JP6675427B2 - Home door basic structure, construction method and screwing jig - Google Patents
Home door basic structure, construction method and screwing jig Download PDFInfo
- Publication number
- JP6675427B2 JP6675427B2 JP2018031287A JP2018031287A JP6675427B2 JP 6675427 B2 JP6675427 B2 JP 6675427B2 JP 2018031287 A JP2018031287 A JP 2018031287A JP 2018031287 A JP2018031287 A JP 2018031287A JP 6675427 B2 JP6675427 B2 JP 6675427B2
- Authority
- JP
- Japan
- Prior art keywords
- slab plate
- spiral pile
- spiral
- embankment
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims description 20
- 229910000831 Steel Inorganic materials 0.000 claims description 36
- 239000010959 steel Substances 0.000 claims description 36
- 230000002093 peripheral effect Effects 0.000 claims description 21
- 239000000463 material Substances 0.000 claims description 11
- 238000005553 drilling Methods 0.000 claims description 5
- 238000007711 solidification Methods 0.000 claims description 2
- 230000008023 solidification Effects 0.000 claims description 2
- 239000004567 concrete Substances 0.000 description 10
- 238000000034 method Methods 0.000 description 8
- 239000011210 fiber-reinforced concrete Substances 0.000 description 7
- 230000003014 reinforcing effect Effects 0.000 description 7
- 239000011347 resin Substances 0.000 description 7
- 229920005989 resin Polymers 0.000 description 7
- 239000004570 mortar (masonry) Substances 0.000 description 6
- 239000002184 metal Substances 0.000 description 5
- 239000000203 mixture Substances 0.000 description 4
- 238000003466 welding Methods 0.000 description 4
- 239000002245 particle Substances 0.000 description 3
- 238000005452 bending Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 239000011384 asphalt concrete Substances 0.000 description 1
- 239000011230 binding agent Substances 0.000 description 1
- 239000003054 catalyst Substances 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 239000011372 high-strength concrete Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 238000006116 polymerization reaction Methods 0.000 description 1
- 239000011164 primary particle Substances 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
- Platform Screen Doors And Railroad Systems (AREA)
Description
本発明は、盛土によって形成されるプラットホームに、可動式ホーム柵やプラットホームスクリーンドアなどのドア装置を設置するためのホームドアの基礎構造、その構築方法及びねじ込み治具に関するものである。 The present invention relates to a foundation structure of a home door for installing a door device such as a movable platform fence or a platform screen door on a platform formed by embankment, a construction method thereof, and a screwing jig.
特許文献1には、盛土によって形成された盛土式プラットホームに、プラットホームドア装置を設置するための固定構造及び固定方法が開示されている。この文献には、プラットホームドア装置を載置するために盛土の上面にコンクリート版を設置し、周囲に注入されたグラウトによって盛土に固定されるロックボルトでコンクリート版を支持させる構造が記載されている。 Patent Literature 1 discloses a fixing structure and a fixing method for installing a platform door device on an embankment-type platform formed by embankment. This document describes a structure in which a concrete slab is installed on the top surface of an embankment for mounting a platform door device, and the concrete slab is supported by rock bolts fixed to the embankment by grout injected around the embankment. .
この特許文献1に開示された方法では、ロックボルトを盛土に打設して削孔との隙間にグラウトを注入するために、注入装置などの施工機械や施工設備をプラットホーム上に設置することになる。 According to the method disclosed in Patent Literature 1, in order to inject a grout into a gap between the drilling hole and a rock bolt on an embankment, a construction machine or a construction facility such as an injection device is installed on a platform. Become.
一方、特許文献2には、平鋼を螺旋状に捩じり加工したスパイラル部と、その上部に接続された鋼管とによって構成されたスパイラル杭が開示されている。このスパイラル杭は、小型標識やカーブミラーなどの支柱を支持させるために、地盤に基礎として埋め込まれる。 On the other hand, Patent Literature 2 discloses a spiral pile composed of a spiral portion formed by twisting flat steel in a spiral shape, and a steel pipe connected to an upper portion thereof. The spiral pile is embedded as a foundation in the ground to support columns such as small signs and curved mirrors.
しかしながらプラットホームにおける工事は、列車の運行スケジュールや利用客の安全確保などの制限を受けながら実施しなければならないため、プラットホーム上に設置する施工機械や施工設備は、少ない方が効率よく施工することができる。さらには、線路側が土留め壁によって保護される盛土式プラットホーム上に、設計荷重を超えるような大型の施工機械などを設置する場合は、事前に土留め壁を補強する工事などを実施しなければならない。 However, construction on the platform must be carried out with restrictions such as train operation schedules and ensuring the safety of passengers.Therefore, the less construction machines and construction equipment installed on the platform, the more efficient the construction. it can. Furthermore, when installing large-scale construction machinery that exceeds the design load on an embankment platform where the track side is protected by retaining walls, construction work to reinforce the retaining walls must be implemented in advance. No.
そこで、本発明は、上載荷重の制限の厳しい盛土によって形成されるプラットホームにドア装置を設置するための簡易な構成のホームドアの基礎構造、その構築方法及びねじ込み治具を提供することを目的としている。 Therefore, an object of the present invention is to provide a basic structure of a home door having a simple configuration for installing a door device on a platform formed by embankment having a severe limitation of an overload, a construction method thereof, and a screwing jig. I have.
前記目的を達成するために、本発明のホームドアの基礎構造は、盛土によって形成されるプラットホームにドア装置を設置するためのホームドアの基礎構造であって、前記プラットホームの線路側縁部に設置される前記ドア装置の支持部を接続させるスラブ板と、前記スラブ板の線路側縁部から離隔した位置において、上部の鋼管部と下部のスパイラル部とを有して前記盛土の内部に打設されるスパイラル杭とを備え、前記スパイラル杭の上端部は前記スラブ板の貫通穴に挿通されて連結部を介して結合されていることを特徴とする。 In order to achieve the above object, a foundation structure of a home door according to the present invention is a foundation structure of a home door for installing a door device on a platform formed by embankment, wherein the foundation device is installed at a track side edge of the platform. A slab plate for connecting a supporting portion of the door device, and an upper steel pipe portion and a lower spiral portion at a position separated from a line side edge of the slab plate, and are poured into the embankment. And an upper end of the spiral pile is inserted into a through hole of the slab plate and is connected via a connecting portion.
ここで、前記スパイラル杭の上端部の外周面には突起部が設けられており、前記貫通穴と前記上端部との隙間に充填された固化材と前記突起部とによって、前記スパイラル杭の軸まわりの回転が阻止される構成とすることができる。 Here, a projection is provided on the outer peripheral surface of the upper end of the spiral pile, and the solidification material filled in the gap between the through hole and the upper end and the projection form the axis of the spiral pile. It is possible to adopt a configuration in which the rotation around is prevented.
また、前記スパイラル杭の上端部の外周面にはネジ溝が刻まれており、前記連結部は前記ネジ溝にねじ込まれる鍔部を有するワッシャーナットを備えている構成とすることもできる。さらに、前記ワッシャーナットの鍔部は、前記スラブ板の下面側に配置される構成とすることができる。 Further, a screw groove may be formed on an outer peripheral surface of an upper end portion of the spiral pile, and the connecting portion may be provided with a washer nut having a flange portion screwed into the screw groove. Further, the flange of the washer nut may be arranged on a lower surface side of the slab plate.
また、ホームドアの基礎構造の構築方法の発明は、前記スパイラル杭を前記盛土に打設する工程と、前記スパイラル杭が打設された位置に合わせて前記スラブ板に前記貫通穴を穿孔する工程と、前記スパイラル杭の上端部に前記貫通穴を通すことで前記スラブ板を設置する工程と、前記連結部により前記スラブ板と前記スパイラル杭の上端部とを結合する工程とを備えたことを特徴とする。 Further, the invention of a method of constructing a foundation structure of a home door includes a step of driving the spiral pile into the embankment and a step of drilling the through hole in the slab plate in accordance with a position where the spiral pile is driven. Setting the slab plate by passing the through hole through the upper end of the spiral pile; and connecting the upper end of the spiral pile to the slab plate by the connecting portion. Features.
一方、ねじ込み治具の発明は、上部の鋼管部と下部のスパイラル部とを有するスパイラル杭を地盤にねじ込むためのねじ込み治具であって、前記鋼管部の外径より大きな内径が形成された筒体部と、前記筒体部の外周面から径方向の外側に向けて張り出される突出棒部と、前記筒体部の内周面に設けられて前記鋼管部の外周面に設けられた受力部に接触可能となるように形成された凸部とを備えたことを特徴とする。 On the other hand, the invention of a screwing jig is a screwing jig for screwing a spiral pile having an upper steel pipe portion and a lower spiral portion into the ground, wherein a tube having an inner diameter larger than the outer diameter of the steel pipe portion is formed. A body portion, a protruding rod portion projecting radially outward from an outer peripheral surface of the tubular body portion, and a support provided on an inner peripheral surface of the tubular body portion and provided on an outer peripheral surface of the steel pipe portion. A protrusion formed to be able to contact the force portion.
このように構成された本発明のホームドアの基礎構造は、ドア装置の支持部を接続させるスラブ板と盛土の内部に打設されるスパイラル杭とを備えている。そして、スパイラル杭の上端部は、スラブ板の貫通穴に挿通されて連結部を介して結合されている。 The basic structure of the home door of the present invention configured as described above includes a slab plate for connecting the support portion of the door device and a spiral pile driven into the embankment. Then, the upper end of the spiral pile is inserted into a through hole of the slab plate and connected via a connecting portion.
スパイラル杭は、専用の重機を使用しなくても盛土に打設することができるので、上載荷重の制限の厳しい盛土によって形成されるプラットホームであっても、ドア装置を設置するための簡易な構成のホームドアの基礎構造を設けることができる。 Spiral piles can be cast on the embankment without using special heavy equipment, so even if the platform is formed by embankment where the loading load is severely restricted, a simple configuration for installing door devices The basic structure of the home door can be provided.
また、スパイラル杭の上端部の外周面に突起部を設けて、スラブ板の貫通穴に充填された固化材と突起部とによってスパイラル杭の軸まわりの回転が阻止される構造とすることで、構築後にスパイラル杭が回転してスラブ板や盛土との結合を弱めることを防ぐことができる。 In addition, by providing a projection on the outer peripheral surface of the upper end of the spiral pile, the solidified material filled in the through hole of the slab plate and the projection prevent rotation around the axis of the spiral pile, It is possible to prevent the spiral pile from rotating after building and weakening the connection with the slab plate or the embankment.
さらに、スパイラル杭の上端部のネジ溝にワッシャーナットをねじ込ませることで、スラブ板を鍔部で下から受けたり、鍔部で上から押し付けたりすることができるようになり、一体性に優れた連結部とすることができる。特に、ワッシャーナットの鍔部をスラブ板の下面側に配置することで、スラブ板を下からスパイラル杭4によって支持させることができる。 Furthermore, by screwing a washer nut into the screw groove at the upper end of the spiral pile, the slab plate can be received from below by the flange, or pressed from above by the flange, and has excellent integrity. It can be a connecting part. In particular, by disposing the flange portion of the washer nut on the lower surface side of the slab plate, the slab plate can be supported by the spiral pile 4 from below.
そして、ホームドアの基礎構造の構築方法の発明では、スパイラル杭が打設された位置に合わせてスラブ板に貫通穴を穿孔するため、例えば地中障害物等により設計通りの位置にスパイラル杭を打設できず、若干のずれが生じた場合でも別の位置に貫通穴を穿孔することが可能であり、スパイラル杭の打設精度を厳密に管理する必要がなく、迅速に施工を行うことができる。 And, in the invention of the method of constructing the foundation structure of the home door, in order to drill a through hole in the slab plate in accordance with the position where the spiral pile is driven, for example, the spiral pile is placed at the designed position due to an underground obstacle or the like. It is possible to drill a through hole at another position even if a slight displacement occurs when it is not possible to drive and it is not necessary to strictly control the placement accuracy of the spiral pile, and it is possible to perform construction quickly it can.
また、ねじ込み治具の発明では、スパイラル杭の上部の鋼管部に筒体部を嵌めることで、人力などの小さい力でも盛土にスパイラル部をねじ込ませることができるようになるので、プラットホーム上に大型の施工機械や施工設備などを設置しなくても施工可能となる。 In addition, in the invention of the screwing jig, the spiral portion can be screwed into the embankment with a small force such as human power by fitting the cylindrical portion to the steel pipe portion on the upper portion of the spiral pile, so that the large size can be mounted on the platform. It is possible to perform construction without installing construction machinery and construction equipment.
以下、本発明の実施の形態について図面を参照して説明する。図1,2は、本実施の形態で例示するプラットホーム1の構成を説明する図である。プラットホーム1は、列車が走行する線路Rに沿って構築される。 Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1 and 2 are diagrams illustrating the configuration of the platform 1 exemplified in the present embodiment. The platform 1 is constructed along a track R on which a train travels.
このプラットホーム1は、土砂や粘土などの盛土11によって形成された盛土式プラットホームであって、線路R側は土留め壁12によって保護されている。盛土11は、N値が2〜5程度の比較的に軟らかい地盤であることが多い。 This platform 1 is an embankment type platform formed by embankment 11 such as earth and sand or clay, and the track R side is protected by an earth retaining wall 12. The embankment 11 is often a relatively soft ground having an N value of about 2 to 5.
プラットホーム1の上層としては、例えばモルタルなどの下地層131の上にタイルなどの床仕上げ層13が設けられる。また、アスファルトコンクリート等が敷き均された舗装部を上層とすることもできる。さらに、上層の線路R側には、ノンスリップタイルや点字ブロックが配置される。 As an upper layer of the platform 1, for example, a floor finishing layer 13 such as a tile is provided on a base layer 131 such as mortar. Further, a pavement portion on which asphalt concrete or the like is spread can be used as an upper layer. Further, a non-slip tile and a Braille block are arranged on the upper layer line R side.
プラットホーム1の線路側縁部1aに設置されるドア装置には、可動式ホーム柵やプラットホームスクリーンドアなどがある。本実施の形態では、ドア装置として可動式ホーム柵2を例に説明する。 Door devices installed on the track side edge 1a of the platform 1 include a movable platform fence and a platform screen door. In the present embodiment, a movable platform fence 2 will be described as an example of the door device.
可動式ホーム柵2は、列車の乗降口に対向させる開閉式の扉部23と、扉部23を可動可能に支持して開放時に収容させる戸袋部22とによって主に構成される。戸袋部22は、図2に示すように、プラットホーム1の線路側縁部1aの延伸方向に間隔を置いて配置される支柱21,21によって支持される。本実施の形態の可動式ホーム柵2では、この支柱21が支持部となる。 The movable platform fence 2 is mainly composed of an openable / closable door portion 23 facing the entrance / exit of the train, and a door pocket portion 22 that movably supports the door portion 23 and accommodates the door portion 23 when opened. As shown in FIG. 2, the door pocket portion 22 is supported by columns 21 and 21 arranged at intervals in the direction in which the line side edge 1 a of the platform 1 extends. In the movable platform fence 2 of the present embodiment, the columns 21 serve as support portions.
支柱21は、支圧板24の上に立てられ、支圧板24は固定アンカー25によってプラットホーム1の上層に固定される。本実施の形態では、図1に示すように、固定アンカー25の先端は、後述するスラブ板3に埋設されて定着される。 The support 21 is erected on the support plate 24, and the support plate 24 is fixed to the upper layer of the platform 1 by the fixing anchor 25. In the present embodiment, as shown in FIG. 1, the distal end of the fixed anchor 25 is embedded and fixed in a slab plate 3 described later.
本実施の形態のホームドアの基礎構造は、上述したような盛土11によって形成されるプラットホーム1にドア装置である可動式ホーム柵2を設置するため支持構造である。可動式ホーム柵2を設置すると、自重の他に、風荷重(列車通過に伴う風荷重も含む)や群集による水平荷重も作用することになる。 The basic structure of the home door of the present embodiment is a support structure for installing the movable home fence 2 which is a door device on the platform 1 formed by the embankment 11 as described above. When the movable platform fence 2 is installed, in addition to its own weight, a wind load (including a wind load accompanying train passing) and a horizontal load due to crowds also act.
本実施の形態のホームドアの基礎構造は、可動式ホーム柵2の支柱21を接続させるスラブ板3と、スラブ板3のホーム側縁部3b側の領域で盛土11の内部に打設されるスパイラル杭4と、スラブ板3とスパイラル杭4とを結合させる連結部5とによって、主に構成される。 The basic structure of the home door according to the present embodiment is cast into the embankment 11 in the region of the slab plate 3 for connecting the column 21 of the movable platform fence 2 and the slab plate 3 on the side of the home edge 3b. It is mainly constituted by a spiral pile 4 and a connecting portion 5 for coupling the slab plate 3 and the spiral pile 4.
スラブ板3には、プラットホーム1の線路側縁部1aに設置される可動式ホーム柵2の支柱21,21を載置させる。この支柱21,21を載せるためのスラブ板3は、線路側縁部3aから反対側のホーム側縁部3bに向けて延伸される。 On the slab plate 3, the columns 21, 21 of the movable platform fence 2 installed on the rail side edge 1a of the platform 1 are placed. The slab plate 3 on which the supports 21 and 21 are placed is extended from the rail side edge 3a to the opposite home side edge 3b.
図2に示すように、例えば平面視長方形に形成されるスラブ板3は、支柱21の設置箇所に合わせて、プラットホーム1の線路側縁部1aの延伸方向(線路Rの延伸方向)に間隔を置いて設置される。 As shown in FIG. 2, the slab plate 3 formed in, for example, a rectangular shape in a plan view has an interval in the extending direction of the line side edge 1 a of the platform 1 (extending direction of the line R) in accordance with the installation position of the column 21. Placed and set.
スラブ板3は、例えば繊維補強コンクリートやレジンコンクリートなどの高強度のコンクリート材料によって成形される。例えば、セメントと、最大粒度が2mm以下の骨材粒子と、一次粒子粒度が1μm以下のポゾラン反応粒子と、長さが2mm以上で長さと径の比が20以上の金属繊維とを主に含有する、金属繊維強化コンクリートによって成形することができる。 The slab plate 3 is formed of a high-strength concrete material such as fiber reinforced concrete or resin concrete. For example, mainly containing cement, aggregate particles having a maximum particle size of 2 mm or less, pozzolanic reaction particles having a primary particle size of 1 μm or less, and metal fibers having a length of 2 mm or more and a length-to-diameter ratio of 20 or more. Can be formed by metal fiber reinforced concrete.
このような金属繊維強化コンクリートの力学特性は、引張強度が12 MPa以上、曲げ強度が25 MPa以上、圧縮強度が150 MPa以上となり、非常に高い強度を示す。また、緻密な成形物になるため、耐久性の高いスラブ板3を形成することができる。 The mechanical properties of such metal fiber reinforced concrete are very high, with a tensile strength of 12 MPa or more, a bending strength of 25 MPa or more, and a compressive strength of 150 MPa or more. Moreover, since it becomes a dense molded product, the slab plate 3 with high durability can be formed.
一方、レジンコンクリートは、セメントに代えて液状の樹脂を結合材として骨材を結合させたコンクリートである。レジンコンクリートは、樹脂と触媒による重合反応によって高い結合力で短時間に硬化することから、高強度で耐久性に優れた緻密な成形物にすることができる。レジンコンクリートの力学特性は、引張強度が10 MPa以上、曲げ強度が20 MPa以上、圧縮強度が100 MPa以上となる。 On the other hand, resin concrete is concrete in which a liquid resin is used as a binder instead of cement to bind aggregate. Resin concrete is cured in a short time with a high bonding force due to a polymerization reaction between a resin and a catalyst, so that a dense molded article having high strength and excellent durability can be obtained. The mechanical properties of the resin concrete are such that the tensile strength is 10 MPa or more, the bending strength is 20 MPa or more, and the compressive strength is 100 MPa or more.
このような金属繊維強化コンクリートやレジンコンクリートによってスラブ板3を製作するに際しては、通常のコンクリートを使用する場合のように鉄筋を配置する必要がない。また、PC鋼線を配置してプレストレスを導入する必要もない。例えば、スラブ板3は、長辺側の長さを1.2mから1.5m程度、短辺側の長さ(幅)を1m程度、厚さを70mm程度にしたパネル状に成形できる。このようなスラブ板3は、打設したスパイラル杭4の位置に合わせるなど任意の位置に貫通穴31を穿孔することができる。 When manufacturing the slab plate 3 by using such metal fiber reinforced concrete or resin concrete, it is not necessary to arrange a reinforcing bar as in the case of using ordinary concrete. Also, there is no need to arrange a PC steel wire to introduce prestress. For example, the slab plate 3 can be formed into a panel having a long side length of about 1.2 m to 1.5 m, a short side length (width) of about 1 m, and a thickness of about 70 mm. In such a slab plate 3, the through hole 31 can be drilled at an arbitrary position, for example, in accordance with the position of the spiral pile 4 that has been cast.
スラブ板3を盛土11に定着させるためのスパイラル杭4は、図1及び図3(a)に示すように、上部の鋼管部41と、下部のスパイラル部42とを備えている。例えば鋼管部41を1mから1.5m程度、スパイラル部42を1mから2m程度の長さにすることができる。また、杭径は、70mmから120mm程度、好ましくは100mm程度にすることができる。 The spiral pile 4 for fixing the slab plate 3 to the embankment 11 is provided with an upper steel pipe part 41 and a lower spiral part 42 as shown in FIG. 1 and FIG. For example, the length of the steel pipe part 41 can be about 1 m to 1.5 m, and the length of the spiral part 42 can be about 1 m to 2 m. Further, the pile diameter can be set to about 70 mm to 120 mm, preferably about 100 mm.
スパイラル杭4は、スラブ板3の線路側縁部3aから離隔したホーム側縁部3b側に配置される。スパイラル杭4と土留め壁12との間に介在される盛土11を、スパイラル杭4に作用する水平力に対する抵抗にするためには、土留め壁12からある程度の距離を離した位置にスパイラル杭4を打設させる必要がある。 The spiral pile 4 is arranged on the side of the home side edge 3b of the slab plate 3 that is separated from the side edge 3a of the track side. In order to make the embankment 11 interposed between the spiral pile 4 and the retaining wall 12 a resistance to the horizontal force acting on the spiral pile 4, the spiral pile 4 is located at a certain distance from the retaining wall 12. 4 must be cast.
1枚のスラブ板3に対しては、4本から8本程度のスパイラル杭4,・・・が配置されることになる。例えばスラブ板3の線路側縁部3aからホーム側縁部3bに向けて、1列から3列程度となるようにスパイラル杭4,・・・が配置される。 About one to four spiral piles 4,... Are arranged for one slab plate 3. For example, the spiral piles 4,... Are arranged in one to three rows from the line side edge 3a of the slab plate 3 to the home side edge 3b.
図3(a)に示すように、スパイラル部42は、例えば平鋼を螺旋状に捩じり加工することによって製作することができる。スパイラル部42は、45度のねじり面を有しているので、引き抜きと押し込みの両方向に同等の鉛直支持力を発揮させることができる。 As shown in FIG. 3A, the spiral portion 42 can be manufactured by, for example, spirally twisting flat steel. Since the spiral portion 42 has a 45-degree twisted surface, the same vertical support force can be exerted in both the pulling and pushing directions.
鋼管部41は、円筒状に形成されていて、水平力に対して強い抵抗体とすることができる。この鋼管部41の下端に切り込みを設けて、その溝にスパイラル部42の上端を挿し込んで溶接などによって固着させる。また、鋼管部41の上端部411(スパイラル杭4の上端部411)は、外周面にネジ溝が刻まれた上端ネジ部43に形成される。 The steel pipe part 41 is formed in a cylindrical shape, and can be a strong resistor against horizontal force. A notch is provided at the lower end of the steel pipe portion 41, and the upper end of the spiral portion 42 is inserted into the groove and fixed by welding or the like. The upper end portion 411 of the steel pipe portion 41 (the upper end portion 411 of the spiral pile 4) is formed in an upper end screw portion 43 having a thread groove formed on the outer peripheral surface.
また、この上端ネジ部43には、後述する突起部53を設けるための上端穴部44が穿孔される。この上端穴部44は、鋼管部41に対してボルト531を横断させるために対向する一対で設けられる。ここでは、図7に示すように、平面視十字状にボルト531,531を配置するために、上下2段にそれぞれ対となる上端穴部44,44が穿孔される。 Further, an upper end hole portion 44 for providing a projection 53 described later is formed in the upper end screw portion 43. The upper end hole portion 44 is provided as a pair facing the steel pipe portion 41 so as to cross the bolt 531. Here, as shown in FIG. 7, the upper end holes 44, 44 that are paired with each other, are arranged in two upper and lower stages in order to arrange the bolts 531, 531 in a cross shape in plan view.
さらに、鋼管部41の外周面には、後述するねじ込み治具6,6Aの凸部63に接触させる受力部45が設けられる。この受力部45は、細い鋼棒や鉄筋などによって形成され、溶接などで鋼管部41の外周面に固着される。例えば、図3(b)に示すように、鋼管部41の周方向に90度ずつの等間隔で複数の受力部45,・・・が取り付けられる。 Further, on the outer peripheral surface of the steel pipe portion 41, a force receiving portion 45 that comes into contact with a convex portion 63 of a screwing jig 6, 6A described later is provided. The force receiving portion 45 is formed of a thin steel rod, a reinforcing bar, or the like, and is fixed to the outer peripheral surface of the steel pipe portion 41 by welding or the like. For example, as shown in FIG. 3B, a plurality of force receiving portions 45 are attached at regular intervals of 90 degrees in the circumferential direction of the steel pipe portion 41.
この受力部45は、スパイラル杭4を盛土11にねじ込む際に使用されるねじ込み治具6,6Aからの回転力を受けるために設けられる。図4(a),(b)に示すように、ねじ込み治具6は、筒体部61と、筒体部61の外周面から径方向の外側に向けて張り出される複数の突出棒部62,・・・と、筒体部61の内周面に設けられる複数の凸部63,・・・とによって、主に構成される。 The force receiving portion 45 is provided to receive a rotational force from the screwing jigs 6 and 6A used when screwing the spiral pile 4 into the embankment 11. As shown in FIGS. 4A and 4B, the screwing jig 6 includes a cylindrical body 61 and a plurality of protruding rods 62 projecting radially outward from the outer peripheral surface of the cylindrical body 61. , And a plurality of convex portions 63, provided on the inner peripheral surface of the cylindrical body portion 61.
筒体部61は、図3(b)に示すように、鋼管部41の外径より大きな内径が形成される。そして、筒体部61の内周面には、複数の受力部45,・・・にそれぞれ接触させるための複数の凸部63,・・・が取り付けられる。凸部63は、細い鋼棒や鉄筋などによって形成され、溶接などで筒体部61の内周面に固着される。 As shown in FIG. 3B, the cylindrical body 61 has an inner diameter larger than the outer diameter of the steel pipe 41. A plurality of projections 63,... For contacting the plurality of force receiving parts 45,. The projection 63 is formed of a thin steel rod, a reinforcing bar, or the like, and is fixed to the inner peripheral surface of the cylindrical body 61 by welding or the like.
筒体部61の下端には円環状のフランジ部64が設けられ、突出棒部62の端部は、筒体部61の外周面とフランジ部64の上面とに溶接などで接合される。突出棒部62は、例えば平面視十字状になるように複数取り付けられ、使用時には補助管621の端部が挿し込まれて長さが調整される。 An annular flange portion 64 is provided at a lower end of the cylindrical body portion 61, and an end of the protruding rod portion 62 is joined to an outer peripheral surface of the cylindrical body portion 61 and an upper surface of the flange portion 64 by welding or the like. A plurality of protruding rods 62 are attached, for example, in a cross shape in a plan view, and the length of the auxiliary rod 621 is adjusted by inserting an end of the auxiliary pipe 621 at the time of use.
図5には、筒体部61Aが長尺となるねじ込み治具6Aを示している。このねじ込み治具6Aは、スパイラル杭4の上端部411が低い位置にある場合に、作業員が作業しやすい高さで回転させる際に使用される。このため、筒体部61Aの下端付近に凸部63,・・・が設けられ、長尺の筒体部61Aの上端に突出棒部62,・・・が取り付けられる。 FIG. 5 shows a screwing jig 6A in which the cylindrical portion 61A is long. The screwing jig 6A is used when the upper end 411 of the spiral pile 4 is at a low position and rotated at a height at which an operator can easily work. .. Are provided near the lower end of the cylindrical body 61A, and the protruding rods 62,... Are attached to the upper end of the elongated cylindrical body 61A.
図6に示すように、スパイラル杭4の上端部411は、スラブ板3の貫通穴31に挿通されて連結部5を介して結合される。この貫通穴31は、鋼管部41の外径より一回り大きな内径の穴に形成される。例えば、鋼管部41の外径より10mmから20mm程度大きい内径の貫通穴31を設ける。 As shown in FIG. 6, the upper end 411 of the spiral pile 4 is inserted into the through hole 31 of the slab plate 3 and is connected via the connecting portion 5. The through hole 31 is formed as a hole having an inner diameter slightly larger than the outer diameter of the steel pipe portion 41. For example, the through hole 31 having an inner diameter that is about 10 mm to 20 mm larger than the outer diameter of the steel pipe part 41 is provided.
連結部5は、上端ネジ部43にねじ込まれるワッシャーナット(51,52)と、上端ネジ部43の外周面から外側に突出される複数の突起部53,・・・と、貫通穴31と上端ネジ部43の外周面との隙間に充填された固化材54とによって、主に構成される。 The connecting portion 5 includes a washer nut (51, 52) screwed into the upper end screw portion 43, a plurality of protrusions 53 projecting outward from the outer peripheral surface of the upper end screw portion 43, the through hole 31, and the upper end. It is mainly constituted by the solidified material 54 filled in the gap between the screw portion 43 and the outer peripheral surface.
ワッシャーナット(51,52)は、鍔部511,521を有しており、スラブ板3の下面側に配置される下ワッシャーナット51の鍔部511は、スラブ板3の下面に接触させる。一方、スラブ板3の上面側に配置される上ワッシャーナット52の鍔部521は、スラブ板3の上面に接触させる。 The washer nut (51, 52) has flange portions 511, 521, and the flange portion 511 of the lower washer nut 51 arranged on the lower surface side of the slab plate 3 is brought into contact with the lower surface of the slab plate 3. On the other hand, the flange 521 of the upper washer nut 52 arranged on the upper surface side of the slab plate 3 is brought into contact with the upper surface of the slab plate 3.
突起部53は、無収縮モルタルなどの固化材54に対して回転抵抗となる程度に突出されていればよい。ここでは、ボルト531とナット532によって形成される突起部53を例に説明する。 The protrusion 53 only needs to be protruded to such an extent that the solidified material 54 such as a non-shrink mortar has a rotational resistance. Here, the protrusion 53 formed by the bolt 531 and the nut 532 will be described as an example.
ボルト531には、例えば頭部のない円柱状の寸切りボルトを使用することができる。図7に示すように、対向する上端穴部44,44にボルト531を挿通させ、鋼管部41の両側に均等に突出されたボルト531の両端に、ナット532,532をそれぞれ装着することで突起部53,53を形成する。なお、頭部のある通常のボルトを使用し、一方の突起部はボルトヘッドによって形成してもよい。 As the bolt 531, for example, a columnar cut bolt having no head can be used. As shown in FIG. 7, bolts 531 are inserted into opposed upper end holes 44, 44, and nuts 532, 532 are respectively mounted on both ends of bolts 531 that are uniformly protruded on both sides of steel pipe part 41. The parts 53 and 53 are formed. Note that a normal bolt having a head may be used, and one of the protrusions may be formed by a bolt head.
ボルト531,531を上下2段に平面視十字状に配置することで、上端部411の周方向に90度ずつ間隔を置いた4箇所に突起部53,・・・を設けることができる。この結果、スパイラル杭4に軸まわりに回転しようとする力が生じたとしても、突起部53,・・・の周囲の硬化した固化材54の抵抗によって回転が阻止されることになる。 By arranging the bolts 531 and 531 in a cross shape in a plan view in two stages, it is possible to provide the protrusions 53 at four locations at 90 ° intervals in the circumferential direction of the upper end portion 411. As a result, even if a force is generated in the spiral pile 4 to rotate around the axis, the rotation is prevented by the resistance of the hardened solidified material 54 around the projections 53.
次に、本実施の形態のホームドアの基礎構造の構築方法について説明する。
既存のプラットホーム1に対して施工する場合、少なくともスラブ板3を設置する範囲の床仕上げ層13及び下地層131は事前に撤去される。また、必要に応じてスラブ板3の厚さ分だけ盛土11の上面を掘り下げる。
Next, a method of constructing the basic structure of the home door according to the present embodiment will be described.
When installing on the existing platform 1, at least the floor finishing layer 13 and the base layer 131 in a range where the slab plate 3 is installed are removed in advance. Further, the upper surface of the embankment 11 is dug down by the thickness of the slab plate 3 as necessary.
続いて、スパイラル杭4を盛土11に打設する工程を実施する。スパイラル杭4を打設する際には、まず鋼管部41の長さ分だけ盛土11を余掘りしておく。そして、スパイラル杭4をその余掘りした孔に建て込む。 Subsequently, a step of placing the spiral pile 4 on the embankment 11 is performed. When driving the spiral pile 4, first, the embankment 11 is dug by the length of the steel pipe portion 41. Then, the spiral pile 4 is erected in the hole dug.
盛土11の上面から突出した鋼管部41には、ねじ込み治具6を装着する。ねじ込み治具6の突出棒部62,・・・には、長尺の補助管621,・・・を継ぎ足し、小さな力で回転力が与えられるようにする。 The screwing jig 6 is attached to the steel pipe portion 41 protruding from the upper surface of the embankment 11. A long auxiliary pipe 621,... Is added to the protruding rods 62,... Of the screwing jig 6 so that a rotational force can be given with a small force.
4本の補助管621,・・・に対してそれぞれ作業員を配置して一方向(例えば時計回り)に回転させると、図3(b)に示すように、ねじ込み治具6の凸部63,・・・が鋼管部41の受力部45,・・・に引っ掛かって、スパイラル杭4に回転力が付与されることになる。回転力が付与されたスパイラル杭4は、スパイラル部42が盛土11にねじ込まれて下方に向けて推進する。 When a worker is arranged for each of the four auxiliary pipes 621 and rotated in one direction (for example, clockwise), as shown in FIG. ,... Are caught by the force receiving portions 45,. The spiral pile 4 to which the rotational force is applied is propelled downward by the spiral portion 42 being screwed into the embankment 11.
スパイラル杭4のねじ込みは、上端部411が地面に近付いたときに、長尺のねじ込み治具6A(図5参照)に切り替えられて続けられる。所望する深さまでスパイラル杭4をねじ込んだ後は、隣接する施工箇所に移動して、次のスパイラル杭4の打設を行う。また、スパイラル杭4と盛土11の削孔との隙間には、山砂などを充填する。 When the upper end 411 approaches the ground, the screwing of the spiral pile 4 is switched to the long screwing jig 6A (see FIG. 5) and continued. After screwing the spiral pile 4 to a desired depth, the spiral pile 4 is moved to an adjacent construction site and the next spiral pile 4 is driven. In addition, the gap between the spiral pile 4 and the drilling of the embankment 11 is filled with mountain sand or the like.
本実施の形態では、図2に示すように、1枚のスラブ板3に対して幅方向3本の前後2列で合計6本のスパイラル杭4,・・・が打設される。スパイラル杭4は、作業員の人力で盛土11に打設することができるが、突出する上端部411,・・・の位置は施工箇所ごとに微妙に異なる。 In the present embodiment, as shown in FIG. 2, a total of six spiral piles 4, in three rows in the width direction and two rows in front and rear, are laid on one slab plate 3. The spiral pile 4 can be driven into the embankment 11 by a worker's manpower, but the positions of the protruding upper ends 411,.
そこで、6本の上端部411,・・・の相対的な位置関係を計測し、スラブ板3のそれらに対応する位置に貫通穴31,・・・を穿孔する。このスラブ板3は、金属繊維強化コンクリートによって成形されていて鉄筋が配筋されていないので、穿孔する際に鉄筋を避ける必要がなく、計測結果に応じて正確な位置に貫通穴31,・・・を穿孔することができる。 Therefore, the relative positional relationship between the six upper end portions 411,... Is measured, and through holes 31,. Since the slab plate 3 is formed of metal fiber reinforced concrete and has no reinforcing bars, it is not necessary to avoid the reinforcing bars when drilling, and the through holes 31,.・ Can be perforated.
スラブ板3を設置する前に、図6に示すように、鋼管部41の上端ネジ部43に下ワッシャーナット51をねじ込む。下ワッシャーナット51は、スラブ板3を設置したい高さに合わせて装着位置が調整される。
続いてその上方の上端穴部44,・・・には、図7に示すようにボルト531を挿し込み、鋼管部41の両側に突出した端部に、それぞれナット532,532を装着する。
Before the slab plate 3 is installed, the lower washer nut 51 is screwed into the upper end screw portion 43 of the steel pipe portion 41 as shown in FIG. The mounting position of the lower washer nut 51 is adjusted according to the height at which the slab plate 3 is to be installed.
Then, bolts 531 are inserted into the upper end holes 44,... As shown in FIG. 7, and nuts 532, 532 are attached to ends protruding on both sides of the steel pipe 41, respectively.
次にスラブ板3を搬送して、盛土11の上面から突出したスパイラル杭4の上端部411,・・・に貫通穴31,・・・を通すことでスラブ板3を設置する。スラブ板3の貫通穴31,・・・は、上端部411,・・・の位置に合わせて穿孔されているので、容易に据え付けることができる。 Next, the slab plate 3 is conveyed, and the slab plate 3 is installed by passing through the through holes 31,... Through the upper end portions 411,. Since the through-holes 31,... Of the slab plate 3 are perforated in accordance with the positions of the upper ends 411,.
スラブ板3の貫通穴31と上端部411との間の隙間には、図6に示すように無収縮モルタルなどの固化材54を充填する。そして、スラブ板3の上面から突出した上端ネジ部43には、上ワッシャーナット52をねじ込んで締め付ける。また、鋼管部41の内空には、必要に応じて無収縮モルタルを充填する。 The gap between the through hole 31 and the upper end 411 of the slab plate 3 is filled with a solidifying material 54 such as non-shrink mortar as shown in FIG. Then, the upper washer nut 52 is screwed into the upper end screw portion 43 protruding from the upper surface of the slab plate 3 and tightened. The inner space of the steel pipe portion 41 is filled with non-shrink mortar as needed.
このようにして連結部5によりスラブ板3とスパイラル杭4の上端部411とを結合した後に、スラブ板3の線路側縁部3a付近の支柱21を立てる箇所に対して、固定アンカー25,・・・を打ち込む。そして、スラブ板3上の所定の範囲に下地層131及び床仕上げ層13を設ける。続いて、固定アンカー25に支柱21の支圧板24を固定して、可動式ホーム柵2を設置する。 After connecting the slab plate 3 and the upper end 411 of the spiral pile 4 by the connecting portion 5 in this manner, the fixed anchors 25,.・ Enter Then, a base layer 131 and a floor finishing layer 13 are provided in a predetermined range on the slab plate 3. Subsequently, the support plate 24 of the column 21 is fixed to the fixed anchor 25, and the movable platform fence 2 is installed.
次に、本実施の形態のホームドアの基礎構造、その構築方法及びねじ込み治具の作用について説明する。
このように構成された本実施の形態のホームドアの基礎構造は、可動式ホーム柵2の支柱21を接続させるスラブ板3と盛土11の内部に打設されるスパイラル杭4とを備えている。そして、スパイラル杭4の上端部411は、スラブ板3の貫通穴31に挿通されて連結部5を介して結合される。
Next, the basic structure of the home door of the present embodiment, a method of constructing the same, and the operation of the screwing jig will be described.
The basic structure of the home door of the present embodiment configured as described above includes the slab plate 3 for connecting the column 21 of the movable platform fence 2 and the spiral pile 4 cast into the embankment 11. . Then, the upper end portion 411 of the spiral pile 4 is inserted into the through hole 31 of the slab plate 3 and connected via the connecting portion 5.
スパイラル杭4は、専用の重機を使用しなくても作業員の人力で打設することができるので、上載荷重の制限の厳しい盛土11によって形成されるプラットホーム1であっても、可動式ホーム柵2を設置するための簡易な構成のホームドアの基礎構造を設けることができる。 The spiral pile 4 can be driven by a worker without using a special heavy machine. Therefore, even if the platform 1 is formed by the embankment 11 whose load on the load is severely restricted, the movable platform fence can be used. 2 can be provided with a basic structure of a home door having a simple configuration.
また、スパイラル杭4の上端部411の外周面に突起部53,・・・を設けて、スラブ板3の貫通穴31に充填された固化材54と突起部53とによってスパイラル杭4の軸まわりの回転が阻止されるように回転防止措置を施す。可動式ホーム柵2には、列車通過に伴う風荷重などの水平荷重が繰り返し作用し、スラブ板3を介してスパイラル杭4が回転するような力が伝達されることがあるが、回転防止措置を施すことによって、スラブ板3との結合や盛土11との付着を弱めるようなスパイラル杭4の回転の発生を防ぐことができる。 Also, projections 53,... Are provided on the outer peripheral surface of the upper end 411 of the spiral pile 4, and the solidified material 54 filled in the through-holes 31 of the slab plate 3 and the projections 53 rotate around the axis of the spiral pile 4. Take anti-rotation measures to prevent rotation. A horizontal load such as a wind load accompanying train passing repeatedly acts on the movable platform fence 2, and a force such that the spiral pile 4 rotates through the slab plate 3 may be transmitted. , It is possible to prevent the rotation of the spiral pile 4 that weakens the connection with the slab plate 3 and the adhesion to the embankment 11.
さらに、上端部411の上端ネジ部43に下ワッシャーナット51と上ワッシャーナット52をねじ込ませることで、スラブ板3を鍔部511で下から受けつつ、鍔部521で上から押し付けることができるようになり、一体性に優れた連結部5とすることができる。特に、下ワッシャーナット51の鍔部511をスラブ板3の下面側に配置することで、スラブ板3を下から確実に支持させることができる。すなわち、スラブ板3に作用した鉛直荷重を、下ワッシャーナット51を介して確実にスパイラル杭4に伝達させることができる。 Further, by screwing the lower washer nut 51 and the upper washer nut 52 into the upper end screw portion 43 of the upper end portion 411, the slab plate 3 can be pressed from above by the flange portion 521 while being received by the flange portion 511 from below. Thus, the connecting portion 5 having excellent integration can be obtained. In particular, by disposing the flange portion 511 of the lower washer nut 51 on the lower surface side of the slab plate 3, the slab plate 3 can be reliably supported from below. That is, the vertical load applied to the slab plate 3 can be reliably transmitted to the spiral pile 4 via the lower washer nut 51.
そして、ホームドアの基礎構造の構築方法では、複数のスパイラル杭4,・・・が打設された位置に合わせてスラブ板3に貫通穴31,・・・を穿孔するため、スパイラル杭4,・・・の打設精度を厳密に管理する必要がなく、人力で迅速に施工を行うことができる。 In the method of constructing the foundation structure of the home door, the spiral piles 4 are drilled in the slab plate 3 in accordance with the positions where the plurality of spiral piles 4,. It is not necessary to strictly control the placing accuracy of the..., And the work can be quickly performed by human power.
特に、高強度の繊維補強コンクリートによって成形されたスラブ板3には鉄筋やPC鋼線が配置されないため、穿孔位置の制約を受けることなくスラブ板3の任意の箇所に穿孔が可能で、複数のスパイラル杭4,・・・が打設された位置に容易に合わせることができる。例えば、盛土11内の地中障害物等により設計通りの位置にスパイラル杭4を打設できずに若干のずれが生じた場合でも、実際に打設された位置に合わせて貫通穴を穿孔することができる。 In particular, since no reinforcing bars or PC steel wires are arranged on the slab plate 3 formed of high-strength fiber-reinforced concrete, it is possible to perforate any part of the slab plate 3 without being restricted by the perforation position. Can be easily adjusted to the position where the spiral piles 4,. For example, even when the spiral pile 4 cannot be driven at the designed position due to an underground obstacle or the like in the embankment 11 and a slight displacement occurs, the through hole is drilled in accordance with the actually driven position. be able to.
また、スパイラル杭4の上部の鋼管部41にねじ込み治具6,6Aの筒体部61,61Aを嵌めて、受力部45,・・・に凸部63,・・・を引っ掛けることで、人力などの小さい力でも盛土11に簡単にスパイラル部42をねじ込ませることができるようになる。このため、プラットホーム1上に大型の施工機械や施工設備などを設置しなくても、迅速に施工することができる。 Also, by fitting the cylindrical portions 61, 61A of the screwing jigs 6, 6A into the steel pipe portion 41 above the spiral pile 4, and hooking the convex portions 63,. The spiral portion 42 can be easily screwed into the embankment 11 with a small force such as human power. For this reason, the construction can be performed quickly without installing large-scale construction machines and construction facilities on the platform 1.
以下、前記実施の形態で説明したスラブ板3とスパイラル杭4との連結部5とは別の形態の連結部5Aについて、図8を参照しながら説明する。なお、前記実施の形態で説明した内容と同一乃至均等な部分の説明については、同一用語又は同一符号を付して説明する。 Hereinafter, a connecting portion 5A of a different form from the connecting portion 5 between the slab plate 3 and the spiral pile 4 described in the above embodiment will be described with reference to FIG. Note that the same or equivalent parts as those described in the above embodiment will be described with the same terms or reference numerals.
この実施例1で説明する連結部5Aは、スラブ板3に作用する鉛直荷重が大きい場合や、盛土11が軟弱でスパイラル杭4に大きな鉛直支持力が期待できない場合などに適用される。要するに、スラブ板3に作用する鉛直荷重をすべてスパイラル杭4に伝達させるのではなく、盛土11の上面にも分散して作用させるようにする。 The connecting portion 5A described in the first embodiment is applied to a case where a vertical load acting on the slab plate 3 is large, a case where the embankment 11 is soft and a large vertical supporting force cannot be expected from the spiral pile 4, and the like. In short, not all the vertical load acting on the slab plate 3 is transmitted to the spiral pile 4, but is also distributed on the upper surface of the embankment 11.
実施例1の連結部5Aでは、上端ネジ部43に下ワッシャーナット51を装着しない。一方、スラブ板3の下面から均等に荷重が伝達されるように、モルタルなどで高さ調整層55を設ける。高さ調整層55の平滑な上面にスラブ板3の下面の全面を密着させることで、局所荷重を発生させることなく均等に鉛直荷重を盛土11に伝達させることができるようになる。 In the connection portion 5A of the first embodiment, the lower washer nut 51 is not attached to the upper end screw portion 43. On the other hand, the height adjusting layer 55 is provided with mortar or the like so that the load is transmitted evenly from the lower surface of the slab plate 3. By bringing the entire lower surface of the slab plate 3 into close contact with the smooth upper surface of the height adjustment layer 55, the vertical load can be evenly transmitted to the embankment 11 without generating a local load.
高さ調整層55にスラブ板3を設置した後は、スラブ板3の貫通穴31と上端部411との間の隙間に無収縮モルタルなどの固化材54を充填する。そして、スラブ板3の上面から突出した上端ネジ部43には、上ワッシャーナット52をねじ込んで締め付ける。 After the slab plate 3 is installed on the height adjustment layer 55, the gap between the through hole 31 and the upper end 411 of the slab plate 3 is filled with a solidifying material 54 such as non-shrink mortar. Then, the upper washer nut 52 is screwed into the upper end screw portion 43 protruding from the upper surface of the slab plate 3 and tightened.
このように構成された連結部5Aは、上ワッシャーナット52の鍔部521で上からスラブ板3を盛土11に対して押し付ける。この結果、スラブ板3に作用した荷重を、スパイラル杭4だけでなく、周辺の盛土11にも分散して伝達できるようになり、軟弱な盛土11や上載荷重が大きくなるプラットホーム1においても適用することができるようになる。
なお、他の構成及び作用効果については、前記実施の形態と略同様であるので説明を省略する。
The connecting portion 5 </ b> A configured as described above presses the slab plate 3 against the embankment 11 from above with the flange portion 521 of the upper washer nut 52. As a result, the load applied to the slab plate 3 can be dispersed and transmitted not only to the spiral pile 4 but also to the surrounding embankment 11, and can be applied to the soft embankment 11 and the platform 1 in which the overhead load becomes large. Will be able to do it.
Note that the other configuration, operation, and effect are substantially the same as those of the above-described embodiment, and thus description thereof is omitted.
以上、図面を参照して、本発明の実施の形態を詳述してきたが、具体的な構成は、この実施の形態及び実施例に限らず、本発明の要旨を逸脱しない程度の設計的変更は、本発明に含まれる。 The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration is not limited to the embodiment and the example, and a design change that does not depart from the gist of the present invention. Are included in the present invention.
例えば、前記実施の形態では、ドア装置として可動式ホーム柵2を設置する場合について説明したが、これに限定されるものではなく、プラットホームスクリーンドアをドア装置として設置する場合にも本発明は適用できる。また、ドア装置の支持部は支柱21に限定されるものではなく、ドア装置の形態によっては、脚部や台座部などが支持部となることもある。 For example, in the above-described embodiment, the case where the movable platform fence 2 is installed as the door device has been described. However, the present invention is not limited to this, and the present invention is also applied to the case where the platform screen door is installed as the door device. it can. Further, the support portion of the door device is not limited to the column 21, and depending on the form of the door device, a leg portion, a pedestal portion, or the like may be the support portion.
また、前記実施の形態では、ねじ込み治具6,6Aを使用してスパイラル杭4を人力のみで盛土11に打設する方法について説明したが、これに限定されるものではなく、小型の打撃装置をスパイラル杭4の上端に装着して打撃を付与することによっても打設を行うことができる。 Further, in the above-described embodiment, the method of driving the spiral pile 4 into the embankment 11 by using only the human power by using the screwing jigs 6 and 6A has been described. However, the present invention is not limited to this, and a small hitting device is used. Can also be driven by attaching a blow to the upper end of the spiral pile 4 to give a blow.
さらに、前記実施の形態では、1枚のスラブ板3に対して6本のスパイラル杭4,・・・を結合させる例について説明したが、これに限定されるものではなく、配置するスパイラル杭4の本数、配置パターン、スラブ板の中での配置される平面位置については、設計によって任意に設定することができる。 Further, in the above-described embodiment, an example in which six spiral piles 4,... Are connected to one slab plate 3 has been described. However, the present invention is not limited to this. , The arrangement pattern, and the plane position of the arrangement in the slab plate can be arbitrarily set by design.
また、前記実施の形態では、無筋の繊維補強コンクリートによって成形されたスラブ板3を例に説明したが、これに限定されるものではなく、鉄筋コンクリート製やPCコンクリート製のスラブ板であってもよい。この場合は、スパイラル杭4の打設位置管理を厳密に行うか、鉄筋等を避けた位置に大き目の貫通穴を設けておくことになる。 Further, in the above embodiment, the slab plate 3 formed of unreinforced fiber reinforced concrete has been described as an example. However, the present invention is not limited to this, and may be a slab plate made of reinforced concrete or PC concrete. Good. In this case, the placement position of the spiral pile 4 is strictly controlled, or a large through-hole is provided at a position avoiding a reinforcing bar or the like.
また、前記実施の形態では、ねじ込み冶具6,6Aの突出棒部62は、平面視十字状になるように複数取り付けられると説明したが、これに限定されるものではなく、例えば平面視120度毎に3本取り付けられても良く、突出棒部62の本数は任意に設定することができる。 Further, in the above embodiment, the plurality of projecting rods 62 of the screwing jigs 6 and 6A are described as being attached in a cross shape in a plan view. However, the present invention is not limited to this. Three protrusions may be attached every time, and the number of protruding rod portions 62 can be arbitrarily set.
1 :プラットホーム
11 :盛土
1a :線路側縁部
2 :可動式ホーム柵(ドア装置)
21 :支柱(支持部)
3 :スラブ板
3a :線路側縁部
31 :貫通穴
4 :スパイラル杭
41 :鋼管部
411 :上端部
42 :スパイラル部
43 :上端ネジ部(ネジ溝)
45 :受力部
5,5A:連結部
51 :下ワッシャーナット(ワッシャーナット)
511 :鍔部
52 :上ワッシャーナット(ワッシャーナット)
521 :鍔部
53 :突起部
54 :固化材
6,6A:ねじ込み治具
61,61A:筒体部
62 :突出棒部
63 :凸部
R :線路
1: Platform 11: Embankment 1a: Track side edge 2: Movable platform fence (door device)
21: Support (support)
3: Slab plate 3a: Track side edge 31: Through hole 4: Spiral pile 41: Steel pipe 411: Upper end 42: Spiral 43: Upper end screw (screw groove)
45: Force receiving part 5, 5A: Connecting part 51: Lower washer nut (washer nut)
511: collar 52: upper washer nut (washer nut)
521: flange 53: projection 54: solidifying material 6, 6A: screwing jig 61, 61A: cylindrical body 62: projecting rod 63: convex R: line
Claims (6)
前記プラットホームの線路側縁部に設置される前記ドア装置の支持部を接続させるスラブ板と、
前記スラブ板の線路側縁部から離隔した位置において、上部の鋼管部と下部のスパイラル部とを有して前記盛土の内部に打設されるスパイラル杭とを備え、
前記スパイラル杭の上端部は前記スラブ板の貫通穴に挿通されて連結部を介して結合されていることを特徴とするホームドアの基礎構造。 A base structure of a home door for installing a door device on a platform formed by embankment,
A slab plate for connecting a support portion of the door device installed at a track side edge of the platform,
At a position separated from the rail side edge of the slab plate, a spiral pile having an upper steel pipe portion and a lower spiral portion and being driven into the embankment,
A base structure of a home door, wherein an upper end of the spiral pile is inserted into a through hole of the slab plate and connected via a connecting portion.
前記スパイラル杭を前記盛土に打設する工程と、
前記スパイラル杭が打設された位置に合わせて前記スラブ板に前記貫通穴を穿孔する工程と、
前記スパイラル杭の上端部に前記貫通穴を通すことで前記スラブ板を設置する工程と、
前記連結部により前記スラブ板と前記スパイラル杭の上端部とを結合する工程とを備えたことを特徴とするホームドアの基礎構造の構築方法。 It is a construction method of the foundation structure of the home door as described in any one of Claims 1 thru | or 4, Comprising:
Driving the spiral pile into the embankment,
Drilling the through hole in the slab plate in accordance with the position where the spiral pile has been cast;
Installing the slab plate by passing the through hole through the upper end of the spiral pile;
Connecting the slab plate and the upper end of the spiral pile by the connecting portion.
前記鋼管部の外径より大きな内径が形成された筒体部と、
前記筒体部の外周面から径方向の外側に向けて張り出される突出棒部と、
前記筒体部の内周面に固着されて前記鋼管部の外周面に固着された棒状の受力部に接触可能となるように形成された棒状の凸部とを備えたことを特徴とするねじ込み治具。 A screwing jig for screwing a spiral pile having an upper steel pipe part and a lower spiral part into the ground,
A tubular body part having an inner diameter larger than the outer diameter of the steel pipe part,
A protruding rod portion that protrudes radially outward from the outer peripheral surface of the cylindrical body portion,
A rod-shaped convex portion fixed to the inner peripheral surface of the cylindrical body portion so as to be able to contact a rod-shaped force receiving portion fixed to the outer peripheral surface of the steel pipe portion. Screwing jig.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2018031287A JP6675427B2 (en) | 2018-02-23 | 2018-02-23 | Home door basic structure, construction method and screwing jig |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2018031287A JP6675427B2 (en) | 2018-02-23 | 2018-02-23 | Home door basic structure, construction method and screwing jig |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2019143449A JP2019143449A (en) | 2019-08-29 |
JP6675427B2 true JP6675427B2 (en) | 2020-04-01 |
Family
ID=67771003
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2018031287A Active JP6675427B2 (en) | 2018-02-23 | 2018-02-23 | Home door basic structure, construction method and screwing jig |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6675427B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU199730U1 (en) * | 2020-03-20 | 2020-09-16 | Федеральное Государственное Казенное Военное Образовательное Учреждение Высшего Образования "Военный Учебно-Научный Центр Сухопутных Войск "Общевойсковая Ордена Жукова Академия Вооруженных Сил Российской Федерации" | ANCHORING DEVICE |
JP7504377B2 (en) | 2021-02-15 | 2024-06-24 | 西日本旅客鉄道株式会社 | Platform fence foundation structure and platform fence construction method |
Family Cites Families (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5989140U (en) * | 1982-12-08 | 1984-06-16 | 石川島建材工業株式会社 | Screw pile driving equipment |
JPS5989141U (en) * | 1982-12-08 | 1984-06-16 | 石川島建材工業株式会社 | Screw pile driving equipment |
JPH1143936A (en) * | 1997-07-29 | 1999-02-16 | Kubota Corp | Pile coupling part structure |
JP3533981B2 (en) * | 1999-03-23 | 2004-06-07 | Jfeスチール株式会社 | Construction method of screwed pile |
JP4473400B2 (en) * | 2000-03-17 | 2010-06-02 | 株式会社フジタ | Foundation of construction and construction method |
JP2001303604A (en) * | 2000-04-25 | 2001-10-31 | Nippon Steel Corp | Joining structure of steel pipe pile and upper structure |
JP4187908B2 (en) * | 2000-06-26 | 2008-11-26 | 日本車輌製造株式会社 | Foundation pile rotary press-fitting machine |
JP3568528B1 (en) * | 2004-01-08 | 2004-09-22 | 積水ハウス株式会社 | Rotating device for steel pipe pile |
JP2006118336A (en) * | 2004-09-21 | 2006-05-11 | Atsushi Nakaya | Drill-like screw pile |
JP4716134B2 (en) * | 2007-04-25 | 2011-07-06 | 東洋建設株式会社 | Slope stabilization method |
JP2012097458A (en) * | 2010-11-02 | 2012-05-24 | Miwa Tokita | Foundation construction method for structure on ground, and component of foundation construction |
JP6021545B2 (en) * | 2012-09-21 | 2016-11-09 | 三菱重工交通機器エンジニアリング株式会社 | Platform door fixing structure and platform door fixing method |
-
2018
- 2018-02-23 JP JP2018031287A patent/JP6675427B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2019143449A (en) | 2019-08-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2017523330A (en) | Tower foundation system and method for installing tower foundation system | |
KR101672924B1 (en) | Fire proof reinforced panel using high strength steel plate and construction method of the same | |
KR101674435B1 (en) | the establishment installation support for poor ground | |
JP5065341B2 (en) | Precast pillar and foundation connection method and temporary cradle. | |
JP4975460B2 (en) | Load bearing material | |
JP6675427B2 (en) | Home door basic structure, construction method and screwing jig | |
KR101341260B1 (en) | Method of reinforcing existing concrete footing structure using micropile | |
KR102269141B1 (en) | Deck plate wall installation method using underground pavement | |
JP2008308945A (en) | Concrete foundation combined with tension pile, and construction method thereof | |
JP6811678B2 (en) | Method of joining concrete structures and concrete members to which continuous fiber reinforced concrete is applied | |
JP7028728B2 (en) | Joint structure of foundation pile and foundation slab | |
JP2011047118A (en) | Foundation for structure and method of constructing the same | |
JP5905802B2 (en) | Construction method of breakwater using multi-purpose post | |
KR20100007721A (en) | Reinforcement | |
KR100922121B1 (en) | Construction Structure of Footing using Hybrid Pile having Various Cross-section | |
JP7241050B2 (en) | Precast/prestressed concrete foundation structure and its construction method | |
JP2008214854A (en) | Apparatus for driving steel pipe and method of driving steel pipe | |
JPH0996197A (en) | Structure of support wall and construction method therefor | |
KR200479516Y1 (en) | The spiral-shaped support structure | |
KR20180114620A (en) | In-place or reinforced grouting foundation, pile and its construction using injection, grouting and reinforced material | |
KR101483865B1 (en) | Construction Method of Underground Structure using Composite Wale | |
US10077539B1 (en) | Wall and retaining members and fluidizing installation of retaining members | |
KR20210073076A (en) | Phc pile for soil retaining wall | |
CN110847498A (en) | Built-in section steel column fixing system and application construction method thereof | |
JP6476483B2 (en) | Embankment resistor and construction method of embankment structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20181001 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20190806 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20190924 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20200303 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20200310 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6675427 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |