JP7179678B2 - 地下構造物の構築方法 - Google Patents
地下構造物の構築方法 Download PDFInfo
- Publication number
- JP7179678B2 JP7179678B2 JP2019096991A JP2019096991A JP7179678B2 JP 7179678 B2 JP7179678 B2 JP 7179678B2 JP 2019096991 A JP2019096991 A JP 2019096991A JP 2019096991 A JP2019096991 A JP 2019096991A JP 7179678 B2 JP7179678 B2 JP 7179678B2
- Authority
- JP
- Japan
- Prior art keywords
- soundproof
- shaft
- underground structure
- constructing
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
これにより、掘削用の重機の故障対応や爆薬等の発破時の作業員の退避などを行うことができ、また開口によって蓋体の防音機能が損なわれることもない。
蓋体に照明装置を設けることで立坑の暗所を照らすことができて掘削作業の助けになり、夜間施工等も可能になる。また蓋体に散水装置や集塵装置を設けることで、地盤の掘削に伴う粉塵対策が可能になる。さらに、蓋体にセンサを設けて重機の動きや立坑の出来形を計測することもでき、それらの計測データによる工事管理を行うことが可能である。
本発明では立坑に蓋体を設けるので、従来のように掘削ずりを上方へ揚重して搬出すると作業効率が悪くなる。そこで、上記のような横坑と排出孔を先行して設けることで、掘削ずりを排出孔を介して下方の横坑へ排出し、横坑から外部に搬出することが可能になり、掘削ずりを容易に搬出できる。
深礎杭のような大規模な地下構造物では地盤掘削時の工事騒音も大きくなるので、防音機構を有する蓋体により周囲への騒音の伝播を防ぐことが特に有効である。
本実施形態では、まず図1に示すように山1の斜面の深礎杭の形成範囲11の下部に当たる深さで横坑2を形成する。また深礎杭の形成範囲11の上方の斜面を整地しておく。
本実施形態では、次に、掘削ずりの排出用のグローリーホール(排出孔)を深礎杭の形成範囲11に形成する。この際、まず図2(a)に示すように深礎杭の形成範囲11の上方の地表面にレイズボーリングマシン3を設置し、ロッド31の先端32に設けたビットで地盤を下方へと横坑2まで穿孔する。
本実施形態では、次に、図4(a)に示すようにグローリーホール12を含む深礎杭の形成範囲11で地盤の掘削を開始する。本実施形態では立坑13の上端外縁(坑口)をコンクリート等によるガイドウォール14によって補強し、地盤の掘削は重機4による削岩や爆薬等の発破によって行う。また、掘削作業と並行してコンクリート吹付による立坑13の孔壁保護も行われる。
この後、重機4等を横坑2から外部に搬出し、防音蓋5を坑内の底面の余掘り部分に吊り降して、深礎杭に必要な鉄筋(不図示)を坑内の所定位置にセットした後、図10に示すように立坑13および横坑2内にコンクリート17を打設することで深礎杭10が構築される。横坑2内のコンクリート17は、立坑13内のコンクリート17よりも貧配合のコンクリートとすることも可能である。
2:横坑
3:レイズボーリングマシン
4:重機
5:防音蓋
10、10a:深礎杭
12:グローリーホール
13:立坑
51:支持部
52:防音パネル
53:レール
54:防音扉
55:照明装置
56:散水装置
57:集塵装置
58:センサ
59:通信設備
Claims (7)
- 地下構造物の構築方法であって、
地盤を所定深さまで掘削して形成した立坑に地下構造物を構築し、
前記地盤を前記所定深さまで掘削する途中において、防音機構を有する蓋体を立坑の深さ方向の途中に設けることを特徴とする地下構造物の構築方法。 - 前記蓋体は、作業員または資機材が出入りするための開口を有し、前記開口が防音機構を有する扉により開閉可能であることを特徴とする請求項1に記載の地下構造物の構築方法。
- 前記蓋体は、前記立坑を照明する照明装置を有することを特徴とする請求項1または請求項2に記載の地下構造物の構築方法。
- 前記蓋体は、散水装置または集塵装置を有することを特徴とする請求項1から請求項3のいずれかに記載の地下構造物の構築方法。
- 前記蓋体は、重機の動きまたは立坑の出来形を計測するためのセンサを有することを特徴とする請求項1から請求項4のいずれかに記載の地下構造物の構築方法。
- 前記地盤に横坑および前記横坑から上方に延びる掘削ずりの排出用の排出孔を構築した後、前記排出孔を含む範囲の前記地盤を前記所定深さまで掘削し、
前記地盤の掘削時の掘削ずりは、前記排出孔に投入して前記横坑から搬出することを特徴とする請求項1から請求項5のいずれかに記載の地下構造物の構築方法。 - 前記地下構造物は、立坑にコンクリートを打設することで構築され、
前記蓋体が、前記立坑の底部において前記コンクリートに埋設されることを特徴とする請求項1から請求項6のいずれかに記載の地下構造物の構築方法。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019096991A JP7179678B2 (ja) | 2019-05-23 | 2019-05-23 | 地下構造物の構築方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019096991A JP7179678B2 (ja) | 2019-05-23 | 2019-05-23 | 地下構造物の構築方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2020190156A JP2020190156A (ja) | 2020-11-26 |
JP7179678B2 true JP7179678B2 (ja) | 2022-11-29 |
Family
ID=73453438
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2019096991A Active JP7179678B2 (ja) | 2019-05-23 | 2019-05-23 | 地下構造物の構築方法 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7179678B2 (ja) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004143742A (ja) | 2002-10-23 | 2004-05-20 | Ig:Kk | 掘削振動伝播抑制方法 |
JP2012229590A (ja) | 2011-04-27 | 2012-11-22 | Taisei Corp | 掘削土砂の搬出方法および掘削土砂の搬出システム |
JP2014091946A (ja) | 2012-11-02 | 2014-05-19 | Taisei Corp | 立坑 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03206299A (ja) * | 1989-12-29 | 1991-09-09 | Daimaru Bouon Kk | 竪坑開口部の防音用パネル蓋 |
JPH1136338A (ja) * | 1997-07-23 | 1999-02-09 | Shimizu Corp | 地下構造物の構築工法 |
-
2019
- 2019-05-23 JP JP2019096991A patent/JP7179678B2/ja active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004143742A (ja) | 2002-10-23 | 2004-05-20 | Ig:Kk | 掘削振動伝播抑制方法 |
JP2012229590A (ja) | 2011-04-27 | 2012-11-22 | Taisei Corp | 掘削土砂の搬出方法および掘削土砂の搬出システム |
JP2014091946A (ja) | 2012-11-02 | 2014-05-19 | Taisei Corp | 立坑 |
Also Published As
Publication number | Publication date |
---|---|
JP2020190156A (ja) | 2020-11-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11746493B2 (en) | Wall sinking construction method | |
CN107542108B (zh) | 一种建筑物地下室结构的逆向施工方法 | |
CN106545007B (zh) | 在下部为硬质岩层的地层中成桩的方法 | |
CN107842368A (zh) | 城市隧道钻凿铣机械组合非爆开挖工艺 | |
CN105714769A (zh) | 一种抗滑灌注桩施工方法 | |
JP6971170B2 (ja) | 地下構造物の構築方法 | |
CN110735432A (zh) | 盾构过侵限隧道范围内桩基清除及参数控制方法 | |
JP6043006B1 (ja) | 地中構造物の構築方法 | |
JP7179678B2 (ja) | 地下構造物の構築方法 | |
CN111851510B (zh) | 土岩基坑爆破开挖体系及应用其的施工方法 | |
CN113684838A (zh) | 一种嵌岩超深地下连续墙成槽施工的方法 | |
CN114855789A (zh) | 软土地区工程桩断桩处理施工工法 | |
KR101437882B1 (ko) | 각종 단면 형상을 갖는 터널 굴진 공법 | |
JPH11350899A (ja) | 大断面地下空洞の掘削方法及び同方法を用いた原石採掘場 | |
KR100731573B1 (ko) | 복선터널의 중간지지대 시공방법 | |
CN110144903A (zh) | 一种基坑支护遇防空洞的施工工法 | |
WO2010104235A1 (ko) | 강재 케이싱 토류벽을 이용한 지하광장 및 해저광장 굴착공법 | |
Baczynski et al. | Factors impacting and controlling water erosion of rock benches and slopes | |
JP2004003229A (ja) | 立坑の築造方法 | |
CN116906049B (zh) | 一种机械劈裂破除顶管大孤石施工方法 | |
CN217923525U (zh) | 岩溶地区近接既有地下结构物的挖孔护壁成桩结构 | |
CN212673968U (zh) | 土岩基坑爆破开挖体系 | |
CN113404496B (zh) | 一种受限空间超深竖井施工方法 | |
Swinn et al. | Cross river rail-blasting AA2 tunnel under cavern | |
SU1105649A1 (ru) | Способ сооружени дробильного пункта в карьере |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20211203 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20220817 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20220830 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20221025 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20221108 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20221116 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7179678 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |