JP7492399B2 - Grade management device, grade management method, and grade management program - Google Patents
Grade management device, grade management method, and grade management program Download PDFInfo
- Publication number
- JP7492399B2 JP7492399B2 JP2020131140A JP2020131140A JP7492399B2 JP 7492399 B2 JP7492399 B2 JP 7492399B2 JP 2020131140 A JP2020131140 A JP 2020131140A JP 2020131140 A JP2020131140 A JP 2020131140A JP 7492399 B2 JP7492399 B2 JP 7492399B2
- Authority
- JP
- Japan
- Prior art keywords
- person
- charge
- month
- hours
- planned
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007726 management method Methods 0.000 title claims description 60
- 238000012545 processing Methods 0.000 claims description 64
- 230000006872 improvement Effects 0.000 claims description 49
- 238000000034 method Methods 0.000 claims description 42
- 230000008569 process Effects 0.000 claims description 34
- 230000007704 transition Effects 0.000 claims description 22
- 238000011156 evaluation Methods 0.000 claims description 21
- 230000010365 information processing Effects 0.000 claims description 8
- 238000012937 correction Methods 0.000 claims 3
- 238000012986 modification Methods 0.000 claims 1
- 230000004048 modification Effects 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 18
- 230000004044 response Effects 0.000 description 13
- 238000004891 communication Methods 0.000 description 7
- 230000006870 function Effects 0.000 description 7
- 238000012546 transfer Methods 0.000 description 7
- 238000012552 review Methods 0.000 description 6
- 238000004590 computer program Methods 0.000 description 4
- 230000001934 delay Effects 0.000 description 4
- 230000007306 turnover Effects 0.000 description 4
- 238000004364 calculation method Methods 0.000 description 3
- 238000000605 extraction Methods 0.000 description 2
- 230000003287 optical effect Effects 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 238000007792 addition Methods 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000006735 deficit Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 230000001052 transient effect Effects 0.000 description 1
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
本発明は、成績管理装置、成績管理方法、及び成績管理プログラムに関する。 The present invention relates to a grade management device, a grade management method, and a grade management program.
プロジェクトの進捗を管理するためには、担当者の作業の進捗を評価する必要がある。従来、担当者の作業の進捗を評価するシステムとして、例えば、特許文献1がある。 To manage the progress of a project, it is necessary to evaluate the progress of the work of the person in charge. Conventionally, for example, Patent Document 1 discloses a system for evaluating the progress of the work of the person in charge.
しかしながら、特許文献1では、プロジェクトの収益がアサインやプロダクトマネージャー(以下、「PM」と省略する場合がある)に起因するものなのか、作業担当者の作業進捗や効率に起因するものかをそれぞれ区別した指標にて明確に捉えられるようにすることに関して何等記載されていない。 However, Patent Document 1 does not state anything about clearly identifying whether project revenue is due to the assignment or product manager (hereinafter sometimes abbreviated as "PM"), or due to the work progress and efficiency of the workers, using indicators that distinguish between the two.
本発明は、上記に鑑みてなされものであり、プロジェクトの収益がプロダクトマネージャーに起因するものなのか、作業担当者の作業進捗や効率に起因するものなのかをそれぞれ区別した指標にて明確に捉えることが可能な成績管理装置、成績管理方法、及び成績管理プログラムを提供することを目的とする。 The present invention has been made in consideration of the above, and aims to provide a performance management device, a performance management method, and a performance management program that can clearly determine whether the profits of a project are attributable to the product manager or to the work progress and efficiency of the workers using indicators that distinguish between the two.
上述した課題を解決し、目的を達成するために、本発明は、制御部を備えた成績管理装置であって、対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力処理手段と、各担当者の月毎の作業時間を含む日報情報を入力する日報入力処理手段と、前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高と、プロジェクトマネージャーの各月の出来高とを含む月次推移表を出力する月次推移表出力手段と、を備えたことを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention is a performance management device equipped with a control unit, characterized in that it comprises: execution budget input processing means for inputting execution budget information for a target project, created by a project manager, including the scheduled hours for each person in charge each month; daily report input processing means for inputting daily report information including the monthly working hours of each person in charge; and monthly trend table output means for outputting a monthly trend table including the amount of work completed according to the monthly work schedule of each person in charge and the amount of work completed by the project manager each month, based on the execution budget information and the daily report information.
また、本発明の一態様によれば、前記予定時間は、標準工数時間から算出した時間であることにしてもよい。 Furthermore, according to one aspect of the present invention, the scheduled time may be calculated from standard labor hours.
また、本発明の一態様によれば、前記実行予算入力処理手段は、前記実行予算情報の担当者の予定時間を修正可能に構成されていることにしてもよい。 According to one aspect of the present invention, the working budget input processing means may be configured to be able to modify the scheduled time of the person in charge of the working budget information.
また、本発明の一態様によれば、担当者の出来高は、契約額×各月の作業時間/実施後の各月の予定時間で算出する投入出来高、進捗出来高-投入出来高で算出する投入改善高、投入改善高/進捗出来高×100で算出する投入改善率、及び管理帳票などで、確定月までは進捗出来高、翌月以降は予定出来高で、最終的な着地予想を捉える指標である着地出来高の少なくとも1つを含むことにしてもよい。 According to one aspect of the present invention, the output of the person in charge may include at least one of the input output calculated by the contract amount x working hours for each month / planned hours for each month after implementation, the input improvement amount calculated by the progress output - the input output, the input improvement rate calculated by the input improvement amount / progress output x 100, and the final output, which is an indicator of the final forecast, with the progress output being the finalized output until the fixed month and the planned output from the following month onwards, as shown in the management report, etc.
プロジェクトマネージャーの出来高は、契約額×計画時の各月の予定時間/総予定時間で算出する予定出来高、契約額×実施後の各月の予定時間/総予定時間で算出する進捗出来高、(進捗出来高-予定出来高)/予定出来高×100で算出する進捗改善率、及び管理帳票などで、確定月までは進捗出来高、翌月以降は予定出来高で、最終的な着地予想を捉える指標である着地出来高の少なくとも1つを含むことにしてもよい。 The project manager's output may include at least one of the planned output, calculated by the contract amount x the planned hours for each month at the time of planning/total planned hours, the progress output, calculated by the contract amount x the planned hours for each month after implementation/total planned hours, the progress improvement rate, calculated by (progress output - planned output)/planned output x 100, and the final output, which is an indicator that captures the final forecast, with progress output up to the final month and planned output from the following month onwards, in the management report, etc.
また、上述した課題を解決し、目的を達成するために、本発明は、制御部を備えた情報処理装置に実行させるための成績管理方法であって、前記制御部において実行される、対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力工程と、各担当者の月毎の作業時間を含む日報情報を入力する日報入力工程と、前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高と、プロジェクトマネージャーの各月の出来高と、を含む月次推移表を出力する月次推移表出力工程と、を含むことを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention is a performance management method to be executed by an information processing device equipped with a control unit, and is characterized by including the following steps executed by the control unit: an execution budget input step for inputting execution budget information for a target project, the execution budget information including the scheduled hours for each person in charge each month, created by the project manager; a daily report input step for inputting daily report information including the monthly working hours of each person in charge; and a monthly trend table output step for outputting a monthly trend table including the amount of work completed according to the monthly work schedule of each person in charge and the amount of work completed by the project manager each month, based on the execution budget information and the daily report information.
また、上述した課題を解決し、目的を達成するために、本発明は、制御部を備えた情報処理装置に実行させるための成績管理プログラムであって、前記制御部において、対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力工程と、各担当者の月毎の作業時間を含む日報情報を入力する日報入力工程と、前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高と、プロジェクトマネージャーの各月の出来高と、を含む月次推移表を出力する月次推移表出力工程と、をコンピュータに実行させるための成績管理プログラムであることを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention is a performance management program to be executed by an information processing device having a control unit, and the control unit executes the following steps on a computer: an execution budget input process for inputting execution budget information for a target project, including the planned hours for each person in charge each month, created by the project manager; a daily report input process for inputting daily report information including the monthly working hours of each person in charge; and a monthly trend table output process for outputting a monthly trend table including the amount of work completed according to the monthly work schedule of each person in charge and the amount of work completed by the project manager for each month, based on the execution budget information and the daily report information.
本発明によれば、プロジェクトの収益がプロダクトマネージャーに起因するものなのか、作業担当者の作業進捗や効率に起因するものなのかをそれぞれ区別した指標にて明確に捉えることが可能になるという効果を奏する。 The present invention has the effect of making it possible to clearly determine whether the profits of a project are attributable to the product manager or to the progress and efficiency of the workers using indicators that distinguish between the two.
本発明の実施形態を図面に基づいて詳細に説明する。なお、本発明は本実施の形態により限定されるものではない。 The embodiment of the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to this embodiment.
[1.概要]
人手不足や働き方改革の対応や労働市場の流動性の高まりに伴い、生産性の効率化を図りつつも、アサインなど会社や案件のPMの評価・責任範囲と、作業効率など個人別の評価・責任範囲を明確化する必要が高まっている。
[1. Overview]
In response to labor shortages, work style reforms, and increased fluidity in the labor market, there is an increasing need to clarify the evaluation and scope of responsibility of PMs for companies and projects, such as assignments, as well as individual evaluation and scope of responsibility, such as work efficiency, while also striving to improve productivity efficiency.
これまでの案件別予算の管理では、原価目線での作業工数の低減と、売上目線での会社貢献が分かれて管理されがちであり、案件の収益がアサインやPMに起因するものなのか、作業担当者の作業進捗や効率に起因するものなのか、明確に判別することは困難であった。 Previously, project-specific budget management tended to separate the reduction in labor hours from a cost perspective from the contribution to the company from a sales perspective, making it difficult to clearly determine whether the revenue from a project was due to the assignment and PM, or the progress and efficiency of the individual workers.
そこで、本実施の形態では、それらをルール化した標準工数時間を基づく実行予算の見積もりを、PMが行うことにより、案件の全体進捗や契約上の売上計上タイミング、サービス形態にかかわらず、個人別の予定作業時間ベースでの出来高進捗管理が算出できるようになり、管理会計上への反映、成績評価ができるようになった。 Therefore, in this embodiment, the PM estimates the working budget based on the standard labor hours that have been regulated, and it becomes possible to calculate the progress management of the completed work volume based on the individual's planned working hours, regardless of the overall progress of the project, the timing of revenue recognition under the contract, or the type of service, and this can be reflected in management accounting and performance evaluation.
すなわち、本実施の形態では、案件の収益がアサインやPMに起因するものなのか、作業担当者の作業進捗や効率に起因するものか、それぞれ区別した指標にて明確に捉えられるようにした。 In other words, in this embodiment, it is possible to clearly grasp whether the revenue of a project is due to the assignment or PM, or due to the work progress and efficiency of the worker, using indicators that distinguish between the two.
本実施の形態では、従来の案件別予算管理手法を踏襲しつつも、標準工程数時間の当初計画と、毎月の実績の結果反映と翌月以降の予定見直しをルール化し、管理会計に反映させることで、PM管理者の指標と、作業担当者の指標を分けて捉え、それぞれに対して具体的な対策を行えるようになった。 In this embodiment, while following the conventional method of project-specific budget management, rules are established for the initial planning of standard process hours, reflection of monthly actual results, and review of plans for the following month and beyond, and these are reflected in management accounting, making it possible to separate the indicators of the PM manager and the indicators of the workers and take specific measures for each.
また、本実施の形態では、進捗遅れや作業効率の指標を分けて捉え、それぞれに対して具体的な対策を行えるようになった。進捗遅れや作業効率の改善度合いなどが、具体的にどのくらい売上額として影響しているかを把握できるようになった。 In addition, in this embodiment, the indicators of progress delays and work efficiency can be captured separately, and specific measures can be taken for each. It is now possible to grasp the specific impact that progress delays and the degree of improvement in work efficiency have on sales figures.
また、本実施の形態では、従来、技術担当からの原価視点での案件予算管理では、作業効率化が原価低減につながっても、売上回転率の向上に繋がりにくかったため、売上額から予算作業時間を加味して、出来高として指標に組み込むことで、作業効率化と売上見込みを別々に捉えて、売上規模と回転率の向上に繋げられるようにした。 In addition, in the past, in project budget management from the perspective of cost from the technical staff, even if work efficiency led to cost reduction, it was difficult to connect it to an improvement in sales turnover. Therefore, by taking into account the budgeted work time from the sales amount and incorporating it into the indicator as the amount of work completed, work efficiency and sales forecasts can be captured separately, which can lead to an improvement in sales scale and turnover.
具体的には、本実施の形態のポイントは、以下の(1)~(4)である。 Specifically, the key points of this embodiment are (1) to (4) below.
(1)PMが月初(作業開始前を含む)に、案件別の実行予算計画を、標準的な作業効率で人別に予定工数時間を見立てる。実際には人によって、作業効率が異なるので、作業結果後では、それら差異が、PMの予算計画での甘さなのか、個人の効率の問題なのかが、分からない。予算計画で、それら個人の効率性を排除して標準工数時間を見立てる必要がある。 (1) At the beginning of the month (including before work begins), the PM creates an execution budget plan for each project, estimating the planned man-hours for each person based on standard work efficiency. In reality, work efficiency differs from person to person, so after the work is completed, it is not clear whether these differences are due to laxity in the PM's budget plan or a problem with individual efficiency. It is necessary to estimate standard man-hours by eliminating the efficiency of individuals in the budget plan.
標準的な作業効率での見立て精度があがることにより、案件収支や担当者の作業負荷管理の精度向上が見込まれる。差異の原因が、個人の作業効率の問題なのか、PMの見立ての甘さの問題なのか、傾向が掴めるようになる。 By improving the accuracy of assessments based on standard work efficiency, it is expected that the accuracy of project income and expenditures and the management of the workload of individuals in charge will improve. It will become possible to grasp trends, such as whether the cause of the discrepancy is a problem with individual work efficiency or a problem with the PM's inadequate assessment.
ここで、「案件収支」は、必要な作業内容を正しく捉えられれば、どのアサイン担当者であっても、赤字にならずに案件完了となる(PMの責任範囲)。「作業負荷管理」は、予定作業内容を標準的な作業効率内で実施すれば、進捗遅れが発生せずに、残業も発生しない(アサイン管理の責任範囲)。 Here, "project income and expenditure" means that if the necessary work content is correctly understood, then the project will be completed without a deficit regardless of who is assigned (responsibility of the PM). "Workload management" means that if the planned work content is carried out within the standard work efficiency, there will be no delays in progress and no overtime will be required (responsibility of assignment management).
実際のアサイン作業は、各個人の効率、適性などを考慮して、標準工数作業が就業時間を超えつつも、実際には就業時間内に完了できるバランスを取っていく。これにより、アサインによる労働資源の最適化を行うことができる。 The actual work assignment takes into account each individual's efficiency and aptitude, and strikes a balance so that the standard labor-hour work exceeds working hours, but can actually be completed within working hours. This makes it possible to optimize labor resources through assignment.
(2)PMが月末(毎月の作業進捗結果が判明した後)に、案件別の実行予算計画で、作業進捗結果に伴って当月の予定工数時間を変更する。人別の予定工数時間は、「月初」に人別の作業予定内容×標準工数時間とし、「月末」に人別の作業結果内容×標準工数時間とする。 (2) At the end of the month (after the monthly work progress results are known), the PM changes the planned man-hours for that month in the execution budget plan for each project based on the work progress results. The planned man-hours for each person are calculated as the planned work content for each person x the standard man-hours at the beginning of the month, and as the work results for each person x the standard man-hours at the end of the month.
案件全体の進捗率を管理する仕組みや手法は、これまでもあったが、これでは個人別のアサインや作業予定、進捗に結び付かなかった。 There have been systems and methods for managing the progress rate of an entire project, but these were not linked to individual assignments, work schedules, or progress.
そこで、人別の予算時間を毎月月初と月末に見直していくことで、個人別の作業予定や進捗に反映されて、翌月以降の案件別の計画にも反映されやすい。これは、当月未消化の作業は、翌月以降に見込むか、別途アサイン追加を行わなければ、当初予算との辻褄が明確に合わなくなるためである。 Therefore, by reviewing the budgeted time for each person at the beginning and end of each month, it is reflected in the work schedule and progress of each individual, and is also likely to be reflected in the project-specific plans for the following month and beyond. This is because unless the work that is not completed in the current month is estimated for the following month or later, or a separate assignment is added, it will not clearly match up with the initial budget.
(3)各作業内容が、最終的に契約額(売上額)として、予定・実績共に、どのくらい会社数字に寄与していくのかを捉えられるようにする。 (3) Make it possible to understand how much each task will ultimately contribute to company figures, both planned and actual, as the contract amount (sales amount).
作業効率だけでは、原価管理での効率化はできても、売上管理としての向上に結び付きにくい(作業部門のPMが原価だけを意識して、売上を意識しない傾向の業界などもある)。各案件での難易度、契約額、利益率などを個人でコントロールできない要素を少なくしつつ、統一的な成績評価を行い、会社としての売上向上につなげる必要がある。 Work efficiency alone may improve cost management efficiency, but it is difficult to link it to improved sales management (there are also industries where PMs in the work department tend to only think about costs and not sales). It is necessary to reduce factors that individuals cannot control, such as the difficulty of each project, contract amount, and profit margin, while conducting unified performance evaluations and linking them to improved sales for the company.
各案件での契約額を作業担当者の作業予定時間で均等に按分する。今回は労働集約型のビジネスモデルを想定。それ以外では、別の指標で按分することも可能である。 The contract amount for each project is apportioned equally based on the planned working hours of each worker. In this example, we are assuming a labor-intensive business model. In other cases, it is also possible to apportion based on a different indicator.
(4)個人毎に、作業進捗の度合いと効率性を分けて明確に捉えられるようにする。与えられた仕事に対して、効率よく、より少ない時間で実施することと、効率性は標準だが、より多くの仕事をこなすことの評価視点は異なる(どちらが良いというものではない)。
これらを数値化して、同じ土俵で評価できるようにする必要があった。
(4) Separate and clearly grasp the degree of work progress and efficiency for each individual. The evaluation perspectives for carrying out a given task efficiently and in less time and for doing more work while efficiency is the standard are different (neither is better).
It was necessary to quantify these so that they could be evaluated on an equal footing.
個人別の予実差異を把握することで、個人ごとの効率化の把握、向上につなげる(効率性)。契約額(出来高)に換算することで、進捗度合い・売上回転率の向上につなげる(案件進捗の寄与)。 By understanding the difference between the actual and forecasted results for each individual, it is possible to understand and improve the efficiency of each individual (efficiency). By converting this into the contract amount (output), it is possible to improve the progress rate and sales turnover rate (contribution to project progress).
本実施の形態の用語及び管理指標を説明する。 Explain the terminology and management indicators used in this embodiment.
「実行予算」は、案件ごとに、PMが各月の作業時間などを見積もり、収支計画を立てることである。毎月見直しも実施する。管理帳票などで、確定月までは実績値、翌月以降は予算値で着地予想を捉えるのが一般的である。
「標準工数時間」は、作業内容に応じて、標準的な作業効率の人が完了までにかかる工数時間である。
「予定時間」は、作業内容に応じて、標準工数時間から算出した完了までにかかる予定時間である。
「日報」は、各個人が日々の作業結果として、どの案件にどれくらい従事したかを作業時間として入力する。
「作業時間」は、日報で入力する案件毎に従事した時間である。
「契約額」は、受注した契約額である。完了時に売上額と同額となる。
「予定出来高(PM指標)」は、契約額×計画時の各月の予定時間/総予定時間で算出する。各予定時間に応じて、どのくらい売上に寄与するかの指標である。
「進捗出来高(PM指標)」は、契約額×実施後の各月の予定時間/総予定時間で算出する。各予定時間に応じて、どのくらい売上に寄与したかの指標である。
「進捗改善率(PM指標)」は、(進捗出来高-予定出来高)/予定出来高×100で算出する。予定していた作業予定に対して、どれくらい進捗して、売上に寄与したかの指標である。
「着地出来高(PM指標&個人指標)」は、管理帳票などで、確定月までは進捗出来高、翌月以降は予定出来高で、最終的な着地予想を捉える指標である。期を跨いで売上が翌期の案件などは、制度会計上は売上0だが、出来高で今期の売上評価が可能になる。
「投入出来高(個人指標)」は、契約額×各月の作業時間/実施後の各月の予定時間で算出する。進捗した作業内容に対して、どのくらいの作業時間で完了させたかの指標である。少ない方が良い。
「投入改善高(個人指標)」は、進捗出来高-投入出来高で算出する。個人の作業効率によって、どのくらい売上高視点で改善したかの指標。大きい方が良い。
「投入改善率(個人指標)」は、投入改善高/進捗出来高×100で算出する。個人の作業効率によって、どのくらい売上高視点で改善したかの指標である。大きい方が良い。
The "working budget" is a plan in which the PM estimates the work hours for each month for each project and creates an income and expenditure plan. It is also reviewed monthly. It is common to use management forms to capture the expected results using actual values up until the final month, and budget values from the following month onwards.
"Standard man-hours" refers to the number of man-hours required for a person with standard work efficiency to complete a task, depending on the task content.
"Scheduled time" is the estimated time required to complete a task, calculated from the standard man-hours, depending on the task content.
In the "Daily Report," each individual enters the results of their daily work, including how much time they spent on each project.
"Working hours" is the time spent on each project entered in the daily report.
"Contract amount" is the contract amount received. It will be equal to the sales amount upon completion.
"Planned output (PM index)" is calculated by multiplying the contract amount by the planned hours for each month at the time of planning/total planned hours. It is an index of how much each planned hour contributes to sales.
"Progress volume (PM index)" is calculated by multiplying the contract amount by the planned time for each month after implementation/total planned time. It is an index of how much each planned time contributed to sales.
The "progress improvement rate (PM index)" is calculated as follows: (progress amount - planned amount) / planned amount x 100. It is an index of how much progress has been made against the planned work schedule and how much it has contributed to sales.
"Landing volume (PM index & individual index)" is an index that captures the final forecast, with progress volume up to the final month in management reports, and planned volume from the following month onwards. For projects that cross over into the next term and have sales for the next term, sales are zero in the accounting system, but it is possible to evaluate the sales for the current term based on the volume.
"Input output (individual indicator)" is calculated by the contract amount x the working hours for each month / the planned hours for each month after implementation. It is an indicator of how much work time was required to complete the progress of the work. The less the better.
"Input improvement amount (individual index)" is calculated by subtracting the input amount from the progress amount. It is an index of how much improvement has been achieved in terms of sales due to the work efficiency of an individual. The larger the better.
"Input improvement rate (individual index)" is calculated by: Input improvement amount / Progress output amount x 100. It is an index of how much improvement in sales has been achieved through individual work efficiency. The higher the better.
図1及び図2は、本実施の形態の管理モデルを示す図である。図1は、プロジェクト別の出来高照会画面イメージを示す図である。図1において、抽出条件は、会計年月「2019/04」、プロジェクトNO「P001~P002」であり、表示結果は、プロジェクトNO(P001,P002)毎に、契約額、総予定時間、社員、社員別総予定時間、予定出来高のデータを示している。 Figures 1 and 2 are diagrams showing the management model of this embodiment. Figure 1 is a diagram showing an image of the progress inquiry screen by project. In Figure 1, the extraction conditions are the accounting year and month "2019/04" and the project number "P001-P002", and the display results show data on the contract amount, total planned hours, employees, total planned hours by employee, and planned progress for each project number (P001, P002).
図2は、人別の出来高照会画面イメージを示す図である。図2において、抽出条件は、会計年月「2019/04」、社員「田中、鈴木、佐藤」であり、表示結果は、社員(田中、鈴木、佐藤)毎に、プロジェクトNO、契約額、総予定時間、社員別総予定時間、予定出来高のデータを示している。 Figure 2 shows an example of the screen for checking the amount of work done by person. In Figure 2, the extraction conditions are the accounting year and month "2019/04" and employees "Tanaka, Suzuki, Sato", and the display results show the project number, contract amount, total planned hours, total planned hours by employee, and planned amount of work done for each employee (Tanaka, Suzuki, Sato).
[2.構成]
図3を参照して、本実施の形態に係る成績評価装置構成の一例について説明する。図3は、本実施の形態に係る成績管理装置100の構成の一例を示すブロック図である。
2. Configuration
An example of the configuration of the grade evaluation device according to the present embodiment will be described with reference to Fig. 3. Fig. 3 is a block diagram showing an example of the configuration of the grade management device 100 according to the present embodiment.
図3において、成績管理装置100は、例えば、ワークステーションやパーソナルコンピュータでもよい。成績管理装置100は、制御部102と通信インターフェース部104と記憶部106と入出力インターフェース部108と、を備えている。成績管理装置100が備えている各部は、任意の通信路を介して通信可能に接続されている。
In FIG. 3, the grade management device 100 may be, for example, a workstation or a personal computer. The grade management device 100 includes a control unit 102, a communication interface unit 104, a memory unit 106, and an input/
通信インターフェース部104は、ルータ等の通信装置および専用線等の有線または無線の通信回線を介して、成績管理装置100をネットワーク300に通信可能に接続する。通信インターフェース部104は、他の装置と通信回線を介してデータを通信する機能を有する。ここで、ネットワーク300は、成績管理装置100とサーバ200や端末400・・・とを相互に通信可能に接続する機能を有し、例えばインターネットやLAN(Local Area Network)等である。端末400・・・は、PMや社員(担当者)が使用するデスクトップPC、ラップトップPC、タブレット等である。
The communication interface unit 104 communicatively connects the grade management device 100 to the
入出力インターフェース部108には、入力装置112および出力装置114が接続されている。出力装置114には、モニタ(家庭用テレビを含む)の他、スピーカやプリンタを用いることができる。入力装置112には、キーボード、マウス、および、マイクの他、マウスと協働してポインティングデバイス機能を実現するモニタを用いることができる。なお、以下では、出力装置114をモニタ114として記載する場合がある。
An input device 112 and an output device 114 are connected to the input/
記憶部106には、各種のデータベース、テーブル、および、ファイルなどが格納され
る。記憶部106には、OS(Operating System)と協働してCPU(Central Processing Unit)に命令を与えて各種処理を行うためのコンピュータプログラムが記録される。記憶部106として、例えば、RAM(Random Access Memory)・ROM(Read Only Memory)等のメモリ装置、ハードディスクのような固定ディスク装置、フレキシブルディスク、および、光ディスク等を用いることができる。また、記憶部106は、データファイル106aを備えている。
The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs for cooperating with an operating system (OS) to give commands to a central processing unit (CPU) to perform various processes. As the storage unit 106, for example, a memory device such as a random access memory (RAM) or a read only memory (ROM), a fixed disk device such as a hard disk, a flexible disk, an optical disk, and the like can be used. The storage unit 106 also includes a data file 106a.
データファイル106aは、契約情報、実行予算情報、及び日報情報等の各種データを格納するためのファイルである。契約情報は、プロジェクトNOと契約金額のデータを含んでいてもよい(図5参照)。実行予算情報は、プロジェクトNO、社員名、年月、及び予定時間のデータを含んでいてもよい(図5参照)。日報情報は、プロジェクトNO、社員名、年月、作業時間のデータを含んでいてもよい(図7参照)。 Data file 106a is a file for storing various data such as contract information, working budget information, and daily report information. Contract information may include data on project number and contract amount (see FIG. 5). Working budget information may include data on project number, employee name, year and month, and scheduled time (see FIG. 5). Daily report information may include data on project number, employee name, year and month, and working hours (see FIG. 7).
制御部102は、成績管理装置100を統括的に制御するCPU等である。制御部102は、OS等の制御プログラム・各種の処理手順等を規定したプログラム・所要データなどを格納するための内部メモリを有し、格納されているこれらのプログラムに基づいて種々の情報処理を実行する。制御部102は、機能概念的に、契約入力処理部102aと、実行予算入力処理部102bと、日報入力処理部102cと、出来高照会処理部102dと、仕訳連携処理部102eと、月次推移表出力部102fとを備えている。
The control unit 102 is a CPU or the like that controls the performance management device 100. The control unit 102 has an internal memory for storing control programs such as an OS, programs that define various processing procedures, required data, etc., and executes various information processing based on these stored programs. In terms of function, the control unit 102 includes a contract
契約入力処理部102aは、例えば、モニタ114に表示される不図示の入力画面上でのオペレータ等の操作に応じて、契約情報を入力してデータファイル106aに登録する。
The contract
実行予算入力処理部102bは、例えば、モニタ114に表示される不図示の入力画面上での操作やPMの端末400の操作に応じて、対象のプロジェクトについて、PMが作成した、社員毎の各月の予定時間を含む実行予算情報を入力して、データファイル106aに登録する。実行予算入力処理部102bは、実行予算情報の担当者の予定時間を修正可能に構成されていることにしてもよい。また、月初(1回目)は、予定作業内容×標準工数時間から予定時間を算出してもよい。月末に見直しを行い、月末(2回目)は、(当月)実際作業内容×標準工数時間から予定時間を算出してもよい。 The working budget input processing unit 102b inputs working budget information for the target project, including the planned hours for each employee for each month, created by the PM, in response to, for example, operations on an input screen (not shown) displayed on the monitor 114 or operations on the PM's terminal 400, and registers it in the data file 106a. The working budget input processing unit 102b may be configured to be able to modify the planned hours of employees in the working budget information. In addition, at the beginning of the month (first time), the planned hours may be calculated from the planned work content x standard labor hours. A review is performed at the end of the month, and at the end of the month (second time), the planned hours may be calculated from the actual work content (of the month) x standard labor hours.
日報入力処理部102cは、例えば、モニタ114に表示される不図示の入力画面上での操作や担当者の端末400の操作に応じて、プロジェクトNO、社員名、年月、作業時間のデータを含む日報情報を入力してデータファイル106aに登録する。
The daily report input processing unit 102c inputs daily report information including project number, employee name, year and month, and working hours in response to, for example, operations on an input screen (not shown) displayed on the monitor 114 or operations on the
出来高照会処理部102dは、例えば、モニタ114に表示される不図示の照会画面上での操作に応じて、データファイル106aに登録された実行予算情報及び日報情報を参照して、対象のプロジェクトについて、全体(PM)についての、総予定時間、対象の年月の時間、出来高と、各社員の予定時間、予定出来高、進捗時間、投入出来高、作業時間を含む照会結果を作成して表示出力する。
The output
仕訳連携処理部102eは、例えば、モニタ114に表示される不図示の仕訳連携画面上での操作に応じて、データファイル106aに登録された実行予算情報及び日報情報を参照して、対象のプロジェクトについて社員毎の各月の仕訳を作成して表示出力する。 The accounting link processing unit 102e, for example, in response to an operation on an accounting link screen (not shown) displayed on the monitor 114, references the working budget information and daily report information registered in the data file 106a, creates and displays accounting entries for each employee for each month for the target project.
月次推移表出力部102fは、例えば、モニタ114に表示される不図示の月次推移表出力画面上での操作に応じて、データファイル106aに登録された実行予算情報及び日報情報を参照して、対象のプロジェクトについて、各社員の月毎の作業予定に応じた出来高と、PMの各月の出来高を帳票形式の月次推移表として表示出力する。 For example, in response to an operation on a monthly trend table output screen (not shown) displayed on the monitor 114, the monthly trend table output unit 102f references the working budget information and daily report information registered in the data file 106a, and displays and outputs the amount of work completed according to each employee's monthly work schedule and the PM's amount of work completed for each month for the target project as a monthly trend table in the form of a report.
社員の出来高は、契約額×各月の作業時間/実施後の各月の予定時間で算出する投入出来高、進捗出来高-投入出来高で算出する投入改善高、投入改善高/進捗出来高×100で算出する投入改善率、及び管理帳票などで、確定月までは進捗出来高、翌月以降は予定出来高で、最終的な着地予想を捉える指標である着地出来高の少なくとも1つを含むことにしてもよい。 Employee output may include at least one of the following: input output calculated by contract amount x working hours for each month / planned hours for each month after implementation, input improvement amount calculated by progress output - input output, input improvement rate calculated by input improvement amount / progress output x 100, and final output, which is an indicator that captures the final forecast, with progress output up to the fixed month and planned output from the following month onwards, in the management document, etc.
PMの出来高は、契約額×計画時の各月の予定時間/総予定時間で算出する予定出来高、契約額×実施後の各月の予定時間/総予定時間で算出する進捗出来高、(進捗出来高-予定出来高)/予定出来高×100で算出する進捗改善率、及び管理帳票などで、確定月までは進捗出来高、翌月以降は予定出来高で、最終的な着地予想を捉える指標である着地出来高の少なくとも1つを含むことにしてもよい。 PM output may include at least one of the planned output calculated by the contract amount x the planned hours for each month at the time of planning/total planned hours, the progress output calculated by the contract amount x the planned hours for each month after implementation/total planned hours, the progress improvement rate calculated by (progress output - planned output)/planned output x 100, and the final output, which is an indicator that captures the final forecast, with progress output up to the fixed month and planned output from the following month onwards, in management reports, etc.
[3.具体例]
図3~図14を参照して、本実施の形態における成績管理装置100の制御部102の処理の具体例について説明する。図4は、本実施の形態における成績管理装置100の制御部102の全体の処理の概略を説明するための図である。
3. Specific Examples
A specific example of the processing of the control unit 102 of the score management device 100 in this embodiment will be described with reference to Figures 3 to 14. Figure 4 is a diagram for explaining an outline of the overall processing of the control unit 102 of the score management device 100 in this embodiment.
(全体の処理)
図4を参照して、本実施の形態における成績管理装置100の制御部102の全体の処理の概略を説明する。
(Overall processing)
An outline of the overall processing of the control unit 102 of the score management device 100 in this embodiment will be described with reference to FIG.
図7において、契約入力処理部102aは、契約情報入力処理を実行する(ステップS1)。具体的には、契約情報入力処理では、契約入力処理部102aは、例えば、モニタ114に表示される不図示の契約入力画面上での操作等に応じて、契約情報を入力してデータファイル106aに登録する。
In FIG. 7, the contract
実行予算入力処理部102bは、実行予算入力処理を実行する(ステップS2)。具体的には、実行予算入力処理では、実行予算入力処理部102bは、例えば、モニタ114に表示される不図示の入力画面上での操作やPMの端末400の操作に応じて、対象のプロジェクトについて、PMが作成した、社員毎の各月の予定時間を含む実行予算情報を入力して、データファイル106aに登録する。月初(1回目)は、予定作業内容×標準工数時間から予定時間を算出してもよい。月末に見直しを行い、月末(2回目)は、(当月)実際作業内容×標準工数時間から予定時間を算出してもよい。 The working budget input processing unit 102b executes the working budget input process (step S2). Specifically, in the working budget input process, the working budget input processing unit 102b inputs working budget information including the planned hours for each employee for each month, created by the PM, for the target project, in response to, for example, operations on an input screen (not shown) displayed on the monitor 114 or operations on the PM's terminal 400, and registers the information in the data file 106a. At the beginning of the month (first time), the planned hours may be calculated from the planned work content x standard labor hours. A review is performed at the end of the month, and at the end of the month (second time), the planned hours may be calculated from the actual work content (of the month) x standard labor hours.
出来高照会処理部102dは、出来高照会処理を実行する(ステップS3)。具体的には、出来高照会処理では、出来高照会処理部102dは、例えば、モニタ114に表示される不図示の照会画面上での操作に応じて、データファイル106aに登録された実行予算情報及び日報情報を参照して、対象のプロジェクトについて、全体についての、総予定時間、対象の年月の時間、出来高と、各社員の予定時間、予定出来高、進捗時間、投入出来高、作業時間を含む照会結果を作成して表示出力する。
The earned amount
仕訳連携処理部102eは、仕訳連携処理を実行する(ステップS4)。具体的には、仕訳連携処理では、仕訳連携処理部102eは、例えば、モニタ114に表示される不図示の仕訳連携画面上での操作に応じて、データファイル106aに登録された実行予算情報及び日報情報を参照して、対象のプロジェクトについて社員毎の各月の仕訳を作成して表示出力する。 The journal entry linkage processing unit 102e executes the journal entry linkage processing (step S4). Specifically, in the journal entry linkage processing, the journal entry linkage processing unit 102e creates and displays the journal entry for each month for each employee for the target project by referring to the working budget information and daily report information registered in the data file 106a in response to an operation on the journal entry linkage screen (not shown) displayed on the monitor 114, for example.
月次推移表出力部102fは、月次推移表出力処理を実行する(ステップS5)。具体的には、月次推移表出力処理では、月次推移表出力部102fは、例えば、モニタ114に表示される不図示の月次推移表出力画面上での操作に応じて、データファイル106aに登録された実行予算情報及び日報情報を参照して、対象のプロジェクトについて、各社員の月毎の作業予定に応じた出来高と、PMの各月の出来高を帳票形式の月次推移表として表示出力する。 The monthly transition table output unit 102f executes the monthly transition table output process (step S5). Specifically, in the monthly transition table output process, the monthly transition table output unit 102f, for example, in response to an operation on a monthly transition table output screen (not shown) displayed on the monitor 114, references the working budget information and daily report information registered in the data file 106a, and displays and outputs the amount of work according to each employee's monthly work schedule and the PM's amount of work for each month for the target project as a monthly transition table in the form of a report.
日報入力処理部102cは、日報入力処理を実行する(ステップS6)。具体的には、日報入力処理では、日報入力処理部102cは、例えば、モニタ114に表示される不図示の入力画面上での操作や担当者の端末400の操作に応じて、プロジェクトNO、社員名、年月、作業時間のデータを含む日報情報を入力してデータファイル106aに登録する。
The daily report input processing unit 102c executes the daily report input process (step S6). Specifically, in the daily report input process, the daily report input processing unit 102c inputs daily report information including project number, employee name, year and month, and work hours in response to operations on an input screen (not shown) displayed on the monitor 114 or operations on the
そして、S2~S6の処理を対象のプロジェクトが完了するまで月単位で繰り返し実行する。 Then, steps S2 to S6 are repeated monthly until the target project is completed.
図5~図14を参照して、本実施の形態における成績管理装置100の制御部102の処理の具体例について説明する。以下では、会計年月「2019/04」~「2019/06」の処理イメージを説明する。 A specific example of the processing of the control unit 102 of the score management device 100 in this embodiment will be described with reference to Figures 5 to 14. Below, the processing image for the fiscal years and months "2019/04" to "2019/06" will be described.
[会計年月:2019/04:月初]
図5及び図6を参照して、会計年月「2019/04」の月初の処理を説明する。
[Fiscal year and month: April 2019: beginning of month]
Processing at the beginning of the month for the accounting year and month "2019/04" will be described with reference to FIGS. 5 and 6.
(1)契約情報の登録
契約情報入力処理では、契約情報を入力して、データファイル106aに登録する。図5に示す契約情報の例では、プロジェクトNO「P001」、契約金額「1000万」となっている。
(1) Registration of Contract Information In the contract information input process, contract information is input and registered in the data file 106a. In the example of the contract information shown in Fig. 5, the project number is "P001" and the contract amount is "10 million".
(2)実行予算情報の登録(4月度月初め:4月案件スタート前)
実行予算入力処理では、実行予算情報(契約情報実行予算月別社員別内訳情報)を入力して、データファイル106aに登録する。
(2) Registration of working budget information (beginning of April: before the April project starts)
In the actual budget input process, actual budget information (contract information, actual budget monthly and employee breakdown information) is input and registered in the data file 106a.
図5に示す実行予算情報の例では、プロジェクトNO「P001」について、社員名「田中」は、年月「2019/04」が予定時間「6時間」、年月「2019/05」が予定時間「8時間」、年月「2019/06」が予定時間「6時間」であり、予定時間計「20時間」となっている。社員名「鈴木」は、年月「2019/04」が予定時間「10時間」、年月「2019/05」が予定時間「20時間」、年月「2019/06」が予定時間「0時間」であり、予定時間計「30時間」となっている。社員名「佐藤」は、年月「2019/04」が予定時間「30時間」、年月「2019/05」が予定時間「10時間」、年月「2019/06」が予定時間「10時間」であり、予定時間計「50時間」となっている。総予定時間は、100時間となっている。 In the example of execution budget information shown in FIG. 5, for project number "P001," employee name "Tanaka" has a scheduled time of "6 hours" for the year and month "2019/04," a scheduled time of "8 hours" for the year and month "2019/05," and a scheduled time of "6 hours" for the year and month "2019/06," for a total scheduled time of "20 hours." Employee name "Suzuki" has a scheduled time of "10 hours" for the year and month "2019/04," a scheduled time of "20 hours" for the year and month "2019/05," and a scheduled time of "0 hours" for the year and month "2019/06," for a total scheduled time of "30 hours." Employee "Sato" has a scheduled time of "30 hours" for the year and month "2019/04", a scheduled time of "10 hours" for the year and month "2019/05", and a scheduled time of "10 hours" for the year and month "2019/06", for a total scheduled time of "50 hours". The total scheduled time is 100 hours.
実務的には、月初と月末の2回の予算見直しをルール化するのが望ましい。例えば、1回目は、予定作業内容×標準工数時間から算出してもよい。2回目は、(当月)実際作業内容×標準工数時間から算出してもよい。翌月以降は、予定作業内容×標準工数時間から算出してもよい。繰り越した作業内容などを加味する。 In practice, it is desirable to make it a rule to review the budget twice a month, once at the beginning and once at the end of the month. For example, the first time, the calculation can be based on the planned work content x standard labor hours. The second time, the calculation can be based on the actual work content (for the current month) x standard labor hours. From the following month onwards, the calculation can be based on the planned work content x standard labor hours. This takes into account any work content that has been carried over, etc.
(3)出来高照会
出来高照会処理では、出来高を照会する。図5に示す出来高の表示結果(4月度月初(案件スタート前))の例では、プロジェクトNO「P001」、契約額「1000万」、総予定時間「100時間」について、年月「2019/04」は、時間「46時間」、出来高「460万(=1000万×46時間/100時間)」、年月「2019/05」は、時間「38時間」、出来高「380万(=1000万×38時間/100時間)」、年月「2019/06」は、時間「16時間」、出来高「160万(=1000万×16時間/100時間)」となっている。
(3) Earnest money inquiry In the earnest money inquiry process, the earnest money is inquired. In the example of the earned money display result (beginning of April (before the project starts)) shown in FIG. 5, for the project number "P001", the contract amount "10 million", and the total planned time "100 hours", the year and month "2019/04" is the time "46 hours" and the earned money "4.6 million (=10 million x 46 hours/100 hours)", the year and month "2019/05" is the time "38 hours" and the earned money "3.8 million (=10 million x 38 hours/100 hours)", and the year and month "2019/06" is the time "16 hours" and the earned money "1.6 million (=10 million x 16 hours/100 hours)".
また、社員「田中」は、予定時間「20時間」、予定出来高「200万(=1000万×20時間/100時間)」、進捗時間「0時間」、投入出来高「0」、作業時間「0時間」、社員「鈴木」は、予定時間「30時間」、予定出来高「300万(=1000万×30時間/100時間)、進捗時間「0時間」、投入出来高「0」、作業時間「0時間」、社員「佐藤」は、予定時間「50時間」、予定出来高「500万(=1000万×50時間/100時間)、進捗時間「0時間」、投入出来高「0」、作業時間「0時間」となっている。 Employee "Tanaka" has a scheduled time of "20 hours", a scheduled output of "2 million (= 10 million x 20 hours / 100 hours)", progress time of "0 hours", input output of "0", and working time of "0 hours". Employee "Suzuki" has a scheduled time of "30 hours", a scheduled output of "3 million (= 10 million x 30 hours / 100 hours), progress time of "0 hours", input output of "0", and working time of "0 hours". Employee "Sato" has a scheduled time of "50 hours", a scheduled output of "5 million (= 10 million x 50 hours / 100 hours), progress time of "0 hours", input output of "0", and working time of "0 hours".
(4)仕訳連携
仕訳連携処理を実行して、社員毎の各月の仕訳を作成する。図6に示す仕訳イメージの例では、例えば、田中は、計上日「4月頭」では、振替勘定「60万」/予定出来高「60万」(補助科目=社員:田中)となっている。計上日「5月頭」では、振替勘定「80万」/予定出来高「80万」(補助科目=社員:田中)、計上日「6月頭」では、振替勘定「60万」/予定出来高「60万」(補助科目=社員:田中)となっている。
(4) Journal entry linkage The journal entry linkage process is executed to create journal entries for each employee for each month. In the example of the journal entry image shown in Figure 6, for example, for Tanaka, on the accounting date "beginning of April", the transfer account is "600,000" / planned amount of work is "600,000" (sub-account = employee: Tanaka). On the accounting date "beginning of May", the transfer account is "800,000" / planned amount of work is "800,000" (sub-account = employee: Tanaka), and on the accounting date "beginning of June", the transfer account is "600,000" / planned amount of work is "600,000" (sub-account = employee: Tanaka).
(5)月次推移表
月次推移表出力処理を実行して、月次推移表を出力する。すなわち、各社員の月毎に割り振った作業予定に応じた出来高を帳票形式で出力する。図6に示す月次推移表の例では、田中の予定出来高は、4月度「60万」、5月度「80万」、6月度「60万」となっている。鈴木の予定出来高は4月度「100万」、5月度「200万」、6月度「0万」となっている。佐藤の予定出来高は、4月度「300万」、5月度「100万」、6月度「100万」となっている。
(5) Monthly Transition Table The monthly transition table output process is executed to output the monthly transition table. That is, the amount of work that corresponds to the work schedule allocated to each employee for each month is output in the form of a report. In the example of the monthly transition table shown in FIG. 6, Tanaka's planned amount of work is "600,000" for April, "800,000" for May, and "600,000" for June. Suzuki's planned amount of work is "1,000,000" for April, "2,000,000" for May, and "0,000" for June. Sato's planned amount of work is "3,000,000" for April, "1,000,000" for May, and "1,000,000" for June.
[会計年月:2019/04:月末]
図7~図10を参照して、会計年月「2019/04」の月末の処理を説明する。
[Fiscal year and month: April 2019: end of month]
The processing at the end of the month for the accounting year and month "2019/04" will be described with reference to FIGS. 7 to 10.
(6)日報情報の登録
日報入力処理を実行して、各社員は日報情報を入力する。図7において、4月度は、全員予定していた作業を全て完了している。図7に示す日報情報の例では、プロジェクトNO「P001」について、社員名「田中」、年月「2019/04」、作業時間「5時間」、社員名「鈴木」、年月「2019/04」、作業時間「12時間」、社員名「佐藤」、年月「2019/04」、作業時間「25時間」となっている。
(6) Registering daily report information Each employee enters daily report information by executing the daily report input process. In FIG. 7, all employees have completed all scheduled work in April. In the example of daily report information shown in FIG. 7, for project number "P001", the employee name is "Tanaka", the month and year is "2019/04", the working hours are "5 hours", the employee name is "Suzuki", the month and year is "2019/04", the working hours are "12 hours", the employee name is "Sato", the month and year is "2019/04", the working hours are "25 hours".
(7)実行予算情報の登録
4月度月末に、当月書き換え、翌月以降見直しを行うことにしてもよい。ここでは、4月度は、全員予定していた作業は全て完了したため、予算見直しは行わない。
(7) Registration of working budget information At the end of April, the information may be rewritten for that month, and then reviewed from the following month onwards. In this case, since all scheduled work has been completed by all employees in April, no review of the budget is required.
(8)出来高照会
図8に示す出来高の表示結果では、社員「田中」は、進捗時間「6時間」、進捗出来高「60万(=460万×6時間/46時間)」、作業時間「5時間」、社員「鈴木」は、進捗時間「10時間」、進捗出来高「100万(=460万×10時間/46時間)」、作業時間「12時間」、社員「佐藤」は、進捗時間「30時間」、進捗出来高「300万(=460万×30時間/46時間)」、作業時間「25時間」である。4月度は、全員予定していた作業は全て完了したが、掛かった時間は人それぞれである。
(8) Amount of Work Inquiry In the display result of the amount of work shown in Fig. 8, employee "Tanaka" has progress time "6 hours", progress amount "600,000 (=4.6 million x 6 hours / 46 hours)", and work time "5 hours", employee "Suzuki" has progress time "10 hours", progress amount "1 million (=4.6 million x 10 hours / 46 hours)", and work time "12 hours", employee "Sato" has progress time "30 hours", progress amount "3 million (=4.6 million x 30 hours / 46 hours)", and work time "25 hours". In April, all employees completed all the scheduled work, but the time it took for each employee varied.
(9)仕訳連携
図9に示す仕訳イメージの例では、田中は、計上日「4月末」について、振替勘定「60万」/進捗出来高「60万」(補助科目=社員:田中)と、投入出来高「50万」(補助科目=社員:田中)/振替勘定「50万」の仕訳が追加されている。ここで、50万は、60万×5時間/6時間で算出される。
(9) Journal entry linkage In the example of the journal entry image shown in Figure 9, for Tanaka, the journal entries of transfer account "600,000" / progress amount "600,000" (subsidiary account = employee: Tanaka) and input amount "500,000" (subsidiary account = employee: Tanaka) / transfer account "500,000" have been added for the recording date "end of April". Here, 500,000 is calculated as 600,000 x 5 hours / 6 hours.
(10)月次推移表
図10に示す月次推移表の例では、担当者の進捗出来高、着地出来高、投入出来高、投入改善高、投入改善率が表示されている。着地出来高は、担当者の売上回転視点での出来高評価である。投入出来高、投入改善高、投入改善率は、個人の作業効率視点での出来高評価である。4月は、予定通り作業が完了しているため、予定出来高=進捗出来高となる。
(10) Monthly Trend Table In the example of the monthly trend table shown in FIG. 10, the progress output, final output, input output, input improvement amount, and input improvement rate of the person in charge are displayed. The final output is an output evaluation from the perspective of the sales turnover of the person in charge. The input output, input improvement amount, and input improvement rate are output evaluation from the perspective of individual work efficiency. In April, the work was completed as scheduled, so the planned output = progress output.
また、PMの予定出来高、進捗出来高、進捗改善率、着地出来高が表示されている。PMの出来高は、社員の合計値に基づいた値である。PMの進捗出来高、進捗改善率、着地出来高は、アサインやPM予算管理の視点での出来高評価である。 In addition, the planned output, progress, progress improvement rate, and final output of PM are displayed. PM output is a value based on the total value of employees. PM progress, progress improvement, and final output are output evaluations from the perspective of assignment and PM budget management.
4月は、予定通り作業が完了しているため、予定出来高=進捗出来高となる。鈴木は、4月度の投入改善高「-20万」、投入改善率「-20%」となっている。 In April, the work was completed as scheduled, so the planned output = the progress output. Suzuki's input improvement amount for April is "-200,000," and the input improvement rate is "-20%."
[会計年月:2019/05:月末]
図11~図14を参照して、会計年月「2019/05」の月末の処理を説明する。
[Fiscal year and month: May 2019: end of month]
The process at the end of the month for the accounting year and month "2019/05" will be described with reference to FIGS. 11 to 14.
(11)日報情報の登録
図11に示す日報情報の例では、プロジェクトNO「P001」について、社員名「田中」、年月「2019/05」、作業時間「10時間」、社員名「鈴木」、年月「2019/05」、作業時間「10時間」、社員名「佐藤」、年月「2019/05」、作業時間「10時間」となっている。5月は、予定していた作業に対して、田中は完了、鈴木は60%完了、佐藤は完了となっている。
(11) Registration of daily report information In the example of daily report information shown in Fig. 11, for project number "P001", employee name "Tanaka", year and month "2019/05", working hours "10 hours", employee name "Suzuki", year and month "2019/05", working hours "10 hours", employee name "Sato", year and month "2019/05", working hours "10 hours". In May, Tanaka completed the scheduled work, Suzuki completed 60%, and Sato completed.
(12)実行予算情報の登録
図11に示す実行予算情報において、2019/05については、鈴木は、予定時間「20時間」に対して、作業時間「10時間」で60%完了しているので、2019/06の予定時間を0時間から8時間に変更する。
(12) Registering Execution Budget Information In the execution budget information shown in FIG. 11, for May 2019, Suzuki completed 60% of the work with a working time of 10 hours compared to the scheduled time of 20 hours, so the scheduled time for June 2019 is changed from 0 hours to 8 hours.
(13)出来高照会
図12に示す5月度の出来高の表示結果では、年月「2019/05」の時間が「30時間」、出来高が「300万(=1000万×30時間/100時間)」、年月「2019/06」の時間が「24時間」、出来高が「240万(=1000万×24時間/100時間)」となっている。
(13) Volume Inquiry In the display result of the volume for May shown in FIG. 12, the time for the year and month "2019/05" is "30 hours", the volume is "3 million (= 10 million x 30 hours / 100 hours)", the time for the year and month "2019/06" is "24 hours", and the volume is "2.4 million (= 10 million x 24 hours / 100 hours)".
社員「田中」は、予定時間「6時間」、予定出来高「90万(=240万×6時間/16時間)」、進捗時間「14時間」、進捗出来高「140万(=760万×14時間/76時間)」、日報時間「15時間」となっている。社員「鈴木」は、予定時間「8時間」、予定出来高「120万(=240万×8時間/16時間)、進捗時間「22時間」、進捗出来高「220万=760万×22時間/16時間)」、作業時間「22時間」となっている。社員「佐藤」は、予定時間「10時間」、予定出来高「150万(=240万×10時間/16時間)、進捗時間「40時間」、進捗出来高「400万=760万×402時間/76時間)」、作業時間「35時間」となっている。 Employee "Tanaka" has a scheduled time of "6 hours", a scheduled output of "900,000 (=2.4 million x 6 hours/16 hours)", progress time of "14 hours", progress output of "1.4 million (=7.6 million x 14 hours/76 hours)", and a daily report time of "15 hours". Employee "Suzuki" has a scheduled time of "8 hours", a scheduled output of "1.2 million (=2.4 million x 8 hours/16 hours)", progress time of "22 hours", progress output of "2.2 million = 7.6 million x 22 hours/16 hours)", and a working time of "22 hours". Employee "Sato" has a scheduled time of "10 hours", a scheduled output of "1.5 million (=2.4 million x 10 hours/16 hours)", progress time of "40 hours", progress output of "4 million = 7.6 million x 402 hours/76 hours)", and a working time of "35 hours".
(14)仕訳連携
図12に示す仕訳イメージの例では、例えば、田中は、計上日「5月末」について、振替勘定「80万」/進捗出来高「80万」(補助科目=社員:田中)と、投入出来高「100万」(補助科目=社員:田中)/振替勘定「100万」の仕訳が追加されている。ここで、100万は、80万×10時間/8時間で算出される。
(14) Journal entry linkage In the example of the journal entry image shown in Fig. 12, for example, for Tanaka, the journal entries of transfer account "800,000" / progress amount "800,000" (subsidiary account = employee: Tanaka) and input amount "1 million" (subsidiary account = employee: Tanaka) / transfer account "1 million" are added for the recording date "end of May". Here, 1 million is calculated as 800,000 x 10 hours / 8 hours.
(15)月次推移表
図14に示す月次推移表の例では、5月度は、田中・佐藤は予定通り作業完了しているので、予定出来高=進捗出来高となっている。5月度は、鈴木は60%のみ進捗しているので、予定出来高「200万」>進捗出来高「120万」となる。そのため、鈴木には、6月度に積み残しの予定作業に応じた予定出来高「80万」が計画されている。
(15) Monthly Transition Table In the example of the monthly transition table shown in Fig. 14, Tanaka and Sato completed their work as scheduled in May, so the planned output = the progress output. Suzuki has only progressed 60% in May, so the planned output of "2 million"> the progress output of "1.2 million." Therefore, Suzuki is scheduled to have a planned output of "800,000" in June based on the remaining scheduled work.
管理会計からの改善行動例(1)
田中さんは、作業効率が悪いので(合計の投入出来高「150万」、投入改善高「-10万」、投入改善率「-7%」)となっているので、効率の良い佐藤さん(合計の投入出来高「500万」、投入改善高「50万」、投入改善率「17%」)に聞いて段取りを見直して作業効率を上げていく。
Examples of improvement actions from management accounting (1)
Tanaka's work efficiency is poor (total input output: 1.5 million, input improvement amount: -100,000, input improvement rate: -7%), so he will consult with Sato, who is more efficient (total input output: 5 million, input improvement amount: 500,000, input improvement rate: 17%) and review the process to improve work efficiency.
管理会計からの改善行動例(2)
鈴木さんは、効率性に問題ないが、他のアサイン予定がなく、年間の出来高目標が未達になる恐れがあるので(合計の着地出来高「300万」)、6月以降のアサインを計画する。
Examples of improvement actions from management accounting (2)
Although there is no problem with Suzuki's efficiency, there are no other assignments scheduled, and there is a risk that the annual volume target will not be achieved (total final volume is "3 million"), so an assignment will be planned for after June.
管理会計からの改善行動例(3)
契約額、予定出来高は、もし進捗遅れが客先要因であれば、追加コストとして契約増額する目安となるので、PMが進捗遅れ(契約額「1000万」、合計の予定出来高「1080万」)の追加請求分を客先交渉して契約増額に繋げる。
Examples of improvement actions from management accounting (3)
If the delay in progress is due to customer factors, the contract amount and planned progress amount will serve as a guideline for increasing the contract amount as additional costs, so the PM will negotiate with the customer about the additional invoice for the delay in progress (contract amount "10 million", total planned progress "10.8 million"), which will lead to an increase in the contract amount.
管理会計からの改善行動例(4)
PMや組織長、アサイン管理者が、6月度や年間の部門別目標予算に対して、出来高不足が見込まれることから(合計の進捗出来高「760万」、進捗改善高「-80万」、進捗改善率「-7%」、着地出来高「1000万」)、追加アサインを実施する。
Examples of improvement actions from management accounting (4)
The PM, organizational head, and assignment manager predict that there will be shortfalls in performance compared to the departmental target budgets for June and the year (total progress performance: 7.6 million, progress improvement amount: -800,000, progress improvement rate: -7%, final performance: 10 million), so they will make additional assignments.
管理会計からの改善行動例(5)
進捗遅れが発生しているため(5月度の進捗改善率「-21%」)、翌月以降の追加アサイン、予定負荷を調整したり、工期延長を客先交渉したりする。
Examples of improvement actions from management accounting (5)
Due to delays in progress (progress improvement rate for May was "-21%)), additional assignments and scheduled workloads will be adjusted from the following month onwards, and negotiations will be made with the client regarding an extension of the construction period.
以上説明したように、本実施の形態によれば、対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力処理部102bと、各担当者の月毎の作業時間を含む日報情報を入力する日報入力処理部102cと、前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高と、プロジェクトマネージャーの各月の出来高とを含む月次推移表を出力する月次推移表出力部102fとを備えているので、プロジェクトの収益がプロダクトマネージャーに起因するものなのか、作業担当者の作業進捗や効率に起因するものなのかをそれぞれ区別した指標にて明確に捉えることが可能になる。 As described above, according to this embodiment, the system includes an execution budget input processing unit 102b that inputs execution budget information including the scheduled hours for each person in charge each month, created by the project manager, a daily report input processing unit 102c that inputs daily report information including the monthly working hours of each person in charge, and a monthly trend table output unit 102f that outputs a monthly trend table including the amount of work completed according to the monthly work schedule of each person in charge and the amount of work completed by the project manager for each month, based on the execution budget information and the daily report information. This makes it possible to clearly grasp whether the profits of the project are due to the product manager or the work progress and efficiency of the workers using indicators that distinguish between the two.
[4.他の実施形態]
本発明は、上述した実施の形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
4. Other embodiments
The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.
例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部または一部を手動的に行うこともでき、あるいは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。 For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using a known method.
また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。 In addition, the processing procedures, control procedures, specific names, registered data for each process, information including parameters such as search conditions, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.
また、成績管理装置100に関して、図示の各構成要素は機能概念的なものであり、必ずしも物理的に図示の如く構成されていることを要しない。 In addition, with regard to the score management device 100, each component shown in the figure is a functional concept, and does not necessarily have to be physically configured as shown in the figure.
例えば、成績管理装置100が備える処理機能、特に制御部にて行われる各処理機能については、その全部または任意の一部を、CPUおよび当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。尚、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じて成績管理装置100に機械的に読み取られる。すなわち、ROMまたはHDD(Hard Disk Drive)などの記憶部などには、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部を構成する。 For example, the processing functions of the score management device 100, particularly the processing functions performed by the control unit, may be realized in whole or in part by a CPU and a program interpreted and executed by the CPU, or may be realized as hardware using wired logic. The program is recorded on a non-transient computer-readable recording medium that contains programmed instructions for causing the information processing device to execute the processes described in this embodiment, and is mechanically read by the score management device 100 as necessary. That is, a computer program is recorded in a storage unit such as a ROM or HDD (Hard Disk Drive) for working with the OS to give instructions to the CPU and perform various processes. This computer program is executed by being loaded into RAM, and works with the CPU to form the control unit.
また、このコンピュータプログラムは、成績管理装置100に対して任意のネットワークを介して接続されたアプリケーションプログラムサーバに記憶されていてもよく、必要に応じてその全部または一部をダウンロードすることも可能である。 This computer program may also be stored in an application program server connected to the score management device 100 via any network, and all or part of it may be downloaded as needed.
また、本実施形態で説明した処理を実行するためのプログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD-ROM(Compact Disk Read Only Memory)、MO(Magneto-Optical disk)、DVD(Digital Versatile Disk)、および、Blu-ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。 In addition, the program for executing the processing described in this embodiment may be stored on a non-transitory computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" refers to a memory card, a USB (Universal Serial Bus) memory, a SD (Secure Digital) card, a flexible disk, a magneto-optical disk, a ROM, an EPROM (Erasable Programmable Read Only Memory), an EEPROM (registered trademark) (Electrically Erasable and Programmable Read Only Memory), a CD-ROM (Compact Disk Read Only Memory), an MO (Magneto-Optical disk), a DVD (Digital Versatile This includes any "portable physical media" such as a DVD (registered trademark) or Blu-ray (registered trademark) Disc.
また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコードまたはバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、実施形態に示した各装置において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。 A "program" is a data processing method written in any language or description method, and may be in any format, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration consisting of multiple modules or libraries, and a program that works in conjunction with a separate program, such as an OS, to achieve its function. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in the embodiments, as well as the installation procedure after reading, can use well-known configurations and procedures.
記憶部に格納される各種のデータベース等は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、および、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、および、ウェブページ用ファイル等を格納する。 The various databases stored in the memory unit are storage devices such as RAM, ROM, etc., fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files used for various processes and providing websites.
また、成績管理装置100は、既知のパーソナルコンピュータまたはワークステーション等の情報処理装置として構成してもよく、また、任意の周辺装置が接続された当該情報処理装置として構成してもよい。また、成績管理装置100は、当該装置に本実施形態で説明した処理を実現させるソフトウェア(プログラムまたはデータ等を含む)を実装することにより実現してもよい。 The score management device 100 may be configured as an information processing device such as a known personal computer or workstation, or may be configured as the information processing device to which any peripheral device is connected. The score management device 100 may be realized by implementing software (including programs or data, etc.) that causes the device to realize the processing described in this embodiment.
更に、装置の分散・統合の具体的形態は図示するものに限られず、その全部または一部を、各種の付加等に応じてまたは機能負荷に応じて、任意の単位で機能的または物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。 Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the figures, and all or part of them can be functionally or physically distributed and integrated in any unit depending on various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively.
100 成績管理装置
102 制御部
102a 契約入力処理部
102b 実行予算入力処理部
102c 日報入力処理部
102d 出来高照会処理部
102e 仕訳連携処理部
102f 月次推移表出力部
106 記憶部
106a データファイル
112 入力装置
114 出力装置
200 サーバ
300 ネットワーク
400 端末
REFERENCE SIGNS LIST 100 Performance management device 102
Claims (4)
対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力処理手段と、
各担当者の月毎の作業時間を含む日報情報を入力する日報入力処理手段と、
前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高評価と、プロジェクトマネージャーの各月の出来高評価とを含む月次推移表を出力する月次推移表出力手段と、
を備え、
前記実行予算入力処理手段は、前記実行予算情報の担当者の予定時間を修正可能に構成されており、
前記月次推移表出力手段は、
担当者別に、
(1)契約額×前記実行予算情報の担当者の予定時間の修正の実施後の前記各月の担当者毎の予定時間/総予定時間で担当者別の進捗出来高を算出し、
(2)前記担当者別進捗出来高×前記月毎の担当者毎の作業時間/前記実行予算情報の担当者の予定時間の修正の実施後の前記各月の担当者毎の予定時間で投入出来高を算出し、
プロジェクト別に、
(3)契約額×計画時の各月のプロジェクト毎の予定時間/総予定時間で予定出来高を算出し、
(4)契約額×前記実行予算情報の担当者の予定時間の修正の実施後の前記各月のプロジェクト毎の予定時間/総予定時間でプロジェクト別の進捗出来高を算出し、
前記各担当者の月毎の作業予定に応じた出来高評価は、前記担当者別進捗出来高-前記投入出来高で算出する投入改善高、及び、前記投入改善高/前記担当者別進捗出来高×100で算出する投入改善率の少なくとも1つを含み、
前記プロジェクトマネージャーの各月の出来高評価は、(前記プロジェクト別進捗出来高-前記予定出来高)/前記予定出来高×100で算出する進捗改善率を含むことを特徴とする成績管理装置。 A score management device including a control unit,
an actual budget input processing means for inputting actual budget information including the scheduled hours for each person in charge for each month, which is prepared by a project manager for the target project;
A daily report input processing means for inputting daily report information including the monthly working hours of each person in charge;
a monthly transition table output means for outputting a monthly transition table including a performance evaluation of each person in charge according to the monthly work schedule and a performance evaluation of each month by the project manager based on the working budget information and the daily report information;
Equipped with
the working budget input processing means is configured to be able to modify the scheduled time of the person in charge of the working budget information,
The monthly transition table output means
By person in charge,
(1) Calculate the progress amount for each person in charge by multiplying the contract amount by the scheduled time for each person in charge for each month after the scheduled time for the person in charge in the execution budget information is corrected/the total scheduled time;
(2) Calculating the input output by multiplying the progress output by each person in charge by the working hours by each person in charge for each month by the scheduled hours by each person in charge for each month after the scheduled hours of the person in charge in the working budget information are corrected;
By project,
(3) Calculate the planned volume of work by multiplying the contract amount by the planned hours for each project in each month at the time of planning / total planned hours.
(4) Calculate the progress amount for each project by multiplying the contract amount by the planned time for each project for each month after the correction of the planned time of the person in charge in the working budget information is made/the total planned time;
The performance evaluation according to the monthly work schedule of each of the workers includes at least one of an input improvement amount calculated by the worker-specific progress performance--the input performance, and an input improvement rate calculated by the input improvement amount/the worker-specific progress performance--×100;
A performance management device , characterized in that the performance evaluation of the project manager for each month includes a progress improvement rate calculated by (progressed performance by project - planned performance) / planned performance x 100 .
前記制御部において実行される、
対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力処理工程と、
各担当者の月毎の作業時間を含む日報情報を入力する日報入力処理工程と、
前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高評価と、プロジェクトマネージャーの各月の出来高評価とを含む月次推移表を出力する月次推移表出力工程と、
を含み、
前記実行予算入力処理工程では、前記実行予算情報の担当者の予定時間を修正可能に構成されており、
前記月次推移表出力工程では、
担当者別に、
(1)契約額×前記実行予算情報の担当者の予定時間の修正の実施後の前記各月の担当者毎の予定時間/総予定時間で担当者別の進捗出来高を算出し、
(2)前記担当者別進捗出来高×前記月毎の担当者毎の作業時間/前記実行予算情報の担当者の予定時間の修正の実施後の前記各月の担当者毎の予定時間で投入出来高を算出し、
プロジェクト別に、
(3)契約額×計画時の各月のプロジェクト毎の予定時間/総予定時間で予定出来高を算出し、
(4)契約額×前記実行予算情報の担当者の予定時間の修正の実施後の前記各月のプロジェクト毎の予定時間/総予定時間でプロジェクト別の進捗出来高を算出し、
前記各担当者の月毎の作業予定に応じた出来高評価は、前記担当者別進捗出来高-前記投入出来高で算出する投入改善高、及び、前記投入改善高/前記担当者別の進捗出来高×100で算出する投入改善率の少なくとも1つを含み、
前記プロジェクトマネージャーの各月の出来高評価は、(前記プロジェクト別進捗出来高-前記予定出来高)/前記予定出来高×100で算出する進捗改善率を含むことを特徴とする成績管理方法。 A score management method executed by an information processing device having a control unit,
Executed in the control unit,
an actual budget input process for inputting actual budget information including the scheduled hours for each person in charge for each month, which is created by the project manager for the target project;
a daily report input process for inputting daily report information including the monthly working hours of each person in charge;
a monthly transition table output step of outputting a monthly transition table including a performance evaluation of each person in charge according to the monthly work schedule and a performance evaluation of each month by the project manager based on the working budget information and the daily report information;
Including,
The working budget input process is configured to allow modification of the scheduled time of the person in charge of the working budget information,
In the monthly transition table output step,
By person in charge,
(1) Calculate the progress amount for each person in charge by multiplying the contract amount by the scheduled time for each person in charge for each month after the scheduled time for the person in charge in the execution budget information is corrected/the total scheduled time;
(2) Calculating the input output by multiplying the progress output by each person in charge by the working hours by each person in charge for each month by the scheduled hours by each person in charge for each month after the scheduled hours of the person in charge in the working budget information are corrected;
By project,
(3) Calculate the planned volume of work by multiplying the contract amount by the planned hours for each project in each month at the time of planning / total planned hours.
(4) Calculate the progress amount for each project by multiplying the contract amount by the planned time for each project for each month after the correction of the planned time of the person in charge in the working budget information is made/the total planned time;
The performance evaluation according to the monthly work schedule of each of the workers includes at least one of an input improvement amount calculated by subtracting the input performance amount from the progress performance of the worker, and an input improvement rate calculated by dividing the input improvement amount by the progress performance of the worker×100;
A performance management method , characterized in that the performance evaluation of the project manager for each month includes a progress improvement rate calculated by (progressed performance by project - planned performance) / planned performance x 100 .
前記制御部に、
対象のプロジェクトについて、プロジェクトマネージャーが作成した、担当者毎の各月の予定時間を含む実行予算情報を入力する実行予算入力処理工程と、
各担当者の月毎の作業時間を含む日報情報を入力する日報入力処理工程と、
前記実行予算情報と前記日報情報に基づいて、各担当者の月毎の作業予定に応じた出来高評価と、プロジェクトマネージャーの各月の出来高評価とを含む月次推移表を出力する月次推移表出力工程と、
を実行させるための成績管理プログラムであり、
前記実行予算入力処理工程では、前記実行予算情報の担当者の予定時間を修正可能に構成されており、
前記月次推移表出力工程では、
担当者別に、
(1)契約額×前記実行予算情報の担当者の予定時間の修正の実施後の前記各月の担当者毎の予定時間/総予定時間で担当者別の進捗出来高を算出し、
(2)前記担当者別進捗出来高×前記月毎の担当者毎の作業時間/前記実行予算情報の担当者の予定時間の修正の実施後の前記各月の担当者毎の予定時間で投入出来高を算出し、
プロジェクト別に、
(3)契約額×計画時の各月のプロジェクト毎の予定時間/総予定時間で予定出来高を算出し、
(4)契約額×前記実行予算情報の担当者の予定時間の修正の実施後の前記各月のプロジェクト毎の予定時間/総予定時間でプロジェクト別の進捗出来高を算出し、
前記各担当者の月毎の作業予定に応じた出来高評価は、前記担当者別進捗出来高-前記投入出来高で算出する投入改善高、及び、前記投入改善高/前記担当者別の進捗出来高×100で算出する投入改善率の少なくとも1つを含み、
前記プロジェクトマネージャーの各月の出来高評価は、(前記プロジェクト別進捗出来高-前記予定出来高)/前記予定出来高×100で算出する進捗改善率を含むことを特徴とする成績管理プログラム。 A score management program to be executed by an information processing device having a control unit,
The control unit ,
an actual budget input process for inputting actual budget information including the scheduled hours for each person in charge for each month, which is created by the project manager for the target project;
a daily report input process for inputting daily report information including the monthly working hours of each person in charge;
a monthly transition table output step of outputting a monthly transition table including a performance evaluation of each person in charge according to the monthly work schedule and a performance evaluation of each month by the project manager based on the working budget information and the daily report information;
This is a performance management program to implement
The working budget input process is configured to allow a person in charge of the working budget information to modify a scheduled time of the person in charge,
In the monthly transition table output step,
By person in charge,
(1) Calculate the progress amount for each person in charge by multiplying the contract amount by the scheduled time for each person in charge for each month after the scheduled time for the person in charge in the execution budget information is corrected/the total scheduled time;
(2) Calculating the input output by multiplying the progress output by each person in charge by the working hours by each person in charge for each month by the scheduled hours by each person in charge for each month after the scheduled hours of the person in charge in the working budget information are corrected;
By project,
(3) Calculate the planned volume of work by multiplying the contract amount by the planned hours for each project in each month at the time of planning / total planned hours.
(4) Calculate the progress amount for each project by multiplying the contract amount by the planned time for each project for each month after the correction of the planned time of the person in charge in the working budget information is made/the total planned time;
The performance evaluation according to the monthly work schedule of each of the workers includes at least one of an input improvement amount calculated by subtracting the input performance amount from the progress performance of the worker, and an input improvement rate calculated by dividing the input improvement amount by the progress performance of the worker×100;
A performance management program , characterized in that the performance evaluation of the project manager for each month includes a progress improvement rate calculated by (progressed performance by project - planned performance) / planned performance x 100 .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020131140A JP7492399B2 (en) | 2020-07-31 | 2020-07-31 | Grade management device, grade management method, and grade management program |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020131140A JP7492399B2 (en) | 2020-07-31 | 2020-07-31 | Grade management device, grade management method, and grade management program |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2022027251A JP2022027251A (en) | 2022-02-10 |
JP7492399B2 true JP7492399B2 (en) | 2024-05-29 |
Family
ID=80264256
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2020131140A Active JP7492399B2 (en) | 2020-07-31 | 2020-07-31 | Grade management device, grade management method, and grade management program |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7492399B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7553995B1 (en) | 2023-12-12 | 2024-09-19 | 有限会社日向栄進産業 | Business management computer, business management method and program |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015222546A (en) | 2014-05-23 | 2015-12-10 | 三菱電機株式会社 | Management device, management method, and program |
JP2018109869A (en) | 2017-01-04 | 2018-07-12 | 株式会社オービック | Amount calculation apparatus, amount calculation method and amount calculation program |
-
2020
- 2020-07-31 JP JP2020131140A patent/JP7492399B2/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015222546A (en) | 2014-05-23 | 2015-12-10 | 三菱電機株式会社 | Management device, management method, and program |
JP2018109869A (en) | 2017-01-04 | 2018-07-12 | 株式会社オービック | Amount calculation apparatus, amount calculation method and amount calculation program |
Also Published As
Publication number | Publication date |
---|---|
JP2022027251A (en) | 2022-02-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20170147960A1 (en) | Systems and Methods for Project Planning and Management | |
US20160048785A1 (en) | A computer implemented system and method for project controls | |
Mueller | Integrated cost and schedule control for construction projects | |
JP7297817B2 (en) | man hour system | |
US20160364809A1 (en) | Personnel expense simulation system, personnel expense simulation method, and personnel expense simulation program | |
JP2008065452A (en) | Management system for personal work results | |
JP6049799B2 (en) | Management support program | |
Versendaal et al. | Procurement maturity and IT-alignment models: overview and a case study | |
JP4152611B2 (en) | Measures planning support method for management reform and system therefor | |
JP7492399B2 (en) | Grade management device, grade management method, and grade management program | |
JP2003288476A (en) | Line capacity integrated evaluation/management operation system for production line and line capacity integrated evaluation/management operation method for the production line | |
JP2016033704A (en) | Income summary prediction device and income summary prediction program | |
JP7220695B2 (en) | Activity management system and method | |
JP2009157489A (en) | Project progress management device and its control method, project progress management system, program and recording medium with the program recorded | |
JP7290963B2 (en) | Money totaling device, money totaling method and money totaling program | |
Seo et al. | Calculating the cost impact in loss of productivity claims | |
JP2018109869A (en) | Amount calculation apparatus, amount calculation method and amount calculation program | |
JP7280931B2 (en) | Information processing device, information processing method, and information processing program | |
JP7308338B1 (en) | Business support device, business support method, and business support program | |
Snijkers et al. | Planning the survey | |
JP7550712B2 (en) | Planned start and end date calculation device, planned start and end date calculation method, and planned start and end date calculation program | |
Golnaraghi | Development of Delays Claims Assessment Model | |
JP2007242063A (en) | Proposed measure planning support method for management reform and system therefor | |
vom Brocke et al. | Justifying ECM investments with the return on process transformation: the case of an ECM-driven transformation of sales processes at Hilti Corporation | |
JP2023115800A (en) | Landing prediction value management device, landing prediction value management method, and landing prediction value management program |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20221215 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20231027 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20231114 |
|
A601 | Written request for extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A601 Effective date: 20240111 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240311 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20240423 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20240517 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7492399 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |