げ、この構造物の重量あるいはこれに付加した
荷重によって浮力と均衡させながら所定の位置に沈設す
ることを特徴とする地中構造物構築工法。
1) Water is stored inside the mountain retaining wall to cancel out part of the groundwater pressure and earth pressure outside the mountain retaining wall, and the lower part of the structure to be constructed is floated on the water inside the mountain retaining wall. The ground below the object is excavated underwater with an excavator, and as this excavation progresses, the upper parts of the structures are erected one after another on the lower parts of the structures, and the weight of this structure or the load added to it is A construction method for underground structures that is characterized by sinking them into a predetermined position while balancing the buoyancy with the buoyancy.
JP1132453A 1989-05-25 1989-05-25 Underground structure construction method Expired - Fee Related JP2876076B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1132453A JP2876076B2 (en) 1989-05-25 1989-05-25 Underground structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1132453A JP2876076B2 (en) 1989-05-25 1989-05-25 Underground structure construction method

Publications (2)

Publication Number Publication Date
JPH02311620A true JPH02311620A (en) 1990-12-27
JP2876076B2 JP2876076B2 (en) 1999-03-31

Family

ID=15081711

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1132453A Expired - Fee Related JP2876076B2 (en) 1989-05-25 1989-05-25 Underground structure construction method

Country Status (1)

Country Link
JP (1) JP2876076B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579045A (en) * 1991-09-24 1993-03-30 Hiroshi Kondo Constructing method for concrete foundation
JPH06272266A (en) * 1993-03-24 1994-09-27 Kajima Corp Method for building underground structure
CN109797760A (en) * 2017-11-17 2019-05-24 李文 Deep foundation pit precipitation buoyant equilibrium working system
CN113373934A (en) * 2021-05-06 2021-09-10 上海建工集团股份有限公司 Foundation pit bottom plate structure and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727321A (en) * 2015-03-31 2015-06-24 广州协安建设工程有限公司 Mud soil excavation method preventing precast pile from inclining and being broken

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579045A (en) * 1991-09-24 1993-03-30 Hiroshi Kondo Constructing method for concrete foundation
JPH06272266A (en) * 1993-03-24 1994-09-27 Kajima Corp Method for building underground structure
CN109797760A (en) * 2017-11-17 2019-05-24 李文 Deep foundation pit precipitation buoyant equilibrium working system
CN113373934A (en) * 2021-05-06 2021-09-10 上海建工集团股份有限公司 Foundation pit bottom plate structure and construction method thereof

Also Published As

Publication number Publication date
JP2876076B2 (en) 1999-03-31

Similar Documents

Publication Publication Date Title
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN112832781A (en) Tunnel construction process
CN110886507B (en) Method for increasing storey and expanding under existing building
Nonveiller Open caissons for deep foundations
JPH02311620A (en) Underground structure construction method
CN107165640A (en) Tunnels and underground engineering surely builds method certainly
JPH06146305A (en) Underwater foundation and installation method thereof
CN209430204U (en) Anti- dash forward of one kind gushes back cover structure
JP2821934B2 (en) Underground structure construction method
JP2588075B2 (en) Underground building construction method
JP2821933B2 (en) Underground structure construction method
JPS6357566B2 (en)
US2164003A (en) Method of building subterranean structures
JP2581602B2 (en) Waste treatment method
JP2536108B2 (en) Foundation construction method for offshore structures
JPS6352193B2 (en)
JP2024092597A (en) Removal method of caisson foundation
Zaťko FOUNDATION OF THE NEW RAILWAY BRIDGE OVER THE NOSICKÁ DAM ON THE RIVER VÁH
JP2576902B2 (en) Construction methods and buildings in landfills
JPS5921831A (en) Reverse placement work
JPH0381420A (en) Sinking method for open caisson
JP2612669B2 (en) Underground tank construction method and underground tank constructed thereby
JPS6331633B2 (en)
JPH04289396A (en) Tunnel construction method
JPH06194485A (en) Construction of nuclear power plant building

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090122

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees