JP7178908B2 - Temporary scaffolding in a tunnel - Google Patents
Temporary scaffolding in a tunnel Download PDFInfo
- Publication number
- JP7178908B2 JP7178908B2 JP2019000913A JP2019000913A JP7178908B2 JP 7178908 B2 JP7178908 B2 JP 7178908B2 JP 2019000913 A JP2019000913 A JP 2019000913A JP 2019000913 A JP2019000913 A JP 2019000913A JP 7178908 B2 JP7178908 B2 JP 7178908B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- scaffolding
- fixed
- joist
- brackets
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
本発明は、建設工事に用いられるトンネル内の仮設作業足場に関する。 The present invention relates to temporary work scaffolding in tunnels used in construction work.
シールド工法におけるトンネル工事のうち、特に道路トンネルでは、緊急時の避難や点検を目的として、併設する上下線トンネルの一部を切開き、互いを横坑で接続するUターン路や連絡道等が施工される。これらは一般に、地中内を非開削で行われるため、薬液注入工法やパイプルーフ等の補助工法を併用して、トンネル間の止水及び支保を確保する。この場合、補助工法の施工に必要な推進装置や薬液注入装置といった設備類を仮置きする足場が必要になるが、こうした横坑は、トンネル工事区間内に所定の間隔で複数設けられるため、横坑工事に補助工法施工のための諸設備を仮置きするための仮設足場を先行して架設すると、トンネル内を走行可能な大型の仮設台車(例えば、鉄筋台車、型枠台車、床版設置台車等)を必要とする側壁や床版の設置工事の障害になり得る。
そこで従来は、このような台車が全て通過した後に、仮設足場を設置して施工を行ってきた。
特許文献1,2には、トンネル工事における移動足場が開示されているが、これらはいずれもトンネル下部に施工されたインバートもしくは枕木に設置されたレール上を走行する形態であり、前記の仮設台車との干渉は免れない。
Among the tunnel constructions in the shield tunneling method, especially road tunnels, for the purpose of evacuation and inspection in an emergency, cut open a part of the parallel tunnels for up and down lines, and connect them with horizontal tunnels such as U-turn roads and connecting roads. be constructed. Since these are generally carried out without excavation in the ground, supplementary construction methods such as chemical injection methods and pipe roofs are used together to ensure water stoppage and support between tunnels. In this case, scaffolding is required to temporarily place equipment such as propulsion equipment and chemical injection equipment required for construction of the auxiliary construction method. If temporary scaffolding is installed in advance to temporarily place various equipment for auxiliary construction method construction in the tunnel, a large temporary trolley that can travel in the tunnel (e.g., reinforcing bar trolley, formwork trolley, floor slab installation trolley etc.) can be an obstacle to the installation work of side walls and floor slabs.
Therefore, conventionally, temporary scaffolding has been installed and construction has been carried out after all such trolleys have passed.
本発明は、補助工法の施工を確保することを可能としたトンネル内仮設足場を提供することを課題とする。 SUMMARY OF THE INVENTION An object of the present invention is to provide a temporary scaffolding in a tunnel that can ensure the construction of an auxiliary construction method.
前記課題を解決するための本発明のトンネル内仮設足場は、複数のセグメントピースからなるトンネル内面の断面方向の両側にそれぞれ該トンネルの軸方向に向かって間隔を開けて配置された複数のブラケットからなる2列のブラケット群と、前記各列のブラケット群の複数のブラケット上面を架渡すように前記トンネルの軸方向に向かって配置され、該複数のブラケットに固定された根太材と、対向する前記根太材の上面に架渡されるように前記トンネルの断面方向に配置され、該根太材に固定された梁と、前記トンネル上部に取り付けられた前記梁の中間部を支持する吊材と、前記梁の上に敷設された足場材と、を備えたトンネル内足場であって、前記ブラケットは、前記セグメントピース内に埋設されたインサートにボルトを介して前記覆工内面に固定され、前記梁は前記トンネルの略中央で上下に隙間を開けて重なるように配置された梁上段材および梁下段材と、該隙間に介設され、該梁上段材と該梁下段材とを連結した高さ調整材と、からなることを特徴とする。 The tunnel temporary scaffolding of the present invention for solving the above-mentioned problems comprises a plurality of brackets arranged on both sides in the cross-sectional direction of the inner surface of the tunnel made up of a plurality of segment pieces and spaced apart in the axial direction of the tunnel. and a joist material fixed to the plurality of brackets arranged in the axial direction of the tunnel so as to bridge the upper surfaces of the brackets of each row of the bracket group, and the joists facing the A beam arranged in the cross-sectional direction of the tunnel so as to span the upper surface of the joist material and fixed to the joist material, a suspension member that supports an intermediate portion of the beam attached to the upper part of the tunnel, and the beam scaffolding material laid on top of the bracket, wherein the bracket is fixed to the inner surface of the lining via a bolt to an insert embedded in the segment piece, and the beam is the An upper beam step member and a lower beam step member are arranged so as to overlap each other with a vertical gap in substantially the center of the tunnel, and a height adjustment member is interposed in the gap and connects the upper beam step member and the lower beam step member. and
本発明のトンネル内仮設足場をトンネルの上部に設けたことにより、簡易な構成で、かつ比較的安価に、補助工法の施工を確保することを可能にする。 By providing the in-tunnel temporary scaffolding of the present invention in the upper part of the tunnel, it is possible to secure the construction of the auxiliary construction method with a simple structure and at a relatively low cost.
以下に、本発明の実施形態について、図面を参照しながら説明する。
図1に薬液注入機材を載置した本発明のトンネル内仮設足場を示す。
本実施形態におけるトンネル内仮設足場3は、地盤G内に構築された円形トンネルTの外殻を形成する複数のセグメントピースからなる覆工1内面の幅方向に横架するように架渡された梁材33と、梁材33の上面に敷き詰められた足場材35とによって構成され、梁材33の両端は覆工1の内面に固定されたブラケット31,31から支持され、梁材33の略中央部を覆工1の内面から吊り下ろされた吊材34に固定されている。
Embodiments of the present invention will be described below with reference to the drawings.
FIG. 1 shows the temporary scaffolding in the tunnel of the present invention on which chemical injection equipment is placed.
The in-tunnel
ブラケット31は、複数のL形鋼材(アングル材)を組み合わせ、溶接により一体に加工されており、覆工1の内面の曲率に沿って密着する支持材と、該支持材の頂部に水平に覆工1の内面側に張出すようにその一端を固定された水平材と、該水平材の他端と該支持材の下方に固定された杖材とによってトラス形状に形成されており、山留支保工の腹起しを載置する際に用いるブラケットと同様の形態である。ブラケット31は、覆工1を形成するセグメントピース内に埋設されたインサートにボルトを介して覆工1に螺着、固定されている。
ブラケット31,31・・・は、トンネルTの軸方向に対しても、間隔を開けて配置され、ブラケット31,31・・・の上面を架渡すようにH形鋼材である側部根太材32がトンネル軸方向に載置され、固定されている。
The
The
次に、H形鋼材からなる梁材33は、左右の側部根太材32,32上面に架渡されるように、直交方向(トンネルTの断面方向)に配置され、側部根太材32,32間に固定されている。本実施形態における梁材33は、トンネルTの略中央で、2本の梁上段材331、梁下段材332が上下方向に重なるように配置されている。梁上段材331と梁下段材332は、H形鋼材からなる高さ調整材333を介して一体に固定されている。
Next, the
次に、H形鋼材から構成される吊材34は、孤材341と上部根太材342と柱材344及び下部根太材343を具備する。孤材341は、覆工1の上部略中央にトンネルTの断面方向に覆工1の内面に沿って密着するように、不図示のセグメントに埋設されたインサートにボルトで固定されている。孤材341,341・・・は、トンネルTの軸方向に所定の間隔を開けて複数設置されており、上部根太材342がトンネルTの軸方向に、孤材341,341・・・の下面に密着するように固定されている。トンネルTの平面視で上部根太材342に重なるように、下部根太材343が梁上段材331の上面に固定されている。また、鉛直に配置された柱材344は、上部根太材342の下面及び下部根太材343の上面に固定されている。
Next, the hanging
さらに、足場板35は、梁材33の上面に敷き詰められ足場が形成される。
足場板35は、既成品として一般に流通している鋼製の足場板を主として用いるが、端部等に生じる隙間については、必要に応じて鋼板等を加工して養生する。
Further, the
As the
このトンネル内仮設足場構造3は、例えば、図示されるように覆工1のインバート部に形成された軌条設備2上をトンネルTの軸方向に走行する側壁型枠台車F等の大型台車の往来に干渉しないように、側壁型枠台車Fよりも高い位置に配置することで、トンネル内仮設足場3上で行われる作業と、トンネル足場構造3の下方で行われる作業を安全かつ確実に分離することが可能になる。これにより、トンネルT内で複数の作業を並行して行うことが可能になり、工事全体の工程短縮を図れる。
同図のトンネル内仮設足場3上では、間隔を開けて併設された別なトンネルとの接続工事のための止水用の薬液注入に必要な施工設備等Mを配置しながら、覆工1の内部から外部に向かって複数の薬液注入管R,R・・・を打設、注入作業をすることができる。
This in-tunnel
On the
図2にパイプルーフ設置機材を載置した本発明のトンネル内仮設足場を示す。図1の薬液注入と同様に、トンネル内仮設足場3上に設置したパイプルーフを設置するための推進装置等の施工設備等Mを用いて、覆工1の内部から併設された別なトンネルに向かって複数のパイプルーフP,P・・・が打設することができる。
トンネル内仮設足場3の形態は、その下方を通過する側壁型枠台車F等の大型台車の障害にならない範囲で、高さ等を変更することで、トンネル内仮設足場3上で行われる各種作業に必要な内空を確保することが可能になる。
FIG. 2 shows the temporary scaffolding in the tunnel of the present invention on which the pipe roof installation equipment is placed. In the same way as the chemical solution injection in FIG. A plurality of pipe roofs P, P . . .
The form of the
以上より、本実施形態に係るトンネル内仮設足場は構成が簡易であるので安価であり、係る足場の下方で行われる施工を止めることなく足場上部の補助工法の施工を可能にする。 As described above, the in-tunnel temporary scaffolding according to the present embodiment has a simple structure, is inexpensive, and enables the construction of the upper part of the scaffolding by the auxiliary construction method without stopping the construction performed under the scaffolding.
以上、本発明の実施形態について説明したが、本発明は前記の実施形態に限られず、本発明の趣旨を逸脱しない範囲で適宜変更が可能である。
例えば、セグメントはコンクリート系ではなく鋼製セグメントでも良い。この場合、縦リブ等の仮設部材への溶接やボルト固定がインサートに代替される。また、上下段に分割された梁材を適用したが、1本ものでも良い。さらにトンネル形状は円形に係わらず、矩形や馬蹄形でも良い。
Although the embodiments of the present invention have been described above, the present invention is not limited to the above embodiments, and can be modified as appropriate without departing from the scope of the present invention.
For example, the segments may be steel segments rather than concrete-based. In this case, welding and bolting to temporary members such as vertical ribs are replaced by inserts. Moreover, although the beam material divided|segmented into the upper and lower stages was applied, a single piece may be sufficient. Furthermore, the shape of the tunnel may be rectangular or horseshoe-shaped instead of circular.
以上、本発明の実施形態について説明したが、本発明は前記の実施形態に限られず、本発明の趣旨を逸脱しない範囲で適宜変更が可能である。 Although the embodiments of the present invention have been described above, the present invention is not limited to the above embodiments, and can be modified as appropriate without departing from the scope of the present invention.
G 地盤
T トンネル
F 側壁型枠台車
R 薬液注入管
P パイプルーフ
M 施工設備等
1 覆工
2 軌条設備
3 トンネル内仮設足場
31 ブラケット
32 側部根太材
33 梁材
331 梁上段材
332 梁下段材
333 高さ調整材
34 吊材
341 孤材
342 上部根太材
343 下部根太材
344 柱材
35 足場板
G Ground T Tunnel F Side wall formwork truck R Chemical injection pipe P Pipe roof M Construction equipment, etc. 1
Claims (1)
前記各列のブラケット群の複数のブラケット上面を架渡すように前記トンネルの軸方向に向かって配置され、該複数のブラケットに固定された根太材と、
対向する前記根太材の上面に架渡されるように前記トンネルの断面方向に配置され、該根太材に固定された梁と、
前記トンネル上部に取り付けられた前記梁の中間部を支持する吊材と、
前記梁の上に敷設された足場材と、を備えたトンネル内足場であって、
前記ブラケットは、前記セグメントピース内に埋設されたインサートにボルトを介して前記覆工内面に固定され、
前記梁は前記トンネルの略中央で上下に隙間を開けて重なるように配置された梁上段材および梁下段材と、該隙間に介設され、該梁上段材と該梁下段材とを連結した高さ調整材と、からなることを特徴とするトンネル内足場。 two rows of bracket groups each comprising a plurality of brackets arranged at intervals in the axial direction of the tunnel on both sides in the cross-sectional direction of the inner surface of the tunnel composed of a plurality of segment pieces;
a joist member arranged in the axial direction of the tunnel so as to span the upper surfaces of the brackets of the bracket group in each row and fixed to the brackets;
a beam arranged in the cross-sectional direction of the tunnel so as to span the upper surfaces of the facing joist members and fixed to the joist members ;
a hanging member for supporting an intermediate portion of the beam attached to the upper part of the tunnel;
A scaffolding in a tunnel comprising scaffolding materials laid on the beams,
The bracket is fixed to the inner surface of the lining via a bolt to an insert embedded in the segment piece,
The beam is an upper beam step member and a lower beam step member which are arranged so as to overlap each other with a vertical gap in the approximate center of the tunnel, and are interposed in the gap to connect the upper beam step member and the lower beam step member. A scaffolding in a tunnel characterized by comprising a height adjusting member .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019000913A JP7178908B2 (en) | 2019-01-08 | 2019-01-08 | Temporary scaffolding in a tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2019000913A JP7178908B2 (en) | 2019-01-08 | 2019-01-08 | Temporary scaffolding in a tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2020111874A JP2020111874A (en) | 2020-07-27 |
JP7178908B2 true JP7178908B2 (en) | 2022-11-28 |
Family
ID=71665859
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2019000913A Active JP7178908B2 (en) | 2019-01-08 | 2019-01-08 | Temporary scaffolding in a tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7178908B2 (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014077283A (en) | 2012-10-10 | 2014-05-01 | Nippon Civic Engineering Consultant Co Ltd | Widened part construction method of tunnel and structure of tunnel widened part |
JP2016142098A (en) | 2015-02-04 | 2016-08-08 | 株式会社大林組 | Removal method for ceiling board |
JP2018044392A (en) | 2016-09-15 | 2018-03-22 | サンオー産業株式会社 | Length adjustment tool |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS50623B1 (en) * | 1969-04-26 | 1975-01-10 | ||
US3970200A (en) * | 1975-01-16 | 1976-07-20 | George Hyman Construction Co. | Gantry |
JPS5196141A (en) * | 1975-02-03 | 1976-08-23 | ||
US4051682A (en) * | 1976-07-15 | 1977-10-04 | Lockwood Jr James L | Method for installing ceiling panels in a tunnel |
-
2019
- 2019-01-08 JP JP2019000913A patent/JP7178908B2/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014077283A (en) | 2012-10-10 | 2014-05-01 | Nippon Civic Engineering Consultant Co Ltd | Widened part construction method of tunnel and structure of tunnel widened part |
JP2016142098A (en) | 2015-02-04 | 2016-08-08 | 株式会社大林組 | Removal method for ceiling board |
JP2018044392A (en) | 2016-09-15 | 2018-03-22 | サンオー産業株式会社 | Length adjustment tool |
Also Published As
Publication number | Publication date |
---|---|
JP2020111874A (en) | 2020-07-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7229368B2 (en) | High-speed construction structure and method for secondary lining in excavated tunnels with various cross-sections | |
JP5319216B2 (en) | Bridge girder erection device and bridge girder erection method | |
CN111236254A (en) | Foundation pit supporting structure close to subway and partition construction method | |
JP2018104972A (en) | Floor slab erection method and floor slab erection device | |
JP2020002563A (en) | Deck slab construction method | |
KR101844977B1 (en) | Scaffolding frame for tunnel | |
CN111305221A (en) | Method for replacing inner support of foundation pit | |
JP7178908B2 (en) | Temporary scaffolding in a tunnel | |
CN105971110A (en) | Construction method for fire control corridor steel structure supporting system | |
JP6644657B2 (en) | Temporary sleepers for shield tunnel construction | |
JP7185567B2 (en) | Bridge pier repair method | |
KR101653890B1 (en) | Tunnel elephant foot reinforcement beam construction method for tunnel stabilizing | |
JP4880374B2 (en) | How to build a bridge | |
CN110030005A (en) | The light-duty guarantor's circle support system of shield tunnel and its construction method | |
CN102454298B (en) | Large-sized reinforced concrete construction of frame beam method | |
JP2019173435A (en) | Floor system replacement method and floor system replacement device | |
JP2003027404A (en) | Method for constructing under-track structure | |
JP6740846B2 (en) | Floor slab replacement structure and floor slab replacement construction method | |
JP7003376B2 (en) | Construction method of structure | |
KR200432268Y1 (en) | Cover Plate integrated with the Frame | |
JP2020133214A (en) | Floor slab replacement method and vehicle going-over board | |
JP3665909B2 (en) | Bridge reconstruction method | |
CN216663835U (en) | Beam section sliding track system | |
JP7201449B2 (en) | Fixing jig for temporary internal shoring | |
US683426A (en) | Fireproof construction. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20210803 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20220525 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20220531 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20220726 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20221108 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20221115 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7178908 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |