JP7284104B2 - Method for constructing cast-in-place concrete piles and concrete structures - Google Patents

Method for constructing cast-in-place concrete piles and concrete structures Download PDF

Info

Publication number
JP7284104B2
JP7284104B2 JP2020001821A JP2020001821A JP7284104B2 JP 7284104 B2 JP7284104 B2 JP 7284104B2 JP 2020001821 A JP2020001821 A JP 2020001821A JP 2020001821 A JP2020001821 A JP 2020001821A JP 7284104 B2 JP7284104 B2 JP 7284104B2
Authority
JP
Japan
Prior art keywords
concrete
height
placing
cast
placement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020001821A
Other languages
Japanese (ja)
Other versions
JP2021110130A (en
Inventor
定幸 石▲崎▼
徹 渡邊
雅樹 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2020001821A priority Critical patent/JP7284104B2/en
Publication of JP2021110130A publication Critical patent/JP2021110130A/en
Application granted granted Critical
Publication of JP7284104B2 publication Critical patent/JP7284104B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、場所打ちコンクリート杭およびコンクリート構造物の構築方法に関する。 The present invention relates to cast-in-place concrete piles and methods of constructing concrete structures.

コンクリート構造物は、場所によって作用応力が異なり、必要とされる設計耐力が場所ごとに異なっている。例えば、場所打ちコンクリート杭は、通常、上部ほど地震時の応力が大きくなる。そのため、場所打ちコンクリート杭を設計する場合には、杭頭部において必要な曲げ耐力およびせん断耐力を確保できるコンクリート強度および断面寸法に合わせて杭全体を設計するのが一般的である。
ところが、曲げ応力およびせん断応力が最大となる杭頭部に必要な設計耐力は、その他の部分において必要な設計耐力を大きく上回っている場合がある。そのため、杭頭部で杭全体のコンクリート強度等を設計すると、コスト高になるおそれがある。
そのため、特許文献1では、杭体底部から、杭体中間部、杭体頭部に向かうに従ってコンクリート中のセメント量を増加させることで、部位毎に必要な強度を確保できる場所打ちコンクリート杭が開示されている。特許文献1では、場所打ちコンクリート杭のコンクリートの配合を変化させる計画高さ(例えば、杭体底部と杭体中間部との境界)よりも2mほど下部から配合を変化させたコンクリートを打設している。
場所打ちコンクリート杭では、トレミー管の先端を既打設コンクリートに挿入した状態で打設するため、既打設コンクリートは後から打設されたコンクリートによって周囲に押し広げられる。押し広げられたコンクリートの挙動は、コンクリート構造物の断面寸法、鉄筋等の補強材の配置、コンクリート打設に使用するトレミー管の既打設コンクリートへの挿入深さ等によって変化する。そのため、打設コンクリートの配合を切り換えるタイミングをコンクリート配合の変化点から一定の深さで設定すると、コンクリートの変化点が設計通りに形成されない場合もある。
Concrete structures have different acting stresses depending on the location, and the required design bearing capacity differs from location to location. For example, cast-in-place concrete piles generally experience greater stress during an earthquake as they go up. Therefore, when designing a cast-in-place concrete pile, it is common to design the entire pile according to the concrete strength and cross-sectional dimensions that ensure the necessary bending and shear strength at the pile head.
However, the design yield strength required for the pile head where the bending stress and shear stress are maximum may greatly exceed the design yield strength required for other portions. Therefore, if the concrete strength of the entire pile is designed based on the pile head, the cost may increase.
Therefore, Patent Document 1 discloses a cast-in-place concrete pile that can secure the required strength for each part by increasing the amount of cement in the concrete as it goes from the bottom of the pile body to the middle part of the pile body and the head of the pile body. It is In Patent Document 1, concrete with a different mix is poured from about 2m below the planned height (for example, the boundary between the bottom of the pile body and the middle part of the pile body) for changing the mix of concrete of the cast-in-place concrete pile. ing.
In the cast-in-place concrete pile, since the tip of the tremie pipe is inserted into the existing concrete, the existing concrete is spread out by the concrete that is placed later. The behavior of the expanded concrete changes depending on the cross-sectional dimensions of the concrete structure, the arrangement of reinforcing materials such as reinforcing bars, the insertion depth of the tremie pipe used for concrete placement into the already placed concrete, and the like. Therefore, if the timing for switching the mixing ratio of the placed concrete is set at a constant depth from the changing point of the concrete mixing ratio, the changing point of the concrete may not be formed as designed.

特開2006-16787号公報JP 2006-16787 A

本発明は、前記の問題点を解決することを目的とするものであり、種類が異なるコンクリートを高さ方向で連続して打設する場合において、打設コンクリートの強度の変化点を合理的に設定する構造を有した場所打ちコンクリート杭およびコンクリート構造物の構築方法を提案することを課題とする。 An object of the present invention is to solve the above problems. The object of the present invention is to propose a cast-in-place concrete pile having a set structure and a method of constructing a concrete structure.

前記課題を解決するための本発明の場所打ちコンクリート杭は、下部コンクリートの上に前記下部コンクリートとは異なる種類のコンクリートからなる上部コンクリートが打ち継がれることにより形成されたものであって、フープ筋の内側において、上下方向に所定の間隔をあけて配設された複数の環状部材を備え、最下段に配設された前記環状部材は、前記上部コンクリートの打設を開始する際のトレミー管の下端の高さ位置から下方1000mm以下までの間に配置されている。
先行打設高さよりも下側に上部コンクリートを供給すると、上部コンクリートの領域が外側に向けて拡がり、下部コンクリートを外側に押し付けつつ上方に押し上げるようになるが、本発明の場所打ちコンクリート杭は、上部コンクリートがフープ筋の内側に配設された環状部材の外側に広がり難くなるので、外面(掘削孔の孔壁)に沿って押し上げられる下部コンクリートの高さを制限することができる。先行打設高さよりも上方に押し上げられる下部コンクリートの高さを小さくすることで、下部コンクリートから上部コンクリートに切り換える領域の高さが小さくなり、その結果、上部コンクリートの数量を削減することができるため、合理的な場所打ちコンクリート杭を構築できる。
The cast-in-place concrete pile of the present invention for solving the above-mentioned problems is formed by placing an upper concrete made of a different type of concrete from the lower concrete on the lower concrete, and comprising a hoop bar. A plurality of annular members arranged at predetermined intervals in the vertical direction are provided inside the . It is arranged between the height position of the lower end and 1000 mm or less below .
When the upper concrete is supplied below the pre-casting height, the area of the upper concrete expands outward, pushing the lower concrete upward while pushing it outward. However, the cast-in-place concrete pile of the present invention, Since it is difficult for the upper concrete to spread outside the annular member disposed inside the hoop reinforcement, the height of the lower concrete pushed up along the outer surface (hole wall of the borehole) can be limited. By reducing the height of the lower concrete that is pushed upwards from the pre-placement height, the height of the area where the lower concrete is switched to the upper concrete is reduced, and as a result, the quantity of the upper concrete can be reduced. , can construct reasonable cast-in-place concrete piles.

なお、最上段に配設された前記環状部材は、前記下部コンクリートの供給を停止するコンクリート打設面の高さ位置から上方1500mm以下に配設するのが望ましい。このようにすれば、先行打設高さよりも上方に押し上げられる下部コンクリートを環状部材に沿って誘導することができる。 In addition, it is preferable that the annular member arranged on the uppermost stage is arranged 1500 mm or less above the height position of the concrete placing surface where the supply of the lower concrete is stopped. In this way, the lower concrete pushed up above the pre-placement height can be guided along the annular member.

本発明のコンクリート構造物の構築方法は、下部コンクリートの上に前記下部コンクリートとは異なる種類のコンクリートからなる上部コンクリートを打ち継ぐコンクリート構造物の構築方法であって、地盤に掘削孔を形成する掘削工程と、主筋の内側に誘導部材が配筋された鉄筋籠を前記掘削孔に配置する配筋工程と、予め設定された先行打設高さまで前記下部コンクリートを供給する第一打設工程と、前記先行打設高さよりも下方の上部コンクリート供給開始高さから前記上部コンクリートの供給を開始して、予め設定された切換完了高さまで前記上部コンクリートを供給する第二打設工程と、前記切換完了高さの上方に前記上部コンクリートを供給する第三打設工程とを備えるものである。前記誘導部材は、前記上部コンクリート供給開始高さ位置から下方1000mm以下の高さ位置から前記先行打設高さ位置から上方1500mm以下の高さ位置の範囲内に配筋する。また、前記第二打設工程では、前記先行打設高さよりも下側において前記上部コンクリートを前記誘導部材の内側に供給し、前記下部コンクリートの一部が前記誘導部材の外側において前記先行打設高さよりも上側に押上げられる。
先行打設高さよりも下側に上部コンクリートを供給すると、上部コンクリートの領域が外側に向けて拡がり、下部コンクリートを外側に押し付けつつ上方に押し上げるようになるが、本発明によると、上部コンクリートが誘導部材の外側に広がり難くなるので、外面(掘削孔の孔壁)に沿って押し上げられる下部コンクリートの高さを制限することができる。先行打設高さよりも上方に押し上げられる下部コンクリートの高さを小さくすることで、下部コンクリートから上部コンクリートに切り換える領域の高さが小さくなり、その結果、上部コンクリートの数量を削減することができるため、合理的なコンクリート構造物を施工することができる。
A method of constructing a concrete structure according to the present invention is a method of constructing a concrete structure in which an upper concrete made of a different type of concrete from that of the lower concrete is placed on the lower concrete, and an excavation is performed to form an excavation hole in the ground. a rebar arrangement step of arranging a reinforcing bar cage in which a guide member is arranged inside the main reinforcement in the excavation hole; and a first placing step of supplying the lower concrete to a preset pre-placement height; a second placing step of starting supply of the upper concrete from an upper concrete supply start height lower than the preceding placing height and supplying the upper concrete to a preset switching completion height; and and a third placing step of supplying the upper concrete above the height. The guide members are arranged within a range from a height position of 1000 mm or less below the upper concrete supply starting height position to a height position of 1500 mm or less above the preceding placing height position. Further, in the second placing step, the upper concrete is supplied to the inside of the guide member below the pre-placement height, and a part of the lower concrete is placed outside the guide member by the pre-placement. Pushed upwards above height.
When the upper concrete is supplied below the pre-placement height, the area of the upper concrete expands outward, pushing the lower concrete outward while pushing it upward. According to the present invention, the upper concrete is guided. Since it becomes difficult to spread outside the member, it is possible to limit the height of the lower concrete pushed up along the outer surface (bore wall of the borehole). By reducing the height of the lower concrete that is pushed upwards from the pre-placement height, the height of the area where the lower concrete is switched to the upper concrete is reduced, and as a result, the quantity of the upper concrete can be reduced. , it is possible to construct rational concrete structures.

本発明の場所打ちコンクリート杭およびコンクリート構造物の構築方法によれば、種類が異なるコンクリートを高さ方向で連続して打設する場合において、打設コンクリートの強度の変化点を合理的に設定することが可能となる。その結果、上部コンクリートの数量を削減し、経済的なコンクリート構造物を施工することができる。 According to the cast-in-place concrete pile and the concrete structure construction method of the present invention, when concrete of different types is continuously placed in the height direction, the change point of the strength of the placed concrete is rationally set. becomes possible. As a result, the quantity of upper concrete can be reduced, and an economical concrete structure can be constructed.

本発明の実施形態に係る場所打ちコンクリート杭の一部を示す断面図である。It is a sectional view showing a part of cast-in-place concrete pile concerning an embodiment of the present invention. 場所打ちコンクリートの構築方法の各工程を示す断面図であって、(a)は掘削工程、(b)は配筋工程、(c)は第一打設工程、(d)は第二打設工程、(e)は第三打設工程である。Fig. 2 is a cross-sectional view showing each step of a cast-in-place concrete construction method, wherein (a) is an excavation step, (b) is a reinforcing bar arrangement step, (c) is a first placing step, and (d) is a second placing step. Step (e) is the third placing step. 先行打設高さよりも下側に供給した上部コンクリートを模式的に示す斜視図である。It is a perspective view which shows typically the upper concrete supplied below pre-placement height. 環状領域を模式的に示す斜視図である。FIG. 4 is a perspective view schematically showing an annular region; 場所打ちコンクリート杭の構築方法について実施した解析結果であって、比較例のトラックミキサー毎の打設終了時のコンクリート分布を示す。FIG. 10 shows the results of an analysis performed on the construction method of cast-in-place concrete piles, showing the distribution of concrete at the end of placing for each truck mixer of a comparative example. FIG. 場所打ちコンクリート杭の構築方法について実施した解析結果であって、実施例のトラックミキサー毎の打設終了時のコンクリート分布を示す。FIG. 5 shows the results of analysis performed on the construction method of cast-in-place concrete piles, showing the distribution of concrete at the end of placing for each truck mixer of the example. 場所打ちコンクリート杭の構築方法について実施した解析結果であって、(a)は比較例のコンクリート分布、(b)は実施例のコンクリート分布である。It is the analysis result which was implemented about the construction method of the cast-in-place concrete pile, and (a) is the concrete distribution of a comparative example, (b) is the concrete distribution of an Example.

本実施形態では、場所打ちコンクリート杭1において、合理的な杭の構築を目的として、図1に示すように、強度の異なる二種類のコンクリート(下部コンクリート2および上部コンクリート3)を深さ方向に連続して打設する場合について説明する。図1は、本実施形態の場所打ちコンクリート杭1の一部を示す断面図である。本実施形態の場所打ちコンクリート杭1(コンクリート構造物)の構築方法は、下部コンクリート2の上に下部コンクリート2よりも設計基準強度が高い上部コンクリート3を打ち継ぐものである。このようにすると、地震時に応力が大きくなる杭上部のコンクリート強度を高くすることができる。
場所打ちコンクリート杭1には、主筋41とフープ筋42とを組み合わせてなる鉄筋籠4が配筋されている。鉄筋籠4は、フープ筋42の内側に配筋された誘導筋(誘導部材)6を備えている。本実施形態の誘導筋6は、上下方向に所定の間隔をあけて配設された複数の第二のフープ筋(環状部材)61と、周方向に間隔をあけて配設されて第二のフープ筋61を支持する縦筋62とを備えている。
In this embodiment, in the cast-in-place concrete pile 1, as shown in FIG. A case of continuous casting will be described. FIG. 1 is a cross-sectional view showing part of a cast-in-place concrete pile 1 of this embodiment. In the construction method of the cast-in-place concrete pile 1 (concrete structure) of this embodiment, the upper concrete 3 having a higher design standard strength than the lower concrete 2 is placed on the lower concrete 2 . By doing so, it is possible to increase the concrete strength of the upper portion of the pile where stress increases during an earthquake.
The cast-in-place concrete pile 1 is provided with a reinforcement cage 4 formed by combining a main reinforcement 41 and a hoop reinforcement 42.例文帳に追加The reinforcing bar cage 4 includes guiding bars (guiding members) 6 arranged inside the hoop bars 42 . The guide bars 6 of the present embodiment include a plurality of second hoop bars (annular members) 61 arranged at predetermined intervals in the vertical direction, and second hoop bars (annular members) 61 arranged at intervals in the circumferential direction. and vertical bars 62 that support the hoop bars 61 .

以下、図2を参照して、本実施形態の場所打ちコンクリート杭1の構築方法について説明する。図2は、場所打ちコンクリート杭1の構築方法の各工程を示す断面図である。場所打ちコンクリート杭1の構築方法は、地盤Gに掘削孔11を形成する掘削工程と、掘削孔11内に場所打ちコンクリート杭1の鉄筋を配筋する配筋工程と、予め設定された先行打設高さHまで下部コンクリート2を掘削孔11内に供給する第一打設工程と、予め設定された切換完了高さHまで上部コンクリート3を掘削孔11内に供給する第二打設工程と、切換完了高さHの上方に上部コンクリート3を供給する第三打設工程とを備えている。 Hereinafter, a construction method of the cast-in-place concrete pile 1 of this embodiment will be described with reference to FIG. FIG. 2 is a sectional view showing each step of the construction method of the cast-in-place concrete pile 1. As shown in FIG. The construction method of the cast-in-place concrete pile 1 includes an excavation step of forming an excavation hole 11 in the ground G, a reinforcing bar arrangement step of arranging reinforcing bars of the cast-in-place concrete pile 1 in the excavation hole 11, and a pre-set pre-casting step. A first placing step of supplying the lower concrete 2 into the excavated hole 11 up to the installation height HL , and a second placing step of supplying the upper concrete 3 into the excavated hole 11 up to a preset switching completion height H. and a third placing step of supplying the upper concrete 3 above the switching completion height H.

掘削工程では、図2(a)に示すように、地盤Gを削孔することにより掘削孔11を形成する。掘削孔11は、設計された場所打ちコンクリート杭1の直径および長さを確保できる大きさに形成する。本実施形態では、ドリリングバケット7を回転させて掘削を行うアースドリル工法により掘削孔11を形成するものとする。なお、掘削孔11の掘削工法は限定されるものではない。 In the excavation step, as shown in FIG. 2(a), an excavation hole 11 is formed by excavating the ground G. As shown in FIG. The excavated hole 11 is formed in a size that can secure the designed diameter and length of the cast-in-place concrete pile 1 . In this embodiment, the excavation hole 11 is formed by an earth drilling method in which the drilling bucket 7 is rotated for excavation. In addition, the excavation construction method of the excavation hole 11 is not limited.

配筋工程では、図2(b)に示すように、主筋41とフープ筋42とを組み合わせた鉄筋籠4を掘削孔11に配置する。鉄筋籠4は、掘削孔11の孔壁から所定の被り厚さを確保できるように建て込む。このとき、鉄筋籠4の中央部に、トレミー管5を配管しておく。また、鉄筋籠4には、主筋41の内側に誘導筋6を配筋しておく。誘導筋6は第二のフープ筋61と縦筋62とを備えている。第二のフープ筋61は、鉄筋籠4のフープ筋42の内径よりも小さい内径を有している。第二のフープ筋61は、所定の範囲内において、高さ方向に所定の間隔をあけて配筋されている。上下に配筋された第二のフープ筋61は、周方向に間隔をあけて配筋された複数の縦筋62に固定されている。また、縦筋62は、鉄筋籠4を構成する主筋41またはフープ筋42から延設された横筋(図示せず)により支持されている。なお、第二のフープ筋61を横筋で支持する場合には、縦筋62は省略してもよい。また、第二のフープ筋61を省略し、上部コンクリート供給開始高さH以下の高さ位置から先行打設高さ以上の高さ位置までの長さを有した複数の鉄筋(縦筋62)を、周方向に所定の間隔をあけて配筋したものを誘導筋6としてもよい。
誘導筋6は、上部コンクリート供給開始高さH以下の高さ位置から先行打設高さH以上の高さ位置の範囲内に配筋する。本実施形態では、誘導筋6を配筋する範囲の下端を、上部コンクリート供給開始高さHから600mm下方の位置とする。また、誘導筋6を配筋する範囲の上端は、先行打設高さHから300mm上方に位置とする。なお、誘導筋6を配筋する範囲は、下端(最下段の第二のフープ筋61)が上部コンクリート供給開始高さHから掘削孔11の底面(杭下端)までの間で、上端(最上段の第二のフープ筋61)が先行打設高さH以上の位置であれば限定されるものではない。例えば、誘導筋6の下端と上部コンクリート供給開始高さHとの高低差が1000mm以下、誘導筋6の上端と先行打設高さHとの高低差が1500mm以下、より好ましくは500mm以下となるように設定してもよい。
In the bar arrangement process, as shown in FIG. 2B, a reinforcing bar cage 4 in which main bars 41 and hoop bars 42 are combined is placed in the excavation hole 11 . The reinforcing bar cage 4 is erected so as to secure a predetermined covering thickness from the hole wall of the excavation hole 11.例文帳に追加At this time, a tremie pipe 5 is laid in the center of the reinforcing bar cage 4 . Further, in the reinforcing bar cage 4, a guiding bar 6 is arranged inside the main bar 41.例文帳に追加The guide muscle 6 comprises a second hoop muscle 61 and a longitudinal muscle 62 . The second hoop bar 61 has an inner diameter smaller than the inner diameter of the hoop bar 42 of the reinforcing bar cage 4 . The second hoop reinforcements 61 are arranged at predetermined intervals in the height direction within a predetermined range. The second hoop reinforcements 61 arranged vertically are fixed to a plurality of vertical reinforcements 62 arranged at intervals in the circumferential direction. The vertical reinforcements 62 are supported by horizontal reinforcements (not shown) extending from the main reinforcements 41 or the hoop reinforcements 42 forming the reinforcing bar cage 4 . In addition, when the second hoop reinforcement 61 is supported by the horizontal reinforcement, the vertical reinforcement 62 may be omitted. In addition, the second hoop bar 61 is omitted, and a plurality of reinforcing bars (vertical bars 62 ) may be arranged at predetermined intervals in the circumferential direction as the guiding reinforcements 6 .
The guide bars 6 are arranged within a range from a height position equal to or lower than the upper concrete supply start height HT to a height position equal to or higher than the pre-placement height HL . In this embodiment, the lower end of the range in which the guide bars 6 are arranged is positioned 600 mm below the upper concrete supply start height HT . In addition, the upper end of the range in which the guide bars 6 are arranged shall be positioned 300 mm above the pre-placement height HL . The range in which the guide bars 6 are arranged is between the lower end (lowermost second hoop bar 61) and the upper end ( There is no limitation as long as the uppermost second hoop reinforcement 61) is at a position equal to or higher than the pre-placement height HL . For example, the height difference between the lower end of the guide bar 6 and the upper concrete supply start height HT is 1000 mm or less, and the height difference between the upper end of the guide bar 6 and the pre-placement height HL is 1500 mm or less, more preferably 500 mm or less. may be set so that

第一打設工程では、先行打設高さHまで下部コンクリート2を打設する。下部コンクリート2は、図2(c)に示すように、地中に形成された掘削孔11内に挿入されたトレミー管5を利用して掘削孔11の下端から供給する。下部コンクリート2の打設は、トレミー管5の下部の所定範囲が打設コンクリートに埋まるまでトレミー管5を固定した状態行い、その後、コンクリート打設面2aの上昇に伴ってトレミー管5を上昇させる。なお、トレミー管5は、一定量のコンクリートを打設する度に上昇させてもよいし、コンクリート打設面2aの上昇に合わせて上昇させてもよい。先行打設高さHは、切換完了高さHの下方に設定する。すなわち、場所打ちコンクリート杭1に作用する応力の推定値(設計値)から切換完了高さH(コンクリート強度を高くする範囲)を設定し、この切換完了高さHにおいてコンクリートが完全に切り換えられるように、先行打設高さHを設定する。 In the first placing step, the lower concrete 2 is placed to the pre-placement height HL . As shown in FIG. 2(c), the lower concrete 2 is supplied from the lower end of the excavated hole 11 using a tremie pipe 5 inserted into the excavated hole 11 formed in the ground. The lower concrete 2 is placed in a state where the tremie pipe 5 is fixed until a predetermined range of the lower part of the tremie pipe 5 is buried in the placed concrete, and then the tremie pipe 5 is raised as the concrete placing surface 2a rises. . The tremie pipe 5 may be raised each time a certain amount of concrete is placed, or may be raised in accordance with the rise of the concrete placing surface 2a. The pre-placement height HL is set below the switching completion height H. That is, from the estimated value (design value) of the stress acting on the cast-in-place concrete pile 1, the switching completion height H (the range in which the concrete strength is increased) is set, and the concrete is completely switched at this switching completion height H. , set the pre-placement height HL .

第二打設工程では、図2(d)に示すように、先行打設高さHよりも下方の上部コンクリート供給開始高さHにトレミー管5の先端を配置させた状態で、上部コンクリート3の供給を開始する。上部コンクリート3の供給は、コンクリートの打設面が切換完了高さHに到達するまで、トレミー管5の高さ位置を固定した状態で行う。上部コンクリート3を先行打設高さHよりも下側において誘導筋6の内側に供給すると、上部コンクリート3によって下部コンクリート2が押しのけられる。上部コンクリート3は、図3に示すように、下部コンクリート2内において供給開始時点のトレミー管5の直下に半楕円状または半円状(先端部分31)に供給された後、先端部分31の直上に広がり、図2(e)に示すように、誘導筋6の内面に沿った円柱状(円柱部分32)になる。一方、下部コンクリート2は、上部コンクリート3が供給されることによって、先行打設高さHの下側に供給された上部コンクリート3と同等の体積の下部コンクリート2が先行打設高さHの下側から先行打設高さよりも上側に移動する。先行打設高さHの上側に移動する下部コンクリート2は、誘導筋6の外側において上側に押し上げられる。誘導筋6の外側部分(トレミー管5を中心とした環状領域21)に押し上げられた下部コンクリート2の上端は、切換完了高さH以下に位置する。 In the second placing step, as shown in FIG. 2(d), the tip of the tremie pipe 5 is positioned at the upper concrete supply start height HT lower than the preceding placement height HL , and the upper portion Supply of concrete 3 is started. The upper concrete 3 is supplied while the height position of the tremie pipe 5 is fixed until the concrete placement surface reaches the switching completion height H. When the upper concrete 3 is supplied to the inner side of the guide bar 6 below the pre-placement height HL , the lower concrete 2 is pushed away by the upper concrete 3 . As shown in FIG. 3, the upper concrete 3 is supplied in a semielliptical or semicircular shape (tip portion 31) immediately below the tremie pipe 5 at the start of supply in the lower concrete 2, and then immediately above the tip portion 31. and, as shown in FIG. On the other hand, since the upper concrete 3 is supplied, the lower concrete 2 having a volume equivalent to that of the upper concrete 3 supplied to the lower side of the pre-placement height HL is increased to the pre-placement height HL. Move from the bottom of the to the top of the pre-placement height. The lower concrete 2 moving above the pre-placement height HL is pushed upward outside the guide bars 6 . The upper end of the lower concrete 2 pushed up by the outer portion of the guide bar 6 (annular region 21 centered on the tremie pipe 5) is positioned below the switching completion height H.

第三工程では、杭頭部まで上部コンクリート3を打設する。図2(e)に示すように、上部コンクリート3は、既打設コンクリートにトレミー管5の下端を挿入した状態で、トレミー管5を引き上げつつ打設する。トレミー管5を介して上部コンクリート3を供給することで、切換完了高さHの上方に上部コンクリート3が供給される。 In the third step, the upper concrete 3 is placed up to the pile head. As shown in FIG. 2( e ), the upper concrete 3 is placed while pulling up the tremie tube 5 with the lower end of the tremie tube 5 inserted into the already placed concrete. By supplying the upper concrete 3 through the tremie pipe 5, the upper concrete 3 is supplied above the switching completion height H.

先行打設高さHは、上部コンクリート3によって押し上げられた下部コンクリート2の上端が、切換完了高さH以下に位置するように設定する。
本実施形態では、先行打設高さHを式1により算出する。式1は、場所打ちコンクリート杭1の作用応力に基づいて設定された切換完了高さHから、上部コンクリート3の供給により上側に押し上げられる下部コンクリート2の環状領域21の高さhを差し引くことにより先行打設高さHを算出するものである。環状領域の高さhは、先行打設高さHよりも下側に供給された上部コンクリート3の体積Vが、環状領域21に移動した下部コンクリート2の体積であるとして、環状領域21の体積から算出する。ここで、先行打設高さHよりも下側に供給された上部コンクリート3は、図3に示すように、先端部分31と円柱部分32の体積の合計とする。一方、環状領域21は、図4に示すように、内径φ、外径φの円筒状体とする。ここで、内径φは、誘導筋6の内径とし、外径φは場所打ちコンクリート杭1の外径とする。また、円柱部分の直径φは、誘導筋6の内径とする。
The pre-placement height HL is set so that the upper end of the lower concrete 2 pushed up by the upper concrete 3 is positioned at the switching completion height H or less.
In this embodiment, the pre-placement height HL is calculated by Equation (1). Equation 1 is obtained by subtracting the height h of the annular region 21 of the lower concrete 2 pushed upward by the supply of the upper concrete 3 from the switching completion height H set based on the acting stress of the cast-in-place concrete pile 1. This is for calculating the pre-placement height HL . The height h of the annular region 21 is obtained by assuming that the volume V of the upper concrete 3 supplied below the pre-placement height HL is the volume of the lower concrete 2 moved to the annular region 21. Calculated from volume. Here, the upper concrete 3 supplied below the pre-placement height HL is the total volume of the tip portion 31 and the cylindrical portion 32, as shown in FIG. On the other hand, as shown in FIG. 4, the annular region 21 is a cylindrical body having an inner diameter φ i and an outer diameter φ 0 . Here, the inner diameter φ i is the inner diameter of the guide bar 6 and the outer diameter φ 0 is the outer diameter of the cast-in-place concrete pile 1 . Also, the diameter φr of the cylindrical portion is the inner diameter of the guide bar 6 .

=H-h ・・・ 式1
h=V/S
V=V1+V2
S=π/4×(φ -φ
V1=πφ /4×Δh
V2=2/3×πφ /4×Δh
:切換完了高さ
:環状領域の高さ
:先行打設高さよりも下側に供給した上部コンクリートの体積
V1 :先行打設高さよりも下側に供給した上部コンクリートの円柱部分の体積
V2 :先行打設高さよりも下側に供給した上部コンクリートの先端部分の体積
:環状領域の断面積
φ :環状領域の外径
φ :環状領域の内径
φ :先行打設高さよりも下側に供給した上部コンクリートの円柱部分の直径
Δh :第二工程において下部コンクリートに挿入するトレミー管の深さ
Δh:第二工程において供給された上部コンクリートの下端からトレミー管先端までの距離である下部流出深さ
H L =H−h Expression 1
h=V/S
V=V1+V2
S=π/4×(φ o 2 −φ i 2 )
V1=πφ r 2 /4×Δh
V2=2/3×πφ r 2 /4×Δh 0
H. : Switching completion height h : height of annular region V : Volume of upper concrete supplied below the pre-placement height V1 : Volume of the cylindrical portion of the upper concrete supplied below the pre-placement height V2 : Volume of the top part of the upper concrete supplied below the pre-placement height S : Cross-sectional area of the annular area φ o : Outer diameter of the annular area φ i : Inner diameter of the annular area φ r : Diameter of the cylindrical portion of the upper concrete supplied below the pre-placement height Δh : Depth of the tremie pipe inserted into the lower concrete in the second step Δh 0 : Lower outflow depth, which is the distance from the lower end of the upper concrete supplied in the second step to the tip of the tremie pipe

以上、本実施形態のコンクリート構造物の構築方法によれば、設計上の切換完了高さの近傍で、コンクリートの切り換えを完了させることができるため、強度が異なるコンクリートを高さ方向で連続して打設する場合において、打設コンクリートの強度の変化点を合理的に設定することが可能となる。その結果、必要な耐力を有した場所打ちコンクリート杭1を経済的に施工することができる。
先行打設高さよりも下側に上部コンクリート3を供給すると、上部コンクリート3の領域が外側に向けて拡がり、下部コンクリート2を外側に押し付けつつ上方に押し上げるようになるが、本実施形態のコンクリート構造物の構築方法によると、上部コンクリート3が誘導筋6の外側に広がり難くなるので、外面(掘削孔11の孔壁)に沿って押し上げられる下部コンクリート2の高さを制限することができる。先行打設高さよりも上方に押し上げられる下部コンクリート2の高さを小さくすることで、下部コンクリート2から上部コンクリート3に切り換える領域の高さが小さくなり、その結果、上部コンクリート3の数量を削減することができるため、合理的な場所打ちコンクリート杭1を施工することができる。
下部コンクリート2は、先行打設高さHの上側において誘導筋6の外周側を移動することが予想されるため、誘導筋6の外側部分を環状領域と仮定することで、切換完了高さHをより合理的に算出することができる。
As described above, according to the method for constructing a concrete structure of the present embodiment, the changeover of concrete can be completed near the designed changeover completion height. When placing concrete, it becomes possible to rationally set the change point of the strength of the placed concrete. As a result, the cast-in-place concrete pile 1 having the necessary bearing strength can be economically constructed.
When the upper concrete 3 is supplied below the pre-placement height, the region of the upper concrete 3 expands outward, pushing the lower concrete 2 outward while pushing it upward, but the concrete structure of this embodiment. According to the construction method of the object, since the upper concrete 3 is less likely to spread outside the guide bars 6, the height of the lower concrete 2 pushed up along the outer surface (hole wall of the excavation hole 11) can be limited. By reducing the height of the lower concrete 2 to be pushed upward from the pre-placement height, the height of the region where the lower concrete 2 is switched to the upper concrete 3 is reduced, and as a result, the quantity of the upper concrete 3 is reduced. Therefore, a rational cast-in-place concrete pile 1 can be constructed.
Since the lower concrete 2 is expected to move on the outer peripheral side of the guide bar 6 above the pre-placement height HL , by assuming that the outer portion of the guide bar 6 is an annular region, the switching completion height H can be calculated more rationally.

次に、本実施形態の場所打ちコンクリート杭1の構築方法について実施した解析結果について説明する。
本解析では、杭長8m、杭径2.4mのコンクリート杭に対して、被りが100mmとなるように、フープ筋42を160mm間隔で配筋した。また、フープ筋42の内側300mmの位置に、誘導筋6として、第二のフープ筋61を160mm間隔で配筋した。第二のフープ筋61は、杭底の上1.4m~3.6mの範囲に配筋した。コンクリート杭は、普通コンクリートである下部コンクリート2上に高強度コンクリートである上部コンクリート3を連続して打設するものとした。表1に上部コンクリート3と下部コンクリート2の諸元を示す。
コンクリートは、トレミー管5の上端から落下させることにより供給するものとし、トラックミキサー毎に打設されたコンクリートの挙動について解析を行った。表2にコンクリートの打設条件(トラックミキサー毎のコンクリート種類、打設量、打ち上がり高さ等)を示す。
また、比較例として、誘導筋6(第二のフープ筋61)を配筋しない場合についても同様の方法により解析を行った。
図5は、比較例における各トラックミキサー打設終了時のコンクリート分布の軸対称モデルであり、図6は、実施例における各トラックミキサー打設終了時のコンクリート分布の軸対称モデルである。また、図7(a)は、比較例の最終的なコンクリート分布の軸対称モデルであり、図7(b)は、実施例の最終的なコンクリート分布の軸対称モデルである。
Next, the results of the analysis performed for the construction method of the cast-in-place concrete pile 1 of this embodiment will be described.
In this analysis, hoop reinforcements 42 were arranged at intervals of 160 mm so as to cover a concrete pile having a pile length of 8 m and a pile diameter of 2.4 m so that the covering was 100 mm. Further, at a position 300 mm inside the hoop bar 42, as the guide bar 6, second hoop bars 61 were arranged at intervals of 160 mm. The second hoop reinforcement 61 was arranged in a range of 1.4m to 3.6m above the pile bottom. Concrete piles were constructed by continuously placing an upper concrete 3 of high-strength concrete on a lower concrete 2 of ordinary concrete. Table 1 shows the specifications of the upper concrete 3 and the lower concrete 2.
Concrete was supplied by dropping it from the upper end of the tremie pipe 5, and the behavior of the concrete placed for each truck mixer was analyzed. Table 2 shows concrete placement conditions (concrete type, placement amount, rising height, etc. for each truck mixer).
In addition, as a comparative example, the same method was used to analyze a case in which the guiding muscle 6 (second hoop muscle 61) was not arranged.
FIG. 5 is an axisymmetric model of concrete distribution at the end of placing each truck mixer in the comparative example, and FIG. 6 is an axisymmetric model of concrete distribution at the end of placing each truck mixer in the example. Also, FIG. 7(a) is an axisymmetric model of the final concrete distribution of the comparative example, and FIG. 7(b) is an axisymmetric model of the final concrete distribution of the example.

Figure 0007284104000001
Figure 0007284104000001

Figure 0007284104000002
Figure 0007284104000002

図5の5台目の図に示すように、比較例では、上部コンクリート3がトレミー管5の先端部で球根状に広がり、トレミー管5を周囲から直径を維持したまま円柱状に上昇する。その後、6台目以降のトラックミキサーのコンクリートが投入されると、上部コンクリート3がコンクリート打設面に広がった。球根状に広がった上部コンクリート3の直径は、鉄筋籠4の内径程度に留まる結果となった。一方、上部コンクリート3(鉄筋籠4)の外側では、下部コンクリート2が外面に押し付けられながら上昇した。すなわち、上部コンクリート3は、鉄筋籠4の内側で大きく広がるため、上部コンクリート3によって押し上げられた下部コンクリート2は大きく上昇する。その結果、図7(a)に示すように、先行打設高さHよりも上において、下部コンクリート2と上部コンクリート3とが混在する切り換え区間が2.1mになった。
図6の5台目の図に示すように、実施例においても、上部コンクリート3がトレミー管5の先端部で球根状に広がり、直径を維持したまま円柱状に上昇した。その後、6台目以降のトラックミキサーのコンクリートが投入されると、上部コンクリート3がコンクリート打設面に広がった。球根状に広がった上部コンクリート3の直径は、誘導筋6の内径程度に留まる結果となった。すなわち、実施例では、トレミー管5の先端近傍に誘導筋6を配置することで、上部コンクリート3の広がる範囲(直径)を小さくすることができた。上部コンクリート3の広がる範囲(直径)を小さくすることで、上部コンクリート3の外周囲の体積が大きくなるため、下部コンクリート2の上昇高さを抑制することができる。その結果、図7(b)に示すように、先行打設高さHよりも上において広がる切り換え区間(高さ)が1.4になり、比較例に比べて小さくなった。切換区間を小さくすることができれば、高強度コンクリートの打設量を少なくすることができ、その結果、合理的な構造設計や施工が可能となる。
As shown in the fifth diagram of FIG. 5, in the comparative example, the upper concrete 3 spreads in a bulbous shape at the tip of the tremie pipe 5 and rises in a columnar shape from the periphery of the tremie pipe 5 while maintaining its diameter. After that, when the concrete from the sixth and subsequent truck mixers was put in, the upper concrete 3 spread over the concrete placement surface. As a result, the diameter of the upper concrete 3, which spreads like a bulb, remains about the inner diameter of the reinforcing bar cage 4. On the other hand, outside the upper concrete 3 (reinforcement cage 4), the lower concrete 2 rose while being pressed against the outer surface. That is, since the upper concrete 3 spreads widely inside the reinforcing bar cage 4, the lower concrete 2 pushed up by the upper concrete 3 rises greatly. As a result, as shown in FIG. 7(a), the switching section where the lower concrete 2 and the upper concrete 3 coexist was 2.1 m above the pre-placement height HL .
As shown in the fifth figure of FIG. 6, also in the example, the upper concrete 3 spreads in a bulbous shape at the tip of the tremie pipe 5 and rises in a columnar shape while maintaining its diameter. After that, when the concrete from the sixth and subsequent truck mixers was put in, the upper concrete 3 spread over the concrete placement surface. As a result, the diameter of the upper concrete 3, which spreads like a bulb, remains about the inner diameter of the guide bar 6. That is, in the embodiment, by arranging the guide bars 6 in the vicinity of the tip of the tremie pipe 5, the range (diameter) over which the upper concrete 3 spreads can be reduced. By reducing the range (diameter) over which the upper concrete 3 spreads, the volume of the outer periphery of the upper concrete 3 increases, so that the height of the lower concrete 2 can be suppressed. As a result, as shown in FIG. 7(b), the switching section (height) widened above the pre-placement height HL was 1.4, which was smaller than in the comparative example. If the switching section can be made smaller, the amount of high-strength concrete placed can be reduced, and as a result, rational structural design and construction become possible.

以上、本発明に係る実施形態について説明したが、本発明は前述の実施形態に限られず、前記の各構成要素については本発明の趣旨を逸脱しない範囲で適宜変更が可能である。
例えば、前記実施形態では、円柱状の場所打ちコンクリート杭1を構築する場合について説明したが、コンクリート構造物は場所打ちコンクリート杭1に限定されるものではない。
前記実施形態では、上部コンクリート3として、下部コンクリート2よりも設計基準強度が高いコンクリートを打設するものとしたが、上部コンクリート3は、例えば、下部コンクリート2よりも流動性が高い等、下部コンクリート2とは種類が異なるコンクリートであれば限定されない。
また、前記実施形態では、第一打設工程および第三打設工程においてトレミー管5を引き上げつつコンクリートを打設する場合について説明したが、コンクリート打設時にトレミー管5を引き上げるか否かは適宜決定すればよく、トレミー管5を固定した状態で打設してもよい。同様に、第二打設工程においてはトレミー管5の高さ位置を固定した状態でコンクリートを打設する場合について説明したが、第二打設工程においてもトレミー管5を引き上げつつコンクリートを打設してもよい。
前記実施形態では、環状部材として、第二のフープ筋61を採用したが、環状部材を構成する材料は鉄筋に限定されるものではない。
Although the embodiments according to the present invention have been described above, the present invention is not limited to the above-described embodiments, and the constituent elements described above can be appropriately modified without departing from the scope of the present invention.
For example, in the above-described embodiment, a case of constructing a cylindrical cast-in-place concrete pile 1 has been described, but the concrete structure is not limited to the cast-in-place concrete pile 1 .
In the above-described embodiment, as the upper concrete 3, concrete having a higher design standard strength than the lower concrete 2 is cast. There is no limitation as long as the type of concrete is different from that of 2.
Further, in the above-described embodiment, the case where concrete is placed while pulling up the tremie tube 5 in the first placing process and the third placing process has been described, but whether or not the tremie tube 5 is pulled up during concrete placing is determined as appropriate. It may be determined, and the tremie tube 5 may be placed in a fixed state. Similarly, in the second placing process, the case where concrete is placed with the height position of the tremie tube 5 fixed has been described, but in the second placing process as well, the concrete is placed while pulling up the tremie tube 5. You may
In the above-described embodiment, the second hoop bar 61 is used as the annular member, but the material forming the annular member is not limited to reinforcing bars.

1 場所打ちコンクリート杭
11 掘削孔
2 下部コンクリート
3 上部コンクリート
4 鉄筋籠
41 主筋
42 フープ筋
5 トレミー管
6 誘導筋(誘導部材)
61 第二のフープ筋(環状部材)
REFERENCE SIGNS LIST 1 cast-in-place concrete pile 11 drill hole 2 lower concrete 3 upper concrete 4 reinforcing bar cage 41 main bar 42 hoop bar 5 tremie pipe 6 guiding bar (guiding member)
61 Second hoop muscle (annular member)

Claims (3)

下部コンクリートの上に前記下部コンクリートとは異なる種類のコンクリートからなる上部コンクリートが打ち継がれることにより形成された場所打ちコンクリート杭であって、
フープ筋の内側において、上下方向に所定の間隔をあけて配設された複数の環状部材を備え、
最下段に配設された前記環状部材は、前記上部コンクリートの打設を開始する際のトレミー管の下端の高さ位置から下方1000mm以下までの間に配置されていることを特徴とする場所打ちコンクリート杭。
A cast-in-place concrete pile formed by joining an upper concrete made of a different type of concrete from the lower concrete on the lower concrete,
A plurality of annular members arranged at predetermined intervals in the vertical direction inside the hoop muscles,
A casting-in-place characterized in that the annular member arranged at the lowest stage is arranged from the height position of the lower end of the tremie pipe when the placing of the upper concrete is started to 1000 mm or less below. Concrete pile.
最上段に配設された前記環状部材は、前記下部コンクリートの供給を停止するコンクリート打設面の高さ位置から上方1500mm以下に配設されていることを特徴とする、請求項1に記載の場所打ちコンクリート杭。 2. The method according to claim 1, wherein said annular member arranged at the uppermost stage is arranged at a height of 1500 mm or less above a concrete placing surface where supply of said lower concrete is stopped. Cast-in-place concrete piles. 下部コンクリートの上に前記下部コンクリートとは異なる種類のコンクリートからなる上部コンクリートを打ち継ぐコンクリート構造物の構築方法であって、
地盤に掘削孔を形成する掘削工程と、
主筋の内側に誘導部材を配設した鉄筋籠を前記掘削孔に配置する配筋工程と、
予め設定された先行打設高さまで前記下部コンクリートを供給する第一打設工程と、
前記先行打設高さよりも下方の上部コンクリート供給開始高さから前記上部コンクリートの供給を開始して、予め設定された切換完了高さまで前記上部コンクリートを供給する第二打設工程と、
前記切換完了高さの上方に前記上部コンクリートを供給する第三打設工程と、を備えており、
前記誘導部材は、前記上部コンクリート供給開始高さ位置から下方1000mm以下の高さ位置から前記先行打設高さ位置から上方1500mm以下の高さ位置の範囲内に配設し、
前記第二打設工程では、前記先行打設高さよりも下側において前記上部コンクリートを前記誘導部材の内側に供給し、前記下部コンクリートの一部が前記誘導部材の外側において前記先行打設高さよりも上側に押上げられることを特徴とする、コンクリート構造物の構築方法。
A method for constructing a concrete structure in which an upper concrete made of a different type of concrete from the lower concrete is placed on the lower concrete, comprising:
A drilling step of forming a drill hole in the ground;
A reinforcement arrangement step of arranging a reinforcing bar cage in which a guide member is arranged inside the main reinforcement in the excavation hole;
a first placing step of supplying the lower concrete to a preset pre-placement height;
a second placing step of starting to supply the upper concrete from an upper concrete supply start height lower than the preceding placing height, and supplying the upper concrete to a preset switching completion height;
a third placing step of supplying the upper concrete above the switching completion height,
The guide member is disposed within a range from a height position of 1000 mm or less below the upper concrete supply start height position to a height position of 1500 mm or less above the preceding placing height position,
In the second placing step, the upper concrete is supplied to the inside of the guide member below the pre-placement height, and part of the lower concrete is above the pre-placement height outside the guide member. A method for constructing a concrete structure, characterized in that both are pushed upward.
JP2020001821A 2020-01-09 2020-01-09 Method for constructing cast-in-place concrete piles and concrete structures Active JP7284104B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020001821A JP7284104B2 (en) 2020-01-09 2020-01-09 Method for constructing cast-in-place concrete piles and concrete structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020001821A JP7284104B2 (en) 2020-01-09 2020-01-09 Method for constructing cast-in-place concrete piles and concrete structures

Publications (2)

Publication Number Publication Date
JP2021110130A JP2021110130A (en) 2021-08-02
JP7284104B2 true JP7284104B2 (en) 2023-05-30

Family

ID=77059291

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020001821A Active JP7284104B2 (en) 2020-01-09 2020-01-09 Method for constructing cast-in-place concrete piles and concrete structures

Country Status (1)

Country Link
JP (1) JP7284104B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018119303A (en) 2017-01-25 2018-08-02 清水建設株式会社 Method for constructing cast-in-place concrete pile

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2757721B2 (en) * 1992-11-26 1998-05-25 株式会社大林組 Superfluid concrete casting method
JPH0762650A (en) * 1993-08-23 1995-03-07 Fujita Corp Assembling method of reinforcement cage
JP3094368B2 (en) * 1997-11-19 2000-10-03 大成建設株式会社 Construction of on-site development pile
JP4187738B2 (en) * 2005-10-14 2008-11-26 将玄 大川 Pile head treatment cap and mounting method of pile head treatment cap on top of double reinforcing bar

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018119303A (en) 2017-01-25 2018-08-02 清水建設株式会社 Method for constructing cast-in-place concrete pile

Also Published As

Publication number Publication date
JP2021110130A (en) 2021-08-02

Similar Documents

Publication Publication Date Title
KR101859136B1 (en) Cast in place top base having deep pile and construction method thereof
KR101777176B1 (en) Construction method of cast-in-placed-pile using steel pipes having different shapes to each other
CN105178358B (en) Vertical supporting system for reverse construction method and construction method of vertical supporting system
KR101977791B1 (en) Construction method of pile with Soil Cement mixing Foundation
JP7284104B2 (en) Method for constructing cast-in-place concrete piles and concrete structures
JP7085464B2 (en) How to build a retaining wall structure in the reverse striking method
JP7187743B2 (en) Confirmation method of concrete pouring and construction method of concrete structure
JP2001348866A (en) Work execution method for cast-in-place steel pipe concrete pile by all-casing construction method
KR101383817B1 (en) Top down method
JP7145682B2 (en) Concrete structure construction method
JP2005282043A (en) Earth retaining wall reinforcing method
JP6730121B2 (en) Underground wall construction method
JP7182485B2 (en) building construction method
JP5176788B2 (en) Construction method of underground structure
JP6693115B2 (en) Underground construction method
JP4833949B2 (en) Concrete integrated structure pillar
JP7171328B2 (en) Construction method of cast-in-place expansion piles
JP7230313B2 (en) Basement structure and construction method of basement
JP6938198B2 (en) Construction method
JP6514739B2 (en) Construction method for forming underground structure and underground structure completed thereby
JP5201719B2 (en) Column construction method and column structure
JP2021113400A (en) Underground wall
JP6740064B2 (en) Construction method of concrete frame
JP2022554045A (en) Underground vertical member construction method of reversed construction that is alternately constructed every other floor
KR20210073076A (en) Phc pile for soil retaining wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220419

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230123

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230124

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230222

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230509

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230518

R150 Certificate of patent or registration of utility model

Ref document number: 7284104

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150