JP5049309B2 - Process planning apparatus and process planning method - Google Patents

Process planning apparatus and process planning method Download PDF

Info

Publication number
JP5049309B2
JP5049309B2 JP2009073271A JP2009073271A JP5049309B2 JP 5049309 B2 JP5049309 B2 JP 5049309B2 JP 2009073271 A JP2009073271 A JP 2009073271A JP 2009073271 A JP2009073271 A JP 2009073271A JP 5049309 B2 JP5049309 B2 JP 5049309B2
Authority
JP
Japan
Prior art keywords
personnel
work
information
skill
allocation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009073271A
Other languages
Japanese (ja)
Other versions
JP2010225017A (en
Inventor
英一郎 高久田
Original Assignee
株式会社 日立東日本ソリューションズ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社 日立東日本ソリューションズ filed Critical 株式会社 日立東日本ソリューションズ
Priority to JP2009073271A priority Critical patent/JP5049309B2/en
Publication of JP2010225017A publication Critical patent/JP2010225017A/en
Application granted granted Critical
Publication of JP5049309B2 publication Critical patent/JP5049309B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、複数の作業工程に分けられた工程計画の担当要員の割付作業を容易にする技術に関する。   The present invention relates to a technique for facilitating assignment work of personnel in charge of a process plan divided into a plurality of work processes.

複数の作業工程に対し作業工程毎に担当要員の割付作業をするために、各種の方法が行われている。例えば、作業工程の工程計画装置の表示部に工程計画の画面を出し、作業工程毎の担当要員の設定画面を表示し、要員管理者が、担当要員の条件を考慮しながら選択している。また、担当要員の割付の調整が必要な場合に担当割付結果の表示画面を見ながら、要員担当者が担当要員に連絡し確認後確認結果を入力すると、工程計画装置内の結果ファイルに反映する(例えば、特許文献1参照)。   Various methods are used in order to assign personnel in charge for a plurality of work processes. For example, a process plan screen is displayed on the display unit of the process planning apparatus for work processes, and a setting screen for personnel in charge for each work process is displayed, and the personnel manager makes a selection in consideration of the conditions of the personnel in charge. In addition, when the assignment of assigned personnel needs to be adjusted, when the assigned personnel contact the responsible personnel and input the confirmation result after confirming it while viewing the assigned assignment result display screen, it is reflected in the result file in the process planning device. (For example, refer to Patent Document 1).

特開平11−306232号公報Japanese Patent Laid-Open No. 11-306232

作業工程毎の担当要員の設定画面から担当要員を選択する方法は、従来、表示部に工程計画の別画面を出しチェックボックスなどをクリックして選択していたので、操作選択する時間がかかる問題がある。また、要員の空き時間、資格、スキルなどがよくわからないまま割り付けるので、再度、割り付けの作業が発生し、作業工程毎の要員の割り付けが予定数に達したか、即座にわからない問題があった。さらに、要員のスキルなどは、要員担当者(要員管理者)が作業の経験に基づき管理していることが多く、要員のスキル情報に関する管理も容易でない問題があった。   The method of selecting the person in charge from the setting screen of the person in charge for each work process has conventionally been to select another operation plan by clicking on a check box etc. on the display section, so it takes time to select the operation There is. In addition, since assignments were made without knowing the availability, qualifications, and skills of the personnel, there was a problem that the assignment work occurred again and it was not immediately known whether the assignment of personnel for each work process reached the planned number. Furthermore, personnel skills (manage managers) are often managed based on work experience, and there is a problem that management of skill information of personnel is not easy.

本発明は、前記した課題を解決するためになされたものであり、複数の作業工程に分けられた工程計画の担当要員の割付作業を容易にすることができる工程計画装置および工程計画方法を提供することを目的とする。   The present invention has been made to solve the above-described problems, and provides a process planning apparatus and a process planning method capable of facilitating the assignment work of personnel in charge of a process plan divided into a plurality of work processes. The purpose is to do.

前記目的を達成するため、工程計画装置は、表示部に表示された工程管理表(例えば、タスク別ガントチャート41)の画面上から、作業工程が選択され、要員管理表(例えば、リソース別ガントチャート42)にドラッグ&ドロップ(ドラッグアンドドロップ)などの対象を選択し移動する操作を受理すると、要員管理表に選択された作業工程を割り付けて、担当要員として登録し、工程表画面の工程枠内に割り付けられた割付予定数を表示する。このとき、工程計画装置はドロップ時に担当要員として所定条件(例えば、ダブルブッキングや資格有無)を満たすか否かのチェックを行う。所定条件を満たした場合、要員管理表に割り付けられた担当要員として確定する。所定条件を満たさない場合は、工程管理表および要員管理表の作業工程にエラー情報を告知する。また、所定条件のひとつである要員スキル情報(例えば、要員スキル情報214)に関する管理もスキルアップの基準情報(例えば、スキルアップ基準情報232)をもとに実施できる。   In order to achieve the object, the process planning apparatus selects a work process from the screen of the process management table (for example, the task-specific Gantt chart 41) displayed on the display unit, and the personnel management table (for example, the resource-specific Gantt). When an operation for selecting and moving an object such as drag and drop (drag and drop) is accepted on the chart 42), the selected work process is assigned to the personnel management table, and is registered as a responsible personnel. The number of allocations allocated in is displayed. At this time, the process planning apparatus checks whether or not a predetermined condition (for example, double booking or presence / absence of qualification) is satisfied as a person in charge at the time of dropping. If the prescribed conditions are met, the person in charge assigned to the personnel management table is confirmed. When the predetermined condition is not satisfied, error information is notified to the work process of the process management table and the personnel management table. Also, management regarding personnel skill information (for example, personnel skill information 214), which is one of the predetermined conditions, can be performed based on skill improvement reference information (for example, skill improvement criterion information 232).

本発明によれば、複数の作業工程に分けられた工程計画の担当要員の割付作業を容易にすることができる。また、要員のスキルアップ判定も容易にできる。   ADVANTAGE OF THE INVENTION According to this invention, the assignment work of the person in charge of the process plan divided into several work processes can be made easy. In addition, it is easy to determine the skill improvement of personnel.

本発明の実施形態に係る工程計画装置を示す図である。It is a figure which shows the process planning apparatus which concerns on embodiment of this invention. 表示画面の画面構成の一例を示す図である。It is a figure which shows an example of the screen structure of a display screen. 時分別表示画面の画面構成の一例を示す図である。It is a figure which shows an example of a screen structure of a time classification display screen. 工程情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of process information. 要員割付引当情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of personnel allocation provision information. 要員限度時間情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of personnel limit time information. 要員シフト情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of personnel shift information. 要員保有資格情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of personnel possession qualification information. 要員スキル情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of personnel skill information. 作業必要資格情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of work required qualification information. 作業必要スキル情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of work required skill information. 作業時間実績情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of work time performance information. スキルアップ基準情報のデータ構造の一例を示す図である。It is a figure which shows an example of the data structure of skill up reference | standard information. 要員割付手順の方法(ステップS101)を示す図である。It is a figure which shows the method (step S101) of a personnel assignment procedure. 要員割付手順の方法(ステップS102)を示す図である。It is a figure which shows the method (step S102) of a personnel assignment procedure. 要員割付手順の方法(ステップS103)を示す図である。It is a figure which shows the method (step S103) of a personnel assignment procedure. 要員割付手順の処理を示すフローチャートである。It is a flowchart which shows the process of a personnel allocation procedure. 要員割付時の制約チェック処理の機能関係を示す図である。It is a figure which shows the functional relationship of the constraint check process at the time of personnel assignment. 要員割付時の制約チェック処理を示すフローチャートである。It is a flowchart which shows the restriction | limiting check process at the time of personnel assignment. スキルアップ判定処理の機能関係を示す図である。It is a figure which shows the functional relationship of a skill up determination process. 表示画面の画面構成のその他の例を示す図である。It is a figure which shows the other example of the screen structure of a display screen.

以下、本発明の実施形態について図面を参照して詳細に説明する。
図1は、本発明の実施形態に係る工程計画装置を示す図である。工程計画装置100は、工程計画の処理を行う処理部10、工程計画の処理を行う際にデータを格納する記憶部20、データを入力、操作指令する入力部30、データを表示する表示部40、およびLAN(Local Area Network)などのネットワーク300を介して他のサーバなどと通信を行う通信部50から構成される。
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
FIG. 1 is a diagram showing a process planning apparatus according to an embodiment of the present invention. The process planning apparatus 100 includes a processing unit 10 that processes a process plan, a storage unit 20 that stores data when the process plan is processed, an input unit 30 that inputs and commands data, and a display unit 40 that displays the data. And a communication unit 50 that communicates with other servers via a network 300 such as a LAN (Local Area Network).

記憶部20は、RAM(Random Access Memory)やHDD(Hard disk drive)装置などにより構成される。処理部10は、CPU(Central Processing Unit)によって、RAMやHDD上のプログラムを実行することで実現される。入力部30は、キーボードやマウスなどのコンピュータに指示を入力するための装置であり、プログラム起動などの指示を入力する。表示部40は、ディスプレイなどであり、工程計画装置100による処理の実行状況や実行結果などを表示する。通信部50は、ネットワーク300を介して、他のサーバなどと各種データやコマンドを交換する。   The storage unit 20 includes a RAM (Random Access Memory), a HDD (Hard disk drive) device, and the like. The processing unit 10 is realized by executing a program on a RAM or HDD by a CPU (Central Processing Unit). The input unit 30 is a device for inputting an instruction to a computer such as a keyboard and a mouse, and inputs an instruction such as starting a program. The display unit 40 is a display or the like, and displays an execution status or an execution result of the process performed by the process planning apparatus 100. The communication unit 50 exchanges various data and commands with other servers via the network 300.

処理部10は、作業管理表および要員管理表をもとに工程計画を作成する工程計画作成部11(工程計画作成手段)、割り付けられた要員数をチェックする割付要員数チェック部12(割付要員数判定手段)、割り付け予定の要員の制約条件をチェックする制約チェック部13(制約条件判定手段)、作業者の実績の作業時間を登録する作業時間実績登録部14、作業者のスキルがアップしているか否かを判定するスキルアップ判定部15(スキルアップ判定手段)の複数のプログラムを有する。   The processing unit 10 includes a process plan creation unit 11 (process plan creation means) that creates a process plan based on the work management table and the personnel management table, and an allocation personnel number check unit 12 (assignment required) that checks the number of assigned personnel. (Number determination means), constraint check section 13 (constraint condition determination means) for checking the constraint conditions of the personnel scheduled to be allocated, work time result registration section 14 for registering the work time of the worker's results, and the skill of the worker is improved A plurality of programs of a skill up determination unit 15 (skill up determination means) for determining whether or not the user has

記憶部20には、作業工程の開始条件、終了条件、作業内容などの情報である工程情報201(図4参照)、要員の割り付け・引き当ての情報である要員割付引当情報202(図5参照)、要員の限度時間の情報である要員限度時間情報211(図6参照)、作業のシフト勤務の情報である要員シフト情報212(図7参照)、要員の保有の資格情報である要員保有資格情報213(要員資格情報)(図8参照)、要員のスキル情報である要員スキル情報214(図9参照)、作業に必要な資格情報である作業必要資格情報221(図10参照)、作業に必要なスキル情報である作業必要スキル情報222(図11参照)、要員の作業時間の実績情報である作業時間実績情報231(図12参照)、要員のスキルアップを判定するための基準情報であるスキルアップ基準情報232(図13参照)などが格納されている。なお、各情報の詳細は、図4から図13を参照して後述する。   The storage unit 20 includes process information 201 (see FIG. 4), which is information such as work process start conditions, end conditions, and work contents, and personnel allocation allocation information 202 (see FIG. 5), which is information on personnel allocation / allocation. Personnel limit time information 211 (refer to FIG. 6), which is information on the limit time of personnel, Personnel shift information 212 (refer to FIG. 7), which is information on work shift work, and Personnel retention qualification information which is qualification information of personnel possession 213 (personal qualification information) (see FIG. 8), personnel skill information 214 (see FIG. 9) which is the skill information of personnel, work necessary qualification information 221 (see FIG. 10) which is necessary qualification information for work, necessary for work Required skill information 222 (refer to FIG. 11), which is necessary skill information, work time result information 231 (refer to FIG. 12), which is a result of personnel work time, and criteria for determining the skill improvement of the personnel Skills reference information 232 (see FIG. 13), and the like is broadcast. Details of each information will be described later with reference to FIGS.

本実施形態の要員割付の操作方法の概要を、図2を参照して説明する。
図2は、表示画面の画面構成の一例を示す図である。図2には、工程計画作成部11が表示部40に表示した画面構成を示す。画面構成としては、工程管理表であるタスク別ガントチャート41と、要員管理表であるリソース別ガントチャート42などが含まれる。タスク別ガントチャート41から、各作業の開始日と終了日がわかり、作業に必要な要員数(分母に表示)および要員割付数(分子に表示)が表示されている。また、作業工程中の「0/2」(分子/分母)などの表記は、要員割付数/必要な要員数を意味し、割り付け後の制約チェック判定をふまえ色を変えて表示している。
An outline of the operation method of personnel assignment according to the present embodiment will be described with reference to FIG.
FIG. 2 is a diagram illustrating an example of a screen configuration of the display screen. In FIG. 2, the screen structure which the process plan preparation part 11 displayed on the display part 40 is shown. The screen configuration includes a task-specific Gantt chart 41, which is a process management table, and a resource-specific Gantt chart 42, which is a personnel management table. From the task-specific Gantt chart 41, the start date and end date of each operation are known, and the number of personnel required for the operation (displayed in the denominator) and the number of personnel allocation (displayed in the numerator) are displayed. In addition, notation such as “0/2” (numerator / denominator) in the work process means the number of personnel allocation / the number of necessary personnel, and is displayed in a different color based on the constraint check determination after allocation.

例えば、要員割付数がゼロ(未設定)の場合、黄色(細かいドット表示)、
要員割付数<必要な要員数(予定要員数)の場合、青色(少し荒いドット表示)、
要員割付数≧必要な要員数(予定要員数)の場合、緑色(斜め斜線)、
作業者が所定条件(制約条件)を満たしていない場合、赤色(クロス斜線)、
とするとよい。なお、本実施形態では4色で表示しているが、これに限定されるものではない。
For example, when the number of assigned personnel is zero (not set), yellow (displays fine dots)
If the number of assigned personnel is less than the required number of people (planned number of people), blue (a little rough dot display),
If the number of personnel allocation ≥ the required number of personnel (planned personnel), green (diagonal line),
If the worker does not meet the predetermined conditions (constraints), red (cross diagonal line),
It is good to do. In the present embodiment, four colors are displayed, but the present invention is not limited to this.

要員の割付方法は、下記の手順による。
(1)割付管理者が、タスク別ガントチャート41の作業工程をマウスなどで選択して、リソース別ガントチャート42にドラッグ&ドロップすると、リソース別ガントチャート42の要員に作業工程が割り付けられる。
(2)割り付けられると、タスク別ガントチャート41の作業工程の要員割付数がカウントアップする(符号43参照、第1のエレメント)。なお、リソース別ガントチャート42の割付状態を削除すると、要員割付数がカウントダウンする。
The staff assignment method is as follows.
(1) When the allocation manager selects a work process of the task-specific Gantt chart 41 with a mouse or the like and drags and drops it on the resource-specific Gantt chart 42, the work process is allocated to the personnel of the resource-specific Gantt chart 42.
(2) When assigned, the number of personnel assigned to the work process of the task-specific Gantt chart 41 is counted up (see reference numeral 43, first element). If the allocation state of the resource-specific Gantt chart 42 is deleted, the number of personnel allocation is counted down.

図2を参照して、タスク別ガントチャート41を説明すると、作業(YASU−PRJ2)は、7月3日から7月17日の予定であり、複数の作業内容で構成されており、作業(TSK01−03)は、7月3日、7月10日、7月12日の予定である。   The task-specific Gantt chart 41 will be described with reference to FIG. 2. The work (YASU-PRJ2) is scheduled from July 3 to July 17, and is composed of a plurality of work contents. TSK01-03) is scheduled for July 3, July 10, and July 12.

要員割付数/必要な要員数は、作業(TSK01−03)の7月3日の作業(青色表示)には、必要な要員数は2名であるが、割付数が1名となっている。作業(TSK01−03)の7月10日の作業(緑色表示)には、必要な要員数は0名(現時点では、未確定であることを意味する。)であるが、割付数が2名である。作業(TSK01−03)の7月12日の作業(黄色表示)には、必要な要員数は2名であるが、割付数がなされておらず0名となっている。さらに、作業(TSK01−02)の7月4日の作業(赤色表示)には、必要な要員数は2名であり、割付数が2名が割り当てられているが、作業者が所定の条件を満たしておらず、割り当て済みであるが確定されていない。   The number of personnel allocated / the number of necessary personnel is 2 for the work (blue display) on July 3 of the work (TSK01-03), but the number of assignment is 1 . For the work (TSK01-03) on July 10 (green display), the required number of personnel is 0 (currently means undecided), but the number of assignments is 2 It is. For the work (TSK01-03) on July 12 (yellow display), the required number of personnel is two, but the number of assignments is not made and is zero. Furthermore, the work (TSK01-02) on July 4th work (displayed in red) requires two personnel and is assigned two people. Is not satisfied and assigned but not confirmed.

一方、リソース別ガントチャート42を説明すると、作業(TSK01−03)の7月12日の作業(符号43参照、第1のエレメント)は作業者1に割り付けされ、緑色で割り付けが確定している(符号44参照、第2のエレメント)。また、作業(TSK01−03)の7月3日の作業は作業者1に割り付けされ、緑色で割り付けが確定している。作業(TSK01−02)の7月4日の作業は作業者1および作業者2に割り付けされたが、赤色で割り付けが確定していない。   On the other hand, the Gantt chart 42 by resource will be described. The work on July 12 of the work (TSK01-03) (see reference numeral 43, first element) is assigned to the worker 1, and the assignment is confirmed in green. (See symbol 44, second element). The work on July 3 of the work (TSK01-03) is assigned to the worker 1 and the assignment is confirmed in green. The work on July 4th of work (TSK01-02) was assigned to worker 1 and worker 2, but the assignment was not confirmed in red.

作業工程の調整が必要な場合には、タスク別ガントチャート41の該当作業工程を図面の横方向に移動させると、リソース別ガントチャート42の割り付けされた作業工程も、同期して移動することができる。この際には、移動後の状態で、制約チェック判定を行い色表示が変更される。   When adjustment of the work process is necessary, if the corresponding work process of the task-specific Gantt chart 41 is moved in the horizontal direction of the drawing, the work process assigned to the resource-specific Gantt chart 42 may be moved in synchronization. it can. At this time, the constraint display is determined in the state after the movement, and the color display is changed.

また、図示はしていないが、複数のプロジェクトの工程計画を切替えてみることができる。例えば、プロジェクトとして、A社の電気設備点検の工程計画、B社の電気設備点検の工程計画、C社の電気設備点検の工程計画のようなものが想定される。   Although not shown, it is possible to switch the process plans of a plurality of projects. For example, as a project, an electric equipment inspection process plan of company A, an electric equipment inspection process plan of company B, and an electric equipment inspection process plan of company C are assumed.

本実施形態では、要員割り付けは、必要な要員数が登録されていない場合においても実施できる。符号47には、要員割付数が2であるが、必要な要員数は0(ゼロ)である。工程計画をする際には、必要な要員数が確定していないが最小限の要員数を確保したい場合がある。このような場合にもドラッグ&ドロップ操作により、タスク別ガントチャート41からリソース別ガントチャート42に要員の割り付け操作ができる。符号47の第1のエレメントを指定してドラッグ操作し、符号48aにドロップ操作する。すると、第2のエレメントとして表示される。そして、同様に符号47の第1のエレメントを指定してドラッグ操作し、符号48bにドロップ操作する。すると、他の第2のエレメントとして表示される。符号48a、符号48bの要員が、制約チェック部13により所定の制約条件を満たすと判定されている場合、告知情報として緑色で表示される。第1のエレメントにおける表示は「2/0」となっており、要員割付数≧必要な要員数の場合を満たすため、割り付けを確定し、告知情報として緑色で表示されている。   In the present embodiment, the personnel assignment can be performed even when the necessary number of personnel is not registered. In the reference numeral 47, the number of assigned personnel is 2, but the required number of personnel is 0 (zero). When planning a process, the required number of personnel is not fixed, but there is a case where it is desired to secure a minimum number of personnel. Even in such a case, the assignment operation of the personnel from the task-specific Gantt chart 41 to the resource-specific Gantt chart 42 can be performed by a drag and drop operation. A first element designated by reference numeral 47 is designated and dragged, and a drop operation is carried out at numeral 48a. Then, it is displayed as the second element. Similarly, the first element denoted by reference numeral 47 is designated and dragged, and a drop operation is performed at numeral 48b. Then, it is displayed as another second element. When the personnel of the reference numerals 48a and 48b are determined to satisfy the predetermined constraint condition by the constraint check unit 13, they are displayed in green as notification information. The display in the first element is “2/0”, and in order to satisfy the case of the number of personnel allocation ≧ the necessary number of personnel, the allocation is confirmed and displayed in green as notification information.

図3は、時分別表示画面の画面構成の一例を示す図である。図2は日別表示の表示画面を示したが、図3は時分別表示の表示画面について説明する。リソース別ガントチャート42において、割り付けの時間帯において重複した場合には、作業工程のグラフを2段として表示(ブッキング(予約)が段表示)しており(符号45参照)、グラフの1つを赤色で他を緑色で表示がされている。ブッキングしない場合には、作業工程は重ならないで、緑色で表示されている(符号46参照)。   FIG. 3 is a diagram illustrating an example of a screen configuration of the hourly sorting display screen. FIG. 2 shows a display screen for daily display, but FIG. 3 explains a display screen for hourly and divided display. In the resource-specific Gantt chart 42, when there is an overlap in the allocation time zone, the graph of the work process is displayed as two stages (booking (reservation) is displayed in a column) (see reference numeral 45), and one of the graphs is displayed. The others are displayed in red and green. When the booking is not made, the work processes do not overlap and are displayed in green (see reference numeral 46).

割付管理者が、段表示を解消するため作業工程を図中の横方向にずらすと、工程計画装置100は、時間帯の重複が解消したならば段表示を解除し、エラー表示を示す赤色から緑色に変更することができる。また、段表示を解消するために、リソース別ガントチャート42内での要員間でドラッグ&ドロップ操作をしてもよい。具体的には、時間が重複している作業工程の一方について、「東北太郎」さんから「青葉一志」さんに変更する。このドラッグ&ドロップ操作は、複数のプロジェクトのガントチャートを同じ画面に表示している状態であれば、異なるプロジェクト間でも可能である。   When the allocation manager shifts the work process in the horizontal direction in the figure to cancel the column display, the process planning device 100 cancels the column display when the time zone overlap is resolved, and starts from the red indicating the error display. Can be changed to green. Further, in order to eliminate the column display, a drag and drop operation may be performed between the personnel in the resource-specific Gantt chart 42. Specifically, “Taro Tohoku” is changed to “Kazushi Aoba” for one of the work processes with overlapping time. This drag and drop operation can be performed between different projects as long as Gantt charts of a plurality of projects are displayed on the same screen.

次に各情報について図4から図13を参照して説明する。
図4は、工程情報のデータ構造の一例を示す図である。工程情報201には、管理番号(No)、工程ID(IDentification)、作業の開始日時、作業の終了日時、作業の具体的内容(作業)、所要員数(必要な要員数、予定要員数)、割り付け済み数である割付済数(要員割付数)などが含まれる。工程IDは、ユニークなIDでありタスク別ガントチャート41に、マウスなどで設定されたときに、処理部10が設定するとよい。具体的には、工程A1は、2008年4月1日の8時に開始され、同日の12時に終了予定であり、作業内容は部品交換、所要員数は3名であり、割付済数は1名と設定されている。
Next, each information will be described with reference to FIGS.
FIG. 4 is a diagram illustrating an example of a data structure of process information. The process information 201 includes a management number (No), a process ID (IDentification), a work start date and time, a work end date and time, a specific content of the work (work), a required number of persons (necessary number of persons, planned number of persons), Allocated number (number of personnel allocation) that is the allocated number is included. The process ID is a unique ID, and may be set by the processing unit 10 when set in the task-specific Gantt chart 41 with a mouse or the like. Specifically, the process A1 starts at 8:00 on April 1, 2008 and is scheduled to end at 12:00 on the same day. The work content is parts replacement, the required number is 3, and the assigned number is 1. Is set.

図5は、要員割付引当情報のデータ構造の一例を示す図である。要員割付引当情報202には、管理番号(No)、要員名(要員)、工程IDなどが含まれる。具体的には、田中さんは、工程A1を担当し、佐藤さんおよび鈴木さんは、工程B2を担当する。なお、図5には、要員ID、要員への連絡先などが含まれていてもよい。   FIG. 5 is a diagram illustrating an example of a data structure of personnel allocation allocation information. The personnel allocation allocation information 202 includes a management number (No), a personnel name (personnel), a process ID, and the like. Specifically, Mr. Tanaka is in charge of the process A1, and Mr. Sato and Mr. Suzuki are in charge of the process B2. Note that FIG. 5 may include a personnel ID, contact information for the personnel, and the like.

図6は、要員限度時間情報のデータ構造の一例を示す図である。要員限度時間情報211には、管理番号(No)、要員名(要員)、一日あたりの限度の作業時間(時間)などが含まれる。具体的には、佐藤さんは、一日あたり7時間の作業時間が限度であり、鈴木さんおよび田中さんは、一日あたり8時間の作業時間が限度である。また、同様に、要員限度時間情報には、週当り、月当り、年当りの要員限度時間情報がある(図示せず)。   FIG. 6 is a diagram illustrating an example of a data structure of personnel limit time information. The personnel limit time information 211 includes a management number (No), a personnel name (personnel), a maximum work time (hour) per day, and the like. Specifically, Mr. Sato has a limit of 7 hours per day, and Mr. Suzuki and Mr. Tanaka have a limit of 8 hours per day. Similarly, the personnel limit time information includes personnel limit time information per week, per month, and per year (not shown).

図7は、要員シフト情報のデータ構造の一例を示す図である。要員シフト情報212には、管理番号(No)、要員名(要員)、シフト情報(シフト)などが含まれる。具体的には、佐藤さんおよび田中さんは、土曜・日曜が休みであり、鈴木さんは、水曜日・木曜日が休みとなっている。   FIG. 7 is a diagram illustrating an example of a data structure of personnel shift information. The staff shift information 212 includes a management number (No), a staff name (personnel), shift information (shift), and the like. Specifically, Mr. Sato and Mr. Tanaka are closed on Saturdays and Sundays, while Mr. Suzuki is closed on Wednesdays and Thursdays.

図8は、要員保有資格情報のデータ構造の一例を示す図である。要員保有資格情報213には、管理番号(No)、要員名(要員)、資格名(資格)などが含まれる。具体的には、佐藤さんおよび鈴木さんは資格Aを保有しており、田中さんは資格Aおよび資格Bの両方の資格を保有している。なお、図8には、資格を取得した年月日などが含まれていることが好ましい。   FIG. 8 is a diagram illustrating an example of the data structure of the personnel possession qualification information. The personnel holding qualification information 213 includes a management number (No), a personnel name (personnel), a qualification name (qualification), and the like. Specifically, Mr. Sato and Mr. Suzuki have the qualification A, and Mr. Tanaka has both the qualification A and the qualification B. In addition, it is preferable that the date etc. which acquired the qualification are included in FIG.

図9は、要員スキル情報のデータ構造の一例を示す図である。要員スキル情報214には、管理番号(No)、要員名(要員)、作業内容(作業)、スキル内容(スキル)などが含まれる。具体的には、佐藤さんは、機器点検の作業に対するスキルAを保有しており、鈴木さんは、機器点検の作業に対するスキルAと部品交換の作業に対するスキルBを保有している。同様に、田中さんは、機器点検の作業に対するスキルAと部品交換の作業に対するスキルBを保有している。なお、図9には、スキルを取得した年月日などが含まれていることが好ましい。   FIG. 9 is a diagram illustrating an example of a data structure of personnel skill information. The personnel skill information 214 includes a management number (No), a personnel name (personnel), work content (work), skill content (skill), and the like. Specifically, Mr. Sato possesses skill A for equipment inspection work, and Mr. Suzuki possesses skill A for equipment inspection work and skill B for parts replacement work. Similarly, Mr. Tanaka has skill A for equipment inspection work and skill B for parts replacement work. Note that FIG. 9 preferably includes the date on which the skill is acquired.

図10は、作業必要資格情報のデータ構造の一例を示す図である。作業必要資格情報221には、管理番号(No)、作業内容(作業)、資格内容(資格)などが含まれる。具体的には、機器点検には資格Aが必要であり、部品交換には資格Bが必要である。   FIG. 10 is a diagram illustrating an example of a data structure of work necessary qualification information. The work necessary qualification information 221 includes a management number (No), work content (work), qualification content (qualification), and the like. Specifically, qualification A is required for equipment inspection, and qualification B is required for parts replacement.

図11は、作業必要スキル情報のデータ構造の一例を示す図である。作業必要スキル情報222には、管理番号(No)、作業内容(作業)、スキル内容(スキル)などが含まれる。具体的には、機器点検の作業にはスキルAが必要であり、部品交換の作業にはスキルBが必要である。   FIG. 11 is a diagram illustrating an example of a data structure of work-necessary skill information. The work required skill information 222 includes a management number (No), work content (work), skill content (skill), and the like. Specifically, skill A is required for the equipment inspection work, and skill B is required for the part replacement work.

図12は、作業時間実績情報のデータ構造の一例を示す図である。作業時間実績情報231には、管理番号(No)、要員名(要員)、工程ID、作業予定の開始日時、作業予定の終了日時、作業内容(作業)、実績時間などが含まれる。作業時間実績登録部14(図1参照)は、作業時間実績の登録要求があると、工程IDをキーとして、工程情報201および要員割付引当情報202を検索して、要員、作業、開始日時、終了日時の情報を取得し、入力された実績時間と関連付けて、作業時間実績情報231が作成される。なお、図12には、作業実績の開始日時、作業実績の終了日時なども含めてもよい。また、実績時間は、開始時間と終了時間との差分時間ではなく、実際に作業した実績時間であるため、佐藤さんと鈴木さんとの実績時間が異なっている。   FIG. 12 is a diagram illustrating an example of a data structure of work time record information. The work time result information 231 includes a management number (No), a personnel name (person), a process ID, a work schedule start date and time, a work schedule end date and time, a work content (work), a performance time, and the like. When there is a registration request for the work time record, the work time record registration unit 14 (see FIG. 1) searches the process information 201 and the personnel allocation allocation information 202 using the process ID as a key, Information on the end date and time is acquired, and the work time result information 231 is created in association with the input result time. Note that FIG. 12 may also include the start date / time of work results, the end date / time of work results, and the like. In addition, the actual time is not the difference time between the start time and the end time, but is the actual time actually worked. Therefore, the actual time differs between Mr. Sato and Mr. Suzuki.

図13は、スキルアップ基準情報のデータ構造の一例を示す図である。スキルアップ基準情報232には、管理番号(No)、スキル内容(スキル)、作業内容(作業)、スキルアップに必要な時間などが含まれる。スキルアップ判定部15(図1参照)は、各要員の作業内容の累積作業時間と、スキルアップに必要な時間とを比較し、所定の時間に達したと判定すると、要員スキル情報214に登録する。具体的には、スキルAは機器点検の補助の作業を150時間必要であり、スキルBは機器点検の作業を200時間以上が必要である。すなわち、スキルAの機器点検には、機器点検の補助作業に経験を積む必要があり、また、スキルBの部品交換には、機器点検の作業の経験を積む必要があることを意味する。   FIG. 13 is a diagram illustrating an example of a data structure of skill-up criterion information. The skill up reference information 232 includes a management number (No), skill content (skill), work content (work), time required for skill up, and the like. The skill-up determination unit 15 (see FIG. 1) compares the accumulated work time of each worker's work content with the time required for skill improvement, and if it is determined that the predetermined time has been reached, it is registered in the personnel skill information 214. To do. Specifically, Skill A requires 150 hours of assistance for equipment inspection, and Skill B requires 200 hours or more for equipment inspection. That is, it means that it is necessary to gain experience in assisting equipment inspection for skill A equipment inspection, and it is necessary to gain experience in equipment inspection work for replacing parts of skill B.

次に要員割付手順の詳細な方法について、図14から図16を参照して説明する。
図14は、要員割付手順の方法(ステップS101)を示す図である。図14(a)には、画面での新規に作業工程を登録するときの操作例を示し、図14(b)は、工程情報201および要員割付引当情報202の登録内容について示す。割付管理者は、タスク別ガントチャート41上で、マウスなどを使用して矩形(点線部分)を描いて、作業工程を作成する。描くときには、5分刻みなどのグリッド機能を活用して分単位にひくことが好ましい。正確に描くときには、タスク別ガントチャート41を拡大表示して、1分単位などのグリッド機能を利用するとよい。この時点においては、工程情報201および要員割付引当情報202は、空白の状態である。矩形を確定すると、次のステップS102に進む。
Next, a detailed method of the personnel assignment procedure will be described with reference to FIGS.
FIG. 14 is a diagram showing a method for assigning personnel (step S101). FIG. 14A shows an operation example when a new work process is registered on the screen, and FIG. 14B shows the registration contents of the process information 201 and the personnel allocation allocation information 202. The assignment manager creates a work process by drawing a rectangle (dotted line portion) on the task-specific Gantt chart 41 using a mouse or the like. When drawing, it is preferable to use a grid function such as a 5-minute increment to draw in minutes. When drawing accurately, it is preferable to enlarge and display the task-specific Gantt chart 41 and use a grid function such as one minute unit. At this time, the process information 201 and the personnel allocation allocation information 202 are blank. When the rectangle is confirmed, the process proceeds to the next step S102.

図15は、要員割付手順の方法(ステップS102)を示す図である。図15(a)には、タスク別ガントチャート41上に作業工程が配置がされた状態であり、要員割付数/必要な要員数が入力され、作業工程をリソース別ガントチャート42にドラッグ&アンドするときの操作例を示し、図15(b)は、工程情報201および要員割付引当情報202の登録内容について示す。工程計画作成部11(図1参照)は、タスク別ガントチャート41上で作業工程の配置状況に応じて、工程情報201に工程ID、開始日時、終了日時、所要員数、割付済数を登録する。作業内容(作業)は、図2に示した作業名から取得し工程情報201に登録する。なお、「TSK01−03」などを「部品交換」に変換するためのテーブルが記憶されているものとする。そして、次のステップS103に進む。   FIG. 15 is a diagram showing a method for assigning personnel (step S102). FIG. 15A shows a state in which work processes are arranged on the task-specific Gantt chart 41. The number of assigned personnel / the number of necessary personnel is input, and the process is dragged and dragged to the resource-specific Gantt chart 42. FIG. 15B shows the registered contents of the process information 201 and the personnel allocation allocation information 202. The process plan creation unit 11 (see FIG. 1) registers the process ID, the start date / time, the end date / time, the required number, and the allocated number in the process information 201 on the task-specific Gantt chart 41 in accordance with the arrangement state of the work process. . The work content (work) is acquired from the work name shown in FIG. 2 and registered in the process information 201. It is assumed that a table for converting “TSK01-03” or the like to “part replacement” is stored. Then, the process proceeds to the next step S103.

図16は、要員割付手順の方法(ステップS103)を示す図である。図16(a)には、リソース別ガントチャート42に、作業工程が割り付けをしたとき、エラー表示である赤色が表示された状態を示し、図16(b)には、エラー表示されたときの工程情報201および要員割付引当情報202の登録内容について示す。図16(a)に示す工程A1は、ひとりを割り付けしているので、要員割付引当情報202に登録されるとともに、要員割付数は1(図中(1/3)を参照)となっているが、エラー判定されているため確定されていない。このため、工程情報201の割付済数は0のままとなっている。なお、エラー判定された際に、最終的に要員管理者が割付済数を確定してもよい。   FIG. 16 is a diagram showing a method (step S103) of the personnel assignment procedure. FIG. 16A shows a state in which red, which is an error display, is displayed on the resource-specific Gantt chart 42 when a work process is assigned, and FIG. 16B shows a state when an error is displayed. The registration contents of the process information 201 and the personnel allocation allocation information 202 will be described. In the process A1 shown in FIG. 16A, since one person is assigned, it is registered in the personnel allocation allocation information 202, and the number of personnel allocation is 1 (see (1/3) in the figure). However, it is not fixed because an error is determined. For this reason, the allocated number of process information 201 remains 0. When an error is determined, the personnel manager may finally determine the number of assigned items.

図16(a)に示すリソース別ガントチャート42の工程A1および工程B2には、エラー判定がされている。部品交換作業は、作業必要スキル情報222からスキルBが必要であり、かつ、作業必要資格情報221から資格Bが必要である。しかしながら、佐藤さんは、要員スキル情報214を参照することによりスキルAであるため、前記の所定条件を満たしていないと判定(スキル不足のエラー判定)となっている。また、佐藤さんは、要員限度時間情報211から、一日あたりの作業時間は7時間と制限されているが、工程A1および工程B2との合計は8時間となりエラー判定となっている。   Error determination is performed in step A1 and step B2 of the resource-specific Gantt chart 42 shown in FIG. The part replacement work requires the skill B from the work required skill information 222 and the qualification B from the work necessary qualification information 221. However, since Mr. Sato is skill A by referring to the personnel skill information 214, it is determined that the predetermined condition is not satisfied (error determination of insufficient skill). In addition, Mr. Sato is limited to 7 hours in the work time per day based on the personnel limit time information 211, but the sum of the process A1 and the process B2 is 8 hours, which is an error determination.

図16(c)には、正常に割り付けが行われた場合のタスク別ガントチャート41およびリソース別ガントチャート42の画面例について示す。タスク別ガントチャート41の工程A1の場合、リソース別ガントチャート42に示す田中さんに割り付けが確定され、タスク別ガントチャート41の工程B2の場合、リソース別ガントチャート42に示す佐藤さんおよび鈴木さんに割り付けが確定されている。このとき、図4に示す工程情報201の登録状態となり、かつ、図5に示す要員割付引当情報202の登録状態となる。なお、工程A1の割付変更する際、リソース別ガントチャート42内で、ドラッグ&ドロップ操作により、佐藤さんから田中さんに変更することができる。   FIG. 16C shows a screen example of the task-specific Gantt chart 41 and the resource-specific Gantt chart 42 when the assignment is performed normally. In the process A1 of the task-specific Gantt chart 41, the assignment is confirmed to Mr. Tanaka shown in the resource-specific Gantt chart 42, and in the case of the process B2 of the task-specific Gantt chart 41, Mr. Sato and Mr. Suzuki shown in the resource-specific Gantt chart 42 Allocation is finalized. At this time, the process information 201 is registered as shown in FIG. 4, and the personnel allocation allocation information 202 is registered as shown in FIG. When changing the allocation of the process A1, in the resource-specific Gantt chart 42, it is possible to change from Mr. Sato to Mr. Tanaka by a drag and drop operation.

図17は、要員割付手順の処理を示すフローチャートである。図17には、ステップS102における工程計画作成部11の処理フローを示す。工程計画作成部11は、タスク別ガントチャート41からリソース別ガントチャート42へのドラッグ&ドロップ(ドラッグアンドドロップ)の操作があるか否かを判定する(ステップS1)。ドラッグ&ドロップの操作がなければ(ステップS1,No)、ステップS1に戻り、ドラッグ&ドロップの操作であれば(ステップS1,Yes)、ステップS2に進む。なお、ステップS1において、対象を選択し移動する操作としてドラッグ&ドロップの操作について示したがこれに限定されるものではない。例えば、タスク別ガントチャート41の工程を選択し、マウスなどの右クリックでメニューを選択し、メニュー内のリソース別ガントチャート42を選択などの操作であってもよい。   FIG. 17 is a flowchart showing the process of the personnel assignment procedure. In FIG. 17, the processing flow of the process plan preparation part 11 in step S102 is shown. The process plan creation unit 11 determines whether or not there is a drag and drop (drag and drop) operation from the task-specific Gantt chart 41 to the resource-specific Gantt chart 42 (Step S1). If there is no drag and drop operation (step S1, No), the process returns to step S1, and if it is a drag and drop operation (step S1, Yes), the process proceeds to step S2. In step S1, the drag and drop operation is shown as the operation for selecting and moving the target, but the present invention is not limited to this. For example, an operation such as selecting a process of the task-specific Gantt chart 41, selecting a menu by right-clicking with a mouse or the like, and selecting a resource-specific Gantt chart 42 in the menu may be performed.

工程計画作成部11は、タスク別ガントチャート41で指定されたセル(画面上の位置情報を有する第1のエレメント)に基づいて、工程IDを特定し(ステップS2)、リソース別ガントチャート42にドロップされたセル(第2のエレメント)に基づいて、要員と工程IDとを関連付けて要員割付引当情報202に登録し(ステップS3)、処理を終了する。なお、工程IDとセルとは関連付けられているものとする。   The process plan creation unit 11 specifies a process ID based on the cell (first element having position information on the screen) specified in the task-specific Gantt chart 41 (step S2), and the resource-specific Gantt chart 42 Based on the dropped cell (second element), the personnel and the process ID are associated with each other and registered in the personnel allocation allocation information 202 (step S3), and the process is terminated. In addition, process ID and a cell shall be linked | related.

図18は、要員割付時の制約チェック処理の機能関係を示す図である。入力部30からドラッグ&ドロップの指令を受理すると、割付要員数チェック部12は、工程情報201と要員割付引当情報202を参照して、割付状態とエラー状態の表示を表示部40に指令する。一方、制約チェック部13は、工程情報201と要員割付引当情報202を参照して、作業内容および作業時間を特定し、要員が保有している要員保有資格情報213、要員スキル情報214に基づいて、特定した作業内容が作業必要資格情報221および作業必要スキル情報222を満たすか否かを判定する。また、制約チェック部13は、特定された作業時間が、要員限度時間情報211、要員シフト情報212を満たすか否かを判定する。判定結果を表示部40に表示指示する。   FIG. 18 is a diagram illustrating the functional relationship of the constraint check process when assigning personnel. When the drag & drop command is received from the input unit 30, the allocation number-of-workers check unit 12 refers to the process information 201 and the personnel allocation allocation information 202 and instructs the display unit 40 to display the allocation status and the error status. On the other hand, the constraint check unit 13 refers to the process information 201 and the personnel allocation allocation information 202, identifies the work content and the work time, and based on the personnel possession qualification information 213 and the personnel skill information 214 possessed by the personnel. Then, it is determined whether or not the specified work content satisfies the work qualification information 221 and the work skill information 222. Further, the constraint checking unit 13 determines whether or not the specified work time satisfies the personnel limit time information 211 and the personnel shift information 212. The display unit 40 is instructed to display the determination result.

図19は、要員割付時の制約チェック処理を示すフローチャートである。制約チェック部13は、タスク別ガントチャート41からリソース別ガントチャート42へのドラッグ&ドロップの操作を受理すると(ステップS10)、ドロップした要員の当日別工程と時間帯が重複なしか否かを判定し(ステップS11)、重複なしの場合(ステップS11,Yes)、ステップS12に進む。重複している場合(ステップS11,No)、重複工程ガントチャートを段表示し、重複数を表示し、エラー色表示対象とし(ステップS21)、ステップS12に進む。   FIG. 19 is a flowchart showing a constraint check process when assigning personnel. When the constraint checking unit 13 accepts a drag and drop operation from the task-specific Gantt chart 41 to the resource-specific Gantt chart 42 (Step S10), the constraint check unit 13 determines whether or not the day-by-day process and the time zone of the dropped personnel overlap. If there is no overlap (step S11, Yes), the process proceeds to step S12. If there is an overlap (No in step S11), the overlap process Gantt chart is displayed in stages, the multiple overlap is displayed, and the error color is displayed (step S21), and the process proceeds to step S12.

ステップS12において、制約チェック部13は、ドロップした要員のシフト出勤対象日か否かを判定する。シフト出勤対象日である場合(ステップS12,Yes)、ステップS13に進む。シフト出勤対象日でない場合(ステップS12,No)、エラー色表示対象とし(ステップS22)、ステップS13に進む。   In step S <b> 12, the constraint checking unit 13 determines whether or not it is a shift attendance target date of the dropped personnel. When it is a shift work day (step S12, Yes), it progresses to step S13. When it is not a shift work day (step S12, No), it is set as an error color display target (step S22), and the process proceeds to step S13.

ステップS13において、制約チェック部13は、ドロップした要員に当該工程実施に必要な資格があるか否かを判定する。資格がある場合(ステップS13,Yes)、ステップS14に進む。資格がない場合(ステップS13,No)、エラー色表示対象とし(ステップS23)、ステップS14に進む。   In step S <b> 13, the constraint checking unit 13 determines whether the dropped personnel have the qualifications necessary for performing the process. If it is qualified (step S13, Yes), the process proceeds to step S14. When there is no qualification (No at Step S13), the error color is to be displayed (Step S23), and the process proceeds to Step S14.

ステップS14において、制約チェック部13は、ドロップした要員に当該工程実施に必要なスキルがあるか否かを判定する。スキルがある場合(ステップS14,Yes)、ステップS15に進む。スキルがない場合(ステップS14,No)、エラー色表示対象とし(ステップS24)、ステップS15に進む。   In step S <b> 14, the constraint checking unit 13 determines whether the dropped personnel have the skills necessary for performing the process. If there is a skill (step S14, Yes), the process proceeds to step S15. If there is no skill (No at Step S14), the error color is displayed (Step S24), and the process proceeds to Step S15.

ステップS15において、制約チェック部13は、ドロップした要員の日ごと勤務時間限度を超過しないか否かを判定する。超過しない場合(ステップS15,Yes)、ステップS16に進む。超過する場合(ステップS15,No)、エラー色表示対象とし(ステップS25)、ステップS16に進む。   In step S15, the constraint checking unit 13 determines whether or not the daily work limit of the dropped personnel is exceeded. When not exceeding (step S15, Yes), it progresses to step S16. When it exceeds (No at Step S15), it is set as an error color display target (Step S25), and the process proceeds to Step S16.

ステップS16において、制約チェック部13は、エラー表示対象か否かを判定し、エラー表示対象の場合(ステップS16,Yes)、エラー色(具体的には赤色)で割付結果を表示し(ステップS17)、処理を終了する。一方、エラー表示対象でない場合(ステップS16,No)、通常色(具体的には緑色)の割付結果を表示し(ステップS18)、処理を終了する。   In step S16, the constraint check unit 13 determines whether or not it is an error display target, and if it is an error display target (Yes in step S16), displays the allocation result in an error color (specifically, red) (step S17). ), The process is terminated. On the other hand, if it is not an error display target (No at Step S16), the allocation result of the normal color (specifically, green) is displayed (Step S18), and the process ends.

具体的には、部品交換の作業工程を、鈴木さんにドラッグ&ドロップされたとすると、
鈴木さんは、要員保有資格情報213から資格Aを有し、要員スキル情報214から部品交換においてスキルBを有していることがわかる。部品交換の作業工程に必要な資格は、作業必要資格情報221から資格Bであり、かつ、作業必要スキル情報222からスキルBであることがわかる。このため、鈴木さんは、ステップS14において、部品交換に必要なスキルがあると判定されるが、ステップS13において、部品交換作業に必要な資格がないため、ステップS23において、エラー色表示対象となる。
Specifically, if the part replacement work process is dragged and dropped by Mr. Suzuki,
It can be seen that Mr. Suzuki has the qualification A from the staff possession qualification information 213 and the skill B in the parts replacement from the staff skill information 214. It can be seen that the qualification necessary for the part replacement work process is the qualification B from the work qualification information 221 and the skill B from the work necessary skill information 222. For this reason, it is determined in Step S14 that Mr. Suzuki has the skills necessary for parts replacement. However, since there is no qualification necessary for parts replacement work in Step S13, Mr. Suzuki becomes an error color display target in Step S23. .

図19においては、リソース別ガントチャート42へのドラッグ&ドロップ操作を受理後、要員の当該工程実施に必要な資格があるか否か(例えば、ステップS13)などを判定しているが、これに限定されるものではない。例えば、タスク別ガントチャート41の作業工程(第1のエレメント)をクリックした段階で、リソース別ガントチャート42内の要員の中で必要な資格があるか否かを判定して、その判定結果をエラー色表示対象としてもよい(図21参照)。   In FIG. 19, after receiving the drag and drop operation to the resource-specific Gantt chart 42, it is determined whether or not a person has the qualification necessary for performing the process (for example, step S <b> 13). It is not limited. For example, when the work process (first element) of the task-specific Gantt chart 41 is clicked, it is determined whether there is a necessary qualification among the personnel in the resource-specific Gantt chart 42, and the determination result is obtained. An error color may be displayed (see FIG. 21).

図21は、表示画面の画面構成のその他の例を示す図である。図21の表示画面は、図2に示した表示画面と基本的には同じであるが、作業(TSK01−02)の7月4日の作業(符号49参照)を選択した時点で、リソース別ガントチャート42の要員の欄を、「必要な資格がない」として、特定のエラー色(図では細かいドット表示)で表示してもよい。具体的には、行421、行422がエラー色で表示されている。この場合においても、要員の割付の操作はできるが、作業者の所定の条件(制約条件)を満たさないとして、赤色(クロス斜線)で表示されている。   FIG. 21 is a diagram illustrating another example of the screen configuration of the display screen. The display screen of FIG. 21 is basically the same as the display screen shown in FIG. 2, but at the time when the work on July 4th (see reference numeral 49) of the work (TSK01-02) is selected, it is classified by resource. The personnel column of the Gantt chart 42 may be displayed with a specific error color (indicated by fine dots in the figure) as “no necessary qualification”. Specifically, the row 421 and the row 422 are displayed in error colors. In this case as well, the operation of assigning personnel can be performed, but it is displayed in red (cross diagonal lines) as not satisfying the operator's predetermined condition (constraint condition).

図20は、スキルアップ判定処理の機能関係を示す図である。処理部10は、入力部30から作業時間実績登録要求を受理すると、作業時間実績登録部14が、工程情報201および要員割付引当情報202を参照して、作業時間実績情報231を作成し、入力された実績時間を登録する。また、作業時間実績登録部14は、要員の作業内容毎に累積の作業時間を算出し、作業時間実績情報231に登録し、登録通知をスキルアップ判定部15に通知する。   FIG. 20 is a diagram illustrating a functional relationship of the skill up determination process. When the processing unit 10 receives the work time result registration request from the input unit 30, the work time result registration unit 14 creates the work time result information 231 by referring to the process information 201 and the personnel allocation allocation information 202, and inputs the work time result information 231. Registered actual time. The work time record registration unit 14 calculates the accumulated work time for each work content of the personnel, registers the work time record information 231, and notifies the skill up determination unit 15 of registration notification.

スキルアップ判定部15は、登録通知を受理すると、要員の作業内容毎に累積の作業時間および作業必要スキル情報222を取得し、作業必要スキル情報222に関し、要員の作業内容毎に累積の作業時間とスキルアップ基準情報232とを比較して、スキルアップの所定の時間に達したと判定したとき、要員スキル情報214に登録する。具体的には、佐藤さんの場合、スキルアップ判定部15は、スキルアップ基準情報232を参照して機器点検の作業の200時間を超過した場合スキルBと判定し、要員スキル情報214に機器点検の作業のスキルBを追加して登録する。   Upon receiving the registration notification, the skill-up determination unit 15 acquires the accumulated work time and work-necessary skill information 222 for each work content of the personnel, and regarding the work-necessary skill information 222, the accumulated work time for each work content of the personnel. And skill up reference information 232 are compared, and when it is determined that a predetermined skill up time has been reached, it is registered in the personnel skill information 214. Specifically, in the case of Mr. Sato, the skill-up determination unit 15 refers to the skill-up standard information 232, determines that it exceeds 200 hours of equipment inspection work, determines that it is skill B, and equipment inspection in the personnel skill information 214 Add and register skill B for work.

本実施形態の工程計画装置100は、表示部40(表示手段)に表示された工程管理表(例えば、タスク別ガントチャート41)の画面上から第1のエレメント(例えば、符号43)をドラッグアンドドロップなどの対象を選択し移動する操作により表示部40に表示された要員管理表(例えば、リソース別ガントチャート42)に第2のエレメント(例えば、符号44)として割り付け要求をする入力部30(入力手段)と、第1のエレメントに係る作業工程に必要な要員数と割り付け要求された1以上の前記第2のエレメントに該当する要員数との大小関係を判定する割付要員数チェック部12(割付要員数判定手段)と、第2のエレメントに該当する要員が、記憶部20(記憶手段)に格納されている制約条件を満たすか否かを判定する制約チェック部13(制約判定手段)と、割り付け要求された第2のエレメントを要員管理表に表示するとともに、第2のエレメントに該当する要員と第1のエレメントに該当する作業工程とを関連付けて要員割付引当情報202として記憶部20に登録し、登録された要員が制約判定手段で所定の制約条件を満たすと判定された場合、第2のエレメントへの割り付け要求を確定する工程計画作成部11(工程計画作成手段)とを有する。   The process planning apparatus 100 according to the present embodiment drags the first element (for example, reference numeral 43) from the screen of the process management table (for example, task-specific Gantt chart 41) displayed on the display unit 40 (display unit). An input unit 30 (for example, 44) assigned to the personnel management table (for example, resource-specific Gantt chart 42) displayed on the display unit 40 by selecting and moving a target such as a drop. An allocation means number check unit 12 for determining a magnitude relationship between the input means) and the number of personnel required for the work process related to the first element and the number of personnel corresponding to the one or more second elements requested to be allocated; Allocation personnel number determination means) and whether the personnel corresponding to the second element satisfy the constraint condition stored in the storage unit 20 (storage means). The constraint check unit 13 (constraint determination means) displays the second element requested to be allocated in the personnel management table, and associates the personnel corresponding to the second element with the work process corresponding to the first element. The process plan creation unit 11 that registers in the storage unit 20 as the personnel allocation allocation information 202 and determines the allocation request to the second element when it is determined by the constraint determination means that the registered personnel satisfy a predetermined constraint condition. (Process plan creation means).

工程管理表および要員管理表は、ガントチャートとして表示部40に表示されており、
工程計画作成部11は、第1のエレメントに係る作業工程に割り付けた要員割付数と作業工程に必要な要員数とを表示し、ドラッグアンドドロップ操作により要員管理表に第2のエレメントが割り付けられると、要員割付数に加算して表示することができる。
The process management table and personnel management table are displayed on the display unit 40 as Gantt charts,
The process plan creation unit 11 displays the number of personnel allocated to the work process related to the first element and the number of personnel required for the work process, and the second element is allocated to the staff management table by a drag and drop operation. And added to the number of personnel assignments.

工程計画作成部11は、第1のエレメントに入力された作業工程に必要な要員数を受理すると、作業工程と関連付けて工程情報201として記憶部20に登録し、割付要員数チェック部12は、登録された要員の要員数が必要な要員数に満たないと判定した場合、第1のエレメントに割り付けが不足している旨の告知情報を表示することができる。   When the process plan creation unit 11 receives the number of personnel required for the work process input to the first element, the process plan creation unit 11 associates it with the work process and registers it in the storage unit 20 as the process information 201. When it is determined that the number of registered personnel is less than the required number of personnel, notification information indicating that the allocation of the first element is insufficient can be displayed.

工程計画作成部11は、制約チェック部13が制約条件を満たさないと判定した場合、第1のエレメントおよび第2のエレメントに、割り付けができない旨の告知情報を表示することができる。   If the constraint check unit 13 determines that the constraint condition is not satisfied, the process plan creation unit 11 can display notification information indicating that allocation cannot be performed for the first element and the second element.

記憶部20には、作業工程に必要とする作業資格の情報である作業必要資格情報221と、作業工程に必要とするスキルの情報である作業必要スキル情報222と、要員が保有する資格の情報である要員保有資格情報213(要員資格情報)と、要員が保有するスキルの情報である要員スキル情報214と、が格納されており、制約チェック部13は、要員資格情報が作業必要資格情報221を満たすか否か、かつ、要員スキル情報214が、作業必要スキル情報222を満たすか否かを判定することができる。   The storage unit 20 includes work qualification information 221 that is work qualification information necessary for the work process, work skill information 222 that is skill information necessary for the work process, and qualification information held by personnel. Are stored, and personnel skill information 214, which is information on skills held by the personnel, is stored, and the constraint check unit 13 includes the personnel qualification information as the necessary qualification information 221. It can be determined whether or not the personnel skill information 214 satisfies the work skill information 222.

記憶部20には、作業工程におけるスキルアップの基準情報であるスキルアップ基準情報232と、作業工程毎の要員の作業時間の実績情報である作業時間実績情報231(要員作業実績情報)と、が格納されており、工程計画装置100は、さらに、作業工程における要員作業実績情報がスキルアップ基準情報を満たすか否かを判定し、満たす場合には、満たしたスキル情報を要員スキル情報214に登録するスキルアップ判定部15(スキルアップ判定手段)を有する。   The storage unit 20 includes skill improvement reference information 232 that is reference information for skill improvement in a work process, and work time result information 231 (personnel work result information) that is a result information of a worker's work time for each work process. The process planning device 100 further determines whether or not the personnel work performance information in the work process satisfies the skill-up standard information, and if so, registers the satisfied skill information in the personnel skill information 214. A skill-up determination unit 15 (skill-up determination means).

10 処理部
11 工程計画作成部(工程計画作成手段)
12 割付要員数チェック部(割付要員数判定手段)
13 制約チェック部(制約判定手段)
14 作業時間実績登録部
15 スキルアップ判定部(スキルアップ判定手段)
20 記憶部(記憶手段)
30 入力部(入力手段)
40 表示部(表示手段)
41 タスク別ガントチャート(工程管理表)
42 リソース別ガントチャート(要員管理表)
43 第1のエレメント
44 第2のエレメント
50 通信部
100 工程計画装置
201 工程情報
202 要員割付引当情報
211 要員限度時間情報
212 要員シフト情報
213 要員保有資格情報(要員資格情報)
214 要員スキル情報
221 作業必要資格情報
222 作業必要スキル情報
231 作業時間実績情報(要員作業実績情報)
232 スキルアップ基準情報
300 ネットワーク
10 processing section 11 process plan creation section (process plan creation means)
12 Allocation staff number check (allocation staff number determination means)
13 Constraint check unit (Constraint determination means)
14 Work time record registration part 15 Skill up judgment part (skill up judgment means)
20 storage unit (storage means)
30 Input section (input means)
40 Display section (display means)
41 Gantt chart by task (process control table)
42 Gantt chart by resource (personnel management table)
43 First element 44 Second element 50 Communication unit 100 Process planning device 201 Process information 202 Personnel allocation allocation information 211 Personnel limit time information 212 Personnel shift information 213 Personnel holding qualification information (personnel qualification information)
214 Personnel skill information 221 Work necessary qualification information 222 Work required skill information 231 Work time result information (personnel work result information)
232 Skill Up Standard Information 300 Network

Claims (6)

作業工程に必要な要員を割り付けて工程計画をする工程計画装置において、
表示手段に表示された工程管理表の画面上から第1のエレメントを選択し移動する操作により前記表示手段に表示された要員管理表に第2のエレメントとして割り付け要求をする入力手段と、
前記第1のエレメントに係る作業工程に必要な要員数と、割り付け要求された1以上の前記第2のエレメントに該当する要員数との大小関係を判定する割付要員数判定手段と、
前記第2のエレメントに該当する要員が、記憶手段に格納されている制約条件を満たすか否かを判定する制約判定手段と、
前記選択し移動する操作により前記割り付け要求された第2のエレメントを前記要員管理表に表示するとともに、前記第2のエレメントに該当する要員と前記第1のエレメントに該当する作業工程とを関連付けて要員割付引当情報として前記記憶手段に登録し、登録された要員が前記制約判定手段で所定の制約条件を満たすと判定された場合、第2のエレメントへの割り付け要求を確定する工程計画作成手段とを有し、
前記工程管理表および前記要員管理表は、ガントチャートとして前記表示手段に表示されており、
前記工程計画作成手段は、前記第1のエレメントに係る作業工程を示す枠内に、前記作業工程に割り付けた要員割付数と前記作業工程に必要な要員数とを表示し、前記選択し移動する操作により前記要員管理表に前記第2のエレメントが割り付けられると、前記要員割付数に加算して表示する
ことを特徴とする工程計画装置。
In the process planning device that assigns the necessary personnel to the work process and plans the process,
An input means for making an allocation request as a second element to the personnel management table displayed on the display means by an operation of selecting and moving the first element from the screen of the process management table displayed on the display means;
An allotted manpower determining means for determining a magnitude relationship between the number of personnel required for the work process related to the first element and the number of personnel corresponding to one or more second elements requested to be allocated;
Constraint determination means for determining whether or not the personnel corresponding to the second element satisfies the constraint conditions stored in the storage means;
The second element requested to be allocated by the operation of selecting and moving is displayed on the personnel management table, and the personnel corresponding to the second element and the work process corresponding to the first element are associated with each other. Process plan creation means for registering in the storage means as personnel allocation allocation information, and confirming the allocation request to the second element when the registered personnel are determined to satisfy a predetermined constraint condition by the constraint determination means; Have
The process management table and the personnel management table are displayed on the display means as a Gantt chart,
The process plan creation means displays the number of personnel assigned to the work process and the number of personnel required for the work process in a frame indicating the work process related to the first element, and selects and moves the work plan. When the second element is assigned to the personnel management table by an operation , the process planning device displays the result by adding to the personnel allocation number .
前記工程計画作成手段は、
前記第1のエレメントに入力された前記作業工程に必要な要員数を受理すると、前記作業工程と関連付けて工程情報として前記記憶手段に登録し、
前記割付要員数判定手段は、
前記登録された要員の要員数が前記必要な要員数に満たないと判定した場合、前記第1のエレメントに割り付けが不足している旨の告知情報を表示する
ことを特徴とする請求項1に記載の工程計画装置。
The process plan creation means includes:
When the number of personnel required for the work process input to the first element is received, it is registered in the storage means as process information in association with the work process,
The allocation personnel number judging means is:
The notification information indicating that the allocation is insufficient in the first element is displayed when it is determined that the number of registered personnel is less than the necessary number of personnel. The process planning device described.
前記制約判定手段は、
前記制約判定手段が前記制約条件を満たさないと判定した場合、前記第1のエレメントおよび前記第2のエレメントに、割り付けができない旨の告知情報を表示する
ことを特徴とする請求項1に記載の工程計画装置。
The constraint determining means is
2. The notification information indicating that allocation cannot be performed is displayed on the first element and the second element when the constraint determination unit determines that the constraint condition is not satisfied. 2. Process planning device.
前記記憶手段には、
前記作業工程に必要とする作業資格の情報である作業必要資格情報と、
前記作業工程に必要とするスキルの情報である作業必要スキル情報と、
前記要員が保有する資格の情報である要員資格情報と、
前記要員が保有するスキルの情報である要員スキル情報と、が格納されており、
前記制約判定手段は、前記要員資格情報が前記作業必要資格情報を満たすか否か、かつ、前記要員スキル情報が前記作業必要スキル情報を満たすか否かを判定する
ことを特徴とする請求項1に記載の工程計画装置。
In the storage means,
Work qualification information that is work qualification information required for the work process;
Work required skill information that is information of skills required for the work process;
Employee qualification information, which is qualification information held by the personnel,
Personnel skill information, which is information of skills held by the personnel, is stored,
The restriction determination unit determines whether the personnel qualification information satisfies the work requirement qualification information and whether the personnel skill information satisfies the work requirement skill information. The process planning device described in 1.
前記記憶手段には、
前記作業工程におけるスキルアップの基準情報であるスキルアップ基準情報と、
前記作業工程毎の要員の作業時間の実績情報である要員作業実績情報と、が格納されており、
前記工程計画装置は、さらに、
前記作業工程における前記要員作業実績情報が前記スキルアップ基準情報を満たすか否かを判定し、満たす場合には、満たしたスキル情報を前記要員スキル情報に登録するスキルアップ判定手段を有する
ことを特徴とする請求項に記載の工程計画装置。
In the storage means,
Skill-up standard information that is standard information for skill-up in the work process;
Personnel work performance information, which is the work information of the work time of personnel for each work process, is stored,
The process planning device further includes:
It is determined whether or not the personnel work performance information in the work process satisfies the skill-up criterion information, and when satisfied, the skill-up determination means for registering the satisfied skill information in the personnel skill information. The process planning apparatus according to claim 4 .
作業工程に必要な要員を割り付けて工程計画をする工程計画装置を用いた工程計画方法において、
前記工程計画装置が、
表示手段に表示された工程管理表の画面上から第1のエレメントを選択し移動する操作により前記表示手段に表示された要員管理表に第2のエレメントとして割り付け要求をする入力ステップと、
前記第1のエレメントに係る作業工程に必要な要員数と、割り付け要求された1以上の前記第2のエレメントに該当する要員数との大小関係を判定する割付要員数判定ステップと、
前記第2のエレメントに該当する要員が、記憶手段に格納されている制約条件を満たすか否かを判定する制約判定ステップと、
前記選択し移動する操作により前記割り付け要求された第2のエレメントを前記要員管理表に表示するとともに、前記第2のエレメントに該当する要員と前記第1のエレメントに該当する作業工程とを関連付けて要員割付引当情報として前記記憶手段に登録し、登録された要員が前記制約判定ステップで所定の制約条件を満たすと判定された場合、第2のエレメントへの割り付け要求を確定する工程計画作成ステップとを実行するに際し、
前記工程管理表および前記要員管理表は、ガントチャートとして前記表示手段に表示されており、
前記工程計画作成ステップは、前記第1のエレメントに係る作業工程を示す枠内に、前記作業工程に割り付けた要員割付数と前記作業工程に必要な要員数とを表示し、前記選択し移動する操作により前記要員管理表に前記第2のエレメントが割り付けられると、前記要員割付数に加算して表示する
ことを特徴とする工程計画方法。
In the process planning method using the process planning device that allocates the necessary personnel for the work process and plans the process,
The process planning device is
An input step of making an allocation request as a second element to the personnel management table displayed on the display means by an operation of selecting and moving the first element from the screen of the process management table displayed on the display means;
Allocation personnel number determination step for determining a magnitude relationship between the number of personnel required for the work process related to the first element and the number of personnel corresponding to one or more second elements requested to be allocated;
A constraint determination step for determining whether a person corresponding to the second element satisfies a constraint condition stored in a storage unit;
The second element requested to be allocated by the operation of selecting and moving is displayed on the personnel management table, and the personnel corresponding to the second element and the work process corresponding to the first element are associated with each other. A process plan creation step for registering in the storage means as personnel allocation allocation information, and confirming an allocation request to the second element when it is determined that the registered personnel satisfy a predetermined constraint condition in the constraint determination step; upon the execution,
The process management table and the personnel management table are displayed on the display means as a Gantt chart,
The process plan creation step displays the number of personnel assigned to the work process and the number of personnel required for the work process in a frame indicating the work process related to the first element, and selects and moves the work plan. When the second element is assigned to the personnel management table by operation , the process planning method is displayed by adding to the personnel allocation number .
JP2009073271A 2009-03-25 2009-03-25 Process planning apparatus and process planning method Active JP5049309B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009073271A JP5049309B2 (en) 2009-03-25 2009-03-25 Process planning apparatus and process planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009073271A JP5049309B2 (en) 2009-03-25 2009-03-25 Process planning apparatus and process planning method

Publications (2)

Publication Number Publication Date
JP2010225017A JP2010225017A (en) 2010-10-07
JP5049309B2 true JP5049309B2 (en) 2012-10-17

Family

ID=43042117

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009073271A Active JP5049309B2 (en) 2009-03-25 2009-03-25 Process planning apparatus and process planning method

Country Status (1)

Country Link
JP (1) JP5049309B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014191390A (en) * 2013-03-26 2014-10-06 Hitachi Systems Ltd System and method for automatically assigning worker
JP5801352B2 (en) * 2013-07-04 2015-10-28 株式会社大和総研ビジネス・イノベーション Order system and program
JP6027515B2 (en) * 2013-10-09 2016-11-16 東京都下水道サービス株式会社 Equipment maintenance management system
JP6476574B2 (en) * 2014-03-28 2019-03-06 富士通株式会社 Production plan preparation support program, production plan preparation support method and production plan preparation support device
JP6903950B2 (en) * 2017-02-28 2021-07-14 富士通株式会社 Work plan creation program, work plan creation device, and work plan creation method
JP7177597B2 (en) * 2018-03-28 2022-11-24 三菱重工業株式会社 Production planning device, production planning system, production planning method, and program
JP6611025B1 (en) * 2019-01-07 2019-11-27 公立大学法人大阪 Crop production management system, server, information processing method, terminal, and program
JP7075906B2 (en) * 2019-03-19 2022-05-26 株式会社日立製作所 Work instruction support system and work instruction support method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3526163B2 (en) * 1997-02-28 2004-05-10 三菱電機株式会社 Knitting table creation device
JP2005293099A (en) * 2004-03-31 2005-10-20 Ricoh Co Ltd Engineer dispatch support method, engineer dispatch support program and engineer dispatch support apparatus
JP5006594B2 (en) * 2006-07-31 2012-08-22 ピーアンドダブリューソリューションズ株式会社 Method, computer and program for planning personnel allocation based on priority
JP2008299762A (en) * 2007-06-01 2008-12-11 Kazuo Kobayashi Production management program

Also Published As

Publication number Publication date
JP2010225017A (en) 2010-10-07

Similar Documents

Publication Publication Date Title
JP5049309B2 (en) Process planning apparatus and process planning method
US20110184771A1 (en) Implementation resource project management
JP2666755B2 (en) Workflow system
US11610670B1 (en) System and method of dynamically generating work assignments
US20080059267A1 (en) Employee setup management system
US20040010437A1 (en) Method and system for scheduling and sharing a pool of resources across multiple distributed forecasted workloads
US20070150327A1 (en) Project management method and system
US20100312604A1 (en) Technician control system
JP2008299762A (en) Production management program
CA2497221A1 (en) Report generation and distribution system and method for a time and attendance recording system
JP3992111B2 (en) Systems, methods and programs for adjusting work schedules
US20090125368A1 (en) System and Method for Scheduling Work Orders
JP5256546B2 (en) Direct employment support system and server
JPH03268098A (en) Building maintenance control system
US20110313934A1 (en) System and Method for Configuring Workflow Templates
JP7297817B2 (en) man hour system
JP2007213141A (en) Personnel distribution system, personnel distribution method, personnel distribution program, and recording medium with the program recorded thereon
US20180253701A1 (en) System and method for tracking and maintaining equipment
JP7348827B2 (en) Information processing device and information processing method
JP4982526B2 (en) Work assignment support terminal and work assignment support program
JP2003006393A (en) Scheduling device and its method
JP2008204150A (en) Business management method, business management device, storage medium, and computer program
JP2011100225A (en) Personnel assignment system
US20070174460A1 (en) Method and system for on demand weighted proportional distribution of enterprise allocations
JP7179301B1 (en) multitasking management system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20101216

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120501

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120508

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120618

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120710

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120720

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150727

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5049309

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150727

Year of fee payment: 3

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150727

Year of fee payment: 3

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150727

Year of fee payment: 3

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150727

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S802 Written request for registration of partial abandonment of right

Free format text: JAPANESE INTERMEDIATE CODE: R311802

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250