JP7028639B2 - Filling construction method for joints - Google Patents

Filling construction method for joints Download PDF

Info

Publication number
JP7028639B2
JP7028639B2 JP2017253716A JP2017253716A JP7028639B2 JP 7028639 B2 JP7028639 B2 JP 7028639B2 JP 2017253716 A JP2017253716 A JP 2017253716A JP 2017253716 A JP2017253716 A JP 2017253716A JP 7028639 B2 JP7028639 B2 JP 7028639B2
Authority
JP
Japan
Prior art keywords
concrete
joint portion
filling
precast concrete
presser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017253716A
Other languages
Japanese (ja)
Other versions
JP2019120003A (en
Inventor
真男 福井
秀臣 河原
誠道 大場
孝之 岩城
高行 富永
一成 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Obayashi Road Corp
Original Assignee
Obayashi Corp
Obayashi Road Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Obayashi Road Corp filed Critical Obayashi Corp
Priority to JP2017253716A priority Critical patent/JP7028639B2/en
Publication of JP2019120003A publication Critical patent/JP2019120003A/en
Application granted granted Critical
Publication of JP7028639B2 publication Critical patent/JP7028639B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、継手部の充填施工方法に関し、特に、連設方向に複数並べて配置されたプレキャストコンクリート床版の継手部にコンクリートを充填して固化させることにより、隣接するプレキャストコンクリート床版を互いに接合する際に用いる継手部の充填施工方法に関する。 The present invention relates to a method for filling a joint portion, and in particular, joins adjacent precast concrete decks to each other by filling and solidifying the joint portions of a plurality of precast concrete decks arranged side by side in the continuous installation direction. It relates to the filling construction method of the joint part used at the time.

例えば道路橋においては、老朽化したコンクリート床版を撤去して、新しいコンクリート床版と置き換える工事が、今後益々増大してゆくものと考えられている。道路橋は、橋脚や橋台の上に架設された複数の橋桁に支持させて、これらの橋桁の上にコンクリート床版を設置し、さらにアスファルト舗装を施すことによって形成されるものであり、老朽化した道路橋が構築された当時は、コンクリート床版は、主に現場打ちコンクリートによって形成されていたが、新しいコンクリート床版と置き換える際には、工期の短縮化を図ると共に、道路橋をいち早く開放できるようにするために、予め工場等で精度良く形成されたプレキャスト製のコンクリート床版(以下プレキャストコンクリート床版とする)を用いて、コンクリート床版を形成する工事が主流になっている(例えば、特許文献1参照)。 For example, in road bridges, it is expected that the number of works to remove old concrete decks and replace them with new concrete decks will increase in the future. Road bridges are formed by supporting multiple bridge girders erected on pedestals and pedestals, installing concrete decks on these girders, and applying asphalt pavement, and are aging. At the time when the new concrete deck was constructed, the concrete deck was mainly made of cast-in-place concrete, but when replacing it with a new concrete deck, the construction period was shortened and the road bridge was opened as soon as possible. In order to make it possible, the mainstream work is to form a concrete deck using a precast concrete deck (hereinafter referred to as a precast concrete deck) that has been accurately formed in advance at a factory or the like (for example). , Patent Document 1).

例えば道路橋のコンクリート床版をプレキャストコンクリート床版を用いて形成する場合、図1に示すように、例えば橋桁50の延設方向Xの幅Bが180cm程度、橋桁50の延設方向Xと垂直な方向Yの長さLが10m程度の大きさとなるように形成された複数のプレキャストコンクリート床版10を、橋桁50の延設方向Xに例えば幅が20~40cm程度の間隔の継手部11を介在させながら、例えば2m程度のピッチで複数並べて設置し、しかる後に継手部11にコンクリートを供給して固化させることにより、隣接して設置されたプレキャストコンクリート床版10同士を一体として接合するようになっている。また、各々のプレキャストコンクリート床版10の幅方向(橋桁の延設方向)の端面には、プレキャストコンクリート床版10に埋設された鉄筋16の端部が突出しており(図2参照)、継手部11において、これらの対向する端面から突出する鉄筋16の端部をラップさせた状態で、コンクリートを供給して固化させることにより、複数のプレキャストコンクリート床版10が強固に接合一体化されたコンクリート床版20を得ることが可能になる。 For example, when a concrete deck of a road bridge is formed using a precast concrete deck, for example, the width B of the extension direction X of the bridge girder 50 is about 180 cm, and it is perpendicular to the extension direction X of the bridge girder 50, as shown in FIG. A plurality of precast concrete decks 10 formed so that the length L in the direction Y is about 10 m, and joint portions 11 having a width of about 20 to 40 cm, for example, in the extension direction X of the bridge girder 50. By interposing a plurality of them side by side at a pitch of, for example, about 2 m, and then supplying concrete to the joint portion 11 to solidify the concrete, the precast concrete decks 10 installed adjacent to each other are joined together. It has become. Further, the end of the reinforcing bar 16 embedded in the precast concrete slab 10 protrudes from the end face of each precast concrete slab 10 in the width direction (extending direction of the bridge girder) (see FIG. 2), and the joint portion. In 11, a concrete floor in which a plurality of precast concrete slabs 10 are firmly joined and integrated by supplying and solidifying concrete in a state where the ends of the reinforcing bars 16 protruding from these opposite end faces are wrapped. It becomes possible to obtain version 20.

特開2017-179926号公報JP-A-2017-179926

一方、例えば道路橋では、路面に降り注いだ雨水を排水するための例えば1.5~2%程度の排水勾配を、道路の横断方向に横断勾配として形成する必要があり、また道路の曲線部分では、車両の走行を安定させるための例えば6%程度の道路勾配を、道路の横断方向に横断勾配として形成する必要がある。このため、コンクリート床版20を形成するプレキャストコンクリート床版10もまた、表面部分に横断勾配Zを備えるように形成される場合があり、表面部分に横断勾配Zを備えるプレキャストコンクリート床版10の継手部11のコンクリートは、表面部分に横断勾配を備えるように形成する必要がある。 On the other hand, for example, in a road bridge, it is necessary to form a drainage gradient of, for example, about 1.5 to 2% for draining rainwater that has fallen on the road surface as a cross slope in the crossing direction of the road, and in the curved portion of the road. It is necessary to form a road gradient of, for example, about 6% in order to stabilize the running of the vehicle as a cross slope in the crossing direction of the road. Therefore, the precast concrete deck 10 forming the concrete deck 20 may also be formed so as to have a cross slope Z on the surface portion, and the joint of the precast concrete deck 10 having the cross slope Z on the surface portion. The concrete of the portion 11 needs to be formed so as to have a cross slope on the surface portion.

継手部11のコンクリートを、表面部分に横断勾配Zを備えるように形成する際に、施工性を鑑みて、特にコンクリートとして流動性が高くセルフレベリング性に優れた高強度のコンクリートを使用する場合には、継手部11に供給されたコンクリートは、横断勾配の下流側部分において、表面が水平になろうとすることで、継手部11の上面開口から溢れ易くなって、コンクリートの表面仕上げを行い難くなる。 When forming the concrete of the joint portion 11 so as to have a transverse gradient Z on the surface portion, in consideration of workability, particularly when a high-strength concrete having high fluidity and excellent self-leveling property is used as the concrete. The concrete supplied to the joint portion 11 tends to overflow from the upper surface opening of the joint portion 11 because the surface tends to be horizontal in the downstream portion of the transverse gradient, which makes it difficult to finish the surface of the concrete. ..

このため、従来の工法では、例えば図6に示すように、継手部11’の上面開口を覆って押え型枠12’を設置しておき、設置した押え型枠12’と、両側のプレキャストコンクリート床版10’の側面部10a’と、底型枠13’とによって囲まれる充填空間14’に、横断勾配の上流側からコンクリート15’を供給して充填することにより、充填されたコンクリート15’が継手部11’から溢れ出ないようにする施工方法が採用されていた。また、図6に示す従来の工法では、押え型枠12’は、継手部11’の両側のプレキャストコンクリート床版10’の端縁部の上面との間に、スペーサ部材30’を介在させて、プレキャストコンクリート床版10’の上面や継手部11’の上面開口よりも、5mm程度高い位置に下面を配置して、取り付けられるようになっている。これらの両側のスペーサ部材30’によって挟まれる嵩上げされた部分に、コンクリート15’が充填空間14’に充填された際にコンクリート15’から抜ける空気を逃がすことで、固化した後に嵩上げされた部分のコンクリ―ト15a’を除去して、品質が良好なコンクリート15’が、プレキャストコンクリート床版10’の上面よりも下方部分の継手部11’に、得られるようにしていた。 For this reason, in the conventional construction method, for example, as shown in FIG. 6, a presser form 12'is installed so as to cover the upper surface opening of the joint portion 11', and the set presser form 12'and precast concrete on both sides are installed. The concrete 15'filled by supplying concrete 15' from the upstream side of the transverse gradient to the filling space 14' surrounded by the side surface portion 10a' of the deck 10'and the bottom formwork 13'. A construction method was adopted to prevent concrete from overflowing from the joint portion 11'. Further, in the conventional construction method shown in FIG. 6, in the presser form 12', the spacer member 30'is interposed between the upper surface of the end edge portion of the precast concrete deck 10'on both sides of the joint portion 11'. , The lower surface is arranged at a position about 5 mm higher than the upper surface of the precast concrete deck 10'and the upper surface opening of the joint portion 11', and can be attached. When the concrete 15'is filled in the filling space 14', the air that escapes from the concrete 15'is released to the raised portion sandwiched by the spacer members 30'on both sides, so that the raised portion after solidification is formed. The concrete 15a'was removed to allow good quality concrete 15'to be obtained at the joint 11', which is below the top surface of the precast concrete deck 10'.

しかしながら、図6に示す従来の工法では、充填空間14’に充填されたコンクリート15’から抜ける空気を逃がすために余分に充填される、両側のスペーサ部材30’によって挟まれる嵩上げされた部分のコンクリート15a’は、充填されたコンクリート15’が固化した後に押え型枠12’やスペーサ部材30’を取り外した際に、相当の容積を保持したまま、プレキャストコンクリート床版10’の上面よりも突出した状態で残置されることになるため、このような突出した部分のコンクリート15a’を削り取って継手部11’の表面を仕上げる作業に、多くの手間を要することになる。 However, in the conventional construction method shown in FIG. 6, the raised portion of the concrete sandwiched between the spacer members 30'on both sides, which is additionally filled to allow air to escape from the concrete 15'filled in the filling space 14', is used. When the presser form 12'and the spacer member 30' are removed after the filled concrete 15'is solidified, the 15a'protrudes from the upper surface of the precast concrete deck 10' while maintaining a considerable volume. Since it is left in a state, it takes a lot of time and effort to scrape off the concrete 15a'of such a protruding portion and finish the surface of the joint portion 11'.

すなわち、例えば道路橋では、形成されたコンクリート床版20の上面に、アスファルト舗装を施工するのに先立って、防水層を敷設する必要があり、防水層を敷設するには、継手部11のコンクリート15の上面(表面)を、予め工場等で精度良く形成された高品質のプレキャストコンクリート床版10の上面(表面)と面一に、且つ平滑で均一に仕上げる必要がある。このようなことから、プレキャストコンクリート床版10’の上面よりも突出した部分の継手部11’のコンクリート15a’は、削り取って表面を仕上げる必要があり、継手部11’のコンクリート15a’を削り取って表面を仕上げるには、荒削りしたり、研磨したりするなどして、多くの手間を要することになる。また、研磨する際に粉塵や騒音を発生させて、周囲の環境に影響を及ぼすことになる。特に継手部11’のコンクリート15’として、流動性が高くセルフレベリング性に優れた高強度のコンクリートを用いた場合には、荒削りしたり、研磨したりする作業を複数回繰り返す必要を生じて、さらに多くの手間を要することになる。 That is, for example, in a road bridge, it is necessary to lay a waterproof layer on the upper surface of the formed concrete deck 20 prior to constructing asphalt pavement, and in order to lay the waterproof layer, the concrete of the joint portion 11 is laid. It is necessary to finish the upper surface (surface) of 15 so as to be flush with the upper surface (surface) of the high-quality precast concrete deck 10 formed in advance in a factory or the like with high accuracy, and to be smooth and uniform. For this reason, it is necessary to scrape off the concrete 15a'of the joint portion 11'that protrudes from the upper surface of the precast concrete deck 10', and scrape off the concrete 15a'of the joint portion 11'. Finishing the surface requires a lot of labor, such as rough cutting and polishing. In addition, dust and noise are generated during polishing, which affects the surrounding environment. In particular, when high-strength concrete having high fluidity and excellent self-leveling property is used as the concrete 15'of the joint portion 11', it becomes necessary to repeat rough cutting and polishing work a plurality of times. It will take more time and effort.

本発明は、横断勾配を有するプレキャストコンクリート床版の継手部のコンクリートの表面を、プレキャストコンクリート床版の表面と面一に、且つ平滑に仕上げる作業の手間を効果的に低減することのできる継手部の充填施工方法を提供することを目的とする。 INDUSTRIAL APPLICABILITY The present invention can effectively reduce the labor of finishing the concrete surface of the joint portion of the precast concrete deck having a transverse gradient so that it is flush with the surface of the precast concrete deck and is smooth. It is an object of the present invention to provide a filling construction method.

本発明は、連設方向に複数並べて配置されたプレキャストコンクリート床版の継手部にコンクリートを充填して固化させることにより、隣接するプレキャストコンクリート床版を互いに接合する際に用いる継手部の充填施工方法であって、複数並べて配置されたプレキャストコンクリート床版は、連設方向と垂直な方向に傾斜する横断勾配を表面部分に備えており、前記継手部の上面開口を覆って、押え型枠を、前記継手部の両側のプレキャストコンクリート床版の上に跨がるようにして設置し、継手部のコンクリートは、設置した前記押え型枠と、両側のプレキャストコンクリート床版の側面部と、底型枠とによって囲まれる充填空間に、横断勾配の上流側から供給されて充填されるようになっており、前記押え型枠の前記継手部の上面開口を覆う部分の下面には、空気溜リ部を形成する線状の凹溝が、当該継手部の上面開口を覆う部分の下面の全域に亘って複数形成されており、コンクリートの充填時にコンクリートから上方に抜ける空気を、複数の前記線状の凹溝に溜めながら、前記充填空間にコンクリートを充填する継手部の充填施工方法を提供することにより、上記目的を達成したものである。 INDUSTRIAL APPLICABILITY The present invention is a method for filling a joint portion used when joining adjacent precast concrete slabs to each other by filling and solidifying the joint portion of a plurality of precast concrete slabs arranged side by side in the continuous installation direction. The precast concrete slabs arranged side by side are provided with a cross slope inclined in the direction perpendicular to the continuous installation direction on the surface portion, and cover the upper surface opening of the joint portion to form a holding mold. It is installed so as to straddle the precast concrete slabs on both sides of the joint portion, and the concrete of the joint portion is the installed presser mold, the side portions of the precast concrete slabs on both sides, and the bottom mold. The filling space surrounded by the concrete is supplied from the upstream side of the transverse gradient to be filled, and an air reservoir is provided on the lower surface of the portion of the holding mold that covers the upper surface opening of the joint portion. A plurality of linear concave grooves to be formed are formed over the entire lower surface of the portion covering the upper surface opening of the joint portion, and the air that escapes upward from the concrete when the concrete is filled is allowed to flow upward from the concrete. The above object is achieved by providing a method for filling a joint portion in which concrete is filled in the filling space while being stored in a groove.

そして、本発明の継手部の充填施工方法は、前記線状の凹溝が、2~5mmの溝深さを有するように形成されていることが好ましい。 In the method for filling the joint portion of the present invention, it is preferable that the linear concave groove is formed so as to have a groove depth of 2 to 5 mm.

また、本発明の継手部の充填施工方法は、前記線状の凹溝が、三角形の断面形状を備えるように形成されていることが好ましい。 Further, in the method for filling the joint portion of the present invention, it is preferable that the linear concave groove is formed so as to have a triangular cross-sectional shape.

さらに、本発明の継手部の充填施工方法は、前記線状の凹溝が、これの延設方向と垂直な方向に並べて複数連接して形成されていることが好ましい。 Further, in the filling construction method of the joint portion of the present invention, it is preferable that the linear concave grooves are arranged in a direction perpendicular to the extending direction thereof and connected to each other.

さらにまた、本発明の継手部の充填施工方法は、前記線状の凹溝が、延設方向をプレキャストコンクリート床版の表面部分の横断勾配の傾斜方向に沿わせるようにして形成されていることが好ましい。 Furthermore, in the method of filling the joint portion of the present invention, the linear concave groove is formed so that the extension direction is along the inclination direction of the transverse gradient of the surface portion of the precast concrete deck. Is preferable.

また、本発明の継手部の充填施工方法は、前記押え型枠が、前記継手部の上面開口を覆って横断勾配の下流側から上流側に順次継ぎ足されて設置されるようになっており、順次継ぎ足された押え型枠と、両側のプレキャストコンクリート床版の側面部と、底型枠とによって囲まれる充填空間に、横断勾配の下流側から上流側に向けてコンクリートが順次充填されるようになっていることが好ましい。 Further, in the method of filling the joint portion of the present invention, the presser form is installed so as to cover the upper surface opening of the joint portion and to be sequentially added from the downstream side to the upstream side of the transverse gradient. The filling space surrounded by the presser form that was sequentially added, the side parts of the precast concrete decks on both sides, and the bottom formwork is filled with concrete sequentially from the downstream side to the upstream side of the cross slope. It is preferable that it is.

さらに、本発明の継手部の充填施工方法は、前記横断勾配の下流側から上流側に順次継ぎ足される前記押え型枠が、下流側の前記押え型枠に形成された線状の凹溝に、上流側の前記押え型枠に形成された線状の凹溝が連通するように配置されて、前記継手部の上面開口を覆って設置されるようになっていることが好ましい。 Further, in the method of filling the joint portion of the present invention, the presser form that is sequentially added from the downstream side to the upstream side of the cross slope is formed into a linear concave groove formed in the presser form on the downstream side. It is preferable that the linear concave groove formed in the presser form on the upstream side is arranged so as to communicate with each other so as to cover the upper surface opening of the joint portion.

また、本発明の継手部の充填施工方法は、前記押え型枠が、透明な合成樹脂による成形品となっていることが好ましい。 Further, in the method for filling the joint portion of the present invention, it is preferable that the presser form is a molded product made of a transparent synthetic resin.

本発明の継手部の充填施工方法によれば、横断勾配を有するプレキャストコンクリート床版の継手部のコンクリートの表面を、プレキャストコンクリート床版の表面と面一に、且つ平滑に仕上げる作業の手間を効果的に低減することができる。 According to the method of filling the joint portion of the present invention, it is effective to finish the concrete surface of the joint portion of the precast concrete deck having a transverse gradient so that it is flush with the surface of the precast concrete deck and is smooth. Can be reduced.

本発明の好ましい一実施形態に係る継手部の充填施工方法が適用される、道路橋にプレキャストコンクリート床版による新しいコンクリート床版を設ける工事を説明する略示斜視図である。It is a schematic perspective view explaining the construction which installs the new concrete deck by the precast concrete deck to the road bridge to which the filling construction method of the joint part which concerns on one preferred embodiment of this invention is applied. 本発明の好ましい一実施形態に係る継手部の充填施工方法を説明する、図1のA部拡大図である。It is an enlarged view of the part A of FIG. 1 explaining the filling construction method of the joint part which concerns on one preferable embodiment of this invention. 複数のプレキャストコンクリート床版を、継手部を介在させて橋桁の延設方向に所定のピッチで複数並べて設置した状態を説明する上面図である。It is a top view explaining the state in which a plurality of precast concrete decks are arranged side by side at a predetermined pitch in the extension direction of a bridge girder with a joint portion interposed therebetween. 本発明の好ましい一実施形態に係る継手部の充填施工方法を説明する、図2のB-Bに沿った断面図である。It is sectional drawing which follows BB of FIG. 2 explaining the filling construction method of the joint part which concerns on one preferable embodiment of this invention. 線状の凹溝に空気が溜められた状態を説明する、図4のC部拡大図である。It is an enlarged view of the part C of FIG. 4 explaining the state which the air is accumulated in the linear concave groove. 従来の継手部の充填施工方法を説明する、図3のB-Bに沿った断面図である。It is sectional drawing which follows the BB of FIG. 3 explaining the conventional filling construction method of a joint part.

本発明の好ましい一実施形態に係る継手部の充填施工方法は、例えば図1に示す道路橋における老朽化したコンクリート床版を撤去して、プレキャストコンクリート床版10による新しいコンクリート床版20と置き換える工事において、図2に示すように、隣接するプレキャストコンクリート床版10の間の継手部11の上面開口を覆って、押え型枠12を設置することにより実施される。本実施形態に係る継手部の充填施工方法は、現場打ちによるコンクリートを継手部11に供給して固化させることにより、隣接するプレキャストコンクリート床版10同士を接合一体化する際に、継手部11のコンクリート15(図4参照)を、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13と、継手部11の上面開口を覆う押え型枠12とによって囲まれる充填空間14に、横断勾配Zの上流側から供給して充填するための施工方法として採用されたものである。 The method for filling the joint portion according to a preferred embodiment of the present invention is, for example, a work of removing an aged concrete deck in a road bridge shown in FIG. 1 and replacing it with a new concrete deck 20 by a precast concrete deck 10. In, as shown in FIG. 2, it is carried out by covering the upper surface opening of the joint portion 11 between the adjacent precast concrete decks 10 and installing the holding mold 12. In the method of filling the joint portion according to the present embodiment, concrete cast in the field is supplied to the joint portion 11 and solidified, so that when adjacent precast concrete slabs 10 are joined and integrated, the joint portion 11 is formed. The concrete 15 (see FIG. 4) is traversed by a filling space 14 surrounded by side surface portions 10a of the precast concrete floor slabs 10 on both sides, a bottom formwork 13, and a holding formwork 12 covering the upper surface opening of the joint portion 11. It was adopted as a construction method for supplying and filling from the upstream side of the gradient Z.

すなわち、本実施形態では、道路橋は、例えば道路の曲線部分を構成する道路橋となっており、形成されるコンクリート床版20は、道路の横断方向に、片側に傾斜する道路勾配のための例えば6%程度の横断勾配Zを有するものとなっている。また、コンクリート床版20を形成するプレキャストコンクリート床版10もまた、表面部分に道路勾配のための横断勾配Zを備えるように形成されており、これらの横断勾配Zを備えるプレキャストコンクリート床版10の間の継手部11のコンクリートもまた、表面部分に横断勾配Zを備えるように形成する必要がある。 That is, in the present embodiment, the road bridge is, for example, a road bridge constituting a curved portion of the road, and the formed concrete deck 20 is for a road slope inclined to one side in the crossing direction of the road. For example, it has a cross slope Z of about 6%. Further, the precast concrete deck 10 forming the concrete deck 20 is also formed so as to have a cross slope Z for the road slope on the surface portion, and the precast concrete deck 10 having these cross slopes Z is provided. The concrete of the joint portion 11 between them also needs to be formed so as to have a transverse gradient Z on the surface portion.

このため、本実施形態では、継手部11に供給されたまだ固まらない状態のコンクリート15は、特に流動性が高くセルフレベリング性に優れた高強度のコンクリートが用いられている場合には、横断勾配Zの下流側部分において、表面が水平になろうとすることで、継手部11の上面開口から溢れ易くなることから、継手部11の上面開口を覆って好ましくは横断勾配Zの下流側から押え型枠12を設置しておき、設置した押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの上流側からコンクリート15(図4参照)を供給して充填することにより、充填されたコンクリート15が継手部11から溢れ出ないようにすることができるようになっている。 Therefore, in the present embodiment, the concrete 15 in a state of not being solidified supplied to the joint portion 11 has a transverse gradient, especially when a high-strength concrete having high fluidity and excellent self-leveling property is used. Since the surface of the downstream portion of Z tends to be horizontal, it tends to overflow from the upper surface opening of the joint portion 11. Therefore, it covers the upper surface opening of the joint portion 11 and is preferably a presser form from the downstream side of the transverse gradient Z. A frame 12 is installed, and concrete is placed in the filling space 14 surrounded by the installed presser form 12, the side surface portions 10a of the precast concrete deck 10 on both sides, and the bottom form 13 from the upstream side of the transverse gradient Z. By supplying and filling the concrete 15 (see FIG. 4), the filled concrete 15 can be prevented from overflowing from the joint portion 11.

また、本実施形態の継手部の充填施工方法は、上述のように押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの上流側からコンクリート15(図4参照)を供給して充填する際に、充填したコンクリート15から抜ける空気を、プレキャストコンクリート床版10の上面や継手部11の上面開口よりも上方に逃がすことができるようにすると共に、充填したコンクリート15が固化した後に、固化した継手部11のコンクリートの表面を、プレキャストコンクリート床版10の表面と面一に、且つ平滑に仕上げる作業の手間を、効果的に低減できるようにする機能を備えている。 Further, in the method of filling the joint portion of the present embodiment, as described above, the filling space 14 surrounded by the presser form 12, the side surface portions 10a of the precast concrete deck 10 on both sides, and the bottom form 13 is used. When the concrete 15 (see FIG. 4) is supplied and filled from the upstream side of the transverse gradient Z, the air released from the filled concrete 15 is sent above the upper surface of the precast concrete deck 10 and the upper surface opening of the joint portion 11. It takes time and effort to make the concrete surface of the solidified joint portion 11 flush with the surface of the precast concrete floor slab 10 and to be smooth after the filled concrete 15 is solidified. It has a function that enables effective reduction.

そして、本実施形態の継手部の充填施工方法は、図1~図3に示すように、連設方向である橋桁50の延設方向Xに複数並べて配置されたプレキャストコンクリート床版10の継手部11にコンクリート15を充填して固化させることにより、隣接するプレキャストコンクリート床版10を互いに接合する際に用いる充填施工方法であって、複数並べて配置されたプレキャストコンクリート床版10は、連設方向Xと垂直な方向Yに片側に傾斜する横断勾配Zを表面部分に備えており、継手部11のコンクリート15は、図4にも示すように、当該継手部11の上面開口を覆って押え型枠12を設置し(図2参照)、設置した押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの上流側から供給されて充填されるようになっている。押え型枠12の継手部11の上面開口を覆う部分の下面には、図4に示すように、空気溜リ部を形成する線状の凹溝12aが、当該継手部11の上面開口を覆う部分の下面の全域に亘って複数形成されており、コンクリート15の充填時にコンクリート15から上方に抜ける空気を、複数の線状の凹溝12aに溜めながら、充填空間14にコンクリート15を充填するようになっている。 As shown in FIGS. 1 to 3, the method of filling the joint portion of the present embodiment is a joint portion of the precast concrete floor slab 10 arranged side by side in the extension direction X of the bridge girder 50 which is the continuous installation direction. It is a filling construction method used when adjoining adjacent precast concrete slabs 10 by filling 11 with concrete 15 and solidifying the concrete 15, and a plurality of precast concrete slabs 10 arranged side by side are connected in the continuous direction X. The surface portion is provided with a transverse gradient Z that is inclined to one side in the direction Y perpendicular to the direction Y, and the concrete 15 of the joint portion 11 covers the upper surface opening of the joint portion 11 and is a presser form as shown in FIG. 12 is installed (see FIG. 2), and the upstream side of the cross slope Z is provided in the filling space 14 surrounded by the installed presser form 12, the side surface portions 10a of the precast concrete floor slabs 10 on both sides, and the bottom form 13. It is supplied from and filled. As shown in FIG. 4, a linear concave groove 12a forming an air reservoir portion covers the upper surface opening of the joint portion 11 on the lower surface of the portion of the presser form 12 that covers the upper surface opening of the joint portion 11. A plurality of pieces are formed over the entire lower surface of the portion, and the filling space 14 is filled with the concrete 15 while collecting the air that escapes upward from the concrete 15 in the plurality of linear concave grooves 12a when the concrete 15 is filled. It has become.

また、本実施形態では、線状の凹溝12aは、好ましくは三角形の断面形状を備えるように形成されており、これの延設方向と垂直な方向に並べて複数連接して形成されている。さらに、線状の凹溝12aは、これの延設方向をプレキャストコンクリート床版10の表面部分の横断勾配Zの傾斜方向である、プレキャストコンクリート床版10の連設方向Xと垂直な方向Yに、沿わせるようにして形成されている。 Further, in the present embodiment, the linear concave groove 12a is preferably formed so as to have a triangular cross-sectional shape, and is formed by arranging a plurality of linear concave grooves 12a in a direction perpendicular to the extending direction thereof. Further, the linear concave groove 12a extends in the direction Y perpendicular to the continuous installation direction X of the precast concrete deck 10, which is the inclination direction of the transverse gradient Z of the surface portion of the precast concrete deck 10. , It is formed so as to follow.

本実施形態では、老朽化したコンクリート床版を撤去して、プレキャストコンクリート床版10による新しいコンクリート床版20と置き換える工事が行われる道路橋は、例えば高速道路の曲線部分を構成する道路橋となっており、図1に示すように、道路の延長方向に所定の間隔をおいて構築された橋脚51に支持させて、複数本の橋桁50が、延設方向Xを平行に配置して架設されている。これらの橋桁50に支持させて、複数のプレキャストコンクリート床版10が、図2及び図3に示すように、橋桁50の延設方向Xに例えば幅が15~50cm程度、より好ましくは20~40cm程度の間隔の継手部11を介在させながら、例えば2m程度のピッチで複数並べて設置される。プレキャストコンクリート床版10は、例えば橋桁50の延設方向Xの幅Bが180cm程度、橋桁50の延設方向Xと垂直な方向Yの長さLが10m程度の大きさとなるように形成されており、各々のプレキャストコンクリート床版10の幅方向(橋桁の延設方向)の端面である側面部10aには、プレキャストコンクリート床版10に埋設された鉄筋16の端部が突出している。継手部11において、これらの対向する側面部10aから突出する鉄筋16の端部をラップさせると共に、適宜補強用の鉄筋が配筋されるようになっている。 In the present embodiment, the road bridge to which the old concrete deck is removed and replaced with the new concrete deck 20 by the precast concrete deck 10 is, for example, a road bridge constituting a curved portion of a highway. As shown in FIG. 1, a plurality of bridge girders 50 are erected with extension directions X arranged in parallel so as to be supported by bridge pedestals 51 constructed at predetermined intervals in the extension direction of the road. ing. Supporting these bridge girders 50, a plurality of precast concrete decks 10 have a width of, for example, about 15 to 50 cm, more preferably 20 to 40 cm, in the extension direction X of the bridge girder 50, as shown in FIGS. 2 and 3. A plurality of joint portions 11 are installed side by side at a pitch of, for example, about 2 m while interposing joint portions 11 at intervals of about 2 m. The precast concrete deck 10 is formed so that, for example, the width B of the extension direction X of the bridge girder 50 is about 180 cm, and the length L of the direction Y perpendicular to the extension direction X of the bridge girder 50 is about 10 m. The end portion of the reinforcing bar 16 embedded in the precast concrete deck 10 projects from the side surface portion 10a which is the end surface of each precast concrete deck 10 in the width direction (extending direction of the bridge girder). In the joint portion 11, the end portions of the reinforcing bars 16 protruding from the facing side surface portions 10a are wrapped, and reinforcing bars for reinforcement are appropriately arranged.

また、本実施形態では、各々のプレキャストコンクリート床版10の底面部における、橋桁50の延設方向Xと垂直な方向Yに沿った両側の端縁部には、コンクリートを打ち込んだ後に構造物の一部となって解体を要しない型枠となる埋設型枠13aが、プレキャストコンクリート床版10の製造時に両側に張り出すようにして予め取り付けられている(図2、図3参照)。プレキャストコンクリート床版10を、橋桁50に支持させて複数並べて設置する際に、各々の継手部11においてこれらの埋設型枠13aを互いに突き合わせることによって、底型枠13が継手部11の底面部に形成される。さらに、本実施形態では、継手部11の横断勾配Zの下流側の端部には、プレキャストコンクリート床版10の橋桁50の延設方向Xと垂直な方向Yの端部の側面に沿わせるようにして、妻型枠17、が公知の方法によって取り付けられている(図2参照)。 Further, in the present embodiment, in the bottom surface portion of each precast concrete deck 10, concrete is poured into the end edges on both sides along the extension direction X and the direction Y perpendicular to the extension direction X of the bridge girder 50, and then the structure is constructed. An embedded formwork 13a, which is a part of the formwork that does not require dismantling, is preliminarily attached so as to project to both sides at the time of manufacturing the precast concrete deck 10 (see FIGS. 2 and 3). When a plurality of precast concrete floor slabs 10 are supported by the bridge girder 50 and installed side by side, the bottom formwork 13 is formed by abutting the embedded formwork 13a at each joint portion 11 so that the bottom form 13 is formed on the bottom surface portion of the joint portion 11. Formed in. Further, in the present embodiment, the downstream end of the cross slope Z of the joint portion 11 is aligned with the side surface of the end portion in the direction Y perpendicular to the extension direction X of the bridge girder 50 of the precast concrete deck 10. The wife mold 17 is attached by a known method (see FIG. 2).

そして、本実施形態では、底型枠13及び妻型枠17が取り付けられた各々の継手部11の好ましくは横断勾配Zの下流側から、継手部11の上面開口を覆って押え型枠12を設置し、設置した押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの上流側から継手部11のコンクリート15を供給して充填するようになっている。 Then, in the present embodiment, the presser form 12 is formed by covering the upper surface opening of the joint portion 11 from the downstream side of each joint portion 11 to which the bottom form 13 and the end form 17 are attached , preferably from the downstream side of the transverse gradient Z. In the filling space 14 surrounded by the presser formwork 12 installed and installed, the side surface portions 10a of the precast concrete deck 10 on both sides, and the bottom formwork 13, the concrete 15 of the joint portion 11 from the upstream side of the cross slope Z. Is to be supplied and filled.

ここで、本実施形態では、押え型枠12は、図4に示すように、例えば橋桁50の延設方向Xに例えば15~50cm程度の間隔をおいて設けられた継手部11の幅よりも大きな、例えば30~60cm程度の幅を備えている。押え型枠12は、両側の側端部12bの間の部分である、下面側に線状の凹溝12aが形成された中間部分を、継手部11の上面開口を覆ってこれの直上部分に配置した状態で、継手部11の両側のプレキャストコンクリート床版10の上に跨がるようにして取り付けられる。押え型枠12は、例えば1.5m程度の長さを有しており、両側の側端部12bを、両側のプレキャストコンクリート床版10の側縁部の上に載置した状態で、押え型枠12の長さ方向に所定の間隔をおいて配設された桟木18を、押え型枠12の幅方向に交差させて取り付け、押え型枠12からはみ出している桟木18の両端部分から両側のプレキャストコンクリート床版10に向けて、アンカー部材19を打ち込むことによって、プレキャストコンクリート床版10から浮き上がらない状態で固定される。これによって、押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる、充填空間14が形成される。 Here, in the present embodiment, as shown in FIG. 4, the presser form 12 is wider than the width of the joint portion 11 provided at an interval of, for example, about 15 to 50 cm in the extension direction X of the bridge girder 50, for example. It has a large width, for example, about 30 to 60 cm. The presser form 12 covers the upper surface opening of the joint portion 11 with an intermediate portion having a linear concave groove 12a formed on the lower surface side, which is a portion between the side end portions 12b on both sides, and forms a portion directly above the intermediate portion. In the arranged state, it is attached so as to straddle the precast concrete decks 10 on both sides of the joint portion 11. The presser form 12 has a length of, for example, about 1.5 m, and the presser form 12b is placed on the side edges of the precast concrete floor slabs 10 on both sides. The stiles 18 arranged at predetermined intervals in the length direction of the frame 12 are attached so as to cross each other in the width direction of the presser form 12, and both sides of the stile 18 protruding from the presser form 12 are both sides. By driving the anchor member 19 toward the precast concrete slab 10, the anchor member 19 is fixed in a state where it does not rise from the precast concrete slab 10. As a result, a filling space 14 is formed, which is surrounded by the presser form 12, the side surface portions 10a of the precast concrete decks 10 on both sides, and the bottom form 13.

また、本実施形態では、押え型枠12は、例えば1.5m程度の長さを有しており、隣接するプレキャストコンクリート床版10の間の継手部11は、例えば10m程度の長さを有していることから、継手部11の上面開口を覆って横断勾配Zの下流側から上流側に順次継ぎ足されて設置されるようになっている(図2参照)。順次継ぎ足された押え型枠12と、両側のプレキャストコンクリート床版10の側面部と、底型枠13とによって囲まれる充填空間14には、横断勾配Zの下流側から上流側に向けてコンクリート15が順次充填されるようになっている。 Further, in the present embodiment, the presser form 12 has a length of, for example, about 1.5 m, and the joint portion 11 between the adjacent precast concrete decks 10 has a length of, for example, about 10 m. Therefore, the joint portion 11 is installed so as to cover the upper surface opening of the joint portion 11 and to be sequentially added from the downstream side to the upstream side of the transverse gradient Z (see FIG. 2). In the filling space 14 surrounded by the presser form 12 which is sequentially added, the side surface portions of the precast concrete deck 10 on both sides, and the bottom form 13, the concrete 15 is formed from the downstream side to the upstream side of the cross slope Z. Are sequentially filled.

さらに、本実施形態では、押え型枠12は、好ましくは透明な合成樹脂として、例えばアクリルによる成形品であるアクリル板を用いて形成されている。押え型枠12が、透明な合成樹脂による成形品となっていることにより、充填空間14にコンクリート15が充填されてゆく状況を、充填しながら容易に確認することが可能になる。 Further, in the present embodiment, the presser form 12 is formed by using, for example, an acrylic plate which is a molded product made of acrylic, preferably as a transparent synthetic resin. Since the presser form 12 is a molded product made of a transparent synthetic resin, it is possible to easily confirm the situation in which the concrete 15 is being filled in the filling space 14 while filling.

さらにまた、本実施形態では、上述のように、押え型枠12の継手部11の上面開口を覆う部分の下面には、空気溜リ部を形成する線状の凹溝12aが、当該継手部11の上面開口を覆う部分の下面の全域に亘って複数形成されている。ここで、線状の凹溝12aは、2~5mmの溝深さを有するように形成されていることが好ましい。線状の凹溝12aが、2mm以上の溝深さを有していることにより、充填されたコンクリート15の内部に存在する気泡から抜ける空気を、溝の内部に確実に取り込むことが可能になる。線状の凹溝12aが、5mm以下の溝深さを有していることにより、充填されたコンクリート15の表面に健全なコンクリート面を確保することが可能になる。 Furthermore, in the present embodiment, as described above, on the lower surface of the portion of the presser form 12 that covers the upper surface opening of the joint portion 11, a linear concave groove 12a forming an air reservoir portion is formed in the joint portion. A plurality of pieces are formed over the entire lower surface of the portion covering the upper surface opening of 11. Here, it is preferable that the linear concave groove 12a is formed so as to have a groove depth of 2 to 5 mm. Since the linear concave groove 12a has a groove depth of 2 mm or more, it is possible to reliably take in the air released from the air bubbles existing inside the filled concrete 15 into the inside of the groove. .. Since the linear concave groove 12a has a groove depth of 5 mm or less, it is possible to secure a sound concrete surface on the surface of the filled concrete 15.

また、本実施形態では、線状の凹溝12aは、2~5mmの溝幅を有するように形成されていることが好ましく、三角形の断面形状を備えるように形成されていることが好ましい。線状の凹溝12aが、2~5mmの溝幅を有していることにより、充填されたコンクリート15の内部に存在する気泡から抜ける空気を、溝の内部に確実に取り込むことが可能になると共に、充填されたコンクリート15の表面に健全なコンクリート面を確保することが可能になる。線状の凹溝12aが、三角形の断面形状を備えていることにより、気泡から抜けた空気と、充填された健全なコンクリート15とが、上下分かれた状態で溝の内部に確実に配置されるようにすることが可能になる。なお、線状の凹溝12aは、三角形の断面形状を備えている必要は必ずしも無く、半円形状、矩形状、台形状等、その他の種々の断面形状を備えていても良い。 Further, in the present embodiment, the linear concave groove 12a is preferably formed so as to have a groove width of 2 to 5 mm, and is preferably formed so as to have a triangular cross-sectional shape. Since the linear concave groove 12a has a groove width of 2 to 5 mm, it is possible to reliably take in the air released from the air bubbles existing inside the filled concrete 15 into the inside of the groove. At the same time, it becomes possible to secure a sound concrete surface on the surface of the filled concrete 15. Since the linear concave groove 12a has a triangular cross-sectional shape, the air released from the air bubbles and the filled sound concrete 15 are surely arranged inside the groove in a state of being separated into upper and lower parts. It becomes possible to do so. The linear concave groove 12a does not necessarily have to have a triangular cross-sectional shape, and may have various other cross-sectional shapes such as a semicircular shape, a rectangular shape, and a trapezoidal shape.

さらに、線状の凹溝12aは、これの延設方向と垂直な方向に並べて複数連接して形成されていることが好ましい。これによって、充填されたコンクリート15の内部に存在する気泡から抜ける空気を、より確実に溝の内部に取り込むことが可能になると共に、充填されたコンクリート15の表面に健全なコンクリート面を、より確実に確保することが可能になる。また後述するように押え型枠12を横断勾配Zの下流側から上流側に順次継ぎ足して設置した場合でも、気泡から抜ける空気を、継ぎ足された型枠の端部から容易に抜くことが可能になる。線状の凹溝12aは、これの延設方向と垂直な方向に並べて複数連接して形成されている必要は必ずしも無く、縦横に交差するように並べて配置されていたり、隣接する線状の凹溝12aの間にある程度の間隔を保持した状態で並べて配置されていても良い。 Further, it is preferable that a plurality of linear concave grooves 12a are arranged side by side in a direction perpendicular to the extending direction thereof and connected to each other. This makes it possible to more reliably take in the air that escapes from the air bubbles existing inside the filled concrete 15 into the inside of the groove, and more reliably to make a sound concrete surface on the surface of the filled concrete 15. It will be possible to secure it. Further, as will be described later, even when the presser form 12 is sequentially added from the downstream side to the upstream side of the transverse gradient Z, the air released from the air bubbles can be easily removed from the end of the added form. Become. The linear concave grooves 12a do not necessarily have to be formed by arranging and connecting a plurality of linear concave grooves in a direction perpendicular to the extending direction thereof, and the linear concave grooves 12a are arranged side by side so as to intersect vertically and horizontally, or are adjacent linear concave grooves. They may be arranged side by side while maintaining a certain distance between the grooves 12a.

さらにまた、線状の凹溝12aは、これの延設方向をプレキャストコンクリート床版10の表面部分の横断勾配Zの傾斜方向に沿わせるようにして形成されていることが好ましい。これによって、コンクリート15の充填時に、コンクリート15から上方に抜けて線状の凹溝12aに溜められた空気を、当該線状の凹溝12aの傾斜によって端部から抜くことで、外気に向けてよりスムーズに排除することが可能になる。 Furthermore, it is preferable that the linear concave groove 12a is formed so that the extending direction thereof is along the inclination direction of the transverse gradient Z of the surface portion of the precast concrete deck 10. As a result, when the concrete 15 is filled, the air that has escaped upward from the concrete 15 and is stored in the linear concave groove 12a is removed from the end portion by the inclination of the linear concave groove 12a, so that the air is directed toward the outside air. It becomes possible to eliminate more smoothly.

また、本実施形態では、上述のように、押え型枠12は、継手部11の上面開口を覆って横断勾配Zの下流側から上流側に順次継ぎ足されて設置されるようになっており、横断勾配Zの下流側から上流側に順次継ぎ足される押え型枠12は、下流側の押え型枠12に形成された線状の凹溝12aに、上流側の押え型枠12に形成された線状の凹溝12aが連通するように配置されて、継手部11の上面開口を覆って設置されるようになっていることが好ましい。これによって、順次継ぎ足された押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの下流側から上流側に向けてコンクリートを順次充填して行く際に、継ぎ足された押え型枠12の間で連通する線状の凹溝12aの傾斜によって端部から抜くことで、コンクリート15から上方に抜けて線状の凹溝12aに溜められた空気を、外気に向けてよりスムーズに排除することが可能になる。 Further, in the present embodiment, as described above, the presser form 12 is installed so as to cover the upper surface opening of the joint portion 11 and to be sequentially added from the downstream side to the upstream side of the transverse gradient Z. The presser form 12 to be sequentially added from the downstream side to the upstream side of the transverse gradient Z is a line formed in the presser form 12 on the upstream side in the linear concave groove 12a formed in the presser form 12 on the downstream side. It is preferable that the concave groove 12a having a shape is arranged so as to communicate with each other so as to cover the upper surface opening of the joint portion 11. As a result, the filling space 14 surrounded by the presser form 12 sequentially added, the side surface portions 10a of the precast concrete deck 10 on both sides, and the bottom form 13 is directed from the downstream side to the upstream side of the transverse gradient Z. By pulling out from the end due to the inclination of the linear concave groove 12a communicating between the added presser form 12 when the concrete is sequentially filled, the concrete is pulled out upward from the concrete 15 and the linear concave is formed. The air stored in the groove 12a can be discharged more smoothly toward the outside air.

本実施形態の継手部の充填施工方法では、上述の構成を備える、継手部11の上面開口を覆う部分の下面に複数の線状の凹溝12aが形成された押え型枠12を、好ましくは横断勾配Zの下流側から設置して、押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの上流側から、好ましくは流動性が高くセルフレベリング性に優れた高強度のコンクリートを、継手部11のコンクリート15として供給して充填する。このような高強度のコンクリートとしては、例えば常温硬化型の超高強度繊維補強コンクリートである、商品名「スリムクリート」(株式会社大林組製)を用いることができる。 In the method for filling the joint portion of the present embodiment, the presser form 12 having the above-mentioned configuration and having a plurality of linear concave grooves 12a formed on the lower surface of the portion covering the upper surface opening of the joint portion 11 is preferably used. Installed from the downstream side of the cross slope Z, the filling space 14 surrounded by the presser form 12, the side surface portions 10a of the precast concrete deck 10 on both sides, and the bottom form 13 is entered from the upstream side of the cross slope Z. , Preferably, high-strength concrete having high fluidity and excellent self-leveling property is supplied and filled as the concrete 15 of the joint portion 11. As such high-strength concrete, for example, the trade name "Slim Cleat" (manufactured by Obayashi Corporation), which is a room temperature curing type ultra-high strength fiber reinforced concrete, can be used.

充填空間14に供給されたコンクリート15は、バイブレータ等の公知の振動装置を使用したり、押え型枠12を木槌で叩いたりすることなどによって振動が加えられて、十分に締め固められると共に、複数の線状の凹溝12aが形成された押え型枠12の下面に上面を密着させた状態で、充填空間14に充填される。押え型枠12の下面には、空気溜リ部を形成する線状の凹溝12aが、継手部11の上面開口を覆う部分の全域に亘って複数形成されているので、コンクリート15の充填時にコンクリート15から上方に抜ける空気を、複数の線状の凹溝12aに溜めながら、充填空間14にコンクリート15を充填することが可能になる。 The concrete 15 supplied to the filling space 14 is sufficiently compacted by being vibrated by using a known vibrating device such as a vibrator or by hitting the presser form 12 with a mallet. The filling space 14 is filled with the upper surface in close contact with the lower surface of the presser form 12 in which the plurality of linear concave grooves 12a are formed. Since a plurality of linear concave grooves 12a forming the air reservoir portion are formed on the lower surface of the presser form 12 over the entire area covering the upper surface opening of the joint portion 11, when the concrete 15 is filled. It is possible to fill the filling space 14 with the concrete 15 while accumulating the air flowing upward from the concrete 15 in the plurality of linear concave grooves 12a.

そして、本実施形態の継手部の充填施工方法によれば、横断勾配Zを有するプレキャストコンクリート床版10の継手部11のコンクリート15の表面を、プレキャストコンクリート床版10の表面と面一に、且つ平滑に仕上げる作業の手間を、効果的に低減することが可能になる。 Then, according to the method of filling the joint portion of the present embodiment, the surface of the concrete 15 of the joint portion 11 of the precast concrete deck 10 having a transverse gradient Z is flush with the surface of the precast concrete deck 10. It is possible to effectively reduce the time and effort required for smooth finishing.

すなわち、本実施形態によれば、継手部11のコンクリート15は、当該継手部11の上面開口を覆って好ましくは横断勾配Zの下流側から押え型枠12を設置し、設置した押え型枠12と、両側のプレキャストコンクリート床版10の側面部10aと、底型枠13とによって囲まれる充填空間14に、横断勾配Zの上流側から供給されて充填されるようになっており、押え型枠12の継手部11の上面開口を覆う部分の下面には、空気溜リ部を形成する線状の凹溝12aが、当該継手部11の上面開口を覆う部分の下面の全域に亘って複数形成されており、コンクリート15の充填時にコンクリート15から上方に抜ける空気を、複数の線状の凹溝12aに溜めながら、充填空間14にコンクリート15を充填するようになっている。 That is, according to the present embodiment, the concrete 15 of the joint portion 11 covers the upper surface opening of the joint portion 11 and preferably installs the presser formwork 12 from the downstream side of the transverse gradient Z, and the presser form 12 is installed. The filling space 14 surrounded by the side surface portions 10a of the precast concrete floor slabs 10 on both sides and the bottom formwork 13 is supplied from the upstream side of the cross slope Z and filled. A plurality of linear concave grooves 12a forming an air reservoir are formed on the lower surface of the portion covering the upper surface opening of the joint portion 11 of the joint portion 11 over the entire lower surface of the portion covering the upper surface opening of the joint portion 11. The filling space 14 is filled with the concrete 15 while accumulating the air that escapes upward from the concrete 15 in the plurality of linear concave grooves 12a when the concrete 15 is filled.

これによって、本実施形態によれば、図5に示すように、各々の線状の凹溝12aに溜められる空気によって、充填時に各々の線状の凹溝12aに侵入しようとするコンクリート15の量を抑制することで、継手部11に充填されたコンクリート15が固化した後に押え型枠12を取り外した際に、プレキャストコンクリート床版10の上面よりも突出した状態で残置される固化したコンクリート15の厚さを小さく、且つ突出するコンクリート15の量を少なくすることが可能になる。これによって、このような突出した部分のコンクリート15を荒削りしたり、研磨したりすることによって、継手部11のコンクリート15の表面を、プレキャストコンクリート床版10の表面と面一に、且つ平滑に仕上げる作業の手間を、効果的に低減することが可能になると共に、研磨する際に粉塵や騒音を発生させて、周囲の環境に影響を及ぼすことになるのを、効果的に抑制することが可能になる。 As a result, according to the present embodiment, as shown in FIG. 5, the amount of concrete 15 that tends to invade each linear concave groove 12a at the time of filling by the air stored in each linear concave groove 12a. When the presser form 12 is removed after the concrete 15 filled in the joint portion 11 is solidified, the solidified concrete 15 is left in a state of protruding from the upper surface of the precast concrete deck 10. It is possible to reduce the thickness and the amount of protruding concrete 15. As a result, the surface of the concrete 15 of the joint portion 11 is finished flushly and smoothly with the surface of the precast concrete deck 10 by rough-cutting or polishing the concrete 15 of such a protruding portion. It is possible to effectively reduce the labor of work, and it is also possible to effectively suppress the generation of dust and noise during polishing, which affects the surrounding environment. become.

なお、本発明は上記実施形態に限定されることなく種々の変更が可能である。例えば、押え型枠は、透明な合成樹脂による成形品となっている必要は必ずしも無く、不透明が成形品であっても良い。プレキャストコンクリート床版は、道路橋のコンクリート床版を形成するものである必要は必ずしも無く、鉄道橋等のその他の種々のコンクリート床版を形成するものであっても良い。 The present invention is not limited to the above embodiment, and various modifications can be made. For example, the presser form does not necessarily have to be a molded product made of a transparent synthetic resin, and the opaque product may be a molded product. The precast concrete deck does not necessarily have to form a concrete deck of a road bridge, but may form various other concrete decks such as a railroad bridge.

10 プレキャストコンクリート床版
10a 側面部
11 継手部
12 押え型枠
12a 線状の凹溝
12b 側端部
13 底型枠
13a 埋設型枠
14 充填空間
15 継手部のコンクリート
16 鉄筋
17 妻型枠
18 桟木
19 アンカー部材
20 コンクリート床版
50 橋桁
51 橋脚
X 橋桁の延設方向(連設方向)
Y 連設方向(延設方向)と垂直な方向
Z 横断勾配
10 Precast concrete deck 10a Side part 11 Joint part 12 Presser formwork 12a Linear concave groove 12b Side end part 13 Bottom formwork 13a Buried formwork 14 Filling space 15 Joint part concrete 16 Reinforcing bar 17 Wife formwork 18 Crosspiece 19 Anchor member 20 Concrete deck 50 Bridge girder 51 Bridge pedestal X Extension direction of bridge girder (continuous installation direction)
Y Direction perpendicular to the continuous installation direction (extension direction) Z Transverse gradient

Claims (8)

連設方向に複数並べて配置されたプレキャストコンクリート床版の継手部にコンクリートを充填して固化させることにより、隣接するプレキャストコンクリート床版を互いに接合する際に用いる継手部の充填施工方法であって、
複数並べて配置されたプレキャストコンクリート床版は、連設方向と垂直な方向に傾斜する横断勾配を表面部分に備えており、前記継手部の上面開口を覆って、押え型枠を、前記継手部の両側のプレキャストコンクリート床版の上に跨がるようにして設置し、継手部のコンクリートは、設置した前記押え型枠と、両側のプレキャストコンクリート床版の側面部と、底型枠とによって囲まれる充填空間に、横断勾配の上流側から供給されて充填されるようになっており、
前記押え型枠の前記継手部の上面開口を覆う部分の下面には、空気溜リ部を形成する線状の凹溝が、当該継手部の上面開口を覆う部分の下面の全域に亘って複数形成されており、
コンクリートの充填時にコンクリートから上方に抜ける空気を、複数の前記線状の凹溝に溜めながら、前記充填空間にコンクリートを充填する継手部の充填施工方法。
It is a method of filling joints used when joining adjacent precast concrete decks to each other by filling concrete into the joints of precast concrete decks arranged side by side in the continuous installation direction and solidifying them.
A plurality of precast concrete slabs arranged side by side have a cross slope inclined in a direction perpendicular to the continuous installation direction on the surface portion, cover the upper surface opening of the joint portion, and provide a presser formwork to the joint portion. It is installed so as to straddle the precast concrete slabs on both sides, and the concrete of the joint part is surrounded by the installed presser form, the side surface portions of the precast concrete slabs on both sides, and the bottom formwork. The filling space is supplied from the upstream side of the transverse gradient and filled.
On the lower surface of the portion of the presser form that covers the upper surface opening of the joint portion, a plurality of linear concave grooves forming an air reservoir portion are formed over the entire lower surface of the portion that covers the upper surface opening of the joint portion. Is formed and
A method for filling a joint portion in which concrete is filled in the filling space while accumulating air that escapes upward from the concrete when filling the concrete in a plurality of the linear concave grooves.
前記線状の凹溝は、2~5mmの溝深さを有するように形成されている請求項1記載の継手部の充填施工方法。 The method for filling a joint portion according to claim 1, wherein the linear concave groove is formed so as to have a groove depth of 2 to 5 mm. 前記線状の凹溝は、三角形の断面形状を備えるように形成されている請求項1又は2記載の継手部の充填施工方法。 The method for filling a joint portion according to claim 1 or 2, wherein the linear concave groove is formed so as to have a triangular cross-sectional shape. 前記線状の凹溝は、これの延設方向と垂直な方向に並べて複数連接して形成されている請求項1~3のいずれか1項記載の継手部の充填施工方法。 The method for filling a joint portion according to any one of claims 1 to 3, wherein the linear concave groove is formed by arranging and connecting a plurality of the linear concave grooves in a direction perpendicular to the extending direction thereof. 前記線状の凹溝は、延設方向をプレキャストコンクリート床版の表面部分の横断勾配の傾斜方向に沿わせるようにして形成されている請求項1~4のいずれか1項記載の継手部の充填施工方法。 The joint portion according to any one of claims 1 to 4, wherein the linear groove is formed so that the extending direction is along the inclination direction of the transverse gradient of the surface portion of the precast concrete deck. Filling construction method. 前記押え型枠は、前記継手部の上面開口を覆って横断勾配の下流側から上流側に順次継ぎ足されて設置されるようになっており、順次継ぎ足された押え型枠と、両側のプレキャストコンクリート床版の側面部と、底型枠とによって囲まれる充填空間に、横断勾配の下流側から上流側に向けてコンクリートが順次充填されるようになっている請求項1~5のいずれか1項記載の継手部の充填施工方法。 The presser form is installed by sequentially adding from the downstream side to the upstream side of the transverse gradient so as to cover the upper surface opening of the joint portion, and the presser form that is sequentially added and the precast concrete on both sides. One of claims 1 to 5, wherein the filling space surrounded by the side surface portion of the deck and the bottom formwork is sequentially filled with concrete from the downstream side to the upstream side of the cross slope. The described method for filling joints. 前記横断勾配の下流側から上流側に順次継ぎ足される前記押え型枠は、下流側の前記押え型枠に形成された線状の凹溝に、上流側の前記押え型枠に形成された線状の凹溝が連通するように配置されて、前記継手部の上面開口を覆って設置されるようになっている請求項6記載の継手部の充填施工方法。 The presser form, which is sequentially added from the downstream side to the upstream side of the transverse gradient, has a linear concave groove formed in the presser form on the downstream side and a linear shape formed in the presser form on the upstream side. The method for filling a joint portion according to claim 6, wherein the concave grooves are arranged so as to communicate with each other so as to cover the upper surface opening of the joint portion. 前記押え型枠が、透明な合成樹脂による成形品となっている請求項1~7のいずれか1項記載の継手部の充填施工方法。
The method for filling a joint portion according to any one of claims 1 to 7, wherein the presser form is a molded product made of a transparent synthetic resin.
JP2017253716A 2017-12-28 2017-12-28 Filling construction method for joints Active JP7028639B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017253716A JP7028639B2 (en) 2017-12-28 2017-12-28 Filling construction method for joints

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017253716A JP7028639B2 (en) 2017-12-28 2017-12-28 Filling construction method for joints

Publications (2)

Publication Number Publication Date
JP2019120003A JP2019120003A (en) 2019-07-22
JP7028639B2 true JP7028639B2 (en) 2022-03-02

Family

ID=67306980

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017253716A Active JP7028639B2 (en) 2017-12-28 2017-12-28 Filling construction method for joints

Country Status (1)

Country Link
JP (1) JP7028639B2 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000290935A (en) 1999-04-08 2000-10-17 Kawaju Koji Kk Form timbering structure of haunch part of bridge floorboard
JP2003147959A (en) 2001-11-16 2003-05-21 Tetsuji Tatsuoka Concrete framework and method of construction using the framework
JP2004074703A (en) 2002-08-21 2004-03-11 Asahi Concrete Works Co Ltd Method for manufacturing concrete product, concrete product by the manufacturing method and shuttering for manufacturing concrete product
JP2004092384A (en) 2003-10-02 2004-03-25 Jfe Engineering Kk Steel bottomed form
JP2005067146A (en) 2003-08-27 2005-03-17 Ohbayashi Corp Segment production method
JP2006283360A (en) 2005-03-31 2006-10-19 Nagashima Imono Kk Method for constructing cover supporting frame on inclined plane
JP2007169886A (en) 2005-12-19 2007-07-05 Sho Bond Constr Co Ltd Composite structure of main girder and precast floor slab
JP2017179926A (en) 2016-03-30 2017-10-05 三井住友建設株式会社 CONSTRUCTION METHOD OF FLOOR SLAB AND JOINT STRUCTURE OF PCa FLOOR SLAB

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6347421A (en) * 1986-08-12 1988-02-29 Nippon Houkou:Kk Concrete covering work for slope frame
JP2655847B2 (en) * 1987-10-01 1997-09-24 株式会社青木建設 Concrete casting formwork
JPH03161655A (en) * 1989-11-20 1991-07-11 Central Eng:Kk Concrete form panel
JPH0540495U (en) * 1991-10-29 1993-06-01 清水建設株式会社 Mesh and synthetic resin foam composite formwork for concrete pouring
JP2671197B2 (en) * 1995-04-13 1997-10-29 ショーボンド建設株式会社 Reinforced concrete precast floor slab
JPH1034618A (en) * 1996-07-19 1998-02-10 Kayaba Ind Co Ltd Charging method of ready-mixed concrete and its form
JP3261696B2 (en) * 1998-04-28 2002-03-04 日本サミコン株式会社 Concrete formwork

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000290935A (en) 1999-04-08 2000-10-17 Kawaju Koji Kk Form timbering structure of haunch part of bridge floorboard
JP2003147959A (en) 2001-11-16 2003-05-21 Tetsuji Tatsuoka Concrete framework and method of construction using the framework
JP2004074703A (en) 2002-08-21 2004-03-11 Asahi Concrete Works Co Ltd Method for manufacturing concrete product, concrete product by the manufacturing method and shuttering for manufacturing concrete product
JP2005067146A (en) 2003-08-27 2005-03-17 Ohbayashi Corp Segment production method
JP2004092384A (en) 2003-10-02 2004-03-25 Jfe Engineering Kk Steel bottomed form
JP2006283360A (en) 2005-03-31 2006-10-19 Nagashima Imono Kk Method for constructing cover supporting frame on inclined plane
JP2007169886A (en) 2005-12-19 2007-07-05 Sho Bond Constr Co Ltd Composite structure of main girder and precast floor slab
JP2017179926A (en) 2016-03-30 2017-10-05 三井住友建設株式会社 CONSTRUCTION METHOD OF FLOOR SLAB AND JOINT STRUCTURE OF PCa FLOOR SLAB

Also Published As

Publication number Publication date
JP2019120003A (en) 2019-07-22

Similar Documents

Publication Publication Date Title
RU2586101C2 (en) Method for producing ballastless track
KR102061224B1 (en) Sectionally devided precast box culverts and the construction method thereof
KR100916973B1 (en) Construction method of prestressed concrete pavement and its structure
KR101761476B1 (en) Change construction method of bridge expansion joint for quick construction
KR101076029B1 (en) Replacing Method of Old Train Track using Twin-Block Type Train Track
KR100603901B1 (en) Girder bridge construction make use of a part existing girder and that execution method
KR101613784B1 (en) Integral abutment bridge construction method of old joint butment bridge
KR20140092734A (en) Rahmen Bridge PSC girder and construction method thereof
KR101627279B1 (en) Biased soil pressure reinforcement rigid-frame bridge and construction method of the same
JP7028639B2 (en) Filling construction method for joints
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
CN208685424U (en) Spelling fills precast concrete beam bridge superstructure
JP7290389B2 (en) Concrete structure construction equipment
JP6889010B2 (en) Bridge construction method
JP7306053B2 (en) Joint structure of precast floor slab and construction method of joint
JP4020918B2 (en) Bridge structure of girder bridge
JP7249202B2 (en) Replacement and repair method for drainage groove forming members and highway bridge drainage grooves
JP2004011124A (en) Draining structure for road surface and draining concrete block
JP5166333B2 (en) Telescopic device support structure
JP7414657B2 (en) How to repair existing rails
JP7317663B2 (en) Precast PC floor slab
KR101962709B1 (en) Composite deck slab construction method with trench
KR200414459Y1 (en) Structure for paving bridge installed expansion joint
KR101025019B1 (en) Sheet pile composition rigid-frame bridge using temporary installation vent and constructing method thereof
JP2620675B2 (en) Reinforcement earth method such as roadbed reinforcement, embankment, slope reinforcement and formwork for concrete block retaining wall

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180124

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201105

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211028

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211109

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220201

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220217

R150 Certificate of patent or registration of utility model

Ref document number: 7028639

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150