JP6108337B2 - Concrete stacking time interval management system - Google Patents
Concrete stacking time interval management system Download PDFInfo
- Publication number
- JP6108337B2 JP6108337B2 JP2012270359A JP2012270359A JP6108337B2 JP 6108337 B2 JP6108337 B2 JP 6108337B2 JP 2012270359 A JP2012270359 A JP 2012270359A JP 2012270359 A JP2012270359 A JP 2012270359A JP 6108337 B2 JP6108337 B2 JP 6108337B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- time interval
- time
- stacking
- management system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009415 formwork Methods 0.000 claims description 14
- 238000004364 calculation method Methods 0.000 claims description 6
- 238000007726 management method Methods 0.000 description 21
- 230000005540 biological transmission Effects 0.000 description 7
- 238000010276 construction Methods 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 230000004397 blinking Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000002513 implantation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
Images
Description
本発明は、コンクリートの打重ね時間間隔管理システムに関する。 The present invention relates to a concrete stacking time interval management system.
従来、コンクリート工事において、コンクリートを打重ねる時間の間隔は、非常に重要な管理項目であり、適切な管理を怠るとコールドジョイント等の初期欠陥の発生を招き、所定のコンクリート品質を確保できなくなる。このため、例えば、公益社団法人土木学会では、環境温度が25℃を超える場合には2.0時間、25℃以下の場合には2.5時間を標準としてコンクリートを打重ねるよう、許容打重ね時間間隔標準値を規定している(例えば、非特許文献1、非特許文献2、非特許文献3参照)。
Conventionally, in concrete work, the time interval for stacking concrete is a very important management item, and neglecting proper management leads to the occurrence of initial defects such as cold joints, making it impossible to ensure a predetermined concrete quality. For this reason, for example, in the Japan Society of Civil Engineers, the allowable stacking is performed so that the concrete is stacked for 2.0 hours when the environmental temperature exceeds 25 ° C and 2.5 hours when the environmental temperature is 25 ° C or less. A time interval standard value is defined (for example, see Non-Patent
一方、現場でのコンクリート打設工事では、打重ね部分が複数個所存在するため、打重ね時間間隔を詳細に管理することが難しいケースも多々ある。そして、現場では、例えば、看板を掲示し、コンクリートを打設する度に打重ね許容時刻を看板に明記し、作業者等にコンクリートの打重ね時間を周知する管理手法が多用されている。しかしながら、このような看板を用いた管理手法では、看板の作製や掲示などの手間がかかるとともに、記載ミスなど、人的なミスが生じるおそれがある。 On the other hand, there are many cases where it is difficult to manage the stacking time interval in detail because there are a plurality of stacked portions in the concrete placement work on site. At the site, for example, a management method is often used in which a signboard is posted, the allowable stacking time is specified on the signboard every time concrete is placed, and the concrete stacking time is made known to workers and the like. However, in such a management method using a signboard, it takes time and labor to produce and post a signboard, and there is a risk of human error such as a description mistake.
本発明は、上記事情に鑑み、より適切にコンクリートの打重ね時間間隔の管理を可能にするコンクリートの打重ね時間間隔管理システムを提供することを目的とする。 In view of the above circumstances, an object of the present invention is to provide a concrete overlay time interval management system that enables more appropriate management of concrete overlay time intervals.
上記の目的を達するために、この発明は以下の手段を提供している。 In order to achieve the above object, the present invention provides the following means.
本発明のコンクリートの打重ね時間間隔管理システムは、コンクリート工事を行う際にコンクリートの打重ね時間を管理するためのコンクリートの打重ね時間間隔管理システムであって、型枠の上方に配設され、予め設定した時間間隔毎に、型枠内のコンクリートの打ち込み範囲が型枠によって目視困難な部位に打設されたコンクリートの形状を捉える形状センサと、前記形状センサから送られたコンクリートの形状データに基づいて、コンクリートの打ち込み領域と、打重ね面に対応する打重ね線とを求める画像処理・演算装置と、前記画像処理・演算装置で求めた前記時間間隔毎の打ち込み領域と打重ね線を表示し、且つ前記打重ね線の発生からの経過時間が予め設定した警告時間に達するとともに警告を発する表示装置とを備えて構成されていることを特徴とする。 The concrete stacking time interval management system of the present invention is a concrete stacking time interval management system for managing the stacking time of concrete when performing concrete work, and is disposed above the formwork. For each time interval set in advance, a shape sensor that captures the shape of concrete placed in a part where the concrete placement range in the mold is difficult to see by the mold, and the shape data of the concrete sent from the shape sensor Based on this, the image processing / calculation device for obtaining the concrete placement area and the overlay line corresponding to the overlay surface, and the placement area and the overlay line for each time interval obtained by the image processing / calculation apparatus are displayed. And a display device that issues a warning when the elapsed time from the occurrence of the overlay line reaches a preset warning time. It is characterized in that is.
また、本発明のコンクリートの打重ね時間間隔管理システムは、コンクリート工事を行う際にコンクリートの打重ね時間を管理するためのコンクリートの打重ね時間間隔管理システムであって、型枠の上方に配設され、予め設定した時間間隔毎に、型枠内に打設されたコンクリートの形状を捉える形状センサと、前記形状センサから送られたコンクリートの形状データに基づいて、コンクリートの打ち込み領域と、打重ね面に対応する打重ね線とを求める画像処理・演算装置と、前記画像処理・演算装置で求めた前記時間間隔毎の打ち込み領域と打重ね線を表示し、且つ前記打重ね線の発生からの経過時間が予め設定した警告時間に達するとともに警告を発する表示装置とを備え、前記画像処理・演算装置は、前記型枠内を横方向の一方向から見た平面視で分散配置して仮想の複数の打重ね参照点を予め設定しておき、前記型枠内に打設したコンクリートが達した位置の複数の打重ね参照点を連結処理して、前記打ち込み領域と前記打重ね線を求めるように構成されていることを特徴とする。 The concrete overlay time interval management system of the present invention is a concrete overlay time interval management system for managing the concrete overlay time when performing concrete work, and is disposed above the formwork. At a predetermined time interval, a shape sensor that captures the shape of the concrete placed in the mold, a concrete placement area based on the concrete shape data sent from the shape sensor, and the overlay An image processing / arithmetic device for determining a lap line corresponding to a surface, a driving area and a laying line for each time interval determined by the image processing / arithmetic device, and the generation of the lap line comprising a display device and for issuing a warning with time reaches the warning time set in advance, the image processing and computing apparatus, the lateral one direction inside the formwork A plurality of virtual reference points are set in advance in a distributed manner in a plan view, and a plurality of reference points at the position where the concrete placed in the mold has reached are connected, characterized in that it is configured to determine the punching overlapping line and the implanted region.
本発明のコンクリートの打重ね時間間隔管理システムにおいては、複数回にわたって型枠内に打設される各コンクリートの打ち込み領域と打重ね面に対応する打重ね線をリアルタイムで自動的に表示することができる。また、打重ね線の発生から経過時間、すなわち、型枠内に打設して表面が露出しているコンクリートの打設からの経過時間が予め設定した警告時間に達するとともに、打重ね線の表示色が変わったり、警告表示が表示されたり、警告音が発生されるなど、自動的に警告を発することができる。 In the concrete stacking time interval management system of the present invention, it is possible to automatically display, in real time, a stacking area corresponding to a stacking area and a stacking surface of each concrete to be placed in a mold multiple times. it can. In addition, the elapsed time from the occurrence of the overlay line, that is, the elapsed time from the placement of the concrete that has been exposed in the formwork and the surface is exposed reaches a preset warning time, and the overlay line is displayed. A warning can be automatically issued such as a color change, a warning display, or a warning sound.
これにより、各打重ね線の経過時間表示で適切にコンクリートの打重ね時間間隔を管理することが可能になる。また、コンクリートの打ち込み領域と打重ね線の情報に基づいて、打ち込み数量や、未打設領域の残量、残コンクリート、戻りコンクリートの数量などを特定することも可能になる。 This makes it possible to appropriately manage the concrete stacking time interval by displaying the elapsed time of each stacking line. It is also possible to specify the amount of placement, the remaining amount of unplaced area, the amount of remaining concrete, the amount of return concrete, and the like based on the information of the concrete placement area and the overlay line.
さらに、梁や柱、壁等、コンクリートの打ち込み範囲が型枠によって目視困難な部位であっても、コンクリートの打ち込み領域をほぼリアルタイムで可視化してコンクリートの打ち込み状況を確認することができる。 Furthermore, even if the concrete placement range, such as a beam, a column, or a wall, is difficult to see due to the formwork, the concrete placement area can be visualized almost in real time to confirm the concrete placement status.
よって、本発明のコンクリートの打重ね時間間隔管理システムによれば、より適切に(精度よく)、且つ効率的にコンクリートの打重ね時間間隔の管理を行うことができ、コールドジョイント発生リスクの低減を図り、コンクリート工事における品質や生産性を向上させることが可能になる。 Therefore, according to the concrete stacking time interval management system of the present invention, the concrete stacking time interval can be managed more appropriately (accurately) and efficiently, and the risk of cold joint occurrence can be reduced. It is possible to improve the quality and productivity in planning and concrete work.
以下、図1から図4を参照し、本発明の一実施形態に係るコンクリートの打重ね時間間隔管理システムについて説明する。 Hereinafter, a concrete stacking time interval management system according to an embodiment of the present invention will be described with reference to FIGS. 1 to 4.
本実施形態のコンクリートの打重ね時間間隔管理システムは、コンクリート打設工事において、コンクリートの打重ね時間間隔を適切に管理し、また、梁や柱、壁等、コンクリートの打ち込み範囲が型枠によって目視困難な部位であっても、コンクリートの打ち込み領域をほぼリアルタイムで可視化してコンクリートの打ち込み状況を確認するためのシステムである。 The concrete stacking time interval management system according to the present embodiment appropriately manages the concrete stacking time interval in concrete placing work, and the concrete placing range such as a beam, a column, and a wall is visually checked by a formwork. This is a system for visualizing the concrete placement area in almost real time to confirm the concrete placement status even in difficult areas.
具体的に、まず、本実施形態のコンクリートの打重ね時間間隔管理システムAは、図1に示すように、形状センサ1と、第1データ伝送装置2と、画像処理・演算装置3と、画像モニタ(表示装置)4と、第2データ伝送装置5と、タイマ6とを備えて構成されている。
Specifically, first, the concrete stacking time interval management system A according to the present embodiment includes a
形状センサ1は、例えば3Dレーザスキャナやレーザ距離計等であり、図2に示すように、コンクリート7の打ち込み領域をセンシングするように、型枠8の上方に配設される。そして、この形状センサ1は、例えば、5〜10分程度の任意の時間間隔(予め設定した時間間隔)△t毎に作動し、その時点でのコンクリート打ち込み状況に関する形状、すなわち、打重ね面7aの形状を取得する。また、形状センサ1によって取得したコンクリート打ち込み状況に関する形状データは、図1に示すように、打重ね面7aの情報として、任意の時間間隔毎に第1データ伝送装置2を通じて画像処理・演算装置3に送られる。
The
画像処理・演算装置3には、図3に示すように、例えば、型枠8を正面から見たときの平面視(型枠8内を横方向の一方向から見た平面視)で、縦横整列配置(分散配置)した仮想上の複数の打重ね参照点9を予め設定しておく。この打重ね参照点9の間隔は、所定の精度が得られるように適宜設定される。
As shown in FIG. 3, the image processing /
そして、画像処理・演算装置3では、図4に示すように、第1データ伝送装置2を通じて送られた打重ね面7aの情報を基づいた打重ね参照点9を連結処理することによって、すなわち、型枠8内に打設したコンクリート7が達した表面位置の複数の打重ね参照点9を連結処理することによって、コンクリート7の打ち込み領域(R1,R2,R3・・・)と打重ね面7aに対応する線((S1,S2,S3,S4・・・))を計算して求める。また、タイマ6によって予め設定した時間間隔で、随時、コンクリート7の打ち込み領域(R1,R2,R3・・・)と打重ね面7aに対応する打重ね線(S1,S2,S3,S4・・・)を計算し、各打重ね線(S1,S2,S3,S4・・・)の発生時刻を記憶する。
Then, in the image processing /
そして、上記のように算定された打ち込み領域(R1,R2,R3・・・)と打重ね線(S1,S2,S3,S4・・・)を、第2データ伝送装置5を通じて画像モニタ4で表示する。さらに、各打重ね線(S1,S2,S3,S4・・・)の打ち込み時刻、もしくは打ち込み時刻からの経過時間を表示する。
Then, the driving area (R1, R2, R3...) And the overlapping line (S1, S2, S3, S4...) Calculated as described above are displayed on the image monitor 4 through the second
このとき、打ち込み領域(R1,R2,R3・・・)は、例えば灰色などの特定色で表示するようにし、他の部分と区別できるようにしておく。なお、前後の打ち込み領域(R1,R2,R3・・・)を同色とし、特に区別しなくてもよい。また、打ち込み線(S1,S2,S3,S4・・・)は、センシング時刻の経過に従ってグラデーション状に変化させて表示する。また、打ち込み領域(R1,R2,R3・・・)に包含され、ある程度、例えば5×△t(5〜10分程度の任意の時間間隔)の時間が経過した打ち込み線(S1,S2,S3,S4・・・)は消去されるようにしてもよい。 At this time, the driving regions (R1, R2, R3...) Are displayed in a specific color such as gray so that they can be distinguished from other portions. The front and rear driving regions (R1, R2, R3,...) Have the same color and need not be particularly distinguished. Further, the driving lines (S1, S2, S3, S4...) Are displayed in a gradation shape as the sensing time elapses. In addition, the driving lines (S1, S2, S3, etc.) that are included in the driving regions (R1, R2, R3...) And have passed a certain amount of time, for example, 5 × Δt (an arbitrary time interval of about 5 to 10 minutes). , S4...) May be deleted.
そして、記憶されている各打重ね線(S1,S2,S3,S4・・・)の発生からの経過時間を計測し、この経過時間がJASS5や土木学会で示されている打重ね時間間隔に近くなった場合には、その打重ね線(S1,S2,S3,S4・・・)(もしくは打ち込み領域(R1,R2,R3・・・))を赤色などの他の色に変更したり、点滅させたり、音を発するなど、警告を発し、作業者等に打重ねの許容(制限)時間が迫っていることを認識させる。 And the elapsed time from generation | occurrence | production of each stored overlay line (S1, S2, S3, S4 ...) is measured, and this elapsed time is set to the overlay time interval shown by JASS5 or the Japan Society of Civil Engineers. When it becomes close, the overlay line (S1, S2, S3, S4...) (Or the implantation area (R1, R2, R3...)) Is changed to another color such as red, A warning is issued, such as blinking or a sound, and the operator is made aware that the allowable (restricted) time for striking is approaching.
したがって、本実施形態のコンクリートの打重ね時間間隔管理システムAにおいては、複数回にわたって型枠8内に打設される各コンクリート7の打ち込み領域(R1,R2,R3・・・)と打重ね面7aに対応する打重ね線(S1,S2,S3,S4・・・)をリアルタイムで自動的に表示することができる。また、打重ね線(S1,S2,S3,S4・・・)の発生から経過時間、すなわち、型枠8内に打設して表面7aが露出しているコンクリート7の打設からの経過時間が予め設定した警告時間に達するとともに、打重ね線(S1,S2,S3,S4・・・)の表示色が変わったり、警告表示が表示されたり、警告音が発生されるなど、自動的に警告を発することができる。
Therefore, in the concrete stacking time interval management system A of the present embodiment, the driving area (R1, R2, R3...) And the stacking surface of each concrete 7 to be placed in the
これにより、各打重ね線(S1,S2,S3,S4・・・)の経過時間表示で適切にコンクリート7の打重ね時間間隔を管理することが可能になる。また、コンクリート7の打ち込み領域(R1,R2,R3・・・)と打重ね線(S1,S2,S3,S4・・・)の情報に基づいて、打ち込み数量や、未打設領域の残量、残コンクリート、戻りコンクリートの数量などを特定することも可能になる。
Thereby, it becomes possible to manage the overlay time interval of the concrete 7 appropriately by displaying the elapsed time of each overlay line (S1, S2, S3, S4...). Further, based on the information of the
さらに、梁や柱、壁等、コンクリート7の打ち込み範囲が型枠8によって目視困難な部位であっても、コンクリート7の打ち込み領域(R1,R2,R3・・・)をほぼリアルタイムで可視化してコンクリート7の打ち込み状況を確認することができる。
Furthermore, even if the
よって、本実施形態のコンクリートの打重ね時間間隔管理システムAによれば、より適切に(精度よく)、且つ効率的にコンクリート7の打重ね時間間隔の管理を行うことができ、コールドジョイント発生リスクの低減を図り、コンクリート工事における品質や生産性を向上させることが可能になる。
Therefore, according to the concrete laying time interval management system A of the present embodiment, the laying time interval of the
以上、本発明に係るコンクリートの打重ね時間間隔管理システムの一実施形態について説明したが、本発明は上記の一実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。 As mentioned above, although one embodiment of the concrete stacking time interval management system according to the present invention has been described, the present invention is not limited to the above-described embodiment, and can be appropriately changed without departing from the gist thereof. is there.
1 形状センサ
2 第1データ伝送装置
3 画像処理・演算装置
4 画像モニタ(表示装置)
5 第2データ伝送装置
6 タイマ
7 コンクリート
7a 打重ね面(表面)
8 型枠
9 打重ね参照点
A コンクリートの打重ね時間間隔管理システム
R 打ち込み領域
S 打重ね線
DESCRIPTION OF
5 Second
8
Claims (2)
型枠の上方に配設され、予め設定した時間間隔毎に、型枠内のコンクリートの打ち込み範囲が型枠によって目視困難な部位に打設されたコンクリートの形状を捉える形状センサと、
前記形状センサから送られたコンクリートの形状データに基づいて、コンクリートの打ち込み領域と、打重ね面に対応する打重ね線とを求める画像処理・演算装置と、
前記画像処理・演算装置で求めた前記時間間隔毎の打ち込み領域と打重ね線を表示し、且つ前記打重ね線の発生からの経過時間が予め設定した警告時間に達するとともに警告を発する表示装置とを備えて構成されていることを特徴とするコンクリートの打重ね時間間隔管理システム。 A concrete stacking time interval management system for managing concrete stacking time when performing concrete work,
A shape sensor that is disposed above the formwork and captures the shape of the concrete placed in a site where the concrete placement range in the formwork is difficult to see by the formwork at predetermined time intervals;
Based on the concrete shape data sent from the shape sensor, an image processing / arithmetic device for obtaining a concrete driving area and a laying line corresponding to the laying surface;
A display device that displays a driving area and a lap line for each time interval obtained by the image processing / calculation device, and that issues a warning when an elapsed time from the generation of the lap line reaches a preset warning time; A concrete overlay time interval management system characterized by comprising:
型枠の上方に配設され、予め設定した時間間隔毎に、型枠内に打設されたコンクリートの形状を捉える形状センサと、
前記形状センサから送られたコンクリートの形状データに基づいて、コンクリートの打ち込み領域と、打重ね面に対応する打重ね線とを求める画像処理・演算装置と、
前記画像処理・演算装置で求めた前記時間間隔毎の打ち込み領域と打重ね線を表示し、且つ前記打重ね線の発生からの経過時間が予め設定した警告時間に達するとともに警告を発する表示装置とを備え、
前記画像処理・演算装置は、前記型枠内を横方向の一方向から見た平面視で分散配置して仮想の複数の打重ね参照点を予め設定しておき、前記型枠内に打設したコンクリートが達した位置の複数の打重ね参照点を連結処理して、前記打ち込み領域と前記打重ね線を求めるように構成されていることを特徴とするコンクリートの打重ね時間間隔管理システム。 A concrete stacking time interval management system for managing concrete stacking time when performing concrete work,
A shape sensor that is disposed above the formwork and captures the shape of the concrete placed in the formwork at preset time intervals;
Based on the concrete shape data sent from the shape sensor, an image processing / arithmetic device for obtaining a concrete driving area and a laying line corresponding to the laying surface;
A display device that displays a driving area and a lap line for each time interval obtained by the image processing / calculation device, and that issues a warning when an elapsed time from the generation of the lap line reaches a preset warning time; With
The image processing / arithmetic apparatus is arranged in a distributed manner in a plan view when the inside of the mold is viewed from one side in the horizontal direction, and a plurality of virtual overlay reference points are set in advance, A concrete stacking time interval management system characterized in that a plurality of stacking reference points at positions where the concrete has reached is connected to obtain the driving region and the stacking line.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012270359A JP6108337B2 (en) | 2012-12-11 | 2012-12-11 | Concrete stacking time interval management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012270359A JP6108337B2 (en) | 2012-12-11 | 2012-12-11 | Concrete stacking time interval management system |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2014114638A JP2014114638A (en) | 2014-06-26 |
JP6108337B2 true JP6108337B2 (en) | 2017-04-05 |
Family
ID=51170938
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2012270359A Expired - Fee Related JP6108337B2 (en) | 2012-12-11 | 2012-12-11 | Concrete stacking time interval management system |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6108337B2 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6592271B2 (en) * | 2015-04-17 | 2019-10-16 | 大和ハウス工業株式会社 | Placing management support device and program |
JP7030024B2 (en) * | 2018-06-26 | 2022-03-04 | 鹿島建設株式会社 | Filling management method for fluid solidifying material, filling management system for fluid solidifying material, and formwork for filling management of fluid solidifying material |
JP6797500B2 (en) * | 2018-09-12 | 2020-12-09 | 西松建設株式会社 | Concrete placement quantity calculation system and construction method of concrete structure |
JP7158321B2 (en) * | 2019-03-18 | 2022-10-21 | 大成建設株式会社 | concrete tracking system |
JP7178330B2 (en) * | 2019-06-26 | 2022-11-25 | 大成建設株式会社 | Placement plan creation device and placement plan creation method |
CN114393689B (en) * | 2021-12-07 | 2024-05-03 | 河北雄安京德高速公路有限公司 | Layered automatic feeding control system and method for T beam production |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5406090B2 (en) * | 2010-03-25 | 2014-02-05 | 戸田建設株式会社 | Concrete placement management system |
-
2012
- 2012-12-11 JP JP2012270359A patent/JP6108337B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2014114638A (en) | 2014-06-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6108337B2 (en) | Concrete stacking time interval management system | |
JP5681581B2 (en) | Concrete floor slab finish height management method | |
US11094120B2 (en) | Inspection processing system, inspection processing method, and inspection processing program | |
Dias-da-Costa et al. | Laboratorial test monitoring applying photogrammetric post-processing procedures to surface displacements | |
WO2015111735A1 (en) | Concrete structure maintenance system | |
JP2018180662A (en) | Material receiving inspection system | |
JP6952469B2 (en) | On-site construction management system | |
JP2019028595A (en) | Inspection processing system, inspection processing method and inspection processing program | |
JP2012021323A (en) | Inspection support system and program | |
JP2019191927A (en) | Structure inspection system and inspection method | |
JP2018193681A (en) | Concrete compaction management device | |
TW578056B (en) | Device and method for assisting the monitoring process on building construction | |
JP2019027817A (en) | Construction completion degree data acquisition system | |
JP7128013B2 (en) | Buried object recognition method | |
JP2018055246A (en) | Image processing device, image processing method and image processing program | |
JP2014074317A (en) | Construction support apparatus, and the method and program | |
JP2004037419A (en) | Tunnel control chart and its system | |
JP6660732B2 (en) | Steel frame measurement system, method and program | |
JP7033851B2 (en) | Construction volume data acquisition system | |
KR102238193B1 (en) | Method and server for managing construction information and maintenance information based on augmented reality | |
KR101237434B1 (en) | Realistic 3D Architecture Modeling Method using Survey Instrument | |
JP2005310044A (en) | Apparatus, method and program for data processing | |
JP2015190967A (en) | Building accuracy management system and method | |
JP6040538B2 (en) | Server device and information management system | |
JP2006095054A5 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20150611 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20160422 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20160607 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20160808 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20170131 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20170228 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6108337 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
LAPS | Cancellation because of no payment of annual fees |