JPH02144433A - Constructing connection for column-girder - Google Patents

Constructing connection for column-girder

Info

Publication number
JPH02144433A
JPH02144433A JP29806888A JP29806888A JPH02144433A JP H02144433 A JPH02144433 A JP H02144433A JP 29806888 A JP29806888 A JP 29806888A JP 29806888 A JP29806888 A JP 29806888A JP H02144433 A JPH02144433 A JP H02144433A
Authority
JP
Japan
Prior art keywords
column
steel
concrete
columns
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP29806888A
Other languages
Japanese (ja)
Inventor
Akira Kurosawa
明 黒澤
Kazutoshi Kikukawa
菊川 和俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Construction Co Ltd
Original Assignee
Mitsubishi Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Construction Co Ltd filed Critical Mitsubishi Construction Co Ltd
Priority to JP29806888A priority Critical patent/JPH02144433A/en
Publication of JPH02144433A publication Critical patent/JPH02144433A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To heighten rigidity by laying a steel girder, with stud bolts planted thereto, in a way that the girder covers a span between two reinforced concrete columns facing each other, after casting concrete to the column up to the underside of the girder, and by casting concrete only to capital parts. CONSTITUTION:After casting concrete to a reinforced concrete columns A up to the underside of a girder, a steel girder B, with stud bolts 1 planted thereto, is laid, spanning a distance between the columns A, erected facing each other with the column's main reinforcements 2 protruding therefrom, and placed at the inside of each of capital parts. The steel girder ia then connected, at its opposite ends, to the columns through steel sheets to which the girder is fastened with bolts. Bottom reinforcements 6 and top reinforcements 6' are then arranged over each of the opposite ends of the capital parts. Tie-hoops 7 are arranged encircling the column's main reinforcements 2, and stirrups 8 are also arranged encircling the top and bottom reinforcements 6' and 6. Forms are then constructed for connection of the column-girder, and after forms for a floor are also constructed, concrete is cast for the connection and the floor.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、鉄筋コンクリート柱と鉄骨梁とよりなる構造
物における柱梁の仕口構法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a column-beam joint construction method in a structure consisting of reinforced concrete columns and steel beams.

(従来の技術) 従来この種の工法として、特開昭59−179946号
公報に示すように、端部に大納筋材が固定された鉄骨梁
を、同太納筋材が柱主筋及び帯筋間に位置するように支
持し、この状態で柱の型枠を組付け、コンクリートを打
設する施工方法が提案されている。
(Prior art) As shown in Japanese Unexamined Patent Application Publication No. 59-179946, a conventional construction method of this type is to construct a steel beam with large reinforcements fixed at the ends, and use the same reinforcements to connect the main reinforcements of the column and the band. A construction method has been proposed in which the column is supported between the reinforcements, the formwork of the column is assembled in this state, and concrete is poured.

(発明が解決しようとする課題) 前記従来の施工方法においては柱梁の仕口部の配筋が複
雑で、コンクリート打設前において太納筋が配設された
鉄骨梁の端部の納まりが複雑であり、また同鉄骨梁の重
量の支持が困難である。
(Problems to be Solved by the Invention) In the conventional construction method described above, the reinforcement arrangement at the joints of columns and beams is complicated, and the ends of the steel beams with thick reinforcing reinforcements cannot be accommodated before concrete pouring. It is complex and difficult to support the weight of the steel beams.

一般に鉄筋コンクリート柱と鉄骨梁からなる構造物にお
いては、鉄骨梁と鉄筋コンクリート柱の応力伝達の際に
、鉄骨梁が変形し易く、同鉄骨梁の変形に伴って、応力
伝達が集中し柱コンクリートとの剥離が生起し易い。
In general, in structures consisting of reinforced concrete columns and steel beams, the steel beams tend to deform when stress is transferred between the steel beams and the reinforced concrete columns, and as the steel beams deform, stress transfer is concentrated and Peeling is likely to occur.

本発明は前記従来技術の有する問題点に迄みて提案され
たもので、その目的とする処は剛性の高い鉄骨鉄筋コン
クリートのキャピタル部を構築し、応力の伝達が円滑に
行われ、施工が合理化された柱梁の仕口構法を提供する
点にある。
The present invention has been proposed in view of the problems of the prior art, and its purpose is to construct a capital section of highly rigid steel-framed reinforced concrete, to ensure smooth transmission of stress, and to streamline construction. The main point of this invention is to provide a shikiguchi construction method for columns and beams.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係J柱梁の仕口構
法は、鉄筋コンクリート柱と鉄骨梁とよりなる構造物に
おいて、鉄筋コンクリート柱を梁下までコンクリートを
打設し、次いで相隣る同柱間に亘って、スタッドボルト
が植立された鉄骨梁を横架し、前記鉄筋コンクリート柱
の柱頭部内において、間柱頭部に立設した接合用鋼板を
介して相隣る前記鉄骨梁を接合し、次いで同各鉄骨梁の
端部部分と柱頭部とに跨って梁主筋を配筋し、次いで夫
々肋筋及び帯筋で補強された梁端部部分と柱頭部とに跨
ってコンクリ−1・を打設して鉄骨鉄筋コンクリートの
キャピタル部を構築するものである。
(Means for Solving the Problems) In order to achieve the above-mentioned object, the J-column and beam joint construction method according to the present invention, in a structure consisting of reinforced concrete columns and steel beams, concrete is applied to the reinforced concrete columns to the bottom of the beams. Then, a steel beam with stud bolts is placed horizontally between the adjacent columns, and within the column head of the reinforced concrete column, through a connecting steel plate erected at the stud head. The adjacent steel beams are joined, then main beam reinforcement is placed across the end portions and column heads of each steel beam, and then the beam end portions and column heads are reinforced with ribs and ties, respectively. A capital section of steel-framed reinforced concrete will be constructed by pouring concrete over the two sections.

(作用) 本発明においては前記したように、鉄筋コンクリート柱
のコンクリートを梁下まで打設し、柱主筋が上方に突設
された状態で、スタッドボルトが植立された鉄骨梁を相
隣る柱間に亘って横架することによって、同鉄骨梁を相
隣る柱間にサポートを要することなく横架し、前記柱の
柱頭部内において相隣る同鉄骨梁を同柱頭部に立設した
接合用鋼板を介して接合し、しかるのち同鉄骨梁の端部
部分と柱頭部とに跨って梁主筋を配筋し、次いで肋筋及
び帯筋で補強された梁端部部分と柱頭部とに跨ってコン
クリートを打設することによって剛性の高い鉄骨鉄筋コ
ンクリートのキャピタル部を構築するものである。
(Function) As described above, in the present invention, concrete for a reinforced concrete column is poured to the bottom of the beam, and with the main reinforcement of the column protruding upward, a steel beam with stud bolts is attached to the adjacent column. A joint in which the same steel beams are horizontally mounted between adjacent columns without requiring support, and adjacent steel beams are erected in the same column head within the column head of the column. After that, main beam reinforcement is placed across the end portion of the steel beam and the column head, and then the beam end portion and the column head reinforced with ribs and stirrups are connected. By pouring concrete across the bridge, a highly rigid steel reinforced concrete capital section is constructed.

従って前記鉄筋コンクリート柱と鉄骨梁とは剛性の高い
鉄骨鉄筋コンクリートのキャピタル部を介して一体に接
合され、柱梁間の応力伝達が確実に行なわれ、且つ梁端
部の変形が抑止され、同梁端部にスタッドボルトが植立
されて剪断耐力が増大されたことと相俟って、鉄骨梁か
ら鉄筋コンクリート柱へ徐々に応力が伝達され、鉄骨梁
端部とコンクリートとの接触面でコンクリートの剥離が
生起することがない。
Therefore, the reinforced concrete column and the steel beam are integrally connected via the highly rigid steel-framed reinforced concrete capital part, and stress transmission between the column and beam is reliably carried out, and deformation of the beam end is suppressed. Coupled with the fact that stud bolts were erected to increase shear strength, stress was gradually transmitted from the steel beam to the reinforced concrete column, causing concrete spalling at the contact surface between the steel beam end and the concrete. There's nothing to do.

また前記柱頭部には、柱頭の内にまでスタッドボルトを
植立した鉄骨梁を配設し、且つ前記接合用鋼板を介して
接合することによって、同梁鉄骨によって柱梁接合部の
剪断強さが増大し、柱梁接合部の破壊が防止される。
Furthermore, by installing a steel beam with stud bolts installed deep into the column head and connecting it via the joining steel plate, the steel beam can increase the shear strength of the column-beam joint. increases, and destruction of the beam-column joint is prevented.

(実施例) 以下本発明を図示の実施例によって説明する。(Example) The present invention will be explained below with reference to illustrated embodiments.

鉄筋コンクリート柱(A)のコンクリートを梁下まで打
設し、(第1図参照)次いでスタッドボルト(1)が植
立されたI(型鋼等の鉄骨梁(B)を、柱主筋(2)が
−上方に突出した相隣る鉄筋コンクリート柱(A)の柱
頭部内に跨って横架し、前記各鉄骨梁(B)のウェブ部
を柱頭部中央におけるレベル調整した鋼板光モルタル(
3)上に立設された接合用鋼板(4)によって、ボルト
(5)を介して接合する(第2図参照)なお前記鉄骨梁
(B)は接合用鋼板(4)に溶接によって接合されても
よい。
Concrete for the reinforced concrete column (A) is poured to the bottom of the beam (see Figure 1). Next, the steel beam (B), such as a steel beam (shaped steel), with stud bolts (1) is placed, and the column main reinforcement (2) is placed. - A steel plate light mortar installed horizontally across the column heads of adjacent reinforced concrete columns (A) that protrudes upward, and the web portion of each steel beam (B) is level-adjusted at the center of the column head (
3) The steel beam (B) is joined to the joining steel plate (4) by welding using the bolt (5) (see Figure 2). It's okay.

第12図は前記接合用鋼板(4)の柱頭部に対する取付
部の構造を示し、端縁に沿ってボルト孔(4a)が列設
された十字状鋼板(4b)の下端に円盤(4c)が−体
に固着され、同円1(4c)を柱頭上におけるレベル調
整された鋼板光モルタル(3)上に載架、固定するもの
である。
Fig. 12 shows the structure of the attachment part of the joining steel plate (4) to the column head, in which a disk (4c) is attached to the lower end of the cross-shaped steel plate (4b) with bolt holes (4a) arranged in rows along the edge. is fixed to the body, and the same circle 1 (4c) is mounted and fixed on the level-adjusted steel plate light mortar (3) above the column head.

図中(4d)は前記十字状鋼板(411)の下端縁に設
けた欠截部で、同欠截部(4d)内に前記鉄骨梁(B)
の下部フランジが嵌入するようになっている。
In the figure, (4d) is a notch provided at the lower edge of the cross-shaped steel plate (411), and the steel beam (B) is located within the notch (4d).
The lower flange of the is designed to fit.

第13図及び第14図に示す実施例においては、前記接
合用鋼板(4)の円盤(4c)にルーズホール(4e)
が穿設され、同ルーズホール(4e)に鉄筋コンクリー
ト柱(1)に植立されたアンカーボルト(4f)が嵌挿
され、前記接合用鋼板(4)のずれが防止されている。
In the embodiment shown in FIGS. 13 and 14, a loose hole (4e) is formed in the disc (4c) of the joining steel plate (4).
is drilled, and an anchor bolt (4f) planted on the reinforced concrete column (1) is inserted into the loose hole (4e) to prevent the joining steel plate (4) from shifting.

このように鉄骨梁(B)を柱間に横架し、接合用鋼板(
4)を介して接合したのち、前記鉄骨梁(B)の端部と
柱頭部とに跨って端部にフックを有する下端主筋(6)
を取付け、柱主筋(2)間に帯筋(7)を配筋し、更に
端部にフックを有する上端主筋いを梁端部部分と柱頭部
とに跨って取付け、しかるのち上下端主筋(6’l (
6)間に肋筋(8)を配筋する。(第3図参照)次いで
柱梁仕口部の型枠(9)を設置するとともに、床型枠(
図示せず)を設置する。(第4図参照)次いで前記仕口
部のコンクリート00)および床コンクリート(It)
を打設し、かくし7て構築された剛性の高い鉄骨鉄筋コ
ンクリートのキャピタル部0りを介して、柱梁を一体に
接合する。(第5図、第6図及び第9図参照)なお図中
(C)は小梁である。
In this way, the steel beams (B) are hung horizontally between the columns, and the joining steel plates (
4), and then a lower end main reinforcement (6) having a hook at the end, spanning the end of the steel beam (B) and the column head.
, place the tie reinforcements (7) between the column main reinforcements (2), and then install the upper end main reinforcements with hooks at the ends across the beam end portion and the column head, and then install the upper and lower end main reinforcements ( 6'l (
6) Place ribs (8) in between. (See Figure 3) Next, install the formwork (9) for the column and beam joints, and also install the floor formwork (9).
(not shown). (See Figure 4) Next, the concrete 00) of the joint section and the floor concrete (It)
The columns and beams are connected together through the capital section of the highly rigid steel-framed reinforced concrete constructed in this way. (See Figures 5, 6, and 9) In the figure, (C) is a small beam.

なお前記実施例は柱頭部に鉄骨梁(B)が十字状に交叉
した場合を示すものであるが、第7図及び第8図は夫々
柱頭部に鉄骨梁(B)がT型並にL型に交叉した場合を
示す。
Note that the above embodiment shows a case where the steel beams (B) intersect with each other in a cross shape at the column head, but in Figs. Indicates the case where the type is crossed.

図中前記実施例と均等部分には同一符号が附されている
In the figure, parts equivalent to those of the above embodiment are given the same reference numerals.

このように前記実施例によれば、鉄筋コンクリート柱(
A)のコンクリートを梁下まで打設し、同社(^)の柱
頭部内に鉄骨梁(B)を横架し、間柱頭部に立設された
接合用鋼板(4)を介して鉄骨梁(B)相互をボルト(
5)接合または溶接接合したのち現場打コンクリートを
打設するという単純な作業を反覆してIll宛柱、梁を
組にげろことによって作業を著し2く単純化できる。
In this way, according to the embodiment, the reinforced concrete column (
Concrete from A) is poured to the bottom of the beam, and a steel beam (B) is placed horizontally within the column head of the company (^), and the steel beam (B) is placed horizontally through the connecting steel plate (4) installed at the head of the stud. B) Bolt each other (
5) The work can be significantly simplified by repeating the simple work of placing cast-in-place concrete after joining or welding and assembling columns and beams.

また前記実施例によれば、前記柱頭部内に鉄骨梁(B)
を載架することによって、同鉄骨梁(B)の柱(A)に
対するセットをサポートを要することなく単純に行なう
ことができ、更に現場配筋によってコンクリートを打設
して、柱頭部に剛性の高い鉄骨鉄筋コンクリートのキャ
ピタル部021を構築し、同キャピタル部0′IJによ
って柱(A)梁(B)を一体的に接合して、柱梁間の合
理的な応力伝達を図り、且つ前記梁に植立されたスタッ
ドボルト(1)によって剪断耐力を増大し、応力伝達時
における鉄骨梁端部におけるコンクリートの剥離を防止
するものである。
Further, according to the embodiment, a steel beam (B) is provided in the column head.
By mounting the steel beam (B) on the column (A), it is possible to simply set the same steel beam (B) to the column (A) without requiring support, and in addition, concrete can be placed using on-site reinforcement to provide rigidity to the column head. A high steel-framed reinforced concrete capital section 021 is constructed, and the columns (A) and beams (B) are integrally joined by the capital section 0'IJ to achieve rational stress transmission between the columns and beams. The vertical stud bolts (1) increase shear strength and prevent concrete from peeling off at the ends of the steel beams when stress is transmitted.

更に柱頭部内位置までスタッドボルト(1)が植立され
た相隣る鉄骨梁(B)が配設され、接合用鋼板(4)で
接合されているので、柱頭部が同鉄骨梁の鉄骨で剪断補
強され、柱梁接合部の破壊が防止される。
Furthermore, adjacent steel beams (B) with stud bolts (1) installed up to the inside of the column head are installed and connected with a joining steel plate (4), so that the column head is a steel frame of the same steel beam. Shear reinforcement is applied to prevent the beam-column joint from collapsing.

第1θ図及び第11図は本発明の他の実施例を示し、キ
ャピタル部側の断面を拡大しかつ帯筋を二重にして、柱
梁接合部の剛性及び剪断耐力をより増大せしめたもので
ある。
Figures 1θ and 11 show another embodiment of the present invention, in which the cross section on the capital side is enlarged and the ties are doubled to further increase the rigidity and shear strength of the column-beam joint. It is.

図中前記実施例と均等部分には同一符号が附されている
In the figure, parts equivalent to those of the above embodiment are given the same reference numerals.

(発明の効果) このように本発明によれば、梁下までコンクリートが打
設された鉄筋コンクリート柱の柱間に亘って鉄骨梁を載
架することによって、鉄骨梁を柱にサポートを要するこ
となく簡単にセットしうるちのであり、現場配筋によっ
てコンクリートを打設して柱頭部に剛性の高い鉄骨鉄筋
コンクリートのキャピタル部を構築し、同キャピタル部
を介して柱梁間に応力伝達を確実ならしめるとともに、
前記鉄骨梁に植立した、スタッドボルトにより剪断耐力
が増大されたことと相俟って、合理的な応力伝達が図ら
れ、鉄骨梁端部におけるコンクリートの剥離が防止され
るものである。
(Effects of the Invention) According to the present invention, by mounting a steel beam between the columns of reinforced concrete columns in which concrete is poured to the bottom of the beam, the steel beam can be mounted without requiring support from the column. It is easy to set up, and concrete is poured using on-site reinforcement to construct a highly rigid steel reinforced concrete capital section at the column head, ensuring stress transmission between the columns and beams through the capital section. ,
Coupled with the fact that the shear strength is increased by the stud bolts erected on the steel beam, rational stress transmission is achieved and separation of concrete at the ends of the steel beam is prevented.

また柱頭部の内位置までスタッドボルトを植立した相隣
る鉄骨梁が配設され且つ柱頭部に立設された接合用鋼板
を介して接合されているので、柱頭部が同梁の鉄骨によ
って剪断補強され、柱頭部の破壊が防止される。
In addition, adjacent steel beams with stud bolts installed up to the inner position of the column head are installed and connected via a joining steel plate installed at the column head, so that the column head is connected to the steel frame of the same beam. Shear reinforcement prevents the column head from collapsing.

更にまた本発明は、鉄筋コンクリート柱のコンクリート
を梁下まで打設し、間柱の柱頭部内に鉄骨梁をセットし
、キャピタル部のみ型枠を取付けて現場打コンクリート
を打設するという単純な作業を反覆してIN宛柱、梁を
組上げることによって、作業を著しく単純化しうるもの
であり、安全性の高い構法となる。
Furthermore, the present invention repeats the simple work of pouring concrete for a reinforced concrete column to the bottom of the beam, setting a steel beam inside the column head of a stud, attaching formwork only to the capital portion, and pouring cast-in-place concrete. By assembling IN columns and beams, the work can be significantly simplified and the construction method is highly safe.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第5図は、本発明に係る柱梁の仕口構法の一
実施例の工程を示す側面図、第6図は同施工法によって
構成された柱梁の仕口部を示す横断平面図、第7図及び
第8図は夫々同柱梁の仕口部の他の各実施例を示す横断
平面図、第9図は同仕口部を有する構造物の部分斜面図
、第1θ図は本発明に係る構法の他の実施例によって構
成された柱梁の仕口部を示す横断平面図、第11図は同
仕口部を有する構造物の部分斜面図、第12図は柱頭に
す斜面図並に縦断面図である。 (A)−・・鉄筋コンクリート柱 (B)・・・鉄骨梁      (1)・・−スタッド
ボルト(2)・−柱主筋       (3)・・・鋼
板受モルタル(4)・・・接合用鋼板     (5)
・・・ボルト(6)・・・下端主筋      (6)
−上端主筋(7)・・−帯筋        (8)・
・−助筋(9)・・・型枠 0ω・・−仕口部コンクリート O[)−床コンクリー
ト021・・−キャピタル部 代理人 弁理士 岡 本 重 文 外2名 第4図 第5図 第6図 第7図
Figures 1 to 5 are side views showing the steps of an embodiment of the joint construction method for columns and beams according to the present invention, and Figure 6 is a cross-sectional view showing the joint section of the columns and beams constructed by the same construction method. The plan view, FIGS. 7 and 8 are cross-sectional plan views showing other examples of the joint part of the same column and beam, and FIG. 9 is a partial slope view of a structure having the same joint part, and the first θ The figure is a cross-sectional plan view showing the joint part of a column and beam constructed according to another embodiment of the construction method according to the present invention, FIG. 11 is a partial slope view of a structure having the same joint part, and FIG. 12 is a column head. It is a vertical cross-sectional view as well as a slope view. (A) - Reinforced concrete column (B) Steel beam (1) - Stud bolt (2) - Column main reinforcement (3) - Steel plate support mortar (4) - Steel plate for joining ( 5)
...Bolt (6) ...Lower end main reinforcement (6)
-Top main reinforcement (7)... -Strap bar (8)...
・-Auxiliary bars (9)...Formwork 0ω...-Joining section concrete O[)-Floor concrete 021...-Capital department agent Patent attorney Shige Okamoto 2 outsiders Figure 4 Figure 5 Figure 6 Figure 7

Claims (1)

【特許請求の範囲】[Claims] 鉄筋コンクリート柱と鉄骨梁とよりなる構造物において
、鉄筋コンクリート柱を梁下までコンクリートを打設し
、次いで相隣る同柱間に亘って、スタッドボルトが植立
された鉄骨梁を横架し、前記鉄筋コンクリート柱の柱頭
部内において、同柱頭部に立設した接合用鋼板を介して
相隣る前記鉄骨梁を接合し、次いで同各鉄骨梁の端部部
分と柱頭部とに跨って梁主筋を配筋し、次いで夫々肋筋
及び帯筋で補強された梁端部部分と柱頭部とに跨ってコ
ンクリートを打設して鉄骨鉄筋コンクリートのキヤピタ
ル部を構築することを特徴とする柱梁の仕口構法。
In a structure consisting of reinforced concrete columns and steel beams, concrete is poured into the reinforced concrete columns to the bottom of the beams, and then steel beams with stud bolts are placed horizontally between the adjacent columns, and the above-mentioned Within the head of the reinforced concrete column, the adjacent steel beams are connected via a joining steel plate erected at the head of the column, and then main beam reinforcement is placed across the end portion of each steel beam and the head of the column. A column-beam joint construction method characterized by constructing a capital section of steel-framed reinforced concrete by reinforcing the beam and then pouring concrete over the column head and the end portion of the beam each reinforced with ribs and ties, respectively. .
JP29806888A 1988-11-28 1988-11-28 Constructing connection for column-girder Pending JPH02144433A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29806888A JPH02144433A (en) 1988-11-28 1988-11-28 Constructing connection for column-girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29806888A JPH02144433A (en) 1988-11-28 1988-11-28 Constructing connection for column-girder

Publications (1)

Publication Number Publication Date
JPH02144433A true JPH02144433A (en) 1990-06-04

Family

ID=17854726

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29806888A Pending JPH02144433A (en) 1988-11-28 1988-11-28 Constructing connection for column-girder

Country Status (1)

Country Link
JP (1) JPH02144433A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008180008A (en) * 2007-01-25 2008-08-07 Toda Constr Co Ltd Connection structure between column and beam, and method of constructing the same
JP2013136878A (en) * 2011-12-28 2013-07-11 Tokyu Construction Co Ltd Composite structure and construction
JP2014031613A (en) * 2012-08-01 2014-02-20 Taisei Corp Composite structural beam
JP2014088764A (en) * 2014-01-10 2014-05-15 Tokyu Construction Co Ltd Composite structure and construction

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63241233A (en) * 1987-03-30 1988-10-06 三菱建設株式会社 Joint method of pillar and beam

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63241233A (en) * 1987-03-30 1988-10-06 三菱建設株式会社 Joint method of pillar and beam

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008180008A (en) * 2007-01-25 2008-08-07 Toda Constr Co Ltd Connection structure between column and beam, and method of constructing the same
JP2013136878A (en) * 2011-12-28 2013-07-11 Tokyu Construction Co Ltd Composite structure and construction
JP2014031613A (en) * 2012-08-01 2014-02-20 Taisei Corp Composite structural beam
JP2014088764A (en) * 2014-01-10 2014-05-15 Tokyu Construction Co Ltd Composite structure and construction

Similar Documents

Publication Publication Date Title
JP2001123534A (en) Construction of composite precast beam
JPH02144433A (en) Constructing connection for column-girder
JP4577004B2 (en) Construction method for building frames consisting of steel-concrete composite beams and SRC columns
JP4307109B2 (en) Beam-column joint structure
JP2747678B2 (en) Composite beam
CN112359966A (en) Connecting joint of superposed beam and concrete column and construction method thereof
JPH04128424A (en) Method for constructing anchor supporting beam
KR102585526B1 (en) Composite frame with end-buried girder joint
JP2522708B2 (en) Reinforcing bar tip assembly beam with formwork and reinforcing bar tip assembly method with formwork
JP2001090240A (en) Deck plate and concrete floor
JPH02252830A (en) Pre-fabricated cruciform beam construction method
JPS63241233A (en) Joint method of pillar and beam
JP3589329B2 (en) Construction method
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH084107A (en) Connecting method for column/beam connection
JPH0334402Y2 (en)
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPS62178634A (en) Framework construction method of structure
JPH0343282Y2 (en)
JPH076338U (en) PC beam
JP2600411Y2 (en) Column-beam joint structure
JPS5925931Y2 (en) Composite girder using π-shaped steel
JPS5926001Y2 (en) Precast beam and girder joint structure
JP2893406B2 (en) Precast concrete beam-column joining method
JPH0830360B2 (en) Connection method for columns and beams