JP5231338B2 - How to build a brick panel wall - Google Patents
How to build a brick panel wall Download PDFInfo
- Publication number
- JP5231338B2 JP5231338B2 JP2009136221A JP2009136221A JP5231338B2 JP 5231338 B2 JP5231338 B2 JP 5231338B2 JP 2009136221 A JP2009136221 A JP 2009136221A JP 2009136221 A JP2009136221 A JP 2009136221A JP 5231338 B2 JP5231338 B2 JP 5231338B2
- Authority
- JP
- Japan
- Prior art keywords
- brick
- panel wall
- brick panel
- slab
- panel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000011449 brick Substances 0.000 title claims description 319
- 238000010276 construction Methods 0.000 claims description 30
- 238000000034 method Methods 0.000 claims description 20
- 239000004570 mortar (masonry) Substances 0.000 claims description 18
- 238000009415 formwork Methods 0.000 claims description 15
- 239000000463 material Substances 0.000 claims description 9
- 239000011810 insulating material Substances 0.000 claims description 7
- 230000000149 penetrating effect Effects 0.000 claims description 2
- 230000008569 process Effects 0.000 description 10
- 230000008859 change Effects 0.000 description 8
- 238000010586 diagram Methods 0.000 description 8
- 230000003014 reinforcing effect Effects 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 230000002452 interceptive effect Effects 0.000 description 3
- 239000002184 metal Substances 0.000 description 3
- 238000005520 cutting process Methods 0.000 description 2
- 229920001084 poly(chloroprene) Polymers 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 238000000926 separation method Methods 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 235000014121 butter Nutrition 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000004939 coking Methods 0.000 description 1
- 229920001971 elastomer Polymers 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000005304 joining Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Description
本発明は、マンション等の複数階層を備える集合住宅において、レンガパネルを用いてレンガパネル壁を構築する方法に関するものである。 The present invention relates to a method for building a brick panel wall using a brick panel in an apartment house having a plurality of floors such as an apartment.
マンションなどの集合住宅のバルコニーに構築される手摺や、廊下に構築される腰壁として好適な低位壁を、本出願人は先に提案した(特許文献1:特開2001−164646号公報)。 The present applicant has previously proposed a handrail constructed on the balcony of an apartment house such as an apartment, and a lower wall suitable as a waist wall constructed in a corridor (Patent Document 1: Japanese Patent Application Laid-Open No. 2001-164646).
さて、100年あるいはそれ以上(例えば、300年)の長寿命の集合住宅を求める傾向が強まっているが、集合住宅の実質的に延長するためには、住人の世代や所有者が変わっても、それに応じて柔軟に間取り等を変更できることが望ましい。より具体的には、住居を、躯体部分(スケルトン)と、住人の希望通りに変更できる部分(インフィル)とに分離してとらえるスケルトン・インフィル分離思想が提案されている。 Now, there is an increasing tendency to demand long-lived apartments of 100 years or more (for example, 300 years). However, in order to substantially extend an apartment house, the generation and owner of the resident change. It is desirable that the floor plan and the like can be flexibly changed accordingly. More specifically, a skeleton / infill separation idea has been proposed in which a residence is separated into a housing part (skeleton) and a part (infill) that can be changed as desired by the resident.
集合住宅は、およそ20年から50年ほどの期間を周期として、その所有者が変化することが多い。所有者が変われば、その家族構成や好み等も変化するから、それを機にインフィルを変えるということになりやすい。集合住宅の壁、特に、共用廊下側の壁には一般に玄関ドアや窓が設けられることが多い。インフィルを自由に変えられるようにするには、玄関ドアや窓の位置等も変更できるように配慮する必要がある。ここで、壁をコンクリートの打設により構築すると、このような変更時には、コンクリートのはつりが必要になり、騒音・振動が発生し、現実的でない。即ち、壁をコンクリートの打設により構築すると、壁のレイアウト変更は事実上無理となり、結果的にインフィルを自由に変更できなくなってしまう。さらに、所有権上も廊下側の壁は共有部分にあたるため、個人では自由に変更できない。 Apartment houses often change their owners with a period of about 20 to 50 years as a cycle. If the owner changes, the family structure, preferences, etc. also change, so it is easy to change the infill. In general, entrance walls and windows are often provided on the walls of apartment buildings, especially on the common corridor. In order to be able to change the infill freely, it is necessary to consider that the position of the entrance door and the window can be changed. Here, if the wall is constructed by placing concrete, it will be necessary to hang concrete, and noise and vibration will be generated at the time of such changes, which is not realistic. That is, if the wall is constructed by placing concrete, it is practically impossible to change the wall layout, and as a result, the infill cannot be freely changed. Furthermore, because of the ownership, the walls on the corridor side are common areas and cannot be freely changed by individuals.
このような事情に鑑み、壁をコンクリートではなく、ALC版やセメント成型版を使用して構築することが検討されている。 In view of such circumstances, it has been studied to construct a wall using an ALC plate or a cement molding plate instead of concrete.
一方、本発明は、壁をレンガブロックを使用して構築しようとするものである。古来から用いられているレンガは、耐久性や耐候性が高い。しかしながら、特許文献1で指摘したように、共用廊下側の壁を構築するについて、単純に市販のレンガを現場で1枚1枚積むと、非常に手間や時間がかかり、工事費がかさんでしまう。
On the other hand, the present invention intends to construct a wall using brick blocks. Brick that has been used since ancient times has high durability and weather resistance. However, as pointed out in
また、特許文献1では、上端部が片持ち梁状となる、低い壁しか想定しておらず、ドア枠や窓枠に対応することが容易でない。
Moreover, in
さらに重要なことには、そもそも現場では、下層階のスラブを形成した後、上層階用のスラブ、大梁または柱をコンクリートで構築するために、上層階には型枠が設けられ、型枠を支持する支保工など様々な部材が、所狭しとあちらこちらに張出したり起立したりしており、作業員は、辛うじてこれらをかわしながら、ぎりぎりで移動できるどうかという有様である。 More importantly, in the first place, in the first place, after forming the slabs for the lower floors, in order to construct the slabs, girder or pillars for the upper floors with concrete, formwork is provided on the upper floors, Various members, such as supporting supporters, are protruding and standing up and down here, and it seems that workers can barely move while dodging them.
レンガパネルを用いて壁を構築する上では、これら様々な部材は、邪魔物以外の何でもなく、このように邪魔な部材が溢れている現場に、レンガパネル壁を構築することは、現実には無理(熟練の作業者といえども)としてあきらめられているといっても過言ではない。
そこで本発明は、上層階用のスラブ、大梁または柱のための型枠が組まれている現場において、レンガパネル壁を構築できる方法を提供することを目的とする。 Therefore, an object of the present invention is to provide a method capable of constructing a brick panel wall at a site where a formwork for a slab, upper beam or column for upper floors is assembled.
第1の発明に係るレンガパネル壁の構築方法は、下層階に形成されているスラブから、上層階用のスラブ又は大梁を形成するために組まれる型枠へ向けて、起立するレンガパネル壁を構築する方法であって、それぞれ複数のレンガブロックを組み合わせてなる、複数のレンガパネルを用意する工程と、複数のレンガパネルを起立させてレンガパネル壁を構築するとともに、起立するレンガパネル壁を仮設固定材により、挟んで締め付ける工程とを含み、レンガパネル壁の周囲と上階層用のスラブ又は大梁との間の少なくとも一部に隙間があけられており、上階層用のスラブ又は大梁を形成した後、型枠を撤去し、隙間の少なくとも一部をレンガブロックで埋め、仮設固定材を撤去する。 According to a first aspect of the present invention, there is provided a method of building a brick panel wall, wherein a brick panel wall that stands up from a slab formed on a lower floor toward a formwork formed to form a slab or a large beam for an upper floor. It is a method of construction, a process of preparing a plurality of brick panels each composed of a plurality of brick blocks, and a brick panel wall is constructed by erecting a plurality of brick panels, and a standing brick panel wall is temporarily installed Including a step of sandwiching and tightening with a fixing material, and a gap is formed in at least a part between the periphery of the brick panel wall and the slab or girder for the upper layer to form the slab or girder for the upper layer Then, the formwork is removed, at least part of the gap is filled with brick blocks, and the temporary fixing material is removed.
この構成において、レンガパネル壁の周囲と上階層用のスラブ又は大梁との間に隙間があけられているため、レンガパネル壁と型枠とが干渉せず、型枠の形成・支持やレンガパネル壁の構築にいずれも支障がない。また、レンガパネル壁を複数のレンガパネルに小分けして構築するようにしたため、各レンガパネルは、作業員が人手で運びうる程度の重量大きさにもすることができ、作業性を向上できる。レンガパネル壁の周囲と上階層用のスラブ又は大梁との間の少なくとも一部に存在する隙間は、コンクリート打設用の仮枠を組むためのスペースとして活用できる。 In this configuration, because there is a gap between the periphery of the brick panel wall and the upper slab or girder, the brick panel wall and the formwork do not interfere, and the formwork is formed and supported, and the brick panel. There are no obstacles to the construction of the walls. In addition, since the brick panel wall is constructed by dividing it into a plurality of brick panels, each brick panel can be made large enough to be carried manually by an operator, and workability can be improved. A gap existing in at least a part between the periphery of the brick panel wall and the upper slab or the large beam can be used as a space for assembling a temporary frame for placing concrete.
また、型枠を撤去した後、隙間をレンガブロックで埋めることとしたため、元は隙間であった箇所においても、レンガパネルと同様のテクスチャを呈することができ、外観上の統一性を得やすい。さらに、隙間をレンガブロックで埋めるという作業は、レンガブロックを手積みする場合と殆ど同じであり、格段の困難性を伴わない。 In addition, since the gap is filled with a brick block after the formwork is removed, the same texture as the brick panel can be exhibited even at the location where the gap was originally, and it is easy to obtain uniformity in appearance. Furthermore, the work of filling the gaps with brick blocks is almost the same as when brick blocks are stacked by hand, and does not involve any particular difficulty.
第2の発明に係るレンガパネル壁の構築方法では、仮設固定材は、複数のレンガパネル同士間の少なくとも一部に通されるセパレータと、セパレータに着脱自在に装着されレンガパネル壁を挟んで締め付ける、水平な複数のバタ角材とを含む。 In the method for building a brick panel wall according to the second invention, the temporary fixing material is attached to the separator through at least a part between the plurality of brick panels, and is detachably attached to the separator and clamped with the brick panel wall interposed therebetween. , Including a plurality of horizontal square bars.
この構成により、型枠を構築する際に使用される部材をそのままレンガパネルの構築及び支持に流用することができ、部材の調達を容易にできるだけでなく、無駄なコストアップを抑制できる。 With this configuration, the members used when building the formwork can be used as they are for the construction and support of the brick panel, and not only can the procurement of the members be facilitated, but also wasteful cost increases can be suppressed.
第3の発明に係るレンガパネル壁の構築方法では、複数のレンガブロックは、第1レンガパネルと、第2レンガパネルとを含み、第1レンガパネルの高さは、下層階のスラブから上層階用のスラブ又は大梁に至る高さよりも所定寸法だけ低くなるように定められ、第1レンガパネルは、縦筋が挿通される孔を有する複数の第1レンガブロックを目地モルタルで上下に接着してなり、第2レンガパネルの高さは、下層階のスラブから窓枠に至る高さよりも所定寸法だけ低くなるように定められ、第2レンガパネルは、縦筋が挿通される孔を有する複数の第2レンガブロックを目地モルタルで上下に接着してなる複数のレンガブロック群を幅方向に並べ、複数の第2レンガブロックの一部は、幅方向を長手方向とする横筋が挿入される横筋レンガブロックで構成され、第1レンガパネルと第2レンガパネルとで囲まれる空間に窓枠を配置し、窓枠に窓を設ける。 In the construction method of the brick panel wall according to the third invention, the plurality of brick blocks include a first brick panel and a second brick panel, and the height of the first brick panel is higher than the lower floor slab. The first brick panel is formed by bonding up and down a plurality of first brick blocks having holes through which vertical bars are inserted with joint mortar up and down. The height of the second brick panel is determined to be lower than the height from the lower floor slab to the window frame by a predetermined dimension, and the second brick panel has a plurality of holes through which the vertical bars are inserted. A plurality of brick block groups formed by adhering the second brick blocks up and down with joint mortars are arranged in the width direction, and a part of the plurality of second brick blocks is a horizontal stripe brick into which a horizontal line having the width direction as a longitudinal direction is inserted. It consists of lock, the window frame in a space surrounded by the first brick panel and the second brick panel arranged, providing a window to the window frame.
この構成により、第1レンガパネルにより、ほぼ下層階のスラブから上層階のスラブ又は大梁まで起立するレンガパネル壁を構築できるし、第2レンガパネルにより、上層階のスラブ又は大梁までは至らないが、窓枠まで至るレンガパネル壁を構築できる。さらに、レンガパネル壁に囲まれる窓を構築でき、このレンガパネル壁を、例えば、共用廊下側の壁として利用することができる。 With this configuration, the first brick panel can be used to construct a brick panel wall that rises from the lower floor slab to the upper floor slab or the large beam, and the second brick panel does not reach the upper floor slab or the large beam. A brick panel wall can be built up to the window frame. Furthermore, a window surrounded by a brick panel wall can be constructed, and this brick panel wall can be used as, for example, a wall on the shared corridor side.
また、第2レンガパネルには、幅方向を長手方向とする横筋が挿入される横筋レンガブロックで構成されているので、レンガを横方向につないでなるレンガパネルを構築して、窓枠や窓による荷重を十分支持することができる。 In addition, since the second brick panel is composed of horizontal brick blocks into which horizontal stripes with the width direction as the longitudinal direction are inserted, a brick panel that connects bricks in the horizontal direction is constructed, and a window frame or window Can fully support the load.
数十年程度の時間が経過し、インフィルを変更しようとするときには、レンガパネルは、そのまま間取り変更先の位置にレイアウトでき、資源を無駄なく再利用できる。しかも、レンガパネルを構成する各レンガブロックは、時間が経過するにつれ、味わい深い色合いに変化してゆくものであるが、これもそのまま利用できる。さらに、レンガパネルの構成を変更すれば、例えば玄関位置の変更により間取りが変わり窓の位置を変えるなど、種々のレイアウト変更を行える。 When several decades have passed and the infill is to be changed, the brick panel can be laid out as it is at the location where the floor plan is changed, and resources can be reused without waste. In addition, each brick block constituting the brick panel changes to a tasteful color as time passes, but this can also be used as it is. Furthermore, if the configuration of the brick panel is changed, various layout changes can be made, such as changing the layout by changing the entrance position and changing the position of the window.
第4の発明に係るレンガパネル壁の構築方法では、下層階のスラブから上方へ延びる差筋に複数のレンガパネルの下端部を連結し、上層階用のスラブ又は大梁から下方へ延びる差筋に複数のレンガパネルの上端部を連結する。 In the construction method of the brick panel wall according to the fourth invention, the lower ends of the plurality of brick panels are connected to the differential bars extending upward from the slab on the lower floor, and the differential bars extending downward from the slab or upper beam for the upper floor. The upper ends of a plurality of brick panels are connected.
この構成により、レンガパネル壁は、差筋によって、その上下がピン止めされることになり、地震時のように振動が発生したとき、レンガパネル壁が振動による力に抵抗しないようにすることができる。地震時には、振動による力が始めに壁に伝わり、これが梁に伝わるような力の流れができるが、この流れをピン止めにより伝わりにくくすることができる。 With this configuration, the top and bottom of the brick panel wall are pinned by the difference bars, so that when the vibration occurs as in an earthquake, the brick panel wall does not resist the force caused by the vibration. it can. At the time of an earthquake, the force of vibration is transmitted to the wall first, and the force can be transmitted to the beam, but this flow can be made difficult to transfer by pinning.
第5の発明に係るレンガパネル壁の構築方法では、複数のレンガパネルを起立させるに先立ち、下層階のスラブ上で複数のレンガパネルを起立させるべき位置に、レンガブロックを長手方向中心線で縦断した形状をなす一対の半割レンガブロックを複数個配置し、配置された半割レンガブロック上に複数のレンガパネルを起立させる。 In the construction method of the brick panel wall according to the fifth aspect of the invention, prior to raising the plurality of brick panels, the brick block is longitudinally cut along the longitudinal center line at the position where the plurality of brick panels should be raised on the lower floor slab. A plurality of a pair of half-brick blocks having the above-described shape are arranged, and a plurality of brick panels are erected on the arranged half-brick blocks.
この構成により、最下層に半割レンガブロックを敷き、その上に、レンガパネルを起立させることになる。レンガパネルは、工場で大量にかつ正確に製造できるし、最下層の半割レンガブロックにより、現場(例えば、不陸等)にあわせて施工できる。半割レンガブロックを使用することにより、差筋が半割レンガブロックの付近に位置していても、差筋に干渉せずに、半割レンガブロックを配置でき、円滑・容易に工事を進めることができる。 With this configuration, a half brick block is laid on the lowermost layer, and a brick panel is erected thereon. Brick panels can be manufactured in large quantities and accurately at the factory, and can be constructed according to the site (for example, non-land) by using the lower half brick block. By using a half-brick block, even if the difference bar is located near the half-brick block, the half-brick block can be placed without interfering with the difference bar, and the construction can proceed smoothly and easily. Can do.
また、壁は、全体としては、レンガパネルと、半割レンガブロックとにより構成されるから、壁の外観は、レンガを手積みしたような場合と同様であり、見た目の統一感を得やすい。 Moreover, since the wall as a whole is composed of brick panels and half-brick blocks, the appearance of the wall is the same as when bricks are stacked by hand, and it is easy to obtain a uniform appearance.
本発明によれば、型枠及びその関連部材により邪魔されて、現実には無理と考えられていた、上層階用の型枠に関する工事と並行して、それと干渉することなく、レンガパネル壁を現場で構築することができる。 According to the present invention, the brick panel wall can be installed without interfering with the upper floor in parallel with the construction related to the formwork for the upper floor, which has been disturbed by the formwork and its related members, and which is considered impossible in reality. Can be built on site.
しかも、背が高いレンガ造りの壁を、容易かつ効率的に構築できるというだけでなく、インフィルを変更する際にも、半割レンガの弱い部分を除去することにより、レンガパネルのほとんどを再利用でき、資源を無駄なく活用できる。この際、コンクリートのはつりに比べて大きな振動・騒音を減じて、実施することができ、インフィルの変更自由度を維持したまま、容易にしかも住人への迷惑を減らし、集合住宅のエコロジー化に資することができる。 Moreover, not only can you build tall brick walls easily and efficiently, but you can reuse most of the brick panels by removing the weak parts of the halved bricks when changing the infill. Can be used without waste. At this time, it can be carried out with less vibration and noise compared to concrete fishing, and while maintaining the freedom to change infill, it easily reduces inconvenience to residents and contributes to the ecology of housing complexes. be able to.
具体的な実施の形態の説明に先立ち、本発明が立脚するスケルトン及びインフィルの新たな考え方について説明する。この考え方は、建物を300年継続して使用できるようにするためのコンセプトである。 Prior to the description of specific embodiments, a new concept of skeleton and infill based on the present invention will be described. This concept is a concept for enabling a building to be used continuously for 300 years.
建物をスケルトンとインフィルとに分類する。この考え方自体は、従前から存在するが、次の点が従来の考え方とは大きく相違する。まず、スケルトンを、パブリックな躯体と共用部分の設備とが一体として存在するものと考える。 Classify buildings into skeletons and infills. This idea itself has existed for a long time, but the following points are significantly different from the conventional idea. First, the skeleton is considered to be a public enclosure and common facilities.
また、スケルトンの共用部分設備を、水道、ガス、電気及び排水のためのパイピングスペース、メーターボックス等のパブリック設備と、エレベータ、ポンプ等消耗する設備であるセミパブリック設備との、2つに分けて考える。 In addition, the shared parts of the skeleton are divided into two parts: public facilities such as piping spaces for water, gas, electricity and drainage, meter boxes, and semi-public facilities that are consumables such as elevators and pumps. Think.
今まで共用部分と考えられていた、廊下側の玄関ドア、壁、サッシュ、バルコニー側のサッシュ及び壁を、インフィル・パブリックと考え、インフィルは、専有のインフィルと、インフィル・パブリックとからなるものと考える。 The entrance door on the corridor side, walls, sashes, and the sash and walls on the balcony side, which were previously considered common areas, are considered as infill public, and the infill is composed of proprietary infill and infill public. Think.
即ち、スケルトンは、日常的に使用されるパブリックな躯体と、パブリック設備と、セミパブリック設備とからなり、インフィルは、内装と、専有部分の設備と、インフィル・パブリックとからなると考える。 In other words, the skeleton is composed of a public enclosure, a public facility, and a semi-public facility that are used daily, and the infill is composed of an interior, a dedicated portion of the facility, and an infill public.
そして、50年ごとにパブリック設備を全て取り替えるとする。50年ごとに安定してパブリック設備を更新し、これを繰り返すことにより、建物は300年もつ。 And all public facilities are replaced every 50 years. By updating public facilities stably every 50 years and repeating this, the building has 300 years.
50年目で足場を架け躯体の修理を行う。弱い部位の材料を工夫し、50年もつように配慮する。 In the 50th year, build a scaffold and repair the frame. We devise materials for weak parts and consider it to last 50 years.
20年乃至30年ごとに、足場なしで天井、床、内壁等についてメンテナンスする。具体的には、塗装の吹替え、コーキングの打替え、共用配管の清掃等を実施する。 Every 20-30 years, maintenance is performed on the ceiling, floor, inner wall, etc. without a scaffold. Specifically, paint dubbing, coking replacement, common piping cleaning, etc. will be implemented.
100年を単位とすれば、50年、100年間で集めた修繕積立金内で2回の改修工事を行う。これを繰り返して建物を300年もたせる。 If the unit is 100 years, the repair work will be carried out twice in the reserve fund collected over 50 years, 100 years. Repeat this to build the building for 300 years.
以上の考え方に基づき、建物が300年もつストーリーを設定する。本発明のレンガパネル壁は、この長いストーリーの中に織り込まれる一つであり、20年乃至50年程度で、住宅の所有者が変更され、インフィルの変更が望まれるときに、壁を含めてインフィルの変更を実現可能とする思想に立脚するものである。従来技術は、いずれもこのようなロングスパンでものを考えるということをしておらず、せいぜい60年ぐらいで建物は使用できなくなるだろうという程度の認識しかない。本発明は基本的なコンセプトにおいても、従来技術とは一線を画すものである。 Based on the above thinking, a story that the building has for 300 years is set. The brick panel wall of the present invention is one that is woven into this long story, and in about 20 to 50 years, when the homeowner is changed and infill changes are desired, including the wall It is based on the idea of enabling infill changes. None of the prior arts considers such a long span, and only recognizes that the building will not be usable in about 60 years. Even in the basic concept, the present invention is different from the prior art.
以下図面を参照しながら、本発明の実施の形態を説明する。本発明のレンガパネル壁の骨子は、次の通りである。即ち、
(1)第1レンガパネルと、第2レンガパネルとを用意する。第1レンガパネルは、縦筋が挿通される孔を有する複数の第1レンガブロックを目地モルタルで上下に接着してなり、スラブから天井又は梁に至る高さよりも所定寸法だけ低くなるように高さが定められる。第2レンガパネルは、縦筋が挿通される孔を有する複数の第2レンガブロックを目地モルタルで上下に接着してなる複数のレンガブロック群を幅方向に並べ、複数の第2レンガブロックの一部を幅方向を長手方向とする横筋が挿入される横筋レンガブロックで構成し、スラブから窓枠に至る高さよりも所定寸法だけ低くなるように高さが定められる。
Embodiments of the present invention will be described below with reference to the drawings. The gist of the brick panel wall of the present invention is as follows. That is,
(1) A first brick panel and a second brick panel are prepared. The first brick panel is formed by adhering a plurality of first brick blocks having holes through which vertical bars are inserted vertically with joint mortar, so that the height is lower by a predetermined dimension than the height from the slab to the ceiling or beam. Is determined. The second brick panel includes a plurality of brick block groups formed by adhering a plurality of second brick blocks having holes through which vertical bars are inserted vertically with joint mortar in the width direction, and one of the plurality of second brick blocks. The section is configured by a horizontal brick block into which a horizontal line having a width direction as a longitudinal direction is inserted, and the height is determined to be lower by a predetermined dimension than the height from the slab to the window frame.
(2)第1レンガブロックを長手方向中心線で縦断した形状をなす一対の半割レンガブロックを横に複数個、一対の半割レンガブロックがスラブから上方に突出する第1差筋を挟むように配置して固定する。 (2) A plurality of a pair of half brick blocks having a shape obtained by longitudinally cutting the first brick block along the longitudinal center line, and a pair of the half brick blocks sandwiching a first difference line projecting upward from the slab Place and fix to.
(3)配置された一対の半割レンガブロック上において、窓なしで天井又は梁に至る壁を形成すべき箇所には、第1レンガパネルを一対の半割レンガブロック上に配置する。 (3) On the pair of half-brick blocks arranged, the first brick panel is arranged on the pair of half-brick blocks at a place where a wall reaching the ceiling or the beam without a window is to be formed.
(4)配置された一対の半割レンガブロック上において、窓を形成すべき箇所には、第2レンガパネルを一対の半割レンガブロック上に配置する。 (4) The second brick panel is disposed on the pair of half-brick blocks at positions where the windows are to be formed on the pair of half-brick blocks.
(5)天井又は梁から第2差筋を第1レンガパネル側へ下向きに突出させると共に、天井又は梁を構成する箇所にコンクリートを打設し、第2差筋と、第1レンガブロックの縦筋及び第2レンガブロックの縦筋とを、それぞれ固着する。 (5) The second difference bar is projected downward from the ceiling or beam to the first brick panel side, and concrete is placed at a location constituting the ceiling or beam, and the second difference bar and the first brick block are vertically arranged. The streak and the vertical streak of the second brick block are fixed to each other.
(6)第1レンガブロックを長手方向中心線で縦断した形状をなす一対の半割レンガブロックを複数個、一対の半割レンガブロックが天井又は梁から下向きに突出する第2差筋を挟むように配置して固定して、第1レンガブロックと天井又は梁との間を埋める。そして、
(7)第1、第2レンガブロックで囲まれる空間に窓枠を配置し、窓を形成する。
(6) A plurality of a pair of half-brick blocks having a shape obtained by longitudinally cutting the first brick block along the longitudinal center line, and the pair of half-brick blocks sandwiching a second difference bar projecting downward from the ceiling or beam The first brick block and the ceiling or beam are buried between the first brick block and the ceiling. And
(7) A window frame is arranged in a space surrounded by the first and second brick blocks to form a window.
次に図面を参照しながら、本発明の実施の形態について説明する。図1(a)は、本発明の一実施の形態におけるレンガブロックの斜視図、図1(b)は、本発明の一実施の形態における横筋レンガブロックの斜視図、図1(c)は、本発明の一実施の形態における半割レンガブロックの斜視図である。 Next, embodiments of the present invention will be described with reference to the drawings. FIG. 1A is a perspective view of a brick block according to an embodiment of the present invention, FIG. 1B is a perspective view of a horizontal brick block according to an embodiment of the present invention, and FIG. It is a perspective view of the half brick block in one embodiment of the present invention.
図1(a)、図1(c)に示すように、レンガブロック1、横筋レンガブロック5及び一対の半割レンガブロック7には、第1孔2、8、第2孔3、9及び第3孔4、10が、それぞれ上下(厚さ方向)に貫通するように形成されている。図1(b)では、横筋レンガブロック5の孔は隠れているが、レンガブロック1と同様に、横筋レンガブロック5にも孔が形成されている。これらの孔2、8、3、9、4、10の形状は、図1(a)に示すように、角張ったものとしても良いし、あるいは、丸みを帯びたようにしても良い。
As shown in FIGS. 1 (a) and 1 (c), the
第1孔2、8及び第3孔10には、図2に示すように、縦筋11がその上下端がさらに上下に延出するように貫通し、第1孔2、8及び第3孔10には、モルタルが工場で埋め込まれている。但し、第2孔3、9には、何も充填されず、単なる空洞になっている。
As shown in FIG. 2, the
また、この例では、レンガブロック1、横筋レンガブロック5及び一対の半割レンガブロック7のそれぞれ1個当たり、モルタルが充填される孔2、7、3、10を2つ、空洞の孔3、9を1つとしたが、これらの位置や個数は、便宜変更できる。
Further, in this example, two
ここで、レンガブロック1は、通常使用されるブロックであり、横筋レンガブロック5は、長手方向に沿う配筋用溝6を有し、配筋用溝6には、図2(c)に示すように、横筋12を入れ、さらに配筋用溝6にモルタルを充填することにより、横に並ぶ2つのブロックを横方向に強固に連結できるようになっている。
Here, the
また、一対の半割レンガブロック7は、丁度レンガブロック7をその長手方向中心線を境にして、縦に切断した形状をなすように工場で加工されている。そして、工場ではなく、構築現場で、壁の最下層あるいは最上層において、スラブ、天井或いは梁から延出する差筋に奥側あるいは手前側から嵌め込み、第1孔8、第3孔10にモルタルを充填できるようになっている。
Further, the pair of half brick blocks 7 are processed in a factory so as to have a shape that is cut vertically with the
図2(a)は、本発明の一実施の形態における第1レンガパネルの斜視図、図2(b)は、本発明の一実施の形態における第2レンガパネルの斜視図、図2(c)は、本発明の一実施の形態における横筋レンガブロックの説明図である。 FIG. 2A is a perspective view of a first brick panel according to an embodiment of the present invention, FIG. 2B is a perspective view of a second brick panel according to an embodiment of the present invention, and FIG. ) Is an explanatory diagram of a horizontal brick block according to an embodiment of the present invention.
図2(a)に示すように、第1レンガパネル13は、複数のレンガブロック1を目地モルタルで上下に接着してなり、スラブから天井又は梁に至る高さよりも所定寸法(半割レンガブロック7等の積みしろ)だけ低くなるように全高が定められる。
As shown to Fig.2 (a), the
図2(b)に示すように、第2レンガパネル14は、第1レンガパネル13と同様に、基本的には、複数のレンガブロック1を目地モルタルで上下に接着してなるが、このようなブロック群をさらに幅方向に並べてなる点が第1レンガパネル13とは異なる。
As shown in FIG. 2 (b), the
また、上下に接着されるブロックがレンガブロック1のみならず、その一部には、所定間隔をあけて、横筋レンガブロック5が挿入され、図2(c)に示すように、横筋レンガブロック5には、横筋12が配筋用溝6が入れられ、配筋用溝6はモルタルが充填される。これにより、2本のレンガブロックの柱がブロックの長手方向に剛結される。また、第2レンガパネル14の全高は、スラブから窓枠に至る高さよりも所定寸法(半割レンガブロック7等の積みしろ)だけ低くなるように定められる。なお、図示していないが、最上段のレンガブロック1から上向きに、又、再下段のレンガブロック1から下向きに、第2孔3、9から差筋を延出させ、この差筋により、レンガパネルを点状に支持すると、振動などを吸収できて、好適である。
In addition to the
なお、隣接するレンガブロックの柱の間にモルタル目地を設けるのが望ましい。図2(a)、図2(b)に示される第1、第2レンガパネル13、14は、所定の寸法系となるように、工場で予め製造されるものであり、それぞれ、クレーン等により釣られて現場へ配置される。
In addition, it is desirable to provide a mortar joint between columns of adjacent brick blocks. The first and
次に、図3及び図4を参照しながら、以上のように工場で製造された、第1レンガブロック13、第2レンガブロック14、半割レンガブロック7等を使用した、レンガパネル壁の構築工程を説明する。
Next, referring to FIG. 3 and FIG. 4, construction of a brick panel wall using the
ここで、図3(a)〜図3(e)は、本発明の一実施の形態におけるレンガパネル壁の構築工程説明図、図4は、本発明の一実施の形態におけるレンガパネル壁の組立工程説明図である。 Here, FIGS. 3 (a) to 3 (e) are diagrams for explaining a construction process of a brick panel wall in one embodiment of the present invention, and FIG. 4 is an assembly of the brick panel wall in one embodiment of the present invention. It is process explanatory drawing.
まず、図3(a)に示すように、レンガパネル壁を構築すべきラインを設定し、このラインに沿って半割レンガブロック7を並べてゆく。この際、スラブから上向きに差筋が延出しているので、差筋を第1孔8、第3孔10に通しておく。
First, as shown to Fig.3 (a), the line which should build a brick panel wall is set, and the
次に、図3(b)に示すように、間取りにあわせて第1レンガパネル13、第2レンガパネル14を、並べた半割レンガブロック7の上に配置する。このとき、窓を設ける箇所の下部には第2レンガパネル14を配置し、そうでない箇所には、第1レンガパネル13を配置する。
Next, as shown in FIG.3 (b), the
そして、図3(c)及び図4に示すように、組みあがるパネル群の両袖に、角材19(レンガパネルをいためないようにするため、レンガと等しい幅、例えば、100mm角程度とするのが望ましい)を立て、レンガパネル同士の目地に適宜セパレータ15を挿入し、バタ角材16を水平に何段か掛け渡し、端部を角材19に連結する。バタ角材16の手前側にクサビ付当金17を、奥側に当金18を、それぞれ配置し、これらの当金17、18により、バタ角材16により組みあがるパネル群を、両側から挟んで締め付ける。
And as shown in FIG.3 (c) and FIG.4, it is set as the width | variety equal to a brick, for example, about 100 mm square, in order to avoid damaging a brick panel in the both sleeves of the panel group to assemble. The
さらに、図3(d)に示すように、サポートを斜めに配置し、バタ角材16ごと組みあがるパネル群を仮固定するのが望ましい。図4に示すパネル群は、組上がると、図5に示すような状態となる。
Further, as shown in FIG. 3D, it is desirable that the support is disposed obliquely and the panel group assembled together with the butterfly
同時に、上層階へのコンクリート壁、上層階のスラブ、梁等を構築するため、図3(e)に示すように、型枠を組み、支柱で型枠を支持する。そして、上層階側から下向きに差筋を延出させ、第1レンガパネル13から上向きに延出する縦筋11に臨ませる。
At the same time, in order to construct a concrete wall to the upper floor, a slab, a beam and the like of the upper floor, as shown in FIG. Then, the difference bars are extended downward from the upper floor side, and face the
そして、図8及び図10に示すように、レンガパネル壁の最下層において、第1レンガパネル13及び第2レンガパネル14から下向きに延出する縦筋11と、スラブからこの縦筋11に臨む差筋とを固定する。また、レンガパネル壁の最上層において、第1レンガパネル13から上向きに延出する縦筋11と、上層階の天井又は梁からこの縦筋11に臨む差筋とを固定する。これらの固定は、溶接によるのが望ましいが、強度的に問題なければ他の固定手段によっても良い。
And in the lowest layer of a brick panel wall, as shown in FIG.8 and FIG.10, the
固定が済んだら、組みあがるパネル群の上(最上層)にも、半割レンガ7を積み、適宜モルタル充填を行う。さらに、半割レンガ7の上端と天井又は梁の間に隙間ができるときは、この隙間もモルタル充填により塞ぐ。
After fixing, the
以上により、窓なしの箇所では、第1レンガパネル13を中核とするレンガパネル壁が天井又は梁まで形成されたことになる。一方、窓ありの箇所では、第2レンガパネル14が立てられている。
As described above, a brick panel wall having the
本形態では、さらに図10に示すように、第2レンガパネル14の奥側に骨組みを設け、この骨組みに水平なアングル鋼26を固定し、アングル鋼6に大型窓23あるいは小型窓25の窓枠を固定している。窓枠には、第2レンガパネル14の前側に延びる水切金物27を設けるのが防水性を保持するため望ましい。
In this embodiment, as shown in FIG. 10, a frame is provided on the back side of the
なお、図9に拡大して示しているように、上下に組まれるレンガブロック同士の隙間は、この隙間に挿入されるネオプレーンゴム28と、さらにその外側を充填するモルタル目地29により封鎖するのが望ましい。こうすると、レンガパネル同時の分離が容易になり、ネオプレーンゴム28の後方の空間が地震時の変形を吸収するので、好ましい。
In addition, as shown in an enlarged view in FIG. 9, the gap between the brick blocks assembled vertically is sealed with a
図6は、本発明の一実施の形態におけるレンガパネル壁の構築例示図である。この例では、スラブ20から柱20が立ち、柱20には梁22が連結されており、スラブ20、柱21及び梁22に囲まれた箇所にレンガパネル壁が構築されている。このレンガパネル壁には、大型窓23が嵌め込まれている。
FIG. 6 is a construction example diagram of a brick panel wall in one embodiment of the present invention. In this example, a
図7は、他のレンガパネル壁の構築例示図である。この例では、小型窓25及び扉24を含む、レンガパネル壁が構築されている。
FIG. 7 is an example of construction of another brick panel wall. In this example, a brick panel wall including a
図11は、さらに他のレンガパネル壁の構築例示図である。この例では、小型窓25を含む、レンガパネル壁が構築されているが、小型窓25は、天井又は梁まで至らない。この場合、アングル鋼26を支持し、さらに第1レンガパネル13の上部、小型窓25及び天井又は梁により囲まれた空間に、枠30が嵌め込まれ、枠30はアングル鋼26に固定される。そして、枠30に、耐火ボードが固定されることにより、この空間が封鎖されている。
FIG. 11 is a construction example of still another brick panel wall. In this example, a brick panel wall including a
図6、図7及び図11を注意深く見れば明らかなように、半割レンガ7等を取り外せば、第1レンガパネル13及び第2レンガパネル14のレイアウトを自由に変更できる点が理解されよう。この変更により、インフィルを、住居の所有者の変更、家族構成の変化、好みの変化等に合わせて、現実的に対応できるものである。
It will be understood that the layout of the
このような対応を可能とするだけでなく、第1レンガパネル13及び第2レンガパネル14は、変更に際してもほとんどそのまま再利用が可能である。しかも、現場でレンガを一つずつ手積みする場合と同じ優れた外観及び耐久性が得られるだけでなく、現場でレンガを一つずつ手積みする場合に比べ、本形態によれば、現場で構築に要する手間及び時間を大幅に削減できる。
In addition to enabling such a response, the
以上の説明では、共用廊下部分にレンガパネル壁を構築するケースを取り扱った。しかしながら、本発明は、これに限定されるわけではない。 In the above description, the case of building a brick panel wall in the shared corridor was handled. However, the present invention is not limited to this.
次に、図12〜図14を参照しながら、妻側のレンガパネル壁を構築する方法を説明する。 Next, a method for constructing a wife-side brick panel wall will be described with reference to FIGS.
この方法の要点((1)〜(4))は、次のとおりである。 The main points ((1) to (4)) of this method are as follows.
(1)下層階に形成されているスラブから、下層階から上層階に至る柱の間に、柱に対して隙間をあけて、起立する妻側のレンガパネル壁を構築する。 (1) Build a wife-side brick panel wall that stands between the pillars from the lower floor to the upper floor, with a gap between the pillars from the lower floor to the upper floor.
(2)それぞれ複数のレンガブロックを組み合わせてなる、複数のレンガパネルであって厚さ方向に貫通する孔を有するものを用意する。 (2) Prepare a plurality of brick panels each having a plurality of brick blocks and having holes penetrating in the thickness direction.
図12に示す第3レンガパネル40がこのレンガパネルである。第3レンガパネル40は、概ね第2レンガパネル14と似ている。即ち、最も下部には、第3レンガパネル40を支持する半割レンガ7が敷かれる。そして、レンガブロック1と、適宜間隔をあけて横筋レンガブロック5とが、組み合わされる。
The
しかしながら、第3レンガパネル40は、第2レンガパネル14よりも巾及び高さのいずれもが大となるように、大型に形成される。ここで言う「大型」とは、概略一階層分の高さ・巾を持つという意味である。また、図12に示すものでは窓が設けられていないが、図13(b)に示すように、必要に応じて、第3レンガパネル40’の内部に窓41を設けることができる。
However, the
上述の孔は、セパレータ15を厚さ方向に貫通させるために、所定個数所定の箇所にあけられている。窓41を設けるか否かで、孔の箇所を変更しても差し支えない。孔は、目地になる箇所に設けるのが望ましい。
The above-described holes are opened at a predetermined number of predetermined positions so as to penetrate the
(3)複数のレンガパネルを起立させてレンガパネル壁を構築するとともに、孔にセパレータを通し、起立するレンガパネル壁を仮設固定材により、挟んで締め付ける。 (3) A brick panel wall is constructed by erecting a plurality of brick panels, and a separator is passed through the hole, and the standing brick panel wall is clamped with a temporary fixing material.
(4)図14に示すように、第3レンガパネル40、40’の上部は、上層階の大梁の室外側に位置し、第3レンガパネル40、40’の上部と上層階の大梁との間に断熱材43を介在させる。これにより、第3レンガパネル40、40’は、躯体の構造から力学的に縁切りされることになる。また、断熱材43が躯体の外側に設けられることとなって、大梁のコンクリート面と第3レンガパネル40、40’とは、直接的には接触せず、室内は、断熱材43により外断熱されることになる。なお妻側のレンガパネル壁は、大梁の仮枠となる。
(4) As shown in FIG. 14, the upper part of the
次に、妻側のレンガパネル壁の構築法をさらに詳しく説明する。 Next, the construction method of the brick panel wall on the wife side will be described in more detail.
まず、図14に示すように、下層階の床スラブ35から、更に室外側へ突出する飛び出しスラブ36が形成され、飛び出しスラブ36内には、鉄筋37が配設される。
First, as shown in FIG. 14, a protruding
つまり、図13(a)に示すように、水平な飛び出しスラブ36が巾方向に飛び出して形成される。
That is, as shown in FIG. 13A, a horizontal protruding
次に、下層階から上層階へ至る柱39を形成し、それらの柱39のための型枠が組まれた状態で、第3レンガパネル40、40’の組み込みを開始する。即ち、まず、半割レンガ7を飛び出しスラブ36上に敷設する。
Next, the
クレーンで建物の外から第3レンガパネル40、40’を吊り、半割レンガ7の上に起立するように、第3レンガパネル40、40’を組み込む。
The
第3レンガパネル40、40’と柱39との間には、レンガ1枚分の隙間をあけておく。これにより、柱39のための型枠と第3レンガパネル40、40’とが干渉しないようにすることができる。
A gap corresponding to one brick is left between the
また、吊り込まれた第3レンガパネル40、40’に開けられた孔にセパレータ15を貫通させ、バタ角材16を第3レンガパネル40、40’に水平に当て、セパレータ15の両端部に金物を取付け、金物を締め付けることにより、バタ角材16と第3レンガパネル40、40’とを一体化する。さらに、バタ角材16の室内側に、斜め支柱42を斜めに取付け、斜め支柱42の先端部により、室内側にあるバタ角材16を支持する。
Further, the
図13(a)に示すように、必要な第3レンガパネル40、40’を全てくみ終わったら、図14に示すように、第3レンガパネル40、40’の上部の室内側に、断熱材43を貼り付ける。こうすると、断熱材43は、室内の断熱機能を有するだけでなく、横に並ぶ第3レンガパネル40、40’の間(特に目地の部分)への、コンクリート(上層階の打設用)の漏れを抑止する、型枠の機能をも有する。
As shown in FIG. 13 (a), when all the necessary
断熱材43の取付が済んでから、下層階の床スラブ35上に、支柱44、45を立て、上層階のスラブ用型枠46、大梁用型枠47を組むと共に、これらの型枠46、47を支柱44により支持する。
After the installation of the
第3レンガパネル40、40’の上部外側に、大梁49の高さに合わせて、仮枠を設置し、第3レンガパネル40、40’に開けられている孔にセパレータを貫通させ、大梁用型枠47と第3レンガパネル40、40’の上部とを挟み込んで一体化する。このセパレータは、一体化するための固定力を付与するだけでなく、上層階の大梁49構築のため、コンクリートが打設される際における側圧に耐え、所定間隔を維持する型枠としての機能を有する。
A temporary frame is installed on the outside of the upper part of the
そして、型枠46、47の準備が完了したら、鉄筋を適宜配置し、型枠46、47内へコンクリートを打設し、上層階の床スラブ48及び大梁49を構築する。
When the preparation of the
1 レンガブロック
2 第1孔
3 第2孔
4 第3孔
5 横筋レンガブロック
6 配筋用溝
7 半割レンガ
8 第1溝
9 第2溝
10 第3溝
11 縦筋
11a 差筋
12 横筋
13 第1レンガパネル
14 第2レンガパネル
15 セパレータ
16 バタ角材
17 クサビ付当金
18 当金
19 角材
20 床
21、39 柱
22 梁
23 大型窓
24 扉
25 小型窓
26 アングル鋼
27 水切金物
28 ネオプレーンゴム
29 モルタル目地
30 枠
31 鋼板
32 窓枠
33、41 窓
35、48 床スラブ
36 飛び出しスラブ
40、40’ 第3レンガパネル
42 斜め支柱
43 断熱材
44、45 支柱
46 スラブ用型枠
47 大梁用型枠
49 大梁
DESCRIPTION OF
Claims (7)
それぞれ複数のレンガブロックを組み合わせてなる、複数のレンガパネルを用意する工程と、
前記複数のレンガパネルを起立させてレンガパネル壁を構築するとともに、起立する前記レンガパネル壁を仮設固定材により、挟んで締め付ける工程とを含み、
前記レンガパネル壁の周囲と前記上階層用のスラブ又は大梁との間の少なくとも一部に隙間があけられており、前記上階層用のスラブ又は大梁を形成した後、前記型枠を撤去し、
前記隙間の少なくとも一部をレンガブロックで埋め、
前記仮設固定材を撤去することを特徴とするレンガパネル壁の構築方法。 A method of constructing a standing brick panel wall from a slab formed on a lower floor toward a formwork assembled to form a slab or upper beam for an upper floor,
A step of preparing a plurality of brick panels each composed of a plurality of brick blocks;
Building the brick panel wall by raising the plurality of brick panels, and clamping the sandwiched brick panel wall with a temporary fixing material,
A gap is opened in at least a part between the periphery of the brick panel wall and the upper slab or girder, and after forming the upper slab or girder, the formwork is removed,
Fill at least part of the gap with a brick block;
The construction method of the brick panel wall characterized by removing the said temporary fixing material.
前記第1レンガパネルの高さは、前記下層階のスラブから前記上層階用のスラブ又は大梁に至る高さよりも所定寸法だけ低くなるように定められ、前記第1レンガパネルは、縦筋が挿通される孔を有する複数の第1レンガブロックを目地モルタルで上下に接着してなり、
前記第2レンガパネルの高さは、前記下層階のスラブから窓枠に至る高さよりも所定寸法だけ低くなるように定められ、前記第2レンガパネルは、縦筋が挿通される孔を有する複数の第2レンガブロックを目地モルタルで上下に接着してなる複数のレンガブロック群を幅方向に並べ、複数の第2レンガブロックの一部は、幅方向を長手方向とする横筋が挿入される横筋レンガブロックで構成され、
前記第1レンガパネルと前記第2レンガパネルとで囲まれる空間に窓枠を配置し、前記窓枠に窓を設けることを特徴とする請求項1または2記載のレンガパネル壁の構築方法。 The plurality of brick blocks include a first brick panel and a second brick panel,
The height of the first brick panel is determined to be lower by a predetermined dimension than the height from the slab on the lower floor to the slab or upper beam for the upper floor, and the first brick panel has a vertical line inserted through it. A plurality of first brick blocks having holes to be bonded up and down with joint mortar,
The height of the second brick panel is determined to be lower by a predetermined dimension than the height from the slab on the lower floor to the window frame, and the second brick panel has a plurality of holes through which vertical bars are inserted. A plurality of brick block groups formed by adhering the second brick blocks vertically with joint mortar are arranged in the width direction, and a part of the plurality of second brick blocks is inserted with a horizontal line having the width direction as a longitudinal direction. Consists of brick blocks,
The construction method of a brick panel wall according to claim 1 or 2, wherein a window frame is arranged in a space surrounded by the first brick panel and the second brick panel, and a window is provided in the window frame.
配置された前記半割レンガブロック上に前記複数のレンガパネルを起立させることを特徴とする請求項1から4のいずれかに記載のレンガパネル壁の構築方法。 Prior to erecting the plurality of brick panels, a pair of half brick blocks having a shape in which the brick blocks are vertically cut along the longitudinal center line at positions where the plurality of brick panels should be erected on the slab of the lower floor. Place several,
The method for constructing a brick panel wall according to any one of claims 1 to 4, wherein the plurality of brick panels are erected on the arranged half brick blocks.
それぞれ複数のレンガブロックを組み合わせてなる、複数のレンガパネルであって厚さ方向に貫通する孔を有するものを用意する工程と、
前記複数のレンガパネルを起立させてレンガパネル壁を構築するとともに、前記孔にセパレータを通し、起立する前記レンガパネル壁を仮設固定材により、挟んで締め付ける工程とを含むことを特徴とするレンガパネル壁の構築方法。 A method of constructing a standing brick panel wall on a wive side between pillars from the lower floor to the upper floor from the slab formed on the lower floor,
A step of preparing a plurality of brick panels each having a hole penetrating in the thickness direction, each formed by combining a plurality of brick blocks;
And a step of building a brick panel wall by erecting the plurality of brick panels, passing a separator through the hole, and sandwiching and tightening the standing brick panel wall with a temporary fixing material. How to build a wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009136221A JP5231338B2 (en) | 2009-06-05 | 2009-06-05 | How to build a brick panel wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009136221A JP5231338B2 (en) | 2009-06-05 | 2009-06-05 | How to build a brick panel wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2010281135A JP2010281135A (en) | 2010-12-16 |
JP5231338B2 true JP5231338B2 (en) | 2013-07-10 |
Family
ID=43538093
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2009136221A Active JP5231338B2 (en) | 2009-06-05 | 2009-06-05 | How to build a brick panel wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5231338B2 (en) |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62202149A (en) * | 1986-02-28 | 1987-09-05 | 旭化成株式会社 | Method for mounting room partitioning wall |
JP3328252B2 (en) * | 1999-12-10 | 2002-09-24 | 有限会社福永博建築研究所 | Low-level walls for apartment balconies |
-
2009
- 2009-06-05 JP JP2009136221A patent/JP5231338B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2010281135A (en) | 2010-12-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102449246B (en) | Building and method of constructing a building | |
TW201022503A (en) | Unitised building system | |
US3678638A (en) | Building construction of modular units with settable material therebetween | |
ES2969483T3 (en) | Building construction procedure | |
RU2376424C1 (en) | Ready-built and solid-cast building construction system | |
CN103821229A (en) | Rapid assembly type integrated house and installation method | |
CN111456252A (en) | Steel assembled synthetic concrete building and construction method thereof | |
CN106958293A (en) | A kind of big plate prefabricated buildings and its assembly and disassembly methods | |
ES2333636B1 (en) | PRE-MANUFACTURED SEMIRRESISTENT MODULE FOR CONSTRUCTION AND PROCEDURE ASSEMBLY ON THE WORK OF THE SAME. | |
CN110612373A (en) | Prefabricated pre-decorated volume construction of buildings | |
RU2399731C1 (en) | Method for erection of multilayer building wall, which is self-bearing within floor | |
JP4976938B2 (en) | Seismic reinforcement structure | |
JP5302441B2 (en) | Construction method of concrete container house | |
JP5231338B2 (en) | How to build a brick panel wall | |
CN212295078U (en) | Steel assembled synthetic concrete building | |
KR101086060B1 (en) | Prefebrication module | |
RU2634139C1 (en) | Framework universal prefabricated architectural and construction system | |
JP5433035B2 (en) | Seismic reinforcement structure | |
RU89859U1 (en) | FRAME-PANEL BUILDING | |
US20220235547A1 (en) | Steel and concrete building module and connections | |
RU2699092C1 (en) | Frame-panel construction system | |
BRPI1103773A2 (en) | constructive process of modular units and modular units thus obtained | |
JP5588653B2 (en) | How to renovate unit buildings | |
WO1991012386A1 (en) | Modular buildings | |
RU2609035C2 (en) | Carcass unit for modular construction of buildings and system of such blocks |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20120215 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20130215 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20130306 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20130321 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160329 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5231338 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |