JPH02296915A - Construction method for steel pipe pile head connection part - Google Patents

Construction method for steel pipe pile head connection part

Info

Publication number
JPH02296915A
JPH02296915A JP11574589A JP11574589A JPH02296915A JP H02296915 A JPH02296915 A JP H02296915A JP 11574589 A JP11574589 A JP 11574589A JP 11574589 A JP11574589 A JP 11574589A JP H02296915 A JPH02296915 A JP H02296915A
Authority
JP
Japan
Prior art keywords
steel pipe
connection part
pipe pile
head connection
pile head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11574589A
Other languages
Japanese (ja)
Other versions
JPH0579764B2 (en
Inventor
Mizuki Mori
瑞樹 森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIIGUMI KK
Original Assignee
FUJIIGUMI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIIGUMI KK filed Critical FUJIIGUMI KK
Priority to JP11574589A priority Critical patent/JPH02296915A/en
Publication of JPH02296915A publication Critical patent/JPH02296915A/en
Publication of JPH0579764B2 publication Critical patent/JPH0579764B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Revetment (AREA)

Abstract

PURPOSE:To easily and positively construct a steel pipe pile head connection part by loading positioning fitting members at lower side of hollow frames for constructing the pile head connection part to be mounted on rows of constructed steel pipe piles so that they can be moved, and fitting the fitting members into the upper ends of the respective steel pipe piles, thereafter locking the fitting members. CONSTITUTION:Plural positioning fitting members 17, 17 prearranged to be fitted into the upper ends of respective steel pipe piles 3... respectively are loaded at lower side of hollow frames 16, 16 for constructing a pile head connection part to be mounted on a constructed row 2 of steel pipe piles so that they can moved in the direction of length of the row 1 of the steel pipe piles. The respective positioning fitting members 17, 17 are fitted into the upper ends of the respective steel pipe plies 3..., and the fitting members 17, 17 are locked to the frames 16, 16 in that condition. Successively, concrete is placed into the frames 16, 16, or the frames remain hollow so as to obtain the pile head connection part. Thus, the need for concrete placing forms for constructing the pile head connection part is eliminated, and the pile head connection part can be positively and firmly connected to the row of piles without being affected by irregular intervals of the steel pipe piles 3.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、土留め壁や護岸等に利用される鋼管杭柱列に
於ける頭繋部の構築工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing a head joint in a row of steel pipe pile columns used for earth retaining walls, seawalls, etc.

(従来の技術) 土留め壁や護岸等に利用される鋼管杭柱列の上端には、
当該柱列方向に連続する頭繋部が構築されるが、従来は
、鋼管杭柱列の上部に頭繋部構築用コンクリート型枠を
現場で組立て、当該型枠内に配筋及びコンクリート打設
を行い、コンクリートの養生後に前記型枠を解体除去し
て前記頭繋部を構築していた。
(Conventional technology) At the upper end of a row of steel pipe pile columns used for earth retaining walls and bank protection, etc.
A continuous head joint is constructed in the direction of the column row, but conventionally, a concrete formwork for constructing the head joint is assembled on site at the top of the steel pipe pile column row, and reinforcement is placed and concrete is poured within the formwork. After curing the concrete, the formwork was dismantled and removed to construct the head joint.

(発明が解決しようとする課題) 上記のような従来の頭繋部構築工法では、コンクリート
型枠の現場での組立て作業や解体作業に多大の手間と時
間を要する欠点があった。
(Problems to be Solved by the Invention) The conventional head joint construction method as described above has the drawback that it requires a great deal of effort and time to assemble and dismantle the concrete formwork on site.

(課題を解決するための手段) 本発明は上記のような従来の問題点を解決するために、
構築された鋼管杭柱列上に乗る頭繋部構築用中空フレー
ムの下側に、前記鋼管杭柱列に於ける鋼管杭の上端に各
別に内嵌する複数の位置決め用嵌合部材を柱列長さ方向
に移動可能に装着しておき、各位置決め用嵌合部材を前
記鋼管杭柱列の複数の鋼管杭上端に内嵌させた状態で、
各位置決め用嵌合部材を前記フレームに固定し、当該フ
レーム内にコンクリートを打設するか又は、当該フレー
ムを中空のままで頭繋部とすることを特徴とする鋼管杭
柱列1上部の構築工法を提案するものである。
(Means for Solving the Problems) In order to solve the conventional problems as described above, the present invention has the following features:
A plurality of positioning fitting members that are individually fitted into the upper ends of the steel pipe piles in the steel pipe pile column are installed on the lower side of the hollow frame for constructing the head connection part that rests on the constructed steel pipe pile column. It is mounted so as to be movable in the length direction, and each positioning fitting member is fitted into the upper ends of the plurality of steel pipe piles of the steel pipe pile column row,
Construction of the upper part of the row of steel pipe pile columns 1, characterized in that each positioning fitting member is fixed to the frame, and concrete is poured into the frame, or the frame is left hollow and used as a head connecting part. This project proposes a construction method.

(実施例) 以下に本発明の一実施例を添付の例示図に基づいて説明
する。
(Example) An example of the present invention will be described below based on the attached illustrative drawings.

第1図及び第2図に於いて、1は護岸用鋼管杭柱列であ
り、2は当該鋼管杭柱列lの上端に本発明工法に従って
構築される頭繋部である。
In FIGS. 1 and 2, 1 is a row of steel pipe pile columns for revetment, and 2 is a head connection part constructed at the upper end of the steel pipe pile column row L according to the construction method of the present invention.

前記鋼管杭柱列lは、第3図にも示すように、外周面に
軸心方向に沿った連結部材が突設されていない鋼管杭3
を適当間隔おきに回転させながら圧入し、隣接する鋼管
杭3の間に、画調管杭3の最接近位置の両側で画調管杭
3の外周面に近接する両側縁4a、5aを有する一対の
側板4,5を、画調管杭3間を通る連結部材6で連結一
体化したジャンクション7を所要深さまで圧入すること
により構成したものである。
As shown in FIG. 3, the steel pipe pile column row 1 is a steel pipe pile 3 that does not have a connecting member protruding along the axial direction on the outer peripheral surface.
are press-fitted while rotating at appropriate intervals, and between the adjacent steel pipe piles 3, there are both side edges 4a, 5a close to the outer peripheral surface of the painting pipe pile 3 on both sides of the closest position of the painting pipe pile 3. The pair of side plates 4 and 5 are constructed by press-fitting a junction 7, which is integrally connected by a connecting member 6 passing between the art tube piles 3, to a required depth.

鋼管杭3は、必要な垂直支持強度が得られるように第1
図に示す如く河川床15から所要深さDIまで回転圧入
されるが、全長が長くなるときは、複数本の単位長さの
鋼管杭を現場溶接その他の方法で順次接続して回転圧入
される。
The steel pipe pile 3 is installed at the first
As shown in the figure, rotational press-fitting is carried out from the riverbed 15 to the required depth DI, but when the total length becomes long, multiple unit-length steel pipe piles are sequentially connected by on-site welding or other methods and rotary press-fitted. .

前記ジャンクション7は、既に回転圧入された2本の鋼
管杭3間に、当該側鋼管杭3をガイドにして垂直に圧入
されるが、鋼管杭3間の止水効果を得ることが主たる目
的である場合には、河川床15から当該止水効果を得る
ことの出来る深さD2まで圧入される。勿論、当該ジャ
ンクション7の上端は、鋼管杭3の上端と路間−レベル
に位置する。
The junction 7 is vertically press-fitted between the two steel pipe piles 3 that have already been rotationally press-fitted, using the side steel pipe piles 3 as a guide, but the main purpose is to obtain a water-stopping effect between the steel pipe piles 3. In some cases, it is press-fitted from the river bed 15 to a depth D2 that can provide the water-stopping effect. Of course, the upper end of the junction 7 is located at the upper end of the steel pipe pile 3 and the roadway level.

ジャンクション7の横断面形状は第3図に示すものに限
定されない。又、このように鋼管杭3とジャンクション
7とから構成された鋼管杭柱列1を例示したが、直径方
向両側に横断面C形又はT形の連結部材を鋼管杭の全長
にわたって固着突設された従来の一般的な鋼管矢板のみ
を、隣接する連結部材どうしが互いに嵌合するように柱
列状に圧入して構成された鋼管杭柱列であっても良い。
The cross-sectional shape of the junction 7 is not limited to that shown in FIG. In addition, although the steel pipe pile column row 1 composed of the steel pipe pile 3 and the junction 7 is illustrated as above, connecting members having a C-shaped or T-shaped cross section are fixed and protruded over the entire length of the steel pipe pile on both sides in the diametrical direction. It may also be a steel pipe pile pillar row formed by press-fitting only conventional general steel pipe sheet piles into a pillar row so that adjacent connecting members fit into each other.

上記のように構成された鋼管杭柱列lの上端に頭繋部2
が構築されるのであるが、当該頭繋部2は、第4図〜第
6図に示すように鋼管杭柱列l上に乗る頭繋部構築用中
空フレーム16の下側に、前記鋼管杭柱列1に於ける鋼
管杭3の上端に各別に内嵌する複数(図示例では3つ)
の位置決め用嵌合部材17を柱列長さ方向に移動可能に
装着したものを使用して構築される。
A head connection part 2 is attached to the upper end of the steel pipe pile column row L constructed as described above.
As shown in FIGS. 4 to 6, the head joint 2 is constructed by attaching the steel pipe pile to the underside of the hollow frame 16 for constructing the head joint that rests on the steel pipe pile column row l. A plurality of pieces (three in the illustrated example) that are individually fitted into the upper ends of the steel pipe piles 3 in the column row 1.
It is constructed using a positioning fitting member 17 attached movably in the length direction of the column column.

即ち、前記頭繋部構築用中空フレーム16は、アングル
材等から構成した骨組み18に両側板19のみを張設し
、上下両側と長さ方向両端を開放状態にした横長箱形の
ものであって、底部両側辺には、内向きに溝形ガイドレ
ール20a、20bが設けられ、当該溝形ガイドレール
20a、20bの上側板は、鋼管杭柱列lの上端左右両
側辺を覆うカバープレート21a、21bとなっている
。又、前記各位置決め用嵌合部材17は、鋼管杭3内に
嵌合する有底円筒体22の底部外側に先細り状嵌合ガイ
ド23を突設すると共に、前記頭繋部構築用中空フレー
ム16の溝形ガイドレール2Oa、20bに嵌合する2
つの摺動体24a、24bを有底円筒体22の上端に連
結板25a、25bを介して取付けたものであり、これ
ら頭繋部構築用中空フレーム16及び位置決め用嵌合部
材17は工場に於いて前辺って製造され、現場に搬入さ
れる。
That is, the hollow frame 16 for constructing the head connection part has an oblong box shape in which only the side plates 19 are stretched over a frame 18 made of angle material or the like, and the upper and lower sides and both lengthwise ends are open. Inward groove-shaped guide rails 20a and 20b are provided on both sides of the bottom, and the upper plate of the groove-shaped guide rails 20a and 20b is a cover plate 21a that covers both left and right sides of the upper end of the steel pipe pile column row l. , 21b. Further, each of the positioning fitting members 17 has a tapered fitting guide 23 protruding from the outside of the bottom of the bottomed cylindrical body 22 that fits into the steel pipe pile 3, and the hollow frame 16 for constructing the head connecting portion. 2 that fits into the groove-shaped guide rails 2Oa and 20b of
Two sliding bodies 24a and 24b are attached to the upper end of the bottomed cylindrical body 22 via connecting plates 25a and 25b, and these hollow frame 16 for constructing the head connection part and fitting member 17 for positioning are installed at the factory. The front part is manufactured and delivered to the site.

然して、各位置決め用嵌合部材17がセットされた前記
中空フレーム16を、各嵌合部材17が各鋼管杭3の真
上に位置する状態で鋼管杭柱列1上に吊り降ろし、各嵌
合部材17を鋼管杭3の上端に内嵌させる。このとき鋼
管杭3の間隔にばらつきがあっても、各嵌合部材17は
、ガイドレール20’a、20bの長さ方向(柱列方向
)に中空フレーム16に対し移動可能であるから、先細
り状嵌合ガイド23の誘導作用と相俟って各鋼管杭3に
確実円滑に嵌合することが出来る。
The hollow frame 16 in which each positioning fitting member 17 is set is suspended above the steel pipe pile column row 1 with each fitting member 17 positioned directly above each steel pipe pile 3, and each fitting member 17 is The member 17 is fitted into the upper end of the steel pipe pile 3. At this time, even if there are variations in the spacing between the steel pipe piles 3, each fitting member 17 is movable relative to the hollow frame 16 in the length direction (column row direction) of the guide rails 20'a, 20b. Coupled with the guiding action of the shape fitting guide 23, it is possible to fit each steel pipe pile 3 reliably and smoothly.

このように中空フレーム16を鋼管杭柱列lの上端に載
置したならば、各嵌合部材17の左右−対の連結板25
a、25bをその上側に重なる中空フレーム16側のカ
バープレー)21a、21bにボルトナツト26により
結合して、各嵌合部材17を中空フレーム16に固定す
る。然して、各鋼管杭3の上端やジャンクション7の上
端のレベルのばらつきにより、中空フレーム16を水平
状態で安定させることが出来ない場合には、第6図に示
すように中空フレーム16に於ける四隅、例えばカバー
プレート21a、21bの両端に螺合貫通させたレベル
調整用ボルト27の捻子込み捻子戻しによって、中空フ
レーム16を水平状態で安定的に支持することが出来る
。このとき、各レベル調整用ボルト27を介して中空フ
レーム16を支持する面として、ジャンクション7の内
部で土壌と置換して充填硬化させたモルタル充填部28
を使用することが出来るが、ジャンクション7の上端に
プレートを取付けておき、当該プレートにより前記レベ
ル調整用ボルト27の先端を受けるようにしても良い。
When the hollow frame 16 is placed on the upper end of the steel pipe pile column row l in this way, the left and right pair of connecting plates 25 of each fitting member 17 are
a, 25b are connected to cover plates (21a, 21b) on the side of the hollow frame 16 overlapping with bolts/nuts 26, and each fitting member 17 is fixed to the hollow frame 16. However, if the hollow frame 16 cannot be stabilized horizontally due to variations in the level of the upper ends of the steel pipe piles 3 and the upper ends of the junctions 7, the four corners of the hollow frame 16 may be fixed as shown in FIG. For example, the hollow frame 16 can be stably supported in a horizontal state by screwing and unscrewing the level adjustment bolts 27 screwed through both ends of the cover plates 21a and 21b. At this time, a mortar-filled portion 28 filled with soil and hardened inside the junction 7 serves as a surface that supports the hollow frame 16 via each level adjustment bolt 27.
Alternatively, a plate may be attached to the upper end of the junction 7, and the tip of the level adjustment bolt 27 may be received by the plate.

更に必要ならば、中空フレーム16と鋼管杭柱列1とを
固定するために、各鋼管杭3とこれに内嵌する各嵌合部
材17とを例えば接着剤により互いに固着することが出
来る。
Furthermore, if necessary, in order to fix the hollow frame 16 and the steel pipe pile column row 1, each steel pipe pile 3 and each fitting member 17 fitted therein can be fixed to each other by, for example, an adhesive.

上記のようにして鋼管杭柱列1の上部に、当該柱列方向
に連続するように中空フレーム16を順次セットし、隣
接する中空フレーム16の端部どうしを、中空フレーム
16の両端にある接続用プレート18aを利用してボル
トナツトにより連結する。そして頭繋部2の両端に位置
する中空フレーム16の遊端には、カバープレートを取
付けて閉塞する。この後、各中空フレーム16内及び各
嵌合部材17の有底円筒体22内にコンクリートを打設
し、頭繋部2を構築する。この場合、必要に応じて中空
フレーム16内に配筋して鉄筋コンクリート製とするこ
とも出来るが、この配筋作業は、中空フレーム16を工
場で製造した際に行っておき、工事現場での配筋作業を
なくすことも出来る。勿論、頭繋部2のサイズが小さい
場合には前記中空フレーム16内へのコンクリート打設
は省き、中空フレーム16の上側開口部をカバープレー
トで閉じて、頭繋部2を中空のままにしても良い。
As described above, the hollow frames 16 are sequentially set on top of the steel pipe pile column row 1 so as to be continuous in the direction of the column row, and the ends of the adjacent hollow frames 16 are connected to each other at both ends of the hollow frame 16. They are connected by bolts and nuts using the plate 18a. Then, cover plates are attached to the free ends of the hollow frame 16 located at both ends of the head connecting part 2 to close them off. Thereafter, concrete is placed inside each hollow frame 16 and inside the bottomed cylindrical body 22 of each fitting member 17 to construct the head connecting portion 2. In this case, if necessary, it is possible to arrange reinforcement inside the hollow frame 16 to make it made of reinforced concrete, but this reinforcement work should be done when the hollow frame 16 is manufactured at the factory, and the arrangement at the construction site. Muscle work can also be eliminated. Of course, if the size of the head joint 2 is small, pouring concrete into the hollow frame 16 is omitted, and the upper opening of the hollow frame 16 is closed with a cover plate, leaving the head joint 2 hollow. Also good.

又、第1図、第2図及び第5図に示すように、鋼管杭柱
列1の水面上に露出する上端部外側に鋼板製やコンクリ
ート板製の化粧パネル29を張設する必要がある場合に
は、当該化粧パネル29の上端を前記中空フレーム16
の左右両側下端に形成した化粧パネル取付は部30にボ
ルト31等により取付けることが出来る。更に、第5図
及び第6図に示すように、中空フレーム16そのものに
も、例えば外側を覆う化粧パネル32を張りつけること
も出来るし、第1図及び第2図に示すように、構築した
頭繋部2を遊歩道として利用するときには、手摺り33
やその他、フェンス、花壇等のエフステリア類も設置す
ることが出来る。
Additionally, as shown in Figures 1, 2, and 5, it is necessary to install a decorative panel 29 made of steel plate or concrete plate on the outside of the upper end of the steel pipe pile column row 1 that is exposed above the water surface. In this case, the upper end of the decorative panel 29 is connected to the hollow frame 16.
The decorative panels formed at the lower ends of both left and right sides can be attached to the portion 30 with bolts 31 or the like. Furthermore, as shown in FIGS. 5 and 6, for example, a decorative panel 32 covering the outside can be pasted on the hollow frame 16 itself, or as shown in FIGS. When using the connecting part 2 as a promenade, the handrail 33
In addition, it is also possible to install Efsteria such as fences and flower beds.

(発明の作用及び効果) 本発明工法は以上のように実施し得るものであって、係
る本発明工法によれば、構築された鋼管杭柱列上に頭繋
部構築用中空フレームを、その下側の各位置決め用嵌合
部材が各々鋼管杭上端に内嵌するように移載した後、前
記各嵌合部材と中空フレームとを固定し、必要に応じて
前記中空フレーム内にコンクリートを打設すれば良いの
であるから、鋼管杭柱列上での頭繋部構築用コンクリー
ト型枠の組立て作業やコンクリート養生後の型枠解体除
去作業が全く不要となり、現場での頭繋部製造工数を大
幅に低減することが出来る。
(Operations and Effects of the Invention) The construction method of the present invention can be implemented as described above, and according to the construction method of the present invention, a hollow frame for constructing a head connection part is placed on the constructed steel pipe pile column row. After each lower positioning fitting member is transferred so that it fits inside the upper end of the steel pipe pile, each of the fitting members and the hollow frame are fixed, and if necessary, concrete is poured into the hollow frame. This eliminates the need to assemble concrete formwork for constructing head connections on steel pipe pile column rows and to dismantle and remove formwork after concrete curing, reducing man-hours for manufacturing head connections on site. It can be significantly reduced.

又、複数の前記位置決め用嵌合部材により、前記中空フ
レームを鋼管杭柱列に強固に連結することが出来るので
あるが、当該位置決め用嵌合部材が柱列方向に移動可能
であるから、鋼管杭柱列に於ける各鋼管杭の間隔のばら
つきに影響されずに中空フレームを鋼管杭柱列に確実に
連結することが出来る。
Moreover, the hollow frame can be firmly connected to the steel pipe pile column row by the plurality of positioning fitting members, and since the positioning fitting members are movable in the direction of the column column, the steel pipe The hollow frame can be reliably connected to the steel pipe pile column without being affected by variations in the spacing between the steel pipe piles in the pile column.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は側面図、第2図は縦断正面図、第3図は横断平
面図、第4図は頭繋部構築工法を説明する側面図、第5
図は構築された頭繋部の詳細を説明する縦断正面図、第
6図は同横断平面図であるl・・・護岸用鋼管杭柱列、
2・・・頭繋部、3・・・鋼管杭、7・・・ジャンクシ
ョン、16・・・頭繋部構築用中空フレーム、17・・
・位置決め用嵌合部材、20a20b・・・溝形ガイド
レール、21a、21b・・・カバープレート、22・
・・有底円筒体、23・・・先細り状嵌合ガイド、24
 a、  24 b・・・摺動体、2932・・・化粧
パネル。
Figure 1 is a side view, Figure 2 is a vertical front view, Figure 3 is a cross-sectional plan view, Figure 4 is a side view explaining the construction method for the head joint, and Figure 5 is a side view.
The figure is a longitudinal front view explaining the details of the constructed head joint, and Figure 6 is a cross-sectional plan view of the same.
2... Head connection part, 3... Steel pipe pile, 7... Junction, 16... Hollow frame for constructing the head connection part, 17...
・Fitting member for positioning, 20a20b...Groove guide rail, 21a, 21b...Cover plate, 22・
...Bottomed cylindrical body, 23...Tapered fitting guide, 24
a, 24 b...Sliding body, 2932... Decorative panel.

Claims (1)

【特許請求の範囲】[Claims] 構築された鋼管杭柱列上に乗る頭繋部構築用中空フレー
ムの下側に、前記鋼管杭柱列に於ける鋼管杭の上端に各
別に内嵌する複数の位置決め用嵌合部材を柱列長さ方向
に移動可能に装着しておき、各位置決め用嵌合部材を前
記鋼管杭柱列の複数の鋼管杭上端に内嵌させた状態で、
各位置決め用嵌合部材を前記フレームに固定し、当該フ
レーム内にコンクリートを打設するか又は、当該フレー
ムを中空のままで頭繋部とすることを特徴とする鋼管杭
柱列頭繋部の構築工法。
A plurality of positioning fitting members that are individually fitted into the upper ends of the steel pipe piles in the steel pipe pile column are installed on the lower side of the hollow frame for constructing the head connection part that rests on the constructed steel pipe pile column. It is mounted so as to be movable in the length direction, and each positioning fitting member is fitted into the upper ends of the plurality of steel pipe piles of the steel pipe pile column row,
Each positioning fitting member is fixed to the frame, and concrete is poured into the frame, or the frame is left hollow to serve as the head connection. Construction method.
JP11574589A 1989-05-09 1989-05-09 Construction method for steel pipe pile head connection part Granted JPH02296915A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11574589A JPH02296915A (en) 1989-05-09 1989-05-09 Construction method for steel pipe pile head connection part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11574589A JPH02296915A (en) 1989-05-09 1989-05-09 Construction method for steel pipe pile head connection part

Publications (2)

Publication Number Publication Date
JPH02296915A true JPH02296915A (en) 1990-12-07
JPH0579764B2 JPH0579764B2 (en) 1993-11-04

Family

ID=14670005

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11574589A Granted JPH02296915A (en) 1989-05-09 1989-05-09 Construction method for steel pipe pile head connection part

Country Status (1)

Country Link
JP (1) JPH02296915A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0492035U (en) * 1990-12-27 1992-08-11
JPH0538030U (en) * 1991-10-24 1993-05-21 川崎製鉄株式会社 Steel pipe pile connection fittings
CN106545014A (en) * 2016-11-07 2017-03-29 金陵科技学院 A kind of many pile-type, assembled pile sinking verticality control device
CN108104369A (en) * 2017-12-15 2018-06-01 刘明辉 Constraint composite column structure for building
CN112726614A (en) * 2020-12-24 2021-04-30 中国水电基础局有限公司 Construction method for inland steel pipe pile in comprehensive treatment of bridge construction in plain river

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0492035U (en) * 1990-12-27 1992-08-11
JPH0538030U (en) * 1991-10-24 1993-05-21 川崎製鉄株式会社 Steel pipe pile connection fittings
CN106545014A (en) * 2016-11-07 2017-03-29 金陵科技学院 A kind of many pile-type, assembled pile sinking verticality control device
CN106545014B (en) * 2016-11-07 2018-08-21 金陵科技学院 A kind of more pile-type, assembled pile sinking verticality control device
CN108104369A (en) * 2017-12-15 2018-06-01 刘明辉 Constraint composite column structure for building
CN112726614A (en) * 2020-12-24 2021-04-30 中国水电基础局有限公司 Construction method for inland steel pipe pile in comprehensive treatment of bridge construction in plain river
CN112726614B (en) * 2020-12-24 2022-08-02 中国水电基础局有限公司 Construction method for land steel pipe pile in comprehensive treatment of bridge construction in plain river

Also Published As

Publication number Publication date
JPH0579764B2 (en) 1993-11-04

Similar Documents

Publication Publication Date Title
DE69611931T2 (en) UNDERGROUND CONSTRUCTION, ESPECIALLY FOR THE PRODUCTION OF TUNNELS, UNDERWAYS, UNDERGROUND GARAGE, ETC. AND ITS MANUFACTURING PROCESS
EP2088244B1 (en) Reinforced concrete or composite bridge and method for their production
US4481743A (en) System and method for constructing walls and foundations employing structural components
US4015379A (en) In-ground swimming pool and apparatus and method for constructing same
US4976088A (en) Method for construction of an in-ground swimming pool
JPH02296915A (en) Construction method for steel pipe pile head connection part
CN115162507B (en) Assembled frame beam column connection node and construction method
JP3612600B2 (en) Unit anchor and structural steel foundation beam
JP3084654B2 (en) Construction foundation, foundation structure using the same, and construction method thereof
CH687553A5 (en) Spherical building
CN206396764U (en) A kind of supporting pile column of deep basal pit
JPH0925637A (en) Method of connected construction of pile head and beam
JPH09228653A (en) Aseismicity reinforcing method of building and earthquake-resistant block
JP2001311247A (en) Construction method for concrete structure
JP3114141B2 (en) Basement
KR850002239Y1 (en) A prefab ricated form
JPS61134422A (en) Method of building precast concrete underground continuous wall
JPS6355581B2 (en)
DE7913787U1 (en)
DE19748050A1 (en) Foundation for advertising hoardings, traffic guide displays, acoustic wall shields and fences
JPH0716733Y2 (en) Woodworking floor block
JPH0113751Y2 (en)
JPH0492021A (en) Foundation structure of building and construction method thereof
JPH04128430A (en) Concrete foundation
DE69109650T2 (en) METHOD FOR CONSTRUCTING AN UNDERGROUND CONSTRUCTION, IN PARTICULAR A PARKING GARAGE, WITH OBSTACLES AS E.g. GET TREES.