JPH01210510A - Method of installation construction of structure such as bridge - Google Patents

Method of installation construction of structure such as bridge

Info

Publication number
JPH01210510A
JPH01210510A JP3582388A JP3582388A JPH01210510A JP H01210510 A JPH01210510 A JP H01210510A JP 3582388 A JP3582388 A JP 3582388A JP 3582388 A JP3582388 A JP 3582388A JP H01210510 A JPH01210510 A JP H01210510A
Authority
JP
Japan
Prior art keywords
bridge
structural
piers
crane
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3582388A
Other languages
Japanese (ja)
Other versions
JP2578152B2 (en
Inventor
Yoshito Tanaka
義人 田中
Toshio Haraguchi
原口 俊男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobelco Wire Co Ltd
Original Assignee
Shinko Wire Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shinko Wire Co Ltd filed Critical Shinko Wire Co Ltd
Priority to JP3582388A priority Critical patent/JP2578152B2/en
Publication of JPH01210510A publication Critical patent/JPH01210510A/en
Application granted granted Critical
Publication of JP2578152B2 publication Critical patent/JP2578152B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To shorten the term of works, and to reduce construction cost by constituting the width of a leg member for a structure in width sufficient for fixing a traveling type crane under a stable state. CONSTITUTION:Abutments 3, 3 are constructed on both banks 2, 2 of a ravine 1, while piers 4 in width in an extent that an outrigger mounted to a truck crane 5 can land sufficiently are installed on both banks 2a, 2a of a river in the deepest section of the ravine 1. Bridge girders 6 are erected among the side spans of the abutments 3 and the piers 4 by the truck crane 5, the truck crane 5 is moved up to the positions of the previously mounted piers by utilizing the previously mounted bridge girders 6, and a bridge girder 6 is built between the piers 4, 4. Accordingly, the preparation, conveyance, installation and preparatory works of erection materials such as an erection work tower, a cable crane, an anchor block, a temporary cable, etc. are unnecessitated.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、橋梁等の構造物を構成する構造物用脚部材及
び構造用桁部材を走行式クレーンにより順次移行させつ
つ架設するようにした橋梁等構造物の架設工法に係る。
[Detailed Description of the Invention] (Industrial Application Field) The present invention is a method for constructing a structure such as a bridge by sequentially moving structural leg members and structural girder members constituting a structure such as a bridge. Pertains to construction methods for structures such as bridges.

(従来技術) 谷幅が広く、しかも最深部に川が流れている渓谷に橋梁
等の構造物を構成する構造用脚部材(以下、これを橋脚
または橋台と言う。)や構造用桁部材(以下、これを橋
桁と言う。)を架設する場合には、最深部の川の両側に
橋脚を各々架設し、渓谷の両側に設置した各橋台と橋脚
との側径間に橋桁を架設し、その後前記橋脚間に橋桁を
架設するようにしている。
(Prior art) Structural leg members (hereinafter referred to as bridge piers or abutments) and structural girder members (hereinafter referred to as bridge piers or abutments) that constitute structures such as bridges in valleys with wide valleys and a river flowing through the deepest part. (Hereinafter, this is referred to as a bridge girder.) When constructing bridge piers on both sides of the river at the deepest point, bridge girders are constructed in the side spans between the abutments and piers installed on both sides of the ravine. After that, a bridge girder is constructed between the piers.

そして、前記橋梁の架設工法としては、■ −プルクレ
ーン加晋  ゛ 渓谷の両岸の橋台に仮設作業塔を構築すると共に渓谷の
最環部の川の両岸に各々橋脚を架設し、そして、前記仮
設作業塔間にケーブルクレーンを張架し、このケーブル
クレーンに走行自在に取り付けられた滑車により橋桁を
吊持して移行させ、前記橋脚と橋台との側径間に橋桁を
架設し、次いで、二つの橋脚間に橋桁を架設するように
した架設工法。
The method for constructing the bridge is as follows: ■ - Pull crane construction: Build temporary work towers on the bridge abutments on both banks of the valley, and construct bridge piers on both banks of the river at the ringmost part of the valley. A cable crane is stretched between the temporary work towers, the bridge girder is suspended and moved by a pulley attached to the cable crane so as to be freely movable, the bridge girder is erected between the side spans of the bridge piers and abutments, and then , a construction method in which a bridge girder is erected between two piers.

■キ ン レバー77I+−゛ 渓谷の両岸に橋台を構築すると共に渓谷め最深部の川の
両岸に各々橋脚を架設し、そして、これら橋台及び橋脚
上に仮設作業塔を構築し、この仮設作業塔に張架した仮
ケーブルによって分割した橋桁を片持梁(キャンチレバ
ー)として取付け、それらを連結して長尺の橋桁として
、橋台と橋脚との側径間或いは橋脚相互の側径間に架設
するようにした架設工法。
■ Kin Lever 77I Split bridge girders are installed as cantilevers using temporary cables strung on work towers, and then connected to form a long bridge girder that is constructed in the side span between the abutment and the pier, or between the side spans of each pier. The construction method was designed to

■ −・・り レーン加量 渓谷の両岸に橋台を構築すると共に渓谷の最深部の川の
両岸に各々橋脚を架設し、そして、前記橋台と橋脚との
側径間にトラッククレーンにより吊持された橋桁を架設
し、そして、既架設橋桁上にトラッククレーンを移動さ
せ、その後再度トラッククレーンにより吊持された橋桁
を橋梁間に架設し、その後上述と同じく既架設橋桁上に
トラッククレーンを移動させ、今度は対岸の橋台と橋脚
との側径間に新たな橋桁を架設するようにした架設工法
■ -... Bridge abutments will be constructed on both banks of the lane gorge, and bridge piers will be erected on both banks of the river at the deepest part of the gorge, and a truck crane will be used to suspend the bridge between the abutments and the side spans of the piers. The suspended bridge girder is erected, the truck crane is moved onto the existing bridge girder, the bridge girder suspended by the truck crane is then erected between the bridges, and then the truck crane is moved onto the existing bridge girder in the same manner as above. The construction method involved moving the bridge and then constructing a new bridge girder between the abutment and the pier on the opposite bank.

等が実施されている。etc. are being implemented.

ところが、上述の何れの架設工法にあっても架設工事期
間が長期化すること、架設に必要な機材や資材が多く必
要となること等によって架設費用が高騰し、また安全面
においても満足できる状況ではなかった。即ち、 ■ −プル レー〃1  について見れば、渓谷の両岸
の橋台に設けた仮設作業塔間にケーブルクレーンを張架
させ、且つそれをアンカーブロックに繋留しなければな
らないこと、また、前記ケーブルクレーンに走行自在に
取り付けられ、そして、橋桁を吊持して移行させる滑車
を要する等架設工事を実施するための架設資材及び機材
が多数必要となり、更に、上述のように仮設作業塔間に
ケーブルクレーンを張架させる等架設工事のだめの準備
工事が必要であるから、架設工事期間が長期化すること
と相俟って総架設工事費が高騰する問題点を有している
However, with any of the above-mentioned construction methods, the construction period becomes long, and a large amount of equipment and materials are required for construction, which increases construction costs, and the situation is not satisfactory in terms of safety. It wasn't. In other words, with regard to ■-Pull Relay 1, it is necessary to stretch a cable crane between temporary work towers installed on bridge abutments on both sides of the gorge, and to anchor it to an anchor block. A large number of construction materials and equipment are required to carry out the construction work, such as pulleys that are movably attached to a crane and that suspend and move the bridge girder, and as mentioned above, cables between temporary work towers are required. Preparatory work for the erection work, such as hoisting a crane, is required, which leads to the problem of prolonging the construction period and raising the total construction cost.

■キ ン レバーIAU   について見れば、渓谷の
両岸に設けた橋台及び川の両岸に各々設けた橋脚上に仮
設作業塔を構築し、この仮設作業塔に仮ケーブルを張架
させなければならないので、架設工事を実施するための
架設資材が多数必要となる上に架設工事のための準備工
事が必要であり、更には、分割した橋桁を片持梁(キャ
ンチレバー)として取付け、それらを連結して長尺の橋
桁としているので、架設工事期間が長期化することと相
俟って総架設工事費が高騰する問題点を有している。
■If we look at the Kin Lever IAU, temporary work towers must be built on abutments installed on both sides of the valley and piers installed on both banks of the river, and temporary cables must be strung on these temporary work towers. Therefore, in order to carry out the erection work, a large number of construction materials are required, as well as preparation work for the erection work.Furthermore, it is necessary to attach the divided bridge girders as cantilevers and connect them. Since the bridge girder is long, the construction period becomes long and the total construction cost increases.

■トー・・ククレーン声量° について見れば、橋台と
橋脚との側径間にトラッククレーンにより吊持された橋
桁を架設し、そして、既架設橋桁上にトランククレーン
を移動させ、その後再度トラッククレーンにより吊持さ
れた橋桁を橋脚間に架設し、その後上述と同じく既架設
橋脚上にトラッククレーンを移動させ、今度は対岸の橋
台と橋脚との側径間に新たな橋桁を架設するようにした
ので前記■及び■の場合にあるような架設工事のための
準備工事並びにこ多くの架設資材は不要である反面トラ
ッククレーンが既架設の橋脚上で架設工事を行うので、
特に当該トラッククレーンの安定化のためのアウトリガ
−の接地スペースを考慮する必要がある。
■Torque Crane Volume The suspended bridge girder was erected between the piers, then a truck crane was moved onto the existing pier as described above, and a new bridge girder was then erected between the abutment on the opposite bank and the side span between the pier. Preparatory work and a large amount of construction materials are not required for the erection work as in cases ① and ③ above, but on the other hand, a truck crane performs the erection work on the existing bridge piers.
In particular, it is necessary to consider the grounding space of the outrigger for stabilizing the truck crane.

(発明が解決しようとする課題) 前掲の通り、橋梁等の構造物を架設する工法としては種
々の工法が実施されているが、その何れの工法にあって
も次の問題点を抱えている。
(Problem to be solved by the invention) As mentioned above, various construction methods have been implemented for constructing structures such as bridges, but all of them have the following problems. .

即ち、上述の■ケーブルクレーン架設工法においては、
仮設作業塔間にケーブルクレーンを張架させ、且つそれ
をアンカーブロックに繋留しなければならないこと、ま
た、前記ケーブルクレーンに走行自在に取り付けられ、
橋桁を吊持して移行させる滑車を要する等架設工事を実
施するための架設資材及び機材が多数必要となり、更に
、架設工事のための準備工事が必要であるから、架設工
事期間が長期化することと相俟って総架設工事費が高騰
する問題点を有している。また、■キャンチレバー架設
工法においては、橋脚上に仮設作業塔を構築し、この仮
設作業塔に仮ケーブルを張架させなければならないので
、架設工事を実施するための架設資材及び機材が多数必
要となる上に架設工事のための準備工事が必要であり、
更には、架設工事期間が長期化することと相俟って総架
設工事費が高騰する等の問題点があり、そして、何りよ
りも重大なことは■及び■の何れの工法も渓谷の両岸に
仮設基、橋台並びに渓谷の中央位置に橋脚が接地出来る
立地条件が満たされていることが必要であって、この条
件が満たされない立地条件下、換言すれば、一方が山岳
地であり、しかも山道等作業する場所や架設資材の置く
場所がないような立地条件下の場合には実施できない問
題点がある。
In other words, in the above ■ cable crane erection method,
A cable crane must be strung between temporary work towers, and it must be moored to an anchor block;
A large number of erection materials and equipment are required to carry out the erection work, such as the need for pulleys to suspend and move the bridge girders, and preparatory work for the erection work is also required, which lengthens the construction period. Coupled with this, there is a problem in that the total construction cost is rising. In addition, in the cantilever construction method, a temporary work tower must be built on the pier and a temporary cable must be strung on the temporary work tower, so a large number of construction materials and equipment are required to carry out the construction work. In addition, preparatory work for erection work is required.
Furthermore, there are problems such as the total construction cost rising due to the lengthening of the construction period, and the most important thing is that both construction methods It is necessary that the location conditions for temporary bases and bridge abutments on both banks and for the bridge piers to touch the ground in the center of the valley are met, and for location conditions where these conditions are not met, in other words, one side is in a mountainous area. Moreover, there is a problem in that it cannot be carried out under location conditions such as mountain roads where there is no place to work or place construction materials.

反面、■トラッククレーン架設工法であれば、上記■及
び■とは相異し、架設工事を実施するために必要な架設
資材の準備、搬送、設置並びに準備工事が要らないので
、架設工事期間の短縮化、工事費の低廉化が図れると共
に一方が山岳地であり、しかも山道等作業する場所や架
設資材の置く場所がないような立地条件下でも実施可能
な利点を有しているが、架設する橋脚や橋桁を搬送する
ためにトラッククレーンを用い、且つ架設工事を実施す
る場所が橋脚上に定置して行うようにしているので、橋
脚の幅はトラッククレーンのアウトリガ−が着地し、且
つトラッククレーン自体を安定させるに充分なスペース
とする必要があり、この幅がトラッククレーンのアウト
リガ−を着地させるのに充分でないと、架設工事を行っ
て要る間にトラッククレーンが転倒落下する等不測の事
故が発生しかねない。
On the other hand, ■the truck crane erection method, unlike the above ■ and ■, does not require the preparation, transportation, installation, and preparatory work of the erection materials necessary to carry out the erection work, so the construction period can be reduced. It has the advantage of shortening the construction time and reducing construction costs, as well as being able to be carried out even in locations where one side is mountainous and there is no place to work such as a mountain road or place to store construction materials. A truck crane is used to transport the bridge piers and bridge girders, and the construction site is fixed on the piers. It is necessary to provide enough space to stabilize the crane itself. If this width is not sufficient for the outriggers of the truck crane to land on the ground, unexpected accidents such as the truck crane falling during the erection work may occur. Accidents may occur.

またトラッククレーンが走行するための道路として既架
設橋桁を利用するので、この橋桁が軽量物でなければそ
れを懸架するトラッククレーンの定格荷重が大きいもの
を使用しなければならず、この結果、橋桁自体が大重量
となってそれを懸架するトラッククレーンをより大きい
定格荷重のものを使用せざるをえないとの悪循環が生じ
、架設工事を効果的に行えない。
In addition, since the existing bridge girder is used as the road for the truck crane to travel, unless the bridge girder is lightweight, the truck crane that suspends it must have a large load rating, and as a result, the bridge girder This creates a vicious cycle in which the heavy weight of the truck crane must be used to suspend it and a truck crane with a higher rated load, making it impossible to carry out the erection work effectively.

(課題を解決するための手段) 本発明は、前述の諸々の問題点に鑑み成されたものであ
って、架設資材の準備、搬送、設置並びに準備工事が不
要で、架設工事期間が短かく、工事費の低廉化が図れる
と共に如何なる立地条件下でも安全確実に実施できる橋
梁等構造物の架設工法を提供することを目的とするもの
であって、その解決手段として、走行式クレーンにより
構造物用脚部材を架設位置へ移走した後架設し、次いで
、当該構造物用脚部材に構造用桁部材を張架し、その後
次位の構造物用脚部材を懸架した走行式クレーンを既張
架の構造用桁部材上を利用して前記既架設の構造物用脚
部材位置まで移動させ、その後前記次位の構造物用脚部
材を架設し、そして、これら既架設の構造物用脚部材の
側径間に構造物用脚部材を張架するようにした構造物の
架設工法において、使用する構造用脚部材は、その幅が
走行式クレーンを安定状態に定置させるに充分な幅に構
成されてなること及び使用する構造用桁部材は、軽量な
トラ入構造損或いは高強度ケーブルを用いた構造桁であ
ることを特徴とする橋梁等構造物の架設工法を採用した
(Means for Solving the Problems) The present invention was made in view of the various problems mentioned above, and eliminates the need for preparing, transporting, and installing construction materials, as well as preparatory work, and shortens the construction period. The purpose of this project is to provide a construction method for structures such as bridges that can be carried out safely and reliably under any location conditions while reducing construction costs. After moving the structural leg members to the erection position, they are erected, and then the structural girder members are stretched over the structural leg members, and then the traveling crane with the next structural leg member suspended is stretched. The frame is moved to the position of the leg member for the already erected structure using the structural girder member, and then the leg member for the next structure is erected, and these leg members for the already erected structure are moved. In a structure erection method in which structural leg members are stretched across the side span of The construction method for structures such as bridges was adopted, which is characterized by the structure being constructed and the structural girder members used being structural girders using lightweight trussed structures or high-strength cables.

(実施例) 以下、本発明の実施例を第1図乃至第6図に基すき詳述
する。
(Example) Hereinafter, an example of the present invention will be described in detail with reference to FIGS. 1 to 6.

第1図の架設工法の全容を示す模式説明図によりその概
要を説明すると、渓谷(1)の両岸(2)(2)に橋台
(3)を構築すると共に渓谷(1)の最深部の川の両岸
(2a) (2a)に各々橋脚(4)を架設し、そして
、前記橋台(3)と橋脚(4)との側径間にトラックク
レーン(5)により懸架された橋桁(6)を架設し、そ
して、既架設橋桁(6)を利用してトラッククレーン(
5)を既架設橋脚位置まで移動させ、その後再度トラッ
ククレーン(5)により吊持された橋桁(6)を橋脚(
4)(4)間に架設し、その後上述と同じく既架設橋桁
(6)、橋脚(4)を利用してトラッククレーン(5)
を既架設橋脚位置まで移動させ、今度は対岸(2)の橋
台(3)と橋脚(4)との側径間に新たな橋桁(6)を
架設するようにしている、本発明の架設工法は概略上述
のようにして行われるが、詳細については第2図乃至第
7図の工程説明図により説明する。
To explain the outline using the schematic explanatory diagram shown in Figure 1 showing the entire construction method, bridge abutments (3) are constructed on both banks (2) (2) of the valley (1), and the bridge is constructed at the deepest part of the valley (1). Bridge piers (4) are constructed on each bank of the river (2a) (2a), and bridge girders (6) are suspended by a truck crane (5) between the abutments (3) and the side spans of the piers (4). ), and then using the existing bridge girder (6) to install a truck crane (
5) to the existing pier position, and then move the bridge girder (6) suspended by the truck crane (5) again to the pier (
4) After constructing the bridge between (4) and then using the existing bridge girders (6) and piers (4) as described above, a truck crane (5) will be installed.
The construction method of the present invention, in which the bridge girder (6) is moved to the position of the existing bridge pier, and a new bridge girder (6) is then constructed in the side span between the abutment (3) and the bridge pier (4) on the opposite bank (2). The process is generally carried out as described above, but the details will be explained with reference to the process diagrams of FIGS. 2 to 7.

第2回において、先ずコンクリート製の橋台(3)(3
)を渓谷(1)の両岸(2)(2)に構築し、次いで渓
谷(1)の最深部の川の両岸(2a) (2a)にコン
クリート製の橋脚台(4a) (4a)を設置固定する
。 そして、橋台(3)(3)及び橋脚台(4a) (
4a)の設置が終了すれば、第3図に示すように、前記
橋台(3)の近傍に定置させていたトラッククレーン(
5)により工場等で既に構築された橋脚(4)を懸架し
つ\一方の橋脚台(4a) (図では右岸)の位置まで
搬送し、当該橋脚台(4a)上に設置固定する。
In the second session, we first learned about concrete abutments (3) (3
) on both banks (2) (2) of the valley (1), and then concrete abutments (4a) (4a) were constructed on both banks (2a) (2a) of the river at the deepest part of the valley (1). Install and fix. And abutment (3) (3) and abutment (4a) (
Once the installation of 4a) is completed, as shown in Figure 3, the truck crane (
5), the pier (4) already constructed in a factory, etc. is suspended and transported to the position of one pier abutment (4a) (on the right bank in the figure), and installed and fixed on the pier abutment (4a).

尚、前記橋脚(4)(4)の幅は、トラッククレーン(
5)に具備したアウトリガ−が充分に着地することが出
来る程度の幅に構成している。
In addition, the width of the piers (4) (4) is the same as that of the truck crane (
5) The width is wide enough to allow the outriggers provided in 5) to sufficiently land on the ground.

橋脚(4)の設置固定が完了し、その橋脚(4)と前記
橋台(3)との側径間に橋桁(6)を架設する場合には
、第4図にある通り、橋脚(4)と前記橋台(3)とに
橋桁(6)の支持部材(7)(7)を据え付け、その後
、トラッククレーン(5)によって剛性が高く、しかも
軽量な後述するトラス構造桁の橋桁(6)を懸架しつ一
搬送して橋脚(4)前記橋台(3)との側径間に橋桁(
6)を張架する。そして、この張架された橋桁(6)上
に床材(8)を敷設固着し、橋桁(6)の架設を終了す
る。
When the installation and fixing of the pier (4) is completed and the bridge girder (6) is to be constructed between the pier (4) and the abutment (3), the pier (4) is installed as shown in Figure 4. The supporting members (7) (7) of the bridge girder (6) are installed on the abutment (3) and the bridge girder (6), which is a highly rigid and lightweight truss structure girder (described later), is then installed using a truck crane (5). The bridge girder (4) is suspended and transported and installed in the side span between the bridge pier (4) and the abutment (3).
6) Stretch it. Then, the flooring material (8) is laid and fixed on the stretched bridge girder (6), and the construction of the bridge girder (6) is completed.

このようにして一つの橋脚(4)と橋台(3)との側径
間に橋桁(6)の張架が終われば、対岸の橋脚台(4a
)上に次の橋脚(4)を設置するのであるが、それは前
述した第3図の場合と同様にしてトラッククレーン(5
)によって橋脚(4)を吊持し、当該トランククレーン
(5)が既架設橋桁(6)上を自走して端部に達した位
置で停止させる。
In this way, once the bridge girder (6) has been stretched between the side span of one pier (4) and abutment (3), the pier abutment (4a) on the opposite bank is finished.
), the next pier (4) is installed on top of the truck crane (5) in the same way as in the case shown in Figure 3 above.
), the bridge pier (4) is suspended, and the trunk crane (5) moves by itself on the existing bridge girder (6) and stops when it reaches the end.

そして、橋脚(4)を橋脚台(4a)上に設置固定する
(第5図参照)。
Then, the pier (4) is installed and fixed on the pier abutment (4a) (see FIG. 5).

次に、橋脚(4) (4)の側径間に橋桁(6)を架設
する場合には、第6図にある通り、橋脚(4)(4)に
橋桁(6)の支持部材(7)(7)を据え付け、その後
、トラッククレーン(5)によって既架設橋桁(6)上
に載置している剛性が高く、しかも軽量な後述するトラ
ス桁構造の橋桁(6]吊り下げつ\搬送して橋脚(4)
 (4)の側径間に橋桁(6)を架設する。そして、こ
の架設された橋桁(6)上に床材(8)を敷設固着し、
橋桁(6)の架設を終了する。
Next, when constructing the bridge girder (6) in the side span of the bridge pier (4) (4), as shown in Figure 6, the supporting member (7) of the bridge girder (6) ) (7), and then the highly rigid and lightweight bridge girder (6) with a truss girder structure, which will be described later, is placed on the existing bridge girder (6) using a truck crane (5) and transported. Pier (4)
A bridge girder (6) will be constructed in the side span of (4). Then, the flooring material (8) is laid and fixed on the constructed bridge girder (6),
Erection of bridge girder (6) is completed.

橋脚(4) (4)の側径間に橋桁(6)の架設が終了
すれば、対岸の橋台(3)と橋脚(4)との側径間に新
たな橋桁(6)を架設するのであるが、それは前述した
第3図の場合と同様にしてトラッククレーン(5)によ
って橋脚(4)を懸架し、当該トラッククレーン(5)
が既架設橋桁(6)上を自走して橋脚(4)端部に達し
た位置で停止させ、前述の通り架設する(第7図参照)
Pier (4) Once the construction of the bridge girder (6) is completed in the side span of (4), a new bridge girder (6) will be constructed in the side span between the abutment (3) and pier (4) on the opposite bank. However, the pier (4) is suspended by a truck crane (5) in the same way as in the case of Fig. 3 mentioned above, and the truck crane (5)
The bridge runs on the existing bridge girder (6), stops when it reaches the end of the bridge pier (4), and is erected as described above (see Figure 7).
.

以上のようにして架設工事は完了するが、前述した橋桁
(6)は剛性が高く、しかも軽量なトラス構造桁が適し
ているが、それは当該橋桁(6)が重量物であるとそれ
を懸架するトラッククレーン(5)を大定格荷重のもの
にしなければならず、結果として好ましくない。また、
この橋桁(6)は前述の通りトランククレーン(5)が
路面として利用するが、この際横倒れ座屈が生じるので
この防止構造も採用しているものであって、その詳細構
造を第8図及び第9″図の斜視図により説明する。
The erection work is completed as described above, but a truss structure girder with high rigidity and light weight is suitable for the bridge girder (6) mentioned above, but if the bridge girder (6) is heavy, it cannot be suspended. The truck crane (5) must have a large load rating, which is undesirable as a result. Also,
As mentioned above, this bridge girder (6) is used as a road surface by the trunk crane (5), but since sideways buckling occurs at this time, a structure to prevent this is also adopted, and its detailed structure is shown in Figure 8. This will be explained with reference to the perspective view of FIG.

第8図は橋桁(6)の基本例を示す斜視図であるが橋桁
(6)の本体(61)は断面I型の鋼材を使用し、中央
下面に適当長さの柱材(62)を取りつけ、この柱材(
62)に鋼製型材の下弦材(63) (63)を図示の
通り張架させたトラス構造指形状としている。
Figure 8 is a perspective view showing a basic example of a bridge girder (6). The main body (61) of the bridge girder (6) is made of steel with an I-shaped cross section, and a column (62) of an appropriate length is installed on the lower center surface. Install this pillar material (
As shown in the figure, the lower chord members (63) (63) of steel shapes are stretched over the truss structure fingers (62).

尚、下弦材(63) (63)は高強度ケーブル部材(
直径7fflIlのPCl線を束ねた平行線ケーブル、
引張強度i 165 kg/mm2)を使用してもよい
。 ところが、第8図の橋桁(6)形状だけでば本体(
61)の構成要素である上フランジ(6]a)が弱く、
前述の通り、横倒れ座屈が生じるのでこれを防止するた
めに、第9図にある横倒れ防止構造0■を採用している
In addition, the lower chord material (63) (63) is a high-strength cable member (
Parallel wire cable made by bundling PCl wires with a diameter of 7fflIl,
A tensile strength i 165 kg/mm2) may be used. However, if only the shape of the bridge girder (6) in Figure 8 is used, the main body (
The upper flange (6]a), which is a component of 61), is weak;
As mentioned above, sideways falling buckling occurs, and in order to prevent this, the sideways falling prevention structure 0■ shown in FIG. 9 is adopted.

横倒れ防止構造00は、2本のL型鋼(ss41  !
i材)を背面接合して一対とした主部材(10a) (
10a)が橋桁(6)本体(61)の上フランジ(61
a)にそれと直交する方向に配設されると共にボルトで
定着され、この主部材(10a) (10a)の各端部
には4本の副部材(10b) (10b)の各端部がボ
ルト止めされると共に他端が前記上フランジ(61a)
に各々ボルト止めされ、全体が平面夏型とされている構
成である。そして、この横倒れ防止構造00は橋桁(6
)本体(61)に横桁(図示省略)を取りつけた後取り
外すようにしている。
Side fall prevention structure 00 consists of two L-shaped steels (ss41!
The main member (10a) (
10a) is the upper flange (61) of the bridge girder (6) main body (61).
a) in a direction perpendicular thereto and fixed with bolts, and each end of four sub-members (10b) (10b) is bolted to each end of this main member (10a) (10a). The other end is fixed to the upper flange (61a).
They are bolted to each other, and the whole structure is a flat summer type. This horizontal collapse prevention structure 00 is a bridge girder (6
) A cross beam (not shown) is attached to the main body (61) and then removed.

本発明の架設工法は以上の通りであるが、橋脚が2以上
架設される場合には前述の工程を反復継続して行うよう
にすれば良く、立地条件に適応した架設工事をすれば良
い。
The construction method of the present invention is as described above, but when two or more piers are to be constructed, the above-mentioned steps may be repeated and continued, and the construction work may be carried out in accordance with the site conditions.

尚、本発明を実際に適用する構造物の一例は第10図の
模式図に示す通り、橋全長L;105m、橋脚間421
;35m、橋台と橋脚間ff12;35m、橋脚の高さ
H; 20 m、橋脚幅T ; 6 m、橋脚間に架設
する橋桁の幅tl;4m、橋台と橋脚間に架設する橋桁
の幅t2 ;2.5m、とした。
An example of a structure to which the present invention is actually applied is, as shown in the schematic diagram of FIG.
35 m, height H of the bridge pier; 20 m, width T of the pier; 6 m, width tl of the bridge girder installed between the abutment; 4 m, width t2 of the bridge girder installed between the abutment and the pier; ;2.5m.

この結果、20tのダンプ車が走行しても何ら影響がな
く、定格荷重の小さい70tのトラッククレーンが使用
でき、しかも、その工事期間も従来の工法に比べて17
4と短かく、架設工事費用も従来の工法に比べて174
の費用で済むことが確認できた。
As a result, there is no effect even when a 20-ton dump truck is driven, and a 70-ton truck crane with a small rated load can be used. Moreover, the construction period is 17 times longer than with conventional construction methods.
4, and the construction cost is 174 yen compared to the conventional construction method.
It was confirmed that the cost would be .

(発明の効果) 本発明の架設工法は以上の通りであるが、この架設工法
によれば、架設作業塔、ケーブルクレーン、アンカーブ
ロック、仮ケーブル等の架設資材の準備、搬送、設置並
びに準備工事が不要となり、架設機材のトラッククレー
ンも軽量なものが使用でき、その結果、架設工事期間の
短縮化、工事費の低廉化が図れると共に如何なる立地条
件下でも安全確実に実施できる等有益な発明である。
(Effects of the Invention) The erection method of the present invention is as described above. According to this erection method, preparation, transportation, installation and preparatory work of erection materials such as an erection work tower, cable crane, anchor block, temporary cable, etc. This is a beneficial invention, as it eliminates the need for a lightweight truck crane, which is used as construction equipment, and as a result, the construction period can be shortened, construction costs can be reduced, and construction can be carried out safely and reliably under any site conditions. be.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の架設工法の概要を示す模式説明図、第
2図乃至第7図は本発明の架設工法に係る各工程を示す
工程説明図、第8図は本発明の架設方法に使用する橋桁
の基本構造例を示す斜視図、第9図は本発明の架設工法
に使用する橋桁に横倒れ防止構造を附帯させた構造を示
す斜視図、第10図は本発明に係る構造物の寸法関係を
示す模式図である。 符号の名称は以下の通りである。 (1)−・渓谷、(2)−渓谷の両岸、(3)・・・橋
台、(4)−・−橋脚、(5)−・トラッククレーン、
(6)−橋桁、(7)・−橋桁支持部材、(8)−橋桁
床材、0ω−・横倒れ防止構造、(10a)・・−横倒
れ防止構造の主部材、(10b)・−・横倒れ防止構造
の副部材、(61)−橋桁本体、(61a)−・−橋桁
本体の上フランジ、(62)−柱材、(63)−・−下
弦材。 特許出願人 神鋼鋼線工業株式会社
Fig. 1 is a schematic explanatory diagram showing an overview of the erection method of the present invention, Figs. FIG. 9 is a perspective view showing an example of the basic structure of the bridge girder used, FIG. 9 is a perspective view showing a structure in which the bridge girder used in the construction method of the present invention is attached with a side collapse prevention structure, and FIG. 10 is a structure according to the present invention. It is a schematic diagram showing the dimensional relationship of. The names of the codes are as follows. (1) - Valley, (2) - Both banks of the valley, (3) - Bridge abutment, (4) - Bridge pier, (5) - Truck crane,
(6) - Bridge girder, (7) - Bridge girder support member, (8) - Bridge girder floor material, 0ω - Side collapse prevention structure, (10a) - Main member of side collapse prevention structure, (10b) - - Sub-members of side collapse prevention structure, (61) - bridge girder main body, (61a) - upper flange of bridge girder main body, (62) - column material, (63) - lower chord member. Patent applicant: Shinko Wire Industry Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] (1)走行式クレーンにより構造物用脚部材を架設位置
へ移走した後架設し、次いで、当該構造物用脚部材に構
造用桁部材を張架し、その後次位の構造物用脚部材を懸
架した走行式クレーンを既張架の構造用桁部材を利用し
て前記既架設の構造物用脚部材位置まで移動させ、その
後前記次位の構造物用脚部材を架設し、そして、これら
既架設の構造物用脚部材の側径間に構造物用脚部材を張
架するようにした構造物の架設工法において、使用する
構造用脚部材は、その幅が走行式クレーンを安定状態に
定置させるに充分な幅に構成されてなることを特徴とす
る橋梁等構造物の架設工法。
(1) Move the structural leg member to the erection position using a traveling crane, then erect it, then stretch the structural girder member to the structural leg member, and then install the next structural leg member. The mobile crane suspending the structure is moved to the position of the leg member for the already erected structure using the structural girder member of the existing frame, and then the leg member for the next structure is erected. In a structure erection method in which the structural leg members are stretched between the side spans of the existing structural leg members, the width of the structural leg members used is such that the width of the structural leg members is sufficient to keep the traveling crane in a stable state. A construction method for a structure such as a bridge, which is characterized by being constructed with a width sufficient to allow it to be placed in a fixed position.
(2)使用する構造用桁部材は、軽量なトラス構造桁或
いは高強度ケーブルを用いた構造桁であることを特徴と
する請求項(1)記載の橋梁等構造物の架設工法。
(2) The method for constructing a structure such as a bridge according to claim (1), wherein the structural girder member used is a lightweight truss structural girder or a structural girder using high-strength cables.
JP3582388A 1988-02-18 1988-02-18 Construction method for bridges and other structures Expired - Lifetime JP2578152B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3582388A JP2578152B2 (en) 1988-02-18 1988-02-18 Construction method for bridges and other structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3582388A JP2578152B2 (en) 1988-02-18 1988-02-18 Construction method for bridges and other structures

Publications (2)

Publication Number Publication Date
JPH01210510A true JPH01210510A (en) 1989-08-24
JP2578152B2 JP2578152B2 (en) 1997-02-05

Family

ID=12452674

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3582388A Expired - Lifetime JP2578152B2 (en) 1988-02-18 1988-02-18 Construction method for bridges and other structures

Country Status (1)

Country Link
JP (1) JP2578152B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1333136C (en) * 2004-09-20 2007-08-22 四川石油管理局 Construction technology of suspensing truss crossing river
JP2009035946A (en) * 2007-08-02 2009-02-19 Taisei Corp Oscillation preventive structure of columnar structure, installation system of columnar structure and installation method of columnar structure
US20110219554A1 (en) * 2010-03-15 2011-09-15 Aumuller Paul M Bridge construction and method of replacing bridges
JP2014025337A (en) * 2012-06-21 2014-02-06 Jfe Steel Corp Construction method of temporary bridge and precast floor slab used for construction method
JP2019090221A (en) * 2017-11-14 2019-06-13 日本橋梁株式会社 Composite girder removal method
CN110306433A (en) * 2019-04-29 2019-10-08 中铁大桥局集团有限公司 A kind of turbulent flow waters guide cable is quick to cross river method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1333136C (en) * 2004-09-20 2007-08-22 四川石油管理局 Construction technology of suspensing truss crossing river
JP2009035946A (en) * 2007-08-02 2009-02-19 Taisei Corp Oscillation preventive structure of columnar structure, installation system of columnar structure and installation method of columnar structure
US20110219554A1 (en) * 2010-03-15 2011-09-15 Aumuller Paul M Bridge construction and method of replacing bridges
US8234738B2 (en) * 2010-03-15 2012-08-07 Newton Bridge Solutions Ltd Bridge construction and method of replacing bridges
US8448280B2 (en) 2010-03-15 2013-05-28 Newton Bridge Solutions Ltd Method of providing a parapet wall on a bridge
JP2014025337A (en) * 2012-06-21 2014-02-06 Jfe Steel Corp Construction method of temporary bridge and precast floor slab used for construction method
JP2019090221A (en) * 2017-11-14 2019-06-13 日本橋梁株式会社 Composite girder removal method
CN110306433A (en) * 2019-04-29 2019-10-08 中铁大桥局集团有限公司 A kind of turbulent flow waters guide cable is quick to cross river method

Also Published As

Publication number Publication date
JP2578152B2 (en) 1997-02-05

Similar Documents

Publication Publication Date Title
US5511268A (en) Construction of large structures by robotic crane placement of modular bridge sections
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN110042769B (en) Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge
WO1996005375A9 (en) Construction of large structures by robotic crane placement of modular bridge sections
JP3440422B2 (en) Bridge construction method and bridge construction device
CN106049293A (en) Method for installing stiffening beam of suspension bridge over navigable river and swing shift system used in method
CN110820602A (en) Single-segment box girder bridge girder erection machine and operation method thereof
US2878498A (en) Bridge construction
CN112160246B (en) Method for installing composite beam
JPH01210510A (en) Method of installation construction of structure such as bridge
CN113026528A (en) Method for mounting mountain forest space curve steel structure plank road
CN110344334B (en) Construction method for two-span continuous steel-concrete composite bridge by adopting back cable type bridge girder erection machine
CN111851307A (en) Large-span prefabricated assembly type corrugated web combined box girder transportation frame construction method
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
CN214328478U (en) Three-tower self-anchored suspension bridge
CN116043715A (en) Construction method for construction of prefabricated segmental beams under complex working conditions
CN115748513A (en) Construction method of ultra-small high-span-ratio all-welded steel truss girder bridge based on cantilever aerial work platform
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
JP2002309511A (en) Main girder structure of truss bridge and construction method for main girder
CN114427199A (en) Excavation-free mechanized construction method for mountain pedestrian footpath
CN110725208A (en) Construction method for erecting pier top superposed beam without support
CN206034290U (en) Installation of suspension bridge stiffening beam is with swinging system of moving on navigable river
JP4375788B2 (en) Construction method of upper-floor type suspension floor slab bridge
CN113718654B (en) Installation structure for ropeless beam section of bridge tower area
CN217174379U (en) A portable basket of hanging for I-steel girder installation construction