JP5074254B2 - Temporary water supply installation structure and installation method - Google Patents

Temporary water supply installation structure and installation method Download PDF

Info

Publication number
JP5074254B2
JP5074254B2 JP2008074861A JP2008074861A JP5074254B2 JP 5074254 B2 JP5074254 B2 JP 5074254B2 JP 2008074861 A JP2008074861 A JP 2008074861A JP 2008074861 A JP2008074861 A JP 2008074861A JP 5074254 B2 JP5074254 B2 JP 5074254B2
Authority
JP
Japan
Prior art keywords
water supply
temporary
supply pipe
water
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2008074861A
Other languages
Japanese (ja)
Other versions
JP2009228299A (en
Inventor
弘泰 正野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Homes Corp
Original Assignee
Asahi Kasei Homes Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Homes Corp filed Critical Asahi Kasei Homes Corp
Priority to JP2008074861A priority Critical patent/JP5074254B2/en
Publication of JP2009228299A publication Critical patent/JP2009228299A/en
Application granted granted Critical
Publication of JP5074254B2 publication Critical patent/JP5074254B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Domestic Plumbing Installations (AREA)

Description

本発明は、建物の建築工事中に使用する上水を供給するための仮設給水設備に関するものである。   The present invention relates to a temporary water supply facility for supplying clean water used during building construction of a building.

一般に住宅等の建物の工事中には、工事に使用する上水を供給するための仮設給水設備が敷地内に設けられる。仮設給水設備は、前面道路に埋設されている水道本管から給水管(本管側給水管)を分岐し敷地内に引き込み、敷地内の所定の位置(本設される位置)に量水器ボックスを埋め込み、量水器ボックス内部に導入した給水管(本管側給水管)に仮設給水管を接続し、更に仮設給水管の他端に仮設水栓を接続して構成される。   In general, during construction of a building such as a house, a temporary water supply facility for supplying clean water used for the construction is provided on the site. Temporary water supply facilities branch water supply pipes (main water supply pipes) from the water mains buried in the front road and draw them into the site. A temporary water supply pipe is connected to a water supply pipe (main water supply pipe) introduced into the water meter box and a temporary water tap is connected to the other end of the temporary water supply pipe.

一方、敷地の前面道路に隣接した領域の床面(地表面)は、カーポートや建物へのアプローチとして利用する為に、土間コンクリートを打設したうえでモルタルやタイル等で仕上げたり、地業の後にインターロッキングブロック等が敷き詰めて仕上げたりするのが一般的である。特に建物が都市部に立地する場合、前面道路に隣接した領域は、土がむき出しとなった部分を残すことなく上記のような床仕上げが施されることが多い。   On the other hand, the floor (ground surface) in the area adjacent to the front road of the site is finished with mortar, tiles, etc. after placing soil concrete to be used as an approach to carports and buildings. In general, an interlocking block or the like is laid down and finished. In particular, when the building is located in an urban area, the area adjacent to the front road is often subjected to the floor finish as described above without leaving a portion where the soil is exposed.

量水器は敷地内の前面道路寄りの位置に設置することが義務付けられているので、上記の場合、量水器(量水器ボックス)の周囲やこれに接続される給水管の上方の床面も仕上げがなされることになる。そして、建物の建築工事の完了直前には、仮設給水設備(仮設給水管及び仮設水栓)を撤去し、建物側給水管と本管側給水管とを量水器ボックス内部にて量水器を介して接続する作業が発生する。   Since the water meter is obliged to be installed near the front road in the site, in the above case, the floor around the water meter (meter box) and above the water pipe connected to it. The surface will also be finished. Immediately before the completion of the building construction of the building, the temporary water supply equipment (temporary water supply pipe and temporary water tap) is removed, and the water supply pipe is installed inside the water supply box with the building side water supply pipe and the main side water supply pipe. Work to connect through the.

建物側給水管と本管側給水管は、互いに接続されていない状態ではその端部が固定されないので相対的な位置関係が安定しないが、両者が互いに接続されることにより相対的な位置が確定しその関係が保持される。従って、上記接続作業が完了しなければ、給水管(少なくとも一方の給水管)の上方の床面の仕上げ工事に取りかかることができなかった。換言すると、給水工事が完了しなければ外構工事に着手できなかった。   The end of the water supply pipe on the building side and the main water supply pipe is not fixed because they are not connected to each other, so the relative positional relationship is not stable, but the relative position is determined by connecting them together. The relationship is maintained. Therefore, if the connection work is not completed, it is not possible to start the finishing work for the floor surface above the water supply pipe (at least one of the water supply pipes). In other words, the external work could not be started unless the water supply work was completed.

この為、建物工事着手から外構工事完了までの全体の工期の短縮化が困難、あるいは、給水工事完了前に外構工事に着手しても建物側給水管の上方の床面の仕上げ工事を行うことができず手待ちが発生する、という問題があった。   For this reason, it is difficult to shorten the overall construction period from the start of building construction to the completion of external construction work, or even if the external construction work is started before the completion of water supply work, finishing work on the floor above the water supply pipe on the building side There was a problem that it was not possible to carry out and waiting was generated.

なお、特許文献1には、地面に埋め込まれた消火栓や散水栓から応急給水や仮設給水を行う為の簡易給水栓セットに関する技術が開示されている。しかし、この技術は職種の異なる給水工事と外構工事とが絡むことにより発生する上記のような問題を解決しうるものではない。   Patent Document 1 discloses a technique related to a simple water faucet set for performing emergency water supply or temporary water supply from a fire hydrant or a water spigot embedded in the ground. However, this technology cannot solve the above-mentioned problems that occur when water supply works and exterior works involving different occupations are involved.

本発明は、上記従来技術の課題を解決し、給水工事と外構工事との交錯を可及的に低減することによって工期の短縮化を図り得る仮設給水設備の設置構造及びその設置方法を提供することを目的とするものである。   The present invention solves the above-mentioned problems of the prior art, and provides an installation structure of a temporary water supply facility and an installation method thereof that can shorten the construction period by reducing the crossover between water supply work and exterior work as much as possible It is intended to do.

上記従来技術の課題を解決する為の本発明に係る仮設給水設備の設置構造の第1の構成は、本設位置に埋設された埋め込み式の量水器ボックスと、本設位置に埋設され、前記量水器ボックス内に導入された本管側給水管及び建物側給水管と、前記量水器ボックス内に設置され、前記本管側給水管と前記建物側給水管が接続された仮設接続部材と、前記仮設接続部材の本管側給水管接続部と建物側給水管接続部との中間部から分岐した分岐管接続部に接続された仮設水栓と、からなり、前記本管側給水管接続部と前記建物側給水管接続部は、本設される量水器の2つの給水管接続部と同一の接続形状と同一の離間寸法を有し、前記本管側給水管接続部から供給された水は前記分岐管接続部方向にのみ導かれることを特徴とする。なお、ここで接続とは、直接的につなぎ合わせること以外に、他の部材を介して間接的につなぎ合わせることも含む概念である(以下同様)。   The first configuration of the temporary water supply facility installation structure according to the present invention for solving the above-described problems of the prior art is an embedded water meter box embedded in the main installation position, embedded in the main installation position, Temporary connection in which the main water supply pipe and the building side water supply pipe introduced into the water meter box and the main water supply pipe and the building side water supply pipe are connected to each other. And a temporary faucet connected to a branch pipe connecting part branched from an intermediate part between the main side water supply pipe connecting part and the building side water supply pipe connecting part of the temporary connecting member. The pipe connection part and the building-side water supply pipe connection part have the same connection shape and the same spacing as the two water supply pipe connection parts of the water meter to be installed, and from the main pipe-side water supply pipe connection part The supplied water is guided only in the direction of the branch pipe connecting portion. Here, the term “connection” is a concept including not only directly connecting but also indirectly connecting through another member (the same applies hereinafter).

本発明に係る仮設給水設備の設置構造の第2の構成は、前記第1の構成において、前記仮設水栓は、仮設量水器と可撓性を有するフレキシブル管からなる仮設給水管とを介して前記分岐管接続部に接続され、前記仮設水栓と仮設量水器は、前記量水器ボックスの上方に配置され、前記量水器ボックスは、本設蓋が取り外され、前記本設蓋と同一の外形を有し前記仮設給水管取り出しの為の切り欠き部が設けられ、前記仮設量水器、前記仮設給水管及び前記仮設水栓が接続された状態で開閉自在な仮設蓋を備えたことを特徴とする。   According to a second configuration of the temporary water supply facility installation structure according to the present invention, in the first configuration, the temporary water tap is provided via a temporary water meter and a temporary water supply pipe including a flexible flexible tube. The temporary water faucet and the temporary water meter are disposed above the water meter box, and the water meter box has its main lid removed, and the permanent lid And a temporary lid that is openable and closable in a state in which the temporary metering water device, the temporary water supply pipe, and the temporary water faucet are connected to each other. It is characterized by that.

本発明に係る仮設給水設備の設置構造の第3の構成は、前記第2の構成において前記仮設蓋の上面は、虎縞状に彩色されたことを特徴とする。   The third configuration of the temporary water supply facility installation structure according to the present invention is characterized in that, in the second configuration, the upper surface of the temporary lid is colored in a tiger stripe shape.

本発明に係る仮設給水設備の設置方法の構成は、量水器及び量水器ボックスが埋設される敷地における仮設給水設備の設置方法であって、本設される量水器の2つの給水管接続部と同一形状かつ同一離間寸法の2つの給水管接続部と前記2つの給水管接続部の中間部から分岐した分岐管接続部とを有するとともに一方の給水管への給水が遮断された仮設接続部材を用いて前記量水器ボックス内で本管側給水管と建物側給水管とを接続し、前記分岐管接続部に仮設給水管を接続して前記量水器ボックスの上方に立ち上げ、前記本管側給水管から仮設給水管方向にのみ給水し得るように前記仮設給水管に仮設水栓を接続したことを特徴とする。   The configuration of the temporary water supply facility installation method according to the present invention is a temporary water supply facility installation method in a site where a water meter and a water meter box are embedded, and two water pipes of the water meter to be installed Temporary construction having two water supply pipe connection parts having the same shape and the same spacing as the connection part and a branch pipe connection part branched from an intermediate part of the two water supply pipe connection parts, and water supply to one water supply pipe is interrupted A main water supply pipe and a building water supply pipe are connected in the water meter box using a connecting member, and a temporary water supply pipe is connected to the branch pipe connection portion, and the water meter box is raised above the water meter box. A temporary faucet is connected to the temporary water supply pipe so that water can be supplied only from the main water supply pipe to the temporary water supply pipe.

本発明に係る仮設給水設備の設置構造の第1の構成及び本発明に係る仮設給水設備の設置方法によれば、本管側給水管と建物側給水管とを量水器ボックス内で仮設接続部材を介して接続し、仮設接続部材に接続した仮設水栓によって工事中に必要な水を供給するように構成したので、両者の位置関係が外構工事等の影響によって狂うことがなく、仮設接続部材及び仮設水栓を取り外した後、給水管及び量水器ボックスの位置を調整することなく量水器を容易に接続することができる。従って、仮設接続部材及び仮設水栓を取り外しや量水器の接続を待たずに給水管や量水器ボックス周囲の外構工事を行うことができ、工期の短縮化や手間、コストの低減をはかることができる。   According to the first configuration of the temporary water supply facility installation structure according to the present invention and the temporary water supply facility installation method according to the present invention, the main water supply pipe and the building side water supply pipe are temporarily connected in the water meter box. Because it is configured to supply necessary water during construction by a temporary faucet connected to the temporary connection member, the positional relationship between the two will not be upset by the influence of external work, etc. After removing the connecting member and the temporary water faucet, the water meter can be easily connected without adjusting the positions of the water supply pipe and the water meter box. Therefore, it is possible to perform external work around the water supply pipe and the water meter box without removing the temporary connection member and the temporary water faucet and waiting for the connection of the water meter, thereby shortening the construction period and reducing labor and cost. Can measure.

本発明に係る仮設給水設備の設置構造の第2の構成によれば、仮設接続部材に対し仮設量水器及び仮設水栓を可撓性を有するフレキシブル管からなる仮設給水管を介して接続するとともに、量水器ボックスの上面は切り欠き部を備えた仮設蓋でカバーしたので、仮設接続部材に仮設給水管、仮設量水器及び仮設水栓を接続した後に仮設蓋の切り欠き部の位置に合わせて仮設給水管の位置や形状を調整することで仮設蓋を閉じることができ、更に仮設蓋を閉じた後に仮設量水器及び仮設水栓の位置を作業の邪魔にならない適正な位置に移動しその状態を保持することができる。従って、工事中の作業者の安全性を高めることができ、量水器ボックス内部への土砂やコンクリートの流入を防止することもでき、更には仮設量水器の検針も容易に行うことができる。
本発明に係る仮設給水設備の設置構造の第3の構成によれば、虎縞状の彩色によって突出した仮設水栓や仮設量水器の存在を作業者に知らしめることができ、作業の安全性を更に高めることができる。
According to the 2nd structure of the installation structure of the temporary water supply equipment which concerns on this invention, a temporary quantity water device and a temporary water tap are connected with respect to a temporary connection member via the temporary water supply pipe which consists of a flexible pipe which has flexibility. In addition, since the upper surface of the water meter box is covered with a temporary lid provided with a notch portion, the position of the notch portion of the temporary lid after the temporary water supply pipe, the temporary water meter and the temporary water tap are connected to the temporary connection member. The temporary lid can be closed by adjusting the position and shape of the temporary water supply pipe according to the conditions, and after the temporary lid is closed, the temporary water dispenser and the temporary faucet are positioned in an appropriate position that does not interfere with the work. It can move and hold its state. Therefore, it is possible to improve the safety of workers during the construction, to prevent the inflow of earth and sand and concrete into the water meter box, and to easily perform the meter reading of the temporary water meter. .
According to the 3rd structure of the installation structure of the temporary water supply equipment which concerns on this invention, the presence of the temporary water tap and the temporary watering device which protruded with the tiger stripe-like coloring can be notified to an operator, and safety of work The sex can be further enhanced.

本発明に係る仮設給水設備の設置構造の好ましい実施形態について図を用いて説明する。図1は敷地、前面道路、建物等の配置を示す配置図、図2は量水器まわりの構成を示す図、図3は仮設接続部材の図である。   A preferred embodiment of an installation structure of a temporary water supply facility according to the present invention will be described with reference to the drawings. FIG. 1 is a layout diagram showing the layout of a site, a front road, buildings, etc., FIG. 2 is a diagram showing a configuration around a water meter, and FIG. 3 is a diagram of a temporary connection member.

図1に示すように、戸建住宅である建物Bが建築される敷地Aは前面道路Cに面しており、建物Bは敷地Aの奥寄りに配置されている。敷地Aの前面道路C寄りの領域は、カーポート及び建物Bへのアプローチとして利用される為、外構工事において、土間コンクリートが打設されたのち、タイルやモルタル等によって仕上げが施される。   As shown in FIG. 1, the site A where the building B, which is a detached house, is built faces the front road C, and the building B is arranged at the back of the site A. Since the area close to the front road C of the site A is used as an approach to the carport and the building B, after the soil concrete is placed in the exterior work, finishing is performed with tiles or mortar.

本実施例における仮設給水設備の設置構造は、図1、図2に示すように、本管側給水管2、量水器ボックス3、仕切弁4、仮設接続部材5、建物側給水管6、ボールバルブ7、仮設給水管8、仮設量水器9、仮設水栓10で構成されている。本管側給水管2は、前面道路Cに埋設された水道本管1から分岐され、建物B内部及び敷地A内の給水設備へ上水を供給する為に敷地A内に引き込まれている。   As shown in FIGS. 1 and 2, the installation structure of the temporary water supply facility in the present embodiment includes a main water supply pipe 2, a water meter box 3, a gate valve 4, a temporary connection member 5, a building side water supply pipe 6, It consists of a ball valve 7, a temporary water supply pipe 8, a temporary water meter 9, and a temporary water tap 10. The main water supply pipe 2 is branched from the water main pipe 1 buried in the front road C, and is drawn into the site A to supply clean water to the water supply facilities in the building B and the site A.

量水器ボックス3は、敷地A内の前面道路Cの近傍で検針に支障がない本設位置に、その上面のレベルが床仕上げ面に一致するように埋設されている。量水器ボックス3は、略直方体状であり、本来は本体3a、本設蓋(不図示)及び底板3cからなるものであるが、本設蓋は取り外されており、これに代わって仮設蓋3bが取り付けられている。仮設蓋3bは、本設蓋と同様に一方の長辺側を軸として回動させて開閉するように構成され、他方の長辺側には後述する仮設給水管8の径に対応した切り欠き部3b1が形成されている、そして、仮設蓋3bの上面には虎縞状の彩色が施されている。   The water meter box 3 is embedded in the main position in the vicinity of the front road C in the site A so as not to interfere with the meter reading so that the level of the upper surface coincides with the floor finish surface. The water meter box 3 has a substantially rectangular parallelepiped shape, and is originally composed of a main body 3a, a permanent lid (not shown), and a bottom plate 3c, but the permanent lid has been removed and replaced with a temporary lid. 3b is attached. The temporary lid 3b is configured to open and close by rotating around one long side as an axis similarly to the permanent lid, and a cutout corresponding to the diameter of the temporary water supply pipe 8 described later is formed on the other long side. The portion 3b1 is formed, and the upper surface of the temporary lid 3b is colored with a tiger stripe.

量水器ボックス3の短辺側の面には、本管側給水管導入口3dおよび建物側給水管導入口3eが穿設され、本管側給水管導入口3dには本管側給水管2が、建物側給水管導入口3eには建物側給水管6が夫々導入されている。そして、本管側給水管2の端部には水道本管1からの給水を制御する仕切弁4が接続され、仕切弁4と建物側給水管6とが仮設接続部材5によって接続されている。仕切弁4は弁の開閉により本管側給水管2から給水を制御するものであり、竣工後も本管側給水管2と量水器との間に介在した状態で使用される。また、建物側給水管6は建物B方向に向かって延伸され、途中で適宜分岐されて建物B内外の給水設備に接続されている。   A main-side water supply pipe introduction port 3d and a building-side water supply pipe introduction port 3e are drilled in the short side surface of the water meter box 3, and the main-side water supply pipe introduction port 3d has a main-side water supply pipe. 2, building-side water supply pipes 6 are respectively introduced into the building-side water supply pipe introduction ports 3 e. And the gate valve 4 which controls the water supply from the water main pipe 1 is connected to the edge part of the main pipe side water supply pipe 2, and the gate valve 4 and the building side water supply pipe 6 are connected by the temporary connection member 5. . The gate valve 4 controls water supply from the main water supply pipe 2 by opening and closing the valve, and is used in a state of being interposed between the main water supply pipe 2 and the water meter after completion. Moreover, the building-side water supply pipe 6 is extended toward the building B direction, and is appropriately branched on the way to be connected to water supply facilities inside and outside the building B.

図3に示す仮設接続部材5は、給水管の配管工事と器具付けが完了した後、接続部からの漏水が発生しないかを確認する際に使用する水圧テスト用チーズ(株式会社日邦バルブ社製の「砲金製接続管」等)を転用したものである。仮設接続部材5は、T字状の継手部材(チーズ)であり、本管側給水管接続部5aと建物側給水管接続部5bとの中間部に、分岐管接続部5cを有している。本管側給水管接続部5aと建物側給水管接続部5bは、本設される量水器の両端の給水管接続部(不図示)と同一の形状、同一の離間寸法を有している。従って、仮設接続部材5によって接続された本管側給水管2と建物側給水管6との相対的位置関係は、量水器によって接続された場合と同一の状態に維持される。   The temporary connection member 5 shown in FIG. 3 is a hydraulic pressure test cheese (Nihon Valve Co., Ltd.) used for checking whether or not water leakage from the connection portion occurs after the plumbing and installation of the water supply pipe are completed. "Gunmetal connecting pipe" etc.). The temporary connection member 5 is a T-shaped joint member (cheese), and has a branch pipe connection part 5c at an intermediate part between the main water supply pipe connection part 5a and the building side water supply pipe connection part 5b. . The main-side water supply pipe connection portion 5a and the building-side water supply pipe connection portion 5b have the same shape and the same spacing as the water supply pipe connection portions (not shown) at both ends of the water meter provided. . Therefore, the relative positional relationship between the main-side water supply pipe 2 and the building-side water supply pipe 6 connected by the temporary connection member 5 is maintained in the same state as that when connected by the water meter.

仮設接続部材5の建物側給水管接続部5bは建物側給水管6に接続されるが、本管側給水管2の方向から給水された場合、建物側給水管6の方向への給水は遮断され、分岐管接続部5c方向にのみ給水されるような内部構成となっている。   The building-side water supply pipe connection portion 5b of the temporary connection member 5 is connected to the building-side water supply pipe 6. However, when water is supplied from the main-side water supply pipe 2, the water supply in the direction of the building-side water supply pipe 6 is cut off. The internal structure is such that water is supplied only in the direction of the branch pipe connecting portion 5c.

分岐管接続部5cには、レバーハンドル付のボールバルブ7が接続され、更にボールバルブ7には可撓性を有するフレキシブル管からなる仮設給水管8が接続されている。仮設給水管8は仮設蓋3bの切り欠き部3b1から量水器ボックス3の外部に取り出されている。仮設給水管8の中途には仮設量水器9が接続され、末端には仮設水栓10が接続されている。仮設水栓10は、所謂埋め込み式散水栓であり、蛇口が水平線に対し略45度の角度で上向きに屈曲したものである。仮設給水管8は適宜屈曲されて、仮設給水管8、仮設量水器9、仮設水栓10のすべてが平面的に量水器ボックス3からはみ出すことがないようにコンパクトにまとめられている。なお、ここで仮設量水器9は本設される量水器と同一のものである。仮設量水器とは、仮設専用の量水器という意味ではなく仮設状態の量水器という意味である。   A ball valve 7 with a lever handle is connected to the branch pipe connecting portion 5c, and a temporary water supply pipe 8 made of a flexible pipe having flexibility is connected to the ball valve 7. The temporary water supply pipe 8 is taken out of the water meter box 3 from the cutout portion 3b1 of the temporary lid 3b. A temporary water meter 9 is connected in the middle of the temporary water supply pipe 8, and a temporary water tap 10 is connected to the end. The temporary faucet 10 is a so-called embedded water spigot, and a faucet is bent upward at an angle of approximately 45 degrees with respect to the horizontal line. The temporary water supply pipe 8 is appropriately bent so that the temporary water supply pipe 8, the temporary water meter 9, and the temporary water tap 10 are all compactly arranged so as not to protrude from the water meter box 3 in a plane. Here, the temporary water meter 9 is the same as the water meter provided here. The temporary water meter means not a temporary water meter, but a temporary water meter.

上記のような構成とする場合、仮設接続部材5に仮設給水管8、仮設量水器9及び仮設水栓10を接続した後に、仮設給水管8の位置や形状を調整して切り欠き部3b1の位置に合わせ、仮設給水管8、仮設量水器9及び仮設水栓10と干渉することがないように仮設蓋3bを閉じ、仮設給水管8、仮設量水器9及び仮設水栓10の位置を上記のように設定することができる。   In the case of the above configuration, after connecting the temporary water supply pipe 8, the temporary water meter 9 and the temporary water tap 10 to the temporary connection member 5, the position and shape of the temporary water supply pipe 8 are adjusted to make the cutout portion 3 b 1. The temporary lid 3b is closed so as not to interfere with the temporary water supply pipe 8, the temporary water meter 9 and the temporary water tap 10, and the temporary water pipe 8, the temporary water meter 9 and the temporary water tap 10 are The position can be set as described above.

上記構成の仮設給水設備は、建物Bの建築工事及び外構工事の期間中使用される。そして、竣工間近に仮設接続部材5、ボールバルブ7、仮設給水管8、仮設量水器9、仮設水栓10、仮設蓋3bが取り外され、これらに代わって量水器と本設蓋が取り付けられて竣工を迎える。   The temporary water supply system having the above-described configuration is used during the construction work and exterior work of the building B. Then, the temporary connection member 5, the ball valve 7, the temporary water supply pipe 8, the temporary water meter 9, the temporary water tap 10, and the temporary cover 3b are removed near the completion of the construction, and the water meter and the main cover are attached instead. It will be completed.

本管側給水管接続部5aと建物側給水管接続部5bは、本設される量水器の2つの給水管接続部と同一の形状、同一の離間寸法を有する仮設接続部材5によって接続された状態で本設位置に埋設されており、相対的な位置関係が変わることはないので、量水器を本設する際に本管側給水管2および建物側給水管6の位置を再調整する必要がない。従って、給水工事の完了(量水器の接続)を待たずに本管側給水管2、建物側給水管6及び量水器ボックス3の周囲の外構工事を完成させることができる。   The main water supply pipe connection portion 5a and the building side water supply pipe connection portion 5b are connected by a temporary connection member 5 having the same shape and the same distance as the two water supply pipe connection portions of the water meter to be installed. Since the relative position is not changed, the positions of the main water supply pipe 2 and the building side water supply pipe 6 are readjusted when the water meter is installed. There is no need to do. Therefore, the external construction around the main water supply pipe 2, the building water supply pipe 6, and the water meter box 3 can be completed without waiting for the completion of the water supply work (connection of the water meter).

また、量水器ボックス3には工事中も仮設蓋3bが装着されているので、作業者が誤って足を量水器ボックス3の内部に踏み入れて怪我をする虞がなく、作業中に量水器ボックス3内部に土砂等が流れ込むことを防止することもでき、更に、仮設蓋3bには虎縞状の彩色が施されているので、仮設給水管8、仮設量水器9、仮設水栓10が突出していることを作業者に認識させることができ安全性を増すことができる。   In addition, since the temporary lid 3b is attached to the water meter box 3 during construction, there is no risk that an operator will accidentally step into the water meter box 3 and get injured. It is also possible to prevent earth and sand from flowing into the water container box 3 and the temporary lid 3b is colored with a tiger stripe, so that the temporary water supply pipe 8, the temporary water meter 9, the temporary water An operator can recognize that the stopper 10 protrudes, and safety can be increased.

また、仮設給水管8、仮設量水器9、仮設水栓10のすべてが平面視量水器ボックス3の領域内にまとまっているので、量水器ボックス3周囲の外構工事を行う際も位置の変更や一時的な撤去等をする必要がなく、効率よく工事を進めることができる。また、仮設量水器9は仮設蓋3bの上方に露出した状態で配置されており、検針員が検針の都度仮設給水管8を伸縮するなどして仮設蓋3bを開閉する必要がない。   Moreover, since all of the temporary water supply pipe 8, the temporary water meter 9, and the temporary water tap 10 are gathered in the area of the plan view water meter box 3, the external work around the water meter box 3 is also performed. There is no need to change the position or remove it temporarily, and work can be carried out efficiently. In addition, the temporary watering device 9 is disposed in an exposed state above the temporary lid 3b, and it is not necessary for the meter reader to open and close the temporary lid 3b by expanding and contracting the temporary water supply pipe 8 each time a meter is read.

本発明は、戸建住宅に限らず、上水道が供給され量水器ボックス内に量水器が収容され、量水器ボックス周囲を舗装等によって仕上げる建物全般に適用することができる。   The present invention is not limited to a detached house, and can be applied to all buildings in which a water supply is supplied, a water meter is accommodated in a water meter box, and the periphery of the water meter box is finished by paving or the like.

敷地、前面道路、建物等の配置を示す配置図である。It is a layout diagram showing the layout of a site, a front road, buildings, and the like. 量水器まわりの構成を示す図である。It is a figure which shows the structure around a water meter. 仮設接続部材の図である。It is a figure of a temporary connection member.

符号の説明Explanation of symbols

A…敷地
B…建物
C…前面道路
1…水道本管
2…本管側給水管
3…量水器ボックス
3a…本体
3b…仮設蓋
3b1…切り欠き部
3c…底板
3d…本管側給水管導入口
3e…建物側給水管導入口
4…仕切弁
5…仮設接続部材
5a…本管側給水管接続部
5b…建物側給水管接続部
5c…仮設給水管接続部
6…建物側給水管
7…ボールバルブ
8…仮設給水管
9…仮設量水器
10…仮設水栓
A ... Site B ... Building C ... Front road 1 ... Main water pipe 2 ... Main water supply pipe 3 ... Water meter box 3a ... Main body 3b ... Temporary cover 3b1 ... Notch 3c ... Bottom plate 3d ... Main water supply pipe Inlet 3e ... Building side water supply pipe introduction port 4 ... Gate valve 5 ... Temporary connection member 5a ... Main side water supply pipe connection 5b ... Building side water supply pipe connection 5c ... Temporary water supply pipe connection 6 ... Building side water supply pipe 7 ... ball valve 8 ... temporary water supply pipe 9 ... temporary water meter
10 ... Temporary faucet

Claims (4)

本設位置に埋設された埋め込み式の量水器ボックスと、
本設位置に埋設され、前記量水器ボックス内に導入された本管側給水管及び建物側給水管と、
前記量水器ボックス内に設置され、前記本管側給水管と前記建物側給水管が接続された仮設接続部材と、
前記仮設接続部材の本管側給水管接続部と建物側給水管接続部との中間部から分岐した分岐管接続部に接続された仮設水栓と、からなり、
前記本管側給水管接続部と前記建物側給水管接続部は、本設される量水器の2つの給水管接続部と同一の接続部形状と同一の離間寸法を有し、
前記本管側給水管接続部から供給された水は前記分岐管接続部方向にのみ導かれることを特徴とする仮設給水設備の設置構造。
An embedded water meter box embedded in the main position,
A main-side water supply pipe and a building-side water supply pipe embedded in the main installation position and introduced into the water meter box;
A temporary connection member installed in the water meter box and connected to the main water supply pipe and the building water supply pipe;
A temporary faucet connected to a branch pipe connection portion branched from an intermediate portion between the main side water supply pipe connection portion and the building side water supply pipe connection portion of the temporary connection member,
The main water supply pipe connection part and the building side water supply pipe connection part have the same separation dimensions and the same separation dimensions as the two water supply pipe connection parts of the water meter to be installed,
An installation structure of a temporary water supply facility, wherein water supplied from the main pipe side water supply pipe connection part is guided only in the direction of the branch pipe connection part.
前記仮設水栓は、仮設量水器と可撓性を有するフレキシブル管からなる仮設給水管とを介して前記分岐管接続部に接続され、
前記仮設水栓と仮設量水器は、前記量水器ボックスの上方に配置され、
前記量水器ボックスは、本設蓋が取り外され、前記本設蓋と同一の外形を有し前記仮設給水管取り出しの為の切り欠き部が設けられ、前記仮設量水器、前記仮設給水管及び前記仮設水栓が接続された状態で開閉自在な仮設蓋を備えた
ことを特徴とする請求項1に記載した仮設給水設備の設置構造。
The temporary faucet is connected to the branch pipe connecting portion via a temporary water meter and a temporary water supply pipe made of a flexible flexible pipe,
The temporary faucet and the temporary water meter are disposed above the water meter box,
The water meter box has a permanent lid removed, and has the same outer shape as the permanent lid, and is provided with a notch for taking out the temporary water supply pipe. The temporary water meter and the temporary water pipe The temporary water supply facility installation structure according to claim 1, further comprising a temporary lid that can be opened and closed in a state where the temporary water faucet is connected.
前記仮設蓋の上面は、虎縞状に彩色されたことを特徴とする請求項2に記載した仮設給水設備の設置構造。   The installation structure of the temporary water supply equipment according to claim 2, wherein the upper surface of the temporary lid is colored in a tiger stripe shape. 量水器及び量水器ボックスが埋設される敷地における仮設給水設備の設置方法であって、
本設される量水器の2つの給水管接続部と同一形状かつ同一離間寸法の2つの給水管接続部と前記2つの給水管接続部の中間部から分岐した分岐管接続部とを有するとともに一方の給水管への給水が遮断された仮設接続部材を用いて前記量水器ボックス内で本管側給水管と建物側給水管とを接続し、
前記分岐管接続部に仮設給水管を接続して前記量水器ボックスの上方に立ち上げ、
前記本管側給水管から仮設給水管方向にのみ給水し得るように前記仮設給水管に仮設水栓を接続した
ことを特徴とする仮設給水設備の設置方法。
A method for installing a temporary water supply facility on a site where a water meter and a water meter box are buried,
While having two water supply pipe connection parts of the same shape and the same distance as the two water supply pipe connection parts of the water meter to be installed, and a branch pipe connection part branched from an intermediate part of the two water supply pipe connection parts Using a temporary connection member in which water supply to one of the water supply pipes is interrupted, the main water supply pipe and the building side water supply pipe are connected in the water meter box,
Connect a temporary water supply pipe to the branch pipe connection portion and start up above the water meter box,
A temporary water supply installation method, wherein a temporary water tap is connected to the temporary water supply pipe so that water can be supplied only in the direction of the temporary water supply pipe from the main water supply pipe.
JP2008074861A 2008-03-24 2008-03-24 Temporary water supply installation structure and installation method Expired - Fee Related JP5074254B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008074861A JP5074254B2 (en) 2008-03-24 2008-03-24 Temporary water supply installation structure and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008074861A JP5074254B2 (en) 2008-03-24 2008-03-24 Temporary water supply installation structure and installation method

Publications (2)

Publication Number Publication Date
JP2009228299A JP2009228299A (en) 2009-10-08
JP5074254B2 true JP5074254B2 (en) 2012-11-14

Family

ID=41243998

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008074861A Expired - Fee Related JP5074254B2 (en) 2008-03-24 2008-03-24 Temporary water supply installation structure and installation method

Country Status (1)

Country Link
JP (1) JP5074254B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7194986B2 (en) * 2019-01-04 2022-12-23 株式会社日邦バルブ water discharge unit
JP7097425B2 (en) * 2020-11-27 2022-07-07 有限会社樋口水道 Temporary faucet and its water supply temporary construction method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06105199B2 (en) * 1989-12-26 1994-12-21 株式会社太陽商工 Water pressure test method for water supply pipe
JP2002090255A (en) * 2000-09-11 2002-03-27 Nagoya Valve Kogyo Kk Inspection apparatus for water leakage in newly installed water pipe

Also Published As

Publication number Publication date
JP2009228299A (en) 2009-10-08

Similar Documents

Publication Publication Date Title
KR200417638Y1 (en) piping inspect of a wall reclamation style that insulation attached
CN107587584A (en) Drainpipe leakage-resistant device and its construction method
KR101451935B1 (en) Valve room with a iron cover for valve opening and closeing
JP5074254B2 (en) Temporary water supply installation structure and installation method
CN108443590A (en) Side-type direct-burried part and its construction method
KR101212107B1 (en) Drainpipe structure with improved manhole and drainpipe inspection method therof
KR100654632B1 (en) A water turning method of powerless drain pipe and apparatus thereof
CN103835421B (en) Leakage-proof floor and anti-seepage construction method
CN207268010U (en) Drainpipe leakage-resistant device
CN202519628U (en) Inlet plugging device for temporary buried pipe in dense dam body
KR100732938B1 (en) That inspect piping of wall reclamation styleand form of construction work of double pipe
JP2002115294A (en) Drain-forming method and drain apparatus
CN208074294U (en) Side-type direct-burried part
JP2007009980A (en) Real pipe sleeve with collar made of vinyl chloride
JP4750159B2 (en) Relay sprinkler block that relays unit water pipes
KR100807538B1 (en) The revival method which union lays the new waterworks steel pipe on the waterworks steel pipe inside which is been old
JP4293623B2 (en) Stop cock and water supply piping system, its embedding method and its construction method
KR200435698Y1 (en) Apparatus for discharge of concrete drainfield
KR200424768Y1 (en) The connected socket of the double drain pipe with transfer a fluid
KR20100037227A (en) A water supply facilities and construction method thereof
KR101523270B1 (en) A Water Turning Method and Repairing Method for Pipe Lines with Non-Excavation
KR20070113329A (en) Composite manhole and construction method using thereby
CN111139898B (en) Construction method of buried fire hydrant well
CN106049693B (en) The advanced construction method of cover board and post-cast strip for the construction of top plate pouring after settlement
KR20210051130A (en) Fixing well cover of underground water

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20090807

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110317

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120731

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120823

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150831

Year of fee payment: 3