JP6403470B2 - Equipment management system - Google Patents

Equipment management system Download PDF

Info

Publication number
JP6403470B2
JP6403470B2 JP2014144159A JP2014144159A JP6403470B2 JP 6403470 B2 JP6403470 B2 JP 6403470B2 JP 2014144159 A JP2014144159 A JP 2014144159A JP 2014144159 A JP2014144159 A JP 2014144159A JP 6403470 B2 JP6403470 B2 JP 6403470B2
Authority
JP
Japan
Prior art keywords
inspection
work time
maintenance
plan
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014144159A
Other languages
Japanese (ja)
Other versions
JP2016021121A (en
Inventor
白石 孝
孝 白石
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Building Solutions Corp
Original Assignee
Mitsubishi Electric Building Techno Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Building Techno Service Co Ltd filed Critical Mitsubishi Electric Building Techno Service Co Ltd
Priority to JP2014144159A priority Critical patent/JP6403470B2/en
Publication of JP2016021121A publication Critical patent/JP2016021121A/en
Application granted granted Critical
Publication of JP6403470B2 publication Critical patent/JP6403470B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Maintenance And Inspection Apparatuses For Elevators (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、設備ごとに決められた保守点検計画に従って点検を実行する際の点検漏れを防止する設備管理システムおよび設備管理方法に関するものである。   The present invention relates to a facility management system and a facility management method for preventing an inspection omission when performing an inspection according to a maintenance inspection plan determined for each facility.

従来では、エレベータ装置等といった保守点検が必要な設備に対しては、設備ごとに決められた保守点検計画に従って、定期的にさまざまな保守点検が実行される。具体的には、例えば、エレベータ装置に対応する保守点検計画として、安全スイッチの動作点検、ブレーキトルクの点検、チェーンへの給油、およびレールへの給油という4つの点検項目がある場合、作業員は、これらの4つの点検項目について漏れなく点検を実行しなければならない。   Conventionally, various maintenance inspections such as an elevator apparatus are periodically performed according to a maintenance inspection plan determined for each facility for maintenance inspections. Specifically, for example, when the maintenance inspection plan corresponding to the elevator apparatus includes four inspection items, that is, safety switch operation inspection, brake torque inspection, chain lubrication, and rail lubrication, These four inspection items must be inspected without omission.

ここで、保守点検計画に含まれる点検項目について漏れなく点検が実行されているかを把握するために、端末装置を所持する作業員が、保守点検計画に含まれる点検項目について点検を実行すれば、実行済の点検項目として端末装置に手動で登録し、端末装置に登録された点検項目が、作業実績として外部の監視センターに通知される保守点検管理システムが提案されている(例えば、特許文献1参照)。   Here, in order to grasp whether the inspection items included in the maintenance inspection plan are executed without omission, if the worker who possesses the terminal device executes inspections regarding the inspection items included in the maintenance inspection plan, A maintenance inspection management system has been proposed in which an inspection item registered in the terminal device is manually registered as an executed inspection item, and the inspection item registered in the terminal device is notified to an external monitoring center as an operation result (for example, Patent Document 1). reference).

特開2007−137658号公報JP 2007-137658 A

実行済の点検項目を端末装置に手動で登録する従来のシステムにおいては、作業員は、保守点検計画に含まれる点検項目の一部について点検を実行していないにも関わらず、実行済の点検項目として端末装置に誤って登録してしまう可能性がある。   In the conventional system in which the inspection items that have already been executed are manually registered in the terminal device, the operator does not carry out inspections for some of the inspection items included in the maintenance inspection plan. There is a possibility that the item is erroneously registered in the terminal device.

このような場合、実際には点検漏れが発生しているにも関わらず、漏れなく点検が実行されたものとして端末装置に登録されているので、点検漏れが発生したことに誰も気付かず、結果として、点検漏れを防止することができない。したがって、点検漏れを防止するためには、実際に点検漏れが発生すれば、その点検漏れを精度良く検出することが前提となる。   In such a case, even though an inspection omission has actually occurred, it is registered in the terminal device as having been inspected without omission, so no one notices that an omission has occurred, As a result, inspection omission cannot be prevented. Therefore, in order to prevent an inspection omission, it is assumed that if an inspection omission actually occurs, the inspection omission is detected with high accuracy.

本発明は、前記のような課題を解決するためになされたものであり、設備ごとに決められた保守点検計画に従って点検を実行する際に発生しうる点検漏れを、簡単な構成で、かつ精度良く検出することのできる設備管理システムおよび設備管理方法を得ることを目的とする。   The present invention has been made in order to solve the above-described problems, and has a simple configuration and accuracy to prevent an inspection omission that may occur when an inspection is performed according to a maintenance inspection plan determined for each facility. The object is to obtain an equipment management system and equipment management method that can be detected well.

本発明における設備管理システムは、保守点検対象である設備の保守点検計画と、保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルを記憶する記憶部と、保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、実作業時間計測部によって計測された、今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、を備え、端末装置は、点検を実行開始する場合に操作されることによって、電源がON状態になり、端末制御部と設備とが接続されて、設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、点検を実行終了する場合に操作されることによって、運転状態がメンテナンスモードから通常モードに切り替えられ、端末制御部と設備との接続が切り離され、電源がOFF状態になるように構成され、実作業時間計測部は、端末装置の電源がON状態になってからOFF状態になるまでの間に経過する時間を、実作業時間として計測するものである。 In the equipment management system according to the present invention, a maintenance inspection plan for equipment that is a maintenance inspection object is associated with an estimated work time estimated to be required when inspections are performed without omission on inspection items included in the maintenance inspection plan. A storage unit for storing the working time table, an actual working time measuring unit for measuring the actual working time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution, and terminal control for controlling operation The estimated work time corresponding to the current maintenance inspection plan is extracted from the terminal device having a work section and the work time table, and the estimated work time and the current work inspection plan measured by the actual work time measurement section are extracted. by comparing the actual operation time required for, and a determining inspection leak judgment unit whether the inspection leak, the terminal device is operated to begin executing the inspection It is configured so that the power supply is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. The operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power is turned off. The actual work time measurement unit is turned on in the terminal device. The time that elapses from when the state is entered until the state is turned off is measured as the actual work time .

本発明によれば、今回の保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する時間として計測された実作業時間と、作業時間テーブルから抽出された、今回の保守点検計画に対応する推定作業時間とを比較することで、点検漏れの有無を判定する構成を備える。これにより、設備ごとに決められた保守点検計画に従って点検を実行する際に発生しうる点検漏れを、簡単な構成で、かつ精度良く検出することのできる設備管理システムおよび設備管理方法を得ることができる。   According to the present invention, the actual work time measured as the time elapsed from the start of the inspection to the end of the execution according to the current maintenance inspection plan, and the current maintenance inspection extracted from the work time table. By comparing the estimated work time corresponding to the plan, a configuration for determining whether there is an inspection omission is provided. As a result, it is possible to obtain an equipment management system and equipment management method capable of accurately detecting an inspection omission that may occur when performing an inspection in accordance with a maintenance inspection plan determined for each equipment with a simple configuration. it can.

本発明の実施の形態1における設備管理システムの構成を示すブロック図である。It is a block diagram which shows the structure of the equipment management system in Embodiment 1 of this invention. 本発明の実施の形態1における設備管理システムの一連の動作を示すフローチャートである。It is a flowchart which shows a series of operation | movement of the equipment management system in Embodiment 1 of this invention.

以下、本発明による設備管理システムを、好適な実施の形態に従って図面を用いて説明する。なお、以降では、本願発明をエレベータ装置に適用した場合を例示して説明する。   Hereinafter, the equipment management system by this invention is demonstrated using drawing according to suitable embodiment. Hereinafter, a case where the present invention is applied to an elevator apparatus will be described as an example.

実施の形態1.
図1は、本発明の実施の形態1における設備管理システムの構成を示すブロック図である。図1における設備管理システムは、エレベータの保守点検を実行する作業者が所有する端末装置10と、保守点検対象の設備であるエレベータ装置20とを備える。
Embodiment 1 FIG.
FIG. 1 is a block diagram showing a configuration of a facility management system according to Embodiment 1 of the present invention. The facility management system in FIG. 1 includes a terminal device 10 owned by an operator who performs maintenance and inspection of an elevator, and an elevator device 20 that is a facility to be subjected to maintenance and inspection.

ここで、エレベータ装置20の保守点検においては、一般的に、作業者(フィールドエンジニア)が端末装置10を持って、担当するエレベータ装置20が設置された建物に赴いて、決められた保守点検計画に従って点検を実行する。また、エレベータ装置20の保守点検においては、複数の種類の保守点検計画があらかじめ決められており、端末装置10には、今回の保守点検で実行する保守点検計画に含まれる点検項目(すなわち、作業者が今回実行すべき点検の種類)が画面表示される。作業者は、この画面表示された点検項目について漏れなく点検を実行しなければならない。   Here, in the maintenance and inspection of the elevator apparatus 20, generally, an operator (field engineer) holds the terminal device 10, visits the building where the elevator apparatus 20 in charge is installed, and has a determined maintenance inspection plan. Perform inspection according to In the maintenance inspection of the elevator apparatus 20, a plurality of types of maintenance inspection plans are determined in advance, and the terminal device 10 includes inspection items (that is, work items included in the maintenance inspection plan executed in the current maintenance inspection). The type of inspection that the person should perform this time) is displayed on the screen. The operator must perform inspection without omission on the inspection items displayed on this screen.

端末装置10は、端末制御部11および実作業時間計測部12を含んで構成される。また、エレベータ装置20は、エレベータ制御部21、記憶部22、点検漏れ判定部23、作業時間テーブル更新部24および報知部25を含んで構成される。   The terminal device 10 includes a terminal control unit 11 and an actual work time measurement unit 12. The elevator apparatus 20 includes an elevator control unit 21, a storage unit 22, an inspection omission determination unit 23, a work time table update unit 24, and a notification unit 25.

端末制御部11は、端末装置10の動作を制御する。また、作業者は、エレベータ装置20の保守点検を開始する場合、端末装置10を操作することで、端末装置10の電源をON状態にして端末制御部11とエレベータ制御部21とを接続し、エレベータ装置20の運転状態を通常モードからメンテナンスモードに切り替える。このように、メンテナンスモードに切り替えることで、点検が実行されている場合に、エレベータ制御部21は、エレベータ装置20を監視する外部の監視センターに警報を通知しない。また、端末制御部11は、今回の保守点検で実行する保守点検計画をエレベータ制御部21に出力する。   The terminal control unit 11 controls the operation of the terminal device 10. Further, when starting maintenance and inspection of the elevator apparatus 20, the operator operates the terminal apparatus 10 to turn on the terminal apparatus 10 and connect the terminal control unit 11 and the elevator control unit 21. The operation state of the elevator apparatus 20 is switched from the normal mode to the maintenance mode. Thus, when the inspection is being performed by switching to the maintenance mode, the elevator control unit 21 does not notify the external monitoring center that monitors the elevator device 20. Further, the terminal control unit 11 outputs a maintenance inspection plan to be executed in the current maintenance inspection to the elevator control unit 21.

また、端末制御部11とエレベータ制御部21とが接続されているので、設備側から実績データとして電気信号が取得可能な点検(例えば、安全スイッチの動作点検またはブレーキトルクの点検)が実行された場合、エレベータ制御部21から端末制御部11へ点検の種類に応じた電気信号が入力される。また、端末制御部11に電気信号が入力されれば、この電気信号に対応する点検は、実行済の点検項目として端末装置10に自動的に登録される。一方、手作業の点検(例えば、チェーンへの給油またはレールへの給油)が実行された場合、このような点検は、実行済の点検項目として端末装置10に手動で登録される。   In addition, since the terminal control unit 11 and the elevator control unit 21 are connected, an inspection (for example, a safety switch operation inspection or a brake torque inspection) that can acquire an electrical signal as performance data from the equipment side has been performed. In this case, an electrical signal corresponding to the type of inspection is input from the elevator control unit 21 to the terminal control unit 11. Further, if an electrical signal is input to the terminal control unit 11, the inspection corresponding to the electrical signal is automatically registered in the terminal device 10 as a completed inspection item. On the other hand, when a manual inspection (for example, lubrication of the chain or lubrication of the rail) is performed, such inspection is manually registered in the terminal device 10 as an performed inspection item.

したがって、このように手動で端末装置10に登録しなければならない点検項目について、作業者は、点検を実行していないにも関わらず、実行済の点検項目として端末装置10に誤って登録してしまう可能性がある。本実施の形態1における設備管理システムでは、このように誤って登録した場合に発生しうる点検漏れを簡単な構成で、かつ精度良く検出することが可能となる。   Therefore, regarding the inspection items that must be manually registered in the terminal device 10 as described above, the operator mistakenly registers the inspection items in the terminal device 10 as the inspection items that have been performed even though the inspection has not been performed. There is a possibility. In the facility management system according to the first embodiment, it is possible to accurately detect an inspection omission that may occur when such an erroneous registration is performed with a simple configuration.

また、保守点検計画に含まれる点検項目について点検が実行され、実行済の点検項目として端末装置10にすべて登録されれば、エレベータ装置20の保守点検が終了となる。この場合、作業員は、端末装置10を操作することで、エレベータ装置20の運転状態をメンテナンスモードから通常モードに切り替え、端末制御部11とエレベータ制御部21との接続を切り離し、端末装置10の電源をOFF状態にする。   Further, if inspections are performed on the inspection items included in the maintenance inspection plan and all the inspection items are registered in the terminal device 10, the maintenance inspection of the elevator apparatus 20 is completed. In this case, the operator operates the terminal device 10 to switch the operation state of the elevator apparatus 20 from the maintenance mode to the normal mode, disconnects the terminal control unit 11 and the elevator control unit 21, and Turn off the power.

実作業時間計測部12は、作業者が保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する時間を測定し、測定結果をエレベータ制御部21に出力する。なお、この経過時間が、保守点検計画に含まれる点検項目について点検が実行されたときに要する実作業時間に相当する。このように、端末装置10は、測定された実作業時間をエレベータ装置20へ自動的に送信することとなる。   The actual work time measurement unit 12 measures the time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution, and outputs the measurement result to the elevator control unit 21. Note that this elapsed time corresponds to the actual work time required when inspections are performed on the inspection items included in the maintenance inspection plan. Thus, the terminal device 10 automatically transmits the measured actual work time to the elevator device 20.

具体的には、実作業時間計測部12は、端末装置10の電源がON状態になってからOFF状態になるまでの間に経過する時間を、実作業時間として計測する。すなわち、前述したように、作業員は、保守点検の開始時に端末装置10の電源をON状態にし、保守点検の終了時に電源をOFF状態にする。したがって、端末装置10の電源がON状態になってからOFF状態になるまでの間に経過する経過時間は、実作業時間と同等であるといえる。なお、実作業時間を測定することができれば、実作業時間計測部12をどのように構成してもよく、例えば、メンテナンスモードに切り替えてから通常モードに切り替えるまでの間に経過する時間、または端末制御部11とエレベータ制御部21とを接続してから接続を切り離すまでの間に経過する時間を、実作業時間として測定するように構成すればよい。   Specifically, the actual work time measurement unit 12 measures the time that elapses from when the terminal device 10 is turned on until it is turned off as the actual work time. That is, as described above, the worker turns on the power supply of the terminal device 10 at the start of the maintenance inspection and turns off the power supply at the end of the maintenance inspection. Therefore, it can be said that the elapsed time elapsed from when the power supply of the terminal device 10 is turned on to when it is turned off is equivalent to the actual work time. Note that the actual work time measurement unit 12 may be configured in any manner as long as the actual work time can be measured. For example, the time that elapses between the switch to the maintenance mode and the switch to the normal mode, or the terminal What is necessary is just to comprise so that the time which passes after connecting the control part 11 and the elevator control part 21 until it disconnects may be measured as real work time.

エレベータ制御部21は、エレベータ全体の動作を制御する。また、エレベータ制御部21は、端末装置10から、今回の保守点検計画と、実作業時間とを取得し、取得結果を点検漏れ判定部23に出力する。   The elevator control unit 21 controls the operation of the entire elevator. In addition, the elevator control unit 21 acquires the current maintenance inspection plan and the actual work time from the terminal device 10, and outputs the acquisition result to the inspection omission determination unit 23.

記憶部22には、保守点検対象である設備の保守点検計画と、保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルがあらかじめ記憶されている。なお、推定作業時間については、作業条件(例えば、エレベータの機種、かごの容量、エレベータが設置された建物の階床数、または作業者の技術レベル等)に応じてあらかじめ設定しておけばよい。また、エレベータ制御部21が端末装置10からそれを所持する作業員に対応した作業条件を取得し、取得した作業条件に基づいて、作業時間テーブルに含まれる推定作業時間を適宜変更するように構成してもよい。   The storage unit 22 is associated with a maintenance inspection plan for equipment that is a maintenance inspection target, and an estimated work time estimated to be required when the inspection items included in the maintenance inspection plan are executed without omission. A time table is stored in advance. The estimated work time may be set in advance according to work conditions (for example, elevator model, car capacity, number of floors of the building in which the elevator is installed, or the technical level of the worker). . Further, the elevator control unit 21 is configured to acquire a work condition corresponding to the worker who possesses it from the terminal device 10 and appropriately change the estimated work time included in the work time table based on the acquired work condition. May be.

点検漏れ判定部23は、エレベータ制御部21から、今回の保守点検計画と、実作業時間とを取得する。また、点検漏れ判定部23は、記憶部22に記憶されている作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、取得した実作業時間とを比較することで、点検漏れの有無を判定する。すなわち、点検漏れが発生していれば、本来実行するはずの点検が実際には実行されていないこととなるので、その分だけ作業時間が短くなり、抽出した推定作業時間に対して、取得した実作業時間が短くなる。したがって、点検漏れ判定部23は、抽出した推定作業時間と、取得した実作業時間とを比較することで、点検漏れの有無を判定することができる。   The inspection omission determination unit 23 acquires the current maintenance inspection plan and the actual work time from the elevator control unit 21. Further, the inspection omission determination unit 23 extracts the estimated work time corresponding to the current maintenance check plan from the work time table stored in the storage unit 22, and extracts the estimated work time and the acquired actual work time. To determine whether there is an inspection omission. In other words, if an inspection omission has occurred, the inspection that should have been performed is not actually executed, so the work time is shortened by that amount, and the obtained estimated work time is obtained. Actual work time is shortened. Therefore, the inspection omission determination unit 23 can determine the presence or absence of inspection omission by comparing the extracted estimated work time with the acquired actual work time.

具体的には、点検漏れ判定部23は、例えば、抽出した推定作業時間に対する取得した実作業時間の割合があらかじめ設定した閾値割合(例えば、50%程度)未満であれば、点検漏れが有りと判定し、閾値割合以上であれば点検漏れが無しと判定する。   Specifically, the inspection omission determination unit 23 determines that there is an omission if, for example, the ratio of the acquired actual work time to the extracted estimated work time is less than a preset threshold ratio (for example, about 50%). If it is determined that the ratio is greater than or equal to the threshold ratio, it is determined that there is no inspection omission.

このように、実作業時間計測部12から取得された実作業時間と、作業時間テーブルから抽出された推定作業時間とを比較することで点検漏れの有無を判定することによって、点検漏れを精度良く検出することができる。   In this way, by comparing the actual work time acquired from the actual work time measuring unit 12 with the estimated work time extracted from the work time table, it is determined whether there is a check omission, thereby accurately detecting the check omission. Can be detected.

作業時間テーブル更新部24は、点検漏れ判定部23によって点検漏れが無しと判定された場合、点検漏れ判定部23から今回の保守点検計画と実作業時間とを取得し、取得した実作業時間を用いて、記憶部22に記憶されている作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を更新する。具体的には、作業時間テーブル更新部24は、例えば、点検漏れ判定部23によって抽出された推定作業時間と、取得した実作業時間との平均値を算出し、作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を、算出した平均値に置き換えて更新する。なお、作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を、取得した実作業時間にそのまま置き換えて更新するように構成してもよい。   When the inspection omission determination unit 23 determines that there is no inspection omission, the operation time table update unit 24 acquires the current maintenance inspection plan and the actual operation time from the inspection omission determination unit 23, and uses the acquired actual operation time. The estimated work time corresponding to the current maintenance inspection plan in the work time table stored in the storage unit 22 is updated. Specifically, the work time table update unit 24 calculates, for example, an average value of the estimated work time extracted by the inspection omission determination unit 23 and the acquired actual work time, and performs the current maintenance in the work time table. The estimated work time corresponding to the inspection plan is replaced with the calculated average value and updated. Note that the estimated work time corresponding to the current maintenance inspection plan in the work time table may be updated by directly replacing the acquired actual work time.

このように、今回の保守点検計画を実行することで取得した実作業時間に基づいて、作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を更新することによって、今回の保守点検計画と同じものを次回以降に実行した場合に、点検漏れの有無をより精度良く判定することができる。   In this way, by updating the estimated work time corresponding to the current maintenance check plan in the work time table based on the actual work time obtained by executing the current maintenance check plan, When the same thing is executed after the next time, the presence or absence of inspection omission can be determined with higher accuracy.

報知部25は、点検漏れ判定部23によって点検漏れが有りと判定された場合、点検漏れがあったことを報知する。具体的には、例えば、報知部25は、作業者または作業者を現場で管理する管理者の携帯電話に警告メールを送信することで、点検漏れがあったことを報知する。なお、警報音を鳴らしたり、警報画面を表示したりすることで、点検漏れがあったことを報知するように構成してもよい。また、点検漏れ判定部23によって点検漏れが有りと判定された場合に、例えばかごの走行を停止させるといった、エレベータ装置20が通常の動作をできないようにしてもよい。   When the inspection omission determination unit 23 determines that there is an inspection omission, the notification unit 25 notifies that an inspection omission has occurred. Specifically, for example, the notification unit 25 notifies the operator or the administrator who manages the worker on-site that a warning mail is transmitted to notify that there is an inspection failure. In addition, you may comprise so that it may alert | report that there was an inspection omission by sounding an alarm sound or displaying an alarm screen. Further, when the inspection omission determination unit 23 determines that there is an omission in the inspection, the elevator apparatus 20 may be prevented from performing a normal operation, for example, to stop the traveling of the car.

このように、点検漏れ判定部23によって点検漏れが有りと判定された場合、例示した上記の手段によって作業者または管理者に点検漏れがあったことを気付かせることができる。したがって、保守点検計画に従って点検を実行する際の点検漏れを防止することができる。   Thus, when it is determined that there is an inspection omission by the inspection omission determination unit 23, it is possible to make the operator or the administrator aware that there is an omission in inspection by the above-described means. Therefore, it is possible to prevent an inspection omission when the inspection is executed according to the maintenance inspection plan.

次に、本実施の形態1における設備管理システムの一連の動作について、図2のフローチャートを参照しながら説明する。図2は、本発明の実施の形態1における設備管理システムの一連の動作を示すフローチャートである。   Next, a series of operations of the facility management system according to the first embodiment will be described with reference to the flowchart of FIG. FIG. 2 is a flowchart showing a series of operations of the facility management system according to Embodiment 1 of the present invention.

ステップS101において、点検漏れ判定部23は、エレベータ制御部21から、今回の保守点検計画と、実作業時間とが入力されたか否かを判定する。ここで、点検漏れ判定部23は、今回の保守点検計画と、実作業時間とを取得した(すなわち、YES)と判定した場合には、ステップS102へと進む。一方、点検漏れ判定部23は、今回の保守点検計画と、実作業時間とを取得していない(すなわち、NO)と判定した場合には、再びステップS101の処理を繰り返す。すなわち、点検漏れ判定部23は、エレベータ制御部21から、今回の保守点検計画と、実作業時間とを取得するまで、ステップS101の処理を繰り返すこととなる。   In step S <b> 101, the inspection omission determination unit 23 determines whether or not the current maintenance inspection plan and the actual work time are input from the elevator control unit 21. If the inspection omission determination unit 23 determines that the current maintenance inspection plan and the actual work time have been acquired (that is, YES), the process proceeds to step S102. On the other hand, if the inspection omission determination unit 23 determines that the current maintenance inspection plan and the actual work time have not been acquired (that is, NO), the process of step S101 is repeated again. That is, the inspection omission determination unit 23 repeats the process of step S101 until the current maintenance inspection plan and the actual work time are acquired from the elevator control unit 21.

ステップS102において、点検漏れ判定部23は、記憶部22に記憶されている作業時間テーブルから、取得した今回の保守点検計画に対応する推定作業時間を抽出し、ステップS103へと進む。   In step S102, the inspection omission determination unit 23 extracts the estimated work time corresponding to the acquired current maintenance check plan from the work time table stored in the storage unit 22, and proceeds to step S103.

ステップS103において、点検漏れ判定部23は、取得した実作業時間と、抽出した推定作業時間とを比較し、ステップS104へと進む。   In step S103, the inspection omission determination unit 23 compares the acquired actual work time with the extracted estimated work time, and proceeds to step S104.

ステップS104において、点検漏れ判定部23は、ステップS103での比較結果に基づいて、点検漏れの有無を判定する。ここで、点検漏れ判定部23は、点検漏れが有り(すなわち、YES)と判定した場合には、ステップS105へと進む。一方、点検漏れ判定部23は、点検漏れが無し(すなわち、NO)と判定した場合には、ステップS106へと進む。   In step S104, the inspection omission determination unit 23 determines the presence or absence of inspection omission based on the comparison result in step S103. Here, if the inspection omission determination unit 23 determines that there is an inspection omission (that is, YES), the process proceeds to step S105. On the other hand, if the inspection omission determination unit 23 determines that there is no inspection omission (that is, NO), the process proceeds to step S106.

ステップS105において、報知部25は、点検漏れがあったことを報知し、一連の処理を終了する。   In step S105, the notification unit 25 notifies that there is an inspection omission and ends a series of processing.

ステップS106において、作業時間テーブル更新部24は、点検漏れ判定部23から今回の保守点検計画と実作業時間とを取得し、取得した実作業時間を用いて、記憶部22に記憶されている作業時間テーブル内の今回の保守点検計画に対応する推定作業時間を更新し、一連の処理を終了する。   In step S106, the work time table update unit 24 acquires the current maintenance inspection plan and the actual work time from the inspection omission determination unit 23, and uses the acquired actual work time to store the work stored in the storage unit 22. The estimated work time corresponding to the current maintenance inspection plan in the time table is updated, and the series of processes is terminated.

以上、本実施の形態1によれば、今回の保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する時間として計測された実作業時間と、作業時間テーブルから抽出された、今回の保守点検計画に対応する推定作業時間とを比較することで点検漏れの有無を判定する構成を備える。これにより、設備ごとに決められた保守点検計画に従って点検を実行する際に発生しうる点検漏れを、簡単な構成で、かつ精度良く検出することができる。   As described above, according to the first embodiment, the actual work time measured as the time elapsed from the start of the inspection to the end of the execution according to the current maintenance inspection plan is extracted from the work time table. A configuration is provided in which the presence or absence of inspection omission is determined by comparing the estimated work time corresponding to the current maintenance inspection plan. Thereby, the inspection omission which may occur when the inspection is executed according to the maintenance inspection plan determined for each facility can be detected with a simple configuration and with high accuracy.

また、点検漏れが無しと判定されれば、計測された実作業時間を用いて、作業時間テーブルに含まれる今回の保守点検計画に対応する推定作業時間を更新する構成を備える。これにより、今回の保守点検計画と同じものを次回以降に実行した場合に、点検漏れの有無をより精度良く判定することができる。   If it is determined that there is no inspection omission, the estimated operation time corresponding to the current maintenance inspection plan included in the operation time table is updated using the measured actual operation time. Thereby, when the same thing as this maintenance inspection plan is performed after the next time, the presence or absence of inspection omission can be determined more accurately.

さらに、点検漏れが有りと判定された場合、点検漏れがあったことを報知する構成を備える。これにより、設備ごとに決められた保守点検計画に従って点検を実行する際の点検漏れを防止することができる。また、端末装置への登録間違いによる点検漏れを防止することができ、従来以上の機器品質の維持および向上に寄与することができる。   Furthermore, when it is determined that there is an inspection omission, a configuration for notifying that an inspection omission has occurred is provided. Thereby, it is possible to prevent an inspection omission when performing an inspection in accordance with a maintenance inspection plan determined for each facility. In addition, it is possible to prevent omission of inspection due to a registration error in the terminal device, and it is possible to contribute to the maintenance and improvement of the equipment quality higher than the conventional one.

なお、本実施の形態1では、設備管理システムの具体例として、実作業時間計測部12が端末装置10に含まれるように構成し、記憶部22、点検漏れ判定部23、作業時間テーブル更新部24および報知部25がエレベータ装置20に含まれるように構成する場合を例示したが、これに限定されない。すなわち、端末装置10、エレベータ装置20および外部の監視センターは、それぞれ互いに通信可能であるので、本願発明の技術的特徴である実作業時間計測部12、記憶部22、点検漏れ判定部23、作業時間テーブル更新部24および報知部25のそれぞれは、端末装置10、エレベータ装置20および外部の監視センターのいずれかに含まれていれば、同様の効果が得られる。   In the first embodiment, as a specific example of the equipment management system, the actual work time measurement unit 12 is configured to be included in the terminal device 10, and the storage unit 22, the inspection omission determination unit 23, and the work time table update unit are configured. Although the case where it comprised so that 24 and the alerting | reporting part 25 may be included in the elevator apparatus 20 was illustrated, it is not limited to this. That is, since the terminal device 10, the elevator device 20, and the external monitoring center can communicate with each other, the actual work time measurement unit 12, the storage unit 22, the inspection omission determination unit 23, the work, which are technical features of the present invention. If each of the time table update unit 24 and the notification unit 25 is included in any of the terminal device 10, the elevator device 20, and the external monitoring center, the same effect can be obtained.

また、本実施の形態1では、本願発明をエレベータに適用した場合を例示して説明したが、これに限定されず、決められた保守点検計画に従って、定期的にさまざまな保守点検が実行されるような設備(例えば、エスカレータおよび動く歩道等といった乗客コンベア装置)に対しても本願発明を適用することができる。   In the first embodiment, the case where the present invention is applied to an elevator has been described as an example. However, the present invention is not limited to this, and various maintenance inspections are periodically performed according to a determined maintenance inspection plan. The present invention can also be applied to such facilities (for example, passenger conveyor devices such as escalators and moving walkways).

10 端末装置、11 端末制御部、12 実作業時間計測部、20 エレベータ装置、21 エレベータ制御部、22 記憶部、23 点検漏れ判定部、24 作業時間テーブル更新部、25 報知部。   DESCRIPTION OF SYMBOLS 10 Terminal device, 11 Terminal control part, 12 Actual work time measurement part, 20 Elevator apparatus, 21 Elevator control part, 22 Storage part, 23 Inspection omission judgment part, 24 Work time table update part, 25 Notification part.

Claims (5)

保守点検対象である設備の保守点検計画と、前記保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルを記憶する記憶部と、
前記保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、
前記作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、前記実作業時間計測部によって計測された、前記今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、
を備え
前記端末装置は、
前記点検を実行開始する場合に操作されることによって、電源がON状態になり、前記端末制御部と前記設備とが接続されて、前記設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、
前記点検を実行終了する場合に操作されることによって、前記運転状態が前記メンテナンスモードから前記通常モードに切り替えられ、前記端末制御部と前記設備との接続が切り離され、前記電源がOFF状態になるように構成され、
前記実作業時間計測部は、
前記端末装置の前記電源がON状態になってからOFF状態になるまでの間に経過する時間を、前記実作業時間として計測する
設備管理システム。
Stores a work time table in which a maintenance check plan of equipment that is a maintenance check target and an estimated work time estimated to be required when the check items included in the maintenance check plan are executed without omission are stored. A storage unit;
A terminal device having an actual work time measurement unit that measures an actual work time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution; and a terminal control unit that controls operation;
The estimated work time corresponding to the current maintenance inspection plan is extracted from the work time table, and the extracted estimated work time and the actual work required for the current maintenance inspection plan measured by the actual work time measurement unit. By comparing the time, the inspection omission determination unit that determines the presence or absence of inspection omissions, and
Equipped with a,
The terminal device
By operating when starting the inspection, the power is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. Configured,
By operating when the inspection is finished, the operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power supply is turned off. Configured as
The actual work time measuring unit is
An equipment management system that measures the time elapsed from when the power of the terminal device is turned on to when it is turned off as the actual work time .
保守点検対象である設備の保守点検計画と、前記保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルを記憶する記憶部と、Stores a work time table in which a maintenance check plan of equipment that is a maintenance check target and an estimated work time estimated to be required when the check items included in the maintenance check plan are executed without omission are stored. A storage unit;
前記保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、A terminal device having an actual work time measurement unit that measures an actual work time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution; and a terminal control unit that controls operation;
前記作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、前記実作業時間計測部によって計測された、前記今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、The estimated work time corresponding to the current maintenance inspection plan is extracted from the work time table, and the extracted estimated work time and the actual work required for the current maintenance inspection plan measured by the actual work time measurement unit. By comparing the time, the inspection omission determination unit that determines the presence or absence of inspection omissions, and
を備え、With
前記端末装置は、The terminal device
前記点検を実行開始する場合に操作されることによって、電源がON状態になり、前記端末制御部と前記設備とが接続されて、前記設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、By operating when starting the inspection, the power is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. Configured,
前記点検を実行終了する場合に操作されることによって、前記運転状態が前記メンテナンスモードから前記通常モードに切り替えられ、前記端末制御部と前記設備との接続が切り離され、前記電源がOFF状態になるように構成され、By operating when the inspection is finished, the operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power supply is turned off. Configured as
前記実作業時間計測部は、The actual work time measuring unit is
前記メンテナンスモードに切り替えてから前記通常モードに切り替えるまでの間に経過する時間を、前記実作業時間として計測するThe time elapsed between switching to the maintenance mode and switching to the normal mode is measured as the actual work time.
設備管理システム。Equipment management system.
保守点検対象である設備の保守点検計画と、前記保守点検計画に含まれる点検項目について漏れなく点検が実行されたときに要すると推定される推定作業時間とが関連付けられた作業時間テーブルを記憶する記憶部と、Stores a work time table in which a maintenance check plan of equipment that is a maintenance check target and an estimated work time estimated to be required when the check items included in the maintenance check plan are executed without omission are stored. A storage unit;
前記保守点検計画に従って点検を実行開始してから実行終了するまでの間に経過する実作業時間を計測する実作業時間計測部と、動作を制御する端末制御部とを有する端末装置と、A terminal device having an actual work time measurement unit that measures an actual work time that elapses between the start of execution of inspection according to the maintenance inspection plan and the end of execution; and a terminal control unit that controls operation;
前記作業時間テーブルから、今回の保守点検計画に対応する推定作業時間を抽出し、抽出した推定作業時間と、前記実作業時間計測部によって計測された、前記今回の保守点検計画に要した実作業時間とを比較することで、点検漏れの有無を判定する点検漏れ判定部と、The estimated work time corresponding to the current maintenance inspection plan is extracted from the work time table, and the extracted estimated work time and the actual work required for the current maintenance inspection plan measured by the actual work time measurement unit. By comparing the time, the inspection omission determination unit that determines the presence or absence of inspection omissions, and
を備え、With
前記端末装置は、The terminal device
前記点検を実行開始する場合に操作されることによって、電源がON状態になり、前記端末制御部と前記設備とが接続されて、前記設備の運転状態が通常モードからメンテナンスモードに切り替えられるように構成され、By operating when starting the inspection, the power is turned on, the terminal control unit and the equipment are connected, and the operation state of the equipment is switched from the normal mode to the maintenance mode. Configured,
前記点検を実行終了する場合に操作されることによって、前記運転状態が前記メンテナンスモードから前記通常モードに切り替えられ、前記端末制御部と前記設備との接続が切り離され、前記電源がOFF状態になるように構成され、By operating when the inspection is finished, the operation state is switched from the maintenance mode to the normal mode, the connection between the terminal control unit and the equipment is disconnected, and the power supply is turned off. Configured as
前記実作業時間計測部は、The actual work time measuring unit is
前記端末制御部と前記設備とを接続してから当該接続を切り離すまでの間に経過する時間を、前記実作業時間として計測するThe time elapsed from when the terminal control unit and the equipment are connected to when the connection is disconnected is measured as the actual work time.
設備管理システム。Equipment management system.
前記点検漏れ判定部によって前記点検漏れが無しと判定された場合、前記実作業時間計測部によって計測された前記実作業時間を用いて、前記作業時間テーブルに含まれる前記今回の保守点検計画に対応する推定作業時間を更新する作業時間テーブル更新部をさらに備えた
請求項1から3のいずれか1項に記載の設備管理システム。
When the inspection omission determination unit determines that the inspection omission is absent, the actual operation time measured by the actual operation time measurement unit is used to correspond to the current maintenance inspection plan included in the operation time table. The equipment management system according to any one of claims 1 to 3, further comprising a work time table update unit that updates an estimated work time to be performed.
前記点検漏れ判定部によって前記点検漏れが有りと判定された場合、点検漏れがあったことを報知する報知部をさらに備えた
請求項1から4のいずれか1項に記載の設備管理システム。
The equipment management system according to any one of claims 1 to 4, further comprising a notification unit that notifies that there is an inspection omission when the inspection omission determination unit determines that the inspection omission is present.
JP2014144159A 2014-07-14 2014-07-14 Equipment management system Active JP6403470B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014144159A JP6403470B2 (en) 2014-07-14 2014-07-14 Equipment management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014144159A JP6403470B2 (en) 2014-07-14 2014-07-14 Equipment management system

Publications (2)

Publication Number Publication Date
JP2016021121A JP2016021121A (en) 2016-02-04
JP6403470B2 true JP6403470B2 (en) 2018-10-10

Family

ID=55265929

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014144159A Active JP6403470B2 (en) 2014-07-14 2014-07-14 Equipment management system

Country Status (1)

Country Link
JP (1) JP6403470B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6074079B1 (en) * 2016-02-09 2017-02-01 東芝エレベータ株式会社 Maintenance work safety device
JP2019067050A (en) * 2017-09-29 2019-04-25 株式会社日立ビルシステム Work support system
JP2019125177A (en) * 2018-01-17 2019-07-25 ダイハツ工業株式会社 Inspection system

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000315110A (en) * 1999-04-30 2000-11-14 Mitsubishi Electric Corp Device and method for supporting maintenance inspection
JP4443091B2 (en) * 2002-03-20 2010-03-31 日立オムロンターミナルソリューションズ株式会社 Maintenance server and transaction processing apparatus
JP4370960B2 (en) * 2004-03-29 2009-11-25 三菱自動車エンジニアリング株式会社 Vehicle inspection management system
JP4261435B2 (en) * 2004-08-09 2009-04-30 イオンディライト株式会社 Equipment inspection support system
JP2006151529A (en) * 2004-11-25 2006-06-15 Mitsubishi Electric Building Techno Service Co Ltd Elevator maintenance work check system and elevator maintenance operator terminal device
EP2458466B1 (en) * 2010-11-30 2020-02-26 Industrial Development of Automotivo Components, IDACO corp Automatic supervision and control system
JP2012190209A (en) * 2011-03-10 2012-10-04 Mitsubishi Electric Building Techno Service Co Ltd System for visit maintenance work management of building facility
JP2013205277A (en) * 2012-03-29 2013-10-07 Terumo Corp Visual inspection monitor system and visual inspection monitor method

Also Published As

Publication number Publication date
JP2016021121A (en) 2016-02-04

Similar Documents

Publication Publication Date Title
JP2018169769A5 (en)
JP6169253B2 (en) AIR CONDITIONING SYSTEM AND ITS TRANSMISSION RELAY DEVICE
JP6403470B2 (en) Equipment management system
JP6370132B2 (en) Communication abnormality detection device, communication abnormality detection method and program
JP2013171383A (en) Portable terminal device, work management system and work management method
KR101940633B1 (en) Real time monitoring system for railway vehicles
JP2017192267A (en) Brake inspection apparatus and brake inspection method
CN111137773B (en) Method and system for detecting faults in an elevator system
KR20130080103A (en) Self-diagnostic apparatus and method for electric device
CN102040129B (en) Control operation device of elevator
WO2018122928A1 (en) Recovery support system
KR101602143B1 (en) Crane safety monitoring system
MY181687A (en) Equipment monitoring system, equipment monitoring program, and equipment monitoring method
WO2020147710A1 (en) Elevator fault diagnosis method, apparatus, device and medium
JP2019038650A (en) Remote diagnosis operation method of elevator, elevator control device, and remote diagnosis operation program of elevator
JP2015137156A (en) Elevator remote monitor device
JP2012206800A5 (en) Monitoring system, terminal device and warning method
JP2011132013A (en) Elevator maintenance system, maintenance terminal device, and method of maintaining elevator
KR101552174B1 (en) Apparatus for monitoring multi power isolation having signal detection mode, and method for monitoring multi power isolation using the same
JP2017219926A (en) Sensor system
JP4784949B2 (en) Elevator operation control device
JP2019159853A (en) Production management device, production management system, and production management method
KR101868935B1 (en) Alarm device for parts replacement time of Elevator
JP6403646B2 (en) Elevator remote monitoring system and elevator remote monitoring method
JP6477996B1 (en) Display control device with function to update display of elevator inspection information

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170113

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180125

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180301

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180814

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180911

R150 Certificate of patent or registration of utility model

Ref document number: 6403470

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250