JP4922200B2 - Concrete placement control method and concrete placement system - Google Patents

Concrete placement control method and concrete placement system Download PDF

Info

Publication number
JP4922200B2
JP4922200B2 JP2008017294A JP2008017294A JP4922200B2 JP 4922200 B2 JP4922200 B2 JP 4922200B2 JP 2008017294 A JP2008017294 A JP 2008017294A JP 2008017294 A JP2008017294 A JP 2008017294A JP 4922200 B2 JP4922200 B2 JP 4922200B2
Authority
JP
Japan
Prior art keywords
concrete
wave
lining thickness
vibration receiving
thickness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2008017294A
Other languages
Japanese (ja)
Other versions
JP2009179944A (en
Inventor
邦博 永森
勝 一條
克 戸井田
孝志 小林
克己 沼宮内
孝博 佐々木
仁 千葉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2008017294A priority Critical patent/JP4922200B2/en
Publication of JP2009179944A publication Critical patent/JP2009179944A/en
Application granted granted Critical
Publication of JP4922200B2 publication Critical patent/JP4922200B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

本発明は、場所打ちライニング工法において、未硬化で脱型前のコンクリートの打設を制御する方法およびコンクリート打設システムに関するものである。   The present invention relates to a method and a concrete placement system for controlling placement of uncured concrete before demolding in a cast-in-place lining method.

従来、シールドトンネルの形成に、場所打ちライニング工法、押し出しコンクリートライニング工法、ECL(Extruded Concrete Lining)工法と呼ばれる、シールド掘削機で地山を掘削しつつ、前記シールド掘削機のテール部内側で内型枠を円環状に組立て、前記内型枠と前記掘削した地山との間にコンクリートを流し込んで覆工コンクリートを構築してトンネルを形成する工法が用いられている(例えば、特許文献1参照)。   Conventionally, in forming a shield tunnel, a cast-in-place lining method, an extruded concrete lining method, and an ECL (Extruded Concrete Lining) method are used. A construction method is used in which a frame is assembled in an annular shape, concrete is poured between the inner mold frame and the excavated ground, and lining concrete is constructed to form a tunnel (see, for example, Patent Document 1). .

特開2006−241800号公報JP 2006-241800 A

しかしながら、これまで未硬化で脱型前のコンクリートの覆工厚さを適確に計測する手段がなく、打設圧力、打設量から間接的にコンクリート覆工厚さを推定し、硬化して脱型した後のコンクリートの厚さを計測することで、コンクリートの打設管理を行っていた。しかし、脱型後に覆工厚さの計測を行うため、コンクリートの覆工厚さを間接的にしか制御できない。そのため、覆工厚さを余分に厚くせざるを得ず、コンクリート使用量に無駄が多くなるなどの問題点があった。   However, until now there has been no means to accurately measure the lining thickness of uncured concrete before demolding, and the concrete lining thickness is estimated indirectly from the placement pressure and placement amount and cured. The concrete was managed by measuring the thickness of the concrete after demolding. However, since the lining thickness is measured after demolding, the lining thickness of concrete can only be indirectly controlled. For this reason, the lining thickness has to be increased excessively, and there is a problem that the amount of concrete used is increased.

本発明は、前述した問題点に鑑みてなされたもので、その目的とすることは、場所打ちライニング工法において、打設中のコンクリートの覆工厚さを制御することである。   The present invention has been made in view of the above-described problems, and an object of the present invention is to control the lining thickness of the concrete being placed in the cast-in-place lining method.

前述した目的を達成するために、第1の発明は,シールド掘削機で地山を掘削しつつ、前記シールド掘削機のテール部内側で型枠を環状に組立て、前記型枠と前記掘削した地山との間にコンクリートを打設して覆工コンクリートを構築し、トンネルを形成するにあたり、前記型枠が、超磁歪素子を用いた発振装置と受振装置を有し、前記発振装置が振動して波動を発生させ、前記受振装置が前記波動を受振し、前記波動の到達時間から、前記コンクリートの覆工厚さを測定する工程(a)と、前記覆工厚さが目標覆工厚さの管理範囲内になるようにコンクリートの供給量とコンクリートの打設圧力を変化する工程(b)と、を備えることを特徴とするコンクリート打設制御方法である。   In order to achieve the above-described object, the first invention is to excavate a natural ground with a shield excavator while assembling a mold form inside the tail part of the shield excavator so that the mold form and the excavated ground are formed. In forming concrete tunnel by placing concrete between mountains and forming a tunnel, the formwork has an oscillation device and a vibration receiving device using a giant magnetostrictive element, and the oscillation device vibrates. A step (a) of generating a wave, the vibration receiving device receiving the wave, and measuring the lining thickness of the concrete from the arrival time of the wave, and the lining thickness is a target lining thickness And (b) a step of changing the concrete supply amount and the concrete pouring pressure so as to be within the management range.

また、前記型枠は、スキンプレートに4枚の側板が設けられ、前記スキンプレートに複数の開口部が設けられ、前記開口部に開閉可能なゲートが設けられ、前記スキンプレートの片面側の前記ゲートに対応する位置に、超磁歪素子を用いる発振装置と受振装置とが設けられることが好ましい。   Further, the mold is provided with four side plates on the skin plate, a plurality of openings are provided on the skin plate, a gate that can be opened and closed is provided on the opening, and the one side of the skin plate is It is preferable that an oscillation device using a giant magnetostrictive element and a vibration receiving device are provided at a position corresponding to the gate.

前記発振装置は、超磁歪素子により振動可能なヘッドを有する超磁歪型振動子を備え、前記受振装置は、センサを備えることが好ましい。   The oscillation device preferably includes a giant magnetostrictive vibrator having a head that can vibrate by a giant magnetostrictive element, and the vibration receiving device preferably includes a sensor.

また、前記工程(a)は、前記発振装置と、前記受振装置とを前記コンクリートに押し出す工程と、前記発振装置が振動して波動を発生させる工程と、地山と前記コンクリートの境界により反射した前記波動を前記受振装置が受振する工程と、前記波動に基づき、前記コンクリートの覆工厚さを求める工程と、を備え、前記工程(b)は、前記コンクリートの覆工厚さと目標覆工厚さを比較する工程と、前記覆工厚さが前記目標覆工厚さの管理範囲外にある場合に、コンクリートの供給量と、コンクリートの打設圧力を変更する工程と、を備えることが好ましい。   The step (a) is reflected by the step of pushing the oscillation device and the vibration receiving device to the concrete, the step of causing the oscillation device to vibrate and generating a wave, and the boundary between the natural ground and the concrete. A step of receiving the wave by the vibration receiving device; and a step of obtaining a lining thickness of the concrete based on the wave, wherein the step (b) includes a lining thickness of the concrete and a target lining thickness. And a step of changing the concrete supply amount and the concrete placing pressure when the lining thickness is outside the control range of the target lining thickness. .

第2の発明は、シールド掘削機で地山を掘削しつつ、前記シールド掘削機のテール部内側で型枠を環状に組立て、前記型枠と前記掘削した地山との間にコンクリートを打設して覆工コンクリートを構築し、トンネルを形成するにあたり、前記型枠と前記掘削した地山との間にコンクリートを供給する供給手段と、前記コンクリートを押圧する押圧手段と、前記型枠は、超磁歪素子を用いた発振装置と受振装置を有し、前記発振装置が発生させた波動を前記受振装置が受振して、前記コンクリートの厚さを測定する測定手段と、測定されたコンクリートの厚さに応じて、前記供給手段のコンクリート供給量と、前記押圧手段の押圧力を制御する制御手段とを備えることを特徴とするコンクリート打設システムである。   According to a second aspect of the present invention, while excavating a natural ground with a shield excavator, a mold is assembled in an annular shape inside the tail portion of the shield excavator, and concrete is placed between the mold and the excavated natural ground. In constructing lining concrete and forming a tunnel, a supply means for supplying concrete between the formwork and the excavated ground, a pressing means for pressing the concrete, and the formwork, An oscillation device using a giant magnetostrictive element and a vibration receiving device, wherein the vibration receiving device receives the wave generated by the oscillation device and measures the thickness of the concrete; and the measured concrete thickness Accordingly, a concrete placement system comprising a concrete supply amount of the supply means and a control means for controlling the pressing force of the pressing means.

本発明により、場所打ちライニング工法において、打設中にリアルタイムでコンクリートの覆工厚さを制御できる。   According to the present invention, in the cast-in-place lining method, the concrete lining thickness can be controlled in real time during placement.

以下図面に基づいて、本発明の実施形態を詳細に説明する。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

図1は、地山19にトンネルを形成するシールド掘削機1を示す図である。シールド掘削機1は、前端に回転掘削部3を有し、回転掘削部3の後部に延長する円筒状のテールプレート5を備える。テールプレート5の内側に沿うように、複数のシールドジャッキ7とプレスジャッキ9とが設けられる。プレスジャッキ9の後端には、テールプレート5の内周面に沿って前後に移動可能な妻型枠11を設ける。   FIG. 1 is a diagram showing a shield excavator 1 that forms a tunnel in the natural ground 19. The shield excavator 1 includes a rotary excavation unit 3 at a front end, and includes a cylindrical tail plate 5 that extends to the rear of the rotary excavation unit 3. A plurality of shield jacks 7 and a press jack 9 are provided along the inside of the tail plate 5. At the rear end of the press jack 9, a wife form frame 11 is provided that can move back and forth along the inner peripheral surface of the tail plate 5.

妻型枠11は、テールプレート5の内側と後述する内型枠13との間をふさいだ状態でプレスジャッキ9の伸縮で前後に移動可能な構成物である。また、コンクリート21を加圧するための加圧板としての機能も有する。   The wife formwork 11 is a component that can be moved back and forth by the expansion and contraction of the press jack 9 in a state of blocking between the inside of the tail plate 5 and an inner formwork 13 described later. Moreover, it also has a function as a pressure plate for pressing the concrete 21.

また、シールドジャッキ7は、内型枠13により反力を得ており、その反力によってシールド掘削機1を推進する。また、妻型枠11と内型枠13、地山19との間に、コンクリート21を充填する。コンクリート21は、レミキサー(図示せず)から供給され、打設ポンプ17とコンクリート供給ホース15を通って、妻型枠11のコンクリート供給孔16から、打設される。妻型枠11が形成するリングには、プレスジャッキ9とコンクリート供給孔16の両方が設けられ、コンクリート供給孔16にはコンクリート供給ホース15が設けられる。図1の上部は、プレスジャッキ9が加圧する妻型枠11を、下部はコンクリート供給ホース15とコンクリート供給孔16が設けられた妻型枠11を表している。   Further, the shield jack 7 obtains a reaction force from the inner mold 13, and the shield excavator 1 is propelled by the reaction force. Further, concrete 21 is filled between the end form 11, the inner form 13, and the natural ground 19. The concrete 21 is supplied from a remixer (not shown), and is placed from the concrete supply hole 16 of the end form 11 through the placement pump 17 and the concrete supply hose 15. The ring formed by the end form 11 is provided with both the press jack 9 and the concrete supply hole 16, and the concrete supply hole 16 is provided with a concrete supply hose 15. The upper part of FIG. 1 represents the end form 11 that the press jack 9 pressurizes, and the lower part represents the end form 11 provided with the concrete supply hose 15 and the concrete supply hole 16.

シールド掘削機1は、コンクリート押圧手段としてプレスジャッキ9と妻型枠11を、コンクリート供給手段として、打設ポンプ17、コンクリート供給ホース15、コンクリート供給孔16とを備える。   The shield excavator 1 includes a press jack 9 and a end form 11 as concrete pressing means, and a placing pump 17, a concrete supply hose 15, and a concrete supply hole 16 as concrete supply means.

なお、シールド掘削機1が形成するトンネルは、断面円状のトンネルに限られず、断面かまぼこ状や断面馬てい状のトンネルなどにすることができる。   Note that the tunnel formed by the shield excavator 1 is not limited to a tunnel having a circular cross section, and may be a tunnel having a semi-cylindrical cross section or a horseshoe cross section.

図2は、本実施形態に係る内型枠13の斜視図を示している。
内型枠13は、スキンプレート23と、側板25とからなる。スキンプレート23に発振装置29や受振装置27とが設けられる。
FIG. 2 is a perspective view of the inner mold 13 according to the present embodiment.
The inner mold 13 includes a skin plate 23 and a side plate 25. The skin plate 23 is provided with an oscillation device 29 and a vibration receiving device 27.

スキンプレート23は、湾曲した長方形の板である。スキンプレート23は環の一部を形成しており、内型枠13が複数集まることで環状および筒状になる。スキンプレート23は、鋼製である。   The skin plate 23 is a curved rectangular plate. The skin plate 23 forms a part of an annulus, and is formed into an annular shape and a cylindrical shape by gathering a plurality of inner molds 13. The skin plate 23 is made of steel.

側板25は、長方形の板である。側板25は、スキンプレート23の四方の端部に設けられており、スキンプレート23の強度を高めている。側板25は鋼製である。   The side plate 25 is a rectangular plate. The side plates 25 are provided at the four ends of the skin plate 23 to increase the strength of the skin plate 23. The side plate 25 is made of steel.

内型枠13は発振装置29と受振装置27を各一つ設けているが、測定精度の向上のため、ひとつの発振装置29に対して複数の受振装置27を設けてもよいし、発振装置29と受振装置27の対を複数設けてもよい。   The inner mold 13 includes one oscillation device 29 and one vibration receiving device 27. However, in order to improve measurement accuracy, a plurality of vibration receiving devices 27 may be provided for one oscillation device 29. A plurality of pairs of 29 and vibration receiving device 27 may be provided.

図3は、図2のA−A断面の概略図であり、スキンプレート23の開口部には、ゲート33を有するソケット31が設けられる。ソケット31の下部には、ネジが設けられている。   FIG. 3 is a schematic view of the AA cross section of FIG. 2, and a socket 31 having a gate 33 is provided in the opening of the skin plate 23. A screw is provided at the bottom of the socket 31.

ゲート33は、妻型枠11により加圧されているコンクリート21が、内型枠13の開口部を通って、漏れ出さないように設けられており、ゲートバルブやカットゲートなどが用いられる。   The gate 33 is provided so that the concrete 21 pressed by the end formwork 11 does not leak through the opening of the inner formwork 13, and a gate valve, a cut gate, or the like is used.

図4(a)は、発振装置29を示す図である。発振装置29とは、筒状のケーシング37と、ケーシング37の端部に形成されたニップル39と、ジャッキ45により、ケーシング37上部より突出可能な振動子41及びヘッド43とからなる。   FIG. 4A shows the oscillation device 29. The oscillating device 29 includes a cylindrical casing 37, a nipple 39 formed at an end of the casing 37, and a vibrator 41 and a head 43 that can protrude from the upper portion of the casing 37 by a jack 45.

ニップル39は、前記ソケット31と螺合可能なネジが設けられている。   The nipple 39 is provided with a screw that can be screwed into the socket 31.

また、ニップル39のような螺合による固定に限られず、ソケット31とケーシング37を接合可能な、管用の継手を用いることができる。例えば、ワンタッチカプラーなどを用いることができる。   Moreover, it is not restricted to the fixing by screwing like the nipple 39, The joint for pipes which can join the socket 31 and the casing 37 can be used. For example, a one-touch coupler can be used.

また、振動子41とケーシング37の間に、パッキンを設け、ゲート33の開放時にコンクリート21が、ケーシング37内に進入することを防いでもよい。   Further, a packing may be provided between the vibrator 41 and the casing 37 to prevent the concrete 21 from entering the casing 37 when the gate 33 is opened.

ジャッキ45は、振動子41を前後に移動可能なものであり、油圧ジャッキでもネジジャッキでもよい。なお、ジャッキ45には、ストローク計を設けることが好ましい。コンクリートの覆工厚さを測定する際、ヘッドの位置が異なると波動の伝播距離が異なり、算出される覆工厚さが変化するためである。   The jack 45 can move the vibrator 41 back and forth, and may be a hydraulic jack or a screw jack. The jack 45 is preferably provided with a stroke meter. This is because, when measuring the lining thickness of concrete, if the head position is different, the propagation distance of the wave is different and the calculated lining thickness changes.

図5は、振動子41の断面の概略図である。超磁歪素子51が、コイル49の中におかれ、コイル49の周りを永久磁石53が覆っている。超磁歪素子51はロッド57に接続し、ロッド57は、バネ55により、振動子41の長軸方向に力がかけられている。   FIG. 5 is a schematic view of a cross section of the vibrator 41. A giant magnetostrictive element 51 is placed in a coil 49, and a permanent magnet 53 covers the coil 49. The giant magnetostrictive element 51 is connected to a rod 57, and a force is applied to the rod 57 in the major axis direction of the vibrator 41 by a spring 55.

超磁歪素子51は、Tb0.3Dy0.7Fe2.0(テルビウム‐ディスプロジウム‐鉄)の化合物により形成される。コイル49に電流を流し、磁界を生じることで、超磁歪素子51は、長軸方向へ通常0.1%以上伸張する。コイル49からの磁界がなくなると、元の長さに戻る。コイル49に電流を流す/止めるを繰返し行うことで、超磁歪素子51は、伸縮する。超磁歪素子51の伸縮により、ロッド57が往復運動をし、更にはヘッド43が図5に示した矢印方向に振動することによって波動を発生させることができる。 The giant magnetostrictive element 51 is formed of a compound of Tb 0.3 Dy 0.7 Fe 2.0 (terbium-dysprodium-iron). By causing a current to flow through the coil 49 and generating a magnetic field, the giant magnetostrictive element 51 normally extends 0.1% or more in the major axis direction. When the magnetic field from the coil 49 disappears, the original length is restored. The giant magnetostrictive element 51 expands and contracts by repeatedly applying / stopping the current to the coil 49. As the giant magnetostrictive element 51 expands and contracts, the rod 57 reciprocates, and the head 43 vibrates in the direction of the arrow shown in FIG.

また、図4(b)は、受振装置27を示す図であり、受振装置27は、先端にニップル39を有する筒状のケーシング37に、センサ47が設けられ、センサ47は、ジャッキ45によりケーシング37上部より突出可能である。また、受振装置27は、発振装置29と同様にパッキンやストローク計を備えてもよい。   4B shows the vibration receiving device 27. The vibration receiving device 27 is provided with a sensor 47 in a cylindrical casing 37 having a nipple 39 at the tip. 37 can protrude from the top. Further, the vibration receiving device 27 may include a packing and a stroke meter in the same manner as the oscillation device 29.

センサ47は、ヘッド43が発生させた波動が、コンクリート21と地山19の岩盤との境界部で反射した波動を受振することのできる振動計を一般的に用いることができる。例えば、圧電素子を備えた加速度計を用いることができる。   The sensor 47 can generally use a vibrometer that can receive the wave generated by the head 43 and reflected by the boundary between the concrete 21 and the rock of the natural ground 19. For example, an accelerometer provided with a piezoelectric element can be used.

続いて、図6を用いて、内型枠13において、発振装置29と受振装置27とを用いてコンクリート21の覆工厚さを測定する方法を説明する。   Next, a method of measuring the lining thickness of the concrete 21 using the oscillation device 29 and the vibration receiving device 27 in the inner mold 13 will be described with reference to FIG.

図6(a)に示すように、発振装置29と受振装置27とを内型枠13のソケット31に取り付ける。   As shown in FIG. 6A, the oscillation device 29 and the vibration receiving device 27 are attached to the socket 31 of the inner mold 13.

図6(b)に示すように、発振装置29、受振装置27のニップル39が、ソケット31に螺合する。ニップル39とソケット31の螺合は、コンクリート21の圧力に耐えることができる。   As shown in FIG. 6B, the nipple 39 of the oscillation device 29 and the vibration receiving device 27 is screwed into the socket 31. The screwing of the nipple 39 and the socket 31 can withstand the pressure of the concrete 21.

その後、図6(c)に示すように、ゲート33を開け、発振装置29からは振動子41とヘッド43を、受振装置27からはセンサ47をゲート33から突き出す。この際、波動59が、ソケット31内で反射するなど、ソケット31の影響を受けないように、ヘッド43とセンサ47は、スキンプレート23が形成する平面と同じかそれ以上にコンクリート21中に突き出す。   Thereafter, as shown in FIG. 6C, the gate 33 is opened, and the vibrator 41 and the head 43 are projected from the oscillation device 29, and the sensor 47 is projected from the gate 33 from the vibration receiving device 27. At this time, the head 43 and the sensor 47 protrude into the concrete 21 to be equal to or higher than the plane formed by the skin plate 23 so that the wave 59 is not affected by the socket 31 such as being reflected in the socket 31. .

その後、振動子41がヘッド43を振動させ、P波やS波といった波動59を発生させる。波動59は、コンクリート21と地山19の間の伝播速度が異なるため、境界面で反射し、センサ47で受振する。なお、ヘッド43の先端はコンクリート21に圧縮する方向に振動してP波を発生させ、ヘッド43の側面は、コンクリート21にせん断する方向に振動してS波を発生させる。   Thereafter, the vibrator 41 vibrates the head 43 to generate a wave 59 such as a P wave or an S wave. The wave 59 is reflected at the boundary surface and received by the sensor 47 because the propagation speed between the concrete 21 and the natural ground 19 is different. The tip of the head 43 vibrates in a direction compressing the concrete 21 to generate a P wave, and the side surface of the head 43 vibrates in a direction shearing the concrete 21 to generate an S wave.

その後、図6(d)に示すように、振動子41を発振装置29のケーシング37の内部に、センサ47を受振装置27のケーシング37の内部に収納し、ゲート33を閉じる。   Thereafter, as shown in FIG. 6D, the vibrator 41 is housed in the casing 37 of the oscillation device 29, the sensor 47 is housed in the casing 37 of the vibration receiving device 27, and the gate 33 is closed.

その後、図6(e)に示すように、発振装置29と受振装置27を、内型枠13より撤去する。なお、覆工厚さ測定を完了した内型枠13や、コンクリート21が硬化した内型枠13から、発振装置29と受振装置27とを取り外し、他の内型枠13に設置してもよい。   Thereafter, as shown in FIG. 6 (e), the oscillation device 29 and the vibration receiving device 27 are removed from the inner mold 13. The oscillation device 29 and the vibration receiving device 27 may be removed from the inner mold 13 for which the lining thickness measurement has been completed or the inner mold 13 with the concrete 21 hardened, and installed in another inner mold 13. .

なお、コンクリート覆工厚さの測定において、振動子41やセンサ47をコンクリート21中へ押し出さずに測定することも可能である。押し出さずに測定する場合には、発振装置29と受振装置27にジャッキ45を設ける必要はない。また、測定方法においても、振動子41とセンサ47の押し出し工程および引き戻し工程は不要となる。   In measuring the concrete lining thickness, it is also possible to measure without pushing the vibrator 41 or the sensor 47 into the concrete 21. When measuring without pushing, it is not necessary to provide the jack 45 to the oscillation device 29 and the vibration receiving device 27. Also in the measurement method, the pushing process and the pulling back process of the vibrator 41 and the sensor 47 are not necessary.

受振データを用いた覆工厚さの計算方法の一例を紹介する。センサ47で受振した受振データを用いて、直達波の到達時間と反射波の到達時間を算出する。ここで、発振装置29と受振装置27の距離が既知であるため、直達波の到達時間よりコンクリート21中の波動の伝播速度が計算できる。そのため、この伝播速度と反射波の到達時間より覆工厚さを計算できる。   An example of a method for calculating the lining thickness using vibration receiving data is introduced. Using the received vibration data received by the sensor 47, the arrival time of the direct wave and the arrival time of the reflected wave are calculated. Here, since the distance between the oscillation device 29 and the vibration receiving device 27 is known, the propagation speed of the wave in the concrete 21 can be calculated from the arrival time of the direct wave. Therefore, the lining thickness can be calculated from the propagation speed and the arrival time of the reflected wave.

本測定方法においては、超磁歪素子を用いた発振装置により、従来の超音波発生装置よりも短い波長のS波を発生させることができる。   In this measurement method, an S-wave having a shorter wavelength than that of a conventional ultrasonic generator can be generated by an oscillator using a giant magnetostrictive element.

また、本測定方法においては、従来困難であった、脱型前のコンクリートと発振装置を、金属製の内型枠を間に挟まずに接することができる。   Further, in this measurement method, it is possible to contact the concrete before demolding and the oscillation device, which have been difficult in the past, without interposing a metal inner mold frame between them.

また、本測定方法においては、加圧コンクリートの圧力に耐えながら、発振装置と受振装置を出し入れ可能な内型枠を提供する。   In addition, the present measurement method provides an inner mold that allows the oscillation device and the vibration receiving device to be taken in and out while withstanding the pressure of the pressurized concrete.

つまり、本測定方法においては、従来測定が困難であった、場所打ちライニング工法における脱型前の未硬化のコンクリートの覆工厚さの測定が可能である。   That is, in this measurement method, it is possible to measure the lining thickness of uncured concrete before demolding in the cast-in-place lining method, which has been difficult to measure conventionally.

続いて、図7を用いて、コンクリート21の打設方法を説明する。   Then, the placement method of the concrete 21 is demonstrated using FIG.

図7(a)に示すように、シールドジャッキ7を収縮し、内型枠13cに隣接する空間に、内型枠13dを入れる空間を確保する。   As shown in FIG. 7A, the shield jack 7 is contracted to secure a space for inserting the inner mold 13d in a space adjacent to the inner mold 13c.

図7(b)に示すように、シールドジャッキ7と内型枠13cの間に、内型枠13dを設置する。   As shown in FIG. 7B, an inner mold 13d is installed between the shield jack 7 and the inner mold 13c.

図7(c)に示すように、コンクリート供給ホース15により、内型枠13と妻型枠11と地山19に囲まれた部分へのコンクリート21の打設を開始する。妻型枠11は、プレスジャッキ9により一定の圧力をかけられながら、コンクリート21の打設に伴い、図の左方向へ移動する。   As shown in FIG. 7C, the concrete supply hose 15 starts placing concrete 21 on a portion surrounded by the inner mold 13, the wife mold 11, and the natural ground 19. The wife form frame 11 moves to the left in the figure as the concrete 21 is placed while being applied with a certain pressure by the press jack 9.

図7(d)に示すように、妻型枠11が発振装置29や受振装置27のある部分を通過した後に、図6で示した方法で、コンクリート21の厚さの測定を行う。また、測定された厚さに基づいて、プレスジャッキ9が妻型枠11にかける圧力と、コンクリート供給ホース15により供給されるコンクリート21の量を制御する。   As shown in FIG. 7D, after the end form 11 passes through a portion where the oscillation device 29 and the vibration receiving device 27 are present, the thickness of the concrete 21 is measured by the method shown in FIG. Further, based on the measured thickness, the pressure applied by the press jack 9 to the end form 11 and the amount of the concrete 21 supplied by the concrete supply hose 15 are controlled.

図7(e)に示すように、妻型枠11が内型枠13dの端まで到達すると、再びシールドジャッキ7が縮み、次の内型枠13が入る空間を確保する。つまり、図7(a)の状態に戻る。   As shown in FIG. 7 (e), when the end form 11 reaches the end of the inner form 13d, the shield jack 7 is contracted again to secure a space for the next inner form 13 to enter. That is, the state returns to the state of FIG.

図7に示す工程を繰り返すことで、シールド掘削機1は掘進し、コンクリートの打設が行われ、トンネルのライニングが形成される。   By repeating the process shown in FIG. 7, the shield excavator 1 is dug, concrete is placed, and a tunnel lining is formed.

場所打ちライニング工法においては、硬化後のコンクリート21から内型枠13がはずされ、前に移動して、シールドの中に組み立てられる。   In the cast-in-place lining method, the inner mold 13 is removed from the hardened concrete 21, moved forward, and assembled into a shield.

図8は、本実施形態に係る制御装置61を示す図である。制御装置61は、発振装置29へ発振指令を送ることができ、受振装置27から受振データを受けとることができる。また、打設ポンプ17の回転数を制御してコンクリート21の供給速度を制御可能であり、プレスジャッキ9の圧力を制御してコンクリート21の打設圧力を制御可能である。   FIG. 8 is a diagram illustrating the control device 61 according to the present embodiment. The control device 61 can send an oscillation command to the oscillation device 29 and can receive vibration receiving data from the vibration receiving device 27. Further, it is possible to control the supply speed of the concrete 21 by controlling the rotation speed of the placing pump 17, and to control the placing pressure of the concrete 21 by controlling the pressure of the press jack 9.

例えば、制御装置61は、コンピュータであり、一例として演算手段、記憶手段、通信手段、入力手段、表示手段など備える。   For example, the control device 61 is a computer, and includes, for example, a calculation unit, a storage unit, a communication unit, an input unit, a display unit, and the like.

前記演算手段は、受振データからの覆工厚さの算出や、後述する制御フローを実行する。また、前記記憶手段は、受振データや測定された覆工厚さ、後述する管理値や管理範囲、制御方法を実行するプログラムなどを記憶する。   The calculation means calculates a lining thickness from vibration receiving data and executes a control flow to be described later. The storage means stores vibration receiving data, measured lining thickness, management value and management range, which will be described later, a program for executing a control method, and the like.

前記通信手段は、発振装置29に発振の指令を送信する、受振装置27から波動の受振データを受信する、打設ポンプ17やプレスジャッキ9に設定値の変更を送信するなどの通信を行う。   The communication means performs communication such as transmitting an oscillation command to the oscillating device 29, receiving wave vibration data from the vibration receiving device 27, and transmitting a setting value change to the placing pump 17 and the press jack 9.

前記入力手段は、管理値や管理範囲を手動または自動で入力する。また、表示手段は、現在の打設ポンプ17の回転数、プレスジャッキ9の圧力、コンクリート21の覆工厚さ、受振データなどの情報を表示する。   The input means inputs a management value and a management range manually or automatically. Further, the display means displays information such as the current rotation speed of the placing pump 17, the pressure of the press jack 9, the lining thickness of the concrete 21, and the vibration receiving data.

また、制御装置61は、コンクリート21の覆工厚さの制御だけでなく、シールドの掘進速度の制御をしてもよいし、シールドの切羽土圧、掘削土量、天端部の空隙の有無などのデータを収集してもよい。   The control device 61 may control not only the lining thickness of the concrete 21 but also the shield excavation speed, the face pressure of the shield, the amount of excavated soil, and the presence / absence of a gap at the top end Such data may be collected.

打設圧力を上げると、コンクリート21の覆工厚さは厚くなる。打設圧力の上昇により、地山19にコンクリート21が食い込むためである。逆に、打設圧力を下げると、地山19からの土水圧により、コンクリート21は薄くなる。   When the casting pressure is increased, the lining thickness of the concrete 21 increases. This is because the concrete 21 bites into the natural ground 19 due to an increase in the pouring pressure. On the other hand, when the placing pressure is lowered, the concrete 21 is thinned by the soil water pressure from the natural ground 19.

また、打設圧力を上げると、打設に必要なコンクリート21の量も増すために、打設ポンプ17の回転数を上げ、コンクリートの供給量を増やす必要がある。逆に、打設圧力を下げると、打設ポンプ17の回転数を下げる必要がある。   Further, when the pouring pressure is increased, the amount of concrete 21 necessary for the pouring is increased, so that it is necessary to increase the rotation speed of the pouring pump 17 and increase the supply amount of the concrete. On the contrary, if the driving pressure is lowered, it is necessary to reduce the rotation speed of the driving pump 17.

図9は、制御装置61が行う制御方法を示すフローチャートである。まず、覆工厚さの管理範囲を設定する(ステップ101)。管理範囲の設定方法としては、管理値として「設計厚さ」+「余掘り」を設定し、管理値から上下に一定範囲を設けたものが管理範囲である。例えば、設計厚さが30cmで、余掘り2cmで、一定範囲を±0.5cmとすると、管理範囲は、31.5cmから32.5cmとなる。   FIG. 9 is a flowchart illustrating a control method performed by the control device 61. First, the management range of the lining thickness is set (step 101). As a management range setting method, “design thickness” + “excavation” is set as a management value, and a certain range is provided above and below the management value. For example, if the design thickness is 30 cm, the surplus depth is 2 cm, and the fixed range is ± 0.5 cm, the management range is 31.5 cm to 32.5 cm.

その後、図6で説明した方法により、コンクリート覆工厚さを測定する(ステップ102)。次いで、測定した厚さと管理範囲の最大値を比較し(ステップ103)、測定厚さが管理範囲の最大値よりも大きい場合には、打設設定圧力(プレスジャッキ9の圧力設定と連動)と打設設定流量を下げる(その結果、打設ポンプ17の設定回転数が下がる)(ステップ105)。次いで、測定した厚さと管理範囲の最小値を比較し(ステップ104)、測定厚さが管理範囲の最小値よりも小さい場合には、打設設定圧力と打設設定流量を上げる(ステップ106)。測定厚さが管理範囲内である場合は、設定値を変更せず、次の計測に戻る。   Thereafter, the concrete lining thickness is measured by the method described in FIG. 6 (step 102). Next, the measured thickness is compared with the maximum value of the management range (step 103), and when the measured thickness is larger than the maximum value of the management range, the setting pressure for driving (linked with the pressure setting of the press jack 9) and The placement setting flow rate is lowered (as a result, the setting rotational speed of the placement pump 17 is lowered) (step 105). Next, the measured thickness and the minimum value of the management range are compared (step 104). If the measured thickness is smaller than the minimum value of the management range, the setting pressure and the setting flow rate are increased (step 106). . If the measured thickness is within the control range, the set value is not changed and the process returns to the next measurement.

また、ステップ105において、プレスジャッキ9の設定圧力を例えば0.01MPaといった一定値ずつ自動変化させてもよいし、現在値の5%ずつといった一定割合ずつ自動変化させてもよい。また、変化量を、人の手で決めてもよい。打設ポンプ17の設定回転数においても同様に変化させてもよく、ステップ106においても同様に変化させてもよい。   In step 105, the set pressure of the press jack 9 may be automatically changed by a fixed value such as 0.01 MPa, or may be automatically changed by a fixed rate such as 5% of the current value. Further, the amount of change may be determined manually. The setting rotational speed of the driving pump 17 may be changed in the same manner, and may be changed in the same way in step 106.

また、硬化後のコンクリート21の覆工厚さを、公知の方法などで測定し、硬化後の覆工厚さと、本測定方法で得られた硬化前の覆工厚さとを比較し、前記管理値を変更することが好ましい。   Further, the lining thickness of the concrete 21 after curing is measured by a known method or the like, the lining thickness after curing is compared with the lining thickness before curing obtained by this measuring method, and the management It is preferable to change the value.

本実施の形態によれば、未硬化のコンクリートの覆工厚さを測定し、リアルタイムでコンクリートの打設量と供給量を変化させることで、打設中のコンクリートの覆工厚さを直接制御できる。   According to this embodiment, the lining thickness of uncured concrete is measured, and the lining thickness of concrete being placed is directly controlled by changing the placement amount and supply amount of concrete in real time. it can.

本実施の形態によれば、健全な覆工厚さを持つコンクリート覆工を、確実に行える。覆工厚さを過剰に厚くしてコンクリートを過剰に使用することもなく、覆工厚さを設計厚さより下回ることもなく、覆工を行うことができる。   According to this embodiment, a concrete lining having a sound lining thickness can be reliably performed. The lining can be performed without excessively increasing the lining thickness and using the concrete excessively, and without lowering the lining thickness below the design thickness.

また、本実施の形態によれば、コンクリートに余分な圧力をかけずに施工可能となるため、土被りの薄い箇所においても、土被りを変形させ、地上を隆起させたり、沈下させたりしないで済む。   In addition, according to the present embodiment, it is possible to construct without applying extra pressure to the concrete, so even in a portion where the earth covering is thin, the earth covering is not deformed and the ground is not raised or submerged. That's it.

以上、添付図面を参照しながら、本発明にかかるコンクリートの打設方法や打設システムの好適な実施形態について説明したが、本発明は係る例に限定されない。当業者であれば、本願で開示した技術的思想の範疇内において、各種の変更例または修正例に想到しえることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   While the preferred embodiments of the concrete placing method and the placing system according to the present invention have been described above with reference to the accompanying drawings, the present invention is not limited to such examples. It will be apparent to those skilled in the art that various changes and modifications can be made within the scope of the technical idea disclosed in the present application, and these are naturally within the technical scope of the present invention. Understood.

本実施の形態に係るシールド掘削機1の概要を示す図。The figure which shows the outline | summary of the shield excavator 1 which concerns on this Embodiment. 本実施の形態に係る、発振装置29と受振装置27を有する内型枠13を示す図。The figure which shows the internal mold 13 which has the oscillation apparatus 29 and the vibration receiving apparatus 27 based on this Embodiment. 本実施の形態に係る内型枠13の断面を示す図。The figure which shows the cross section of the inner mold frame 13 which concerns on this Embodiment. 本実施の形態に係る発振装置29と受振装置27を示す図。The figure which shows the oscillation apparatus 29 and the vibration receiving apparatus 27 which concern on this Embodiment. 本実施の形態に係る振動子41の断面の概略図。FIG. 4 is a schematic view of a cross section of a vibrator 41 according to the present embodiment. 本実施の形態に係るコンクリート21の覆工厚さの測定方法を示す図。The figure which shows the measuring method of the lining thickness of the concrete 21 which concerns on this Embodiment. 本実施の形態に係るコンクリート21の覆工厚さの測定方法を示す図。The figure which shows the measuring method of the lining thickness of the concrete 21 which concerns on this Embodiment. 本実施の形態に係るコンクリート21の覆工厚さの測定方法を示す図。The figure which shows the measuring method of the lining thickness of the concrete 21 which concerns on this Embodiment. 本実施の形態に係るコンクリート21の覆工厚さの測定方法を示す図。The figure which shows the measuring method of the lining thickness of the concrete 21 which concerns on this Embodiment. 本実施の形態に係るコンクリート21の覆工厚さの測定方法を示す図。The figure which shows the measuring method of the lining thickness of the concrete 21 which concerns on this Embodiment. 本実施の形態に係るコンクリート21の打設方法を示す図。The figure which shows the placement method of the concrete 21 which concerns on this Embodiment. 本実施の形態に係る制御装置61を示す図。The figure which shows the control apparatus 61 which concerns on this Embodiment. 本実施の形態に係る制御装置61の覆工厚さ制御のフローチャート。The flowchart of the lining thickness control of the control apparatus 61 which concerns on this Embodiment.

符号の説明Explanation of symbols

1………シールド掘削機
3………回転切削部
5………テールプレート
7………シールドジャッキ
9………プレスジャッキ
11………妻型枠
13………内型枠
15………コンクリート供給ホース
16………コンクリート供給孔
17………打設ポンプ
19………地山
21………コンクリート
23………スキンプレート
25………側板
27………受振装置
29………発振装置
31………ソケット
33………ゲート
37………ケーシング
39………ニップル
41………振動子
43………ヘッド
45………ジャッキ
47………センサ
49………コイル
51………超磁歪素子
53………永久磁石
55………ばね
57………ロッド
59………波動
61………制御装置
1 ……… Shield excavator 3 ……… Rotating cutting part 5 ……… Tail plate 7 ……… Shield jack 9 ……… Press jack 11 ……… Wife mold 13 ……… Inner mold 15 ……… Concrete supply hose 16 ……… Concrete supply hole 17 ………… Place pump 19 ……… Machiyama 21 ……… Concrete 23 ……… Skin plate 25 ……… Side plate 27 ……… Vibration device 29 ……… Oscillation Device 31 ......... Socket 33 ......... Gate 37 ......... Case 39 ......... Nipple 41 ......... Vibrator 43 ......... Head 45 ......... Jack 47 ......... Sensor 49 ... …… Coil 51 ... ... Super magnetostrictive element 53 ......... Permanent magnet 55 ......... Spring 57 ... …… Rod 59 ......... Wave 61 ......... Control device

Claims (5)

シールド掘削機で地山を掘削しつつ、前記シールド掘削機のテール部内側で型枠を環状に組立て、前記型枠と前記掘削した地山との間にコンクリートを打設して覆工コンクリートを構築し、トンネルを形成するにあたり、
前記型枠が、超磁歪素子を用いた発振装置と受振装置を有し、
前記発振装置が振動して波動を発生させ、前記受振装置が前記波動を受振し、前記波動の到達時間から、前記コンクリートの覆工厚さを測定する工程(a)と、
前記覆工厚さが目標覆工厚さの管理範囲内になるようにコンクリートの供給量とコンクリートの打設圧力を変化する工程(b)と、
を備えることを特徴とするコンクリート打設制御方法。
While excavating the natural ground with a shield excavator, the formwork is assembled in an annular shape inside the tail part of the shield excavator, and concrete is placed between the formwork and the excavated natural ground to provide lining concrete. In building and forming a tunnel,
The mold has an oscillation device and a vibration receiving device using a giant magnetostrictive element,
(A) measuring the lining thickness of the concrete from the arrival time of the wave, the vibration receiving device receiving the wave, the oscillation device vibrates to generate a wave;
A step (b) of changing the concrete supply amount and the concrete placing pressure so that the lining thickness falls within the control range of the target lining thickness;
A concrete placement control method comprising:
前記型枠は、
スキンプレートに4枚の側板が設けられ、
前記スキンプレートに複数の開口部が設けられ、
前記開口部に開閉可能なゲートが設けられ、
前記スキンプレートの片面側の前記ゲートに対応する位置に、超磁歪素子を用いる発振装置と受振装置とが設けられることを特徴とする請求項1記載のコンクリート打設制御方法。
The formwork is
There are 4 side plates on the skin plate,
The skin plate is provided with a plurality of openings,
A gate that can be opened and closed is provided in the opening,
The concrete placement control method according to claim 1, wherein an oscillation device using a magnetostrictive element and a vibration receiving device are provided at a position corresponding to the gate on one side of the skin plate.
前記発振装置は、超磁歪素子により振動可能なヘッドを有する超磁歪型振動子を備え、
前記受振装置は、センサを備えることを特徴とする請求項2記載のコンクリート打設制御方法。
The oscillation device includes a giant magnetostrictive vibrator having a head that can vibrate by a giant magnetostrictive element,
The concrete placement control method according to claim 2, wherein the vibration receiving device includes a sensor.
前記工程(a)は、
前記発振装置が振動して波動を発生させる工程と、
地山と前記コンクリートの境界により反射した前記波動を前記受振装置が受振する工程と、
前記波動に基づき、前記コンクリートの覆工厚さを求める工程と、
を備え、
前記工程(b)は、
前記コンクリートの覆工厚さと目標覆工厚さを比較する工程と、
前記覆工厚さが前記目標覆工厚さの管理範囲外にある場合に、コンクリートの供給量と、コンクリートの打設圧力を変更する工程と、
を備えることを特徴とする請求項1記載のコンクリート打設制御方法。
The step (a)
A step in which the oscillation device vibrates to generate a wave;
The vibration receiving device receiving the wave reflected by the boundary between the natural ground and the concrete; and
A step of determining a lining thickness of the concrete based on the wave;
With
The step (b)
Comparing the concrete lining thickness with the target lining thickness;
When the lining thickness is outside the control range of the target lining thickness, the step of changing the concrete supply amount and the concrete placement pressure;
The concrete placement control method according to claim 1, further comprising:
シールド掘削機で地山を掘削しつつ、前記シールド掘削機のテール部内側で型枠を環状に組立て、前記型枠と前記掘削した地山との間にコンクリートを打設して覆工コンクリートを構築し、トンネルを形成するにあたり、
前記型枠と前記掘削した地山との間にコンクリートを供給する供給手段と、
前記コンクリートを押圧する押圧手段と、
前記型枠は、超磁歪素子を用いた発振装置と受振装置を有し、前記発振装置が発した振動により発生した波動を前記受振装置が受振して、前記コンクリートの厚さを測定する測定手段と、
測定されたコンクリートの厚さに応じて、前記供給手段のコンクリート供給量と、前記押圧手段の押圧力を制御する制御手段と
を備えることを特徴とするコンクリート打設システム。
While excavating the natural ground with a shield excavator, the formwork is assembled in an annular shape inside the tail part of the shield excavator, and concrete is placed between the formwork and the excavated natural ground to provide lining concrete. In building and forming a tunnel,
Supply means for supplying concrete between the formwork and the excavated ground;
Pressing means for pressing the concrete;
The mold has an oscillation device and a vibration receiving device using a giant magnetostrictive element, and the vibration receiving device receives a wave generated by vibration generated by the oscillation device and measures the thickness of the concrete. When,
A concrete placement system comprising: a concrete supply amount of the supply means and a control means for controlling the pressing force of the pressing means according to the measured concrete thickness.
JP2008017294A 2008-01-29 2008-01-29 Concrete placement control method and concrete placement system Active JP4922200B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008017294A JP4922200B2 (en) 2008-01-29 2008-01-29 Concrete placement control method and concrete placement system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008017294A JP4922200B2 (en) 2008-01-29 2008-01-29 Concrete placement control method and concrete placement system

Publications (2)

Publication Number Publication Date
JP2009179944A JP2009179944A (en) 2009-08-13
JP4922200B2 true JP4922200B2 (en) 2012-04-25

Family

ID=41034132

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008017294A Active JP4922200B2 (en) 2008-01-29 2008-01-29 Concrete placement control method and concrete placement system

Country Status (1)

Country Link
JP (1) JP4922200B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104838A (en) * 2017-11-01 2018-06-01 中铁隧道勘察设计研究院有限公司 A kind of automation control method of lining construction

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5611671B2 (en) * 2010-05-27 2014-10-22 鹿島建設株式会社 Concrete management method and concrete management apparatus
KR101445714B1 (en) 2013-07-19 2014-09-29 한국원자력환경공단 Apparatus for managing silo lining concrete placement using concrete filled detection sensor
AT518000B1 (en) * 2015-11-16 2018-05-15 Oestu Stettin Hoch Und Tiefbau Gmbh Device and method for removing a tunnel, in particular by measuring a concrete pressure
JP6608272B2 (en) * 2015-12-24 2019-11-20 鹿島建設株式会社 Tunnel excavation method and shield excavator
CN108222971A (en) * 2018-02-13 2018-06-29 北京新能正源环境科技有限公司 Filling system
JP7244336B2 (en) * 2019-04-10 2023-03-22 清水建設株式会社 Mountain tunnel concrete thickness measuring method and measuring device

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6049260A (en) * 1983-08-29 1985-03-18 Nippon Telegr & Teleph Corp <Ntt> Method and device for nondestructive inspection of tunnel lining
JPS60126496A (en) * 1983-12-13 1985-07-05 株式会社間組 Control apparatus and method of shield drilling machine
JPH04176998A (en) * 1990-11-09 1992-06-24 Fudo Constr Co Ltd Quality control method for tunnel lining by cast-in-place concrete
JP2809373B2 (en) * 1993-07-14 1998-10-08 三菱重工業株式会社 Filling detection device for lining in formwork
JPH07218477A (en) * 1994-01-31 1995-08-18 Tomohiko Akuta Searching device
JP2005264587A (en) * 2004-03-19 2005-09-29 Mitsubishi Heavy Ind Ltd Form for tunnel excavation, and tunnel excavation method
JP4537229B2 (en) * 2005-03-02 2010-09-01 独立行政法人鉄道建設・運輸施設整備支援機構 Tunnel construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104838A (en) * 2017-11-01 2018-06-01 中铁隧道勘察设计研究院有限公司 A kind of automation control method of lining construction
CN108104838B (en) * 2017-11-01 2019-03-22 中铁隧道勘察设计研究院有限公司 A kind of automation control method of lining construction

Also Published As

Publication number Publication date
JP2009179944A (en) 2009-08-13

Similar Documents

Publication Publication Date Title
JP4922200B2 (en) Concrete placement control method and concrete placement system
CN106703814B (en) Tunneling subway station hole pile construction method
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR101162111B1 (en) Construction Method of Concrete Pile
JP2006226064A (en) Pile construction method and pile structure
JP2005344346A (en) Method for driving steel pipe
JP6987559B2 (en) Construction method of continuous underground wall and steel pipe pile
JP2010242318A (en) Placing joint implement, and method for constructing placing joint portion of underground wall
JP4922199B2 (en) Formwork and concrete lining thickness measurement method
PH12020551966A1 (en) Concrete foundation structure and method for constructing same
JP2020023818A (en) Rectangular pit and its construction method
JP5117369B2 (en) Underpass construction method
JP5016947B2 (en) Solidification material vibration injection method and apparatus
JP2017179904A (en) Support structure of structure and reinforcement method of pile foundation structure
JP3777549B2 (en) Synthetic underground wall, its construction method, and water expansion waterproofing material
KR20120055835A (en) Membrane Cover Apparatus for Concrete Pile
JP2010106545A (en) Method of constructing foundation structure in structure, and foundation structure
JP2835003B2 (en) Formwork equipment for tunnel lining
JP4712529B2 (en) Tunnel excavator
JPWO2006003724A1 (en) Composite anchor bolt and its construction method
JP6019096B2 (en) Concrete structure, method for constructing concrete structure
JP2020007735A (en) Method for reinforcing foundation structure and structure for reinforcing foundation structure
JPH1046573A (en) Bottom enlarged cast-in-place pile and its construction method
CN220521412U (en) Construction structure is restoreed on push pipe well road surface
KR20140109006A (en) Open shield method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20101006

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120124

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120131

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120203

R150 Certificate of patent or registration of utility model

Ref document number: 4922200

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150210

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250