JP5476848B2 - 太陽光発電量予測方法および実負荷予測方法、並びに配電系統制御システム - Google Patents
太陽光発電量予測方法および実負荷予測方法、並びに配電系統制御システム Download PDFInfo
- Publication number
- JP5476848B2 JP5476848B2 JP2009185543A JP2009185543A JP5476848B2 JP 5476848 B2 JP5476848 B2 JP 5476848B2 JP 2009185543 A JP2009185543 A JP 2009185543A JP 2009185543 A JP2009185543 A JP 2009185543A JP 5476848 B2 JP5476848 B2 JP 5476848B2
- Authority
- JP
- Japan
- Prior art keywords
- distribution system
- power generation
- power
- generator
- current
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24S—SOLAR HEAT COLLECTORS; SOLAR HEAT SYSTEMS
- F24S2201/00—Prediction; Simulation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Description
図1は、配電系統100を模式的に示す図である。特に、図1(a)は太陽光発電時における配電系統100を示し、図1(b)は非太陽光発電時における配電系統100を示し、図1(c)は太陽光発電機130の接続形態を例示的に示している。
図2は、本実施形態にかかる配電系統制御システム200の概略的な構成を示す図である。図2に示すように、配電系統制御システム200は、センサ内蔵自動開閉器120、システム制御部210、入力部212、出力部214、記憶部216、第1演算部218、第2演算部220、第3演算部222、予測部224、切替制御部226を包含する。以下、まずこれらの各要素について説明し、その後本実施形態にかかる配電系統制御システム200が適用する太陽光発電量予測方法、実負荷予測方法について詳細に説明する。
IU=IWU−IUV …(式1)
IV=IUV−IVW …(式2)
IW=IVW−IWU …(式3)
図4は本実施形態にかかる太陽光発電量予測方法、実負荷予測方法を例示するフローチャート、図5は太陽光発電量予測方法、実負荷予測方法を説明する図である。以下、この例示的に示されたフローチャートに則って、太陽光発電機130の発電量または実負荷を予測する態様を具体的に説明する。なお、かかる方法は特定の区間に適用されることが想定され、このような場合には上流側における計測値から下流側における計測値を引いた区間電流を用いるものとする。
Claims (7)
- 配電系統における太陽光発電量予測方法であって、
前記配電系統に連系した太陽光発電機の発電を要因とする三相交流の不平衡率を該太陽光発電機の接続形態より算出するステップと、
前記配電系統に連系した前記太陽光発電機の発電がないときの負荷を要因とする三相交流の正相電流と逆相電流との関係式である近似関数を導出するステップと、
前記配電系統の電流を計測して、前記配電系統に連系した前記太陽光発電機の発電および前記負荷を要因とする三相交流の正相電流および逆相電流の予測対象時点における現在値を計測するステップと、
前記不平衡率、前記近似関数、前記現在値に基づいて、前記太陽光発電機の発電量を予測するステップと、
を含むことを特徴とする太陽光発電量予測方法。 - 前記太陽光発電機の発電量の予測には、
前記現在値を包含し、且つ前記不平衡率から比例定数が定められる1次近似関数を導出するステップと、
前記現在値から前記1次近似関数と前記負荷を要因とする近似関数が交わる値までのベクトルを前記太陽光発電機の発電量として予測するステップと、
を含むことを特徴とする請求項1に記載の太陽光発電量予測方法。 - 前記不平衡率は、前記太陽光発電機の接続相ごとの総定格発電容量より算出されることを特徴とする請求項1または2に記載の太陽光発電量予測方法。
- 前記ベクトルを定められない場合には、前記配電系統の経路の切替をその区間を拡縮するように行って予測条件を変動させることを特徴とする請求項2に記載の太陽光発電量予測方法。
- 配電系統における実負荷予測方法であって、
前記配電系統に連系した太陽光発電機の発電を要因とする三相交流の不平衡率を該太陽光発電機の接続形態より算出するステップと、
前記配電系統に連系した前記太陽光発電機の発電がないときの負荷を要因とする三相交流の正相電流と逆相電流との関係式である近似関数を導出するステップと、
前記配電系統の電流を計測して、前記配電系統に連系した前記太陽光発電機の発電および前記負荷を要因とする三相交流の正相電流および逆相電流の予測対象時点における現在値を計測するステップと、
前記不平衡率、前記近似関数、前記現在値に基づいて、前記配電系統の実負荷を予測するステップと、
を含むことを特徴とする実負荷予測方法。 - 前記配電系統の実負荷の予測には、
前記現在値を包含し、且つ前記不平衡率から比例定数が定められる1次近似関数を導出するステップと、
0値から前記1次近似関数と前記負荷を要因とする近似関数が交わる値までのベクトルを実負荷として予測するステップと、
を含むことを特徴とする請求項5に記載の実負荷予測方法。 - 配電系統の電流を計測する計測機器と、
前記配電系統に連系した太陽光発電機のデータを含む所定の情報を入力または更新可能な入力部と、
前記計測機器の計測値や前記所定の情報を記憶する記憶部と、
前記データから前記太陽光発電機の接続相ごとの総定格発電容量を求め、前記配電系統に連系した該太陽光発電機の発電を要因とする三相交流の不平衡率を算出する第1演算部と、
予め計測された前記計測値を参照して、前記配電系統に連系した前記太陽光発電機の発電がないときの負荷を要因とする三相交流の正相電流と逆相電流との関係式である近似関数を導出する第2演算部と、
前記計測機器により計測された予測対象時点における現在値を参照して、前記配電系統に連系した前記太陽光発電機の発電および前記負荷を要因とする三相交流の正相電流および逆相電流を定める第3演算部と、
前記第1演算部が算出した前記不平衡率、前記第2演算部が導出した前記近似関数、前記第3演算部が定めた前記正相電流および前記逆相電流に基づいて、前記太陽光発電機の発電量または前記配電系統の実負荷を予測する予測部と、
前記予測部が予測した前記発電量または前記実負荷に基づいて、前記配電系統の運用を行う切替制御部と、
を備えることを特徴とする配電系統制御システム。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009185543A JP5476848B2 (ja) | 2009-08-10 | 2009-08-10 | 太陽光発電量予測方法および実負荷予測方法、並びに配電系統制御システム |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009185543A JP5476848B2 (ja) | 2009-08-10 | 2009-08-10 | 太陽光発電量予測方法および実負荷予測方法、並びに配電系統制御システム |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2011041384A JP2011041384A (ja) | 2011-02-24 |
JP5476848B2 true JP5476848B2 (ja) | 2014-04-23 |
Family
ID=43768547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2009185543A Active JP5476848B2 (ja) | 2009-08-10 | 2009-08-10 | 太陽光発電量予測方法および実負荷予測方法、並びに配電系統制御システム |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5476848B2 (ja) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105512379A (zh) * | 2015-12-02 | 2016-04-20 | 国家电网公司 | 一种光伏电站逆变器综合评估方法 |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5477038B2 (ja) * | 2010-02-19 | 2014-04-23 | 東京電力株式会社 | 太陽光発電量予測方法および配電系統制御システム |
FR2983363B1 (fr) * | 2011-11-28 | 2014-07-25 | Schneider Electric Ind Sas | Procede et systeme de gestion dynamique d'un reseau de distribution d'electricite |
CN116523148B (zh) * | 2023-07-03 | 2023-09-22 | 广东电网有限责任公司湛江供电局 | 一种配电网配变重过载预警方法、装置和设备 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4576315B2 (ja) * | 2005-10-13 | 2010-11-04 | 関西電力株式会社 | 連系する発電機を探知する方法およびそのプログラム |
JP5239657B2 (ja) * | 2008-09-09 | 2013-07-17 | 東京電力株式会社 | 負荷量推定方法、負荷曲線導出方法、負荷曲線導出装置、および負荷量推定装置 |
JP5442282B2 (ja) * | 2009-03-12 | 2014-03-12 | 株式会社日立製作所 | 発電機出力の推定方法および装置 |
-
2009
- 2009-08-10 JP JP2009185543A patent/JP5476848B2/ja active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105512379A (zh) * | 2015-12-02 | 2016-04-20 | 国家电网公司 | 一种光伏电站逆变器综合评估方法 |
Also Published As
Publication number | Publication date |
---|---|
JP2011041384A (ja) | 2011-02-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6444286B2 (ja) | 配電系統を構成する方法 | |
CN103620903B (zh) | 电力供给系统 | |
Ceran | The concept of use of PV/WT/FC hybrid power generation system for smoothing the energy profile of the consumer | |
Østergaard | Regulation strategies of cogeneration of heat and power (CHP) plants and electricity transit in Denmark | |
JP2015080401A (ja) | 電気ネットワークを制御するための方法およびシステム | |
EP2660943A1 (en) | Power controller | |
WO2014045656A1 (ja) | 系統制御装置および系統制御方法 | |
KR101516802B1 (ko) | 독립형 마이크로그리드용 배전반 | |
CN105556779A (zh) | 用于提供电源接口的设备和方法 | |
JP5505191B2 (ja) | 太陽光発電量予測方法および配電系統制御システム | |
Shahmohammadi et al. | Proper sizing and placement of distributed power generation aids the intentional islanding process | |
JP2010193594A (ja) | 太陽光発電システムの最大発電量推定方法、配電系統の制御方法、及び配電系統制御装置 | |
JP2010193605A (ja) | 配電区間の負荷推定方法及び配電系統制御方法 | |
JP5476848B2 (ja) | 太陽光発電量予測方法および実負荷予測方法、並びに配電系統制御システム | |
JP5556289B2 (ja) | 分散型電源および分散型電源制御方法 | |
JP5477038B2 (ja) | 太陽光発電量予測方法および配電系統制御システム | |
WO2020218191A1 (ja) | 電力制御装置、電力制御装置の制御方法、分散型発電システム | |
JPWO2014167830A1 (ja) | 電力制御システム | |
Yoshizawa et al. | Advanced voltage control based on short-time ahead voltage fluctuation estimation in distribution system | |
Amraee et al. | System protection scheme for mitigation of cascaded voltage collapses | |
Suslov et al. | Expansion planning of active power supply systems | |
JP2019193479A (ja) | 蓄電池制御装置、蓄電池制御プログラム | |
JP2017127129A (ja) | 蓄電池制御方法 | |
JP2011135644A (ja) | 不感帯回避システム、不感帯回避装置及び不感帯回避方法 | |
JP6696235B2 (ja) | 配電制御システム、及び予測プログラム |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20120806 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20130917 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20131010 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140114 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140127 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5476848 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |