CN112376440B - Construction process for non-closure hoisting of main beam of cable-stayed bridge - Google Patents

Construction process for non-closure hoisting of main beam of cable-stayed bridge Download PDF

Info

Publication number
CN112376440B
CN112376440B CN202011220872.0A CN202011220872A CN112376440B CN 112376440 B CN112376440 B CN 112376440B CN 202011220872 A CN202011220872 A CN 202011220872A CN 112376440 B CN112376440 B CN 112376440B
Authority
CN
China
Prior art keywords
pier
temporary
area
cable
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011220872.0A
Other languages
Chinese (zh)
Other versions
CN112376440A (en
Inventor
汪来发
刘占国
黄立男
时蓓玲
黎亚舟
刘卫星
李奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Third Harbor Engineering Co Ltd
Original Assignee
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Third Harbor Engineering Co Ltd filed Critical CCCC Third Harbor Engineering Co Ltd
Priority to CN202011220872.0A priority Critical patent/CN112376440B/en
Publication of CN112376440A publication Critical patent/CN112376440A/en
Application granted granted Critical
Publication of CN112376440B publication Critical patent/CN112376440B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction process for non-closure hoisting of a main beam of a cable-stayed bridge, which comprises the following steps: firstly, carrying out cast-in-place construction on a concrete main beam in a guy cable area; assembling a plurality of standard sections in the inhaul cable area in sequence by using the cantilever crane; step three, hoisting the closure section by using a cantilever crane; tensioning three stay cables at the end part at the small mileage side; step five, at least one temporary pier is erected between the side pier and the abutment; hoisting the pier top section to enable the pier top section to be located on the pier top support; step seven, releasing the three stay cables to press the pier top support; step eight, sequentially hoisting the two ropeless area sections by using a cantilever crane; step nine, mounting a temporary sliding support on the top surface of the temporary pier; step ten, hoisting the rest segments of the ropeless area in sequence by using a cantilever crane; and step eleven, sequentially detaching the temporary sliding support and the temporary pier. The construction process can reduce the construction of a large number of temporary facilities, thereby saving a large amount of construction cost.

Description

Construction process for non-closure hoisting of main beam of cable-stayed bridge
Technical Field
The invention relates to a construction process for non-closure hoisting of a main beam of a cable-stayed bridge.
Background
The cable-stayed bridge related to the invention is a single-tower mixed beam double-track railway cable-stayed bridge, and the bridge span is arranged to be 40+210+80+63 m. The large-mileage side of the main tower is a concrete main beam of 80m +63m, and the small-mileage side of the main tower is a steel box beam in a guyed area of 210m and a steel box beam in a ropeless area of 40 m. The steel box girder has a lateral width of 16.5m and a height of 4m, and the standard sections of the steel box girder have a length of 9m and each standard section weighs about 122 tons. The standard segment consists of a tuyere, a side box, a cross beam and a top plate. The ground elevation 3300 m-3470 m at the bridge position has a relative elevation difference of 170m, and the temporary site is difficult to arrange and has poor transportation conditions.
According to the bridge structure and the topographic conditions of bridge positions, the conventional construction process is that an assembling platform is erected on the large-mileage side, steel box girder segments are processed and pre-assembled, transported through a bridge floor, and assembled and constructed by utilizing cantilevers of cantilever cranes. The steel box girder in the ropeless area of the side span is generally assembled on a support, or construction is carried out by adopting technologies such as pushing, sliding and the like, and finally, the construction of the closure section of the main girder is completed by utilizing a cantilever crane (see figure 1).
The above conventional construction method has the following problems:
(1) the topography of the ropeless area is steep, the slope ratio reaches 1:2.4, and large-scale equipment on site is difficult to operate;
(2) the number of the supports is large, the construction difficulty is large, the construction period is long, and the cost is high;
(3) segment assembling and sliding are carried out in the ropeless area, a construction access road must be opened up from a steel beam processing field to a construction site, and large-scale hoisting equipment and steel beam material transportation are guaranteed;
(4) the field assembly welding operation time is long, and the welding quality is uncontrollable;
(5) because the abutment at the side with small mileage is close to the tunnel, the construction organization is greatly influenced by the restriction of tunnel construction.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a construction process for the closure-free hoisting of a main beam of a cable-stayed bridge, which can reduce the construction of a large amount of temporary facilities, thereby saving a large amount of construction cost.
The purpose of the invention is realized as follows: a construction process for the closure-free hoisting of a main beam of a cable-stayed bridge is characterized in that the cable-stayed bridge is a single-tower four-span bridge; the large mileage side of a main tower of the cable-stayed bridge is a cable area concrete main beam, and the small mileage side of the main tower is a section of cable area steel beam and a section of ropeless area steel beam; the steel beam in the inhaul cable area is formed by splicing a plurality of standard sections, and the steel beam in the ropeless area is formed by splicing a folding section, a pier top section and a plurality of ropeless area sections; the construction process comprises the following steps:
step one, erecting an assembly platform at the side of a large mileage, carrying out cast-in-place construction on a concrete main beam in a guy cable area, and completing stay cable connection between the concrete main beam in the guy cable area and a main tower;
step two, carrying out side bridge deck transportation through a large mileage, sequentially carrying out cantilever assembly on a plurality of standard sections of the steel box girder in the cable area by utilizing a cantilever crane, and completing stay cable connection between the steel girder in the cable area and a main tower;
thirdly, after the cantilever crane moves forwards to the side of the small mileage for anchoring, the cantilever crane hoists the closure segment, so that the closure segment is spliced with the last standard segment;
tensioning three stay cables at the end part at the small mileage side of the steel beam in the stay cable area to raise the elevation of the end part at the small mileage side of the steel beam in the stay cable area and reserve an operation space for the top section of the cantilever hoisting pier;
step five, at least one temporary pier is erected between the small-mileage side pier and the small-mileage side abutment; the distance between the temporary piers is the length of two cable-free area sections; a temporary sliding support is not installed on the top surface of the temporary pier temporarily;
step six, firstly installing a pier top support on the side pier with the small mileage, then moving the cantilever crane forward to the side with the small mileage for anchoring, and hoisting the pier top section by the cantilever to enable the pier top section to be located on the pier top support of the side pier with the small mileage and to be spliced with the folding section;
step seven, releasing the three stay cables at the end part at the small mileage side of the steel beam in the stay cable area, pressing the pier top support, and welding the pier top support with a steel plate preset at the bottom of the pier top section;
step eight, after the cantilever crane moves forwards to a small mileage side for anchoring, two cable-free area sections are hoisted in sequence by a cantilever, and at the moment, the distance between the top surface of the temporary pier and the bottom of the second cable-free area section is kept to be 5-10 cm;
after hoisting the cable-free area section on the temporary pier is completed, jacking the cable-free area section on the temporary pier by using a jack, and installing a temporary sliding support on the top surface of the temporary pier; after the temporary sliding support is installed, the jack falls back to enable the elevation of the section of the ropeless area to be lowered and is supported on the temporary sliding support;
step ten, after the cantilever crane moves forwards to the small mileage side for anchoring, sequentially suspending the remaining segments in the ropeless area by using a cantilever until the last segment in the ropeless area is mounted on the abutment at the small mileage side;
and step eleven, jacking a jack on the temporary pier top, removing the temporary sliding support on the temporary pier top, and then removing the temporary pier.
The construction process for the non-closure hoisting of the main beam of the cable-stayed bridge is characterized in that each temporary pier is composed of a pair of unit piers, and each unit pier comprises two pairs of steel pipe upright posts, two transverse distribution beams, two connecting beams, two longitudinal sliding beams, two jacks, two stainless steel plates and two tetrafluoro sliding plates; wherein, two pairs of steel pipe upright columns are arranged side by side in tandem, and each steel pipe upright column is arranged on a steel pipe foundation; firstly drilling a steel pipe foundation into a rock stratum, then pouring concrete, and connecting a steel pipe upright post after the strength of the concrete reaches the designed strength; an inclined strut and a cross strut are arranged between the two pairs of steel pipe upright columns; the two transverse distribution beams are welded and fixed on the top surfaces of the two pairs of steel pipe stand columns in a one-to-one correspondence manner; the two connecting beams are correspondingly connected between the middle parts of the two ends of the two transverse distribution beams one by one; the two longitudinal sliding beams are welded between the top surfaces of the two transverse distribution beams in a one-to-one correspondence manner; two jacks are arranged on the top surface of one transverse distribution beam positioned in the rear row at intervals; the two stainless steel plates are correspondingly welded in the middle of the top surfaces of the two longitudinal sliding beams one by one, the top surface of each stainless steel plate is polished and smeared with silicone grease, and the longitudinal length of each stainless steel plate is L +2 a; the two tetrafluoro sliding plates are arranged on the top surfaces of the two stainless steel plates in a one-to-one correspondence mode, the longitudinal length of each tetrafluoro sliding plate is L, and the tetrafluoro sliding plates are the temporary sliding supports.
According to the construction process for the closure-free hoisting of the main beam of the cable-stayed bridge, the transverse distribution beam and the longitudinal sliding beam are made of double-spliced I-shaped steel; the connecting beam is made of I-shaped steel.
According to the construction process for the closure-free hoisting of the main beam of the cable-stayed bridge, the diameter of the steel pipe foundation is larger than that of the steel pipe upright post; and the depth of the steel pipe foundation drilled into the rock stratum is calculated according to the geological conditions and the structural stress.
The construction method for the closure-free hoisting of the main beam of the cable-stayed bridge has the following characteristics:
(1) only a small number of temporary buttresses are erected, the hoisting construction of all steel box girders can be completed by adopting the cantilever crane, and the construction of a large number of temporary facilities can be reduced, so that a large amount of construction cost is saved;
(2) all the prefabrication and installation work of the steel box girders is finished on one side of the bridge, the bridge and other engineering construction are crossed and mutually influenced, and the construction period is saved;
(3) the whole bridge is not folded and hoisted, the assembly site of the existing steel box girder can be fully utilized, and the steel box girder is prefabricated and assembled in the whole section, so that the construction quality of the steel box girder construction site can be ensured;
(4) the construction process is simulated by using finite element software, and the assembling precision of the steel box girder can be ensured by combining field monitoring.
Drawings
FIG. 1 is a forward bridge drawing of a state of a steel box girder in a cable-free area of a cable-stayed bridge constructed by adopting the prior art;
FIG. 2 is a forward bridge diagram of the construction method of the present invention in a state in which step three is performed;
FIG. 3 is a forward bridge diagram of the construction method of the present invention in the state of performing step four;
FIG. 4 is a forward bridge diagram of the construction method of the present invention in a state in which step five is performed;
FIG. 5 is a cross-sectional view of a main girder of a cable-stayed bridge at a temporary pier according to the construction method of the present invention;
FIG. 6 is an axial sectional view of a steel pipe foundation of a temporary pier employed in the construction method of the present invention;
FIG. 7 is a forward cross-sectional view of a temporary pier used in the construction method of the present invention;
fig. 8 is a cross-sectional view in the bridge direction of a temporary pier used in the construction method of the present invention;
FIG. 9 is a forward bridge view of the construction method of the present invention in a sixth step;
FIG. 10 is a forward bridge view of the construction method of the present invention in a state in which step seven is performed;
FIG. 11 is a forward bridge view of the construction method of the present invention in the eighth step;
FIGS. 12a and 12b are cross-bridge views in a state where the construction method of the present invention is carried out in step nine;
fig. 13 is a forward bridge view of the construction method of the present invention in a state in which step ten is performed.
Detailed Description
The invention will be further explained with reference to the drawings.
Referring to fig. 1 to 13, the construction process for the cable-stayed bridge without folding and hoisting the main beam of the cable-stayed bridge according to the present invention relates to a single-tower four-span bridge; the large mileage side of a main tower 1 of the cable-stayed bridge is a cable area concrete main beam, and the small mileage side of the main tower is a section of cable area steel beam and a section of ropeless area steel beam; the steel beam in the inhaul cable area is formed by splicing a plurality of standard sections, and the steel beam in the ropeless area is formed by splicing a folding section, a pier top section and a plurality of ropeless area sections;
the invention relates to a construction process for non-closure hoisting of a main beam of a cable-stayed bridge, which comprises the following steps:
step one, a splicing platform is erected on the side of a large mileage to carry out cast-in-place construction of a concrete main beam in a guy cable area, and the connection of a stay cable 20 between the concrete main beam in the guy cable area and a main tower 10 is completed;
secondly, carrying out side bridge deck transportation through a large mileage, sequentially carrying out cantilever assembly on a plurality of standard sections of the steel box girder in the guy area by utilizing a cantilever crane 30, and completing the connection of the steel girder in the guy area and a stay cable 20 between the main tower 10;
step three, after the cantilever crane 30 moves forwards to the small mileage side for anchoring, the cantilever hoists the closure segment, so that the closure segment is spliced with the last standard segment;
tensioning the three stay cables 20 at the end part at the small mileage side of the steel beam in the stay cable area to raise the elevation of the end part at the small mileage side of the steel beam in the stay cable area and reserve an operation space for the top section of the cantilever hoisting pier;
step five, at least one temporary pier 60 is erected between the small mileage side pier 40 and the small mileage side abutment 50; the spacing of the temporary piers 60 is the length of two ropeless zone segments; the temporary sliding support is not installed on the top surface of the temporary pier 60 for the time being;
each temporary pier 60 is composed of a pair of unit piers which are correspondingly supported at the bottoms of two side boxes of the section of the ropeless area one by one, and each unit pier comprises two pairs of steel pipe upright posts 61, two transverse distribution beams 62, two connecting beams 63, two longitudinal sliding beams 64, two jacks 65, two stainless steel plates 66 and two tetrafluoro sliding plates 67; the two pairs of steel pipe columns 61 are arranged side by side in tandem, each steel pipe column 61 is arranged on one steel pipe foundation 61A, the steel pipe foundations 61A are drilled into a rock stratum firstly, concrete is poured, and the steel pipe columns 61 are connected highly after the strength of the concrete reaches the designed strength; the diameter D and the drilling depth h of the steel pipe foundation 61A are calculated according to geological conditions and structural stress, the steel pipe column 61 of the embodiment adopts a steel pipe with the diameter of 630 multiplied by 10mm, the diameter D of the steel pipe foundation 61A is 1000mm, and the drilling depth h of the steel pipe foundation 61A is 3000 mm; an inclined strut and a cross strut are arranged between the two pairs of steel tube upright posts 61; the two transverse distribution beams 62 are welded and fixed on the top surfaces of the two pairs of steel tube upright posts 61 in a one-to-one correspondence manner, and each transverse distribution beam 62 is made of double-spliced 45a I-shaped steel; the two connecting beams 63 are correspondingly connected between the middle parts of the two ends of the two transverse distribution beams 62 one by one, and the connecting beams 63 are made of 20a I-shaped steel; the two longitudinal sliding beams 64 are welded between the top surfaces of the two transverse distribution beams 62 in a one-to-one correspondence manner, and each longitudinal sliding beam 64 adopts double-spliced 45a I-shaped steel; two jacks 65 are arranged on the top surface of one transverse distribution beam 62 positioned in the rear row at intervals, and the rated jacking force of the single jack 65 is not less than the self weight of the two ropeless area sections; the two stainless steel plates 66 are correspondingly welded in the middle of the top surfaces of the two longitudinal sliding beams 64 one by one, the top surface of each stainless steel plate 66 is polished and smeared with silicone grease, and the longitudinal length of each stainless steel plate 66 is L +2 a; the two tetrafluoro sliding plates 67 are correspondingly arranged on the top surfaces of the two stainless steel plates 66 one by one, the longitudinal length of each tetrafluoro sliding plate 67 is L, and each tetrafluoro sliding plate 67 is a temporary sliding support; a is the sliding range of the tetrafluoro slide plate 67 on the stainless steel plate 66, and the specific value of a is calculated according to the environmental temperature difference during construction;
step six, firstly installing the top of the small-mileage side pier 40, sequentially installing a support base cushion 40a and a pier top support base 40b, then moving the cantilever crane 30 forward to the small-mileage side for anchoring, and then hanging the pier top section by using a cantilever to ensure that the pier top section is located on the pier top support base 40b of the small-mileage side pier 40 and is spliced with the folding section;
step seven, releasing the three stay cables 20 at the end part at the small mileage side of the steel beam in the stay cable area, pressing the pier top support 40b, and welding the pier top support 40b with a steel plate preset at the bottom of the pier top section;
step eight, after the cantilever crane 30 moves forwards to a small mileage side for anchoring, two ropeless area sections are sequentially hoisted by the cantilever, and at the moment, the distance between the top surface of the temporary pier 60 and the bottom of the second ropeless area section is kept to be 5-10 cm, so that the posture of the ropeless area section is conveniently adjusted, and the ropeless area section is ensured to be accurately positioned;
step nine, after hoisting the section of the ropeless area on the top of the temporary pier 60 is finished, using a jack 65 to jack the section of the ropeless area on the temporary pier 60, installing a temporary sliding support (a tetrafluoro sliding plate 67) on the top surface of the temporary pier 60, and after the temporary sliding support is installed, falling back the jack 65 to enable the elevation of the section of the ropeless area to be lowered and to be supported on the temporary sliding support; the height difference between the longitudinal sliding beams on a pair of unit piers supporting the same section in the ropeless area and the beam bottom should be equal, and the inequality can be leveled through the support cushion steel plate, so that the temporary sliding support is ensured to be stressed uniformly;
step ten, after the cantilever crane 30 moves forwards to the small mileage side for anchoring, sequentially suspending the remaining segments in the ropeless area by using the cantilever until the last segment in the ropeless area is mounted on the small mileage side bridge abutment 50;
eleven, jacking a jack 65 on the top of the temporary pier 60, removing a temporary sliding support on the top of the temporary pier 60, removing the temporary pier 60, and finally adjusting the cable force of all the stay cables 20.
The above embodiments are provided only for illustrating the present invention and not for limiting the present invention, and those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention, and therefore all equivalent technical solutions should also fall within the scope of the present invention, and should be defined by the claims.

Claims (1)

1. A construction process for the closure-free hoisting of a main beam of a cable-stayed bridge is characterized in that the cable-stayed bridge is a single-tower four-span bridge; the large mileage side of a main tower of the cable-stayed bridge is a cable area concrete main beam, and the small mileage side of the main tower is a section of cable area steel beam and a section of ropeless area steel beam; the steel beam in the inhaul cable area is formed by splicing a plurality of standard sections, and the steel beam in the ropeless area is formed by splicing a folding section, a pier top section and a plurality of ropeless area sections; the construction process is characterized by comprising the following steps:
step one, erecting an assembly platform at the side of a large mileage, carrying out cast-in-place construction on a concrete main beam in a guy cable area, and completing stay cable connection between the concrete main beam in the guy cable area and a main tower;
secondly, carrying out side bridge deck transportation through a large mileage, sequentially assembling the cantilevers of a plurality of standard sections of the steel beams in the stay cable area by using a cantilever crane, and completing stay cable connection between the steel beams in the stay cable area and the main tower;
thirdly, after the cantilever crane moves forwards to the side of the small mileage for anchoring, the cantilever crane hoists the closure segment, so that the closure segment is spliced with the last standard segment;
tensioning three stay cables at the end part at the small mileage side of the steel beam in the stay cable area to raise the elevation of the end part at the small mileage side of the steel beam in the stay cable area and reserve an operation space for the top section of the cantilever hoisting pier;
step five, at least one temporary pier is erected between the small-mileage side pier and the small-mileage side abutment; the distance between the temporary piers is the length of two cable-free area sections; a temporary sliding support is not installed on the top surface of the temporary pier temporarily;
each temporary pier consists of a pair of unit piers, and each unit pier comprises two pairs of steel pipe upright posts, two transverse distribution beams, two connecting beams, two longitudinal sliding beams, two jacks, two stainless steel plates and two tetrafluoro sliding plates; wherein, two pairs of steel pipe upright columns are arranged side by side in tandem, and each steel pipe upright column is arranged on a steel pipe foundation; firstly drilling a steel pipe foundation into a rock stratum, then pouring concrete, and connecting a steel pipe upright post after the strength of the concrete reaches the designed strength; the diameter of the steel tube foundation is larger than that of the steel tube upright post; the depth of the steel pipe foundation drilled into the rock stratum is calculated according to the geological conditions and structural stress; an inclined strut and a cross strut are arranged between the two pairs of steel pipe upright columns; two transverse distribution beams are welded and fixed on the top surfaces of the two pairs of steel pipe stand columns in a one-to-one correspondence manner, and each transverse distribution beam adopts double-spliced I-shaped steel; the two connecting beams are correspondingly connected between the middle parts of two ends of the two transverse distribution beams one by one, and each connecting beam is made of I-shaped steel; the two longitudinal sliding beams are welded between the top surfaces of the two transverse distribution beams in a one-to-one correspondence manner, and each longitudinal sliding beam adopts double-spliced I-shaped steel; two jacks are arranged on the top surface of one transverse distribution beam positioned in the rear row at intervals; the two stainless steel plates are correspondingly welded in the middle of the top surfaces of the two longitudinal sliding beams one by one, the top surface of each stainless steel plate is polished and smeared with silicone grease, and the longitudinal length of each stainless steel plate is L +2 a; wherein L is the longitudinal length of each tetrafluoro slide plate, and a is the sliding range of the tetrafluoro slide plate on the stainless steel plate; the two tetrafluoro sliding plates are correspondingly arranged on the top surfaces of the two stainless steel plates one by one, and the tetrafluoro sliding plates are the temporary sliding supports;
step six, firstly installing a pier top support on the side pier with the small mileage, then moving the cantilever crane forward to the side with the small mileage for anchoring, and hoisting the pier top section by the cantilever to enable the pier top section to be located on the pier top support of the side pier with the small mileage and to be spliced with the folding section;
step seven, releasing the three stay cables at the end part at the small mileage side of the steel beam in the stay cable area, pressing the pier top support, and welding the pier top support with a steel plate preset at the bottom of the pier top section;
step eight, after the cantilever crane moves forwards to a small mileage side for anchoring, two cable-free area sections are hoisted in sequence by a cantilever, and at the moment, the distance between the top surface of the temporary pier and the bottom of the second cable-free area section is kept to be 5-10 cm;
after the suspension arm hoisting of the cable-free area section on the temporary pier is finished, the cable-free area section is jacked up on the temporary pier by using a jack, and a temporary sliding support is installed on the top surface of the temporary pier; after the temporary sliding support is installed, the jack falls back to enable the elevation of the section of the ropeless area to be lowered and is supported on the temporary sliding support;
step ten, after the cantilever crane moves forwards to the small mileage side for anchoring, sequentially suspending the remaining segments in the ropeless area by using a cantilever until the last segment in the ropeless area is mounted on the abutment at the small mileage side;
and step eleven, jacking a jack on the temporary pier top, removing the temporary sliding support on the temporary pier top, and then removing the temporary pier.
CN202011220872.0A 2020-11-05 2020-11-05 Construction process for non-closure hoisting of main beam of cable-stayed bridge Active CN112376440B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011220872.0A CN112376440B (en) 2020-11-05 2020-11-05 Construction process for non-closure hoisting of main beam of cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011220872.0A CN112376440B (en) 2020-11-05 2020-11-05 Construction process for non-closure hoisting of main beam of cable-stayed bridge

Publications (2)

Publication Number Publication Date
CN112376440A CN112376440A (en) 2021-02-19
CN112376440B true CN112376440B (en) 2022-06-03

Family

ID=74578095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011220872.0A Active CN112376440B (en) 2020-11-05 2020-11-05 Construction process for non-closure hoisting of main beam of cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN112376440B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114525727A (en) * 2022-03-03 2022-05-24 长沙理工大学 Temporary pier locking device for steel box girder cable-stayed bridge and construction method
CN117735395B (en) * 2024-02-06 2024-04-16 中交第一航务工程局有限公司 Lifting support structure for lifting large-scale track type gantry crane and mounting method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121234A (en) * 2011-04-23 2011-07-13 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN110042769A (en) * 2019-06-03 2019-07-23 四川公路桥梁建设集团有限公司 Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090126957A (en) * 2008-06-05 2009-12-09 주식회사 후레씨네코리아 Pre-loading apparatus for upper structure unit of a bridge and bending method of upper structure unit using thereof
CN101424072B (en) * 2008-11-18 2011-01-19 中铁一局集团有限公司 Counter weight control construction method for large span un-symmetric segment stayed-cable bridge
CN102286935A (en) * 2011-06-01 2011-12-21 中铁大桥勘测设计院有限公司 Brand-new construction method of cable-stayed bridge with hybrid composite beams
CN103215897B (en) * 2013-03-26 2015-03-25 天津市市政工程研究院 Closure construction method of cable-stayed bridge
CN103741601B (en) * 2013-06-28 2017-02-01 中交第三航务工程局有限公司 Tower, beam and cable synchronous bridge forming technology
CN106522112B (en) * 2016-12-30 2019-05-14 中交路桥华南工程有限公司 Cable-stayed bridge end bay beam section construction system and its method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121234A (en) * 2011-04-23 2011-07-13 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN110042769A (en) * 2019-06-03 2019-07-23 四川公路桥梁建设集团有限公司 Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge

Also Published As

Publication number Publication date
CN112376440A (en) 2021-02-19

Similar Documents

Publication Publication Date Title
CN109868750B (en) Four-point supporting pushing system and pushing method for simply supported steel truss girder
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN113846563B (en) Construction method for side span and auxiliary span steel truss girder erection of large-span cable-stayed bridge
CN112376440B (en) Construction process for non-closure hoisting of main beam of cable-stayed bridge
CN111139749A (en) Large-span bearing type continuous steel truss girder cantilever erection construction method
CN111335187A (en) Construction process for triangular area of open-web rigid frame bridge
CN113123238B (en) Transverse moving erection method for wide-section steel truss girder
CN112726411B (en) Integral dragging construction method for single-hole large cantilever steel truss girder
CN111676835A (en) Cable-stayed bridge steel box girder pushing construction method
CN216640288U (en) Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN111576227A (en) Construction method of main arch and auxiliary arch of double-flying-wing arch bridge and lifting appliance used by same
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
CN216040719U (en) Template support cantilever bearing structure
CN215629392U (en) Wide equipment is pieced together to prefabricated case roof beam
CN112609578B (en) Method for mounting steel truss girder at top section of bridge pier of cable-stayed bridge
CN111335188B (en) Hanging beam for prefabricating No. 1 box beam with small curvature radius and hanging and splicing cast-in-situ No. 0 box beam
CN110593117B (en) Steel box girder installation system and construction method thereof
CN211171637U (en) Steel box girder installation system
CN210262748U (en) Cantilever supporting structure for steel box girder pushing construction
CN209873587U (en) Simply supported steel truss four-point supporting and pushing system
CN112359729A (en) Subway-striding walking type pushing construction method for single-hole large-span steel box girder
CN215800924U (en) High-altitude in-situ cast-in-situ bridge
CN216512506U (en) Gantry crane system
CN220150100U (en) Truss type double-column two-side cantilever type bent cap support
CN116641321A (en) Supporting and protecting method for existing viaduct pier stud close to deep foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant