JPH01187286A - Method and machine for shield construction - Google Patents

Method and machine for shield construction

Info

Publication number
JPH01187286A
JPH01187286A JP763488A JP763488A JPH01187286A JP H01187286 A JPH01187286 A JP H01187286A JP 763488 A JP763488 A JP 763488A JP 763488 A JP763488 A JP 763488A JP H01187286 A JPH01187286 A JP H01187286A
Authority
JP
Japan
Prior art keywords
shield
rotary cutter
pilot
excavator
target position
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP763488A
Other languages
Japanese (ja)
Other versions
JPH0574674B2 (en
Inventor
Tomoyuki Doi
土井 倶之
Hitoshi Takahashi
均 高橋
Fumiya Takano
高野 文哉
Minoru Shiosaki
汐崎 実
Kiyoshi Tsuchiya
清 土屋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Construction Machinery Co Ltd
Maeda Corp
Original Assignee
Hitachi Construction Machinery Co Ltd
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Construction Machinery Co Ltd, Maeda Corp filed Critical Hitachi Construction Machinery Co Ltd
Priority to JP763488A priority Critical patent/JPH01187286A/en
Publication of JPH01187286A publication Critical patent/JPH01187286A/en
Publication of JPH0574674B2 publication Critical patent/JPH0574674B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE:To raise the arriving exactness to a target position by a method in which a pilot shield pit is constructed between a rotary cutter type shield excavator moving under the ground end the arrival target position, and the excavation direction is controlled by utilizing the pilot shield pit. CONSTITUTION:A pilot shield pit 2 is constructed through the ground between a rotary cutter type shield excavator 1A moving under the ground and an arrival target position 1A'. The present position of the excavator 1A in relation to the position 1A' is measured by using the pit 2 repeatedly. On the basis of the results obtained, the excavating direction is controlled consecutively to advance the excavator 1A.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、シールド工事において、掘進中のシールド掘
進機を到達目標位置に正確に到達させるためのシールド
工法およびそれに使用するシールド掘進機に関するもの
である。
[Detailed Description of the Invention] (Industrial Application Field) The present invention relates to a shield construction method for allowing a shield excavator to accurately reach a target position during shield construction, and a shield excavator used therein. It is.

〔従来の技術〕[Conventional technology]

近年、シールド工事において、都市部の交通量の増加等
の事情から立坑の設置を減らし、向い合って掘進する2
台のシールド掘進機を地中で接合する地中ドツキングを
行う場合が増えてきた。また、都市部以外でも、トンネ
ル区間の中間地点に立坑を設置できない海底下トンネル
等においては、シールド掘進機同士の地中ドツキングが
不可欠である。
In recent years, in shield construction, due to circumstances such as increased traffic in urban areas, the number of vertical shafts installed has been reduced and the number of shafts dug facing each other has been reduced.
There has been an increase in the number of cases in which underground docking is performed, in which a shield tunneling machine is joined underground. In addition, even outside of urban areas, underground docking between shield tunneling machines is essential for underground tunnels where it is not possible to install a vertical shaft at the midpoint of the tunnel section.

第2図〜第5図は地中ドツキングの説明図で、図中、接
合すべき2台のシールド掘進機をIA。
Figures 2 to 5 are explanatory diagrams of underground docking, and in the diagram, two shield tunneling machines to be joined are shown as IA.

IBとする。IB.

第2図はドツキング前のシールド位置を示し、第3図は
地中ドツキング時のシールド位置を示す。
Figure 2 shows the shield position before docking, and Figure 3 shows the shield position during underground docking.

第3図のように良好な地中ドツキングを行うための条件
は、地中接合部でシールド掘進機IA、IBの各々の掘
進機の中心位置が一致することと、各々の掘進機の傾き
が一致することである。
The conditions for good underground docking as shown in Figure 3 are that the center positions of the shield tunneling machines IA and IB match at the underground joint, and that the inclination of each tunneling machine is the same. It is about being in agreement.

第4図は掘進機の中心位置がずれた場合、第5図は掘進
機の傾きがずれた場合を示し、各々地中接合部で路線に
段差、急カーブが生じることになる。このような段差や
象、カーブは、地中接合部での止水を困難にし、工期を
長引かせる原因になるので、極力回避しなければならな
い。したがって、掘進中に各々のシールド掘進機の位置
および傾きを正確に把握しておき、地中接合部で各々の
シールド掘進機の中心位置と傾きを一致させるようにシ
ールド掘進機の掘進方向を制御することが重要となる。
Fig. 4 shows a case where the center position of the excavator is shifted, and Fig. 5 shows a case where the inclination of the excavator is shifted, resulting in steps and sharp curves in the route at the underground joints. Such steps, elevations, and curves must be avoided as much as possible, as they make it difficult to stop water at underground joints and prolong the construction period. Therefore, during excavation, the position and inclination of each shield excavator should be accurately grasped, and the direction of excavation of each shield excavator should be controlled so that the center position and inclination of each shield excavator match at the underground joint. It is important to do so.

地中ドツキングを行う場合、各々のシールド掘進機の位
置と傾きは、一般に次のようにして測量されている。
When performing underground docking, the position and inclination of each shield excavator is generally measured as follows.

(1)  地表面に基準点を一つ設定する。(1) Set one reference point on the ground surface.

(2)上記基準点よりトランシット等による測量を行い
、各々の発進立坑内に基準点を移設する。
(2) A survey will be carried out from the above reference point using a transit vehicle, etc., and the reference point will be relocated within each starting shaft.

地表面の基準点と立坑との間に建築物等が存在すれば、
当然基準点の移設回数は増加する。
If there is a building etc. between the reference point on the ground surface and the shaft,
Naturally, the number of times the reference point is relocated increases.

(3)同様な方法により、掘進に伴ってトンネル坑内の
前方に順次基準点を移設してゆく。移設の回数は、測量
機器の性能と精度の関係で、トンネルが長くなるほど、
多くなる。また、トンネルに曲線部があり、直線で測量
できない場合も基準点を移設してゆかなければならない
(3) Using the same method, reference points are sequentially relocated to the front of the tunnel as the tunnel progresses. The number of relocations depends on the performance and accuracy of the surveying equipment, and the longer the tunnel, the more
There will be more. Additionally, if the tunnel has curved sections and it is not possible to survey in a straight line, the reference point must be relocated.

(4)そして、トンネル先端に最も近い基準点よりシー
ルド掘進機内の1つ以上の点を測量し、それを基にシー
ルド掘進機の形状等からカッタの先端位置とシールド掘
進機の傾きとを求める。
(4) Then, measure one or more points inside the shield tunneling machine from the reference point closest to the tunnel tip, and based on that, determine the cutter tip position and the inclination of the shield tunneling machine from the shape of the shield tunneling machine, etc. .

(5)同じ坑内基準点より各セグメントの位置および傾
きを測量し、その結果から掘進路線の方向を求める。
(5) Measure the position and inclination of each segment from the same underground reference point, and determine the direction of the excavation line from the results.

以上が一般に採用されている測量方法であり、その測量
結果に基づいて掘進方向の制御を行っていた。
The above is a commonly used surveying method, and the direction of excavation is controlled based on the survey results.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上記従来技術では、下記の誤差原因により、当初の基準
点位置から離れれば離れるほど、各シールド掘進機の位
置に関する誤差は大きくなる。また、基準点の移設回数
が多くなるほど、誤差は太き(なる。
In the above-mentioned conventional technology, the error regarding the position of each shield tunneling machine increases as it moves away from the initial reference point position due to the following error causes. Furthermore, the larger the number of times the reference point is relocated, the larger the error becomes.

誤差原因は次の諸要素からなる。The causes of error consist of the following elements.

(1)測量機器の精度 (2)測量技術の良否 (3)  シールド掘進機姿勢管理技術の良否(4)セ
グメント組立の良否 (5)裏込め施工の良否(裏込め注入量の過不足がある
と、セグメントが動いてしまう)。
(1) Accuracy of surveying equipment (2) Quality of surveying technology (3) Quality of shield tunneling machine attitude control technology (4) Quality of segment assembly (5) Quality of backfilling work (excessive or insufficient amount of backfill injection) (The segment will move).

(6)坑内測点の保持の良否 (7)地盤の振動による読取り誤差 以上の諸要素から、現在の測量技術を駆使しても、たと
えば掘進長2km程度で±50mm程度の誤差が出る可
能性が大きい。このため、2台のシールド掘進機を地中
ドツキングさせる場合、既述の測量結果より各々のシー
ルド掘進機の中心位置および傾きが完全に一致するもの
として地中ドツキングしでも、この誤差分だけずれてし
まい、第4図。
(6) Whether or not underground survey points are properly maintained (7) Reading errors due to ground vibrations and other factors, even if current surveying technology is used, there is a possibility that an error of about ±50 mm will occur for an excavation length of about 2 km, for example. is large. Therefore, when docking two shield tunneling machines underground, even if it is assumed that the center position and inclination of each shield tunneling machine match perfectly according to the survey results described above, there will be a deviation by this error. Figure 4.

第5図の複合した状態でずれが生じてしまうことになる
Misalignment will occur in the combined state shown in FIG.

したがって、長い距離を掘進してきたシールド掘進機と
シールド掘進機を良好に地中ドツキングさせるためには
、事前に相手機との相対的なずれを把握し、ドツキング
地点での各々のシールド掘進機の中心位置および傾きの
ずれをなくすようにシールド掘進機を掘進制御すること
が必要となる。
Therefore, in order to successfully dock a shield tunneling machine that has dug a long distance underground, it is necessary to understand the relative deviation with the other machine in advance, and to check the position of each shield tunneling machine at the docking point. It is necessary to control the excavation of the shield excavator so as to eliminate deviations in the center position and inclination.

シールド掘進機同士の地中ドツキングのほか、掘進中の
シールド機を既設トンネル、立坑等の地中構造物と接合
する場合においても同様なことが言える。
In addition to underground docking between shield tunneling machines, the same can be said when connecting a shield machine that is currently digging to an underground structure such as an existing tunnel or shaft.

本発明の目的は、上記の課題を解決し、掘進中のシール
ド掘進機を到達目標位置に正確に到達させる手段を提供
することにある。
An object of the present invention is to provide a means for solving the above-mentioned problems and allowing a shield excavator that is excavating to accurately reach a target position.

〔課題を解決するための手段〕[Means to solve the problem]

上記目的は、請求項1から13までに記載した発明によ
って達成される。
The above object is achieved by the invention described in claims 1 to 13.

請求項1記載の発明は、到達目標位置に向って地中を掘
進中の回転カッタ式シールド掘進機と前記到達目標位置
側との間に地中を貫通するパイロットシールド坑を構築
し、このパイロットシールド坑を介して前記到達目標位
置に対する前記回転カッタ式シールド掘進機の現在位置
を測量することを特徴とするシールド工法であり、請求
項2記載の発明は、請求項1記載のシールド工法におい
て、前記パイロットシールド坑が前記回転カッタ式シー
ルド掘進機の回転カッタ中心部を通して構築されること
を特徴とする 請求項3記載の発明は、到達目標位置に向って地中を掘
進中の回転カッタ式シールド掘進機と前記到達目標位置
側との間に地中を貫通するパイロットシールド坑を構築
し、前記回転カッタ式シールド掘進機の後方のトンネル
内に基準点を設置し、前記パイロットシールド坑を介し
て前記到達目標位置に対する前記基準点の位置を測量す
ることを特徴とするシールド工法であり、請求項4記載
の発明は、請求項3記載のシールド工法において、前記
パイロットシールド坑が前記回転カッタ式シ−ルド掘進
機の回転カッタ中心部を通して構築されることを特徴と
する 請求項5記載の発明は、請求項1または2記載の方法に
よる測量結果に基づき、掘進方向の制御を行いながら回
転カッタ式シールド掘進機を掘進させ、到達目標位置に
到達させることを特徴とするシールド工法であり、請求
項6記載の発明は、請求項3または4記載の方法による
測量結果に基づき、掘進方向の制御を行いながら回転カ
ッタ式シールド掘進機を掘進させ、到達目標位置に到達
させることを特徴とするシールド工法である。
The invention according to claim 1 constructs a pilot shield shaft penetrating underground between a rotary cutter type shield excavator that is excavating underground toward a target position and the target position side, and A shield construction method is characterized in that the current position of the rotary cutter type shield excavator with respect to the target position is measured through a shield pit, and the invention according to claim 2 is the shield construction method according to claim 1, wherein: The invention as set forth in claim 3 is characterized in that the pilot shield pit is constructed through the center of the rotary cutter of the rotary cutter type shield excavator. A pilot shield shaft penetrating underground is constructed between the tunneling machine and the target position side, a reference point is installed in the tunnel behind the rotary cutter type shield tunneling machine, and a pilot shield shaft is installed through the pilot shield shaft. The shield construction method is characterized in that the position of the reference point with respect to the target position is surveyed. - The invention according to claim 5 is characterized in that the rotary cutter is constructed through the center of the rotary cutter of a rotary excavator, while controlling the excavation direction based on the survey results by the method according to claim 1 or 2. It is a shield construction method characterized by making a shield excavator dig and reach a target position, and the invention according to claim 6 is a shield construction method characterized by making a shield excavator excavate and reach a target position. This is a shield construction method that is characterized by making a rotary cutter type shield excavator excavate and reach a target position while excavating.

請求項7記載の発明は、到達目標位置に向って地中を掘
進中の回転カッタ式シールド掘進機と前記到達目標位置
側との間に前記回転カッタ式シールド掘進機の回転カッ
タ中心部を通して地中を貫通するパイロットシールド坑
を構築し、前記パイロットシールド坑を存置したまま、
前記パイロットシールド坑を介して前記到達目標位置に
対する前記回転カッタ式シールド掘進機の現在位置の測
量を繰り返し行い、それぞれの測量結果に基づいて逐次
掘進方向の制御を行いながら前記回転カッタ式シールド
掘進機を掘進させ、到達目標位置に到達させることを特
徴とするシールド工法であり、請求項8記載の発明は、
到達目標位置に向って地中を掘進中の回転カッタ式シー
ルド掘進機と前記到達目標位置側との間に前記回転カッ
タ式シールド掘進機の回転カッタ中心部を通して地中を
貫通するパイロットシールド坑を構築し、前記回転カッ
タ式シールド掘進機の後方のトンネル内に基準点を設置
し、前記パイロットシールド坑を存置したまま、前記パ
イロットシールド坑を介して前記到達目標位置に対する
前記基準点の位置の測量を繰り返し行い、それぞれの測
量結果に基づいて逐次掘進方向の制御を行いながら前記
回転カッタ式シールド掘進機を掘進させ、到達目標位置
に到達させることを特徴とするシールド工法である。
The invention as set forth in claim 7 provides a structure in which a rotary cutter type shield excavator is provided between the rotary cutter type shield excavator that is excavating underground toward the target position and the target position side through the center of the rotary cutter of the rotary cutter type shield excavator. Construct a pilot shield hole that penetrates the inside, and leave the pilot shield hole in place,
The current position of the rotary cutter type shield excavator is repeatedly surveyed with respect to the target position through the pilot shield hole, and the rotary cutter type shield excavator is controlled while sequentially controlling the excavation direction based on each survey result. A shield construction method is characterized in that the shield construction method is characterized by excavating and reaching a target position, and the invention according to claim 8,
A pilot shield hole is provided between the rotary cutter type shield excavator which is excavating underground toward the target position and the target position side, and penetrates through the ground through the center of the rotary cutter of the rotary cutter type shield excavator. a reference point is installed in the tunnel behind the rotary cutter type shield excavator, and the position of the reference point is surveyed with respect to the target position via the pilot shield pit while leaving the pilot shield pit in place. This shield construction method is characterized in that the above-mentioned rotary cutter type shield excavator is excavated repeatedly, and the rotary cutter type shield excavator is excavated while controlling the excavation direction sequentially based on the respective survey results to reach the target position.

請求項9記載の発明は、回転カッタ式シールド掘進機に
おいて、該機内に回転カッタの中心部を貫通して前方へ
パイロットシールド坑を構築可能なパイロットシールド
掘進機を設けたことを特徴とするシールド掘進機である
The invention according to claim 9 is a rotary cutter type shield excavator, characterized in that a pilot shield excavator is provided in the rotary cutter type shield excavator, which is capable of penetrating the center of the rotary cutter and constructing a pilot shield tunnel forward. It is an excavator.

請求項1O記載の発明は、請求項9記載のシールド掘進
機において、前記パイロットシールド掘進機が掘進方向
の制御可能な掘進機であることを特徴とする請求項11
記載の発明は、同じく前記パイロットシールド掘進機が
余掘り機能を有する掘進機であることを特徴とする 請求項12記載の発明は、回転カッタ式シールド掘進機
において、回転カッタおよびその後方の隔壁の中心部を
貫通してパイロットシールド掘進機を受入可能な筒状構
造部を設け、この筒状構造部の内側に盲ぶたを機内側に
抜き取り可能なように装着したことを特徴とするシール
ド掘進機であり、請求項13記載の発明は、請求項12
記載のシールド掘進機において、前記前ぶたが前端面に
掘削刃を備えてなることを特徴とする。
The invention according to claim 1O is the shield tunneling machine according to claim 9, wherein the pilot shield tunneling machine is an tunneling machine whose excavation direction can be controlled.
The invention as described in claim 12 is characterized in that the pilot shield excavator is an excavator having an over-digging function.The invention as described in claim 12 is characterized in that the pilot shield excavator is an excavator having an over-digging function. A shield tunneling machine, characterized in that a cylindrical structure that penetrates through the center and can receive a pilot shield tunneling machine is provided, and a blind lid is attached to the inside of this cylindrical structure so that it can be pulled out to the inside of the machine. The invention according to claim 13 is defined as claim 12.
The shield tunneling machine described above is characterized in that the front cover is provided with a digging blade on its front end surface.

〔作用〕[Effect]

請求項1記載の発明は、回転カッタ式シールド掘進機と
到達目標位置側との間に構築したパイロットシールド坑
を測量坑として利用することにより、到達目標位置に対
するシールド掘進機の現在位置を正確に測量することを
可能としたものである。また、請求項3記載のように、
シールド掘進機の現在位置に代えて後方のトンネル内に
基準点を設置し、到達目標位置に対する上記基準点の位
置を正確に測量することもできる。
The invention as claimed in claim 1 accurately determines the current position of the shield excavator with respect to the target position by using a pilot shield pit constructed between the rotary cutter type shield excavator and the target position side as a surveying pit. This made it possible to conduct measurements. Moreover, as claimed in claim 3,
Instead of the current position of the shield tunneling machine, a reference point can be installed in the rear tunnel, and the position of the reference point relative to the target position can be accurately measured.

これらの測量結果より到達目標位置に対するシールド掘
進機のずれが分るので、請求項5または6記載のように
、これらの測量結果に基づいて掘進方向の制御を行いな
がらシールド掘進機を掘進させることで、最終的に路線
を修正して到達目標位置に到達させることができ、到達
目標位置に接合すべき相手側のシールド掘進機がある場
合には、両シールド掘進機を良好に地中ドツキングさせ
ることが可能となる。
Since the deviation of the shield excavator with respect to the target position can be determined from these survey results, the shield excavator can be caused to excavate while controlling the excavation direction based on these survey results, as described in claim 5 or 6. In the end, the route can be corrected to reach the target position, and if there is a shield machine on the other side that should be connected to the target position, both shield machines can be properly docked underground. becomes possible.

請求項2または4記載のようにパイロットシールド坑を
シールド掘進機の回転カッタ中心部を通して構築すれば
、測量後の再掘進時にもパイロットシールド坑が回転カ
ッタと干渉しないため、パイロットシールド坑を撤去す
る必要がなく、いつでも測量ができる。
If the pilot shield hole is constructed through the center of the rotary cutter of the shield excavator as described in claim 2 or 4, the pilot shield hole will not interfere with the rotary cutter even when re-excavating after surveying, so the pilot shield hole can be removed. There is no need for it, and you can take measurements at any time.

特に、請求項7記載のように、回転カッタ中心部を通る
パイロットシールド坑を存置したまま、このパイロット
シールド坑を介して到達目標位置に対するシールド掘進
機の現在位置の測量をくり返し行い、それぞれの測量結
果に基づいて逐次掘進方向の制?ff1lを行いながら
シールド掘進機を掘進させた場合は、常に前方を見通し
ながら路線を修正する、いわゆる有視界状態での掘進を
実現でき、到達目標位置への到達の確度はさらに高まる
In particular, as described in claim 7, the pilot shield hole passing through the center of the rotary cutter is left in place, and the current position of the shield excavator relative to the target position is repeatedly surveyed through the pilot shield hole, and each survey is carried out repeatedly. Is the direction of excavation sequentially controlled based on the results? When the shield excavator excavates while performing ff1l, it is possible to perform excavation in a so-called visual state, in which the route is always corrected while looking ahead, and the accuracy of reaching the target position is further increased.

請求項8記載の発明は、シールド掘進機後方のトンネル
内に基準点を設置し、到達目標位置に対する上記基準点
の位置の測量結果に基づいて掘進方向制御を行う場合で
あるが、この場合も同様に回転カンタ中心部を通るパイ
ロットシールド坑を介してくり返し測量を行うことによ
り、掘進中のセグメントの移動による基準点のずれに対
して掘進路線の修正ができ、到達目標位置への到達の確
度を高めることができる。
The invention according to claim 8 is a case in which a reference point is installed in the tunnel behind the shield tunneling machine, and the excavation direction is controlled based on the survey result of the position of the reference point with respect to the target position. Similarly, by conducting repeated surveys through a pilot shield hole that passes through the center of the rotating canter, the excavation route can be corrected to account for deviations in the reference point due to movement of segments during excavation, and the accuracy of reaching the target position can be improved. can be increased.

シールド掘進機の回転カッタ中心部を通るバイロフトシ
ールド坑の構築は、請求項9記載のようにシールド掘進
機の回転カッタ中心部より発進するパイロットシールド
掘進機により行うことができる。このパイロットシール
ド掘進機には、請求項10記載のように掘進方向の制御
可能な掘進機を用い、計画されたパイロットシールド路
線上がらずれないように掘進制御する。また、このパイ
ロットシールド掘進機は、請求項11記載のように後述
する余掘り機能を備えたものとする。
The construction of the viroft shield pit passing through the center of the rotary cutter of the shield tunneling machine can be carried out by a pilot shield tunneling machine launched from the center of the rotary cutter of the shield tunneling machine. As the pilot shield excavator, an excavator whose excavation direction can be controlled is used, and the excavation is controlled so as not to deviate from the planned pilot shield line. Further, this pilot shield excavator is provided with an over-digging function which will be described later.

シールド掘進機同士を地中ドツキングさせる場合、相手
側のシールド掘進機には、請求項12記載のように回転
カッタおよびその後方の隔壁を貫通する筒状構造部を設
け、請求項9記載のシールド掘進機から発進したパイロ
ットシールド掘進機が相手側シールド掘進機に到達した
とき、前記筒状構造部の内側に装着してあった盲ぶたを
機内側に抜き取り、この筒状構造部の内空を通してパイ
ロットシールド掘進機を相手側シールド掘進機内に突入
させることにより、両シールド掘進機の回転カッタ中心
部を貫通してパイロットシールド坑を構築させる。パイ
ロットシールド坑の外周と両シールド掘進機との間には
、両シールド掘進機の掘進路線のずれを見込んだクリア
ランスを設けておき、このクリアランスにより、パイロ
ットシールド坑を存置したまま、両シールド掘進機を近
付は地中トンキングさせる際の路線修正を可能にする。
When the shield tunneling machines are docked underground, the shield tunneling machine on the other side is provided with a cylindrical structure that penetrates the rotary cutter and the partition wall behind the rotary cutter as described in claim 12, and the shield as described in claim 9 When the pilot shield tunneling machine launched from the tunneling machine reaches the other side's shield tunneling machine, the blind cover attached to the inside of the cylindrical structure is pulled out to the inside of the machine and passed through the inside of this cylindrical structure. By thrusting the pilot shield tunneling machine into the other shield tunneling machine, the pilot shield tunnel is constructed by penetrating the center of the rotary cutter of both shield tunneling machines. A clearance is provided between the outer periphery of the pilot shield pit and both shield excavators, allowing for the deviation of the excavation routes of both shield excavators. The approach allows route correction when tunneling underground.

パイロットシールド掘進機の掘進に際し、あらかじめ前
記クリアランス相当分以上の余掘りをしておくことによ
り、シールド掘進機の再掘進時の堀り残しをなくするこ
とができる。また、請求項13記載のように相手側シー
ルド掘進機の筒状構造部に装着される盲ぶたの前端面に
掘削刃を設けておくことにより、通常の掘進も支障なく
行うことができる。
When excavating with the pilot shield excavator, by excavating more than the amount equivalent to the clearance in advance, it is possible to eliminate any remaining excavation when the shield excavator excavates again. Furthermore, by providing an excavation blade on the front end surface of the blind cover attached to the cylindrical structure of the counterpart shield excavator, normal excavation can be performed without any trouble.

〔実施例〕〔Example〕

以下、図面を参照して本発明の実施例を詳細に説明する
Embodiments of the present invention will be described in detail below with reference to the drawings.

第1図は本発明をシールド掘進機同士の地中ドツキング
に適用した場合の概念図である。(a)は2台のシール
ド掘進機IA、IBが地中で向い合った状態で、各々の
シールド掘進機の中心位置および傾きにずれがあること
を示している。(b)は両シールド掘進機IA、IBの
間にシールド掘進機lB側よりパイロットシールド坑2
を構築した状態を示し、このパイロットシールド坑2を
介し′て両機の相対位置を確認した後、シールド掘進機
IAを掘進させ、仮想線IA’で示すように到達目標位
置であるドツキング地点に到達させる。この再掘進はI
A、IBのいずれのシールド掘進機が行ってもよい。
FIG. 1 is a conceptual diagram when the present invention is applied to underground docking between shield tunneling machines. (a) shows that two shield tunneling machines IA and IB face each other underground, and there is a deviation in the center position and inclination of each shield tunneling machine. (b) shows the pilot shield pit 2 between the shield tunneling machines IA and IB from the shield tunneling machine IB side.
After confirming the relative positions of both machines through this pilot shield pit 2, the shield tunneling machine IA is allowed to dig until it reaches the docking point, which is the target position, as shown by the virtual line IA'. let This re-excavation is I
Either A or IB shield excavator may be used.

地中ドツキングのための測量方法および掘進制御方法の
説明に先立ち、それに使用するシールド掘進機の構造と
パイロットシールド坑2の構築の過程について説明する
Prior to explaining the surveying method and excavation control method for underground docking, the structure of the shield excavator used therein and the process of constructing the pilot shield pit 2 will be explained.

第6図は本発明によるパイロットシールド掘進機を装備
した回転カッタ式シールド掘進機の一例を示す。このシ
ールド掘進機は、前面に備えた回転カッタ3と後方の隔
壁4との間に土砂撹拌装置6を有するチャンバ5が形成
され、隔壁4の後方の機内にリングギヤ7aを有するカ
ッタベアリングア、ピニオン8aを有するカンタ駆動モ
ータ8、推進用シールドジヤツキ9、セグメント11を
組立てるエレクタ10等が設置されており、回転カッタ
3の回転により地山を掘削しつつ、セグメント11を反
力受とするシールドジヤツキ9の推進力によって掘進す
る。従来の回転カッタ式シールド掘進機(第16図)に
設けられていた回転カッタ中心部のカンタヘッド3bを
取り除き、カッタボス部3aおよび隔壁ボス部4aの中
心部にパイロットシールド掘進機14が通過できる円形
の穴12.13が開設されており、パイロットシールド
掘進機14は、そのカンタヘッド14aが他山に接する
ように2つの穴12.13を通してシールド掘進機内に
設置されている。隔壁4の後方の機内には推進ジヤツキ
16と受台17を備えた元押し装置15があり、パイロ
ットシールド掘進機14を保持している。隔壁ボス部穴
13の内周には土砂シール1Bを装備し、パイロットシ
ールド掘進機14の外周面をシール面として隔壁4の後
方機内への土砂の侵入を防止しており、通常掘進時には
、カッタボス部穴12により掘削できなくなった回転カ
ッタ中心部の地山掘削をパイロットシールド掘進機14
のカッタヘッド14aにより行う。
FIG. 6 shows an example of a rotary cutter type shield tunneling machine equipped with a pilot shield tunneling machine according to the present invention. This shield excavator has a chamber 5 having an earth and sand stirring device 6 formed between a rotary cutter 3 provided at the front and a rear bulkhead 4, and a cutter bearing a and a pinion having a ring gear 7a inside the machine behind the bulkhead 4. 8a, a propulsion shield jack 9, an erector 10 for assembling the segments 11, etc. are installed, and while excavating the ground by the rotation of the rotary cutter 3, the shield uses the segments 11 as reaction force receivers. It digs using the propulsion force of Jyatsuki 9. The canter head 3b at the center of the rotary cutter, which was provided in the conventional rotary cutter type shield excavator (Fig. 16), was removed, and a circular shape was created in which the pilot shield excavator 14 could pass through the center of the cutter boss 3a and bulkhead boss 4a. Holes 12.13 are opened, and the pilot shield excavator 14 is installed in the shield excavator through the two holes 12.13 so that its canter head 14a is in contact with another mountain. Inside the machine behind the bulkhead 4, there is a main push device 15 equipped with a propulsion jack 16 and a pedestal 17, which holds the pilot shield tunneling machine 14. A dirt seal 1B is installed on the inner circumference of the bulkhead boss hole 13, and the outer circumferential surface of the pilot shield excavator 14 is used as a sealing surface to prevent dirt from entering the rear part of the bulkhead 4. During normal excavation, the cutter boss The pilot shield excavator 14 excavates the ground in the center of the rotary cutter, which cannot be excavated due to the hole 12.
This is done using the cutter head 14a.

第7図はパイロットシールド掘進機14の内部構造の一
例を示す。パイロットシールド掘進機14の内部には、
カッタヘッド14aを回転させるカッタ駆動モータ14
b、方向修正ジヤツキ14c、レーザ受光器等からなる
測量装置14d、掘削土砂を後方へ排土する送泥管14
e等が装備されている。パイロットシールド掘進機14
の後方に接続されたパイプ19の後端は第6図に示すよ
うに推進ジヤツキ16に接しており、パイロットシール
ド掘進機14は推進ジヤツキ16の推進力により掘進し
、推進ジヤツキ16の1ストロークごとに後続のパイプ
19を継ぎ足すことにより、前方の地中にパイロットシ
ールド坑を構築する構成となっている。パイロットシー
ルド掘進機14の掘進方向制御は、元押し装置15側に
備えたレーザ光′a、(図示せず)からのレーザビーム
を測量装置14dで受光して掘進方向のずれを検出し、
複数本の方向修正ジヤツキ14cを選択作動させること
により行う。また、カッタヘッド14aには遠隔操作さ
れる余堀り用カッタ14fを設けて、掘進時に余堀りを
行わせる。
FIG. 7 shows an example of the internal structure of the pilot shield excavator 14. Inside the pilot shield excavator 14,
Cutter drive motor 14 that rotates cutter head 14a
b, a direction correction jack 14c, a surveying device 14d consisting of a laser receiver, etc., a mud feeding pipe 14 for discharging excavated earth and sand backwards;
E etc. are equipped. Pilot shield excavator 14
The rear end of the pipe 19 connected to the rear of the propulsion jack 16 is in contact with the propulsion jack 16 as shown in FIG. By adding a subsequent pipe 19 to the top, a pilot shield pit is constructed underground in front. The excavation direction of the pilot shield excavator 14 is controlled by detecting a deviation in the excavation direction by receiving a laser beam from a laser beam 'a (not shown) provided on the main pushing device 15 side with a surveying device 14d.
This is done by selectively operating a plurality of direction correction jacks 14c. Further, the cutter head 14a is provided with a cutter 14f for over-drilling which is remotely controlled to perform over-drilling during excavation.

第8図はパイロットシールド掘進機14を装備したシー
ルド掘進機20と地中接合する相手側シールド掘進機2
1の構成例を示す。図中、第6図と共通の部分には同一
符号を付し、説明を省略する。
Figure 8 shows a shield excavator 20 equipped with a pilot shield excavator 14 and a counterpart shield excavator 2 connected underground.
An example of configuration 1 is shown below. In the figure, parts common to those in FIG. 6 are denoted by the same reference numerals, and explanations thereof will be omitted.

この相手側シールド掘進機21も第6図に示したシール
ド掘進機20と同様のカッタ構造を有しているが、その
カッタボス部3aと一体になった筒状構造部22が隔壁
ボス部4aの穴13を通り後方の機内に突き抜けている
。筒状構造部22の内空には回転カッタ3と共回りする
ように筒状構造部22の機内側端部にボルト等により結
合された盲ぶた23が装着されており、通常掘進時には
この盲ふた23で機内への土砂の流入を防止し、かつ盲
ぶた23の前端面に設けた掘削刃23aにより回転カッ
タ中心部の地山掘削を行う。隔壁ボス部4aの内周には
土砂シール18を装備し、筒状構造部22の外周面をシ
ール面として機内への土砂の侵入を防止する。また、筒
状構造部22の内周にも土砂シール24を装備し、通常
掘進時は盲ぶた23の外周面をシール面として機内への
土砂の侵入を防止している。
This counterpart shield tunneling machine 21 also has a cutter structure similar to that of the shield tunneling machine 20 shown in FIG. It passes through hole 13 and penetrates into the interior of the aircraft at the rear. A blind cover 23 is attached to the inner side end of the cylindrical structure 22 with bolts or the like, and is attached to the inner space of the cylindrical structure 22 so as to rotate together with the rotary cutter 3. The lid 23 prevents earth and sand from flowing into the machine, and the excavation blade 23a provided on the front end surface of the blind lid 23 excavates the ground at the center of the rotary cutter. A dirt seal 18 is provided on the inner circumference of the bulkhead boss portion 4a, and the outer circumferential surface of the cylindrical structure portion 22 is used as a sealing surface to prevent dirt from entering the machine. Further, an earth and sand seal 24 is also provided on the inner circumference of the cylindrical structure part 22, and during normal excavation, the outer peripheral surface of the blind lid 23 is used as a sealing surface to prevent earth and sand from entering the inside of the machine.

第9図〜第12図はシールド掘進機20と21を地中ド
ツキングさせる場合のパイロットシールド坑の構築過程
を示す。
9 to 12 show the construction process of a pilot shield pit when the shield tunneling machines 20 and 21 are docked underground.

地中ドツキングに先立つ回転カッタ式シールド掘進機の
路線の修正には、通常、シールド径の4〜5倍の距離が
必要といわれている。そこで、第9図に示すように、シ
ールド掘進機20と21が上記所定距離まで近付いた段
階で掘進を停止し、シールド掘進機20内よりパイロッ
トシールド掘進機14を相手側シールド掘進機21の筒
状構造部22の内空を目標に発進させる。第10図はパ
イロットシールド掘進機14の掘進中の状態を示してい
る。盲ぶた23にパイロットシールド掘進機14が接触
したならば、盲ぶた23と筒状構造部22の結合を解き
、第11図に示すように、パイロットシールド掘進機1
4の推進力によりシールド掘進機2工内に抜き取る。盲
ぶた23が完全に抜けた後、シールド掘進機21内まで
突入したパイロットシールド掘進機14を後続パイプ1
9より切り離し、シールド掘進機20と21がパイプ1
9によりつながった状態とする。第12図は、シールド
掘進機20.21の間にパイプ19によりパイロットシ
ールド坑2が構築された状態を示す。その後、パイロッ
トシールド坑2の内部空間を通して測量を行い、シール
ド掘進機20と21の相対位置を確認する。なお、筒状
構造部22の内周にはあらかじめ土砂シールド24を装
備しておき、パイロットシールド掘進機14の到達後も
土砂の侵入を防ぐようにする。
It is said that a distance of four to five times the shield diameter is normally required to correct the route of a rotary cutter type shield excavator prior to underground docking. Therefore, as shown in FIG. 9, when the shield tunneling machines 20 and 21 come close to the above-mentioned predetermined distance, the tunneling is stopped, and the pilot shield tunneling machine 14 is moved from inside the shield tunneling machine 20 into the cylinder of the other shield tunneling machine 21. It is launched aiming at the inner space of the shaped structure part 22. FIG. 10 shows the state in which the pilot shield excavator 14 is digging. When the pilot shield excavator 14 comes into contact with the blind lid 23, the connection between the blind lid 23 and the cylindrical structure 22 is released, and the pilot shield excavator 1 is removed as shown in FIG.
Extract it into the shield excavator 2 by the propulsion force of step 4. After the blind cover 23 has completely come out, the pilot shield excavator 14 that has penetrated into the shield excavator 21 is moved to the trailing pipe 1.
Separated from 9, shield excavators 20 and 21 are connected to pipe 1.
9, it is in a connected state. FIG. 12 shows the state in which the pilot shield pit 2 is constructed by the pipe 19 between the shield tunneling machines 20 and 21. Thereafter, a survey is conducted through the interior space of the pilot shield pit 2 to confirm the relative positions of the shield tunneling machines 20 and 21. Note that an earth and sand shield 24 is installed in advance on the inner periphery of the cylindrical structure part 22 to prevent earth and sand from entering even after the pilot shield excavator 14 arrives.

このようにして再掘進に当っての補正値が求められたな
らば、シールド掘進機20.21のいずれかを方向制御
しながら再掘進させる。その際、掘進に伴ってパイプ1
9を1スパンごとにシールド掘進機21内で取りはずし
てゆく。ここで、シールド掘進機20のカッタボス部3
a、隔壁ボス部4aとパイプ19の間およびシールド掘
進機21の筒状構造部22とパイプ19の間には、それ
ぞれ再掘進での路線修正に必要なりリアランスが設けら
れている。
Once the correction value for re-excavation has been determined in this manner, either of the shield excavators 20, 21 is re-excavated while controlling the direction. At that time, as the excavation progresses, pipe 1
9 is removed in the shield excavator 21 one span at a time. Here, the cutter boss portion 3 of the shield excavator 20
a, clearances are provided between the bulkhead boss portion 4a and the pipe 19 and between the cylindrical structure portion 22 of the shield excavator 21 and the pipe 19, as necessary for route correction during re-excavation.

第6図には最初からパイロットシールド掘進機14を装
備したシールド掘進機の例を示したが、第13図に示す
ように、回転カッタ3の中心部に隔壁ボス部4aの穴1
3を通って機内側に突き抜ける筒状構造部22を設け、
この筒状構造部22の内空に盲ぶた23を装備した状態
で通常掘進を行い、パイロットシールド坑構築時に、盲
ぶた23を取はずして機内側に抜き取り、筒状構造部2
2の内空を通してパイロットシールド掘進機14を装備
してもよい。
FIG. 6 shows an example of a shield tunneling machine equipped with a pilot shield tunneling machine 14 from the beginning, but as shown in FIG.
A cylindrical structure part 22 is provided that penetrates through 3 into the inside of the machine,
Normal excavation is carried out with a blind cover 23 installed inside the cylindrical structure 22, and when constructing the pilot shield tunnel, the blind cover 23 is removed and pulled out inside the machine, and the cylindrical structure 22 is
A pilot shield excavator 14 may be installed through the inner space of 2.

第14図は第13図に示すシールド掘進機において、盲
ぶた23を取はずしてパイロットシールド掘進機14を
装着し、パイロ7)シールド掘進機14を発進させた状
態を示す。第15図はセンタシャフト付回転カッタ3を
備えたシールド掘進機において、センタシャフト25に
パイロットシールド掘進機14が通過できる内空部を設
けた例であり、通常掘進時にセンタシャフト内空部に装
着されている盲ぶた23を機内側に抜き取り、その内空
部よりパイロットシールド掘進機14を発進させる構造
としたものである。
FIG. 14 shows the shield tunneling machine shown in FIG. 13 with the blind lid 23 removed, the pilot shield tunneling machine 14 installed, and the shield tunneling machine 14 started. Figure 15 shows an example of a shield excavator equipped with a rotary cutter 3 with a center shaft, in which the center shaft 25 is provided with an inner cavity through which the pilot shield excavator 14 can pass, and is attached to the inner cavity of the center shaft during normal excavation. The blind cover 23 is removed to the inside of the machine, and the pilot shield excavator 14 is launched from the inner cavity thereof.

第6図、第14図に示したパイロットシールド掘進機1
4は元押し装置15の推進ジヤツキ16により推進され
る押管式シールド掘進機であるが、シールド掘進機20
が大口径である場合は、このシールド掘進機20を反力
受としてセグメントを組み推進するシールド掘進機をパ
イロットシールド掘進機として用いることもできる。
Pilot shield excavator 1 shown in Figures 6 and 14
4 is a push-pipe type shield tunneling machine propelled by a propulsion jack 16 of a main pushing device 15, and the shield tunneling machine 20
When the shield tunneling machine 20 has a large diameter, the shield tunneling machine 20 can be used as a pilot shield tunneling machine, which propels the shield tunneling machine by assembling segments with the shield tunneling machine 20 as a reaction force receiver.

次に、本発明による測量方法の実施例を第17図〜第2
6図を用いて説明する。
Next, examples of the surveying method according to the present invention are shown in Figs.
This will be explained using Figure 6.

トンネル測量は基本的に下記の二つの測量によって行わ
れる。
Tunnel surveying is basically carried out by the following two types of surveying.

(a)  レベル測量 (b)トラバース測量 各測量の内容は良く知られているので、簡単に記述する
が、一般に高さの測量はレベル測量、平面上の位置測量
はトラバース測量による。
(a) Level survey (b) Traverse survey The contents of each survey are well known, so I will briefly describe them, but in general, height surveying is done by level surveying, and position surveying on a plane is done by traverse surveying.

トンネル内では、通常、測量の基準となる測点を設置し
てゆき、この測点を基準として毎日の測量を行っている
。そのほかに、掘進工期期間に何度か、立坑における基
準点より測点の測量を再度行い、測量精度を高めるのが
一般の測量方法である。
Inside the tunnel, a measurement point is usually set up to serve as a reference for surveying, and daily measurements are conducted using this measurement point as a reference. In addition, the general surveying method is to re-measure the measurement points from the reference point in the shaft several times during the excavation period to improve the accuracy of the survey.

トラバース測量においては、組み上げたセグメントの測
量以外にシールド掘進機の方向を機内基準点2点を用い
て測量し、シールド掘進機の方向制御に役立てる。また
、シールド掘進機のピッチングの測量には、下げ振りを
用いる場合が多い。
In traverse surveying, in addition to surveying the assembled segments, the direction of the shield tunneling machine is also surveyed using two internal reference points, which is useful for controlling the direction of the shield tunneling machine. Furthermore, a plumb bob is often used to measure the pitching of a shield tunneling machine.

第17図はトンネル内のレベル測量の実施状態図である
。100はシールド掘進機、101はセグメント、 1
02は立坑、103はレベル計、104.105はスケ
ールであり、P、を基準点にとった場合、測量点Mの基
準レベルからの高さE L (i)は、B L (i)
 = E L (o)  + B S −F S (i
)で求められる。図は立坑基準点を使っているが、トン
ネル内測点を用いる場合も同じである。
FIG. 17 is a diagram showing the implementation state of level surveying inside the tunnel. 100 is a shield tunneling machine, 101 is a segment, 1
02 is a shaft, 103 is a level meter, and 104.105 is a scale. If P is taken as the reference point, the height E L (i) of the survey point M from the reference level is B L (i)
= E L (o) + B S − F S (i
). Although the figure uses a shaft reference point, the same applies when using a measurement point inside a tunnel.

第18図はトラバース測量でセグメント101の位置を
測量している状態図である。測量点Mに設置したスケー
ル106の上に水準器107を置き、水平にスケール1
06をセットして中心位置をトランシットで読む。この
とき、トランシットを設置した測点P、から後方の測点
Pi−1を見て基準線を出し、確度Aθ、を検出する。
FIG. 18 is a diagram showing the state in which the position of the segment 101 is being surveyed by traverse surveying. Place the level 107 on the scale 106 installed at the survey point M, and set the scale 1 horizontally.
Set 06 and read the center position with transit. At this time, a reference line is drawn by looking at the measuring point Pi-1 behind the measuring point P where the transit is installed, and the accuracy Aθ is detected.

ここで、測点Pi−1の方位角をθト1、測点P、の方
位角をθf+ P LM2点間の距離をり、とすると、
M点の平面座標(X、4.Yl、l)は、 X、4 =Xpi+Lt X  sinθ。
Here, if the azimuth of the measuring point Pi-1 is θto1, the azimuth of the measuring point P is θf+P, and the distance between the two points LM is,
The plane coordinates (X, 4.Yl, l) of point M are: X, 4 = Xpi + Lt X sin θ.

Y、4=Y、4+L”4 X cosθ。Y, 4=Y, 4+L"4 X cos θ.

ただし、 θえ=θ=−+ + A e t   18
0’で求められる。
However, θ=θ=−+ + A e t 18
It is determined by 0'.

第19図はシールド掘進機100のヨーイングを調べる
測量の状態図である。あらかじめシールド掘進機100
内に基準点を2点(M、、M、)設け、シールド掘進機
先端等との座標関係を把握しておく。
FIG. 19 is a state diagram of a survey to check the yawing of the shield tunneling machine 100. Shield tunneling machine 100 in advance
Two reference points (M, , M,) are established within the area, and the coordinate relationship with the tip of the shield tunneling machine, etc. is known.

測点P =、 P =−+間の基準線を出した後、機内
基準点M、、M、の位置を測量することにより、シール
ド掘進機100の方向等が確認できる。
After drawing a reference line between measurement points P = and P = -+, the direction of the shield excavator 100 and the like can be confirmed by surveying the positions of the in-machine reference points M, , M,.

機内基準点の座標M1(Xat、 Vat) 、 MZ
(X、+2゜Y6.)、方位角θイの計算式は下記の通
りである。
Coordinates of the in-flight control point M1 (Xat, Vat), MZ
(X, +2°Y6.) and the calculation formula for the azimuth angle θi is as follows.

θ1.=θi−、+Aθ、 −180”θ1□=θムー
、+Aθz   180″X  B 1 = X pt
 +  f  H1X  stn θ 、電Y6+=Y
pi+j21+X CO5θム区Xat = Xp! 
+ l izX  sinθ1□Yez=Ypf+l!
t× cosθ、2地中ドツキングのためにシールド掘
進機2oと21の間にパイロットシールド坑2を貫通さ
せ、光学測量を可能とした場合の測量状態の例を第20
図〜第23図に示す。パイロットシールド坑を介しての
測量も基本的には前述したトンネル坑内測量と同じであ
るが、測量の目的は2機のシールド掘進機のずれを補正
することにある。
θ1. =θi-, +Aθ, -180"θ1□=θmu, +Aθz 180"X B 1 = X pt
+ f H1X stn θ, electric Y6+=Y
pi+j21+X CO5θmukuXat=Xp!
+ l izX sinθ1□Yez=Ypf+l!
t × cos θ, 2 An example of the surveying state when optical surveying is enabled by penetrating the pilot shield hole 2 between the shield tunneling machines 2o and 21 for underground docking is shown in the 20th example.
It is shown in FIGS. Surveying through the pilot shield pit is basically the same as the tunnel survey described above, but the purpose of the survey is to correct the deviation between the two shield tunneling machines.

第20図はレベルの誤差補正を行うための測量の状態図
である。一方のシールド掘進機21の後方トンネル内の
測点にレベル計108を設置し、パイロットシールド坑
2を通して相手側シールド掘進機20の後方トンネル内
の測点に設置したスケール109を読むことで、両トン
ネルの高さのずれが分る。
FIG. 20 is a state diagram of surveying for level error correction. A level meter 108 is installed at a measuring point in the rear tunnel of one shield tunneling machine 21, and a scale 109 installed at a measuring point in the rear tunnel of the other shield tunneling machine 20 is read through the pilot shield hole 2. You can see the difference in the height of the tunnel.

図はスケール109を測点に設置した場合であるが、相
手側シールド掘進機20内を含む任意の点にスケールを
設置して、両トンネルの測点からレベル測量を行うこと
も可能である。
Although the figure shows the case where the scale 109 is installed at a measurement point, it is also possible to install the scale at any point including inside the other party's shield excavator 20 and perform level surveying from the measurement points of both tunnels.

第21図は両トンネルの座標値のずれを測量した場合を
示している。図では、シールド掘進機20内に目標測量
点110を設け、その点を両トンネル内の測点に設置し
たトランシット111.112よりトラバース測量して
いる。目標測量点はシールド掘進機の後方トンネル内あ
るいはパイロットシールド坑2内に設けてもよい。この
場合、両シールド掘進機の傾きを合わせるための角度の
誤差は把握できない。
FIG. 21 shows the case where the deviation of the coordinate values of both tunnels was measured. In the figure, a target survey point 110 is set up inside the shield excavator 20, and the traverse survey is carried out using transits 111 and 112 installed at survey points in both tunnels. The target survey point may be provided in the rear tunnel of the shield tunneling machine or in the pilot shield shaft 2. In this case, the error in the angle required to match the inclinations of both shield tunneling machines cannot be determined.

第22図は両シールド掘進機20.21の傾きを合わせ
るため、測量に用いている基準線からの角度の誤差まで
補正するための測量を行った場合を示している。すなわ
ち、第21図で用いた目標測量点110と110以外の
任意の点113をシールド掘進機21の後方トンネル内
基準点およびシールド掘進機20の後方トンネル内基準
点の両方より測量することにより角度の相対的なずれを
求めるものである。
FIG. 22 shows a case in which surveying was carried out to match the inclinations of both shield tunneling machines 20 and 21, and to correct even the angular error from the reference line used for surveying. That is, by surveying the target survey points 110 and any point 113 other than 110 used in FIG. The purpose is to find the relative deviation of

第23図はパイロットシールド坑2を介して相手側のシ
ールド掘進機の傾きを直接測量する状態図である。一方
のシールド掘進機21の後方トンネル内の測点に設置し
たトランシット111よりパイロットシールド坑2を介
して相手側シールド掘進機20に設置した2点の目標測
量点110を測量しシールド掘進機20の傾きを求める
ものである。
FIG. 23 is a diagram showing the state in which the inclination of the other shield tunneling machine is directly measured through the pilot shield pit 2. The two target survey points 110 installed on the other shield tunneling machine 20 are surveyed from the transit 111 installed at a measuring point in the rear tunnel of one shield tunneling machine 21 via the pilot shield pit 2. This is to find the slope.

第25図、第26図は第20図、第21図の測量内容を
示したものである。
Figures 25 and 26 show the contents of the survey in Figures 20 and 21.

第25図は立坑基準点P。+poからパイロットシール
ド坑貫通後の最終測量点までの両トンネルのレベル測量
結果を示し、図において、Pは立坑A側より測量して得
られたE L (P)で表わされる高さの点であり、p
は立坑B側より測量して得られたel(p)で表わされ
る高さの点である。(P、〜Pn+  p+〜pカは測
点)。発進立坑Aにおけるレベル測量値E L (a)
および発進立坑Bにおけるレベル測量値el(b)より
、各路線ごとの最終測量点におけるレベル測量値E L
 (P)、 el (p)が求まり、これらの値の差Δ
H(=EL(P) −el(p))が再掘進での高さ補
正値となる。
Figure 25 shows the shaft reference point P. The level survey results for both tunnels from +po to the final survey point after penetrating the pilot shield shaft are shown. In the figure, P is the height point expressed by E L (P) obtained by surveying from the shaft A side. Yes, p
is the height point expressed by el(p) obtained by surveying from the shaft B side. (P, ~Pn+ p+ ~pka are measurement points). Level measurement value E L (a) at starting shaft A
From the level measurement value el(b) at the starting shaft B, the level measurement value E L at the final survey point for each route
(P) and el (p) are found, and the difference between these values Δ
H(=EL(P)-el(p)) is the height correction value for re-excavation.

第26図は立坑基準点Po、poから最終測量点までの
両トンネルの平面位置を示し、図において、Pは立坑A
側より測量して得られた座標であり、pは立坑B側より
測量して得られた座標である。
Figure 26 shows the planar position of both tunnels from the shaft reference point Po, po to the final survey point, and in the figure, P is shaft A.
These are the coordinates obtained by surveying from the side, and p is the coordinates obtained by surveying from the shaft B side.

ここで、立坑入側からの測量による最終測量点の座標P
(P、、P、)は、 立坑B側からの測量による最終測量点の座標p(px、
py)  は、 両者の誤差による最終測量点でのずれ量(ΔX。
Here, the coordinates P of the final survey point from the shaft entry side are
(P,,P,) is the coordinate p(px,
py) is the amount of deviation (ΔX) at the final survey point due to the error between the two.

Δy)は、 Δx = P w  P yt 、  Δy女Py  
Pyとなり、これが再掘進での座標補正値となる。
Δy) is Δx = P w P yt , Δy female Py
Py, which becomes the coordinate correction value for re-excavation.

また、第24図に示すようにパイロットシールド坑2の
内部空間が貫通していない場合も、パイロットシールド
坑2を塞いだ板114に目標測量点を設けることで、両
トンネルの座標値のずれは第21図と同様に求められる
。この場合、シールド掘進機20.21の傾きを正確に
把握するためには、シールド掘進機内にジャイロコンパ
スを設置する方法や、パイロットシールド坑を塞いだ板
114に3箇所以上の測量点を設け、その各点を両方の
トンネル内から測量することによって板114の設置角
度を求め、両トンネルの軸線の角度誤差を出す方法等を
用いることができる。
Furthermore, even if the internal space of the pilot shield shaft 2 is not penetrated as shown in FIG. 24, by setting the target survey point on the plate 114 that closes the pilot shield shaft 2, the deviation of the coordinate values of both tunnels can be reduced. It is obtained in the same manner as in FIG. In this case, in order to accurately grasp the inclination of the shield tunneling machine 20, 21, it is necessary to install a gyro compass inside the shield tunneling machine, or to install three or more survey points on the plate 114 that closes the pilot shield pit. It is possible to use a method such as determining the installation angle of the plate 114 by surveying each point from inside both tunnels and calculating the angular error between the axes of both tunnels.

ジャイロコンパスは、ジャイロが真北を指す特性を利用
し、あらかじめシールド掘進機の軸線に合せて機内に設
置することにより、シールド掘進機の傾きを求めるもの
である。したがって、両方のシールド掘進機に設置する
ことで、互いのシールド掘進機の傾きを比較することが
できる。
A gyro compass takes advantage of the fact that a gyro points to true north, and is used to determine the inclination of a shield machine by installing it inside the machine in advance, aligning it with the axis of the machine. Therefore, by installing it in both shield tunneling machines, it is possible to compare the inclinations of the shield tunneling machines.

以上の測量により求められた両シールド掘進機の位置お
よび傾きの補正値に基づき、再掘進におけるシールド掘
進機の掘進方向を制御し、路線の修正を行う。掘進方向
の制御は、上記補正値に基づき、オペレータが手動操作
によりシールドジヤツキ9を選択作動させることによっ
ても行えるが、レーザビーム装置、ジャイロコンパス等
の自動測量機器を用い、測量機器の検出値を電気信号と
して直接、コンピュータに入力し、再掘進での補正値を
算出した後、その補正値に基づいてシールドジヤツキを
自動操作する自動方向制御システムも採用可能である。
Based on the correction values for the positions and inclinations of both shield excavators determined by the above survey, the direction of excavation of the shield excavators during re-excavation is controlled and the route is corrected. The excavation direction can also be controlled by the operator selecting and operating the shield jack 9 manually based on the above correction value, but it is also possible to control the excavation direction by manually operating the shield jack 9 based on the above correction value. It is also possible to adopt an automatic direction control system that directly inputs this as an electrical signal into a computer, calculates a correction value for re-excavation, and then automatically operates the shield jack based on the correction value.

レーザビーム装置等による自動測量とコンピュータによ
るシールドジヤツキの自動操作を組合せたシールド掘進
機の自動方向制御システムに関しては、特公昭61−5
6755号にシールド掘進機の現在位置を後方より測量
する方式が開示されており、この方式は到達目標位置側
に設置した測量器によりパイロットシールド坑を介して
シールド掘進機の現在位置を測量する場合にも準用でき
るので、本システムについての詳細な記述は省略する。
Regarding an automatic direction control system for a shield excavator that combines automatic surveying using a laser beam device, etc. and automatic operation of a shield jack using a computer, the Japanese Patent Publication Publication No. 61-5
No. 6755 discloses a method for surveying the current position of a shield excavator from the rear, and this method uses a surveying instrument installed on the target position side to survey the current position of a shield excavator through a pilot shield hole. A detailed description of this system will be omitted since it can also be applied to other systems.

掘進制御の一方法として、シールド掘進機後方のトンネ
ル内に設置した基準点と到達目標位置との相対位置を測
量し、以後、その基準点を基準にして到達目標位置に向
はシールド掘進機を掘進させることも可能である。しか
し、一般にトンネルの先端に近い部分はど地山のゆるみ
によるセグメントの移動が生じやすく、−度の測量では
シールド掘進機が到達目標位置に到達するまでの間に基
準点の位置がずれてしまうこともあり、そのほか測定誤
差や方向制御の誤差もあり得るので、パイロットシール
ド坑2を存置したまま、再掘進中も前に述べた測量を繰
り返し行い、その結果に基づいて逐次路線の修正を行う
ようにすれば、到達目標位置への到達の確度をより高め
ることができる。
One way to control excavation is to measure the relative position between a reference point installed in the tunnel behind the shield machine and the target position, and then move the shield machine towards the target position based on that reference point. It is also possible to make it dig. However, in general, segments near the tip of a tunnel tend to move due to loosening of the ground, and in -degree surveying, the position of the reference point shifts before the shield excavator reaches the target position. In addition, there may be measurement errors or errors in direction control, so the survey mentioned above will be repeated during re-excavation, with Pilot Shield Pit 2 left in place, and the route will be corrected one by one based on the results. By doing so, the accuracy of reaching the target position can be further increased.

以上では、パイロットシールド坑を回転カッタ中心部を
通して構築する例について説明してきたが、回転カッタ
の中心部以外の箇所を貫通してパイロットシールド坑を
構築し、測量を行っても、路線の修正1可能である。こ
の場合は、再掘進に先立ち回転カッタと干渉するパイロ
ットシールド坑を撤去しなければならず、掘進中の再測
量はできないが、従来のように各々のシールド掘進機の
ずれを把握できないまま、地中ドツキングさせる場合よ
りは、ドツキング時のずれを小さく抑えることができる
Above, we have explained an example in which the pilot shield hole is constructed through the center of the rotary cutter, but even if the pilot shield hole is constructed by penetrating through a part other than the center of the rotary cutter and surveying is carried out, the line correction 1 It is possible. In this case, the pilot shield hole that interferes with the rotary cutter must be removed before re-excavation, and resurveying during excavation is not possible, but unlike conventional methods, the pilot shield hole that interferes with the rotary cutter cannot be re-surveyed. The deviation at the time of dotting can be suppressed to a smaller value than when dotting in the middle.

以上述べた技術は、シールド掘進機同士の地中ドツキン
グのほか、シールド掘進機と既設トンネルのT字接合あ
るいはシールド掘進機と立坑の接合などにも応用するこ
とができる。
The technology described above can be applied not only to underground docking between shield tunneling machines, but also to T-shaped connections between shield tunneling machines and existing tunnels, or connection between shield tunneling machines and vertical shafts.

また、シールド掘進機に装備したパイロットシールド掘
進機は地山の先行調査、地盤改良および異物撤去対策な
どの他目的にも利用可能である。
In addition, the pilot shield excavator equipped on the shield excavator can be used for other purposes such as advance investigation of the ground, ground improvement, and measures to remove foreign objects.

〔発明の効果] 本発明によれば、パイロットシールド坑を介しての測量
により到達目標位置に対するシールド掘進機のずれを事
前に把握できることと、その測量結果に基づくシールド
掘進機の掘進方向制御により掘進路線の修正ができるこ
とで、シールド掘進機の到達目標位置への到達の確度を
高めることができる。特に、パイロットシールド坑をシ
ールド掘進機の回転カッタ中心部を通して構築し、これ
を存置したまま、パイロットシールド坑を介しての測量
を繰り返し行い、その測量結果に基づいて逐次掘進方向
を制御しながらシールド掘進機を掘進させるようにすれ
ば、いわゆる有視界掘進によって到達目標位置への到達
の確度はさらに高まり、また−度構築したパイロットシ
ールド坑の撤去によって地山の安定を損う恐れもなく、
シールド掘進機の地中ドツキングをより安全に、かつ確
実に達成することができる。
[Effects of the Invention] According to the present invention, the deviation of the shield excavator from the target position can be ascertained in advance by surveying through the pilot shield pit, and the excavation direction of the shield excavator is controlled based on the survey results, so that the excavation can be carried out. By being able to correct the route, it is possible to increase the accuracy with which the shield tunneling machine reaches its target location. In particular, a pilot shield hole is constructed through the center of the rotary cutter of the shield excavator, and while the pilot shield hole remains in place, surveys are repeatedly carried out through the pilot shield hole, and the shield is shielded while sequentially controlling the direction of excavation based on the survey results. If the excavator is allowed to dig, the accuracy of reaching the target position will be further increased through so-called visual excavation, and there will be no risk of destabilizing the ground due to the removal of the pilot shield pit that has been constructed.
It is possible to achieve underground docking of a shield tunneling machine more safely and reliably.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明をシールド掘進機の地中トンキングに適
用した場合の概念図、第2図〜第5図は地中ドツキング
時の掘進路線のずれの説明図、第6図は本発明によるパ
イロットシールド掘進機を装備した回転カッタ式シール
ド掘進機の構成例を示す側断面図、第7図はパイロット
シールド掘進機の内部構造を例示した側断面図、第8図
はパイロットシールド掘進機が到達する相手側シールド
掘進機の構成例を示す側断面図、第9図〜第12図は第
6図、第8図に示す両シールド機の間にパイロットシー
ルド坑を構築する過程の説明図、第13図〜第15図は
本発明によるパイロットシールド掘進機を装備した回転
カッタ式シールド掘進機の他の構成例を示す側断面図、
第16図は従来の回転カッタ式シールド掘進機の側断面
図、第17図はトンネル内のレベル測量の状態図、第1
8図、第19図はトンネル内のトラバース測量の状態図
、第20図〜第24図は本発明によるパイロットシール
ド坑を介しての測量の状態図、第25図、第26図は第
20図。 第21図の測量内容の説明図である。 LA、IB・・・シールド掘進機、2・・・パイロット
シールド坑、3・・・回転カッタ、4・・・隔壁、9・
・・シールドジヤツキ、12・・・カッタボス部穴、1
3・・・隔壁ボス部穴、14・・・パイロットシールド
掘進機、14a・・・カッタヘッド、14b・・・カッ
タ駆動モータ、14c・・・方向修正ジヤツキ、14d
・・・測量装置、14e・・・送泥管、14f・・・余
堀り用カッタ、15・・・元押し装置、16・・・推進
ジヤツキ、19・・・パイプ、20・・・パイロットシ
ールド掘進機を装備した回転カッタ式シールド掘進機、
21・・・相手側シールド掘進機、22・・・筒状構造
部、23・・・盲ぶた、23a・・・掘削刃、108・
・・レベル計、109・・・スケール、110・・・目
標測量点、111゜112・・・トランシット、113
・・・測量点特許出願人 前田建設工業株式会社 〃   日立建機株式会社 代理人 弁理士  秋 本 正 実(外1名)第1図 (a) (b) IA、IS−・シールド掘進機 IA’・・・・・・シールド掘進機IAの最終到達位置
2・・・・・・・・パイロットシールド抗第2図 1Δ 第3図 第4図 A 第13図 9 :シールドジャッキ 第15図 5 :チャンバ 8:カワタ駆動モータ 9:シールドジャッキ
Figure 1 is a conceptual diagram when the present invention is applied to underground tunneling by a shield tunneling machine, Figures 2 to 5 are explanatory diagrams of deviations in the tunneling line during underground tunneling, and Figure 6 is a diagram according to the present invention. A side sectional view showing an example of the configuration of a rotary cutter type shield tunneling machine equipped with a pilot shield tunneling machine. Figure 7 is a side sectional view illustrating the internal structure of the pilot shield tunneling machine. Figure 8 is a side sectional view showing an example of the structure of a rotary cutter type shield tunneling machine equipped with a pilot shield tunneling machine. 9 to 12 are explanatory views of the process of constructing a pilot shield tunnel between both shield machines shown in FIGS. 6 and 8. 13 to 15 are side sectional views showing other configuration examples of a rotary cutter type shield tunneling machine equipped with a pilot shield tunneling machine according to the present invention,
Figure 16 is a side sectional view of a conventional rotary cutter type shield excavator, Figure 17 is a state diagram of level surveying in a tunnel, and Figure 1
Figures 8 and 19 are state diagrams of traverse surveying inside a tunnel, Figures 20 to 24 are state diagrams of surveying via a pilot shield shaft according to the present invention, and Figures 25 and 26 are state diagrams of surveying through a pilot shield shaft according to the present invention. . FIG. 22 is an explanatory diagram of the survey contents in FIG. 21; LA, IB...Shield excavator, 2...Pilot shield pit, 3...Rotary cutter, 4...Bulkhead, 9...
...Shield jack, 12...Cutter boss hole, 1
3... Bulkhead boss hole, 14... Pilot shield excavator, 14a... Cutter head, 14b... Cutter drive motor, 14c... Direction correction jack, 14d
...Surveying device, 14e...Sludge pipe, 14f...Cutter for over-drilling, 15...Main push device, 16...Propulsion jack, 19...Pipe, 20...Pilot A rotary cutter type shield excavator equipped with a shield excavator,
21... Opposite shield excavator, 22... Cylindrical structure part, 23... Blind lid, 23a... Excavation blade, 108...
...Level meter, 109...Scale, 110...Target survey point, 111°112...Transit, 113
...Survey point patent applicant Maeda Construction Industry Co., Ltd. Hitachi Construction Machinery Co., Ltd. Representative Patent attorney Masami Akimoto (1 other person) Figure 1 (a) (b) IA, IS-・Shield excavator IA '......Final position of shield tunneling machine IA 2......Pilot shield drag Fig. 2 1Δ Fig. 3 Fig. 4 A Fig. 13 9: Shield jack Fig. 15 5: Chamber 8: Kawata drive motor 9: Shield jack

Claims (1)

【特許請求の範囲】 1、到達目標位置に向って地中を掘進中の回転カッタ式
シールド掘進機と前記到達目標位置側との間に地中を貫
通するパイロットシールド坑を構築し、このパイロット
シールド坑を介して前記到達目標位置に対する前記回転
カッタ式シールド掘進機の現在位置を測量することを特
徴とするシールド工法。 2、前記パイロットシールド坑は、前記回転カッタ式シ
ールド掘進機の回転カッタ中心部を通して構築されるこ
とを特徴とする請求項1記載のシールド工法。 3、到達目標位置に向って地中を掘進中の回転カッタ式
シールド掘進機と前記到達目標位置側との間に地中を貫
通するパイロットシールド坑を構築し、前記回転カッタ
式シールド掘進機の後方のトンネル内に基準点を設置し
、前記パイロットシールド坑を介して前記到達目標位置
に対する前記基準点の位置を測量することを特徴とする
シールド工法。 4、前記パイロットシールド坑は、前記回転カッタ式シ
ールド掘進機の回転カッタ中心部を通して構築されるこ
とを特徴とする請求項3記載のシールド工法。 5、請求項1または2記載の方法による測量結果に基づ
き、掘進方向の制御を行いながら回転カッタ式シールド
掘進機を掘進させ、到達目標位置に到達させることを特
徴とするシールド工法。 6、請求項3または4記載の方法による測量結果に基づ
き、掘進方向の制御を行いながら回転カッタ式シールド
掘進機を掘進させ、到達目標位置に到達させることを特
徴とするシールド工法。 7、到達目標位置に向って地中を掘進中の回転カッタ式
シールド掘進機と前記到達目標位置側との間に前記回転
カッタ式シールド掘進機の回転カッタ中心部を通して地
中を貫通するパイロットシールド坑を構築し、前記パイ
ロットシールド坑を存置したまま、前記パイロットシー
ルド坑を介して前記到達目標位置に対する前記回転カッ
タ式シールド掘進機の現在位置の測量を繰り返し行い、
それぞれの測量結果に基づいて逐次掘進方向の制御を行
いながら前記回転カッタ式シールド掘進機を掘進させ、
到達目標位置に到達させることを特徴とするシールド工
法。 8、到達目標位置に向って地中を掘進中の回転カッタ式
シールド掘進機と前記到達目標位置との間に前記回転カ
ッタ式シールド掘進機の回転カッタ中心部を通して地中
を貫通するパイロットシールド坑を構築し、前記回転カ
ッタ式シールド掘進機の後方のトンネル内に基準点を設
置し、前記パイロットシールド坑を存置したまま、前記
パイロットシールド坑を介して前記到達目標位置に対す
る前記基準点の位置の測量を繰り返し行い、それぞれの
測量結果に基づいて逐次掘進方向の制御を行いながら前
記回転カッタ式シールド掘進機を掘進させ、到達目標位
置に到達させることを特徴とするシールド工法。 9、回転カッタ式シールド掘進機において、該機内に回
転カッタの中心部を貫通して前方へパイロットシールド
坑を構築可能なパイロットシールド掘進機を設けたこと
を特徴とするシールド掘進機。 10、前記パイロットシールド掘進機が掘進方向の制御
可能な掘進機であることを特徴とする請求項9記載のシ
ールド掘進機。 11、前記パイロットシールド掘進機が余掘り機能を有
する掘進機であることを特徴とする請求項9または10
記載のシールド掘進機。 12、回転カッタ式シールド掘進機において、回転カッ
タおよびその後方の隔壁の中心部を貫通してパイロット
シールド掘進機を受入れ可能な筒状構造部を設け、この
筒状構造部の内側に盲ぶたを機内側に抜き取り可能なよ
うに装着したことを特徴とするシールド掘進機。 13、前記盲ぶたは、その前端面に掘削刃を有すること
を特徴とする請求項12記載のシールド掘進機。
[Claims] 1. A pilot shield shaft penetrating underground is constructed between the rotary cutter type shield excavator which is digging underground toward the target position and the target position side, and this pilot A shield construction method characterized by measuring the current position of the rotary cutter type shield excavator with respect to the target position through a shield pit. 2. The shield construction method according to claim 1, wherein the pilot shield pit is constructed through the center of the rotary cutter of the rotary cutter type shield excavator. 3. A pilot shield pit penetrating underground is constructed between the rotary cutter type shield excavator which is excavating underground toward the target position and the target position side, and the rotary cutter type shield excavator is A shield construction method characterized in that a reference point is installed in a rear tunnel, and the position of the reference point relative to the target position is measured through the pilot shield hole. 4. The shield construction method according to claim 3, wherein the pilot shield pit is constructed through the center of the rotary cutter of the rotary cutter type shield excavator. 5. A shield construction method, characterized in that, based on the survey results obtained by the method according to claim 1 or 2, a rotary cutter type shield excavator is caused to excavate while controlling the excavation direction to reach a target position. 6. A shield construction method, characterized in that, based on the survey results obtained by the method according to claim 3 or 4, a rotary cutter type shield excavator is caused to excavate while controlling the excavation direction to reach a target position. 7. A pilot shield that penetrates the ground through the center of the rotary cutter of the rotary cutter type shield excavator between the rotary cutter type shield excavator that is digging underground toward the target position and the target position side. constructing a pit, and while leaving the pilot shield pit in place, repeatedly surveying the current position of the rotary cutter type shield excavator with respect to the target position via the pilot shield pit;
The rotary cutter type shield excavator excavates while sequentially controlling the excavation direction based on each survey result,
A shield construction method characterized by reaching the target position. 8. A pilot shield pit that penetrates underground through the center of the rotary cutter of the rotary cutter type shield excavator between the rotary cutter type shield excavator that is digging underground toward the target position and the target position. A reference point is installed in the tunnel behind the rotary cutter type shield excavator, and the position of the reference point relative to the target position is determined through the pilot shield pit while leaving the pilot shield pit in place. A shield construction method characterized in that the rotary cutter type shield excavator excavates the excavation machine while repeatedly conducting surveys and sequentially controlling the excavation direction based on the results of each survey to reach a target position. 9. A rotary cutter type shield excavator, characterized in that a pilot shield excavator is provided in the rotary cutter, which is capable of penetrating the center of the rotary cutter and constructing a pilot shield tunnel forward. 10. The shield excavator according to claim 9, wherein the pilot shield excavator is an excavator whose excavation direction can be controlled. 11. Claim 9 or 10, wherein the pilot shield excavator is an excavator having an over-digging function.
The shield excavator described. 12. In a rotary cutter type shield tunneling machine, a cylindrical structure that can receive the pilot shield tunneling machine by penetrating the center of the rotary cutter and the bulkhead behind it is provided, and a blind cover is provided inside this cylindrical structure. A shield excavator characterized by being attached to the inside of the machine so that it can be removed. 13. The shield excavator according to claim 12, wherein the blind lid has a digging blade on its front end surface.
JP763488A 1988-01-19 1988-01-19 Method and machine for shield construction Granted JPH01187286A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP763488A JPH01187286A (en) 1988-01-19 1988-01-19 Method and machine for shield construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP763488A JPH01187286A (en) 1988-01-19 1988-01-19 Method and machine for shield construction

Publications (2)

Publication Number Publication Date
JPH01187286A true JPH01187286A (en) 1989-07-26
JPH0574674B2 JPH0574674B2 (en) 1993-10-18

Family

ID=11671260

Family Applications (1)

Application Number Title Priority Date Filing Date
JP763488A Granted JPH01187286A (en) 1988-01-19 1988-01-19 Method and machine for shield construction

Country Status (1)

Country Link
JP (1) JPH01187286A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0288883A (en) * 1988-09-26 1990-03-29 Mitsui Eng & Shipbuild Co Ltd Method of shielding construction and excavator thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62288297A (en) * 1986-06-04 1987-12-15 株式会社大林組 Method of detecting position of excavated hole
JPS63304894A (en) * 1987-06-05 1988-12-13 清水建設株式会社 Position sensing method of shielding machine

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62288297A (en) * 1986-06-04 1987-12-15 株式会社大林組 Method of detecting position of excavated hole
JPS63304894A (en) * 1987-06-05 1988-12-13 清水建設株式会社 Position sensing method of shielding machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0288883A (en) * 1988-09-26 1990-03-29 Mitsui Eng & Shipbuild Co Ltd Method of shielding construction and excavator thereof

Also Published As

Publication number Publication date
JPH0574674B2 (en) 1993-10-18

Similar Documents

Publication Publication Date Title
JP4642288B2 (en) Underground excavation system
JP4629895B2 (en) Gyrocompass device
JPH01187286A (en) Method and machine for shield construction
JP3989624B2 (en) Position measuring device for submarine or submarine civil engineering machinery or cable burying machine
JPS63210614A (en) Method for correcting varticality of pile in driving of pile
JP2913042B2 (en) Underground excavator propulsion management surveying device
JP3353036B2 (en) Excavator for renewing existing buried pipelines and excavation method when renewing existing buried pipelines
JP2003013687A (en) Method for measuring displacement of ground surface or subbase course in case of shield excavation and method and device for controlling displacement of subbase course
JPH0566130A (en) Automatic searching device for excavator
JPH0727564A (en) Measuring device for position and attitude of excavator
JPH0336399B2 (en)
JPS6117977B2 (en)
JPH0791938B2 (en) Shield machine position detection method
JPH03257321A (en) Relative position detecting apparatus of underground excavator
JPH1088969A (en) Pipeline measuring device
JP2022163601A (en) Segment ring rolling amount measuring method and tunnel digging method
JP2573523B2 (en) Mutual position detection method of shield machine
Peach et al. Tunnel Surveying Works: A Technical Challenge of 10 km-long tunnel under the Arabian Gulf-Qatar
JP3062046B2 (en) Rolling measurement device and method for vertical excavator
JPS62288515A (en) Position/posture measuring apparatus in shielded excavator
JPS62288297A (en) Method of detecting position of excavated hole
JPH0588350B2 (en)
JPH0444072B2 (en)
JP2001082075A (en) Relative position surveying method for shield machines
JPH076347B2 (en) Method and apparatus for detecting relative position of shield machine

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees