JP6403470B2 - Equipment management system - Google Patents
Equipment management system Download PDFInfo
- Publication number
- JP6403470B2 JP6403470B2 JP2014144159A JP2014144159A JP6403470B2 JP 6403470 B2 JP6403470 B2 JP 6403470B2 JP 2014144159 A JP2014144159 A JP 2014144159A JP 2014144159 A JP2014144159 A JP 2014144159A JP 6403470 B2 JP6403470 B2 JP 6403470B2
- Authority
- JP
- Japan
- Prior art keywords
- inspection
- work time
- maintenance
- plan
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007689 inspection Methods 0.000 claims description 205
- 238000012423 maintenance Methods 0.000 claims description 96
- 238000005259 measurement Methods 0.000 claims description 17
- 238000007726 management method Methods 0.000 description 17
- 238000000034 method Methods 0.000 description 6
- 238000005461 lubrication Methods 0.000 description 4
- 239000000284 extract Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
Images
Landscapes
- Maintenance And Inspection Apparatuses For Elevators (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
本発明は、設備ごとに決められた保守点検計画に従って点検を実行する際の点検漏れを防止する設備管理システムおよび設備管理方法に関するものである。 The present invention relates to a facility management system and a facility management method for preventing an inspection omission when performing an inspection according to a maintenance inspection plan determined for each facility.
従来では、エレベータ装置等といった保守点検が必要な設備に対しては、設備ごとに決められた保守点検計画に従って、定期的にさまざまな保守点検が実行される。具体的には、例えば、エレベータ装置に対応する保守点検計画として、安全スイッチの動作点検、ブレーキトルクの点検、チェーンへの給油、およびレールへの給油という4つの点検項目がある場合、作業員は、これらの4つの点検項目について漏れなく点検を実行しなければならない。 Conventionally, various maintenance inspections such as an elevator apparatus are periodically performed according to a maintenance inspection plan determined for each facility for maintenance inspections. Specifically, for example, when the maintenance inspection plan corresponding to the elevator apparatus includes four inspection items, that is, safety switch operation inspection, brake torque inspection, chain lubrication, and rail lubrication, These four inspection items must be inspected without omission.
ここで、保守点検計画に含まれる点検項目について漏れなく点検が実行されているかを把握するために、端末装置を所持する作業員が、保守点検計画に含まれる点検項目について点検を実行すれば、実行済の点検項目として端末装置に手動で登録し、端末装置に登録された点検項目が、作業実績として外部の監視センターに通知される保守点検管理システムが提案されている(例えば、特許文献1参照)。 Here, in order to grasp whether the inspection items included in the maintenance inspection plan are executed without omission, if the worker who possesses the terminal device executes inspections regarding the inspection items included in the maintenance inspection plan, A maintenance inspection management system has been proposed in which an inspection item registered in the terminal device is manually registered as an executed inspection item, and the inspection item registered in the terminal device is notified to an external monitoring center as an operation result (for example, Patent Document 1). reference).
実行済の点検項目を端末装置に手動で登録する従来のシステムにおいては、作業員は、保守点検計画に含まれる点検項目の一部について点検を実行していないにも関わらず、実行済の点検項目として端末装置に誤って登録してしまう可能性がある。 In the conventional system in which the inspection items that have already been executed are manually registered in the terminal device, the operator does not carry out inspections for some of the inspection items included in the maintenance inspection plan. There is a possibility that the item is erroneously registered in the terminal device.
このような場合、実際には点検漏れが発生しているにも関わらず、漏れなく点検が実行されたものとして端末装置に登録されているので、点検漏れが発生したことに誰も気付かず、結果として、点検漏れを防止することができない。したがって、点検漏れを防止するためには、実際に点検漏れが発生すれば、その点検漏れを精度良く検出することが前提となる。 In such a case, even though an inspection omission has actually occurred, it is registered in the terminal device as having been inspected without omission, so no one notices that an omission has occurred, As a result, inspection omission cannot be prevented. Therefore, in order to prevent an inspection omission, it is assumed that if an inspection omission actually occurs, the inspection omission is detected with high accuracy.
本発明は、前記のような課題を解決するためになされたものであり、設備ごとに決められた保守点検計画に従って点検を実行する際に発生しうる点検漏れを、簡単な構成で、かつ精度良く検出することのできる設備管理システムおよび設備管理方法を得ることを目的とする。 The present invention has been made in order to solve the above-described problems, and has a simple configuration and accuracy to prevent an inspection omission that may occur when an inspection is performed according to a maintenance inspection plan determined for each facility. The object is to obtain an equipment management system and equipment management method that can be detected well.
本発明における設備管理システムは、保守点検対象である設備の保守点検計画と、保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルを記憶する記憶部と、保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、実作業時間計測部によって計測された、今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、を備え、端末装置は、点検を実行開始する場合に操作されることによって、電源がON状態になり、端末制御部と設備とが接続されて、設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、点検を実行終了する場合に操作されることによって、運転状態がメンテナンスモードから通常モードに切り替えられ、端末制御部と設備との接続が切り離され、電源がOFF状態になるように構成され、実作業時間計測部は、端末装置の電源がON状態になってからOFF状態になるまでの間に経過する時間を、実作業時間として計測するものである。 In the equipment management system according to the present invention, a maintenance inspection plan for equipment that is a maintenance inspection object is associated with an estimated work time estimated to be required when inspections are performed without omission on inspection items included in the maintenance inspection plan. A storage unit for storing the working time table, an actual working time measuring unit for measuring the actual working time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution, and terminal control for controlling operation The estimated work time corresponding to the current maintenance inspection plan is extracted from the terminal device having a work section and the work time table, and the estimated work time and the current work inspection plan measured by the actual work time measurement section are extracted. by comparing the actual operation time required for, and a determining inspection leak judgment unit whether the inspection leak, the terminal device is operated to begin executing the inspection It is configured so that the power supply is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. The operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power is turned off. The actual work time measurement unit is turned on in the terminal device. The time that elapses from when the state is entered until the state is turned off is measured as the actual work time .
本発明によれば、今回の保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する時間として計測された実作業時間と、作業時間テーブルから抽出された、今回の保守点検計画に対応する推定作業時間とを比較することで、点検漏れの有無を判定する構成を備える。これにより、設備ごとに決められた保守点検計画に従って点検を実行する際に発生しうる点検漏れを、簡単な構成で、かつ精度良く検出することのできる設備管理システムおよび設備管理方法を得ることができる。 According to the present invention, the actual work time measured as the time elapsed from the start of the inspection to the end of the execution according to the current maintenance inspection plan, and the current maintenance inspection extracted from the work time table. By comparing the estimated work time corresponding to the plan, a configuration for determining whether there is an inspection omission is provided. As a result, it is possible to obtain an equipment management system and equipment management method capable of accurately detecting an inspection omission that may occur when performing an inspection in accordance with a maintenance inspection plan determined for each equipment with a simple configuration. it can.
以下、本発明による設備管理システムを、好適な実施の形態に従って図面を用いて説明する。なお、以降では、本願発明をエレベータ装置に適用した場合を例示して説明する。 Hereinafter, the equipment management system by this invention is demonstrated using drawing according to suitable embodiment. Hereinafter, a case where the present invention is applied to an elevator apparatus will be described as an example.
実施の形態1.
図1は、本発明の実施の形態1における設備管理システムの構成を示すブロック図である。図1における設備管理システムは、エレベータの保守点検を実行する作業者が所有する端末装置10と、保守点検対象の設備であるエレベータ装置20とを備える。
Embodiment 1 FIG.
FIG. 1 is a block diagram showing a configuration of a facility management system according to Embodiment 1 of the present invention. The facility management system in FIG. 1 includes a
ここで、エレベータ装置20の保守点検においては、一般的に、作業者(フィールドエンジニア)が端末装置10を持って、担当するエレベータ装置20が設置された建物に赴いて、決められた保守点検計画に従って点検を実行する。また、エレベータ装置20の保守点検においては、複数の種類の保守点検計画があらかじめ決められており、端末装置10には、今回の保守点検で実行する保守点検計画に含まれる点検項目(すなわち、作業者が今回実行すべき点検の種類)が画面表示される。作業者は、この画面表示された点検項目について漏れなく点検を実行しなければならない。
Here, in the maintenance and inspection of the
端末装置10は、端末制御部11および実作業時間計測部12を含んで構成される。また、エレベータ装置20は、エレベータ制御部21、記憶部22、点検漏れ判定部23、作業時間テーブル更新部24および報知部25を含んで構成される。
The
端末制御部11は、端末装置10の動作を制御する。また、作業者は、エレベータ装置20の保守点検を開始する場合、端末装置10を操作することで、端末装置10の電源をON状態にして端末制御部11とエレベータ制御部21とを接続し、エレベータ装置20の運転状態を通常モードからメンテナンスモードに切り替える。このように、メンテナンスモードに切り替えることで、点検が実行されている場合に、エレベータ制御部21は、エレベータ装置20を監視する外部の監視センターに警報を通知しない。また、端末制御部11は、今回の保守点検で実行する保守点検計画をエレベータ制御部21に出力する。
The
また、端末制御部11とエレベータ制御部21とが接続されているので、設備側から実績データとして電気信号が取得可能な点検(例えば、安全スイッチの動作点検またはブレーキトルクの点検)が実行された場合、エレベータ制御部21から端末制御部11へ点検の種類に応じた電気信号が入力される。また、端末制御部11に電気信号が入力されれば、この電気信号に対応する点検は、実行済の点検項目として端末装置10に自動的に登録される。一方、手作業の点検(例えば、チェーンへの給油またはレールへの給油)が実行された場合、このような点検は、実行済の点検項目として端末装置10に手動で登録される。
In addition, since the
したがって、このように手動で端末装置10に登録しなければならない点検項目について、作業者は、点検を実行していないにも関わらず、実行済の点検項目として端末装置10に誤って登録してしまう可能性がある。本実施の形態1における設備管理システムでは、このように誤って登録した場合に発生しうる点検漏れを簡単な構成で、かつ精度良く検出することが可能となる。
Therefore, regarding the inspection items that must be manually registered in the
また、保守点検計画に含まれる点検項目について点検が実行され、実行済の点検項目として端末装置10にすべて登録されれば、エレベータ装置20の保守点検が終了となる。この場合、作業員は、端末装置10を操作することで、エレベータ装置20の運転状態をメンテナンスモードから通常モードに切り替え、端末制御部11とエレベータ制御部21との接続を切り離し、端末装置10の電源をOFF状態にする。
Further, if inspections are performed on the inspection items included in the maintenance inspection plan and all the inspection items are registered in the
実作業時間計測部12は、作業者が保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する時間を測定し、測定結果をエレベータ制御部21に出力する。なお、この経過時間が、保守点検計画に含まれる点検項目について点検が実行されたときに要する実作業時間に相当する。このように、端末装置10は、測定された実作業時間をエレベータ装置20へ自動的に送信することとなる。
The actual work
具体的には、実作業時間計測部12は、端末装置10の電源がON状態になってからOFF状態になるまでの間に経過する時間を、実作業時間として計測する。すなわち、前述したように、作業員は、保守点検の開始時に端末装置10の電源をON状態にし、保守点検の終了時に電源をOFF状態にする。したがって、端末装置10の電源がON状態になってからOFF状態になるまでの間に経過する経過時間は、実作業時間と同等であるといえる。なお、実作業時間を測定することができれば、実作業時間計測部12をどのように構成してもよく、例えば、メンテナンスモードに切り替えてから通常モードに切り替えるまでの間に経過する時間、または端末制御部11とエレベータ制御部21とを接続してから接続を切り離すまでの間に経過する時間を、実作業時間として測定するように構成すればよい。
Specifically, the actual work
エレベータ制御部21は、エレベータ全体の動作を制御する。また、エレベータ制御部21は、端末装置10から、今回の保守点検計画と、実作業時間とを取得し、取得結果を点検漏れ判定部23に出力する。
The
記憶部22には、保守点検対象である設備の保守点検計画と、保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルがあらかじめ記憶されている。なお、推定作業時間については、作業条件(例えば、エレベータの機種、かごの容量、エレベータが設置された建物の階床数、または作業者の技術レベル等)に応じてあらかじめ設定しておけばよい。また、エレベータ制御部21が端末装置10からそれを所持する作業員に対応した作業条件を取得し、取得した作業条件に基づいて、作業時間テーブルに含まれる推定作業時間を適宜変更するように構成してもよい。
The storage unit 22 is associated with a maintenance inspection plan for equipment that is a maintenance inspection target, and an estimated work time estimated to be required when the inspection items included in the maintenance inspection plan are executed without omission. A time table is stored in advance. The estimated work time may be set in advance according to work conditions (for example, elevator model, car capacity, number of floors of the building in which the elevator is installed, or the technical level of the worker). . Further, the
点検漏れ判定部23は、エレベータ制御部21から、今回の保守点検計画と、実作業時間とを取得する。また、点検漏れ判定部23は、記憶部22に記憶されている作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、取得した実作業時間とを比較することで、点検漏れの有無を判定する。すなわち、点検漏れが発生していれば、本来実行するはずの点検が実際には実行されていないこととなるので、その分だけ作業時間が短くなり、抽出した推定作業時間に対して、取得した実作業時間が短くなる。したがって、点検漏れ判定部23は、抽出した推定作業時間と、取得した実作業時間とを比較することで、点検漏れの有無を判定することができる。
The inspection
具体的には、点検漏れ判定部23は、例えば、抽出した推定作業時間に対する取得した実作業時間の割合があらかじめ設定した閾値割合(例えば、50%程度)未満であれば、点検漏れが有りと判定し、閾値割合以上であれば点検漏れが無しと判定する。
Specifically, the inspection
このように、実作業時間計測部12から取得された実作業時間と、作業時間テーブルから抽出された推定作業時間とを比較することで点検漏れの有無を判定することによって、点検漏れを精度良く検出することができる。
In this way, by comparing the actual work time acquired from the actual work
作業時間テーブル更新部24は、点検漏れ判定部23によって点検漏れが無しと判定された場合、点検漏れ判定部23から今回の保守点検計画と実作業時間とを取得し、取得した実作業時間を用いて、記憶部22に記憶されている作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を更新する。具体的には、作業時間テーブル更新部24は、例えば、点検漏れ判定部23によって抽出された推定作業時間と、取得した実作業時間との平均値を算出し、作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を、算出した平均値に置き換えて更新する。なお、作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を、取得した実作業時間にそのまま置き換えて更新するように構成してもよい。
When the inspection
このように、今回の保守点検計画を実行することで取得した実作業時間に基づいて、作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を更新することによって、今回の保守点検計画と同じものを次回以降に実行した場合に、点検漏れの有無をより精度良く判定することができる。 In this way, by updating the estimated work time corresponding to the current maintenance check plan in the work time table based on the actual work time obtained by executing the current maintenance check plan, When the same thing is executed after the next time, the presence or absence of inspection omission can be determined with higher accuracy.
報知部25は、点検漏れ判定部23によって点検漏れが有りと判定された場合、点検漏れがあったことを報知する。具体的には、例えば、報知部25は、作業者または作業者を現場で管理する管理者の携帯電話に警告メールを送信することで、点検漏れがあったことを報知する。なお、警報音を鳴らしたり、警報画面を表示したりすることで、点検漏れがあったことを報知するように構成してもよい。また、点検漏れ判定部23によって点検漏れが有りと判定された場合に、例えばかごの走行を停止させるといった、エレベータ装置20が通常の動作をできないようにしてもよい。
When the inspection
このように、点検漏れ判定部23によって点検漏れが有りと判定された場合、例示した上記の手段によって作業者または管理者に点検漏れがあったことを気付かせることができる。したがって、保守点検計画に従って点検を実行する際の点検漏れを防止することができる。
Thus, when it is determined that there is an inspection omission by the inspection
次に、本実施の形態1における設備管理システムの一連の動作について、図2のフローチャートを参照しながら説明する。図2は、本発明の実施の形態1における設備管理システムの一連の動作を示すフローチャートである。 Next, a series of operations of the facility management system according to the first embodiment will be described with reference to the flowchart of FIG. FIG. 2 is a flowchart showing a series of operations of the facility management system according to Embodiment 1 of the present invention.
ステップS101において、点検漏れ判定部23は、エレベータ制御部21から、今回の保守点検計画と、実作業時間とが入力されたか否かを判定する。ここで、点検漏れ判定部23は、今回の保守点検計画と、実作業時間とを取得した(すなわち、YES)と判定した場合には、ステップS102へと進む。一方、点検漏れ判定部23は、今回の保守点検計画と、実作業時間とを取得していない(すなわち、NO)と判定した場合には、再びステップS101の処理を繰り返す。すなわち、点検漏れ判定部23は、エレベータ制御部21から、今回の保守点検計画と、実作業時間とを取得するまで、ステップS101の処理を繰り返すこととなる。
In step S <b> 101, the inspection
ステップS102において、点検漏れ判定部23は、記憶部22に記憶されている作業時間テーブルから、取得した今回の保守点検計画に対応する推定作業時間を抽出し、ステップS103へと進む。
In step S102, the inspection
ステップS103において、点検漏れ判定部23は、取得した実作業時間と、抽出した推定作業時間とを比較し、ステップS104へと進む。
In step S103, the inspection
ステップS104において、点検漏れ判定部23は、ステップS103での比較結果に基づいて、点検漏れの有無を判定する。ここで、点検漏れ判定部23は、点検漏れが有り(すなわち、YES)と判定した場合には、ステップS105へと進む。一方、点検漏れ判定部23は、点検漏れが無し(すなわち、NO)と判定した場合には、ステップS106へと進む。
In step S104, the inspection
ステップS105において、報知部25は、点検漏れがあったことを報知し、一連の処理を終了する。
In step S105, the
ステップS106において、作業時間テーブル更新部24は、点検漏れ判定部23から今回の保守点検計画と実作業時間とを取得し、取得した実作業時間を用いて、記憶部22に記憶されている作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を更新し、一連の処理を終了する。
In step S106, the work time
以上、本実施の形態1によれば、今回の保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する時間として計測された実作業時間と、作業時間テーブルから抽出された、今回の保守点検計画に対応する推定作業時間とを比較することで点検漏れの有無を判定する構成を備える。これにより、設備ごとに決められた保守点検計画に従って点検を実行する際に発生しうる点検漏れを、簡単な構成で、かつ精度良く検出することができる。 As described above, according to the first embodiment, the actual work time measured as the time elapsed from the start of the inspection to the end of the execution according to the current maintenance inspection plan is extracted from the work time table. A configuration is provided in which the presence or absence of inspection omission is determined by comparing the estimated work time corresponding to the current maintenance inspection plan. Thereby, the inspection omission which may occur when the inspection is executed according to the maintenance inspection plan determined for each facility can be detected with a simple configuration and with high accuracy.
また、点検漏れが無しと判定されれば、計測された実作業時間を用いて、作業時間テーブルに含まれる今回の保守点検計画に対応する推定作業時間を更新する構成を備える。これにより、今回の保守点検計画と同じものを次回以降に実行した場合に、点検漏れの有無をより精度良く判定することができる。 If it is determined that there is no inspection omission, the estimated operation time corresponding to the current maintenance inspection plan included in the operation time table is updated using the measured actual operation time. Thereby, when the same thing as this maintenance inspection plan is performed after the next time, the presence or absence of inspection omission can be determined more accurately.
さらに、点検漏れが有りと判定された場合、点検漏れがあったことを報知する構成を備える。これにより、設備ごとに決められた保守点検計画に従って点検を実行する際の点検漏れを防止することができる。また、端末装置への登録間違いによる点検漏れを防止することができ、従来以上の機器品質の維持および向上に寄与することができる。 Furthermore, when it is determined that there is an inspection omission, a configuration for notifying that an inspection omission has occurred is provided. Thereby, it is possible to prevent an inspection omission when performing an inspection in accordance with a maintenance inspection plan determined for each facility. In addition, it is possible to prevent omission of inspection due to a registration error in the terminal device, and it is possible to contribute to the maintenance and improvement of the equipment quality higher than the conventional one.
なお、本実施の形態1では、設備管理システムの具体例として、実作業時間計測部12が端末装置10に含まれるように構成し、記憶部22、点検漏れ判定部23、作業時間テーブル更新部24および報知部25がエレベータ装置20に含まれるように構成する場合を例示したが、これに限定されない。すなわち、端末装置10、エレベータ装置20および外部の監視センターは、それぞれ互いに通信可能であるので、本願発明の技術的特徴である実作業時間計測部12、記憶部22、点検漏れ判定部23、作業時間テーブル更新部24および報知部25のそれぞれは、端末装置10、エレベータ装置20および外部の監視センターのいずれかに含まれていれば、同様の効果が得られる。
In the first embodiment, as a specific example of the equipment management system, the actual work
また、本実施の形態1では、本願発明をエレベータに適用した場合を例示して説明したが、これに限定されず、決められた保守点検計画に従って、定期的にさまざまな保守点検が実行されるような設備(例えば、エスカレータおよび動く歩道等といった乗客コンベア装置)に対しても本願発明を適用することができる。 In the first embodiment, the case where the present invention is applied to an elevator has been described as an example. However, the present invention is not limited to this, and various maintenance inspections are periodically performed according to a determined maintenance inspection plan. The present invention can also be applied to such facilities (for example, passenger conveyor devices such as escalators and moving walkways).
10 端末装置、11 端末制御部、12 実作業時間計測部、20 エレベータ装置、21 エレベータ制御部、22 記憶部、23 点検漏れ判定部、24 作業時間テーブル更新部、25 報知部。
DESCRIPTION OF
Claims (5)
前記保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、
前記作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、前記実作業時間計測部によって計測された、前記今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、
を備え、
前記端末装置は、
前記点検を実行開始する場合に操作されることによって、電源がON状態になり、前記端末制御部と前記設備とが接続されて、前記設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、
前記点検を実行終了する場合に操作されることによって、前記運転状態が前記メンテナンスモードから前記通常モードに切り替えられ、前記端末制御部と前記設備との接続が切り離され、前記電源がOFF状態になるように構成され、
前記実作業時間計測部は、
前記端末装置の前記電源がON状態になってからOFF状態になるまでの間に経過する時間を、前記実作業時間として計測する
設備管理システム。 Stores a work time table in which a maintenance check plan of equipment that is a maintenance check target and an estimated work time estimated to be required when the check items included in the maintenance check plan are executed without omission are stored. A storage unit;
A terminal device having an actual work time measurement unit that measures an actual work time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution; and a terminal control unit that controls operation;
The estimated work time corresponding to the current maintenance inspection plan is extracted from the work time table, and the extracted estimated work time and the actual work required for the current maintenance inspection plan measured by the actual work time measurement unit. By comparing the time, the inspection omission determination unit that determines the presence or absence of inspection omissions, and
Equipped with a,
The terminal device
By operating when starting the inspection, the power is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. Configured,
By operating when the inspection is finished, the operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power supply is turned off. Configured as
The actual work time measuring unit is
An equipment management system that measures the time elapsed from when the power of the terminal device is turned on to when it is turned off as the actual work time .
前記保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、A terminal device having an actual work time measurement unit that measures an actual work time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution; and a terminal control unit that controls operation;
前記作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、前記実作業時間計測部によって計測された、前記今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、The estimated work time corresponding to the current maintenance inspection plan is extracted from the work time table, and the extracted estimated work time and the actual work required for the current maintenance inspection plan measured by the actual work time measurement unit. By comparing the time, the inspection omission determination unit that determines the presence or absence of inspection omissions, and
を備え、With
前記端末装置は、The terminal device
前記点検を実行開始する場合に操作されることによって、電源がON状態になり、前記端末制御部と前記設備とが接続されて、前記設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、By operating when starting the inspection, the power is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. Configured,
前記点検を実行終了する場合に操作されることによって、前記運転状態が前記メンテナンスモードから前記通常モードに切り替えられ、前記端末制御部と前記設備との接続が切り離され、前記電源がOFF状態になるように構成され、By operating when the inspection is finished, the operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power supply is turned off. Configured as
前記実作業時間計測部は、The actual work time measuring unit is
前記メンテナンスモードに切り替えてから前記通常モードに切り替えるまでの間に経過する時間を、前記実作業時間として計測するThe time elapsed between switching to the maintenance mode and switching to the normal mode is measured as the actual work time.
設備管理システム。Equipment management system.
前記保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、A terminal device having an actual work time measurement unit that measures an actual work time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution; and a terminal control unit that controls operation;
前記作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、前記実作業時間計測部によって計測された、前記今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、The estimated work time corresponding to the current maintenance inspection plan is extracted from the work time table, and the extracted estimated work time and the actual work required for the current maintenance inspection plan measured by the actual work time measurement unit. By comparing the time, the inspection omission determination unit that determines the presence or absence of inspection omissions, and
を備え、With
前記端末装置は、The terminal device
前記点検を実行開始する場合に操作されることによって、電源がON状態になり、前記端末制御部と前記設備とが接続されて、前記設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、By operating when starting the inspection, the power is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. Configured,
前記点検を実行終了する場合に操作されることによって、前記運転状態が前記メンテナンスモードから前記通常モードに切り替えられ、前記端末制御部と前記設備との接続が切り離され、前記電源がOFF状態になるように構成され、By operating when the inspection is finished, the operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power supply is turned off. Configured as
前記実作業時間計測部は、The actual work time measuring unit is
前記端末制御部と前記設備とを接続してから当該接続を切り離すまでの間に経過する時間を、前記実作業時間として計測するThe time elapsed from when the terminal control unit and the equipment are connected to when the connection is disconnected is measured as the actual work time.
設備管理システム。Equipment management system.
請求項1から3のいずれか1項に記載の設備管理システム。 When the inspection omission determination unit determines that the inspection omission is absent, the actual operation time measured by the actual operation time measurement unit is used to correspond to the current maintenance inspection plan included in the operation time table. The equipment management system according to any one of claims 1 to 3, further comprising a work time table update unit that updates an estimated work time to be performed.
請求項1から4のいずれか1項に記載の設備管理システム。 The equipment management system according to any one of claims 1 to 4, further comprising a notification unit that notifies that there is an inspection omission when the inspection omission determination unit determines that the inspection omission is present.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2014144159A JP6403470B2 (en) | 2014-07-14 | 2014-07-14 | Equipment management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2014144159A JP6403470B2 (en) | 2014-07-14 | 2014-07-14 | Equipment management system |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2016021121A JP2016021121A (en) | 2016-02-04 |
JP6403470B2 true JP6403470B2 (en) | 2018-10-10 |
Family
ID=55265929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2014144159A Active JP6403470B2 (en) | 2014-07-14 | 2014-07-14 | Equipment management system |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6403470B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6074079B1 (en) * | 2016-02-09 | 2017-02-01 | 東芝エレベータ株式会社 | Maintenance work safety device |
JP2019067050A (en) * | 2017-09-29 | 2019-04-25 | 株式会社日立ビルシステム | Work support system |
JP2019125177A (en) * | 2018-01-17 | 2019-07-25 | ダイハツ工業株式会社 | Inspection system |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000315110A (en) * | 1999-04-30 | 2000-11-14 | Mitsubishi Electric Corp | Device and method for supporting maintenance inspection |
JP4443091B2 (en) * | 2002-03-20 | 2010-03-31 | 日立オムロンターミナルソリューションズ株式会社 | Maintenance server and transaction processing apparatus |
JP4370960B2 (en) * | 2004-03-29 | 2009-11-25 | 三菱自動車エンジニアリング株式会社 | Vehicle inspection management system |
JP4261435B2 (en) * | 2004-08-09 | 2009-04-30 | イオンディライト株式会社 | Equipment inspection support system |
JP2006151529A (en) * | 2004-11-25 | 2006-06-15 | Mitsubishi Electric Building Techno Service Co Ltd | Elevator maintenance work check system and elevator maintenance operator terminal device |
EP2458466B1 (en) * | 2010-11-30 | 2020-02-26 | Industrial Development of Automotivo Components, IDACO corp | Automatic supervision and control system |
JP2012190209A (en) * | 2011-03-10 | 2012-10-04 | Mitsubishi Electric Building Techno Service Co Ltd | System for visit maintenance work management of building facility |
JP2013205277A (en) * | 2012-03-29 | 2013-10-07 | Terumo Corp | Visual inspection monitor system and visual inspection monitor method |
-
2014
- 2014-07-14 JP JP2014144159A patent/JP6403470B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2016021121A (en) | 2016-02-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2018169769A5 (en) | ||
JP6169253B2 (en) | AIR CONDITIONING SYSTEM AND ITS TRANSMISSION RELAY DEVICE | |
JP6403470B2 (en) | Equipment management system | |
JP6370132B2 (en) | Communication abnormality detection device, communication abnormality detection method and program | |
JP2013171383A (en) | Portable terminal device, work management system and work management method | |
KR101940633B1 (en) | Real time monitoring system for railway vehicles | |
JP2017192267A (en) | Brake inspection apparatus and brake inspection method | |
CN111137773B (en) | Method and system for detecting faults in an elevator system | |
KR20130080103A (en) | Self-diagnostic apparatus and method for electric device | |
CN102040129B (en) | Control operation device of elevator | |
WO2018122928A1 (en) | Recovery support system | |
KR101602143B1 (en) | Crane safety monitoring system | |
MY181687A (en) | Equipment monitoring system, equipment monitoring program, and equipment monitoring method | |
WO2020147710A1 (en) | Elevator fault diagnosis method, apparatus, device and medium | |
JP2019038650A (en) | Remote diagnosis operation method of elevator, elevator control device, and remote diagnosis operation program of elevator | |
JP2015137156A (en) | Elevator remote monitor device | |
JP2012206800A5 (en) | Monitoring system, terminal device and warning method | |
JP2011132013A (en) | Elevator maintenance system, maintenance terminal device, and method of maintaining elevator | |
KR101552174B1 (en) | Apparatus for monitoring multi power isolation having signal detection mode, and method for monitoring multi power isolation using the same | |
JP2017219926A (en) | Sensor system | |
JP4784949B2 (en) | Elevator operation control device | |
JP2019159853A (en) | Production management device, production management system, and production management method | |
KR101868935B1 (en) | Alarm device for parts replacement time of Elevator | |
JP6403646B2 (en) | Elevator remote monitoring system and elevator remote monitoring method | |
JP6477996B1 (en) | Display control device with function to update display of elevator inspection information |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20170113 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20180125 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20180130 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20180301 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20180814 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20180911 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6403470 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |