CN106049693B - Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method - Google Patents

Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method Download PDF

Info

Publication number
CN106049693B
CN106049693B CN201610419741.2A CN201610419741A CN106049693B CN 106049693 B CN106049693 B CN 106049693B CN 201610419741 A CN201610419741 A CN 201610419741A CN 106049693 B CN106049693 B CN 106049693B
Authority
CN
China
Prior art keywords
cover board
cast strip
post
plate
waterproof roll
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610419741.2A
Other languages
Chinese (zh)
Other versions
CN106049693A (en
Inventor
李浩然
谷云宽
徐巍
王代培
张洋
张玉磊
王玲
丁嘉栋
刘谦
姜旭
朱彬马
武杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201610419741.2A priority Critical patent/CN106049693B/en
Publication of CN106049693A publication Critical patent/CN106049693A/en
Application granted granted Critical
Publication of CN106049693B publication Critical patent/CN106049693B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a cover plate for construction of a roof settlement post-cast strip and an advanced construction method of the post-cast strip, wherein the cover plate comprises the following components: the cover plate body is of a rectangular structure and comprises a first side edge and a second side edge which are opposite, and a third side edge and a fourth side edge which are opposite; the connecting piece comprises a first connecting plate and a second connecting plate which are vertically connected with each other, the first connecting plate is provided with a bolt connecting hole, and the second connecting plate is vertically connected with the first side edge of the cover plate body into a whole; the channel steel comprises a middle plate and two side plates, and the side plates are vertically connected with the middle plate; the middle plate of the channel steel is fixedly connected with the third side edge of the cover plate body to form a primary-secondary port used for connecting the fourth side edge of the other cover plate body. The invention has the advantages that: the sealing performance of the joint of the cover plate is high; the cover plate can make up for geometric errors caused by uneven settlement of the two sides of the post-cast strip; the coiled material of the top plate is not damaged in the construction process, and the coiled material has high waterproof sealing performance.

Description

The advanced construction method of cover board and post-cast strip for the construction of top plate pouring after settlement
Technical field
The present invention relates to a kind of advanced construction methods of cover board and post-cast strip for the construction of top plate pouring after settlement.
Background technology
The setting of pouring after settlement is in order to prevent between the main building of skyscraper and group room or basement because of the difference of sedimentation Different difference causes to cause structural cracks.By the requirement of code for structural design and construction specification, the concrete of pouring after settlement Cast, it is necessary to wait for main building(It is high-rise)Structure all constructed(Top out)It can construct later.But it is applied in building In work, especially in the engineering construction of last decade, most of high building project need to be inserted into interior decoration and tube net outside in advance And municipal administration, road, afforestation project etc., but because scene can not be closed in time, basement finishing and electromechanical installation can be poured due to after Band percolating water affects, and exterior components can not almost construct.
The prior art, which solves the above problems, utilizes following construction method:In structure construction, alter-pouring strips mould plate is designed to Independent system is separated with other templates, convenient for the form removable outside post-cast strip region.The construction of first floor floor construction finishes, the buildings Ji Using armored concrete prefabricated cover board covering on plate, and with overall structure synchronous construction waterproof layer and backfill, when construction according to 4m spacing, which is stayed, sets 3m high, diameterPouring hole of 300 concrete reinforced pipes as concrete.Pass through again after structure sediment stabilization Concrete pouring hole pours self-compaction expansive concrete into post-cast strip.
But there is also following disadvantages for the above-mentioned prior art:First, it can not ensure the close of the prefabricated cover board edge joint position in post-cast strip Closing property.Secondly, geometric error caused by the differential settlement of post-cast strip both sides can not be become by the prefabricated cover board of armored concrete Shape is offset, and is existed and is finished the hidden danger that waterproof roll damages to having constructed.In addition, to being poured after L-shaped, cross or fold-line-shaped Band does not solve the cover board piece of turning point.Finally, must reserve concrete casting hole on top plate coiled material, top plate waterproof coiled material without Method seal closure.
Invention content
The first object of the present invention is to provide a kind of cover board for the construction of top plate pouring after settlement, to solve not ensureing The technical issues of seal of the prefabricated cover board edge joint position in post-cast strip.
The second object of the present invention is to provide a kind of advanced construction method in basement roof post-cast strip.
In order to realize that above-mentioned first purpose, the present invention provide a kind of cover board for the construction of top plate pouring after settlement, packet It includes:
Cover board body, the Cover Plate Body Is rectangular configuration, including first side and second side that position is opposite, and The opposite third side in position and four side;
First connector, first connector include the first connecting plate and the second connecting plate being mutually connected vertically, Bolt connecting hole is offered on first connecting plate of middle level, the second vertical connecting plate is vertical with the first side of cover board body It is connected as one;
Second connector, second connector include the first connecting plate and the second connecting plate being mutually connected vertically, Bolt connecting hole is offered on first connecting plate of middle level, the second vertical connecting plate is vertical with the second side of cover board body It is connected as one;
Channel steel, the middle plate of the channel steel are fixedly connected with the third side of cover board body, are formed for connecting another cover board The mother-son mouth of the four side of ontology.
The present invention is used for the cover board of top plate pouring after settlement construction, further, the cover board body, first as described above Connector and the second connector are integrally formed, and whole is in convex shape.
The present invention is used for the cover board of top plate pouring after settlement construction as described above, further, on first connecting plate At least two bolt connecting holes are offered, bolt connecting hole is of a straight line type arrangement, shaped form arrangement or irregular arrangement.
The present invention is used for the cover board of top plate pouring after settlement construction as described above, and further, two cover boards are attached When, the four side of the cover board body of first cover board is fixed to and is formed by plate in the channel steel of second cover board and cover board body Mother-son mouth position.
The cover board that the present invention is used for the construction of top plate pouring after settlement as described above further includes further sealing compound, described Sealing compound is filled in the gap position that the cover board body of two adjacent cover boards is formed.
In order to realize above-mentioned second purpose, the present invention provides a kind of advanced construction method in basement roof post-cast strip, including Following steps:
Step 1, alter-pouring strips mould plate is installed below structure floor, binds post-cast strip steel bar;
Step 2, concrete pumping hose is installed, between concrete pumping hose is placed in top plate double steel bar mesh sheet, Double steel bar mesh sheet muscle smears lubricant, and concrete pumping hose carries out prestretching after installing, it is ensured that concrete pumping hose It can smoothly be pulled;
Step 3, cover board is installed, is secured the lid to above structure floor;The cover board is any one of claim 1-4 institutes The cover board for the construction of top plate pouring after settlement stated;
Step 4, on the inner corner trim position casting concrete inclined-plane that the cover board connecting component of cover board is formed;
Step 5, the laying water-proof coiled material above structure floor and cover board backfills element soil on waterproof roll;
Step 6, the post-cast strip position installation concrete lift-up between structure floor pours device;
Step 7, it after agent structure binds or in the case of meeting design requirement, carries out concrete lift-up and pours, in structure Post-cast strip is formed between floor.
The present invention advanced construction method in basement roof post-cast strip as described above, it is preferable that in step 3, cover board is logical The bolt connecting hole and chemical bolt crossed on connector are fixed to structure floor.
The present invention advanced construction method in basement roof post-cast strip as described above, it is preferable that in steps of 5, described anti- Water coiled material includes the first waterproof roll layer, the second waterproof roll layer and third waterproof roll layer;First waterproof roll layer is laid on Above structure floor and cover board;Second waterproof roll layer is laid on above the first waterproof roll layer;Third waterproof roll layer is laid with Above the second waterproof roll layer;Seam inside first waterproof roll layer and the seam inside the second waterproof roll layer be not mutually be overlapped It is folded.
The present invention advanced construction method in basement roof post-cast strip as described above, it is preferable that in step 6, concrete Jacking pour device post-cast strip length direction interval be arranged, adjacent concrete jacking pour device spacing distance be 8m~ 12m。
The present invention advanced construction method in basement roof post-cast strip as described above, it is preferable that concrete lift-up pours dress It sets including concrete pumping hose and pump line elbow;Concrete pumping hose is installed in post-cast strip position between structure floor, Pump line elbow is arranged in the position that post-cast strip is pierced by concrete pumping hose, and the steel bar welding of pump line elbow and structure floor is in succession It connects.
The beneficial effects of the invention are as follows:
The seal of cover board edge joint position is high.When two cover boards are attached, by the 4th of the cover board body of first cover board the Side is fixed to the mother-son mouth position formed by plate and cover board body in the channel steel of second cover board.In order to further increase cover board Between sealing effect, construct sealing compound in gap position, the sealing compound is filled in the cover board body shape of two adjacent cover boards At gap position.The present invention is improved by above-mentioned improvement, the seal of cover board edge joint position, is avoided piece position and is formed Leak source.
The differential settlement that cover board can make up post-cast strip both sides forms geometric error.Since cover board is by cover board body, A connection piece and the second connector composition, when the differential settlement of post-cast strip both sides forms geometric error, the bending part of cover board Occur to stretch or deformation can make up differential settlement and form geometric error, avoids and finish waterproof roll to having constructed and cause brokenly It is bad.
Work progress does not destroy top plate coiled material, and waterproof coiled material leakproofness is high.Device is poured using concrete lift-up to be mixed Solidifying soil pours, and concrete casting hole must be reserved on top plate coiled material in the prior art by avoiding, and top plate waterproof coiled material can not be close The problem of closing is closed.
Description of the drawings
By being described in detail made by conjunction with the following drawings, above-mentioned and/or other aspects of the invention and advantage will become It becoming apparent from and is easier to understand, these attached drawings are only schematical, are not intended to limit the present invention, wherein:
Fig. 1 is an embodiment of the present invention for top plate pouring after settlement construction schematic diagram;
Fig. 2 is the cover plate schematic diagram of an embodiment of the present invention;
Fig. 3 is the Section A-A schematic diagram of Fig. 2;
Fig. 4 is the section B-B schematic diagram of Fig. 2;
Fig. 5 is that two adjacent cover boards of an embodiment of the present invention dock schematic diagram;
Fig. 6 is that the concrete lift-up of an embodiment of the present invention pours schematic device;
Fig. 7 is the advanced construction method flow chart in basement roof post-cast strip of an embodiment of the present invention;
Fig. 8 is the L corners post-cast strip steel deck-plate schematic diagram of an embodiment of the present invention;
Fig. 9 is the C-C schematic cross-sections of Fig. 8;
Figure 10 is the cross post-cast strip steel deck-plate schematic diagram of an embodiment of the present invention;
Figure 11 is the D-D schematic cross-sections of Figure 10;
Figure 12 is the fold-line-shaped post-cast strip steel deck-plate schematic diagram of an embodiment of the present invention.
In attached drawing, parts list represented by the reference numerals are as follows:
1, cover board, 11, cover board body, the 12, first connector, the 13, second connector, 14, channel steel, 15, chemical bolt, 16, concrete inclined-plane, 17, bolt connecting hole, 18, sealing compound;
2, structure floor;
3, alter-pouring strips mould plate;
4, falsework;
5, post-cast strip, 51, post-cast strip steel bar;
6, waterproof roll, the 61, first waterproof roll layer, the 62, second waterproof roll layer, 63, third waterproof roll layer;
7, element soil;
8, pump line elbow;
9, concrete pumping hose, 91, check-valves;
100, L corners post-cast strip steel deck-plate, 101, angle steel reinforce back cord;
200, cross post-cast strip steel deck-plate, 201, square steel side rib;
300, fold-line-shaped post-cast strip steel deck-plate.
Specific implementation mode
Hereinafter, the cover board of the description present invention constructed for top plate pouring after settlement and post-cast strip are super with reference to the accompanying drawings The embodiment of preceding construction method.
The embodiment recorded herein is the specific specific implementation mode of the present invention, for illustrating design of the invention, It is explanatory and illustrative, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein Outside embodiment, those skilled in the art can also based on the application claims and specification disclosure of that using aobvious and The other technical solutions being clear to, these technical solutions include any obvious using making for the embodiment to recording herein The technical solution of substitutions and modifications.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the present invention, it is schematically indicated the shape of each section And its correlation.The structure of each component for the ease of clearly showing the embodiment of the present invention is note that, between each attached drawing Do not drawn according to identical ratio.Identical reference marker is for indicating identical part.
Fig. 1 shows the basement roof pouring after settlement construction schematic diagram of an embodiment of the present invention, can see in Fig. 1 Go out, the cover board 1 for the construction of top plate pouring after settlement is mounted on above the gap that structure floor is formed.Fig. 2 is that the present invention is a kind of The cover plate schematic diagram of embodiment comprising:
Cover board body 11, the cover board body 11 are rectangular configuration, including the first side and second side that position is opposite, And the third side and four side that position is opposite;
First connector 12, as shown in Fig. 2, first connector 12 include the first connecting plate for being mutually connected vertically and Second connecting plate, wherein bolt connecting hole 17 is offered on the first horizontal connecting plate, the second vertical connecting plate and cover board sheet The first side vertical connection of body is integrated;In a preferred embodiment, at least two spiral shells are offered on first connecting plate Bolt connecting hole 17(It is 2 in Fig. 2), bolt connecting hole 17 is of a straight line type arrangement, shaped form is arranged or irregular arrangement.
Second connector 13, as shown in Fig. 2, second connector 13 include the first connecting plate for being mutually connected vertically and Second connecting plate, wherein bolt connecting hole is offered on the first horizontal connecting plate, vertical the second connecting plate and cover board body Second side vertical connection be integrated;The cover board body 11, the first connector 12 and 13 three in one of the second connector at Type, whole is in convex shape.
Channel steel 14, as shown in figure 4, the channel steel 14 includes middle plate and two side plates, side plate and middle plate vertical connection;Channel steel Middle plate be fixedly connected with the third side of cover board body, form the primary and secondary of four side for connecting another cover board body Mouthful.
The application method and advantage of the above embodiment of the present invention cover board be:As shown in figure 5, when two cover boards are attached, The four side of the cover board body 11 of first cover board is fixed to and is formed by plate in the channel steel of second cover board and cover board body Mother-son mouth position.In order to further increase the sealing effect between cover board, in gap position construction sealing compound 18, the sealing Cream 18 is filled in the gap position that the cover board body 11 of two adjacent cover boards 1 is formed.By above-mentioned improvement, cover board edge joint position it is close Closing property is improved, and is avoided piece position and is formed leak source.Since cover board is by cover board body, the first connector and the second connector Composition, when the differential settlement of post-cast strip both sides forms geometric error, the bending part of cover board occurs to stretch or deformation can be more It mends differential settlement and forms geometric error, avoid and finish waterproof roll to having constructed and damage.
Post-cast strip is used for top plate there are when L-type structure using the combination above-described embodiment of L corners post-cast strip steel deck-plate 100 The cover board of pouring after settlement construction carries out post empiricism.In conjunction with shown in Fig. 8 and Fig. 9, L corners post-cast strip steel deck-plate includes cover board Ontology 11 and the first connector 12, the Cover Plate Body Is rectangular configuration;First connector 12 is connected to two phases of cover board body Adjacent side;Other two side of cover board body forms rim of the mouth piece.Then it utilizes shown in the first embodiment for pushing up Female mouth of the cover board of plate pouring after settlement construction is docked with above-mentioned rim of the mouth.The advantages of this structure is the sealing effect between cover board It is good, spillage problem will not occur.In order to improve the intensity of cover board body 11, angle steel has also been welded on cover board body and has reinforced back cord 101。
Post-cast strip combines being used for for above-described embodiment there are when decussate texture using cross post-cast strip steel deck-plate 200 The cover board of top plate pouring after settlement construction carries out post empiricism.In conjunction with shown in Figure 10 and Figure 11, cross post-cast strip steel deck-plate Including cover board body 11 and square steel side rib 201, the Cover Plate Body Is rectangular configuration;Square steel side rib 201 is connected to cover board body Four sides, and form female mouth.Then the cover board for the construction of top plate pouring after settlement shown in the first embodiment is utilized Rim of the mouth docked with above-mentioned rim of the mouth.The advantages of this structure is that the sealing effect between cover board is good, and spillage problem will not occur.For The intensity of cover board body 11 is improved, angle steel has also been welded on cover board body and has reinforced back cord 101.
Post-cast strip is used to push up there are when meander line structure using the combination above-described embodiment of fold-line-shaped post-cast strip steel deck-plate 300 The cover board of plate pouring after settlement construction carries out post empiricism.As shown in figure 12, fold-line-shaped post-cast strip steel deck-plate above-described embodiment The covering plate structure for the construction of top plate pouring after settlement it is essentially identical, be that the shape of cover board body is not square in place of difference Shape, but according to broken line need to cut into it is trapezoidal.
In conjunction with the schematically illustrate advanced construction method in basement roof post-cast strip of the present invention of flow of Fig. 7, include the following steps:
Step 1,2 lower section of structure floor installs alter-pouring strips mould plate 3, binds post-cast strip steel bar 51;In Fig. 1, further it is shown that It is used to support the falsework 4 of alter-pouring strips mould plate 3.
Step 2, installation concrete pumping hose 9, between concrete pumping hose is placed in top plate double steel bar mesh sheet, Double steel bar mesh sheet muscle smears lubricant, and concrete pumping hose carries out prestretching after installing, it is ensured that concrete pumping hose It can smoothly be pulled;
Step 3, cover board 1 is installed, cover board 1 is fixed to 2 top of structure floor;The cover board 1 describes for above-described embodiment For top plate pouring after settlement construction cover board;As shown in figure 3, cover board 1 is by bolt connecting hole 17 on connector and changes It learns bolt 15 and is fixed to structure floor 2;
Step 4, in the cover board connecting component of cover board 1(First connector 12 and the second connector 13)It pours the inner corner trim position of formation Build concrete inclined-plane 16;
Step 5, the laying water-proof coiled material 6 above structure floor 2 and cover board 1 backfills element soil 7 on waterproof roll;Such as Fig. 1 Shown, the waterproof roll 6 includes the first waterproof roll layer 61, the second waterproof roll layer 62 and third waterproof roll layer 63;The One waterproof roll layer 61 is laid on 1 top of structure floor and cover board;Second waterproof roll layer 62 is laid on the first waterproof roll layer 61 tops;Third waterproof roll layer 63 is laid on 62 top of the second waterproof roll layer;Seam inside first waterproof roll layer 61 With the seam non-overlapping inside the second waterproof roll layer 62.The extensibility of waterproof roll is more than in a preferred embodiment 150%, it is that will not cause to draw after ensureing post-cast strip differential settlement such as to use polyethylene tire modified asphalt waterproof coiled material, effect Disconnected waterproof roll.
Step 6,5 position of the post-cast strip installation concrete lift-up between structure floor 2 pours device;As shown in fig. 6, mixed Solidifying soil jacking pours device and is arranged at 5 length direction interval of post-cast strip, and the spacing distance that adjacent concrete jacking pours device is 8m~12m.
Step 7, it after agent structure binds or in the case of meeting design requirement, carries out concrete lift-up and pours, in structure Post-cast strip 5 is formed between floor 2.
The above-mentioned construction method of the present invention has the following advantages:Device, which is poured, using concrete lift-up carries out concreting, To avoid must reserve concrete casting hole on top plate coiled material in the prior art, top plate waterproof coiled material can not seal closure ask Topic.
In a specific embodiment, as shown in fig. 6, it includes 9 He of concrete pumping hose that concrete lift-up, which pours device, Pump line elbow 8;5 position of post-cast strip installation concrete pumping hose 9 between structure floor 2, wears in concrete pumping hose 9 Go out the position setting pump line elbow 8 of post-cast strip 5, pump line elbow 8 is connect with the reinforcement welding of structure floor 2.
In a preferred embodiment, such as vertical to stop as shown in fig. 6, the end of concrete pumping hose 9 is equipped with check-valves 91 Return valve.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and other feature combination, and those skilled in the art are also Other combinations between each technical characteristic can be carried out according to the purpose of invention, be subject to realize the present invention purpose.

Claims (8)

1. a kind of advanced construction method in basement roof post-cast strip, includes the following steps:
Step 1, alter-pouring strips mould plate is installed below structure floor, binds post-cast strip steel bar;
Step 2, concrete pumping hose is installed, it is double-deck between concrete pumping hose is placed in top plate double steel bar mesh sheet Reinforced mesh muscle smears lubricant, and concrete pumping hose carries out prestretching after installing, it is ensured that concrete pumping hose energy quilt Smoothly pull;
Step 3, cover board is installed, is secured the lid to above structure floor;
Step 4, on the inner corner trim position casting concrete inclined-plane that the cover board connecting component of cover board is formed;
Step 5, the laying water-proof coiled material above structure floor and cover board backfills element soil on waterproof roll;
Step 6, the post-cast strip position installation concrete lift-up between structure floor pours device;
Step 7, it after agent structure binds or in the case of meeting design requirement, carries out concrete lift-up and pours, in structure floor Between form post-cast strip;
For top plate pouring after settlement construction cover board include:
Cover board body, the Cover Plate Body Is rectangular configuration, including position opposite first side and second side and position Opposite third side and four side;
First connector, first connector include the first connecting plate and the second connecting plate being mutually connected vertically, wherein water Bolt connecting hole is offered on the first flat connecting plate, the first side vertical connection of vertical the second connecting plate and cover board body It is integrated;
Second connector, second connector include the first connecting plate and the second connecting plate being mutually connected vertically, wherein water Bolt connecting hole is offered on the first flat connecting plate, the second side vertical connection of vertical the second connecting plate and cover board body It is integrated;
Channel steel, the middle plate of the channel steel are fixedly connected with the third side of cover board body, are formed for connecting another cover board body Four side mother-son mouth.
2. the advanced construction method in basement roof post-cast strip according to claim 1, which is characterized in that in step 3, lid Plate is fixed to structure floor by bolt connecting hole on connector and chemical bolt.
3. the advanced construction method in basement roof post-cast strip according to claim 1, which is characterized in that in steps of 5, institute It includes the first waterproof roll layer, the second waterproof roll layer and third waterproof roll layer to state waterproof roll;First waterproof roll layer is spread It is located above structure floor and cover board;Second waterproof roll layer is laid on above the first waterproof roll layer;Third waterproof roll layer It is laid on above the second waterproof roll layer;The seam inside seam and the second waterproof roll layer inside first waterproof roll layer is not It overlaps.
4. the advanced construction method in basement roof post-cast strip according to claim 1, which is characterized in that in step 6, mix Solidifying soil jacking pours device and is arranged at post-cast strip length direction interval, and the spacing distance that adjacent concrete jacking pours device is 8m ~12m.
5. the advanced construction method in basement roof post-cast strip according to claim 1 or 4, which is characterized in that concrete top It includes concrete pumping hose and pump line elbow to rise and pour device;Post-cast strip position between structure floor is installed by concrete pump Hose is sent, pump line elbow, the reinforcing bar of pump line elbow and structure floor is arranged in the position that post-cast strip is pierced by concrete pumping hose It is welded to connect.
6. the advanced construction method in basement roof post-cast strip according to claim 1, which is characterized in that the cover board sheet Body, the first connector and the second connector are integrally formed, and whole is in convex shape, is offered at least on first connecting plate Two bolt connecting holes, bolt connecting hole are of a straight line type arrangement, shaped form arrangement or irregular arrangement.
7. the advanced construction method in basement roof post-cast strip according to claim 1, which is characterized in that two cover boards carry out When connection, the four side of the cover board body of first cover board is fixed to by plate and cover board body in the channel steel of second cover board The mother-son mouth position of formation.
8. the advanced construction method in basement roof post-cast strip according to claim 7, which is characterized in that further include sealing Cream, the sealing compound are filled in the gap position that the cover board body of two adjacent cover boards is formed.
CN201610419741.2A 2016-06-14 2016-06-14 Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method Active CN106049693B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610419741.2A CN106049693B (en) 2016-06-14 2016-06-14 Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610419741.2A CN106049693B (en) 2016-06-14 2016-06-14 Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method

Publications (2)

Publication Number Publication Date
CN106049693A CN106049693A (en) 2016-10-26
CN106049693B true CN106049693B (en) 2018-10-12

Family

ID=57169215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610419741.2A Active CN106049693B (en) 2016-06-14 2016-06-14 Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method

Country Status (1)

Country Link
CN (1) CN106049693B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111926927A (en) * 2020-07-09 2020-11-13 福建建工集团有限责任公司 Underground chamber roof post-cast strip plugging structure and construction method thereof
CN113047345B (en) * 2021-04-14 2024-07-23 陕西建工集团股份有限公司 Post-pouring belt cover plate and finite element optimization construction method of post-pouring belt with ultra-long underground structure

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002188292A (en) * 2000-12-19 2002-07-05 Shiyuuzo Hiwaki Column setup jack
CN102619329B (en) * 2011-01-26 2015-01-07 甘肃省第八建筑工程公司 Expansion restraint construction method for post-pouring belt
CN103437379B (en) * 2013-09-16 2015-05-20 中建七局(上海)有限公司 Post-cast strip construction and drainage method for base plate of basement
CN104674958A (en) * 2015-03-03 2015-06-03 南通华新建工集团有限公司 Construction method for early intervention of exterior wall post-cast strip in water proofing and extra trench backfill
CN205205876U (en) * 2015-12-02 2016-05-04 福建路港(集团)有限公司 Post -cast strip protection architecture
CN205857418U (en) * 2016-06-14 2017-01-04 中国建筑一局(集团)有限公司 Cover plate for roof settlement post-cast strip construction

Also Published As

Publication number Publication date
CN106049693A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN106930331A (en) Waterproof structure system of underground pipe gallery expansion joint and construction method thereof
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN102535441A (en) Construction method of underground diaphragm wall
CN204199330U (en) The overall steel plate for sealing water in a kind of ater-casting
CN107326918A (en) A kind of concealed type, which passes through raft plate, can block impervious sump and its construction technology
CN106049693B (en) Cover plate for roof settlement post-cast strip construction and post-cast strip advanced construction method
CN205688413U (en) A kind of prefabricated water intaking in power plant immersed tunnel structure
CN108642996B (en) Deformation joint for first floor or basement roof and road square and construction method thereof
CN210621771U (en) Waterproof structure of longitudinal horizontal construction joint of pipe gallery internal and external walls
CN104234089A (en) Construction method for waterproof and water-draining combination of basement
CN103205986A (en) Concrete raft foundation construction-joint grouting device and construction method
CN205804419U (en) The tenon formula joint waterproofing structure of concrete waist rail embedded structure side wall
CN201473974U (en) Novel steel plate water stopper
CN106284303B (en) A kind of prefabricated ground-connecting-wall and its construction method with the limit of angle steel connector
CN205857418U (en) Cover plate for roof settlement post-cast strip construction
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN208039491U (en) Outer wall of basement waterproof construction post-cast strip component
CN106759525A (en) Rich water sand-pebble layer underground engineering deformation joint structure and its construction method
CN207436340U (en) A kind of Large-span Precast floor construction
CN107345405A (en) Grouting method at concrete raft foundation construction joint
CN107152037A (en) Poured band of outer wall of basement construction method
CN109140046B (en) Method for plugging end of pipe jacking pipe curtain
CN105863125A (en) Mounting joint for external wall panel
CN206986930U (en) Connection structure of closed-section steel pipe gallery and concrete cast-in-place section
CN206706843U (en) A kind of basement induction crack structure with gutter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant