JPH02269994A - Time switch - Google Patents

Time switch

Info

Publication number
JPH02269994A
JPH02269994A JP27245789A JP27245789A JPH02269994A JP H02269994 A JPH02269994 A JP H02269994A JP 27245789 A JP27245789 A JP 27245789A JP 27245789 A JP27245789 A JP 27245789A JP H02269994 A JPH02269994 A JP H02269994A
Authority
JP
Japan
Prior art keywords
period
load
setting
output
control means
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP27245789A
Other languages
Japanese (ja)
Inventor
Shunkichi Muraoka
村岡 俊吉
Masanori Matsuda
正則 松田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Electric Works Co Ltd
Original Assignee
Matsushita Electric Works Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Electric Works Ltd filed Critical Matsushita Electric Works Ltd
Priority to JP27245789A priority Critical patent/JPH02269994A/en
Priority to DE1989610661 priority patent/DE68910661T2/en
Priority to EP19890203333 priority patent/EP0376409B1/en
Publication of JPH02269994A publication Critical patent/JPH02269994A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G04HOROLOGY
    • G04GELECTRONIC TIME-PIECES
    • G04G15/00Time-pieces comprising means to be operated at preselected times or after preselected time intervals

Abstract

PURPOSE:To prevent the time switch from not being returned to program operation forgetfully by providing a period setting means which turns on a load temporarily. CONSTITUTION:The period wherein the load 7 is turned on is set by the period setting means 1 and when a setting detecting means 3 detects that, a timer means starts clocking the set period and an output control means 5 turns on the load with the output of the means 4 at this time. Then while the means 4 is in the clocking operation, the load 7 is held on and the output of a program control means 6 is ignored. Then the means 5 turns off the load 7 the set period later and the operation which ignores the program is released, the load 7 is controlled thereafter according to a program. Further, the means 5 controls the operation of the load 7 according to the output of the means 6 unless the period wherein the load 7 is turned on is set in the means 1. Thus, the load 7 can be turned on temporarily by the single-time operation for setting the on period of the load 7 by the means 1, so the operation is simplified and an automatic return to program operation is made, so the switch is never held reset forgetfully.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、マイクロコンピュータを内蔵し、プログラム
に従って負荷の動作を制御するタイムスイッチに関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a time switch incorporating a microcomputer and controlling the operation of a load according to a program.

[従来の技術] タイムスイッチとしては、マイクロコンピュータを内蔵
し、プログラムに従って負荷の動作を制御するものがあ
る。ところで、このタイムスイッチにおいて、例えば一
定期間プログラムを無視して負荷をオン状態に保つ、つ
まり一時的に負荷をオンする場合は次のようにしていた
[Prior Art] Some time switches have a built-in microcomputer and control the operation of a load according to a program. By the way, in this time switch, for example, when the program is ignored and the load is kept on for a certain period of time, that is, when the load is temporarily turned on, the following is done.

(1)  タイムスイッチのマニュアルスイッチでオン
する。
(1) Turn on the time switch using the manual switch.

(2)  タイムスイッチの出力に対して並列に接続さ
れたスイッチでオンする。
(2) Turn on with a switch connected in parallel to the time switch output.

(3)−時的なプログラムを入力し、動作の終了後その
プログラムをキャンセルする。
(3)-Enter a temporal program and cancel the program after the operation is completed.

また、この種のタイムスイッチとしては、曜日毎にプロ
グラムを設定でき、これらプログラムからなる週間プロ
グラムに従って負荷の動作を制御するものがある。この
タイムスイッチで数日に及ぶ期間で負荷の動作を休める
場合、従来では次の方法が採られていた。
Further, as this type of time switch, there is one in which a program can be set for each day of the week, and the operation of the load is controlled according to a weekly program made up of these programs. Conventionally, when using this time switch to suspend load operation for a period of several days, the following method was used.

(1)メインブレーカでオフする。(1) Turn off the main breaker.

(2)  タイムスイッチのマニュアルスイッチでオフ
する。
(2) Turn off the time switch using the manual switch.

(3)  タイムスイッチの出力に対して直列に接続さ
れたスイッチでオフする。
(3) Turn off with a switch connected in series to the output of the time switch.

[発明が解決しようとする課題1 しかしながら、上述のように一時的に負荷をオンする場
合、負荷をオンする前後で2回の操作を必要とし、操作
が煩わしいという問題があった。
[Problem to be Solved by the Invention 1] However, when temporarily turning on the load as described above, there is a problem in that two operations are required before and after turning on the load, making the operation cumbersome.

例えば、上記(1)のマニュアルスイッチを用いる方法
によって第32図(b)の斜線で示すように負荷をオン
にする場合、負荷をオンする期間の開始時点1.でマニ
ュアルスイッチをオンし、上記期間の終了時点t2でマ
ニュアルスイッチをオフしなければならない。しかも、
マニュアルスイッチをオフする操作、つまりはプログラ
ム動作に戻す操作を忘れると、作業上のトラブルを生じ
る場合があった。なお、第32図(、)はタイムスイッ
チに設定されたプログラムを示す。
For example, when the load is turned on as shown by the diagonal lines in FIG. 32(b) using the manual switch method described in (1) above, the start point of the period in which the load is turned on is 1. The manual switch must be turned on at t2, and must be turned off at the end of the period t2. Moreover,
If you forget to turn off the manual switch, that is, to return to programmed operation, problems may occur during work. Note that FIG. 32 (, ) shows the program set in the time switch.

ところで、外部信号により負荷を強制的にオン。By the way, the load is forcibly turned on by an external signal.

オフするタイムスイッチが、実開昭59−115386
号公報等にて提案されているが、このようなタイムスイ
ッチでも上述したマニュアルスイッチの場合と同様の問
題が起こる。
The time switch to turn it off is from Utility Model 59-115386.
Although this type of time switch has been proposed in the above-mentioned publications, the same problems as those of the above-mentioned manual switch occur.

さらに、曜日毎にプログラムを設定できるタイムスイッ
チで、−時的なプログラムを入力し、動作の終了後その
プログラムをキャンセルするものが、例元ば特開昭61
−278784号公報等で提供されているが、このプロ
グラムにより負荷を強制的にオン、オフする場合もマニ
ュアルスイッチの場合と同様の問題が起こり、しかもこ
の場合にはプログラムの書換えを必要とし、−時的な負
荷のオン状態を得るために相当の手間がかかる。
In addition, there is a time switch that can set a program for each day of the week, and that inputs a -temporal program and cancels the program after the operation is completed.
- Although it is provided in Publication No. 278784, etc., the same problem as with manual switches occurs when the load is forcibly turned on and off using this program, and in this case, it is necessary to rewrite the program. Considerable effort is required to obtain a temporary load on state.

また、週間プログラムに従って負荷の動作を制御するタ
イムスイッチにおいて、(1)のブレーカを用いる方法
を用いて、数日に及んで負荷をオフする場合、休日に入
る前日に負荷をオフし、休日明けの始業時に負荷をオン
する。ここで、例えば第33図(a)に示すプログラム
が組まれており・休日前には同図(b)の左側の破線で
示すように負荷をオンする必要がある場合や、休日明け
に同図中の右側の破線で示すように負荷をオンする必要
がある場合、同図(a)のような通常の勤務時間内のブ
レーカの操作では斜線部の出力が得られない。
In addition, in a time switch that controls load operation according to a weekly program, when using the method (1) using a breaker to turn off the load for several days, turn off the load the day before a holiday and Turn on the load at the start of work. For example, if the program shown in Figure 33 (a) is set up, there may be cases where it is necessary to turn on the load before a holiday, as shown by the broken line on the left side of Figure 33 (b), or after a holiday. When it is necessary to turn on the load as shown by the broken line on the right side of the figure, the output shown in the shaded area cannot be obtained by operating the breaker during normal working hours as shown in (a) of the figure.

なお、第33図(a)のT゛は休日の期間を示す。そこ
で、斜線部で負荷をオンする場合、休日の開始日まで負
荷がオフするのを待ってブレーカをオフしたり、あるい
は休日明けに早出してブレーカをオンしたりする必要が
あった。しかも、上記ブレーカを用いた方法では、休日
前にタイムスイッチ自身の電源もオフされてしまうので
、休日期間の長さによってはタイムスイッチのメモリの
バックアップ時間を越えでしまい、始業時に再度プログ
ラムを入力しなくてはならない事態が起こる場合もあっ
た。
Note that T' in FIG. 33(a) indicates a holiday period. Therefore, when turning on the load in the shaded area, it was necessary to wait until the start of the holiday to turn off the load and then turn off the breaker, or to turn on the breaker early after the holiday. Moreover, with the above method using a breaker, the power to the time switch itself is turned off before holidays, so depending on the length of the holiday period, the backup time of the time switch's memory may be exceeded, and the program must be input again at the start of work. There were times when situations occurred where I had to do something.

特定発明は上述の魚に鑑みて為されたものであり、その
目的とするところは、−時的に負荷をオンするための操
作が簡単で、プログラム動作に戻し忘れることがないタ
イムスイッチを提供することにある。
The specific invention has been made in view of the above-mentioned problems, and its purpose is to provide a time switch that is easy to operate to temporarily turn on a load and that does not cause the user to forget to return to programmed operation. It's about doing.

また、関連発明は、休日にまたがって負荷をオンする必
要がある場合の負荷のオフや、休日明け、の始業前の負
荷のオンを自動的に行うことがで終るタイムスイッチを
提供することを目的としたものである。
The related invention also provides a time switch that can automatically turn off the load when it is necessary to turn on the load over holidays, and turn on the load before starting work after the holiday. This is the purpose.

[課題を解決するための手段] 上記目的を達成するために、特定発明は、予め設定され
たプログラムに従って負荷を動作させるプログラム制御
手段と、負荷をオンする期間を設定する期間設定手段と
、この期間設定手段で設定が行われたことを検出する設
定検出手段と、上記期間設定手段で設定された設定期間
を計時するタイマ手段と、このタイマ手段のタイマ動作
期間に負荷をオン状態に保持すると共に、設定期間経過
後はプログラム制御手段の出力に応じて負荷の動作を制
御する出力制御手段とを備えている。
[Means for Solving the Problem] In order to achieve the above object, the specified invention provides a program control means for operating a load according to a preset program, a period setting means for setting a period for turning on the load, and a program control means for operating a load according to a preset program; a setting detection means for detecting that the setting has been made by the period setting means; a timer means for timing the setting period set by the period setting means; and a timer means for keeping the load in an on state during the timer operation period of the timer means. The apparatus also includes output control means for controlling the operation of the load according to the output of the program control means after the set period has elapsed.

なお、週間プログラムに従って負荷の動作を制御するタ
イムスイッチにおいて、操作が簡単で、切忘れを防止で
きるようにするには、曜日毎に予め設定されたプログラ
ムからなる週間プログラムに従って負荷を動作させるプ
ログラム制御手段と、負荷をオン状態に保持する数日に
及ぶ期間を日単位で設定する期間設定手段と、この期間
設定手段で設定が行われたことを検出する設定検出手段
と、上記期間設定手段により設定された設定期間を判定
する期間判定手段と、この期間判定手段及びプログラム
制御手段の出力に応じてオン期間を設定するオン期間設
定手段と、設定期間内はオン期間設定手段の出力に応じ
て負荷の動作を制御すると共に、設定期間経過後はプロ
グラム制御手段の出力に応、じて負荷の動作を制御する
出力制御手段とを備え、上記オン期間設定手段では、設
定期間の開始日になった時、αでプログラム制御手段の
出力が負荷をオンする状態となっている場合、設定期間
の開始時点を負荷をオンにするオン期間の開始時点とす
ると共に、設定期間の開始日になりだ時点でプログラム
制御手段の出力が負荷をオフする状態となっている場合
、設定期間内で最初にプログラム制御手段が負荷をオン
する時点をオン期間の開始時点とし、また設定期間の最
終日が終わる時点でプログラム制御手段の出力が負荷を
オンする状態になっている場合、設定期間の終了時点を
オン期間の終了時点とすると共に、設定期間の最終日が
終わる時点でプログラム制御手段の出力が負荷をオフす
る状態になっている場合には、設定期間の最終日の最終
の負荷をオフするプログラム制御手段の出力時点をオフ
期間の終了時、αとしてオン期間を設定するようにすれ
ば良い。
In addition, in order to make the time switch that controls the operation of the load according to a weekly program easy to operate and prevent forgetting to turn it off, program control that operates the load according to a weekly program consisting of a preset program for each day of the week is required. means, a period setting means for setting a period of several days for keeping the load in an on state in units of days, a setting detection means for detecting that a setting has been made by the period setting means, and a period setting means for a period determining means for determining the set period; an on-period setting means for setting the on-period according to the output of the period determining means and the program control means; The on-period setting means controls the operation of the load and also controls the operation of the load according to the output of the program control means after the set period has elapsed. When the output of the program control means turns on the load at α, the start point of the set period is set as the start point of the on period for turning on the load, and the start date of the set period is set. If the output of the program control means is in a state where the load is turned off at this point, the time when the program control means turns on the load for the first time within the set period is the start point of the on period, and the last day of the set period ends. If the output of the program control means is in a state where the load is turned on at the time, the end of the set period is the end of the on period, and the output of the program control means is set to turn on the load at the end of the last day of the set period. When the load is turned off, the on period may be set by setting the output point of the program control means to turn off the final load on the last day of the set period as α at the end of the off period.

なお、上述のように負荷を数日にわたってオンする設定
を数日前から予約設定がで終るようにする場合には、上
記期間設定手段で負荷をオン状態に保持する数日に及ぶ
期間の開始曜日を設定可能とし、この期間設定手段によ
り設定された上記開始曜日を判定する開始曜日判定手段
を設ければ良s0 また、関連発明では上記目的を達成するために、曜日毎
に予め設定されたプログラムからなる週間プログラムに
従って負荷を動作させるプログラム制御手段と、負荷を
オフ状態に保持する数日に及ぶ期間を日単位で設定する
期間設定手段と、この期間設定手段で設定が行われたこ
とを検出する設定検出手段と、上記期間設定手段により
設定された設定期間を判定する期間判定手段と、この期
間判定手段及びプログラム制御手段の出力に応じてオフ
期間を設定するオフ期間設定手段と、設定期間内はオフ
期間設定手段の出力に応じて負荷の動作を制御すると共
に、オフ期間経過後はプログラム制御手段の出力に応じ
て負荷の動作を制御する出力制御手段とを備え、上記オ
フ期間設定手段では、設定期間の開始日になった時点で
プログラム制御手段の出力が負荷をオフする状態となっ
ている場合、設定期間を負荷をオフにするオフ期間とす
ると共に、設定期間の開始日になった時、直でプログラ
ム制御手段の出力が負荷をオンする状態となっている場
合には、設定期間内で最初にプログラム制御手段が負荷
をオフする時点から設定期間の最終日の終了時点までを
オフ期間に設定しである。
In addition, when setting the load to be turned on for several days as described above, if the reservation setting is made several days in advance, the above period setting means can be used to set the starting day of the period for which the load is to be kept on for several days. can be set, and a start day of the week determination means is provided for determining the start day of the week set by the period setting means.Furthermore, in the related invention, in order to achieve the above object, a program is set in advance for each day of the week. a program control means for operating the load according to a weekly program consisting of; a period setting means for setting a period of several days during which the load is kept in an off state; and a period setting means for detecting that settings have been made by the period setting means. a period determining means for determining the set period set by the period setting means; an off period setting means for setting the off period according to the output of the period determining means and the program control means; and output control means for controlling the operation of the load according to the output of the off-period setting means, and after the lapse of the off-period, controlling the operation of the load according to the output of the program control means, the off-period setting means Now, if the output of the program control means is in a state where the load is turned off when the start date of the set period arrives, the set period is set as the off period for turning off the load, and the start date of the set period is set as the off period. If the output of the program control means immediately turns on the load when It is set in the off period.

なお、関連発明において負荷を数日にわたってオフする
設定を数日前から予約設定ができるようにする場合には
、上記期間設定手段で負荷をオフ状態に保持する数日に
及ぷ期間の開始曜日を設定可能とし、この期間設定手段
により設定された上記開始曜日を判定する開始曜日判定
手段を設ければ良い。
In addition, in the related invention, when the setting for turning off the load for several days can be reserved several days in advance, the start day of the period for keeping the load in the off state for several days can be set using the above-mentioned period setting means. It is only necessary to make the period setting possible and to provide a start day of the week determination means for determining the start day of the week set by the period setting means.

さらに、関連発明において負荷の動作を一時的にオンす
る必要が生じる場合を考慮して、負荷の動作を手動でオ
ン、オフするマニュアルスイッチを設けても良い。
Furthermore, in consideration of the case where it is necessary to temporarily turn on the operation of the load in the related invention, a manual switch may be provided to manually turn on and off the operation of the load.

なお、この場合においては切忘れの恐れがあるので、上
記マニュアルスイッチでオフ期間内におチの操作以降で
プログラム制御手段の出力が最初に負荷をオフする状態
となった時点で負荷をオフするようにすると良い。
In this case, there is a risk of forgetting to turn off the switch, so use the manual switch mentioned above to turn off the load when the output of the program control means reaches the state where the load is turned off for the first time after the operation of 1 within the off period. It's good to do this.

[作用1 特定発明は上述のように構成することにより、期間設定
手段で負荷をオンする期間を設定すると、設定期間経過
後はプログラム制御手段による制御状態に自動的に戻り
、期間設定手段による1回の設定操作だけで、負荷を一
時的にオンさせることができるようにし、操作が簡単と
なるようにすると共に、プログラム動作に戻し忘れるこ
ともないようにしたものである。
[Operation 1] By configuring the specified invention as described above, when the period for turning on the load is set by the period setting means, after the set period elapses, the state is automatically returned to the control state by the program control means, The load can be turned on temporarily with only one setting operation, making the operation simple and preventing forgetting to return to program operation.

また、関連発明は上述のように構成することにより、期
間設定手段で負荷をオフする数日に及ぶ期間を設定する
だけで、オフ期間設定手段が休日にまたがって負荷をオ
ンする必要のある場合を設定期日の開始日となった時点
で判断してオフ期間を設定して、休日にまたがって負荷
をオンする必要のある場合に対応で終るようにし、また
設定期オフ期間設定手段がオン期間を設定しで、休日明
けの始業前の負荷のオンも自動的に行えるようにしたも
のである。
Furthermore, by configuring the related invention as described above, when the off-period setting means needs to turn on the load over a holiday, the off-period setting means can simply set a period of several days during which the load is turned off. The off period is set based on the start date of the set deadline, so that if it is necessary to turn on the load over a holiday, the off period is set, and the off period setting means is set during the on period. By setting , it is possible to automatically turn on the load before starting work after a holiday.

[実施例11 第1図乃至第4図に特定発明の一実施例を示す。[Example 11 An embodiment of the specific invention is shown in FIGS. 1 to 4.

本実施例は、予め設定されたプログラムに従ってプログ
ラム制御手段6が負荷7の動作を制御するタイムスイッ
チにおいて、期間設定手段1で負荷7をオンする期間を
設定すると、負荷7を一時的にオンできるようにしであ
る。そして、上記期間設定手段1で設定された期間に負
荷7をオンするため、期間設定手段1で設定が為された
ことを検出する設定検出手段3と、上記期間設定手段1
で設定された期間を計時するタイマ手段4と、このタイ
マ手段4のタイマ動作期間に負荷7をオン状態に保持す
ると共に、設定期間経過後はプログラム制御手段6の出
力に応じて負荷7の動作を制御する出力制御手段5とを
備えている。なお、上記各手段3〜5及びプログラム制
御手段6はマイクロコンピュータ2でソフト的に構成し
である。
This embodiment is a time switch in which a program control means 6 controls the operation of a load 7 according to a preset program, and when a period setting means 1 sets a period for turning on the load 7, the load 7 can be turned on temporarily. That's how it is. In order to turn on the load 7 during the period set by the period setting means 1, a setting detection means 3 for detecting that the period setting means 1 has made a setting;
A timer means 4 keeps the load 7 on during the timer operation period of the timer means 4, and operates the load 7 according to the output of the program control means 6 after the set period elapses. and output control means 5 for controlling. It should be noted that each of the means 3 to 5 and the program control means 6 are configured by software in the microcomputer 2.

以下、負荷7を一時的にオンする動作を説明する。なお
、第2図はこの動作の70−チャートである。まず、期
間設定手段1により負荷7をオンする期間を設定する。
The operation of temporarily turning on the load 7 will be described below. Note that FIG. 2 is a 70-chart of this operation. First, the period setting means 1 sets a period during which the load 7 is turned on.

そして、期間が設定されたことを設定検出手段3が検出
した場合には、タイマ手段4が設定期間の計時を開始し
、このときのタイマ手段4の出力によって出力制御手段
5が負荷7をオンする。その後のタイマ手段4が計時動
作を行っている期間(設定期間T)は第3図(b)に示
すように負荷7はオンした状態に保持される。
When the setting detection means 3 detects that the period has been set, the timer means 4 starts measuring the set period, and the output control means 5 turns on the load 7 based on the output of the timer means 4 at this time. do. During the subsequent period (setting period T) during which the timer means 4 is performing the time counting operation, the load 7 is maintained in the on state as shown in FIG. 3(b).

つまり、この設定期間Tでは出力制御手段5によりプロ
グラム制御手段6の出力が無視される。これは言い換え
れば第3図(&)のプログラムで負荷7をオフにするオ
フプログラムを無視することになる。そして、その設定
期間Tが経過すると、出力制御手段5が負荷7をオフに
し、その後出力制御手段5のプログラムを無視する動作
は解除される。従って、以降はプログラムに従って負荷
7は動作制御される。なお、負荷7をオンする期間が期
間設定手段1により設定されない限り、出力制御手段5
はプログラム制御手段6の出力に従って負荷7の動作制
御を行う。
That is, during this set period T, the output control means 5 ignores the output of the program control means 6. In other words, the off program for turning off the load 7 in the program shown in FIG. 3 (&) is ignored. Then, when the set period T has elapsed, the output control means 5 turns off the load 7, and thereafter the operation of ignoring the program of the output control means 5 is canceled. Therefore, from now on, the operation of the load 7 is controlled according to the program. Note that unless the period for turning on the load 7 is set by the period setting means 1, the output control means 5
controls the operation of the load 7 according to the output of the program control means 6.

ところで、第4図に示すように、プログラムにより負荷
7がオンしている期間に設定期間Tの開始時点と終了時
点とがある場合、同図(b)に示すように、開始時点で
は設定期間T以前の負荷7をオンする状態が継続され、
設定時開Tが経過すると負荷7はオフとなる。なお、こ
の場合は終了時点におけるプログラム制御手段6の負荷
7をオンする出力は無視され、その後プログラム動作に
戻る。
By the way, as shown in FIG. 4, if there is a start point and an end point of the set period T during the period when the load 7 is on according to the program, as shown in FIG. The state where load 7 is turned on before T continues,
When the set time opening T has elapsed, the load 7 is turned off. In this case, the output of the program control means 6 that turns on the load 7 at the time of termination is ignored, and the program operation returns thereafter.

このように本実施例によれば、期間設定手段1により負
荷7をオンする期間を設定するだけの1回の操作で、負
荷7を一時的にオンすることができるので、操作が簡単
になる利点がある。しかも、プログラム動作に自動的に
戻るので、マニエフルスイッチを用いた場合などのよう
に解除忘れが生じない。
In this way, according to this embodiment, the load 7 can be temporarily turned on with a single operation of setting the period for turning on the load 7 using the period setting means 1, which simplifies the operation. There are advantages. Moreover, since the program operation is automatically returned to, there is no need to forget to release the program, unlike when using a manipulative switch.

[実施例21 第5図乃至第8図に特定発明の池の実施例を示す。本実
施例は、曜日毎に予め設定されたプログラムからなる週
間プログラムに従ってプログラム制御手段6が負荷7を
動作制御するタイムスイッチにおいて、期間設定手段1
°で負荷7をオン状態に保持する数日に及ぶ期間T゛を
日単位で設定するようにしたものである。本実施例では
、上記期間設定手段1゛で設定された設定期間T°に負
荷7をオンするため、上記期間設定手段1°により設定
された設定期間T゛を判定する期間判定手段4°を設定
検出手段3の出力に設け、さらにこの期間判定手El 
4 ’及1プログラム制御手段6の出力に基づいてオン
期間を設定するオン期間設定手段8を設けである。なお
、上記オン期間設定手段8は、設定期間T゛の開始日に
なった時点でプログラム制御手段6の出力が負荷7をオ
ンする状態となっている場合、設定期間T゛の開始時点
を負荷7をオンにするオン期間の開始時点とすると共に
、設定期間T゛の開始日になった時点でプログラム制御
手段6の出力が負荷7をオフする状態となっている場合
、設定期間T゛内で最初にプログラム制御手段6が負荷
7をオンする時点をオン期間の開始時点とし、また設定
期間T゛の最終日が終わる時点でプログラム制御手段6
の出力が負荷7をオンする状態になっている場合、設定
期間T°の終了時点をオン期間の終了時7慨とすると共
に、設定期間T゛の最終日が終わる時点でプログラム制
御手段6の出力が負荷7をオフする状態になっている場
合には、設定期間T゛の最終日の最終の負荷7をオフす
るプログラム制御手段6の出力時点をオン期間の終了時
点としてオン期間を設定する。さらに、出力制御手段5
は、設定期間T゛内は上記オン期間設定手段8の出力に
応じて負荷7の動作を制御すると共に、設定期間T゛の
経過後後はプログラム制御手段6の出力に応じて負荷7
の動作を制御する。なお、上記各手段4゛、8はマイク
ロコンピュータ2でソフト的に構成しである。
[Embodiment 21 Figures 5 to 8 show embodiments of the pond of the specific invention. This embodiment is a time switch in which a program control means 6 controls the operation of a load 7 according to a weekly program consisting of a program preset for each day of the week.
The period T', which lasts several days, during which the load 7 is kept in the on state at 100°C, is set in days. In this embodiment, in order to turn on the load 7 during the set period T° set by the period setting means 1', a period determining means 4° is provided for determining the set period T' set by the period setting means 1'. A period determination means El is provided at the output of the setting detection means 3.
4' and 1. On-period setting means 8 is provided for setting the on-period based on the output of the program control means 6. Note that, if the output of the program control means 6 is in a state to turn on the load 7 at the start date of the set period T', the on-period setting means 8 sets the load 7 to the starting point of the set period T'. 7 is the start point of the on period for turning on, and if the output of the program control means 6 is in a state to turn off the load 7 at the start date of the set period T', then within the set period T' The point in time when the program control means 6 turns on the load 7 for the first time is the start point of the on period, and the point in time when the last day of the set period T' ends, the program control means 6 turns on the load 7.
When the output of the load 7 is turned on, the end point of the set period T° is set as the end of the on period, and at the end of the last day of the set period T, the program control means 6 is turned on. When the output is in a state where the load 7 is turned off, the on-period is set with the output point of the program control means 6 that turns off the load 7 on the last day of the set period T'' as the end point of the on-period. . Furthermore, the output control means 5
controls the operation of the load 7 according to the output of the on-period setting means 8 during the set period T'', and controls the operation of the load 7 according to the output of the program control means 6 after the elapse of the set period T''.
control the behavior of It should be noted that each of the above-mentioned means 4' and 8 is constituted by software in the microcomputer 2.

以下、本実施例の動作を第6図の70−チャートに従っ
て説明する。なお、本実施例の場合の期間の設定は負荷
7をオンする日の前日に行う。本実施例のタイムスイッ
チでは、期間設定手段1゛により期間設定が為されたか
どうかを設定検出手段3で検出しており、期間設定され
た場合、期間判定手段4°で設定期間T°を判定する。
The operation of this embodiment will be described below with reference to chart 70 in FIG. In this embodiment, the period is set the day before the day when the load 7 is turned on. In the time switch of this embodiment, the setting detecting means 3 detects whether or not the period has been set by the period setting means 1. If the period has been set, the period determining means 4 determines the set period T°. do.

そして、24時(午前0時)を経過した時点から負荷7
をオンする期間に入る。但し、本実施例では、設定期間
T′の闇ずっと負荷7をオンにするのではなく、次のよ
うにして負荷7をオンする。つまり、24時になった時
点で、オン期間設定手段8がプログラム制御手段6の出
力が負荷7をオンする状態となっているかどうかを判断
する。今、オンする状態になっている場合には、設定期
間T゛の開始時点を負荷7をオンにするオン期間の開始
時点とし、逆に24時になった時点でプログラム制御手
段6の出力が負荷7をオフする状態となっている場合は
、設定期間T゛内で最初にプログラム制御手段6が負荷
7をオンする時点をオン期間の開始時点とする。また、
このオン期間設定手段8では、設定期間T°の最終日が
終わる時点でも、プログラム制御手段6の出力が負荷7
をオンする状態になっているかどうかを判断し、オン状
態となっている場合、設定期間T°の終了時点をオン期
間の終了時点とすると共に、オフする状態になっている
場合には、設定期間T°の最終日の最終の負荷7をオフ
するプログラム制御手段6の出力時、αをオン期間の終
了時点とする。例えば、第7図のように、24時となっ
た時点でプログラム制御手段6の出力が負荷7をオンす
る状態となっていない場合には、設定期間T°内でプロ
グラム制御子Pi6の出力状態が最初に負荷7をオンす
る状態となった時点をオン期間の開始時、ことする。そ
して、第7図に示すように、設定期間T゛の最終日が終
わる時点でプログラム制御手段6の出力が負荷7をオン
する状態になっていない場合、設定期間T゛の最終日の
最終の負荷7をオフするプログラム制御子Pi6の出力
時点をオン期間の終了時点とする。そして、上記オン期
間内ではプログラム制御手段6のオフプログラムを無視
することにより、オン期間の闇負荷7をオン状態に保持
する。なお、設定期間T゛を経過すると、プログラム制
御手段6のオフプログラムを無視する動作を解除するこ
とにより、プログラム動作に自動的に戻る。
Then, from the time when 24:00 (midnight) has passed, load 7
enters a period in which it is turned on. However, in this embodiment, the load 7 is not turned on throughout the darkness of the set period T', but the load 7 is turned on as follows. That is, at 24:00, the on-period setting means 8 determines whether the output of the program control means 6 is in a state where the load 7 is turned on. If it is currently turned on, the start of the set period T' is the start of the on period in which the load 7 is turned on, and conversely, at 24:00, the output of the program control means 6 is turned on. 7 is in a state where the load 7 is turned off, the time when the program control means 6 first turns on the load 7 within the set period T' is the start time of the on period. Also,
In this on-period setting means 8, even at the end of the final day of the setting period T°, the output of the program control means 6 remains unchanged at the load 7.
If it is in the on state, the end of the setting period T° is set as the end of the on period, and if it is in the off state, the setting When the program control means 6 outputs the final turn off of the load 7 on the last day of the period T°, let α be the end point of the on period. For example, as shown in FIG. 7, if the output of the program control means 6 is not in a state to turn on the load 7 at the time of 24 o'clock, the output state of the program control element Pi6 within the set period T° The time when the load 7 is turned on for the first time is defined as the start of the on-period. As shown in FIG. 7, if the output of the program control means 6 is not in a state where the load 7 is turned on at the end of the last day of the set period T', then the final day of the set period T' ends. The output point of the program controller Pi6 that turns off the load 7 is defined as the end point of the on period. Then, by ignoring the off program of the program control means 6 during the on period, the dark load 7 during the on period is maintained in the on state. Note that when the set period T' has elapsed, the program control means 6 automatically returns to the program operation by canceling the operation of ignoring the off program.

ところで、第8図(a)に示すように設定期間T゛の開
始時点及び終了時点で共にプログラム制御手段6で負荷
7をオンするようになっている場合には、オン期間は設
定期間T゛に設定されることになり、この場合には同図
(b)に示すように前日がら設定期間T゛の翌日まで負
荷7をオンすることになる。
By the way, if the load 7 is turned on by the program control means 6 at both the start and end of the set period T', as shown in FIG. 8(a), the on period is equal to the set period T'. In this case, the load 7 is turned on from the previous day until the next day after the set period T', as shown in FIG.

このように本実施例によれば、週間プログラムに従つて
負荷7の動作制御を行うタイムスイッチにおいても、数
日にわたって負荷7をオンすることができ、しかも期間
設定子#ffi 1 ’に負荷7をオンする期間を設定
するだけの1回の操作で、負荷7を数日にわってオンす
ることができ、操作が簡単であり、またこの設定状態は
自動的に解除されるので解除忘れも生じない。
In this way, according to this embodiment, even in the time switch that controls the operation of the load 7 according to the weekly program, the load 7 can be turned on for several days, and the period setter #ffi 1 ' is set to the load 7. The load 7 can be turned on for several days with a single operation of setting the period for turning on the load.It is easy to operate, and since this setting state is automatically canceled, there is no need to forget to cancel it. Does not occur.

[実施例31 第9図乃至第12図に特定発明のさらに他の実施例を示
す。本実施例は、週間プログラムに従って負荷7の動作
制御を行い、数日にわたって負荷7をオンする期間を設
定可能なタイムスイッチにおいて、負荷7を数日にわた
ってオンする設定を数日前から予約設定できるようにし
たものである。
[Embodiment 31 Still another embodiment of the specific invention is shown in FIGS. 9 to 12. This embodiment controls the operation of the load 7 according to a weekly program, and is a time switch that can set the period during which the load 7 is turned on over several days.The time switch allows the setting to turn on the load 7 for several days to be reserved several days in advance. This is what I did.

このために、本実施例では期間設定手段1゛で開始曜日
を設定できるようにすると共に、第9図に示すように開
始曜日を判定する開始曜日判定手段10を設けである。
To this end, in this embodiment, the period setting means 1'' is capable of setting the starting day of the week, and as shown in FIG. 9, a starting day of the week determining means 10 for determining the starting day of the week is provided.

なお、本実施例の場合には開始曜日の設定は当日を除く
向こう1週間の曜日から選択できるようになっている。
In the case of this embodiment, the starting day of the week can be selected from any day of the week for the next week, excluding the current day.

以下、本実施例の動作を第10図の70−チャートに従
って説明する。なお、以下の説明では第11図に示すよ
うに金曜日から土曜日の2日間にわたって負荷7をオン
し、この期間の設定と開始曜日の設定とを月曜日に行っ
た場合について説明する。本実施例でも、期間設定手段
1゛により期間設定及VrM始曜日の設定が為されたか
どうかを設定検出手段3で検出しており、上記設定が月
曜日に行われると、マイクロコンピュータ2のメモリに
開始曜日及び設定期間T°を記憶させておく。
The operation of this embodiment will be described below with reference to chart 70 in FIG. In the following explanation, as shown in FIG. 11, the load 7 is turned on for two days from Friday to Saturday, and the setting of this period and the starting day of the week are performed on Monday. In this embodiment as well, the setting detection means 3 detects whether or not the period setting means 1'' has set the period and the VrM start day of the week. The starting day of the week and the set period T° are stored.

そして、曜日判定手段11では24時(午前0時)を経
過する時点で設定された開始曜日となったかどうかを判
定する。そして、開始曜日となると、”負荷7をオンす
る期間に入る。但し、本実施例の場合にも、設定期間T
゛の間ずっと負荷7をオンにするのではなく、第2の実
施例と同様にしてオフ期間設定手段8がオン期間を設定
して、このオン期間の間負荷7をオンにする。第11図
及び第12図に本実施例の動作説明図を示す。
Then, the day of the week determining means 11 determines whether or not the set starting day of the week has arrived after 24:00 (midnight). Then, when the start day of the week arrives, a period begins in which the load 7 is turned on. However, in the case of this embodiment as well, the set period T
Instead of turning on the load 7 all the time, the off-period setting means 8 sets an on-period and turns on the load 7 during this on-period, similarly to the second embodiment. FIGS. 11 and 12 are diagrams illustrating the operation of this embodiment.

本実施例の場合には最大1週問前から負荷7をオンする
設定ができ、1週間に1回ないしは数回しか人手に触れ
ないような機器の制御に便利である。
In the case of this embodiment, the load 7 can be set to be turned on at most one week in advance, which is convenient for controlling equipment that is only touched by human hands once or a few times a week.

[実施例4] 第13図乃至第21図に関連発明の一実施例を示す。本
実施例は、週間プログラムに従ってプログラム制入御手
Pi6が負荷7を動作制御するタイムスイッチにおいて
、期間設定手段1゛で負荷7をオフする数日にわたる期
間T゛を日単位で設定するようにしたものであり、負?
i!r7をオフする期間の設定は前日に行う。そして、
本実施例の場合には上記期間設定手段1゛及びプログラ
ム制御手段6の出力に基づいてオフ期間を設定するオフ
期間設定手段9を設け、このオフ期間設定手段9をマイ
クロコンピュータ2でソフト的に構成しである。
[Embodiment 4] An embodiment of the related invention is shown in FIGS. 13 to 21. In this embodiment, in a time switch in which the program controller Pi6 controls the operation of the load 7 according to a weekly program, the period setting means 1'' sets a period T'' over several days during which the load 7 is turned off, in units of days. Is it negative?
i! The period during which r7 is turned off is set the previous day. and,
In the case of this embodiment, an off-period setting means 9 is provided for setting an off-period based on the output of the period setting means 1'' and the program control means 6, and this off-period setting means 9 is controlled by software using the microcomputer 2. It is composed.

なお、上記オフ期間設定手段9では、設定期間T゛の開
始日になった時点でプログラム制御手段6の出力が負荷
7をオフする状態となっている場合、設定期間T°を負
荷7をオフにするオフ期間とすると共に、設定期間T゛
の開始日になった時、αでプログラム制御手段6の出力
が負荷7をオンする状態となっている場合には、設定期
間T゛内で最初にプログラム制御手段6が負荷7をオフ
する時点から設定期間T゛の最終日の終了時点までをオ
フ期間に設定するようにしである。
Note that if the output of the program control means 6 is in a state to turn off the load 7 at the start date of the set period T, the off period setting means 9 sets the set period T° to turn off the load 7. In addition, if the output of the program control means 6 is in a state to turn on the load 7 at α when the start date of the set period T' arrives, the first off period within the set period T' The off period is set from the time when the program control means 6 turns off the load 7 to the end of the last day of the set period T'.

以下、本実施例の動作を!1514図の70−チャート
に従って説明する0本実施例のタイムスイッチでも、期
間設定手段1°で期間設定されたかどうかを設定検出手
段3で検出しており、期間設定された場合、期間判定手
段4゛で設定期間T゛を判定する。そして、24時を経
過した時点から負荷7をオフする設定期間T゛に入る。
Below is the operation of this example! In the time switch of this embodiment, which will be explained according to the chart 70 in Fig. 1514, the setting detecting means 3 detects whether or not the period is set by the period setting means 1°, and if the period is set, the period determining means 4 The set period T is determined by . Then, after 24 hours, a set period T' in which the load 7 is turned off begins.

但し、本実施例では、設定期間T°の間ずっと負荷7を
オフ状態に保持するのではなく、次のように負荷7をオ
フする。つまり、24時になった時、αで、オフ期間設
定手段9がプログラム制御手段6の出力が負荷7をオン
する状態となっているかどうかを判断する。今、第15
図に示すようにオフする状態になっている場合、設定期
間T゛をそのまま負荷7をオフするオフ期間として設定
する。そして、上記オフ期間内ではプログラム制御手段
6のオンプログラムを無視することにより、オフ期間の
間負荷7をオフ状態に保持する。なお、設定期間T゛を
経過すると、プログラム制御手段6のオンプログラムを
無視する動作を解除することにより、プログラム動作に
自動的に戻る。
However, in this embodiment, instead of keeping the load 7 in the off state throughout the set period T°, the load 7 is turned off as follows. That is, at 24:00, the off period setting means 9 determines whether the output of the program control means 6 is in a state to turn on the load 7 at α. Now, the 15th
When the load 7 is turned off as shown in the figure, the set period T' is directly set as the off period during which the load 7 is turned off. Then, by ignoring the on program of the program control means 6 during the off period, the load 7 is kept in the off state during the off period. Note that when the set period T' has elapsed, the program control means 6 automatically returns to the program operation by canceling the operation of ignoring the on-program.

ところで、第16図(a)に示すように、24時になっ
た時点で、オフ期間設定手段9がプログラム制御手段6
の出力が負荷7をオンする状態となりていると、設定期
間T゛内で最初にプログラム制御手段6が負荷7をオフ
する時点から設定期間T゛の最終日の終了時点までをオ
フ期間に設定する。
By the way, as shown in FIG. 16(a), at 24:00, the off period setting means 9 starts the program control means 6.
When the output of is in a state to turn on the load 7, the off period is set from the time when the program control means 6 first turns off the load 7 within the set period T' to the end of the last day of the set period T'. do.

つまり、設定期間T°の前日から開始日にかけて負荷7
をオンする必要がある場合に、第16図(b)に示すよ
うにその前日からの負荷7のオン状態は設定期間T゛内
であっても継続し、この動作が終了する時点から負荷7
をオフするオフ期間となるようにしたものである。
In other words, from the day before the set period T° to the start date, the load 7
When it is necessary to turn on the load 7, as shown in FIG. 16(b), the on state of the load 7 from the previous day continues even within the set period T', and from the time this operation ends, the load 7
This is an off period in which the power is turned off.

このように本実施例によれば、期間設定手段1゛で負荷
7をオンする期間を設定すれば、休日にまたがって負荷
7をオンする必要がある場合はその負荷7のオン状態を
自動的に継続することができ、ブレーカを用いて負荷7
をオフする場合のように休日前に負荷7がオフするのを
待ってブレーカを切るといった操作は不要となる。また
、設定期間T°の経過後には自動的にプログラム動作に
戻るので、休日明けの始業前の負荷7のオンを自動的に
行え、早出してブレーカをオンするといった操作が不要
になり、省人力比を図ることができる。しかも、本実施
例ではン7ト的に負荷7をオフしているので、ブレーカ
で負荷7のオフを行う場合のように、タイムスイッチの
メモリのバックアップ時間を越えるという問題も起こら
ない。
In this way, according to this embodiment, by setting the period during which the load 7 is to be turned on using the period setting means 1'', if it is necessary to turn on the load 7 over a holiday, the on state of the load 7 can be automatically changed. Load 7 can be continued using the breaker.
It is no longer necessary to wait for the load 7 to be turned off before a holiday before turning off the breaker, as in the case of turning off the breaker. In addition, since it automatically returns to the program operation after the set period T° has elapsed, the load 7 can be automatically turned on before the start of work after a holiday, eliminating the need to turn on the breaker early and saving time. It is possible to measure the human power ratio. Moreover, in this embodiment, since the load 7 is turned off automatically, the problem of exceeding the backup time of the time switch memory does not occur, unlike when the load 7 is turned off using a breaker.

このタイムスイッチの操作部の外観を第17図及び第1
8図に示す。なお、第17図は1回路出力タイプで、第
18図は2回路出力タイプのものである。このタイムス
イッチの操作部には、上述した負荷7をオフする期間の
設定を行うモードスイッチSW、、セレクトスイッチS
W2、アノヤストスイッチSW、及びエンタースイッチ
SW、を設けてあり、期間の設定は操作部の備えるLC
D等の表示部11の表示を見ながら行う。なお、このタ
イムスイッチのスイッチSW1〜SW、は、時刻設定、
プログラム設定、あるいはプログラムモニタ等の操作用
として兼用されている。また、その他にサマータイム用
に±1時間ずつ”時”をずらす暗闇切換スイッチSW1
、プログラムのキャンセルを行う際に操作するキャンセ
ルスイッチSW6、マニュアル操作により負荷7をオン
、オフする場合に操作されるマニュアルスイッチS W
 7を備えている。ここで、マニュアルスイッチS W
 7では、負荷7のマニュアル操作によるオン、オフ状
態を解除できるように、プログラムによる自動制御状態
に切り換えることがで終るようになっている。
Figures 17 and 1 show the appearance of the operating section of this time switch.
It is shown in Figure 8. Note that FIG. 17 shows a one-circuit output type, and FIG. 18 shows a two-circuit output type. The operation section of this time switch includes a mode switch SW for setting the period during which the load 7 is turned off, and a select switch S.
W2, an anoyast switch SW, and an enter switch SW are provided, and the period can be set using the LC provided in the operation section.
This is done while looking at the display on the display unit 11 such as D. In addition, switches SW1 to SW of this time switch are for time setting,
It is also used for program settings, program monitor operations, etc. In addition, there is also a darkness selector switch SW1 that shifts the "hour" by ±1 hour for daylight saving time.
, a cancel switch SW6 that is operated when canceling a program, and a manual switch SW6 that is operated when turning the load 7 on and off manually.
It has 7. Here, manual switch SW
7, the on/off state of the load 7 by manual operation can be canceled by switching to an automatic control state by a program.

このタイムスイッチの表示部11では、24時間表示に
より”時”を表示する時表示と、分表示、この時刻表示
の下に表示され曜日を数値で表示する曜日表示「1」、
・・・、「7」、上記時刻表示に時刻が表示されている
ことを示すタイム表示rTIMEJ、上記時刻表示にプ
ログラム内容が表示されていることを示すプログラム表
示[PROG、J、負荷7への出力状態がオンとなって
いることを示すオン表示「I]、負荷7への出力状態が
オフとなっていることを示すオフ表示「0」、マニュア
ルスイッチSW7を自動に操作した際に自動状態を表示
する自動表示rPJ、暗闇切換スイッチSW5でサマー
タイムに設定された場合にサマータイムであることを表
示するサマータイム表示「S」が行われる。
The display section 11 of this time switch has a 24-hour hour display, a minute display, and a day display "1" that displays the day of the week numerically below the time display.
..., "7", time display rTIMEJ indicating that the time is displayed on the above time display, program display [PROG, J, to load 7] indicating that the program content is displayed on the above time display. On display "I" indicates that the output state is on, Off display "0" indicates that the output state to load 7 is off, automatic state when manual switch SW7 is operated automatically When daylight saving time is set with the darkness changeover switch SW5, a daylight saving time display "S" is performed to indicate that it is daylight saving time.

なお、このタイムスイッチの操作部にはタイムスイッチ
への電源の供給状態を示す表示器12も設けである。
The operating section of the time switch is also provided with a display 12 that indicates the state of power supply to the time switch.

以下、この操作部により負荷7をオフする期間を設定す
る操作について説明する。この期間の設定はモードスイ
ッチSW、を押して選択する。この期間設定モードとな
ると、表示部11の時表示部分に第19図(a)に示す
期間設定モードを示す[HO]という文字と、分表示部
分に設定期間を設定する箇所を示す「−一」が表示され
る。そして、セレクトスイッチS W 2を押すと、第
19図(b)に示すように「−一」がブリンクしく2 
Hz)、期間設定を行える状態を示す。そして、この「
−一」部分に7ノヤストスイツチS W 3を押して第
19図(e)に示すように任意の期間を設定する。なお
、このタイムスイッチでは最大99日間まで設定できる
ようになっている。この期間設定を行った後に、エンタ
ースイッチS W 4を押すと、第19図(d)に示す
ように定常モードである時刻表示状態に戻り、このとき
負[7をオフする期間が設定される。ところで、期間の
変更を行うときには上述したと同様の操作により期間を
表示させ、この期間をアジャストスイッチSW、により
変更すれば良い。なお、この変更の際に、負荷7をオフ
する期間となっていない場合には、期間設定モードから
定常モードに戻って第19図(d)に示す現在時刻表示
が行われるのであるが、負荷7をオフする期間となって
いる際に設定変更を行った場合には、期間設定モードか
ら時刻表示モードに戻った際に、第19図(e)に示す
ように、負荷7をオフしていることを示すオフ表示[0
]がブリンクして、設定期間となっていることを示す。
Hereinafter, the operation of setting the period during which the load 7 is turned off using this operation unit will be explained. The setting of this period is selected by pressing the mode switch SW. When this period setting mode is entered, the characters [HO] indicating the period setting mode as shown in FIG. " is displayed. Then, when the select switch S W 2 is pressed, "-1" blinks and changes to 2 as shown in FIG. 19(b).
Hz), indicates a state in which the period can be set. And this “
-1" section, press the 7-stop switch SW3 to set an arbitrary period as shown in FIG. 19(e). Note that this time switch can be set for up to 99 days. After setting this period, press the enter switch SW4 to return to the time display state, which is the steady mode, as shown in FIG. . By the way, when changing the period, the period may be displayed by the same operation as described above, and this period may be changed using the adjustment switch SW. Note that when this change is made, if it is not the period to turn off the load 7, the period setting mode returns to the steady mode and the current time is displayed as shown in FIG. 19(d). If the setting is changed during the period in which the load 7 is turned off, when returning from the period setting mode to the time display mode, the load 7 is turned off as shown in Fig. 19(e). Off display [0
] blinks to indicate that the set period is reached.

ところで、上記設定をキャンセルすることも必要である
が、この場合には第19図(c)に示すように[−−1
表示がブリンクしている状態で、エンタースイッチSW
4を押せば、第19図(「)に示す現在時刻表示が為さ
れた時点で設定期間はキャンセルされる。ここで、設定
のキャンセルはマニュアルスイッチSWフにより負荷7
の動作を制御することによってら可能である。
By the way, it is also necessary to cancel the above settings, but in this case, as shown in FIG. 19(c), [--1
While the display is blinking, press the enter switch SW.
4, the setting period will be canceled when the current time shown in Fig. 19 () is displayed.Here, the setting period can be canceled by pressing the manual switch SW.
This is possible by controlling the operation of

なお、この場合のマニュアルスイッチSW、の操作は、
プログラムに関係なく連続的に負荷7の動作状態を一定
にする所謂パーマネント操作である。
In addition, the operation of the manual switch SW in this case is as follows.
This is a so-called permanent operation that continuously keeps the operating state of the load 7 constant regardless of the program.

そして、設定期間になると、負荷7がオフに制御される
のであるが、上述したように設定期間とその前日との間
にかけて負荷7をオンするプログラムがある場合、プロ
グラム′により負荷7がオフされるまで負荷7はオン状
態のままとなり、この場合には第19図(g)に示すよ
うに設定期間となっていることを、オン表示[Jをブリ
ンクする(o。
Then, when the set period comes, the load 7 is controlled to be turned off. However, as mentioned above, if there is a program that turns on the load 7 between the set period and the previous day, the load 7 is turned off by the program'. The load 7 remains on until the set period is reached, and in this case, as shown in FIG. 19(g), the on display [J blinks (o) to indicate that the set period has come.

5Hz)することで表示する。5Hz).

ところで、上記実施例のタイムスイッチはマニュアルス
イッチSW、を備えでいるので、920図(a)に示す
ように、例えば休日の前日Fら休日期間にわたるオンプ
ログラムがあり、休日前に負荷7をオフじたい状況が生
じたような場合に、同図(b)に示すようにマニュアル
スイッチsw、にょって負荷7をオフすることができる
、また、121図に示すように休日中の一定期間だけ負
荷7をオンしたりすることもできる。なお、この場合に
は、第21図(a)に示すようにプログラム制御手段6
から負荷7をオフする出力が出力された時点で、負荷7
を自動的にオフするようにしておくと、切忘れを防止す
ることができて便利である。なお、上記マニュアルスイ
ッチSW、は現在の負荷7の動作状態を反転するもので
あっても良い。
By the way, since the time switch of the above embodiment is equipped with a manual switch SW, as shown in FIG. If an emergency situation occurs, the load 7 can be turned off using the manual switch sw as shown in Figure 12(b), or the load 7 can be turned off for a certain period of time during holidays as shown in Figure 121. You can also turn on 7. In this case, as shown in FIG. 21(a), the program control means 6
When the output to turn off load 7 is output from
It is convenient to turn off the switch automatically to prevent forgetting to turn it off. Note that the manual switch SW may be one that reverses the current operating state of the load 7.

[実施例51 第2217乃至#1I31図に関連発明の他の実施例を
示す0本実施例は、第4の実施例のタイムスイッチにお
いて、負荷7を数日にわたってオフする設定を数日前か
ら予約設定で終るようにしたものである。このために、
本実施例では期間設定手段1゛で開始曜日を設定できる
ようにすると共に、第22図に示すように開始曜日を判
定する開始曜日判定手段10を設けである。
[Embodiment 51 Figures 2217 to #1I31 show other embodiments of the related invention. In this embodiment, in the time switch of the fourth embodiment, the setting to turn off the load 7 for several days is reserved several days in advance. This ends with the settings. For this,
In this embodiment, the period setting means 1'' can set the starting day of the week, and as shown in FIG. 22, a starting day of the week determining means 10 for determining the starting day of the week is provided.

本実施例の動作は第23図の70−チャートを示し、第
24図及び第25図に金曜日から土曜日の2日問にわた
って負荷7をオフする場合のタイムチャートを示す、な
お、本実施例の動作は上述の各実施例の動作説明から容
易に理解できるので説明は省略する。
The operation of this embodiment is shown in the chart 70 in FIG. 23, and FIGS. 24 and 25 show time charts when the load 7 is turned off for two days from Friday to Saturday. Since the operation can be easily understood from the explanation of the operation of each embodiment described above, the explanation will be omitted.

このタイムスイッチの外観図を第26図及び第28図に
示す、このタイムスイッチは、前面の上部に表示1’i
13を備え、その表示部13の下方に複数のスイッチS
W、、〜S W、、を配置してあり、下部に電源線や負
衡線を接続する接続端子14を配設しである。このタイ
ムスイッチのケースはボディ20とカバー21とからな
り、第28図(d)の背面図に示すように、ボディ20
内に収納されたプリント基板22上に表示部13及び出
力制御用のリレー23等を実装しである。なお、接続端
子14の端子板14aはプリント基板22に直接に接続
してあり、カバー21の接続端子14部分には第28図
(a)に破線で示す開田自在な蓋21aを取り付ける構
造となっている。
The external view of this time switch is shown in Fig. 26 and Fig. 28.
13, and a plurality of switches S are provided below the display section 13.
W, . . . ~S W, , are arranged, and a connection terminal 14 for connecting a power supply line and a negative balance line is arranged at the bottom. The case of this time switch consists of a body 20 and a cover 21, and as shown in the rear view of FIG.
A display section 13, a relay 23 for output control, etc. are mounted on a printed circuit board 22 housed inside. The terminal board 14a of the connection terminal 14 is directly connected to the printed circuit board 22, and a lid 21a that can be opened freely is attached to the connection terminal 14 portion of the cover 21 as shown by the broken line in FIG. 28(a). ing.

このタイムスイッチの操作部には、第26図に示すよう
に、負荷7をオフする期間の設定を什うモードスイッチ
SW、、、セレクトスイッチ5WI2、セットスイッチ
SW、コを設けてあり、期間設定は表示部13の表示を
見て行う、なお、このタイムスイッチでもスイッチSW
、〜SW、、は、時刻設定、プログラム設定、プログラ
ムモニタ等の操作用として兼用されると共に、サマータ
イムの設定用にも用いられる。また、このタイムスイッ
チでは、プログ2ムをモニタするために表示部13にプ
ログラムの内容を表示させる呼出スイッチSW1いマニ
ュアル操作により負荷7をオン、オフする場合に操作さ
れるマニュアルスイッチSW、、、負荷7を制御する信
号をタイマ出力とパルス出力とに切り換える出力状態切
換スイッチSW、、を備えている。なお、タイマ出力と
は上述した期間設定の際の出力で、パルス出力とはパル
ス的に出力をオフする出力であり、負荷をオフする期間
の設定に際しては出力状態切換スイッチSW、、をタイ
マ出力側に切り換えておく。ここで、出力状態をパルス
出力とする場合の設定もスイッチSW、、〜SW、、で
打う。
As shown in FIG. 26, the operation section of this time switch is provided with a mode switch SW, a select switch 5WI2, and a set switch SW, which are used to set the period during which the load 7 is turned off. This is done by looking at the display on the display unit 13. Note that this time switch also uses switch SW.
, ~SW, are used for operations such as time setting, program setting, and program monitor, and are also used for setting summer time. This time switch also includes a call switch SW1 that displays the contents of the program on the display unit 13 in order to monitor the program, and a manual switch SW1 that is operated when turning on and off the load 7 by manual operation. It is provided with an output state changeover switch SW for switching the signal for controlling the load 7 between a timer output and a pulse output. Note that the timer output is the output when setting the period mentioned above, and the pulse output is the output that turns off the output in a pulse-like manner.When setting the period for turning off the load, the output state changeover switch SW is used as the timer output. Switch it to the side. Here, settings for setting the output state to pulse output are also made using switches SW, . . . -SW, .

このタイムスイッチの表示WS13では、24時間表示
により”時”を表示する時表示と、分表示、秒表示、こ
の時刻表示の下に表示され曜日を数値で表示する曜日表
示「月」、・・・、「日J、時刻表示が時刻を表示して
いることを示す時刻呼出表示「時刻呼出」、時刻表示が
プログラム内容を表示していることを示すプログラムモ
ニタ表示「プログラムモニタ」、負荷7への出力状態が
オンとなっていることを示すオン表示「入」、負荷7へ
の出力状態がオフとなっていることを示すオフ表示「切
」、マニュアルスイッチS W tを自動に操作した際
に自動状態を表示する自動表示「連続」、サマータイム
設定が為された場合にサマータイムであることを表示す
るサマータイム表示(プログラム設定モード表示の右横
の太陽マーク)である。なお、このタイムスイッチの操
作部には電源の供給状態を示す電源表示器15と、負荷
ブへの出力状態を示す出力表示器16とを備えている。
This time switch display WS13 has a 24-hour hour display, a minute display, a second display, and a day display "month" that displays the day of the week numerically below the time display.・, "Day J, time call display "Time call" indicating that the time display is displaying the time, program monitor display "Program monitor" indicating that the time display is displaying program content, to load 7 The on display is "ON" indicating that the output status is on, the off display is "off" indicating that the output status to load 7 is off, and when the manual switch S W t is automatically operated. ``Continuous'' is the automatic display that displays the automatic status, and the summer time display (the sun mark on the right side of the program setting mode display) indicates that it is summer time when daylight saving time is set. The operating section of this time switch is equipped with a power display 15 that indicates the state of power supply and an output display 16 that indicates the state of output to the load.

以下、この操作部により期間及び開始曜日を設定する操
作について説明する。この負荷7をオフする期間の設定
はモードスイッチSW、、を押して選択する。この期間
設定モードとなると、表示部13の時表示の部分に第2
7図(a)に示すように期間設定モードを示す「HO」
という文字が表示され、分表示の部分に設定期間を設定
する箇所を示す「−一」が表示される。そして、セレク
トスイッチSW1□を昂、すと、第27図(b)に示す
ように「−一」がプリンクしく2 Hz)、期間設定を
行える状態を示す、そして、二の「−一」部分にセット
スイッチSW、、を押して第27図(e)に示すように
任意の期間を設定する。なお、このタイムスイッチでは
最大99日問まで設定でき、セットスイッチ5W13を
1秒以上押し続けると、数値が8Hzで早送りされる。
The operation of setting the period and starting day of the week using this operation unit will be described below. The setting of the period during which the load 7 is turned off is selected by pressing the mode switch SW. When this period setting mode is entered, a second
As shown in Figure 7(a), “HO” indicates the period setting mode.
The characters "-1" are displayed in the minute display section to indicate where to set the setting period. Then, when the select switch SW1□ is turned on, the "-1" will be switched to 2 Hz) as shown in FIG. 27(b), indicating that the period can be set. Press the set switch SW, , to set an arbitrary period as shown in FIG. 27(e). Note that this time switch allows you to set up to a maximum of 99 days, and if you keep pressing the set switch 5W13 for 1 second or more, the numerical value will be fast-forwarded at 8 Hz.

この期間設定を行った後に、セレクトスイッチSW目を
押すと、このオフ期間の設定を打った曜日である月曜を
示す曜日表示「月1が第27図(d)に示すようにプリ
ンクしく2 Hz)、開始曜日を設定で終ることを示す
。そ・して、セットスイッチSW、ffを押して、月曜
日を除く他の曜日のいずれかを選択する。つまり、この
タイムスイッチで開始曜日の設定を当日を除(向こう1
週間の曜日から選択できるようになっている。ここでは
、第27図(e)に示すように會躍日を選択した場合を
示す。上記期間設定及び開始曜日の設定を行った後、モ
ードスイッチSW、で定常モードに切り換えることによ
り、期間と開始曜日との設定が完了する。この際には第
27図(f)に示すように現在時刻と現在の負荷7の動
作状態が表示されると′共に、開始曜日を示す「會」表
示がプリンクする(O、5Hz)ことで、負荷7をオフ
する期間が予約設定されでいることが分かるようになっ
ている。
After setting this period, when you press the select switch SW, the day of the week display indicating Monday, which is the day of the week when this off period setting was entered, will be displayed. ), indicates that the start day of the week is set and ends.Then, press set switch SW, ff to select any other day of the week except Monday.In other words, use this time switch to set the start day of the week. (over 1
You can choose from days of the week. Here, a case is shown in which the meeting date is selected as shown in FIG. 27(e). After setting the period and starting day of the week, the setting of the period and starting day of the week is completed by switching to the steady mode with the mode switch SW. At this time, as shown in Fig. 27(f), the current time and the current operating state of the load 7 are displayed, and the "Meeting" display indicating the starting day of the week is linked (O, 5Hz). , it can be seen that the period during which the load 7 is turned off has been reserved.

今、設定された開始曜日になったとすると、第27図(
g)に示すように曜日表示「會」のブリンクが停止し、
「切」表示がブリンクしく0.5 Hz)、負荷7をオ
フする期間になっていることを示す0例えば、マニュア
ルスイッチS W 、sにより負荷7を連続的にオフに
設定した場合、つまりは所謂パーマネントオフ操作した
場合には、第29図に示すように、パーマネント操作で
あることを示す連続表示「連続」と、オフ表示「切」が
表示され、このパーマネントオフ操作による負′fr7
のオフ状態と期間設定による負荷7のオフとを識別でき
るようにしである。なお、パーマネントオフ操作時の「
切」表示はブリンクしない。
Assuming that the set start day of the week has now arrived, Figure 27 (
As shown in g), the day of the week display “Meet” stops blinking,
The "OFF" display blinks (0.5 Hz), indicating that it is time to turn off the load 7. For example, if the load 7 is set to be turned off continuously using the manual switches S W and When a so-called permanent off operation is performed, as shown in FIG.
This makes it possible to distinguish between the OFF state of the load 7 and the OFF state of the load 7 according to the period setting. In addition, when performing the permanent off operation,
"Off" display does not blink.

ところで、負荷7をオフする期間の変更は、上述した期
間設定操作とほぼ同様の操作で行うことができる。なお
、この変更の際に既に設定期間となっている場合には開
始曜日の設定は必要ないので、第30図に示すように、
曜日表示はしないようになっている。されに、期間設定
モードとした表示fyIs13の表示状態で、例えば2
4時を越えたとすると、第31図(a)に示す残り期間
を示す数値が同図(b)に示すように1デクリメントさ
れる。
By the way, the period during which the load 7 is turned off can be changed by an operation substantially similar to the period setting operation described above. Note that if the set period has already been reached when making this change, there is no need to set the start day of the week, so as shown in Figure 30,
The day of the week is not displayed. In addition, in the display state of display fyIs13 in the period setting mode, for example, 2
If it exceeds 4 o'clock, the numerical value indicating the remaining period shown in FIG. 31(a) is decremented by 1 as shown in FIG. 31(b).

なお、第31図は最終日で24時を越えた場合で、この
場合には分表示部分がr−−Jとなる。
In addition, FIG. 31 shows a case where 24 o'clock has passed on the last day, and in this case, the minute display part becomes r--J.

[発明の効果] 特定発明は上述のように、予め設定されたプログラムに
従って負荷を動作させるプログラム制御手段と、負荷を
オンする期間を設定する期間設定手段と、この期間設定
手段で設定が行われたことを検出する設定検出手段と、
上記期間設定手段で設定された設定期間を計時するタイ
マ手段と、このタイマ手段のタイマ動作期間に負荷をオ
ン状態に保持すると共に、設定期間経過後はプログラム
制御手段の出力に応じて負荷の動作を制御する出力制御
手段とを備えているので、期間設定手段で負荷をオンす
る期間を設定すると、設定期間経過後はプログラム制御
手段による制御状態に自動的に戻り、期間設定手段によ
る1回の設定操作だけで、負荷を一時的にオンさせるこ
とができ、操作が簡単となり、プログラム動作に戻し忘
れることもない。
[Effects of the Invention] As described above, the specified invention includes a program control means for operating a load according to a preset program, a period setting means for setting a period during which the load is turned on, and a setting performed by the period setting means. a setting detection means for detecting that the
A timer means for timing the set period set by the period setting means, and a timer means for keeping the load in an on state during the timer operation period of the timer means, and operating the load according to the output of the program control means after the set period elapses. Since the output control means is equipped with an output control means for controlling the output, when the period for turning on the load is set by the period setting means, after the set period has elapsed, the control state is automatically returned to the state controlled by the program control means, and one-time control by the period setting means is provided. The load can be temporarily turned on simply by setting the settings, making the operation easy and eliminating the need to forget to return to programmed operation.

なお、曜日毎に予め設定されたプログラムからなる週間
プログラムに従って負荷を動作させるプログラム制御手
段と、負荷をオン状態に保持する数日に及ぶ期間を日単
位で設定する期間設定手段と、この期間設定手段で設定
が行われたことを検出する設定検出手段と、上記期間設
定手段により設定された設定期間を判定する期間判定手
段と、この期間判定手段及びプログラム制御手段の出力
に応じてオン期間を設定するオン期間設定手段と、設定
期間内はオン期間設定手段の出力に応じて負荷の動作を
制御すると共に、設定期間経過後はプログラム制御手段
の出力に応じて負荷の動作を制御する出力制御手段とを
備え、上記オン期間設定手段では、設定期間の開始日に
なった時点でプログラム制御手段の出力が負荷をオンす
る状態となっている場合、設定期間の開始時点を負荷を
オンにするオン期間の開始時点とすると共に、設定期間
の開始日になった時点でプログラム制御手段の出力が負
荷をオフする状態となっている場合、設定期間内で最初
にプログラム制御手段が負荷をオンする時点をオン期間
の開始時点とし、また設定期間の最終日が終わる時点で
プログラム制御手段の出力が負荷をオンする状態になっ
ている場合、設定期間の終了時点をオン期間の終了時点
とすると共に、設定期間の最終日が終わる時点でプログ
ラム制御手段の出力が負荷をオフする状態になっている
場合には、設定期間の最終日の最終の負荷をオフするプ
ログラム制御手段の出力時点をオン期間の終了時、くど
してオン期間を設定するようにすれば、週間プログラム
に従って負荷の動作を制御するタイムスイッチにおいて
も、負荷をオンする操作が簡単に行え、切忘れを防止で
きる。なお、この場合のように負荷を実際にオンする期
間なオン期間設定手段が期間判定手段とプログラム制御
手段の出力に応じて設定するので、設定期間内でも例え
ば深夜に不必要に負荷をオンすることがなく、使い勝手
が良くなる。
In addition, a program control means for operating the load according to a weekly program consisting of a program preset for each day of the week, a period setting means for setting a period of several days during which the load is kept in an on state, and a period setting means for setting the period. a setting detecting means for detecting that the setting has been made by the means; a period determining means for determining the setting period set by the period setting means; and a period determining means for determining the on period according to the output of the period determining means and the program control means On-period setting means to be set, and output control that controls the operation of the load according to the output of the on-period setting means during the set period, and according to the output of the program control means after the set period has elapsed. and the on-period setting means turns on the load at the start of the set period if the output of the program control means is in a state to turn on the load at the start date of the set period. If the output of the program control means turns off the load at the start of the on period and the start date of the set period, the program control means turns on the load for the first time within the set period. If the output of the program control means is in a state to turn on the load at the end of the last day of the set period, the end of the set period is taken as the end of the on period, and If the output of the program control means is in a state where the load is turned off at the end of the last day of the set period, the output point of the program control means that turns off the load on the last day of the set period is set as the on period. By repeatedly setting the ON period at the end of the program, the load can be easily turned on even with a time switch that controls the operation of the load according to the weekly program, and forgetting to turn it off can be prevented. Note that, as in this case, the on-period setting means sets the period during which the load is actually turned on according to the output of the period determining means and the program control means, so even within the set period, the load may be turned on unnecessarily at midnight, for example. This makes it easier to use.

また、上記期間設定手段で負荷をオン状態に保持する数
日に及ぶ期間の開始曜日を設定可能とし、この期間設定
手段により設定された上記開始曜日を判定する開始曜日
判定手段を設ければ、負荷を数日にわたってオンする設
定を数日前から予約設定ができる。
Further, if the period setting means can set a starting day of the week for a period of several days during which the load is kept on, and a starting day of the week determining means is provided for determining the starting day of the week set by the period setting means, You can schedule the load to be turned on for several days several days in advance.

また、1SiI連発明では曜日毎に予め設定されたプロ
グラムからなる週間プログラムに従って負荷を動作させ
るプログラム制御手段と、負荷をオフ状態に保持する数
日に及ぶ期間を日単位で設定する期間設定手段と、この
期間設定手段で設定が打われたことを検出する設定検出
手段と、上記期間設定手段により設定された設定期間を
判定する期間判定手段と、この期間判定手段及びプログ
ラム制御手段の出力に応じてオフ期間を設定するオフ期
間設定手段と、設定期間内はオフ期間設定手段の出力に
応じて負荷の動作を制御すると共に、オフ期間経過後は
プログラム制御手段の出力に応じて負荷の動作を制御す
る出力制御手段とを備え、上記オフ期間設定手段では、
設定期間の開始日になった時点でプログラム制御手段の
出力が負荷をオフする状態となっている場合、設定期間
を負荷をオフにするオフ期間とすると共に、設定期間の
開始日になった時、αでプログラム制御手段の出力が負
荷をオンする状態となっている場合には、設定期間内で
最初にプログラム制御手段が負荷をオフする時点から設
定期間の最終日の終了時点までをオフ期間に設定しであ
るので、期間設定手段で負荷をオフする数日に及ぶ期間
を設定するだけで、オフ期間設定手段が休日にまたがっ
て負荷をオンする必要のある場合を設定期日の開始日と
なった時点で判断してオフ期間を設定して、休日にまた
がって負荷をオンする必要のある場合に対応でき、また
設定期間経過後は自動的にプログラム動作に戻るように
オフ期間設定手段がオフ期間を設定しで、休日明けの始
業前の負荷のオンも自動的に行え、省人力比が図れる。
In addition, the 1SiI series of inventions further includes a program control means for operating the load according to a weekly program consisting of a program preset for each day of the week, and a period setting means for setting a period of several days in which the load is kept in an off state on a daily basis. , a setting detecting means for detecting that a setting has been entered by the period setting means, a period determining means for determining the setting period set by the period setting means, and a period determining means for determining the setting period set by the period setting means, and according to the output of the period determining means and the program control means. an off-period setting means for setting an off-period using and an output control means for controlling the off-period setting means,
If the output of the program control means is in a state to turn off the load when the start date of the set period arrives, the set period is set as an off period for turning off the load, and when the start date of the set period arrives, , if the output of the program control means turns on the load at α, the off period is from the first time the program control means turns off the load within the set period to the end of the last day of the set period. Therefore, by simply setting a period of several days during which the load is to be turned off using the period setting means, the off period setting means can be used to set the start date of the set period when the load needs to be turned on over a holiday. The off-period setting means can be used to determine when the load is off and set the off-period to deal with cases where it is necessary to turn on the load over holidays. By setting the off period, the load can be automatically turned on before the start of work after holidays, resulting in labor savings.

なお、上記期間設定手段で負荷をオフ状態に保持する数
日に及ぶ期間の開始曜日を設定可能とし、この期間設定
手段により設定された上記開始曜日を判定する開始曜日
判定手段を設ければ、負荷を数日にわたってオフする設
定を数日前から予約設定ができる。
In addition, if the period setting means can set the starting day of a period of several days during which the load is kept in an off state, and a starting day of the week determining means is provided for determining the starting day of the week set by the period setting means. You can schedule the load to be turned off for several days several days in advance.

また、負荷の動作を手動でオン、オフするマニュアルス
イッチを設ければ、負荷をオフする期間内に負荷の動作
を一時的にオンする必要が生じる場合等に対応できる。
Further, by providing a manual switch for manually turning on and off the operation of the load, it is possible to cope with cases where it is necessary to temporarily turn on the operation of the load within the period when the load is turned off.

さらに、上記マニュアルスイッチでオフ期間内において
負荷がオンされた場合、上記マニュアルスイッチの操作
以降でプログラム制御手段の出力が最初に負荷をオフす
る状態となった時点で負荷をオフするようにすると、マ
ニュアルスイッチによるオン時の切忘れを防止できる。
Further, when the load is turned on during the off period by the manual switch, the load is turned off when the output of the program control means first turns off the load after the manual switch is operated. You can prevent forgetting to turn off the switch when turning it on using the manual switch.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は特定発明の一実施例の構成を示すブロック図、
第2図は同上の動作を示す70−チャート、第3図及び
第4図は同上の動作説明のためのタイムチャート、PJ
S図は特定発明の他の実施例の構成を示すブロック図、
第6図は同上の動作を示す70−チャート、第7図及び
第8図は同上の動作説明のためのタイムチャート、第9
図は特定発明のさらに他の実施例の構成を示すブロック
図、第10図は同上の動作を示す70−チャート、第1
1図及Ij第12図は同上の動作説明のためのタイムチ
ャート、第13図は関連発明の一実施例の構成を示すブ
ロック図、第14図は同上の70−チャート、第15図
及び第16図は同上の動作説明のためのタイムチャート
、第17図は1回路出力タイプのタイムスイッチの操作
部の外観図、第18図は2回路出力タイプのタイムスイ
ッチの操作部の外観図、第19図(a)〜(I?)は表
示部の表示の説明図、第20図及び第21図は夫々マニ
ュアルスイッチを用いた場合の動作を示すタイムチャー
ト、第22図は関連発明の他の実施例の構成を示すブロ
ック図、第23図は同上の動作を示すフローチャート、
第24図は及V第25図は同上の動作説明のためのタイ
ムチャート、第26図は同上の外観図、第27図(a)
〜(g)は同上の表示部の表示の説明図、第28図(、
)〜(d)は同上の正面図、側面断面図、底面図、及び
背面図、$29図乃至第31図は特定操作時の表示部の
表示の説明図、第32図は特定発明の従来例の動作を示
すタイムチャート、第33図は関連発明の従来例の動作
を示すタイムチャートである。 1は期間設定手段、1゛は期間設定手段、3は設定検出
手段、4はタイマ手段、4゛は期間判定手段、5は出力
制御手段、6はプログラム制御手段、7は負荷、8はオ
フ期間設定手段、9はオフ期間設定手段、10は開始曜
日判定手段である。 代理人 弁理士 石 1)長 七 第10図 第14図 $17図 第19図 (O)Hoニー− 第26図 t 第27図 第28図
FIG. 1 is a block diagram showing the configuration of an embodiment of the specified invention;
Figure 2 is a 70-chart showing the same operation as above, Figures 3 and 4 are time charts for explaining the same operation, and PJ
S diagram is a block diagram showing the configuration of another embodiment of the specific invention,
FIG. 6 is a 70-chart showing the same operation as above, FIGS. 7 and 8 are time charts for explaining the same operation, and FIG.
FIG. 10 is a block diagram showing the configuration of still another embodiment of the specific invention, FIG.
1 and Ij. FIG. 12 is a time chart for explaining the operation of the same as above, FIG. 13 is a block diagram showing the configuration of an embodiment of the related invention, FIG. 14 is a 70-chart of the same, FIG. Fig. 16 is a time chart for explaining the operation of the same as above, Fig. 17 is an external view of the operating part of a one-circuit output type time switch, Fig. 18 is an external view of the operating part of a two-circuit output type time switch, and Fig. 18 is an external view of the operating part of a two-circuit output type time switch. 19(a) to (I?) are explanatory diagrams of the display of the display unit, FIGS. 20 and 21 are time charts showing the operation when using manual switches, respectively, and FIG. 22 is an illustration of other related inventions. A block diagram showing the configuration of the embodiment, FIG. 23 is a flow chart showing the operation of the same as above,
Fig. 24 is a time chart for explaining the operation of the same as above, Fig. 26 is an external view of the same as above, and Fig. 27 (a)
~(g) is an explanatory diagram of the display of the same display section, FIG. 28 (,
) to (d) are the same front view, side sectional view, bottom view, and rear view, Figures 29 to 31 are explanatory diagrams of the display of the display unit during specific operations, and Figure 32 is the conventional method of the specified invention. FIG. 33 is a time chart showing the operation of the example and FIG. 33 is a time chart showing the operation of the conventional example of the related invention. 1 is a period setting means, 1 is a period setting means, 3 is a setting detection means, 4 is a timer means, 4 is a period judgment means, 5 is an output control means, 6 is a program control means, 7 is a load, and 8 is off 9 is an off period setting means, and 10 is a start day of the week determining means. Agent Patent Attorney Ishi 1) Chief 7 Figure 10 Figure 14 Figure 17 Figure 19 (O) Ho knee - Figure 26 t Figure 27 Figure 28

Claims (7)

【特許請求の範囲】[Claims] (1)予め設定されたプログラムに従って負荷を動作さ
せるプログラム制御手段と、負荷をオンする期間を設定
する期間設定手段と、この期間設定手段で設定が行われ
たことを検出する設定検出手段と、上記期間設定手段で
設定された設定期間を計時するタイマ手段と、このタイ
マ手段のタイマ動作期間に負荷をオン状態に保持すると
共に、設定期間経過後はプログラム制御手段の出力に応
じて負荷の動作を制御する出力制御手段とを備えたタイ
ムスイッチ。
(1) program control means for operating the load according to a preset program; period setting means for setting the period during which the load is turned on; and setting detection means for detecting that settings have been made by the period setting means; A timer means for timing the set period set by the period setting means, and a timer means for keeping the load in an on state during the timer operation period of the timer means, and operating the load according to the output of the program control means after the set period elapses. and an output control means for controlling the time switch.
(2)曜日毎に予め設定されたプログラムからなる週間
プログラムに従って負荷を動作させるプログラム制御手
段と、負荷をオン状態に保持する数日に及ぶ期間を日単
位で設定する期間設定手段と、この期間設定手段で設定
が行われたことを検出する設定検出手段と、上記期間設
定手段により設定された設定期間を判定する期間判定手
段と、この期間判定手段及びプログラム制御手段の出力
に応じてオン期間を設定するオン期間設定手段と、設定
期間内はオン期間設定手段の出力に応じて負荷の動作を
制御すると共に、設定期間経過後はプログラム制御手段
の出力に応じて負荷の動作を制御する出力制御手段とを
備え、上記オン期間設定手段では、設定期間の開始日に
なった時点でプログラム制御手段の出力が負荷をオンす
る状態となっている場合、設定期間の開始時点を負荷を
オンにするオン期間の開始時点とすると共に、設定期間
の開始日になった時点でプログラム制御手段の出力が負
荷をオフする状態となっている場合、設定期間内で最初
にプログラム制御手段が負荷をオンする時点をオン期間
の開始時点とし、また設定期間の最終日が終わる時点で
プログラム制御手段の出力が負荷をオンする状態になっ
ている場合、設定期間の終了時点をオン期間の終了時点
とすると共に、設定期間の最終日が終わる時点でプログ
ラム制御手段の出力が負荷をオフする状態になっている
場合には、設定期間の最終日の最終の負荷をオフするプ
ログラム制御手段の出力時点をオン期間の終了時点とし
てオン期間を設定して成るタイムスイッチ。
(2) program control means for operating the load according to a weekly program consisting of a program preset for each day of the week; a period setting means for setting a period of several days during which the load is kept in the on state; a setting detecting means for detecting that the setting has been made by the setting means; a period determining means for determining the setting period set by the period setting means; and an on-period according to the output of the period determining means and the program control means. and an output that controls the operation of the load according to the output of the on-period setting means during the set period and according to the output of the program control means after the set period has elapsed. and a control means, in the on-period setting means, if the output of the program control means is in a state to turn on the load at the start date of the set period, the on-period setting means sets the start of the set period to turn on the load. If the output of the program control means is in a state to turn off the load at the start of the on period, and the start date of the set period is reached, the output of the program control means turns on the load for the first time within the set period. If the output of the program control means is in a state where the load is turned on at the end of the last day of the set period, the end of the set period is the end point of the on period. At the same time, if the output of the program control means is in a state where the load is turned off at the end of the last day of the set period, the output of the program control means is turned on at the end of the last day of the set period to turn off the load. A time switch consisting of an on period set as the end point of the period.
(3)上記期間設定手段で負荷をオン状態に保持する数
日に及ぶ期間の開始曜日を設定可能とし、この期間設定
手段により設定された上記開始曜日を判定する開始曜日
判定手段を設けた請求項2記載のタイムスイッチ。
(3) A claim in which the period setting means is capable of setting a starting day of the week for a period of several days during which the load is kept in an on state, and a starting day of the week determining means is provided for determining the starting day of the week set by the period setting means. Time switch described in item 2.
(4)曜日毎に予め設定されたプログラムからなる週間
プログラムに従って負荷を動作させるプログラム制御手
段と、負荷をオフ状態に保持する数日に及ぶ期間を日単
位で設定する期間設定手段と、この期間設定手段で設定
が行われたことを検出する設定検出手段と、上記期間設
定手段により設定された設定期間を判定する期間判定手
段と、この期間判定手段及びプログラム制御手段の出力
に応じてオフ期間を設定するオフ期間設定手段と、設定
期間内はオフ期間設定手段の出力に応じて負荷の動作を
制御すると共に、オフ期間経過後はプログラム制御手段
の出力に応じて負荷の動作を制御する出力制御手段とを
備え、上記オフ期間設定手段では、設定期間の開始日に
なった時点でプログラム制御手段の出力が負荷をオフす
る状態となっている場合、設定期間を負荷をオフにする
オフ期間とすると共に、設定期間の開始日になった時点
でプログラム制御手段の出力が負荷をオンする状態とな
っている場合には、設定期間内で最初にプログラム制御
手段が負荷をオフする時点から設定期間の最終日の終了
時点までをオフ期間に設定して成るタイムスイッチ。
(4) program control means for operating the load according to a weekly program consisting of a program preset for each day of the week; a period setting means for setting a period of several days in which the load is kept in an off state; a setting detecting means for detecting that the setting has been made by the setting means; a period determining means for determining the set period set by the period setting means; and an off period according to the output of the period determining means and the program control means. and an output that controls the operation of the load according to the output of the off-period setting means during the set period and according to the output of the program control means after the lapse of the off-period. and a control means, and in the off-period setting means, if the output of the program control means is in a state where the load is turned off at the start date of the set period, the set period is set as an off period during which the load is turned off. In addition, if the output of the program control means turns on the load at the start date of the set period, the setting starts from the first time the program control means turns off the load within the set period. A time switch whose off period is set until the end of the last day of the period.
(5)上記期間設定手段で負荷をオフ状態に保持する数
日に及ぶ期間の開始曜日を設定可能とし、この期間設定
手段により設定された上記開始曜日を判定する開始曜日
判定手段を設けた請求項4記載のタイムスイッチ。
(5) A claim in which the period setting means is capable of setting a starting day of the week for a period of several days during which the load is kept in an off state, and a starting day of the week determining means is provided for determining the starting day of the week set by the period setting means. Time switch described in item 4.
(6)負荷の動作を手動でオン、オフするマニュアルス
イッチを備えた請求項4記載のタイムスイッチ。
(6) The time switch according to claim 4, further comprising a manual switch for manually turning on and off the operation of the load.
(7)上記マニュアルスイッチでオフ期間内において負
荷がオンされた場合、上記マニュアルスイッチの操作以
降でプログラム制御手段の出力が最初に負荷をオフする
状態となった時点で負荷をオフして成る請求項6記載の
タイムスイッチ。
(7) If the load is turned on during the off period by the manual switch, the load is turned off when the output of the program control means becomes the first state to turn off the load after the manual switch is operated. The time switch described in item 6.
JP27245789A 1988-12-29 1989-10-19 Time switch Pending JPH02269994A (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP27245789A JPH02269994A (en) 1988-12-29 1989-10-19 Time switch
DE1989610661 DE68910661T2 (en) 1988-12-29 1989-12-27 Timer.
EP19890203333 EP0376409B1 (en) 1988-12-29 1989-12-27 Time switch

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP63-331284 1988-12-29
JP33128488 1988-12-29
JP27245789A JPH02269994A (en) 1988-12-29 1989-10-19 Time switch

Publications (1)

Publication Number Publication Date
JPH02269994A true JPH02269994A (en) 1990-11-05

Family

ID=26550212

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27245789A Pending JPH02269994A (en) 1988-12-29 1989-10-19 Time switch

Country Status (3)

Country Link
EP (1) EP0376409B1 (en)
JP (1) JPH02269994A (en)
DE (1) DE68910661T2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1995007500A1 (en) * 1993-09-04 1995-03-16 Energy Management Team Ag Method and device for minimizing the energy consumption of an electrical load
US8050145B2 (en) 2008-02-26 2011-11-01 Leviton Manufacturing Co., Inc. Wall mounted programmable timer system
USD634276S1 (en) 2009-06-05 2011-03-15 Leviton Manufacturing Co., Inc. Electrical device
US8786137B2 (en) 2009-09-11 2014-07-22 Leviton Manufacturing Co., Inc. Digital wiring device
USD640640S1 (en) 2009-10-28 2011-06-28 Leviton Manufacturing Co., Inc. Electrical device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2064165B (en) * 1979-11-27 1983-11-16 Amure K O Time switch apparatus
JPS57172282A (en) * 1981-04-17 1982-10-23 Hitachi Ltd Timer for thermal accumulator

Also Published As

Publication number Publication date
EP0376409A2 (en) 1990-07-04
EP0376409B1 (en) 1993-11-10
EP0376409A3 (en) 1991-01-30
DE68910661T2 (en) 1994-05-05
DE68910661D1 (en) 1993-12-16

Similar Documents

Publication Publication Date Title
US9014860B2 (en) Rapid programming of thermostat with multiple programming mode conditions
US8441155B2 (en) Electric timer for controlling power to a fan
US6167000A (en) Multiple timer display
JPH02269994A (en) Time switch
JP2000179909A (en) Automatic operation controller
JP2005061781A (en) Operation reserving control method for system
JP3760037B2 (en) Program time switch
JP3135971B2 (en) Electronic time switch
JPH0430966Y2 (en)
JP3547638B2 (en) Portable information equipment
JP3180022B2 (en) Solar time switch
JP2919472B2 (en) Program timer device
JPH04295794A (en) Card type annual program timer
KR20080099708A (en) Nighttime electric power controller and control setting method thereof
JP2001130899A (en) Battery charging device
JP2785431B2 (en) Shower equipment
JPS6145509Y2 (en)
JPH0520716B2 (en)
JPH049690A (en) Time switch
JPH0461820A (en) Display device for rice cooker
JP2001281373A (en) Time switch
JPH0446335B2 (en)
KR101283230B1 (en) Lighting Automatic Reservation Switch for Crime Prevention
JPH10332856A (en) Electric apparatus
JPH0755252A (en) Control device for bath hot water feeding device