JP6251541B2 - Subbase construction method - Google Patents

Subbase construction method Download PDF

Info

Publication number
JP6251541B2
JP6251541B2 JP2013222902A JP2013222902A JP6251541B2 JP 6251541 B2 JP6251541 B2 JP 6251541B2 JP 2013222902 A JP2013222902 A JP 2013222902A JP 2013222902 A JP2013222902 A JP 2013222902A JP 6251541 B2 JP6251541 B2 JP 6251541B2
Authority
JP
Japan
Prior art keywords
roadbed
filler
ballast
filling
pair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2013222902A
Other languages
Japanese (ja)
Other versions
JP2015086506A (en
Inventor
啓晋 鈴木
啓晋 鈴木
宏文 池本
宏文 池本
直幹 冨田
直幹 冨田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East Japan Railway Co
Original Assignee
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East Japan Railway Co filed Critical East Japan Railway Co
Priority to JP2013222902A priority Critical patent/JP6251541B2/en
Publication of JP2015086506A publication Critical patent/JP2015086506A/en
Application granted granted Critical
Publication of JP6251541B2 publication Critical patent/JP6251541B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、バラスト軌道の路盤を構築する方法に関する。   The present invention relates to a method for constructing a roadbed of a ballast track.

バラスト軌道は、土やアスファルト、コンクリート等の路盤の上に設けられるバラスト道床と、その上に敷設される軌きょうからなる。バラスト軌道上に雨が降ると、雨水がバラスト道床を通り抜け路盤に達することになるが、路盤の条件によってはこの雨水が路盤上に長時間滞水し続け、路盤を脆弱化させてしまうことがある。路盤が脆弱化すると、車両が通過する際のバラストの沈下量が大きくなってレールにゆがみが生じ易くなる上に、保線作業の効果が持続しにくくなって頻繁に保線作業が必要となってしまう。
そこで、路盤を強靭化する改良を行うことにより、軌道の保守周期を長くする技術が検討されている。従来、路盤の改良工法の一つとして、バラストに液状の充填材を流し込んで硬化させ、バラストの空隙を充填することにより、バラスト道床のバラストを骨材とする新たな改良路盤を構築する工法が提案されている(非特許文献1参照)。この工法は、既存のバラストを撤去する手間が省けるので、工期の短縮や環境負荷の低減を図ることが出来る。
The ballast track is composed of a ballast roadbed provided on a roadbed made of soil, asphalt, concrete or the like, and a rail laid on the ballast track. When rain falls on the ballast track, rainwater passes through the ballast roadbed and reaches the roadbed. is there. When the roadbed becomes weak, the amount of ballast settlement when the vehicle passes increases, making it easier for the rail to be distorted, and the effect of the track maintenance work becomes difficult to sustain, requiring frequent track maintenance work. .
Therefore, a technique for extending the maintenance cycle of the track by improving the toughness of the roadbed has been studied. Conventionally, as one of the improvement methods of the roadbed, there is a method of constructing a new improved roadbed using the ballast of the ballast roadbed as an aggregate by pouring a liquid filler into the ballast and hardening it, and filling the ballast gap. It has been proposed (see Non-Patent Document 1). This construction method can save time and effort for removing the existing ballast, so that the construction period can be shortened and the environmental load can be reduced.

鉄道総合技術研究所「施設研究ニュース」No.274、p3,4Railway Technical Research Institute “Facility Research News” No. 274, p3,4

ところで、路盤上の滞水は、土路盤の場合に限らず、改良路盤にも影響する場合がある。そこで、改良路盤を設ける際には、改良路盤の上面を軌道の敷設方向と直交する方向に傾斜させ、雨水などを側方へ流すようにすることが求められる。なお、この傾斜は3パーセント程度の勾配を設けるものとされている。
しかしながら、従来行われてきたバラストに充填材を充填して改良路盤とする工法は、5〜10m程度の脆弱化している範囲を部分的に改良することを想定したもので、勾配をどのようにつけるか工夫したものとなっていない。
つまり、従来の既設道床に充填材を流し込む路盤構築方法は、排水勾配を形成することができないために、広範囲に亘る改良路盤の構築には採用することが出来なかった。
By the way, the stagnant water on the road bed is not limited to the earth road bed but may also affect the improved road bed. Therefore, when providing an improved roadbed, it is required to incline the upper surface of the improved roadbed in a direction perpendicular to the track laying direction so that rainwater or the like flows laterally. This inclination is set to have a gradient of about 3%.
However, the conventional method of filling a ballast with a filler and making it an improved roadbed is intended to partially improve the weakened range of about 5 to 10 m. It has not been turned on or devised.
That is, the conventional roadbed construction method in which the filler is poured into the existing roadbed cannot form a drainage gradient, and thus cannot be adopted for construction of an improved roadbed over a wide range.

本発明は、上記課題に鑑みてなされたもので、既設のバラスト道床に充填材を流し込んで新たな路盤を構築する方法において、路盤上面に容易に排水勾配をつけることができるようにすることを目的とする。   The present invention has been made in view of the above problems, and in a method for constructing a new roadbed by pouring a filler into an existing ballast roadbed, it is possible to easily add a drainage gradient to the upper surface of the roadbed. Objective.

上記課題を解決するため、本発明は、既設のバラスト道床の少なくとも一部に充填材を充填し、充填された充填材を硬化させることにより、バラストを骨材とする路盤を構築する路盤構築方法において、前記バラスト道床の上に敷設された軌きょうの幅方向両側方に、一対の土留め壁を、前記軌きょうの敷設方向に沿うように、かつ、少なくとも既存の路盤の上面から新たに設けようとする路盤の上面高さを越える程度の高さとなるように設置し、前記一対の土留め壁のうち一方の土留め壁の近傍から、前記一対の土留め壁に挟まれた前記バラスト道床に、充填開始から所定時間経過後に流動性を失う硬化特性を有するとともに、充填開始から所定時間経過後、前記一対の土留め壁のうち他方の土留め壁の所定高さまで達し、上面に、前記一方の土留め壁から前記他方の土留め壁へ向かうに従って所定の割合で下がっていくような勾配が付いた状態となるような流動性を有する充填材を流し込み、前記充填材を硬化させることにより、上方にバラスト軌道を有する路盤を構築することを特徴とする。 In order to solve the above problems, the present invention provides a roadbed construction method for building a roadbed using ballast as an aggregate by filling at least a part of an existing ballast roadbed with a filler and curing the filled filler. A pair of earth retaining walls are newly provided on both sides of the rail laid on the ballast roadbed so as to extend along the rail laying direction and at least from the upper surface of the existing roadbed. The ballast roadbed is installed so as to have a height exceeding the upper surface height of the roadbed to be installed, and is sandwiched between the pair of retaining walls from the vicinity of one of the pair of retaining walls. In addition, it has a hardening characteristic that loses fluidity after a predetermined time has elapsed from the start of filling, and after a predetermined time has elapsed from the start of filling, reaches the predetermined height of the other retaining wall of the pair of retaining walls, one It poured from the earth retaining wall filler having a condition to become such flowability with gradient as going down at a predetermined rate toward to the other of the earth retaining wall, by curing the filler, A roadbed having a ballast track above is constructed .

本発明は、「既設のバラスト道床の少なくとも一部に充填材を充填」することとしているので、既設のバラスト道床の上部を引き続きバラスト道床として用いる場合や、既設のバラスト道床はすべて新設路盤の骨材に用いる場合が含まれる。
また、「軌きょうの幅方向両側方に、土留め壁を・・設置」には、既設のバラスト道床の側方に既設のバラストを全て挟むように設ける場合と、既設のバラスト道床を途中で分断するように設ける場合とが含まれる。
According to the present invention, “at least a part of the existing ballast roadbed is filled with a filler”. Therefore, when the upper part of the existing ballast roadbed is continuously used as the ballast roadbed, or the existing ballast roadbed is the bone of the new roadbed. The case of using for a material is included.
In addition, in “Installing earth retaining walls on both sides in the width direction of the rail”, there are cases where all existing ballasts are sandwiched on the side of the existing ballast roadbed, and where the existing ballast roadbed is in the middle The case where it is provided so as to be divided is included.

このようにすれば、既存のバラスト道床に充填材を流し込むだけで、硬化した充填材の上に更に充填材を充填して均したり、硬化した充填材の上面を斜めに削ったりする等の工程を経ることなく、路盤の上面に所定の勾配をつけることができるので、広範囲に亘って長く延び、かつ上面に所定の排水勾配が付けられた路盤を容易に新設することができる。   In this way, just by pouring the filler into the existing ballast roadbed, the filler is further filled and leveled on the cured filler, or the upper surface of the cured filler is scraped diagonally, etc. Since a predetermined gradient can be given to the upper surface of the roadbed without going through the process, a roadbed that extends long over a wide area and has a predetermined drainage gradient on the upper surface can be easily installed.

なお、上記発明において、例えば、前記充填材として、超速硬性材料を含む粉体材料、水、および減水剤を、前記粉体材料の総重量に対する水の重量の割合が50%以上55%以下となるように混合されたものを用いるようにするとよい。
このようにすれば、単線軌道の路盤として必要な幅2〜5m程度の路盤を構築する場合であっても、充填材が一方の土留め壁から他方の土留め壁に達することの出来る流動性を有するので、上面に勾配を有する路盤を容易に新設することができる。
In the above invention, for example, as the filler, a powder material containing an ultra-fast hard material, water, and a water reducing agent, the ratio of the weight of water to the total weight of the powder material is 50% or more and 55% or less. It is advisable to use such a mixture.
In this way, even when a roadbed having a width of about 2 to 5 m required as a roadbed for a single track is constructed, the fluidity that the filler can reach from one earth retaining wall to the other earth retaining wall. Therefore, a roadbed having a gradient on the upper surface can be easily installed.

また、好ましくは、上記発明において、前記充填材を充填する前に施工現場の気象条件を測定し、測定した気象条件に基づいて、前記充填材に、凝結遅延剤を、前記充填材が充填開始から20分以上40分以下の時間経過後に流動性を失うようになる量を計りとって添加し、その後、前記充填材を充填するようにするとよい。
このようにすれば、充填材が他方の土留め壁に到達する前、或いは充填材の上面の勾配が所定の範囲となる前に充填材が硬化してしまうのを防ぐことが出来る。
Preferably, in the above invention, the weather conditions at a construction site are measured before filling with the filler, and based on the measured weather conditions, a setting retarder is added to the filler, and the filler starts filling. It is good to measure and add the quantity which loses fluidity | liquidity after the time of 20 minutes or more and 40 minutes or less, and is filled with the said filler after that.
In this way, it is possible to prevent the filler from hardening before the filler reaches the other earth retaining wall or before the gradient of the upper surface of the filler falls within a predetermined range.

本発明によれば、既設のバラスト道床に充填材を流し込んで新たな路盤を構築する方法において、路盤上面に容易に排水勾配をつけることができるようになる。   According to the present invention, in a method for constructing a new roadbed by pouring a filler into an existing ballast roadbed, a drainage gradient can be easily provided on the upper surface of the roadbed.

実施形態の充填材の成分を決定するために行った実験の概要を示した図である。It is the figure which showed the outline | summary of the experiment conducted in order to determine the component of the filler of embodiment. 図1の器具を用いて行った実験の各種条件を示した表である。It is the table | surface which showed the various conditions of the experiment conducted using the instrument of FIG. サンプル1,2の充填材を用いた場合の実験結果を示したグラフである。It is the graph which showed the experimental result at the time of using the filler of samples 1 and 2. FIG. サンプル3,4の充填材を用いた場合の実験結果を示したグラフである。It is the graph which showed the experimental result at the time of using the filler of samples 3 and 4. FIG. サンプル5の充填材を用いた場合の実験結果を示したグラフである。It is the graph which showed the experimental result at the time of using the filler of the sample 5. FIG. サンプル6の充填材を用いた場合の実験結果を示したグラフである。It is the graph which showed the experimental result at the time of using the filler of the sample 6. FIG. 実施形態の充填材の成分を決定するために行った実験の概要を示した図である。It is the figure which showed the outline | summary of the experiment conducted in order to determine the component of the filler of embodiment. サンプル5,6の充填材を用いた場合の実験結果の詳細を示したグラフである。It is the graph which showed the detail of the experimental result at the time of using the filler of samples 5 and 6. FIG. 第1実施形態の路盤構築方法の流れを示した図である。It is the figure which showed the flow of the roadbed construction method of 1st Embodiment. 第2実施形態の路盤構築方法の流れを示した図である。It is the figure which showed the flow of the roadbed construction method of 2nd Embodiment. 第3実施形態の路盤構築方法の流れを示した図である。It is the figure which showed the flow of the roadbed construction method of 3rd Embodiment.

<第1実施形態>
以下、図面を参照して、本発明の実施形態について詳細に説明する。
<First Embodiment>
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

〔充填材〕
まず、本実施形態の路盤構築方法で用いる充填材について説明する。
本実施形態では、充填材として、超速硬性材料、フィラー、水、減水剤、凝結遅延剤を混合したものを用いる。
(Filler)
First, the filler used in the roadbed construction method of this embodiment will be described.
In the present embodiment, as the filler, a mixture of a super fast hard material, a filler, water, a water reducing agent, and a setting retarder is used.

超速硬性材料は、例えば、ジェットセメントクリンカーなどの粉体材料である。
フィラーは、ブリージングを防ぐために添加する粉体材料である。
減水剤は、超速硬性材料を分散させて充填材の流動性を高めるとともに、硬化後の充填材の強度を高めるために添加する液体材料である。
なお、粉体材料(超速硬性材料およびフィラー)の総重量に対する水の重量の割合(以下W/材値)、および減水剤の添加量を調節することにより、充填材の流動性の度合いは調節可能である。本実施形態では、W/材値を50〜55%の範囲にしている。このような混合割合とすることにより、本実施形態の充填材は、JAロート流下時間が12.9〜14.5秒程度の流動性を有したものとなる。
The super fast hard material is, for example, a powder material such as a jet cement clinker.
The filler is a powder material added to prevent breathing.
The water reducing agent is a liquid material that is added to disperse the super fast hard material to increase the fluidity of the filler and to increase the strength of the filler after curing.
Note that the degree of fluidity of the filler can be adjusted by adjusting the ratio of the weight of water to the total weight of the powder material (super-hard material and filler) (hereinafter referred to as W / material value) and the amount of water reducing agent added. Is possible. In the present embodiment, the W / material value is in the range of 50 to 55%. By setting it as such a mixing ratio, the filler of this embodiment has fluidity | liquidity whose JA funnel flow-down time is about 12.9 to 14.5 seconds.

凝結遅延剤は、充填材が硬化するまでの時間を遅らせるために添加するものである。この凝結遅延剤の添加量を多くしていくことで、充填剤の練上がりから流動性を失うまでの時間(以下可使時間)が、添加しない場合に比べて長くなっていく。
なお、同じ量の凝結遅延剤を混入しても、施工時の気象条件(気温等)によって可使時間は変わってくるので、充填材を使用する直前の気象条件に応じて適量を添加するようにする。本実施形態では、可使時間が20〜40分の範囲となるような量を添加する。
The setting retarder is added to delay the time until the filler is cured. By increasing the addition amount of the setting retarder, the time until the fluidity is lost after the filler is kneaded (hereinafter referred to as pot life) becomes longer than when the additive is not added.
Even if the same amount of setting retarder is mixed, the pot life varies depending on the weather conditions (temperature, etc.) at the time of construction, so add an appropriate amount according to the weather conditions immediately before using the filler. To. In the present embodiment, an amount such that the pot life is in the range of 20 to 40 minutes is added.

(具体例)
ここで、本実施形態の充填材のW/材値や可使時間を上記範囲に絞るために行った実験の内容について説明する。図1は実験方法を示した図、図2は実験条件を纏めた表、図3〜6は、各充填材を用いて形成した路盤サンプルについて、流し込み位置からの距離と、固化面のバラスト上面からの距離との関係を示したグラフである。
(Concrete example)
Here, the content of the experiment conducted in order to narrow down the W / material value and pot life of the filler of this embodiment to the said range is demonstrated. FIG. 1 is a diagram showing the experimental method, FIG. 2 is a table summarizing the experimental conditions, and FIGS. 3 to 6 are the distance from the pouring position and the ballast top surface of the solidified surface for the roadbed sample formed using each filler. It is the graph which showed the relationship with the distance from.

まず、流動性および可使時間が異なる5種類の充填材サンプル1〜5と、幅(D)0.3m×高さ(H)0.4m×長さ(W)2.4mの小型型枠M1と、幅(D)0.3m×高さ(H)0.4m×長さ(W)4.8mの大型型枠M2を用意した。サンプル1はW/材値が60%で可使時間が20分、サンプル2はW/材値が70%で可使時間が20分、サンプル3はW/材値が60%で可使時間が40分、サンプル4はW/材値が55%で可使時間が40分、サンプル5はW/材値が50%で可使時間が40分となっている。   First, five types of filler samples 1 to 5 having different fluidity and pot life, and a small formwork having a width (D) of 0.3 m, a height (H) of 0.4 m, and a length (W) of 2.4 m. M1 and a large mold M2 having a width (D) of 0.3 m, a height (H) of 0.4 m, and a length (W) of 4.8 m were prepared. Sample 1 has a W / material value of 60% and a pot life of 20 minutes. Sample 2 has a W / material value of 70% and a pot life of 20 minutes. Sample 3 has a W / material value of 60% and a pot life. The sample 4 has a W / material value of 55% and a pot life of 40 minutes, and the sample 5 has a W / material value of 50% and a pot life of 40 minutes.

次に、各充填材サンプル1〜5の比重をそれぞれ測定した。その結果、サンプル1は1.67kg/m、サンプル2は1.63kg/m、サンプル3は1.67kg/m、サンプル4は1.72kg/m、サンプル5は1.76kg/mであった。
また、各充填材サンプル1〜5を所定量(1000cc)計り取り、それぞれのJAロート流下時間を調べた。その結果、サンプル1は12.6秒、サンプル2は11.6秒、サンプル3は12.3秒、サンプル4は12.9秒、サンプル5は14.5秒であった。
次に、この小型型枠M1または大型型枠M2内にバラストBを、上面が水平で、型枠M1,M2の底面から上面までの高さ(h)が0.3mとなるように詰め、型枠M1,M2の一端から上記5種類の充填材サンプル1〜5のうち何れかを、図1に示すように型枠M1,M2の一端から複数回に分けて連続的に流し込み、充填材サンプル1〜5が硬化してできた路盤サンプル(ケース1〜6)の上面の勾配の出来具合を調べた。
Next, the specific gravity of each filler sample 1 to 5 was measured. As a result, sample 1 is 1.67 kg / m 3 , sample 2 is 1.63 kg / m 3 , sample 3 is 1.67 kg / m 3 , sample 4 is 1.72 kg / m 3 , and sample 5 is 1.76 kg / m 2 . It was m 3.
Moreover, each filler sample 1-5 was measured by predetermined amount (1000 cc), and each JA funnel flow time was investigated. As a result, Sample 1 was 12.6 seconds, Sample 2 was 11.6 seconds, Sample 3 was 12.3 seconds, Sample 4 was 12.9 seconds, and Sample 5 was 14.5 seconds.
Next, the ballast B is packed in the small formwork M1 or the large formwork M2 so that the upper surface is horizontal and the height (h) from the bottom surface to the upper surface of the formwork M1, M2 is 0.3 m, One of the five kinds of filler samples 1 to 5 is continuously poured from one end of the molds M1 and M2 into a plurality of times from one end of the molds M1 and M2 as shown in FIG. The grade of the gradient of the upper surface of the roadbed sample (cases 1 to 6) formed by curing samples 1 to 5 was examined.

ケース1では、まず、バラストBを詰めた小型型枠M1に、充填材サンプル1を流し込んで硬化させた。こうして得られた路盤サンプルの上面は、図3に示すように、型枠一端から1500mm離れた辺りから勾配が急になり、平均勾配は3%を大きく上回った。
ケース2では、小型型枠M1の底面に砂を撒き、その上からバラストを詰め、充填材サンプル1を流し込んで硬化させた。得られた路盤サンプルの上面は、砂を撒かなかったケース1よりも更に平均勾配が急になった。これは、充填材サンプル1の可使時間が短すぎる、或いは流動性が低すぎるために、充填材サンプル1の上面が均される前に硬化し始めてしまったものと考えられる。なお、以下のケース3〜6では、全て型枠M1,M2の底面に砂を撒いてからバラストを詰めて実験を行った。
In case 1, first, the filler sample 1 was poured into a small mold M1 filled with ballast B and cured. As shown in FIG. 3, the upper surface of the roadbed sample thus obtained had a steep gradient from a distance of 1500 mm from one end of the mold, and the average gradient greatly exceeded 3%.
In case 2, sand was spread on the bottom surface of the small formwork M1, and ballast was filled from above, and the filler sample 1 was poured and cured. The average slope of the upper surface of the obtained roadbed sample was steeper than in Case 1 in which the sand was not sprinkled. This is probably because the pot life of the filler sample 1 is too short or the fluidity is too low, so that the upper surface of the filler sample 1 has begun to harden before being leveled. In the following cases 3 to 6, the experiment was performed by sanding the bottom surfaces of the molds M1 and M2 and then filling the ballast.

ケース3では、小型型枠M1に、充填材サンプル2を流し込んで硬化させた。得られた路盤サンプルの上面は、図4に示すように、全体的に緩やかな勾配となり、平均勾配は3%に届かなかった。これは、充填材サンプル2の流動性の割に可使時間が長かったために、充填後に充填材サンプル2の上面が必要以上に均されてしまったものと考えられる。
ケース4では、小型型枠M1に充填材サンプル3を流し込んで硬化させた。得られた路盤サンプルの上面は、ケース3とほぼ同程度の勾配を形成し、平均勾配は3%に届かなかった。これは、充填材サンプル3の流動性が高すぎたために、充填後に充填材が均されてしまったものと考えられる。また、充填材サンプル3は、水が多すぎたためか、材料に分離が見られた。
In case 3, the filler sample 2 was poured into the small mold M1 and cured. As shown in FIG. 4, the upper surface of the obtained roadbed sample had a gentle gradient as a whole, and the average gradient did not reach 3%. This is probably because the upper surface of the filler material sample 2 was leveled more than necessary after filling because the pot life was longer than the fluidity of the filler material sample 2.
In case 4, the filler sample 3 was poured into the small mold M1 and cured. The upper surface of the obtained roadbed sample formed a gradient almost the same as Case 3, and the average gradient did not reach 3%. This is thought to be because the filler material 3 was leveled after filling because the fluidity of the filler sample 3 was too high. In addition, the filler sample 3 was separated due to the excessive amount of water.

ケース5では、大型型枠M2に、充填材サンプル4を流し込んで硬化させた。得られた路盤サンプルの上面は、図5に示すように、平均勾配は3%に僅かに届かなかったが、概ね目標とする範囲の勾配を有するものとすることができた。
ケース6では、大型型枠M2に、充填材サンプル5を流し込んで硬化させた。得られた路盤サンプルの上面は、図6に示すように、平均勾配がほぼ3%となった。
以上の実験結果に基づき、ケース5,6に用いたサンプル4またはサンプル5の混合割合が適切であると考え、本実施形態では、充填材のW/材値を50〜55%、可使時間を20〜40分とした。
In case 5, filler sample 4 was poured into large mold M2 and cured. As shown in FIG. 5, the upper surface of the obtained roadbed sample did not reach a slight average gradient of 3%, but was able to have a gradient in a generally targeted range.
In case 6, the filler sample 5 was poured into the large mold M2 and cured. As shown in FIG. 6, the average slope of the upper surface of the obtained roadbed sample was approximately 3%.
Based on the above experimental results, it is considered that the mixing ratio of sample 4 or sample 5 used in cases 5 and 6 is appropriate, and in this embodiment, the W / material value of the filler is 50 to 55%, the pot life Was set to 20 to 40 minutes.

なお、ケース5,6については、図7に示すように、大型型枠M2に、所定(1000mm)間隔でコンクリートがどの程度の高さまで充填されたかを検知する検知管dを複数設置し、充填材Gを一回流し込む毎に、各検知管の設置箇所におけるコンクリートの深さを調べた。図8(a)はサンプル4についての結果を纏めたグラフであり、図8(b)はサンプル5についての結果を纏めたグラフである。
この結果、充填材Gの上面が段階的に上昇し、最後(サンプル4は10回目、サンプル5は13回目)に流し込んだ充填材Gの上面には概ね3%程度の勾配が形成されることが確認できた。
For the cases 5 and 6, as shown in FIG. 7, a plurality of detector tubes d for detecting how much concrete is filled in the large formwork M2 at predetermined (1000 mm) intervals are installed and filled. Each time the material G was poured once, the depth of the concrete at the location where each detector tube was installed was examined. FIG. 8A is a graph summarizing the results for sample 4, and FIG. 8B is a graph summarizing the results for sample 5. FIG.
As a result, the upper surface of the filler G rises stepwise, and a gradient of about 3% is formed on the upper surface of the filler G poured last (sample 4 is the 10th time and sample 5 is the 13th time). Was confirmed.

〔路盤構築方法〕
次に、上記充填材を用いた路盤構築方法の一例について説明する。図9は施工の流れを示したものである。
[Roadbed construction method]
Next, an example of a roadbed construction method using the filler will be described. FIG. 9 shows the construction flow.

施工前の施工現場は、図9(a)に示したようになっている。すなわち、既設の土路盤(以下既設路盤1)の上に、バラスト道床(以下既設道床21)および軌きょう22からなる軌道2が設けられている。   The construction site before construction is as shown in FIG. That is, a track 2 including a ballast roadbed (hereinafter, existing roadbed 21) and a rail 22 is provided on an existing earth roadbed (hereinafter, existing roadbed 1).

まず、図9(b)に示すように、既設道床21の両側方に、土留め壁11,12を、軌道2の敷設方向に沿うように設ける。本実施形態では、鋼板等を既設路盤1に打ち込むことにより設ける。各土留め壁11,12の高さは、その上端がこれから設けようとする新設路盤の上面よりも高くなる程度とする。そして、一方の土留め壁11(第1土留め壁)と軌きょう22との間、および他方の土留め壁12(第2土留め壁)と軌きょう22との間に新たな骨材用バラストB1を、軌きょう22の上を通行する車両の建築限界に支障のない範囲で投入する。
次に、軌きょう22を撤去し、図9(c)に示すように、既設道床21の、軌きょう22を撤去した跡の上にも新たな骨材用バラストB2を投入する。そして、投入したバラストB1,B2を所定の密度まで締め固めながら整形することにより、バラスト道床21Aを新設し、その上に軌きょう22Aを新たに敷設する。軌きょう22Aを敷設した後は、路盤の新設を行う前であっても列車の通行が可能となる。
First, as shown in FIG. 9B, the retaining walls 11 and 12 are provided on both sides of the existing roadbed 21 so as to follow the laying direction of the track 2. In this embodiment, a steel plate or the like is provided by driving into the existing roadbed 1. The heights of the earth retaining walls 11 and 12 are set such that their upper ends are higher than the upper surface of the new roadbed to be provided. And between one earth retaining wall 11 (first earth retaining wall) and the rail 22 and between the other earth retaining wall 12 (second earth retaining wall) and the rail 22, a new aggregate is used. The ballast B1 is introduced within a range that does not interfere with the construction limit of the vehicle passing over the rail 22.
Next, the rail 22 is removed, and, as shown in FIG. 9C, a new aggregate ballast B2 is also put on the trace of the existing roadbed 21 from which the rail 22 has been removed. Then, the ballast B1 and B2 are shaped while being compacted to a predetermined density, whereby a ballast roadbed 21A is newly provided, and a rail 22A is newly laid thereon. After laying the rail 22A, the train can pass even before the roadbed is newly constructed.

次に、気温等を計測し、充填材Gに最適な量の凝結遅延剤を混入し、充填材Gの可使時間が所望の時間(例えば40分)となるようにする。充填材Gの調整が済んだら、図9(d)に示すように、一方の土留め壁11の近傍から、充填材Gを骨材用バラストB1の中に流し込む。本実施形態では、通行する列車の振動によって充填材が均されてしまわないよう、列車が通り過ぎた後、次の列車が来るまでに、可使時間以上の空きができることを見計らって流し込むようにする。充填材Gを流し込む際は、全量を一度に流し込んでも良いし、少量を複数回に分けて流し込んでも良い。また、複数回に分ける場合には、一回流し込んだ後、間髪を入れずに次の充填材を流し込むようにしてもよいし、一回流し込んだ後、ある程度の時間を置いてから次の充填材Gを流し込むようにしてもよい。   Next, the temperature or the like is measured, and an optimal amount of a setting retarder is mixed into the filler G so that the pot life of the filler G becomes a desired time (for example, 40 minutes). After the adjustment of the filler G, as shown in FIG. 9 (d), the filler G is poured into the aggregate ballast B1 from the vicinity of one retaining wall 11. In this embodiment, in order to prevent the filling material from being leveled by the vibration of the passing train, after the train has passed, it will be poured in anticipation that there will be a vacant time or longer before the next train comes . When pouring the filler G, the whole amount may be poured at once, or a small amount may be poured in multiple times. In addition, when dividing into multiple times, after pouring once, the next filling material may be poured without inserting a gap, or after pouring once, after a certain amount of time, the next filling is performed. The material G may be poured.

充填材Gは、適度な流動性を有しており、骨材用バラストB1の中に流し込まれた後は、自重によって既設道床21や新たに盛った骨材用バラストB1,B2の空隙を通り、上から見たときに充填材Gの注ぎ口を中心として半円形に広がっていく。充填材Gは、適度な粘性も有しているため、既設道床21のバラストおよび新たに盛った骨材用バラストB1,B2の空隙が充填され尽くす頃には、充填材Gの上面に一端側から他端側へと下っていく3%程度の勾配が出来る。そして、概ねこのタイミングで充填材Gの可使時間となり、充填材Gは、上面に所定の勾配を付けたまま流動性を失い始める。   The filler G has an appropriate fluidity, and after being poured into the aggregate ballast B1, it passes through the existing roadbed 21 and the newly formed voids of the aggregate ballasts B1 and B2 by its own weight. When seen from above, it spreads in a semicircular shape centering on the spout of the filler G. Since the filler G also has an appropriate viscosity, when the space between the ballast of the existing roadbed 21 and the newly built aggregate ballasts B1 and B2 is completely filled, one end side is formed on the upper surface of the filler G. A gradient of about 3% can be made from the bottom to the other end. The usable time of the filler G is approximately at this timing, and the filler G starts to lose its fluidity with a predetermined gradient on the upper surface.

充填材Gが硬化したら、充填材Gを流し込む手段を、軌道2の敷設方向に沿って所定距離移動させ、その場所からこれまで説明してきたのと同様の方法で充填材Gを流し込んで硬化させる。この充填材Gの流し込み作業を繰り返すことにより、図9(e)に示すように、既設路盤1の上に、新設路盤1Aが、軌道の付設方向に延びるように構築される。   When the filler G is cured, the means for pouring the filler G is moved a predetermined distance along the laying direction of the track 2, and the filler G is poured and cured from the place in the same manner as described above. . By repeating this pouring operation of the filler G, the new roadbed 1A is constructed on the existing roadbed 1 so as to extend in the track attaching direction, as shown in FIG.

<第2実施形態>
次に、本発明の第2実施形態について説明する。ここでは、第1実施形態と相違する点についてのみ説明する。
Second Embodiment
Next, a second embodiment of the present invention will be described. Here, only differences from the first embodiment will be described.

第1実施形態では、周囲に構造物のない場所で新設路盤を構築し、その上に軌道を新たに敷設した(軌道をこう上させた)が、本実施形態では、駅の改良工事現場(近くにプラットホームがある場所)で新設路盤を構築し、軌道をこう上させるとともに、水平移動も行うようにしている。図10は施工の流れを示したものである。   In the first embodiment, a new roadbed is constructed in a place where there is no structure around it, and a new track is laid thereon (the track is raised above), but in this embodiment, the improvement construction site of the station ( A new roadbed is built near the platform) to move the track up and move horizontally. FIG. 10 shows the flow of construction.

施工前の施工現場は、図10(a)に示したようになっている。すなわち、既設の土路盤(以下既設路盤1)の上に、バラスト道床(以下既設道床21)および軌きょう22からなる軌道2が設けられている。既設路盤1の側面は土留め壁12(第2土留め壁)によって土留めされている。また、軌きょう22の上方かつ軌きょう22の一側方(図10(a)の左側)には、軌道2の敷設方向に沿ってプラットホーム(以下既設ホーム3)が設けられている。   The construction site before construction is as shown in FIG. That is, a track 2 including a ballast roadbed (hereinafter, existing roadbed 21) and a rail 22 is provided on an existing earth roadbed (hereinafter, existing roadbed 1). The side surface of the existing roadbed 1 is earthed by a earth retaining wall 12 (second earth retaining wall). In addition, a platform (hereinafter referred to as an existing platform 3) is provided above the rail 22 and on one side of the rail 22 (left side in FIG. 10A) along the laying direction of the track 2.

まず、図10(b)に示すように、土留め壁12の上端に更に土留め壁を継ぎ足して高くするとともに、既設道床21の、軌きょう22と既設ホーム3との間に、土留め壁11(第1土留め壁)を、既設道床21を貫通し、かつ既設路盤1にくい込むように打ち込む。以下継ぎ足して高さが延びた他方側の土留め壁を土留め壁12Aと称する。そして、一方の土留め壁11と他方の土留め壁12Aとの間に挟まれた空間のうち、既設道床21よりも他方の土留め壁12A側の部分に新たな骨材用バラストB1を、軌きょう22を通行する車両の建築限界に支障のない範囲で投入する。次に、軌きょう22を撤去し、図10(c)に示すように、既設道床21の軌きょう22を撤去した跡の上にも新たな骨材用バラストB2を投入する。そして、骨材用バラストB1,B2上面を、これから構築しようとする新設路盤の上面の傾斜と同程度に傾斜させつつ平らに均す。   First, as shown in FIG. 10 (b), the earth retaining wall is further added to the upper end of the earth retaining wall 12 to make it higher, and the earth retaining wall 21 between the rail 22 and the existing home 3 on the existing road floor 21. 11 (first earth retaining wall) is driven so as to penetrate the existing roadbed 21 and to be fitted into the existing roadbed 1. Hereinafter, the other retaining wall which has been added and extended in height is referred to as retaining wall 12A. And, in the space sandwiched between one earth retaining wall 11 and the other earth retaining wall 12A, a new aggregate ballast B1 is placed on the other earth retaining wall 12A side of the existing road floor 21, The vehicle is introduced within a range that does not interfere with the construction limit of the vehicle passing through the rail 22. Next, the rail 22 is removed, and as shown in FIG. 10C, a new aggregate ballast B2 is also put on the trace of the rail 22 of the existing roadbed 21 removed. Then, the upper surfaces of the aggregate ballasts B1 and B2 are leveled while being inclined to the same extent as the inclination of the upper surface of the new roadbed to be constructed.

次に、図10(d)に示すように、既設ホーム3を撤去する。そして、第1実施形態と同様の充填材Gを用意し、一方の土留め壁11の近傍から、充填材Gを、一方の土留め壁11と他方の土留め壁12Aの間に盛られた骨材用バラストB2の中に流し込んで硬化させる。そして、この充填材Gの流し込み作業を第1実施形態と同様に繰り返すことにより、新設路盤1Aが構築される。新設路盤1Aが完成したら、図10(e)に示すように、新設路盤1Aの上にバラスト道床21Aを新設する。なお、新設路盤1Aの上面には勾配が付けられているので、バラストを土留め壁11側に多く盛ることで、バラスト道床21Aの上面が水平になるようにする。そして、新設したバラスト道床21Aの上に軌きょう22Aを新たに敷設する。また、軌きょう22Aの位置が変更されているので、それに合わせてプラットホーム3Aも新設する。こうして、駅の路盤の改良工事が完了する。   Next, as shown in FIG. 10D, the existing home 3 is removed. And the filler G similar to 1st Embodiment was prepared, and the filler G was piled up between the one retaining wall 11 and the other retaining wall 12A from the vicinity of one retaining wall 11. Pour into aggregate ballast B2 and cure. And the new roadbed 1A is constructed | assembled by repeating the pouring operation | work of this filler G similarly to 1st Embodiment. When the new roadbed 1A is completed, a ballast roadbed 21A is newly provided on the new roadbed 1A as shown in FIG. In addition, since the upper surface of the new roadbed 1A is given a gradient, the upper surface of the ballast roadbed 21A is made horizontal by increasing the amount of ballast on the retaining wall 11 side. Then, a rail 22A is newly laid on the newly established ballast roadbed 21A. In addition, since the position of the rail 22A has been changed, a platform 3A is newly provided in accordance therewith. In this way, the improvement work of the roadbed of the station is completed.

なお、本実施形態では、駅構内で路盤を新設する場合について説明したが、第1実施形態のように、周囲に構造物の無い場所であっても、プラットホームの撤去・設置工程を省けば、同様の方法で新設路盤1Aを構築することができる。   In addition, in this embodiment, the case where a roadbed is newly installed in the station premises has been described, but even in a place where there is no structure around as in the first embodiment, if the removal / installation process of the platform is omitted, A new roadbed 1A can be constructed in the same manner.

<第3実施形態>
次に、本発明の第3実施形態について説明する。ここでは、第1実施形態と相違する点についてのみ説明する。
<Third Embodiment>
Next, a third embodiment of the present invention will be described. Here, only differences from the first embodiment will be described.

第1実施形態では、新設路盤を構築し、その上に軌道を新たに敷設した(軌道をこう上させた)が、本実施形態では、軌きょうの位置は変更せずに新設路盤を構築するようにしている。図11は施工の流れを示したものである。   In the first embodiment, a new roadbed is constructed, and a track is newly laid on the track (the track is raised above), but in this embodiment, the new roadbed is constructed without changing the position of the rail. I am doing so. FIG. 11 shows the flow of construction.

施工前の施工現場は、図11(a)に示したようになっている。すなわち、既設の土路盤(以下既設路盤1)の上に、バラスト道床(以下既設道床21)および軌きょう22からなる軌道2が設けられている。なお、本実施形態で施工対象とする既設道床21は、第1,第2実施形態よりも高く盛られたものとなっている。すなわち、既設路盤1と軌きょう22との間が第1実施形態よりも離れている。   The construction site before construction is as shown in FIG. That is, a track 2 including a ballast roadbed (hereinafter, existing roadbed 21) and a rail 22 is provided on an existing earth roadbed (hereinafter, existing roadbed 1). In addition, the existing roadbed 21 made into construction object by this embodiment is higher than the 1st, 2nd embodiment. That is, the distance between the existing roadbed 1 and the rail 22 is greater than that in the first embodiment.

まず、図11(b)に示すように、既設道床21の両側面に、土留め壁11,12を、軌道2の敷設方向に沿うように、既設道床21の両側部を貫通し、かつ、上端部が側面から露出するように設ける。そして、第1実施形態と同様の充填材Gを用意し、図11(c)に示すように、一方の土留め壁11の近傍から、充填材Gを、一方の土留め壁11と他方の土留め壁12の間に盛られた既設道床21のバラストの中に流し込んで硬化させる。そして、この充填材Gの流し込み作業を第1実施形態と同様に繰り返すことにより、既設道床21の下部に新設路盤1Aが構築される。
なお、新設路盤1Aの上端部が、既設道床21の両面から一部露出するように土留め壁11,12の設置位置を調節すれば、既設道床21の側面と他方の土留め壁12との間から充填材Gが染み出してきたかどうかによって、充填材Gの充填状況を確かめることもできる。
First, as shown in FIG. 11 (b), the retaining walls 11 and 12 are passed through both sides of the existing road bed 21 so as to extend along the laying direction of the track 2 on both sides of the existing road bed 21, and The upper end is provided so as to be exposed from the side surface. And the filler G similar to 1st Embodiment is prepared, and as shown in FIG.11 (c), from the vicinity of one earth retaining wall 11, the filler G is made into one earth retaining wall 11 and the other earth retaining wall 11. Pour into the ballast of the existing roadbed 21 built between the retaining walls 12 and harden. And the new roadbed 1A is constructed in the lower part of the existing roadbed 21 by repeating this pouring operation of the filler G in the same manner as in the first embodiment.
If the installation positions of the retaining walls 11 and 12 are adjusted so that the upper end of the new roadbed 1A is partially exposed from both surfaces of the existing roadbed 21, the side surface of the existing roadbed 21 and the other retaining wall 12 Depending on whether or not the filler G oozes out in between, the filling state of the filler G can be confirmed.

このように、上記実施形態では、既設道床21の少なくとも一部に充填材Gを充填し、充填された充填材Gを硬化させることにより、バラストを骨材とする新設路盤1Aを構築する路盤構築方法において、既設道床21の上に敷設された軌きょう22の幅方向両側方に、一対の土留め壁11,12,12Aを、軌きょう22の敷設方向に沿うように、かつ、少なくとも既設路盤1の上面から新たに設けようとする新設路盤1Aの上面高さを越える程度の高さとなるように設置し、一対の土留め壁のうち一方の土留め壁11の近傍から、一対の土留め壁11,12,12Aに挟まれた既設道床21および/または骨材用バラストB1,B2に、充填開始から所定時間経過後に流動性を失う硬化特性を有するとともに、充填開始から所定時間経過後、一対の土留め壁のうち他方の土留め壁12,12Aの所定高さまで達し、かつ、上面に、一方の土留め壁11から他方の土留め壁12,12Aへ向かうに従って3%程度の割合で下がっていくような勾配が付いた状態となるような流動性を有する充填材Gを流し込み、充填材Gを硬化させるようにした。   Thus, in the said embodiment, the roadbed construction which builds the new roadbed 1A which makes a ballast an aggregate by filling at least one part of the existing roadbed 21 with the filler G, and hardening the filled filler G. In the method, a pair of retaining walls 11, 12, 12 </ b> A are provided along the laying direction of the rail 22 on both sides in the width direction of the rail 22 laid on the existing roadbed 21, and at least the existing roadbed It installs so that it may become the height which exceeds the height of the upper surface of the new roadbed 1A to be newly provided from the upper surface of 1, and a pair of earth retaining from the vicinity of one earth retaining wall 11 of the pair of earth retaining walls The existing roadbed 21 and / or aggregate ballasts B1 and B2 sandwiched between the walls 11, 12, and 12A have a hardening characteristic that loses fluidity after a predetermined time has elapsed from the start of filling, and a predetermined time has elapsed since the start of filling. The ratio of about 3% of the pair of earth retaining walls reaches the predetermined height of the other earth retaining wall 12, 12A and goes from the one earth retaining wall 11 to the other earth retaining wall 12, 12A on the upper surface. Then, the filler G having fluidity so as to be in a state of having a gradient such that the filler G is lowered is poured to cure the filler G.

こうすることで、充填材Gを流し込むだけで、硬化した充填材Gの上に更に充填材を充填して均したり、硬化した充填材Gの上面を斜めに削ったりする等の工程を経ることなく、新設路盤1Aの上面に3%程度の勾配をつけることができるので、広範囲に亘って長く延び、かつ上面に例えば3%程度の排水勾配が付けられた新設路盤1Aを容易に新設することができる。   In this way, just by pouring the filler G, the filler G is further filled with the filler and smoothed, or the upper surface of the cured filler G is cut diagonally. Therefore, it is possible to provide a slope of about 3% on the upper surface of the newly installed roadbed 1A. Therefore, a new roadbed 1A that extends long over a wide area and has a drainage gradient of, for example, about 3% is easily installed. be able to.

また、上記実施形態では、充填材Gとして、超速硬性材料を含む粉体材料、水、および減水剤を、粉体材料の総重量に対する水の重量の割合が50%以上55%以下となるように混合されたものを用いるようにした。
こうすることで、単線軌道の路盤として必要な幅2〜5m程度の路盤を構築する場合であっても、充填材が一方の土留め壁11から他方の土留め壁12,12Aに達することの出来る流動性を有するので、上面に例えば3%の勾配を有する新設路盤1Aを容易に新設することができる。
Moreover, in the said embodiment, the ratio of the weight of the water with respect to the total weight of a powder material is set to 50% or more and 55% or less of the powder material containing a super-fast-hardening material, water, and a water reducing agent as the filler G. What was mixed in was used.
In this way, even when a roadbed having a width of about 2 to 5 m necessary as a roadbed for a single track is constructed, the filler can reach from one earth retaining wall 11 to the other earth retaining wall 12, 12A. Since it has the fluidity that can be achieved, a new roadbed 1A having a gradient of 3% on the upper surface can be easily installed.

また、上記実施形態では、充填材Gを充填する前に施工現場の気温を測定し、測定した気温に基づいて、充填材Gに、凝結遅延剤を、充填材Gが充填開始から20分以上40分以下の時間経過後に流動性を失うようになる量を計りとって添加し、その後、充填材Gを充填するようにするとよい。
こうすることで、充填材Gが他方の土留め壁12,12Aに到達する前、或いは充填材Gの上面の勾配が3%程度となる前に充填材Gが硬化してしまうのを防ぐことが出来る。
Moreover, in the said embodiment, the temperature of a construction site is measured before filling with the filler G, Based on the measured temperature, a setting retarder is used for the filler G, and the filler G is 20 minutes or more from the start of filling. It is good to measure and add the quantity which loses fluidity | liquidity after progress for 40 minutes or less, and to make it fill with the filler G after that.
This prevents the filler G from hardening before the filler G reaches the other earth retaining wall 12, 12A or before the gradient of the upper surface of the filler G reaches about 3%. I can do it.

以上、本発明を実施形態に基づいて具体的に説明してきたが、本発明は上記実施形態に限定されるものではなく、その要旨を逸脱しない範囲で変更可能である。
例えば、上記第1実施形態では、新設路盤の構築前に新たな軌道を設け、新設路盤の構築前から列車の通行を可能としたが、第2実施形態のように、路盤の構築後に新たな軌道を設けるようにしても良い。逆に、第2実施形態において、新設路盤の構築前に新たな軌道を設けるようにしても良い。
また、上記実施形態では、先に空間の片側に骨材用バラストB1を投入し、軌きょう22を撤去した後に更に骨材用バラストB2を投入したが、先に軌きょう22を撤去し、骨材用バラストの投入を一度で済ませるようにしても良い。
As mentioned above, although this invention was concretely demonstrated based on embodiment, this invention is not limited to the said embodiment, It can change in the range which does not deviate from the summary.
For example, in the first embodiment, a new track is provided before the construction of the new roadbed, and the train is allowed to pass before the construction of the new roadbed. However, a new track is created after the construction of the roadbed as in the second embodiment. A track may be provided. Conversely, in the second embodiment, a new track may be provided before the construction of the new roadbed.
Moreover, in the said embodiment, although the ballast B1 for aggregates was thrown into one side of space first and the ballast B2 for aggregates was thrown in after removing the rail 22, the rail 22 was removed first and bone The material ballast may be charged once.

また、上記実施形態では、一方の土留め壁11近傍から充填材Gを流し込んだが、一方の土留め壁11と他方の土留め壁12,12Aの中間地点から充填材Gを流し込み、中心から両側方へ向かうに従って下がって行くような山形の傾斜ができるようにしてもよい。
また、第2実施形態では、既設ホームを撤去して既設ホームのあった方から充填材Gの充填を行ったが、既設ホーム3のある方と反対側から流し込むようにしてもよい。そうすれば、充填材Gの充填作業と既設ホーム3の撤去作業を並行して行うことも可能となる。
また、上記実施形態では、ある箇所で充填材Gを充填した後、場所を移して再び充填材Gを充填するようにしたが、充填材Gの充填手段を軌道の敷設方向に沿って移動させながら連続的に流し込むことにより充填するようにしてもよいし、複数の充填手段を所定間隔で複数配置し、同時に流し込むことで充填するようにしてもよい。
また、第2実施形態では、既存の土留め壁12の上端に土留め壁を継ぎ足して新たな土留め壁12Aとしたが、既存の土留め壁12とは別の土留め壁を既設路盤1に打ち込むようにしても良い。
In the above embodiment, the filler G is poured from the vicinity of one of the retaining walls 11, but the filler G is poured from an intermediate point between the one retaining wall 11 and the other retaining walls 12, 12A, and both sides from the center. You may make it possible to make a mountain-shaped slope that goes down as you go.
Further, in the second embodiment, the existing home is removed and the filler G is filled from the existing home, but it may be poured from the opposite side of the existing home 3. If it does so, it will also become possible to perform the filling operation | work of the filler G and the removal operation | work of the existing home 3 in parallel.
Moreover, in the said embodiment, after filling with the filler G in a certain location, the place was moved and it was filled again with the filler G. However, the filling means of the filler G is moved along the laying direction of the track. However, it may be filled by pouring continuously, or a plurality of filling means may be arranged at predetermined intervals and filled by pouring simultaneously.
In the second embodiment, the earth retaining wall is added to the upper end of the existing earth retaining wall 12 to form a new earth retaining wall 12A. However, an earth retaining wall different from the existing earth retaining wall 12 is used as the existing road base 1. You may be allowed to type in.

21 既設道床(既設のバラスト道床)
22 既設軌きょう
11 土留め壁(一方の土留め壁)
12,12A 土留め壁(他方の土留め壁)
G 充填材
21 Existing roadbed (existing ballast roadbed)
22 Existing gauge 11 Earth retaining wall (One earth retaining wall)
12,12A earth retaining wall (the other earth retaining wall)
G Filler

Claims (4)

既設のバラスト道床の少なくとも一部に充填材を充填し、充填された充填材を硬化させることにより、バラストを骨材とする路盤を構築する路盤構築方法において、
前記バラスト道床の上に敷設された軌きょうの幅方向両側方に、一対の土留め壁を、前記軌きょうの敷設方向に沿うように、かつ、少なくとも既存の路盤の上面から新たに設けようとする路盤の上面高さを越える程度の高さとなるように設置し、
前記一対の土留め壁のうち一方の土留め壁の近傍から、前記一対の土留め壁に挟まれた前記バラスト道床に、充填開始から所定時間経過後に流動性を失う硬化特性を有するとともに、充填開始から所定時間経過後、前記一対の土留め壁のうち他方の土留め壁の所定高さまで達し、上面に、前記一方の土留め壁から前記他方の土留め壁へ向かうに従って所定の割合で下がっていくような勾配が付いた状態となるような流動性を有する充填材を流し込み、前記充填材を硬化させることにより、上方にバラスト軌道を有する路盤を構築することを特徴とする路盤構築方法。
In a roadbed construction method for building a roadbed using ballast as an aggregate by filling at least a part of an existing ballast roadbed with a filler and curing the filled filler,
On both sides in the width direction of the rail laid on the ballast roadbed, a pair of retaining walls are newly provided along the rail laying direction and at least from the upper surface of the existing roadbed Installed so that the height exceeds the top surface height of the roadbed,
The ballast roadbed sandwiched between the pair of retaining walls from the vicinity of one of the pair of retaining walls has a hardening characteristic that loses fluidity after a predetermined time has elapsed from the start of filling, and filling After the elapse of a predetermined time from the start, it reaches the predetermined height of the other retaining wall of the pair of retaining walls, and descends at a predetermined rate toward the upper surface from the one retaining wall toward the other retaining wall. A roadbed construction method characterized by constructing a roadbed having a ballast track on the upper side by pouring a filler having fluidity so as to be in a state of having a gradient, and curing the filler.
前記充填材として、粉体の超速硬性材料、水、減水剤を、粉体材料の総重量に対する水の割合が50%以上55%以下となるように混合されたものを用いることを特徴とする請求項1に記載の路盤構築方法。   The filler is characterized by using a powder super-hard material, water, and a water reducing agent mixed so that the ratio of water to the total weight of the powder material is 50% or more and 55% or less. The roadbed construction method according to claim 1. 前記充填材を充填する前に施工現場の気温を測定し、
測定した気温に基づいて、凝結遅延剤を、前記充填材が充填開始から20分以上40分以下の時間経過後に流動性を失うように前記充填材に添加し、
その後、前記充填材を流し込むことを特徴とする請求項2に記載の路盤構築方法。
Before filling the filler, measure the temperature at the construction site,
Based on the measured temperature, a setting retarder is added to the filler so that the filler loses fluidity after a lapse of 20 minutes to 40 minutes from the start of filling,
3. The roadbed construction method according to claim 2, wherein the filling material is poured thereafter.
既設のバラスト道床の少なくとも一部に充填材を充填し、充填された充填材を硬化させることにより、バラストを骨材とする路盤を構築する路盤構築方法において、  In a roadbed construction method for building a roadbed using ballast as an aggregate by filling at least a part of an existing ballast roadbed with a filler and curing the filled filler,
前記バラスト道床の上に敷設された軌きょうの幅方向両側方に、一対の土留め壁を、前記軌きょうの敷設方向に沿うように、かつ、少なくとも既存の路盤の上面から新たに設けようとする路盤の上面高さを越える程度の高さとなるように設置し、  On both sides in the width direction of the rail laid on the ballast roadbed, a pair of retaining walls are newly provided along the rail laying direction and at least from the upper surface of the existing roadbed Installed so that the height exceeds the top surface height of the roadbed,
前記一対の土留め壁の間から、前記一対の土留め壁に挟まれた前記バラスト道床に、充填開始から所定時間経過後に流動性を失う硬化特性を有するとともに、充填開始から所定時間経過後、前記一対の土留め壁の所定高さまで達し、上面に、前記一対の土留め壁の間から前記一対の土留め壁へ向かうに従って所定の割合で下がっていくような勾配が付いた状態となるような流動性を有する充填材を流し込み、前記充填材を硬化させることにより、上方にバラスト軌道を有する路盤を構築することを特徴とする路盤構築方法。  Between the pair of earth retaining walls, the ballast roadbed sandwiched between the pair of earth retaining walls has a curing characteristic that loses fluidity after a predetermined time has elapsed from the start of filling, and after the elapse of a predetermined time from the beginning of filling, It reaches a predetermined height of the pair of retaining walls, and the upper surface is in a state of being inclined so as to descend at a predetermined rate from the space between the pair of retaining walls toward the pair of retaining walls. A roadbed construction method characterized in that a roadbed having a ballast track upward is constructed by pouring a filler having a proper fluidity and curing the filler.
JP2013222902A 2013-10-28 2013-10-28 Subbase construction method Active JP6251541B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013222902A JP6251541B2 (en) 2013-10-28 2013-10-28 Subbase construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013222902A JP6251541B2 (en) 2013-10-28 2013-10-28 Subbase construction method

Publications (2)

Publication Number Publication Date
JP2015086506A JP2015086506A (en) 2015-05-07
JP6251541B2 true JP6251541B2 (en) 2017-12-20

Family

ID=53049610

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013222902A Active JP6251541B2 (en) 2013-10-28 2013-10-28 Subbase construction method

Country Status (1)

Country Link
JP (1) JP6251541B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108252165A (en) * 2018-03-30 2018-07-06 中铁二局第四工程有限公司 A kind of middle low speed magnetic suspension is low to put circuit road structure and its construction method
CN110055826B (en) * 2019-04-28 2023-09-22 中铁二院工程集团有限责任公司 Construction method of cutting rack rail reinforced track bed structure

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50130105A (en) * 1974-04-01 1975-10-15
JPH01299913A (en) * 1988-05-30 1989-12-04 Chichibu Cement Co Ltd Quick-hardening type ground improver
JPH09268501A (en) * 1996-04-02 1997-10-14 Mitsubishi Heavy Ind Ltd Labor-saving track and construction method therefor
JP3808041B2 (en) * 1996-07-15 2006-08-09 財団法人鉄道総合技術研究所 Railway roadbed construction method using asphalt-based structural materials
JPH10266104A (en) * 1997-03-27 1998-10-06 Railway Technical Res Inst Stabilizing method of ballast by use of stabilizing material and track structure thereof
JP3960403B2 (en) * 1998-09-10 2007-08-15 東京地下鉄株式会社 Method for converting ballast roadbed into concrete roadbed
JP2000154501A (en) * 1998-11-20 2000-06-06 Central Japan Railway Co Infilled ballast and construction method therefor
JP2002242104A (en) * 2001-02-14 2002-08-28 Railway Technical Res Inst Method for constructing ballast reinforcing track
JP4320731B2 (en) * 2004-07-05 2009-08-26 三菱マテリアル株式会社 Construction method of concrete roadbed structure
JP4514214B2 (en) * 2005-04-04 2010-07-28 東亜道路工業株式会社 Method for forming ballast solidified layer
JP3912425B1 (en) * 2005-08-08 2007-05-09 三菱マテリアル株式会社 Admixture and cement composition using the same
DE102007019669A1 (en) * 2007-04-24 2008-11-06 Hennecke Gmbh Method and device for filling ballast beds

Also Published As

Publication number Publication date
JP2015086506A (en) 2015-05-07

Similar Documents

Publication Publication Date Title
CN207987964U (en) A kind of reinforcing inspection shaft
CN106759126B (en) Construction method of side slope support drainage channel
CN106894308A (en) A kind of crack resistance construction of cement stable macadam base method
CN107893353B (en) Construction method of roller compacted concrete road
JP6251541B2 (en) Subbase construction method
CN105803922B (en) A kind of high embankment filled soil end of the bridge anti-settling structure
CN110593063A (en) Simple slip form paving device for cast-in-place concrete hard road shoulder and manufacturing and using method thereof
CN113585317B (en) Construction method for mucky soil support beam cushion layer
CN212000419U (en) Road structure in hilly areas
US11939729B2 (en) High strength porous cement-based materials
CN104746402B (en) The restorative procedure of well lid periphery damaged road surface
CN113186768A (en) Construction method for improving roadbed backfill quality after existing line demolition of frame structure
CN108060621B (en) Waterproof damping asphalt concrete level crossing pavement structure and construction method thereof
CN111576122A (en) Construction method for road in mobile town
JP6106836B1 (en) Aging method for existing spray mortar slopes
CN105036641A (en) Preparation method of kerb and installation method thereof
CN110295523A (en) Road rigid pavement precast concrete block
JPH09316808A (en) Sand cushion material and joint material for paving stone, and work execution method for paving stone using the same
JP4514214B2 (en) Method for forming ballast solidified layer
CN211734973U (en) Simple slip form paving device for cast-in-place concrete hard road shoulder
CN113174797B (en) Device and method for repairing and improving road surface bearing capacity
JP6312289B2 (en) Sand for block paving
JP6996687B2 (en) Installation of a coiled object covered with a net
CN213417457U (en) Highway bituminous paving disease repair brick
US1745744A (en) Method of forming roadbeds for railways

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160907

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170726

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170808

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20171006

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20171121

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171127

R150 Certificate of patent or registration of utility model

Ref document number: 6251541

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250