CN115961549A - Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge - Google Patents
Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge Download PDFInfo
- Publication number
- CN115961549A CN115961549A CN202211541639.1A CN202211541639A CN115961549A CN 115961549 A CN115961549 A CN 115961549A CN 202211541639 A CN202211541639 A CN 202211541639A CN 115961549 A CN115961549 A CN 115961549A
- Authority
- CN
- China
- Prior art keywords
- steel
- support
- section
- standard
- transverse
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本申请公开了一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法,通过在主塔墩旁搭建纵向支架,在纵向支架一侧搭建横向支架,然后在纵向支架上完成主塔两侧的钢混结合段施工;并利用提升站将组焊模块逐一提升至横向支架,并进行拼装成标准节段,完成若干个标准节段的组装和转移,然后在纵向支架上将钢混结合段以及多个标准节段拼装焊接成整体,提升横向支架直至与起始端表面齐平;然后在龙门吊下方完成标准节段拼装,利用提升站和龙门吊接着将标准节段纵移至架桥机下方,最后完成标准节段与钢混结合段的拼接,以完成钢梁的架设。以便在施工场地狭小、周边地形复杂的区域完成钢箱梁拼接步骤。
The present application discloses a construction method of post-feeding girder type erection of large-tonnage steel girders of a cable-stayed bridge. By building a longitudinal support next to the main tower pier, a transverse support is built on one side of the longitudinal support, and then the main structure is completed on the longitudinal support. The construction of the steel-concrete joint section on both sides of the tower; and use the lifting station to lift the welding modules to the horizontal support one by one, and assemble them into standard sections, complete the assembly and transfer of several standard sections, and then place the steel on the longitudinal support. The mixed joint section and multiple standard sections are assembled and welded into a whole, and the horizontal support is raised until it is flush with the surface of the starting end; then the standard section assembly is completed under the gantry crane, and the standard section is moved longitudinally to the bridge erection by using the lifting station and the gantry crane Below the machine, the splicing of the standard section and the steel-concrete joint section is finally completed to complete the erection of the steel beam. In order to complete the steel box girder splicing steps in areas with narrow construction sites and complex surrounding terrain.
Description
技术领域technical field
本申请涉及斜拉桥施工的领域,尤其是涉及一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法。The present application relates to the field of construction of cable-stayed bridges, in particular to a method for constructing large-tonnage full-segment steel girders of a cable-stayed bridge with post-feeding girder type erection.
背景技术Background technique
目前,斜拉桥钢梁架设方法一般有三种,一种是悬臂拼装法,该法主要特征为先将梁段运输到桥位待架处,然后利用桥面吊机垂直起吊架设就位。该方法需要在桥位处有运输通道的情况才可实现;一种是纵向顶推法,该方法法主要特点为在桥位处拼装一排临时墩,在一端架设并顶推到位后挂索实现斜拉桥体系转换,该法需在桥的一头或两头有拼装场地和运输通道,一种是满堂支架法,即比照混凝土现浇梁支架,沿主梁走行搭设满堂支架,在支架上安装钢箱梁制造胎架,钢箱梁板件在工厂下料后运至现场,用现场吊机在胎架上组焊完成钢梁,最后挂设斜拉索,张拉完成体系转换将钢箱梁脱离胎架,完成钢箱梁架设,避免支架下沉影响钢箱梁拼装精度,支架所需钢材数量相当巨大且支架基础处理要求很高。At present, there are generally three methods for erecting steel girders of cable-stayed bridges. One is the cantilever assembly method. The main feature of this method is to transport the girder sections to the bridge position to be erected, and then use the deck crane to vertically lift and erect them in place. This method can only be realized when there is a transportation channel at the bridge site; one is the longitudinal push method, the main feature of this method is to assemble a row of temporary piers at the bridge site, erect at one end and push it into place, then hang the cable To realize the conversion of the cable-stayed bridge system, this method needs to have an assembly site and a transportation channel at one or both ends of the bridge. One is the full hall support method, that is, compared with the concrete cast-in-place beam support, the full hall support is erected along the main beam and installed on the support. The steel box girder manufactures the tire frame. The steel box girder plate is transported to the site after being unloaded in the factory. The steel beam is assembled and welded on the tire frame by an on-site crane. Finally, the stay cable is hung, and the system conversion is completed by tensioning the steel box. The beam is detached from the tire frame to complete the erection of the steel box girder, so as to avoid the subsidence of the bracket and affect the assembly accuracy of the steel box girder. The amount of steel required for the bracket is quite large and the requirements for the foundation treatment of the bracket are very high.
然而,在需要跨越既有道路桥梁、山区、河流等建设场地有限的地方修建钢梁斜拉桥时,尤其是在已经运行的高速公路处,不仅将面临施工场地狭小、地形复杂的问题,施工还容易干扰到地面交通,难以通过悬臂拼装法和纵向顶推法完成钢箱梁节段拼装施工,因此仍有改进空间。However, when building steel girder cable-stayed bridges in places with limited construction sites such as crossing existing roads, bridges, mountains, and rivers, especially on expressways that have already been in operation, not only will the construction site be narrow and the terrain complex, but the construction It is also easy to interfere with the ground traffic, and it is difficult to complete the steel box girder segmental assembly construction through the cantilever assembly method and the longitudinal push method, so there is still room for improvement.
发明内容Contents of the invention
为了在施工场地狭小、周边地形复杂的区域完成钢箱梁拼接步骤,本申请提供一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法。In order to complete the splicing steps of steel box girders in areas with narrow construction sites and complex surrounding terrains, the present application provides a construction method for rear-feeding girder erection of large-tonnage full-segment steel girders of cable-stayed bridges.
本申请提供的一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法采用如下的技术方案:The construction method of rear-feeding girder type erection of a large tonnage entire section steel girder of a cable-stayed bridge provided by the application adopts the following technical scheme:
一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法,包括以下步骤:A cable-stayed bridge large-tonnage full-segment steel girder post-feeding construction method comprises the following steps:
S1: 施工准备:将钢箱梁的标准节段分为三块组合模块进行制作,并在预拼场进行预拼;S1: Construction preparation: divide the standard section of the steel box girder into three combined modules for fabrication, and pre-assemble in the pre-assembly field;
S2: 支架搭设:在主塔墩旁搭建纵向支架,纵向支架沿桥向延伸,且纵向支架的支撑面位于公路上方,在纵向支架一侧搭建横向支架,横向支架的支撑面与纵向支架的支撑面衔接;S2: Bracket erection: build a longitudinal bracket next to the main tower pier, the longitudinal bracket extends along the bridge direction, and the supporting surface of the longitudinal bracket is located above the road, and a horizontal bracket is built on the side of the longitudinal bracket, the supporting surface of the horizontal bracket and the support of the longitudinal bracket face connection;
S3: 钢混结合段施工:在纵向支架上完成主塔两侧的钢混结合段施工;S3: Construction of the steel-concrete joint section: complete the construction of the steel-concrete joint section on both sides of the main tower on the longitudinal support;
S4:提升站施工:在横向支架处搭建提升站,提升站用于将组合模块提升至横向支架上;S4: Lifting station construction: build a lifting station at the horizontal support, and the lifting station is used to lift the combined module to the horizontal support;
S5:起始段施工:利用提升站将组焊模块逐一提升至横向支架,并进行拼装焊接成钢箱梁标准节段,并将标准节段横移至纵向支架支撑面,然后纵移至纵向支架远离主塔的一端位置处,按照以上步骤完成若干个标准节段的组装和转移,然后在纵向支架上将钢混结合段以及多个标准节段拼装焊接成整体,以完成主塔一侧的起始段施工;S5: Construction of the initial section: use the lifting station to lift the assembly and welding modules to the horizontal support one by one, and assemble and weld them into a steel box girder standard section, and move the standard section horizontally to the support surface of the longitudinal support, and then move vertically to the vertical At the end of the bracket away from the main tower, complete the assembly and transfer of several standard sections according to the above steps, and then assemble and weld the steel-concrete joint section and multiple standard sections on the longitudinal support to complete the side of the main tower The initial section of construction;
S6:横向支架提升:将横向支架的支撑面升高至与起始段上表面齐平并进行衔接;S6: Lifting of the horizontal support: raise the support surface of the horizontal support to be flush with the upper surface of the initial section and connect;
S7:安装龙门吊和架桥机:在起始段上表面安装龙门吊和架桥机,龙门吊和架桥机可沿桥向移动;S7: Install gantry crane and bridge erecting machine: Install gantry crane and bridge erecting machine on the upper surface of the initial section, and the gantry crane and bridge erecting machine can move along the bridge direction;
S8:后喂梁施工:利用提升站将组焊模块逐一提升至横向支架的支撑面上,并进行拼装焊接成钢箱梁标准节段,然后将三块组焊模块横移至起始段上表面以及纵移至龙门吊下方,并通过龙门吊调整三块组合模块的位置,然后将三块组合模块拼装成标准节段,接着将标准节段纵移至架桥机下方,架桥机提梁并纵移,标准节段纵移到位后,旋转九十度。然后落梁,最后完成标准节段与钢混结合段的拼接,以完成第一节钢梁的架设;S8: Post-feeding beam construction: use the lifting station to lift the assembly and welding modules one by one to the support surface of the transverse support, and assemble and weld them into a steel box girder standard section, and then move the three assembly and welding modules to the initial section The surface and vertically move to the bottom of the gantry crane, and adjust the position of the three combined modules through the gantry crane, then assemble the three combined modules into a standard segment, and then move the standard segment longitudinally to the bottom of the bridge erecting machine, and the bridge erecting machine lifts the beam and vertically After the standard segment is moved longitudinally in place, it is rotated 90 degrees. Then drop the beam, and finally complete the splicing of the standard section and the steel-concrete joint section to complete the erection of the first steel beam;
S9:重复所述S8,架桥机继续前移,完成剩下钢箱梁标准节段的拼装。S9: Repeat the above S8, the bridge erecting machine continues to move forward, and completes the assembly of the remaining steel box girder standard sections.
通过采用上述技术方案,将钢箱梁标准节段分为三块组焊模块,目的是便于在狭小的地段进行刚箱梁的转运,并且减轻节段起吊重量以及便于在横向支架上横移,另外,钢箱梁从主塔的侧面进行提升、横移、纵移,以便钢箱梁起始段施工,然后通过提升横向支架,以便将梁段转运至起始段表面,通过将拼装好的标准节段到架桥机下面,并旋转90度然后架设,此方案解决了悬吊法运输条件不能满足且桥下也无位置可吊装整段钢箱梁的问题,也改善了满堂支架法中所面临的支架所需钢材数量相当巨大且支架基础处理要求很高的问题,而且在提高钢箱梁施工效率的同时,减少了铁路桥梁对居民、城市地面交通和高速公路高架桥的干扰,在钢箱梁架设过程中将对高速公路及武广高铁造成的影响降到最低,并且达到在施工场地狭小、周边地形复杂的区域完成钢箱梁拼接步骤的目的。By adopting the above technical scheme, the standard section of the steel box girder is divided into three welding modules, the purpose is to facilitate the transfer of the steel box girder in a narrow area, reduce the lifting weight of the section and facilitate the lateral movement on the horizontal support. In addition, the steel box girder is lifted, moved horizontally, and moved vertically from the side of the main tower to facilitate the construction of the initial section of the steel box girder, and then the horizontal support is lifted to transfer the beam section to the surface of the initial section. The standard section is placed under the bridge erecting machine, rotated 90 degrees and then erected. This solution solves the problem that the suspension method cannot meet the transportation conditions and there is no place under the bridge to hoist the entire steel box girder. Faced with the problem that the amount of steel required for the support is quite large and the treatment of the support foundation is very demanding, and while improving the construction efficiency of the steel box girder, it reduces the interference of the railway bridge on residents, urban ground traffic and expressway viaducts. During the erection of the box girder, the impact on the expressway and the Wuhan-Guangzhou high-speed railway will be minimized, and the purpose of completing the splicing steps of the steel box girder in the narrow construction site and complex surrounding terrain will be achieved.
优选的,在所述S5中,在横向支架上安装横向导轨,横向导轨横向延伸至纵向支架上,并在纵向支架上安装纵向导轨,纵向导轨与横向导轨衔接,且纵向导轨沿桥向延伸,在标准节段移动过程中,先沿横向导轨横移至纵向支架上,然后沿纵向导轨纵移至纵向支架端部。Preferably, in said S5, a transverse guide rail is installed on the transverse support, the transverse guide rail extends laterally to the longitudinal support, and a longitudinal guide rail is installed on the longitudinal support, the longitudinal guide rail is connected with the transverse guide rail, and the longitudinal guide rail extends along the bridge direction, During standard segmental movement, first move laterally along the transverse guide rails to the longitudinal support, and then longitudinally move along the longitudinal guide rails to the end of the longitudinal support.
通过采用上述技术方案,设计横纵导轨,以便标准节段精准落位,有利于标准节段拼装。By adopting the above technical scheme, the horizontal and vertical guide rails are designed so that the standard segments can be positioned accurately, which is conducive to the assembly of the standard segments.
优选的,所述提升站包括两列横向分布的支撑架,所述横向支架位于两列支撑架之间,且所述横向支架两侧分别竖向滑动连接于两列支撑架内侧。Preferably, the lifting station includes two rows of supporting frames distributed horizontally, the horizontal frame is located between the two rows of supporting frames, and both sides of the horizontal frame are respectively vertically slidably connected to the inner sides of the two rows of supporting frames.
通过采用上述技术方案,支撑架不仅对提升站起到支撑作用,同时对横向支架起到限位和导向作用,有利于横向支架的稳定升降,进而提高钢箱梁转运效率。By adopting the above technical solution, the support frame not only supports the lifting station, but also limits and guides the transverse support, which is conducive to the stable lifting of the transverse support and improves the transfer efficiency of the steel box girder.
优选的,所述提升站设置有由于提升横向支架的提升装置。Preferably, said lifting station is provided with lifting means for lifting the transverse support.
通过采用上述技术方案,以实现横向支架的自动化升降,减少吊机设备投入,同时有利于提高横向支架的安装效率。By adopting the above-mentioned technical scheme, the automatic lifting of the horizontal support can be realized, the investment in crane equipment can be reduced, and the installation efficiency of the horizontal support can be improved at the same time.
优选的,在所述S6中,将横向支架支撑面提升至设计高度后,然后向上接长横向支架下方的立柱,立柱对横向支架的支撑面进行支撑。Preferably, in the above S6, after the support surface of the transverse support is raised to the designed height, the column below the transverse support is extended upwards, and the column supports the support surface of the transverse support.
通过采用上述技术方案,有利于提高横向支架的稳定性。By adopting the above technical solution, it is beneficial to improve the stability of the transverse support.
优选的,所述S8中,在高速公路处搭建移动式防护棚,移动式防护棚沿高速公路方向移动,在标准节段就位安装过程中,移动式防护棚移动至标准节段下方。Preferably, in said S8, a mobile protective shed is built at the expressway, and the mobile protective shed moves along the direction of the expressway. During the installation process of the standard segment, the mobile protective shed moves below the standard segment.
通过采用上述技术方案,移动式防护棚起到防护作用,有利于提高施工安全性。By adopting the above technical scheme, the mobile protective shed plays a protective role, which is beneficial to improving construction safety.
优选的,所述S3包括:Preferably, said S3 includes:
S3.1:纵向支架上安装胎架,然后在胎架上进行钢箱梁拼装,钢箱梁拼焊完成后拆除胎架,并用分配梁将钢箱梁支撑在纵向支架上;S3.1: Install the tire frame on the longitudinal support, then assemble the steel box girder on the tire frame, remove the tire frame after the tailor welding of the steel box girder, and use the distribution beam to support the steel box girder on the longitudinal support;
S3.2:绑扎钢筋、浇筑钢混结合段底板混凝土;S3.2: Binding steel bars and pouring concrete for the bottom slab of the steel-concrete joint section;
S3.3:底板混凝土达到设计强度后,在钢箱梁顶面安装对拉结构,并对每根对拉钢筋施加预拉力,使钢混结合段与主塔下横梁形成固结;S3.3: After the bottom slab concrete reaches the design strength, install the opposite tension structure on the top surface of the steel box girder, and apply pre-tension force to each opposite tension steel bar, so that the steel-concrete joint section and the lower beam of the main tower are consolidated;
S3.4:在钢混结合段内立内模,浇筑腹板和顶板混凝土。S3.4: Establish the inner form in the steel-concrete joint section, and pour the web and roof concrete.
通过采用上述技术方案,有利于提高钢混结合段施工精度以及稳定性。By adopting the above technical scheme, it is beneficial to improve the construction accuracy and stability of the steel-concrete combination section.
附图说明Description of drawings
图1是本申请实施例一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法中组焊模块在横向支架上拼装成标准节段时的状态示意图。Fig. 1 is a schematic diagram of the status of assembly and welding modules assembled into standard sections on transverse supports in a construction method of post-feeding beam type erection of large-tonnage full-segment steel girders of a cable-stayed bridge according to an embodiment of the present application.
图2是图1中A处的放大示意图。FIG. 2 is an enlarged schematic view of point A in FIG. 1 .
图3是本申请实施例一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法中起始段拼装完毕的状态示意图。Fig. 3 is a schematic diagram of the assembled state of the initial section in the erection method of a large-tonnage full-segment steel girder of a cable-stayed bridge according to an embodiment of the present application.
图4是本申请实施例一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法中安装龙门吊和吊桥机时的状态示意图。Fig. 4 is a schematic diagram of the state when the gantry crane and the suspension bridge crane are installed in the construction method of the large-tonnage full-segment steel girder of the cable-stayed bridge according to the embodiment of the present application.
图5是本申请实施例一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法中悬拼钢箱梁标准节段时的状态示意图。Fig. 5 is a schematic diagram of the state of the standard section of the cantilevered steel box girder in the construction method of the post-feeding girder type erection method of the large-tonnage whole-segment steel girder of the cable-stayed bridge according to the embodiment of the present application.
附图标记说明:1、主塔;2、钢混结合段;3、纵向支架;4、公路;5、提升站;51、支撑架;52、提升装置;6、横向支架;7、标准节段;71、组焊模块;8、横向导轨;9、纵向导轨;10、起始段;11、立柱;12、架桥机;13、龙门吊;14、移动式防护棚。Explanation of reference signs: 1. main tower; 2. steel-concrete combined section; 3. longitudinal support; 4. road; 5. lifting station; 51. support frame; 52. lifting device; 6. horizontal support; 7. standard section Section; 71. Welding module; 8. Transverse guide rail; 9. Longitudinal guide rail; 10. Initial section; 11. Upright column; 12. Bridge erecting machine; 13. Gantry crane;
具体实施方式Detailed ways
以下结合附图1-5对本申请作进一步详细说明。The present application will be described in further detail below in conjunction with accompanying drawings 1-5.
本申请实施例公开一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法。包括以下步骤:The embodiment of the present application discloses a method for constructing a cable-stayed bridge with a large tonnage full-segment steel girder rear-fed girder type erection. Include the following steps:
S1: 施工准备:参照图1和图2,将钢箱梁的标准节段7分为三块组合模块进行制作,并在预拼场进行预拼;S1: Construction preparation: Referring to Figure 1 and Figure 2, the
S2: 支架搭设:在主塔1墩旁搭建纵向支架3,纵向支架3沿桥向延伸,且纵向支架3的支撑面位于公路4上方,在纵向支架3一侧搭建横向支架6,横向支架6的支撑面与纵向支架3的支撑面衔接。S2: Bracket erection: Build a
其中,纵向支架3和横向支架6均是在由φ800mm、φ630mm钢管立柱11上搭设分配梁,分配梁上安装贝雷架组成,方分配梁与贝雷梁共同形成支架的支撑面。利用钢管立柱11间横向联接系共同构成一个稳定的支架系统。钢管立柱11及其柱帽在钢结构加工场地制造好,由安装于主塔1位置处的两台塔吊进行安装,调整好立柱11垂直度后底部与基础预埋件加加劲肋焊接。连接系与抱箍在钢管立柱11安装的同时进行安装,以形成稳定结构。Wherein, the
S3: 钢混结合段2施工:在纵向支架3上完成主塔1两侧的钢混结合段2施工,钢混结合段2的具体施工步骤如下:S3: Construction of steel-concrete joint section 2: Complete the construction of steel-concrete
S3.1:纵向支架3上安装胎架,然后在胎架上进行钢箱梁拼装,钢箱梁拼焊完成后拆除胎架,并用分配梁将钢箱梁支撑在纵向支架3上;S3.1: Install the tire frame on the
S3.2:绑扎钢筋、浇筑钢混结合段2底板混凝土;S3.2: Binding steel bars and pouring concrete for the bottom slab of steel-concrete
S3.3:底板混凝土达到设计强度后,在钢箱梁顶面安装对拉结构,并对每根对拉钢筋施加预拉力,使钢混结合段2与主塔1下横梁形成固结;S3.3: After the bottom slab concrete reaches the design strength, install the anti-tension structure on the top surface of the steel box girder, and apply pre-tension force to each anti-tension steel bar, so that the steel-concrete
S3.4:在钢混结合段2内立内模,浇筑腹板和顶板混凝土。S3.4: Set up the inner formwork in the steel-concrete
其中,为了减少钢混结合段2支架承重和变形,混凝土的浇筑分两次进行,第一次将钢混结合段2钢箱梁底板进行浇筑,浇筑方量为129.6m³;第二次将腹板和顶板进行浇筑,浇筑方量为127.7m³。第一次浇筑前,先将支撑点进行预抬,预抬值根据预压实测数据而定,同时在支撑点处对钢箱梁底板、隔板进行加劲处理。第二浇筑前,在开好孔的顶板安装完毕后进行。将钢箱梁顶板与下横梁顶部端口预埋件通过槽钢进行连接形成临时锚固,以减轻第一次混凝土所承受的荷载,减小支架变形,防止浇筑时造成第一次混凝土与下横梁的接触面产生过大的拉应力而开裂。Among them, in order to reduce the load-bearing and deformation of the steel-concrete
S4:提升站5施工:在横向支架6处搭建提升站5,提升站5用于将组合模块提升至横向支架6上。提升站5主体结构为钢管组成的框架结构,其中包括两列支撑架51,支撑架51作为支撑部,另外主梁及起吊横梁均采用贝雷梁。起吊设备主要有2台8t卷扬机及两台80t天车,卷扬机采用Φ25mm钢丝绳,滑轮采用五门,钢丝绳走十。该提升站5位置在外侧主塔1柱靠大里程一角,与支架主梁平行布置。S4: Construction of the lifting station 5: the lifting
其中,横向支架6位于两列支撑架51之间,且所述横向支架6支撑面两侧分别竖向滑动连接于两列支撑架51内侧,支撑架51不仅对提升站5起到支撑作用,同时对横向支架6起到限位和导向作用,有利于横向支架6的稳定升降。在主梁上安装有用于驱使横向支架6升降的提升装置52,提升装置52具体为卷扬机。Wherein, the
S5:起始段10施工:参照图2和图3,起始段10施工的目的是为拼装龙门吊13和架桥提供平台。S5: Construction of the initial section 10: Referring to Fig. 2 and Fig. 3, the purpose of the construction of the
利用提升站5将组焊模块71逐一提升至横向支架6,并进行拼装焊接成钢箱梁标准节段7,并将标准节段7横移至纵向支架3支撑面,然后纵移至纵向支架3远离主塔1的一端位置处,按照以上步骤完成若干个标准节段7的组装和转移,然后在纵向支架3上将钢混结合段2以及多个标准节段7拼装焊接成整体,以完成主塔1一侧的起始段10施工。Use the lifting
S6:横向支架6提升:将横向支架6的支撑面升高至与起始段10上表面齐平并进行衔接;S6: Lifting of the transverse support 6: raising the support surface of the
S7:安装龙门吊13和架桥机12:参照图4,在起始段10上表面安装龙门吊13和架桥机12,龙门吊13和架桥机12可沿桥向移动。S7: Install the
S8:后喂梁施工:参照图4和图5,利用提升站5将组焊模块71逐一提升至横向支架6的支撑面上,并进行拼装焊接成钢箱梁标准节段7,然后将三块组焊模块71横移至起始段10上表面以及纵移至龙门吊13下方,并通过龙门吊13调整三块组合模块的位置,然后将三块组合模块拼装成标准节段7,接着将标准节段7纵移至架桥机12下方。S8: Rear feeding beam construction: Referring to Figure 4 and Figure 5, use the lifting
在高速公路4处搭建移动式防护棚14,移动式防护棚14沿高速公路4方向移动,在标准节段7就位安装过程中,移动式防护棚14移动至标准节段7下方。A mobile protective shed 14 is built at the
架桥机12提梁并纵移,标准节段7纵移到位后,旋转九十度。然后落梁,最后完成标准节段7与钢混结合段2的拼接,以完成第一节钢梁的架设。The
S9:重复所述S8,架桥机12继续前移,完成剩下钢箱梁标准节段7的拼装。S9: repeating the above S8, the
以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。All of the above are preferred embodiments of the application, and are not intended to limit the protection scope of the application. Therefore, all equivalent changes made according to the structure, shape, and principle of the application should be covered by the protection scope of the application. Inside.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211541639.1A CN115961549A (en) | 2022-12-02 | 2022-12-02 | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211541639.1A CN115961549A (en) | 2022-12-02 | 2022-12-02 | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115961549A true CN115961549A (en) | 2023-04-14 |
Family
ID=87352199
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211541639.1A Pending CN115961549A (en) | 2022-12-02 | 2022-12-02 | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115961549A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117328369A (en) * | 2023-11-30 | 2024-01-02 | 北京建工集团有限责任公司 | Mounting method of combined box girder |
| CN117385761A (en) * | 2023-11-24 | 2024-01-12 | 中铁九桥工程有限公司 | A construction method for a cable-stayed bridge spanning a multi-strand railway marshalling station |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102182147A (en) * | 2011-03-31 | 2011-09-14 | 中铁港航局集团第二工程有限公司 | Steel box girder erection method |
| CN207143754U (en) * | 2017-09-07 | 2018-03-27 | 中铁五局集团第二工程有限责任公司 | A kind of across highway adhesion type protection canopy of continuous beam |
| CN108203934A (en) * | 2018-02-02 | 2018-06-26 | 中交二公局第工程有限公司 | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading |
| CN209873572U (en) * | 2018-12-18 | 2019-12-31 | 中铁十五局集团第一工程有限公司 | A temporary navigable lifting station with adjustable vertical lifting height |
| CN111719437A (en) * | 2020-07-22 | 2020-09-29 | 中交二公局第二工程有限公司 | A construction system and method for vertical and horizontal movement of overweight and ultra-wide steel box girder |
| CN214495437U (en) * | 2021-03-03 | 2021-10-26 | 河南省德立信起重机械有限公司 | Lifting mechanism of double-beam bridge crane |
| CN217536681U (en) * | 2022-04-13 | 2022-10-04 | 中交路桥建设有限公司 | Assembling support of large-tonnage steel-concrete combined cross beam of cable-stayed bridge cable tower |
-
2022
- 2022-12-02 CN CN202211541639.1A patent/CN115961549A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102182147A (en) * | 2011-03-31 | 2011-09-14 | 中铁港航局集团第二工程有限公司 | Steel box girder erection method |
| CN207143754U (en) * | 2017-09-07 | 2018-03-27 | 中铁五局集团第二工程有限责任公司 | A kind of across highway adhesion type protection canopy of continuous beam |
| CN108203934A (en) * | 2018-02-02 | 2018-06-26 | 中交二公局第工程有限公司 | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading |
| CN209873572U (en) * | 2018-12-18 | 2019-12-31 | 中铁十五局集团第一工程有限公司 | A temporary navigable lifting station with adjustable vertical lifting height |
| CN111719437A (en) * | 2020-07-22 | 2020-09-29 | 中交二公局第二工程有限公司 | A construction system and method for vertical and horizontal movement of overweight and ultra-wide steel box girder |
| CN214495437U (en) * | 2021-03-03 | 2021-10-26 | 河南省德立信起重机械有限公司 | Lifting mechanism of double-beam bridge crane |
| CN217536681U (en) * | 2022-04-13 | 2022-10-04 | 中交路桥建设有限公司 | Assembling support of large-tonnage steel-concrete combined cross beam of cable-stayed bridge cable tower |
Non-Patent Citations (1)
| Title |
|---|
| 曲江峰: "贵广(南广)铁路跨广州穗盐路斜拉桥主梁施工", 交通科技, no. 263, 30 April 2014 (2014-04-30), pages 48 - 51 * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117385761A (en) * | 2023-11-24 | 2024-01-12 | 中铁九桥工程有限公司 | A construction method for a cable-stayed bridge spanning a multi-strand railway marshalling station |
| CN117328369A (en) * | 2023-11-30 | 2024-01-02 | 北京建工集团有限责任公司 | Mounting method of combined box girder |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US11655600B2 (en) | Method for installing steel tube arches | |
| JP5047680B2 (en) | Construction method of continuous viaduct | |
| CN102154988B (en) | Arch-after-girder construction method of large-span steel box tacked arch bridge | |
| CN111794119B (en) | Temporary supporting system and hoisting method for basket type steel box tie bar arch | |
| CN100441779C (en) | Bridge construction method with prefabricated translation in place in the air | |
| CN114032791A (en) | A construction method for integral jacking of large-span steel truss bridges | |
| CN114263114A (en) | Construction system and construction method of large-section steel box girder | |
| WO2024148715A1 (en) | Method for erecting continuous steel truss bridge | |
| CN115961549A (en) | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge | |
| CN116479781A (en) | A construction method for long-span prefabricated steel-concrete composite beams | |
| CN109778700B (en) | Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road | |
| CN101324054B (en) | Construction Method of Pushing into Place for Temporary Piers of Segmental Beams of Bridges | |
| CN114561875A (en) | Steel box girder jacking and high-position girder falling method | |
| CN116892172B (en) | Method for erecting sections of public rail co-construction multi-span continuous steel truss bridge | |
| CN111648246B (en) | Construction method for building medium and large steel truss girder | |
| CN112211112A (en) | Steel box girder installation method adopting double-guide-girder erection machine on existing bridge | |
| CN207987749U (en) | Ride cable-styled erection crane | |
| CN116145556A (en) | Construction method for ectopic assembly and translational positioning of high-large steel truss girder adjacent to high-speed railway line | |
| CN221142500U (en) | Steel truss girder falling construction tool | |
| CN212895958U (en) | Lower hanging movable bridge floor crane | |
| CN210315235U (en) | Three-face bridge erection machine that can realize vertical and horizontal assembly | |
| CN115748489B (en) | A method for building a new viaduct on an existing bridge | |
| CN118441575A (en) | A bridge erecting machine and construction method thereof | |
| CN219218724U (en) | Main girder hanging and paving integrated machine for combined girder cable-stayed bridge | |
| CN116427278A (en) | Large multi-span self-propelled automatic die carrier |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |
