JPH01105821A - Increase of duct and execution thereof - Google Patents

Increase of duct and execution thereof

Info

Publication number
JPH01105821A
JPH01105821A JP62261625A JP26162587A JPH01105821A JP H01105821 A JPH01105821 A JP H01105821A JP 62261625 A JP62261625 A JP 62261625A JP 26162587 A JP26162587 A JP 26162587A JP H01105821 A JPH01105821 A JP H01105821A
Authority
JP
Japan
Prior art keywords
hole
duct
extension
duct sleeve
manhole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP62261625A
Other languages
Japanese (ja)
Other versions
JP2581933B2 (en
Inventor
Takayuki Nagaoka
孝幸 長岡
Kazuo Toyokawa
豊川 一男
Takashi Ota
孝 太田
Katsuhiko Akimoto
秋本 克彦
Tetsuo Matsumoto
哲男 松本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Telegraph and Telephone Corp
Hakko Co Ltd
Original Assignee
Nippon Telegraph and Telephone Corp
Hakko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Telegraph and Telephone Corp, Hakko Co Ltd filed Critical Nippon Telegraph and Telephone Corp
Priority to JP62261625A priority Critical patent/JP2581933B2/en
Publication of JPH01105821A publication Critical patent/JPH01105821A/en
Application granted granted Critical
Publication of JP2581933B2 publication Critical patent/JP2581933B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

PURPOSE:To prevent cracks or water leaking of a structure, to shorten the working hours and to improve safety by inserting an extension duct sleeve providing with a collar section and screw section into a through hole which was bored mechanically and fixing with a clamping ring through adhesives. CONSTITUTION:A collar section 12-1 larger than a diameter of a through hole and an extension duct sleeve 12 forming a screw section 12-2 which is continuous to the collar section 12-1 are inserted into the through hole bored on the side wall 2 of a manhole by a boring mechanical means by adhering resin mortar and others to the surface of a metallic duct sleeve 3. At that time, adhesives 13 are applied between skirt walls of the through hole and to the face opposite to the side wall 2 of the manhole and etc. of a clamping ring 14. The clamping ring 14 is screwed into the screw section 12-2 to hold the side wall 2 by the collar section 12-1 and to fix the extension duct sleeve 12 through adhesives 13.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明はダクト増設口とその施工方法に関するもので、
特に通信ケーブル等を収容する管部材を既設マンホール
等の地下構造物に接続手段により接続したダクト増設口
とその施工方法に関するものである。
[Detailed Description of the Invention] (Industrial Application Field) The present invention relates to a duct extension port and a construction method thereof.
In particular, the present invention relates to a duct extension opening in which a pipe member for accommodating a communication cable or the like is connected to an underground structure such as an existing manhole by a connecting means, and a construction method thereof.

(従来の技術) 従来のこの種の技術の1例としては第2図に示す如きも
のがあった。第2図(a) (b) 0 (d)は、図
示は省略したが、通信ケーブル等を内部に収容する管部
材を、既設マンホール等の地下構造物のマンホール等側
壁2を貫通して接続するダクト増設口の従来の構造とそ
の施工方法の説明断面図である。
(Prior Art) An example of this type of conventional technology is shown in FIG. Although not shown in Figure 2 (a), (b), and (d), a pipe member that accommodates a communication cable, etc., is connected by penetrating the side wall 2 of an underground structure such as an existing manhole. FIG. 2 is an explanatory cross-sectional view of the conventional structure of a duct extension port and its construction method.

第2図(、)に示す如く地下構造物の所定の部位に形成
したマンホール等の側壁2に、例えば手のみ、ライトピ
ックハンマ等による掘削手段1でダクト増設口の挿入穴
2−1を後から述べるンクトスリーブ3の外径より大き
く掘削しておく。
As shown in Fig. 2(,), an insertion hole 2-1 for a duct extension opening is made in a side wall 2 of a manhole or the like formed in a predetermined part of an underground structure using an excavating means 1, for example, by hand or with a light pick hammer. The hole is excavated to be larger than the outer diameter of the sleeve 3 described in .

つぎに第2図伽)に示す如く、前記挿入穴2−1にダク
トスリーブ3を挿入しダクト口の型枠4で挿入穴2−1
の両端にとシつける。型枠4は適宜ダクトスリーブの円
形寸法に合わせて木材等で設ける。
Next, as shown in Figure 2, the duct sleeve 3 is inserted into the insertion hole 2-1, and the duct opening mold 4 is inserted into the insertion hole
Attach laces to both ends. The formwork 4 is made of wood or the like to suit the circular dimensions of the duct sleeve.

つぎに第2図(C)に示す如く、前記第2図(b)の挿
入穴2−1とダクトスリーブ3の外側との間の空隙にコ
ンクリート5を打設して挿入穴2−1とダクトスリーブ
3とを固定する。
Next, as shown in FIG. 2(C), concrete 5 is poured into the gap between the insertion hole 2-1 shown in FIG. 2(b) and the outside of the duct sleeve 3 to form the insertion hole 2-1. and the duct sleeve 3 are fixed.

つぎに第2図(d)に示す如くコンクリート5の固着を
まって型枠4を除去し、ダクト増設口は完成する。
Next, as shown in FIG. 2(d), the formwork 4 is removed after waiting for the concrete 5 to set, and the duct extension opening is completed.

以上説明したように従来の技術においては前記のように
既設マンホール等の地下構造物に前記の通シの第2図(
、)ω) 0 (d)で示す施工方法で、ダクト増設口
を設けていた。
As explained above, in the conventional technology, as mentioned above, the above-mentioned through hole (Fig.
, )ω) 0 The duct extension opening was installed using the construction method shown in (d).

(発明が解決しようとする問題点) しかしながら前記の従来の技術による既設マンホール等
の地下構造物へのダクト増設口の形成においてはつぎに
述べる如き問題があるという欠点があった。
(Problems to be Solved by the Invention) However, in forming a duct extension opening into an underground structure such as an existing manhole using the above-mentioned conventional technique, there are drawbacks such as the following problems.

1)前記ダクト増設口の挿入穴の開孔作業及び型枠の作
成、設置、及びコンク−リートの打設作業及びそのコン
クリート養生に数日を要すること。
1) It takes several days to drill the insertion hole for the duct expansion opening, create and install the formwork, pour concrete, and cure the concrete.

2)既設マンホール等の地下構造物への掘削手段、すな
わち手のみ、又はライトピックハンマ等を用いての既設
マンホール等のく体破壊時に手先が滑り、手のみ又はラ
イトピックハンマ等の刃先で、所定個所近傍に収容して
いる通信ケーブルに障害を与えるおそれのあること。
2) Excavation methods for underground structures such as existing manholes, i.e. only by hand or using a light pick hammer etc. When breaking the structure of an existing manhole etc., the tip of the hand slips, There is a risk of causing damage to communication cables housed near a designated location.

3)手のみ又はライトピックハンマ等を用いての既設マ
ンホール等のく体破壊時の衝撃により既設マンホール等
地下構造物に亀裂を生じること。
3) Cracks may occur in underground structures such as existing manholes due to impact when the structure of existing manholes, etc. is destroyed by hand or with a light pick hammer.

4)手のみ又はライトピックハンマ等を用いての既設マ
ンホール等のく体破壊時に粉塵等が発生し作業環境が悪
化すること。
4) When destroying existing manholes etc. by hand or using a light pick hammer, etc., dust is generated and the work environment deteriorates.

5)掘削溝内に入っての開孔作業、型枠作成及び設置、
コンクリート打設及びコンクリート養生等作業時間が長
いため安全性に欠けること。
5) Entering into the excavation trench, drilling work, formwork creation and installation,
Lack of safety due to long working hours such as concrete pouring and concrete curing.

6)コンクリート打設後数年経過したコンク17−トと
増設時に打設するコンクリートの付着が悪いため、コン
クリートの打継目からの漏水が生じること。
6) Water leaks from the concrete joints due to poor adhesion between the concrete that has been poured for several years and the concrete poured during expansion.

以上述べた如き問題があった。There were problems as described above.

(問題点を解決するための手段) 前記問題点を解決するため、本発明に於ては、既設のマ
ンホール等地下構造物の所定部位に貫通孔を設け、該貫
通孔に通信ケーブル等を内挿する管部材を設けるように
形成したダクト増設口において、前記マンホール等地下
構造物の所定部位に削孔機械手段により削孔した貫通孔
と、一端に該貫通孔より大なる直径の鍔部を有するとと
もに、該鍔部に連続して長手方向に該貫通孔の深さより
大なる長さを有し、レジンモルタル等を表面に被着し且
つその被着面にねじ切り面を形成した増設用ダクトスリ
ーブと、前記増設用ダクトスリーブに設けたねじ部に螺
合する締付は環と、接着剤とよりなり、前記貫通孔の1
面より、該貫通孔の壁面との間に接着剤を介して増設用
ダクトスリーブを挿入し、他の面に突出した該増設用ダ
クトスリーブのねじ部を締付は環で螺合してダクト増設
口を構成し、またその施工方法を構成したのである。
(Means for Solving the Problems) In order to solve the above problems, in the present invention, a through hole is provided in a predetermined part of an existing underground structure such as a manhole, and a communication cable, etc. is inserted into the through hole. In a duct extension opening formed to provide a pipe member to be inserted, a through hole is drilled by drilling machine means in a predetermined part of the underground structure such as the manhole, and a flange portion with a diameter larger than the through hole is provided at one end. an extension duct which is continuous with the flange, has a length greater than the depth of the through hole in the longitudinal direction, has resin mortar etc. applied to its surface, and has a threaded surface formed on the applied surface. The sleeve and the tightening member screwed into the threaded part provided on the extension duct sleeve are made of a ring and an adhesive, and one of the through holes is made of a ring and an adhesive.
Insert an extension duct sleeve between the wall surface of the through-hole and the wall surface of the through hole using adhesive, tighten the threaded part of the extension duct sleeve that protrudes from the other surface, and screw the ring into the duct. He designed the expansion opening and also the construction method.

(作 用) 本発明を前記の通シ構成したので前記の従来の技術によ
る既設マンホール等の地下構造物へのダクト増設口の形
成においての諸問題の欠点がつぎの通シ解決されたので
ある。
(Function) Since the present invention has the above-mentioned through-hole construction, the drawbacks of various problems in forming duct extension openings to underground structures such as existing manholes according to the above-mentioned conventional techniques are solved in the following way. .

1)既設マンホール等の地下構造物への増設用ダクトス
リーブを貫通する孔あけ作業が機械化され、また増設用
ダクトスリーブ周シをブロック化することにより、コン
クリート破壊、型枠作成及び設置、コンクリート打設及
び養生の工程がなくなシ作業時間の短縮を図ることがで
きる。
1) The drilling work to penetrate the duct sleeve for expansion into underground structures such as existing manholes is mechanized, and by blocking the circumference of the duct sleeve for expansion, concrete destruction, formwork creation and installation, and concrete pouring are reduced. There is no installation and curing process, and the work time can be shortened.

2)増設用ダクトスリーブの接続に接着剤を用いること
により漏水防止を図ることができる。
2) Water leakage can be prevented by using adhesive to connect the expansion duct sleeve.

3)手のみ又はライトピックハンマ等の掘削手段による
通信ケーブル及°びく体への障害防止を図ることができ
る。
3) It is possible to prevent damage to communication cables and the human body due to digging means such as hand-only or light pick hammer.

4)掘削手段によろく体破壊時の粉塵□等の発生を防ぎ
作業環境の改善を図ることができる。
4) It is possible to improve the work environment by preventing the generation of dust □ when the body is destroyed by the excavation means.

5)掘削溝内の作業時間が大幅に短縮できるため安全性
の向上を図ることができる。
5) Safety can be improved because the working time inside the excavated trench can be significantly shortened.

(実施例) 本発明の一実施例を図面とともに説明する。第1図は本
発明の実施例のダクト増設口とその施工方法説明断面図
であって、第1図(、)は削孔機械手段による開孔説明
断面図である。第1図(、)において11は削孔機械手
段であシ、2はマンホール等の側壁であシ、図にはその
一部を示した。削孔機械手段1ノの詳細は図示を省略し
たが支軸11−1上に支承移動する削孔機械手段11の
削孔具1ノー2の回転により貫通孔2−1がマンホール
等側壁2に機械的に掘削される。第1図伽)は増設用ダ
クトスリーブの挿入説明断面図である。第1図(b)に
おいて、12は増設用ダクトスリーブ、3はダクトスリ
ーブ、13は接着剤である。マンホール等側壁2に掘削
された貫通孔2−1に増設用ダクトスリーブ12が挿入
される。増設用ダクトスリーブ12は図示するようにダ
クトスリーブ3の表面は前面に貫通孔2−1の直径よ)
大なる鍔部12−1が設けられ、該鍔部12−1に連続
してねじ部12−2が長手方向にわたシ設けられ、鍔部
12−1およびねじ部12−2は金属よりなるダクトス
リーブ3の表面に樹脂モルタル等を被着して設けられて
おシ、ねじ部12−2はねじが形成されている。増設用
ダクトスリーブ12をマンホール等側壁2に設けた貫通
孔2−1に挿入する際、貫通孔2−1の壁面との間およ
び後から述べる締付は環14のマンホール等側壁2との
対向面に接着剤13を付着させである。
(Example) An example of the present invention will be described with reference to the drawings. FIG. 1 is a sectional view illustrating a duct extension opening and its construction method according to an embodiment of the present invention, and FIG. In FIG. 1(,), 11 is a drilling machine means, and 2 is a side wall of a manhole etc., a part of which is shown in the figure. Although the details of the drilling machine means 1 are not shown in the drawings, the rotation of the drilling tools 1 and 2 of the drilling machine means 11 supported and moved on the support shaft 11-1 causes the through hole 2-1 to form in the side wall 2 of the manhole, etc. Mechanically excavated. FIG. 1) is a sectional view illustrating insertion of an additional duct sleeve. In FIG. 1(b), 12 is an extension duct sleeve, 3 is a duct sleeve, and 13 is an adhesive. The expansion duct sleeve 12 is inserted into a through hole 2-1 drilled in a side wall 2 of a manhole or the like. As shown in the figure, the expansion duct sleeve 12 has a diameter of the through hole 2-1 on the front surface of the duct sleeve 3.
A large flange 12-1 is provided, a threaded portion 12-2 is provided continuously in the longitudinal direction of the flange 12-1, and the flange 12-1 and the threaded portion 12-2 are made of metal. The surface of the duct sleeve 3 is coated with resin mortar or the like, and the threaded portion 12-2 is threaded. When inserting the expansion duct sleeve 12 into the through hole 2-1 provided in the side wall 2 of the manhole, etc., the ring 14 should be tightened between the wall surface of the through hole 2-1 and the tightening described later. Adhesive 13 is applied to the surface.

第1図(c)は締付は環の取付は説明断面図である。FIG. 1(c) is a sectional view illustrating the tightening ring installation.

第1図(c)において14は締付は環であシ、締付は環
14はマンホール等側壁2の貫通孔2−1に挿入した増
設用ダクトスリーブ12の鍔部12−1のマンホール等
側壁2の他の面側に壁面を挾むように設けられ、また増
設用ダクトスリーブ12の表面のねじ部に螺合して接着
剤13とともに増設用ダクトスリーブ12をマンホール
等側壁2に固定する。締付け1114はナツト機能を有
し樹脂モルタル及びネオプレンゴム等伸縮性の材質の部
材である。
In FIG. 1(c), 14 is a tightening ring, and the tightening ring 14 is a manhole, etc. of the collar 12-1 of the extension duct sleeve 12 inserted into the through hole 2-1 of the side wall 2. It is provided on the other side of the side wall 2 so as to sandwich the wall surface, and is screwed into the threaded portion on the surface of the extension duct sleeve 12 to fix the extension duct sleeve 12 to the side wall 2 such as a manhole together with the adhesive 13. The fastener 1114 is a member having a nut function and made of a stretchable material such as resin mortar or neoprene rubber.

第3図は、本発明の実施例のダクト増設口要部の断側面
図であって、第3図(、)に増設用ダクトスリーブ12
の一部断面正面図、第3図6)は締付は環14の一部断
面正面図である。
FIG. 3 is a cross-sectional side view of the main part of the duct extension port according to the embodiment of the present invention, and FIG.
FIG. 3 (6) is a partially sectional front view of the tightening ring 14.

第4図は第3図のダクトスリーブ12及び締付は環14
断面図である。第3図(、)においてダクトスリーブ3
の側面は樹脂モルタルよりなる増設用ダクトスリーブ1
2を被着したことを示し、端部に設けた鍔部12−1は
前記貫通孔2−1より大なる直径を有するとともに、増
設用ダクトスリーブの長手方向の長さは、該貫通孔2−
1の深さより大であシ、またその表面には締付は環14
と螺合するねじ面が形成されている。第3図(、)のA
−A′断面およびB −B’断面の形状は第4図に示し
た通シである。
Figure 4 shows the duct sleeve 12 of Figure 3 and the tightening ring 14.
FIG. In Figure 3 (,), the duct sleeve 3
The side of the expansion duct sleeve 1 is made of resin mortar.
The flange 12-1 provided at the end has a larger diameter than the through hole 2-1, and the length of the extension duct sleeve in the longitudinal direction is larger than that of the through hole 2. −
The depth is greater than 1, and the surface has a tightening ring 14.
A threaded surface is formed for threading. A in Figure 3 (,)
The shapes of the -A' and B-B' sections are as shown in FIG.

(発明の効果) 以上説明した様に、本発明を実施したダクト増設口及び
その施工方法により以下に述べる様な利点がある。
(Effects of the Invention) As explained above, the duct extension port and its construction method according to the present invention have the following advantages.

1)開孔作業の機械化並びに、型枠作成・設置、コンク
リート打設及びコンクリート養生の作業工程を無くすこ
とにより大幅な作業時間の短縮ができる。又、これによ
り道路交通及び地元に与える影響を減少させることを可
能となる。
1) Work time can be significantly shortened by mechanizing hole-drilling work and eliminating the work processes of formwork creation and installation, concrete pouring, and concrete curing. This also makes it possible to reduce the impact on road traffic and local communities.

2)ブロック化した増設用ダクトスリーブと接着剤の使
用によりコンクリートの打継目からの漏水防止を可能と
なる。
2) The use of block-shaped expansion duct sleeves and adhesives makes it possible to prevent water leakage from concrete joints.

3)手ノミ又はライトビックハンマ等による既設マンホ
ール等く体破壊時の収容ケーブルへの障害防止を可能と
なる。
3) It is possible to prevent damage to the accommodation cable when an existing manhole or other structure is destroyed by a hand chisel or a light hammer.

4)手ノミ又はライトビックハンマ等による既設マンホ
ール等く体破壊時の衝撃による亀裂発生防止を可能とな
る。
4) It is possible to prevent cracks from occurring due to the impact when an existing manhole or the like is destroyed by a hand chisel or a light hammer.

5)手ノミ又はライトピックハンマ等による既設マンホ
ール等く体破壊時の粉塵等の発生防止を可能となる。
5) It is possible to prevent the generation of dust, etc. when an existing manhole, etc. is destroyed by a hand chisel or a light pick hammer.

6)掘削溝内の作業時間を機械化及びブロック化するこ
とにより大幅に短縮することを可能としたため、安全性
の向上が図れる。
6) The work time inside the excavation trench can be significantly shortened by mechanization and block formation, which improves safety.

又、本システムは通信用ケーブルを収容する管だけでな
く、電力、 CAT’V等のケーブルを収容する管と、
マンホール、ハンドホール、トウ道、キャブ等のあらゆ
る地下構造物との接続に応用できるという効果がある。
Additionally, this system not only accommodates communication cables, but also includes tubes that accommodate power, CAT'V, etc. cables.
It has the advantage that it can be applied to connections with all kinds of underground structures such as manholes, handholes, towways, and cabs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の実施例のダクト増設口とその施工方法
説明断面図、第1図(、)は削孔機械手段による開孔説
明断面図、第1図(b)は増設用ダクトスリーブの挿入
説明断面図、第1図(c)は締付は環の取付は説明断面
図、第2図は従来の管部材と既設マンホール等との接続
構造とその施工方法の説明断面図、第2図(、)はマン
ホール等側壁2の掘削手段の説明図、第2図(b)はダ
クトスリーブの取付は及び型枠の設置説明断面図、第2
図(c)はコンクリートの打設説明断面図、第2図(d
)は従来の管部材とマンホール等との接続構造断面図、
第3図は本発明の実施例のダクト増設口要部の断側面図
、第3図(、)は増設用ダクトスリーブ12の一部断面
図、第3図(b)は締付は環14の一部断面図、第4図
は第3図の増設用ダクトスリーブ12及び締付は環14
断面図、である。 1・・・掘削手段、2・・・地下構造物のマンホール等
側壁、2−1・・・貫通孔、3・・・ダクトスリーブ、
4・・・型枠、5・・・打設コンクリート、1ノ・・・
削孔機械手段、11−1・・・支軸、11−2・・・削
孔具、12・・・増設用ダクトスリーブ、12−1・・
・鍔部、12−2・・・ねじ部、13・・・接着剤、1
4・・・締付は環。 図面の浄書( 削孔機械手段による開孔説明断面図 第1図(Q) 第1図(b) 本発明の実施例のダクト増設[]とその施工方法の説明
断面図第1図(C) 第2図(b) 従来のコンクリートの打設説明断面図 第2図(C) 第2図(d) 昭和63年2月1 日
Fig. 1 is a sectional view explaining the duct extension opening and its construction method according to an embodiment of the present invention, Fig. 1 (,) is an illustrative sectional view of opening a hole by drilling machine means, and Fig. 1 (b) is a duct sleeve for extension. Figure 1(c) is a cross-sectional view for explaining the insertion of the tightening ring, Figure 2 is a cross-sectional view for explaining the connection structure between a conventional pipe member and an existing manhole, etc., and its construction method. Figure 2 (,) is an explanatory diagram of the means for excavating the side wall 2 of a manhole, etc. Figure 2 (b) is a cross-sectional diagram illustrating the installation of the duct sleeve and the installation of the formwork.
Figure (c) is a sectional view explaining concrete pouring, Figure 2 (d)
) is a cross-sectional view of the connection structure between a conventional pipe member and a manhole, etc.
FIG. 3 is a cross-sectional side view of the main part of the duct extension port according to the embodiment of the present invention, FIG. FIG. 4 is a partial sectional view of the expansion duct sleeve 12 and tightening ring 14 shown in FIG. 3.
It is a sectional view. DESCRIPTION OF SYMBOLS 1... Excavation means, 2... Side wall of an underground structure such as a manhole, 2-1... Through hole, 3... Duct sleeve,
4... Formwork, 5... Pouring concrete, 1...
Hole drilling machine means, 11-1... Support shaft, 11-2... Hole drilling tool, 12... Duct sleeve for expansion, 12-1...
・Flame part, 12-2... Threaded part, 13... Adhesive, 1
4...Tighten with a ring. Printing of the drawings (Explanatory cross-sectional view of drilling holes by drilling machine means Fig. 1 (Q) Fig. 1 (b) Explanatory cross-sectional view of the duct extension according to the embodiment of the present invention [] and its construction method Fig. 1 (C) Figure 2 (b) Cross-sectional diagram explaining conventional concrete pouring Figure 2 (C) Figure 2 (d) February 1, 1988

Claims (2)

【特許請求の範囲】[Claims] (1)既設のマンホール等地下構造物の所定部位に貫通
孔を設け、該貫通孔に通信ケーブル等を内挿する管部材
を設けるように形成したダクト増設口において、 前記マンホール等地下構造物の所定部位に削孔機械手段
により削孔した貫通孔と、 一端に該貫通孔より大なる直径の鍔部を有するとともに
、該鍔部に連続して長手方向に該貫通孔の深さより大な
る長さを有し、樹脂モルタル等を表面に被着し且つその
被着面にねじ切り面を形成した増設用ダクトスリーブと
、 前記増設用ダクトスリーブに設けたねじ部に螺合する締
付け環と、 接着剤とよりなり、 前記貫通孔の一面より、該貫通孔の壁面との間に接着剤
を介して増設用ダクトスリーブを挿入し、他の面に突出
した該増設用ダクトスリーブのねじ部を締付け環で螺合
して構成したことを特徴とするダクト増設口。
(1) At a duct extension opening formed by providing a through hole at a predetermined location of an existing underground structure such as a manhole and installing a pipe member for inserting a communication cable etc. into the through hole, a through hole drilled in a predetermined location by a drilling machine; a flange having a diameter larger than the through hole at one end; a duct sleeve for expansion, the surface of which is coated with resin mortar or the like and a threaded surface formed on the surface thereof; a tightening ring that is screwed into the threaded portion provided on the duct sleeve for expansion; Insert an extension duct sleeve from one side of the through hole with the wall surface of the through hole via an adhesive, and tighten the threaded portion of the extension duct sleeve that protrudes from the other side. A duct extension opening characterized by being configured by screwing together a ring.
(2)既設のマンホール等地下構造物の所定部位に貫通
孔を設け、該貫通孔に通信ケーブル等を内挿する管部材
を設けるように形成したダクト増設口の施工方法におい
て、 前記マンホール等の地下構造物の所定部位に貫通孔を削
孔機械手段により削孔し、 該貫通孔に一端に該貫通孔より大なる直径の鍔を有する
とともに該鍔に連続して長手方向に、該貫通孔の深さよ
り大なる長さを有し、表面にレジンモルタル等被着させ
、且つその被着面にねじ切り面を形成した増設用ダクト
スリーブを、該貫通孔の壁面との間に接着剤を介して該
貫通孔の一端より挿入貫通し、他端の該増設用ダクトス
リーブの突出部に締付環を螺合して構成したことを特徴
とするダクト増設口の施工方法。
(2) A method for constructing a duct expansion opening in which a through hole is provided in a predetermined part of an existing underground structure such as a manhole, and a pipe member into which a communication cable, etc. is inserted is provided in the through hole, A through hole is drilled in a predetermined part of the underground structure by a drilling machine, and the through hole has a flange having a diameter larger than that of the through hole at one end, and the through hole is continuous with the flange in the longitudinal direction. An extension duct sleeve having a length greater than the depth of the through hole, whose surface is coated with resin mortar, etc., and whose threaded surface is formed, is placed between it and the wall surface of the through hole through an adhesive. A method for constructing a duct extension opening, characterized in that the opening is inserted through the through hole from one end thereof, and a tightening ring is screwed onto a protrusion of the extension duct sleeve at the other end.
JP62261625A 1987-10-19 1987-10-19 Duct extension and its construction method Expired - Fee Related JP2581933B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62261625A JP2581933B2 (en) 1987-10-19 1987-10-19 Duct extension and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62261625A JP2581933B2 (en) 1987-10-19 1987-10-19 Duct extension and its construction method

Publications (2)

Publication Number Publication Date
JPH01105821A true JPH01105821A (en) 1989-04-24
JP2581933B2 JP2581933B2 (en) 1997-02-19

Family

ID=17364490

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62261625A Expired - Fee Related JP2581933B2 (en) 1987-10-19 1987-10-19 Duct extension and its construction method

Country Status (1)

Country Link
JP (1) JP2581933B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2438812B (en) * 2005-03-11 2010-11-03 Gm Rail Services Ltd Improvements to cabling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2438812B (en) * 2005-03-11 2010-11-03 Gm Rail Services Ltd Improvements to cabling

Also Published As

Publication number Publication date
JP2581933B2 (en) 1997-02-19

Similar Documents

Publication Publication Date Title
JP3046548B2 (en) Fixing material injection method
JPH01105821A (en) Increase of duct and execution thereof
KR100501747B1 (en) Sealing constructing method for preventing epoxy leakage when attaching steel plates on by anchor bolts and apparatus thereof
JP3030012B2 (en) Non-widening steel pipe tip receiving drilling method
JP2000297592A (en) Removing method for natural ground reinforcing steel pipe
JP2818807B2 (en) Construction method of duct extension in manhole
GB2153892A (en) A wall tie, a method of tying the leaves of a cavity wall and a cavity wall incorporating a tie
JP2003155887A (en) Immersion construction method of shaft
KR200240012Y1 (en) Section steel protection
JP2000027211A (en) Connection reinforcing method for existing pipe
JPS6272889A (en) Method for tightening jaxtaposed cavity by lock anchor
JPS5837386A (en) Method of clamping propulsive pipe
JPS6261835B2 (en)
JPH039974B2 (en)
JPS61162644A (en) Construction of sewage main pipe connecting pipe
JPH0452316A (en) Permanent ground anchor and its installation
KR200210069Y1 (en) Removal nailing device in excavation work
JPH061498U (en) Expansion packer for backfill injection
JPH0224500A (en) Anchoring of lock bolt
JPS60199123A (en) Water-proofing work for concrete wall
JPS6348115A (en) Method of connecting underground conduit to manhole
JPS6314138B2 (en)
JPH0551926A (en) Constructing method for steel pipe sheet pile wall
JPS587025A (en) Install method for anchor
JPS61191794A (en) Ioint structure of casing

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees