JP4848182B2 - Power supply system - Google Patents

Power supply system Download PDF

Info

Publication number
JP4848182B2
JP4848182B2 JP2005367863A JP2005367863A JP4848182B2 JP 4848182 B2 JP4848182 B2 JP 4848182B2 JP 2005367863 A JP2005367863 A JP 2005367863A JP 2005367863 A JP2005367863 A JP 2005367863A JP 4848182 B2 JP4848182 B2 JP 4848182B2
Authority
JP
Japan
Prior art keywords
power
usage
power supply
supply
identifier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2005367863A
Other languages
Japanese (ja)
Other versions
JP2007172220A (en
Inventor
誠 置田
隆之 重松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hewlett Packard Development Co LP
Original Assignee
Hewlett Packard Development Co LP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hewlett Packard Development Co LP filed Critical Hewlett Packard Development Co LP
Priority to JP2005367863A priority Critical patent/JP4848182B2/en
Publication of JP2007172220A publication Critical patent/JP2007172220A/en
Application granted granted Critical
Publication of JP4848182B2 publication Critical patent/JP4848182B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、電力システムから電力を使用する機器に電力を供給する電力供給システムに関する。   The present invention relates to a power supply system that supplies power to a device that uses power from the power system.

例えば、特許文献1,2は、パーソナルコンピュータおよび携帯電話機などの電力を使用する機器に対して電力を供給し、供給した電力量に応じて電力料金の課金を行うシステムを開示する。
一般に、このような電力使用機器に対して供給される電力量が、企業および家庭などで使用される電力量に占める割合は少なく、その電力料金もごく少ない。
このように少ない電力量を供給するシステムに対しては、電力量に従った電力料金の課金方法は、必ずしも最適ではない。
特開2004−219181号公報 特開2004−234117号公報
For example, Patent Documents 1 and 2 disclose systems that supply power to devices that use power, such as personal computers and mobile phones, and charge a power fee according to the amount of power supplied.
In general, the amount of power supplied to such power-using devices accounts for a small percentage of the amount of power used in businesses, homes, etc., and the power charge is very low.
For such a system that supplies a small amount of power, a billing method for a power charge according to the amount of power is not necessarily optimal.
JP 2004-219181 A JP 2004-234117 A

本発明は、上述のような背景からなされたものであって、電力使用機器に対して電力を供給し、適切に電力料金を課金することができるように改良された電力供給システムを提供することを目的とする。   The present invention has been made from the background as described above, and provides an improved power supply system that can supply power to a power-using device and charge the power charge appropriately. With the goal.

上記目的を達成するために、本発明にかかる第1の電力供給システムは、所定の電力システムに接続されて電力の供給を受ける電力供給装置と、固有の利用識別子が付され、接続された前記電力供給装置から電力の供給を受け、供給された電力を外部に対して供給する電力利用装置と、前記電力利用装置による電力の供給に対する電力料金の課金を、時間単位で行う課金装置とを有する電力供給システムであって、前記電力利用装置は、外部に対する電力供給の開始および終了の操作を受ける操作手段と、前記付された利用識別子と、前記電力供給の開始および終了とを、前記課金装置に通知する通知手段とを有する。   In order to achieve the above object, a first power supply system according to the present invention includes a power supply device that is connected to a predetermined power system and receives power supply, and a unique use identifier is attached and connected. A power usage apparatus that receives power from the power supply apparatus and supplies the supplied power to the outside; and a charging apparatus that charges a power charge for the power supply by the power usage apparatus in units of hours In the power supply system, the power usage apparatus includes: an operating unit that receives a start and end operation of power supply to the outside; the attached usage identifier; and the start and end of the power supply. And a notification means for notifying to.

また、本発明にかかる第2の電力供給システムは、所定の電力システムに接続されて電力の供給を受ける電力供給装置と、固有の利用識別子が付され、接続された前記電力供給装置から電力の供給を受け、供給された電力を外部に対して供給する電力利用装置と、課金装置とを有する電力供給システムであって、前記課金装置は、前記電力供給装置から通知される利用識別子と電力供給の開始および終了との通知に応じて、前記電力利用装置による電力の供給に対する電力料金の課金を、時間単位で行う課金手段と、前記電力供給装置から通知される電力供給の開始および終了との通知に応じて、前記電力供給装置から前記電力利用装置への電力供給を制御する供給制御手段とを有し、前記電力利用装置は、外部に対する電力供給の開始および終了の操作を受ける操作手段と、前記付された利用識別子と、前記電力供給の開始および終了とを、前記電力供給装置に対して通知する通知手段とを有し、前記電力供給装置は、前記通知された利用識別子と前記電力供給の開始および終了とを、前記課金装置に通知する通知手段と、前記課金装置からの制御に従って、前記電力利用装置への電力供給を開始および終了する供給スイッチ手段とを有する。   In addition, a second power supply system according to the present invention includes a power supply device connected to a predetermined power system to receive power supply, a unique usage identifier, and power from the connected power supply device. A power supply system having a power use device that receives supply and supplies the supplied power to the outside, and a billing device, wherein the billing device uses a usage identifier and power supply notified from the power supply device In response to the notification of the start and end of the power supply, charging means for charging the power charge for the power supply by the power utilization device in units of hours, and the start and end of the power supply notified from the power supply device Supply control means for controlling power supply from the power supply device to the power usage device in response to the notification, and the power usage device starts and stops power supply to the outside. An operation means for receiving an end operation; and a notification means for notifying the power supply apparatus of the attached usage identifier and the start and end of the power supply. Notification means for notifying the billing apparatus of the notified usage identifier and the start and end of the power supply, and supply switch means for starting and ending power supply to the power utilization apparatus according to control from the billing apparatus And have.

また、本発明にかかる電力利用装置は、固有の利用識別子が付され、所定の電力システムから電力の供給を受ける電力供給装置に接続されて電力の供給を受ける電力利用装置であって、供給された電力を外部に対して供給する電力利用装置であって、前記電力利用装置による電力供給に対する電力料金の課金が、電力供給の開始および終了の通知に応じて、前記利用識別子を用いて時間単位で行なわれ、前記電力利用装置は、外部に対する電力供給の開始および終了の操作を受ける操作手段と、前記課金のために、前記付された利用識別子と、前記電力供給の開始および終了とを通知する通知手段とを有する。   A power usage apparatus according to the present invention is a power usage apparatus that is supplied with power by being connected to a power supply apparatus that is supplied with power from a predetermined power system with a unique usage identifier attached thereto. A power usage apparatus for supplying the external power to the outside, wherein charging of a power charge for power supply by the power usage apparatus is performed in units of time using the usage identifier in response to notification of start and end of power supply The power utilization apparatus notifies the operation means that receives an operation of starting and ending power supply to the outside, the attached usage identifier, and the start and end of the power supply for the accounting. Notification means.

また、本発明にかかる電力供給装置は、所定の電力システムに接続されて電力の供給を受け、受けた電力を電力利用装置に供給する電力供給装置であって、前記電力供給装置から通知される利用識別子と電力供給の開始および終了との通知に応じて、前記電力利用装置による電力の供給に対する課金が、時間単位で行なわれ、前記電力供給装置から通知される電力供給の開始および終了との通知に応じて、前記電力供給装置から前記電力利用装置への電力供給が制御され、前記電力利用装置は、固有の利用識別子が付され、接続された前記電力供給装置から電力の供給を受け、供給された電力を外部に対して供給し、前記付された利用識別子と、前記電力供給の開始および終了とを、前記電力供給装置に対して通知し、前記電力供給装置は、前記通知された利用識別子と前記電力供給の開始および終了とを、前記課金装置に通知する通知手段と、前記課金装置からの制御に従って、前記電力利用装置への電力供給を開始および終了する供給スイッチ手段とを有する。   A power supply apparatus according to the present invention is a power supply apparatus that is connected to a predetermined power system, receives power supply, and supplies the received power to a power utilization apparatus, and is notified from the power supply apparatus. In response to the notification of the usage identifier and the start and end of power supply, charging for the power supply by the power usage apparatus is performed in units of time, and the start and end of power supply notified from the power supply apparatus In response to the notification, power supply from the power supply device to the power usage device is controlled, the power usage device is assigned a unique usage identifier, and receives power supply from the connected power supply device, Supply the supplied power to the outside, notify the attached usage identifier and the start and end of the power supply to the power supply device, the power supply device, A notification switch for notifying the billing device of the notified usage identifier and the start and end of the power supply, and a supply switch for starting and ending power supply to the power utilization device according to control from the billing device Means.

本発明によれば、上述のような背景からなされたものであって、電力使用機器に対して電力を供給し、適切に電力料金を課金することができるように改良された電力供給システムが提供される。   According to the present invention, there is provided an improved power supply system that has been made from the background as described above and that can supply power to a power-using device and appropriately charge a power charge. Is done.

以下、本発明の実施形態を説明する。   Embodiments of the present invention will be described below.

[第1の電力供給システム1]
図1は、本発明にかかる電力供給方法が適用される第1の電力供給システム1の構成を例示する図である。
電力供給システム1は、図1に示す構成部分により、電気機器100に対する電力の供給、電力の供給を受けた電気機器100の利用者(電力利用者)に対する電力利用時間に応じた課金、および、電力利用装置302の所有者(電力供給者)に対する電力利用時間に応じた電力料金の払い戻しなどを行う。
[First power supply system 1]
FIG. 1 is a diagram illustrating a configuration of a first power supply system 1 to which a power supply method according to the present invention is applied.
The power supply system 1 uses the components shown in FIG. 1 to supply power to the electric device 100, charge according to the power use time for the user (electric power user) of the electric device 100 that has received the power supply, and Refund of the electric power charge according to the electric power utilization time with respect to the owner (electric power supplier) of the electric power utilization apparatus 302 is performed.

なお、図示の明確化および具体化のために、図1およびその他の図においては、本願発明の説明に、直接、必要とされない構成部分は、適宜、省略されている。
また、以下、電力供給システム1などにおいて、情報処理および情報伝送の主体となりうる構成部分を、ノードと総称することがある。
また、以下に示す各ノードの機能が、ハードウエア的に、あるいは、ソフトウエア的に実現されるかは例示であって、各ノードの機能は、可能な範囲で、ハードウエア的にもソフトウエア的にも実現されうる。
また、以下に示す各システムの構成は、例示であって、その各構成部分の数は、1つ以上であればよく、また、ノード間において、データは、有線通信回線および無線通信回線のいずれを介して伝送されてもよい。
また、以下、各図において、実質的に同じ構成部分には、同じ符号が付される。
また、以下に示す電力供給システムにおける使用時間に応じた課金は、電力利用者に対して電力利用時間ごとに課金する方法をとる方法と、例えば、何年何月何日まで使用可能、あるいは、使用開始から1年使用可能など、電力利用者に対して電力を供給する期間を設定して課金する方法とを含むが、以下の説明においては、前者の課金方法が具体例とされている。
For clarity and concreteness of illustration, in FIG. 1 and other drawings, components that are not directly required for the description of the present invention are omitted as appropriate.
In the following, in the power supply system 1 and the like, components that can be the main body of information processing and information transmission may be collectively referred to as nodes.
In addition, whether the functions of each node shown below are realized by hardware or software is an exemplification, and the functions of each node are as much as possible in terms of hardware and software. Can also be realized.
The configuration of each system shown below is an exemplification, and the number of each component may be one or more. In addition, between nodes, data may be either a wired communication line or a wireless communication line. May be transmitted over the network.
Hereinafter, in each figure, the same reference numerals are given to substantially the same components.
In addition, the billing according to the usage time in the power supply system shown below is a method of taking a billing method for each power usage time to the power user, for example, how many months, how many days can be used, or In the following description, the former charging method is taken as a specific example, including a method of charging by setting a period for supplying power to a power user, such as being usable for one year from the start of use.

図1に示すように、第1の電力供給システム1は、通信システム102、電力事業者システム140、第1の電力供給装置202および第1の電力利用装置302から構成される。
通信システム102は、有線通信回線および無線通信回線を介したデータ伝送が可能なネットワーク104および移動体通信用の基地局106から構成される。
電力事業者システム140は、ネットワーク104に接続された課金サーバ12および電力システム142から構成される。
電力システム142は、発電設備、送電設備および変電設備など(図示せず)を含み、電力供給のために一般的に用いられる汎用コンセント146を介して、電気機器100に対して電力を供給可能なように構成されている。
なお、以下の説明においては、電気機器100が、携帯可能な機器(携帯電話機、PCあるいはPDA(Personal Digital Assistance)など)であり、ネットワーク104を介して課金サーバ12との間で通信可能である場合が具体例とされる。
As shown in FIG. 1, the first power supply system 1 includes a communication system 102, a power provider system 140, a first power supply device 202, and a first power usage device 302.
The communication system 102 includes a network 104 capable of data transmission via a wired communication line and a wireless communication line, and a base station 106 for mobile communication.
The electric power company system 140 includes the billing server 12 and the electric power system 142 connected to the network 104.
The power system 142 includes a power generation facility, a power transmission facility, a substation facility, and the like (not shown), and can supply power to the electrical device 100 via a general-purpose outlet 146 that is generally used for power supply. It is configured as follows.
In the following description, electric device 100 is a portable device (such as a mobile phone, a PC, or a PDA (Personal Digital Assistance)) and can communicate with billing server 12 via network 104. The case is a specific example.

電力供給装置202は、例えば、不特定多数に電力を供給する意思を有する企業により設置され、供給アダプタ22と、供給アダプタ22に接続され、電力供給のために一般的に用いられる汎用プラグ144、および、専用コンセント課金サーバ12とから構成される。
電力利用装置302は、携帯可能な電気機器100のユーザにより、電気機器100とともに携帯され、電力供給装置202が設置されている場所で用いられる。
電力利用装置302は、利用アダプタ32と、利用アダプタ32に接続された汎用コンセント146および利用アダプタ32とから構成される。
The power supply device 202 is installed by, for example, a company that intends to supply power to an unspecified number of people, and is connected to the supply adapter 22 and the supply adapter 22 and is generally used for power supply, And a dedicated outlet billing server 12.
The power usage device 302 is carried by the user of the portable electrical device 100 together with the electrical device 100 and used in a place where the power supply device 202 is installed.
The power usage device 302 includes a usage adapter 32, a general-purpose outlet 146 connected to the usage adapter 32, and a usage adapter 32.

電力供給装置202において、供給アダプタ22は、パーソナルコンピュータ(PC)204と接続される。
PC204は、ネットワーク104などを介した電力事業者システム140の課金サーバ12との間の通信、および、利用アダプタ32との間の通信およびこれに対する制御を行う。
また、電力供給装置202において、専用コンセント206は、電力利用装置302の専用プラグ306と接続され、汎用プラグ144は、電力システム142の汎用コンセント146と接続される。
In the power supply apparatus 202, the supply adapter 22 is connected to a personal computer (PC) 204.
The PC 204 performs communication with the charging server 12 of the power provider system 140 via the network 104 and the like, communication with the usage adapter 32, and control thereof.
In the power supply apparatus 202, the dedicated outlet 206 is connected to the dedicated plug 306 of the power utilization apparatus 302, and the general purpose plug 144 is connected to the general purpose outlet 146 of the power system 142.

また、電力利用装置302において、利用アダプタ32は、電気機器100と接続され、さらに、無線通信回線108および基地局106を介して、電力事業者システム140の課金サーバ12と通信可能に接続される。
電気機器100は、利用アダプタ32との通信、利用アダプタ32に対する制御、および、ネットワーク104を介した電力事業者システム140の課金サーバ12との間の通信を行う。
また、電力利用装置302において、汎用コンセント146は、電気機器100の汎用プラグ144と接続され、専用プラグ306は、上述のように、電力供給装置202の専用コンセント206と接続される。
In the power usage apparatus 302, the usage adapter 32 is connected to the electrical device 100 and further connected to the charging server 12 of the power provider system 140 via the wireless communication line 108 and the base station 106 so as to be communicable. .
The electric device 100 performs communication with the usage adapter 32, control over the usage adapter 32, and communication with the billing server 12 of the power provider system 140 via the network 104.
In the power usage apparatus 302, the general-purpose outlet 146 is connected to the general-purpose plug 144 of the electric device 100, and the dedicated plug 306 is connected to the dedicated outlet 206 of the power supply apparatus 202 as described above.

[ハードウエア構成]
図2(A),(B)は、それぞれ、図1に示した専用コンセント206および専用プラグ306の構成を例示する図である。
図2(A),(B)に示すように、専用コンセント206は、専用プラグ306にのみ接続可能に適合し、汎用プラグ144に適合しない形状に構成され、同様に、専用プラグ306は、専用コンセント206にのみ接続可能に適合し、汎用コンセント146に適合しない形状に構成される。
[Hardware configuration]
2A and 2B are diagrams illustrating the configurations of the dedicated outlet 206 and the dedicated plug 306 shown in FIG. 1, respectively.
As shown in FIGS. 2A and 2B, the dedicated outlet 206 is configured to be connectable only to the dedicated plug 306 and not to the general-purpose plug 144. Similarly, the dedicated plug 306 is a dedicated plug 306. It is adapted to be connectable only to the outlet 206 and is configured not to fit the general-purpose outlet 146.

専用コンセント206および専用プラグ306には、データ伝送用のケーブルと、電力供給用のケーブルとを含むデータ・電力ケーブル212が接続される。
専用コンセント206は、データ・電力ケーブル212のデータ用ケーブルを介して、利用アダプタ32との間でデータの伝送を行うために用いられるデータ用受け口210−1,210−2(以下、これらを単にデータ用受け口210と略記する場合がある)を有する。
また、専用コンセント206は、データ・電力ケーブル212の電力用ケーブルを介して、汎用コンセント146と同様に、汎用プラグ144に接続された利用アダプタ32および電気機器100などの電気機器に電力を供給するために用いられる電力用受け口208−1,208−2を有する。
専用プラグ306は、電力用受け口208−1,208−2に挿入され、供給アダプタ22から電力の供給を受けるために用いられる電力用電極308−1,308−2、および、データ用受け口210−1,210−2に挿入され、供給アダプタ22とのデータの伝送のために用いられるデータ用電極310を有する。
なお、実際には、データ用電極310は、データ用受け口210−1,210−2に対応する2つの接点を有する。
A data / power cable 212 including a data transmission cable and a power supply cable is connected to the dedicated outlet 206 and the dedicated plug 306.
The dedicated outlet 206 is a data receiving port 210-1, 210-2 (hereinafter simply referred to as “data receiving port”) used for transmitting data to / from the use adapter 32 via the data cable of the data / power cable 212. May be abbreviated as a data receiving port 210).
In addition, the dedicated outlet 206 supplies power to the usage adapter 32 and the electrical device such as the electrical device 100 connected to the general-purpose plug 144 via the power cable of the data / power cable 212 in the same manner as the general-purpose outlet 146. Power receptacles 208-1 and 208-2 used for the purpose.
The dedicated plug 306 is inserted into the power receiving ports 208-1 and 208-2 and used for receiving power from the supply adapter 22, and the power electrodes 308-1 and 308-2 and the data receiving port 210-. 1 and 210-2 and a data electrode 310 used for data transmission with the supply adapter 22.
In practice, the data electrode 310 has two contacts corresponding to the data receiving ports 210-1 and 210-2.

図3は、図1に示した課金サーバ12、電気機器100およびPC204のハードウエア構成を例示する図である。
図3に示すように、課金サーバ12、電気機器100およびPC204は、CPU122、RAMおよびROMなどを含むメモリ124およびタイマ126などを含む本体120、キーボードおよび表示装置など(図示せず)を含む入出力装置128、他のノードとの間の通信機能およびインターフェース機能を実現する通信・インターフェース(IF)装置130、および、FDD、HDD、CD装置および不揮発性メモリなどの記録装置132から構成される。
つまり、図3に示した課金サーバ12などは、他のノードとの間の通信、および、他のノードに対する制御が可能なコンピュータとしての構成部分を有する。
FIG. 3 is a diagram illustrating a hardware configuration of billing server 12, electrical device 100, and PC 204 shown in FIG.
As shown in FIG. 3, billing server 12, electrical device 100 and PC 204 include CPU 122, memory 124 including RAM and ROM, main body 120 including timer 126, etc., keyboard and display device (not shown). The output device 128 includes a communication / interface (IF) device 130 that realizes a communication function and an interface function with other nodes, and a recording device 132 such as an FDD, HDD, CD device, and nonvolatile memory.
That is, the accounting server 12 shown in FIG. 3 has a component as a computer that can communicate with other nodes and control other nodes.

図4は、図1に示した第1の供給アダプタ22のハードウエア構成を示す図である。
図4に示すように、供給アダプタ22は、データIF部220、ID記憶部222およびPC−IF部224から構成される。
供給アダプタ22は、電力システム142から供給される電力で動作し、これらの構成部分により、供給アダプタ22の所有者(電力供給者)の識別子(供給者ID)、および、電力システム142から供給された電力を、利用アダプタ32に対して出力する。
FIG. 4 is a diagram showing a hardware configuration of the first supply adapter 22 shown in FIG.
As shown in FIG. 4, the supply adapter 22 includes a data IF unit 220, an ID storage unit 222, and a PC-IF unit 224.
The supply adapter 22 operates with the power supplied from the power system 142, and by these components, the identifier (supplier ID) of the owner (power supplier) of the supply adapter 22 and the power system 142 are supplied. The generated power is output to the use adapter 32.

PC−IF部224は、PC204などから供給者IDを受け入れて、ID記憶部222に対して出力する。
ID記憶部222は、PC−IF部224から入力された供給者IDを記憶し、データIF部220に対して出力する。
データIF部220は、専用コンセント206のデータ用受け口210を介した利用アダプタ32からの問い合わせに応じて、ID記憶部222から入力される電力供給者IDを返す。
The PC-IF unit 224 receives the supplier ID from the PC 204 or the like and outputs it to the ID storage unit 222.
The ID storage unit 222 stores the supplier ID input from the PC-IF unit 224 and outputs it to the data IF unit 220.
The data IF unit 220 returns the power supplier ID input from the ID storage unit 222 in response to an inquiry from the usage adapter 32 via the data receptacle 210 of the dedicated outlet 206.

図5は、図1に示した第1の利用アダプタ32のハードウエア構成を示す図である。
図5に示すように、利用アダプタ32は、ユーザインターフェース(UI)部320、CPU122、メモリ124、無線通信装置326、スイッチ制御部328、タイマ部332、データIF部334およびPC−IF部336が、バスを介して接続されて構成される。
さらに、UI部320には、操作ボタン322および動作確認ランプ324が接続され、スイッチ制御部328には、スイッチ330が接続され、データIF部334には、専用プラグ306(図1,図2(B))のデータ用電極310が接続される。
FIG. 5 is a diagram illustrating a hardware configuration of the first usage adapter 32 illustrated in FIG. 1.
As shown in FIG. 5, the usage adapter 32 includes a user interface (UI) unit 320, a CPU 122, a memory 124, a wireless communication device 326, a switch control unit 328, a timer unit 332, a data IF unit 334, and a PC-IF unit 336. Connected via a bus.
Further, an operation button 322 and an operation confirmation lamp 324 are connected to the UI unit 320, a switch 330 is connected to the switch control unit 328, and a dedicated plug 306 (see FIGS. 1 and 2) is connected to the data IF unit 334. The data electrode 310 of B)) is connected.

利用アダプタ32のメモリ124には、利用プログラム34が、ROMなどに記憶されてロードされる。
ロードされた利用プログラム34は、CPU122により、ハードウエア資源の具体的な利用を可能とするリアルタイムOS(図示せず)上で実行される(以下の各プログラムについて同様)。
利用アダプタ32は、供給アダプタ22から供給される電力、あるいは、他の電力供給装置から供給される電力により動作し、実行された利用プログラム34の制御に従って、利用アダプタ32の各構成部分は、電気機器100に対して電力を供給し、その電力の利用を可能とする。
The usage program 34 is stored in the ROM or the like and loaded into the memory 124 of the usage adapter 32.
The loaded utilization program 34 is executed by the CPU 122 on a real-time OS (not shown) that allows specific utilization of hardware resources (the same applies to the following programs).
The usage adapter 32 operates with the power supplied from the supply adapter 22 or the power supplied from another power supply device, and each component of the usage adapter 32 is electrically controlled according to the control of the executed usage program 34. Power is supplied to the device 100 and the power can be used.

UI部320は、利用アダプタ32の利用者による操作ボタン322に対する電力供給の開始および終了のための操作を受け入れて、この操作を示すデータを、CPU122などに対して出力する。
また、CPU122などから設定されるデータに従って、UI部320は、動作確認ランプ324の点灯および消灯を行い、利用アダプタ32の動作状態を利用者に示す。
無線通信装置326は、ネットワーク104、基地局106および無線通信回線108(図1)を介した課金サーバ12との間の通信のために必要な機能を実現する。
The UI unit 320 accepts operations for starting and ending power supply to the operation buttons 322 by the user of the usage adapter 32, and outputs data indicating the operations to the CPU 122 and the like.
Further, the UI unit 320 turns on and off the operation check lamp 324 according to data set by the CPU 122 and the like, and indicates the operating state of the usage adapter 32 to the user.
The wireless communication device 326 implements functions necessary for communication with the accounting server 12 via the network 104, the base station 106, and the wireless communication line 108 (FIG. 1).

スイッチ制御部328は、CPU122により設定されるデータに従って、スイッチ330を制御し、供給アダプタ22から供給された電力の電気機器100に対する供給および供給の停止を行う機能を実現する。
また、スイッチ制御部328は、スイッチ330を介して、供給アダプタ22から電気機器100に対する電力の供給を監視し、電力の供給が行われているか否かを示すデータを、CPU122などに対して通知するための機能を実現する。
スイッチ330は、スイッチ制御部328の制御に従って、電気機器100に対する電力の接続および切断を行う。
なお、スイッチ330は、上述したスイッチとしての機能の他に、例えば、通過する電流が1Aを超えたときに、電流を遮断するブレーカとしての機能を有し、時間に応じた課金により、電力供給者に損失が生じることを防いでいる。
タイマ部332は、利用アダプタ32において用いられるクロック信号を計数し、データ・電力ケーブル212(図2(A),(B))の接続が外れたなどの原因で、供給アダプタ22からの電力供給がなくなってから、一定時間が経過したなどのタイミングで、図12などを参照して後述する利用終了処理を起動するための機能を実現する。
The switch control unit 328 controls the switch 330 in accordance with the data set by the CPU 122 and realizes a function of supplying and stopping the supply of power supplied from the supply adapter 22 to the electrical device 100.
In addition, the switch control unit 328 monitors the supply of power from the supply adapter 22 to the electrical device 100 via the switch 330 and notifies the CPU 122 and the like of data indicating whether or not the supply of power is being performed. The function to do is realized.
The switch 330 connects and disconnects electric power to the electrical device 100 according to the control of the switch control unit 328.
The switch 330 has a function as a breaker that cuts off the current when the passing current exceeds 1 A, for example, in addition to the function as the switch described above, and supplies power by charging according to time. It is preventing the loss to the person.
The timer unit 332 counts the clock signal used in the use adapter 32 and supplies power from the supply adapter 22 due to disconnection of the data / power cable 212 (FIGS. 2A and 2B). A function for starting a use end process described later with reference to FIG.

データIF部334は、CPU122により設定されたデータを、専用プラグ306を介して供給アダプタ22に対して出力するための機能、および、供給アダプタ22から入力されるデータを受けて、CPU122などに対して出力するための機能を実現する。
PC−IF部336は、電気機器100から入力されるデータを受けて、CPU122などに対して出力するための機能、および、CPU122から設定されたデータを、電気機器100に対して出力するための機能を実現する。
The data IF unit 334 receives a function for outputting the data set by the CPU 122 to the supply adapter 22 via the dedicated plug 306 and the data input from the supply adapter 22 to the CPU 122 and the like. Realizes the function to output.
The PC-IF unit 336 receives the data input from the electric device 100 and outputs the data set to the CPU 122 and the data set from the CPU 122 to the electric device 100. Realize the function.

[ソフトウエア]
図6は、図1に示した課金サーバ12において実行される課金プログラム16の構成を示す図である。
図6に示すように、課金プログラム16は、通信制御部160、UI部162、認証部164、利用処理部170および供給処理部180から構成される。
利用処理部170は、利用者管理部172、利用時間管理部174、課金処理部176および利用者データベース(DB)178から構成される。
供給処理部180は、供給者管理部182、供給時間管理部184、返還処理部186および供給者DB188から構成される。
[Software]
FIG. 6 is a diagram showing a configuration of the billing program 16 executed in the billing server 12 shown in FIG.
As shown in FIG. 6, the billing program 16 includes a communication control unit 160, a UI unit 162, an authentication unit 164, a usage processing unit 170 and a supply processing unit 180.
The usage processing unit 170 includes a user management unit 172, a usage time management unit 174, a charging processing unit 176, and a user database (DB) 178.
The supply processing unit 180 includes a supplier management unit 182, a supply time management unit 184, a return processing unit 186, and a supplier DB 188.

課金プログラム16は、記録媒体134(図3)などを介して課金サーバ12に供給され、メモリ124にロードされ、OS(図示せず)上で、課金サーバ12のハードウエア資源を具体的に利用して実行される。
課金プログラム16は、これらの構成部分により、電力利用装置302の利用者(電力利用者)に対して、電力の利用時間に従った課金を行うための処理、および、電力供給装置202の所有者(電力供給者)に対して、利用者の電力利用時間に従って、その電力料金を返還したり、電力料金を支払ったりするための処理を行う。
The billing program 16 is supplied to the billing server 12 via the recording medium 134 (FIG. 3) and the like, loaded into the memory 124, and specifically uses the hardware resources of the billing server 12 on the OS (not shown). And executed.
The billing program 16 uses these components to charge the user (power user) of the power usage apparatus 302 according to the power usage time and the owner of the power supply apparatus 202. (Power supplier) performs processing for returning the power charge or paying the power charge in accordance with the power use time of the user.

課金プログラム16において、通信制御部160は、他のノードとの通信のために必要とされる処理を行う。
つまり、通信制御部160は、他のノードとの間で通信制御を行い、課金プログラム16の各構成部分から入力されるデータの他のノードに対する送信、および、他のノードから受けたデータの課金プログラム16の各構成部分に対する出力を行う。
In the charging program 16, the communication control unit 160 performs processing required for communication with other nodes.
That is, the communication control unit 160 performs communication control with other nodes, transmits data input from each component of the charging program 16 to other nodes, and charges data received from other nodes. Output to each component of the program 16 is performed.

UI部162は、課金サーバ12の使用者のために、ユーザインターフェース機能を提供するための処理を行う。
つまり、UI部162は、入出力装置128のキーボードなどに対する使用者の操作を受け入れ、その操作を示すデータを、課金プログラム16の各構成部分に対して出力する。
また、UI部162は、課金プログラム16の他の構成部分からのデータを、入出力装置128の表示装置などに対して出力する。
認証部164は、他のノードからのアクセスに応じて、アクセスしてきたノードに対する認証のための処理を行う。
The UI unit 162 performs processing for providing a user interface function for the user of the accounting server 12.
In other words, the UI unit 162 accepts a user operation on the keyboard of the input / output device 128 and outputs data indicating the operation to each component of the charging program 16.
The UI unit 162 outputs data from other components of the billing program 16 to the display device of the input / output device 128 and the like.
The authentication unit 164 performs a process for authenticating the accessed node in response to an access from another node.

利用処理部170の利用者管理部172は、電力利用装置302の利用者(電力利用者)の登録のために必要な処理を行い、電力利用者に関する情報、この電力利用者が用いる電力利用装置302のID(図8などを参照して後述)、および、この電力利用装置302(利用者)の認証に必要とされる情報など(これらを総称して電力利用者情報とも記す)を、利用者DB178に記憶し、管理する。
利用時間管理部174は、タイマ126(図3)の機能を利用して、電力利用者が、その電力利用装置302を利用して、電力供給装置202から電力の供給を受けた時間(電力利用時間)を測定し、測定した利用時間を、利用者DB178に記憶し、管理する。
The user management unit 172 of the usage processing unit 170 performs processing necessary for registration of the user (power user) of the power usage device 302, and information on the power user, the power usage device used by the power user. 302 ID (described later with reference to FIG. 8 and the like), information necessary for authentication of the power usage apparatus 302 (user), etc. (these are also collectively referred to as power user information) are used. Stored in the administrator DB 178 and managed.
The usage time management unit 174 uses the function of the timer 126 (FIG. 3) to allow the power user to use the power usage device 302 to receive power from the power supply device 202 (power usage). Time) and the measured usage time is stored in the user DB 178 and managed.

課金処理部176は、利用者DB178に記憶された電力利用者情報、および、その電力利用時間を処理して、電力料金を算出し、電力利用者に対する課金のために必要な処理を行う。
課金処理部176は、例えば、電力料金を、電力供給者により設定される単位時間(例えば1分)あたりの課金単価と、電力利用時間とを乗算することにより算出する。
The charging processing unit 176 processes the power user information stored in the user DB 178 and the power usage time, calculates a power charge, and performs processing necessary for charging the power user.
For example, the billing processing unit 176 calculates the power charge by multiplying the billing unit price per unit time (for example, one minute) set by the power supplier by the power usage time.

利用処理部180の供給者管理部182は、電力供給装置202の所有者(電力供給者)の登録のために必要な処理を行い、電力供給者に関する情報、この電力供給者の電力供給装置202のID(図10などを参照して後述)、および、この電力供給装置202(供給者)の認証に必要とされる情報など(これらを総称して電力供給者情報とも記す)を、供給者DB188に記憶し、管理する。
供給時間管理部184は、利用者DB178に記憶された電力利用時間を集計し、各電力供給者の電力供給装置202が、電力利用装置302に対して電力を供給した時間(電力供給時間)を集計し、集計の結果として得られた電力供給時間を、供給者DB188に記憶し、管理する。
The supplier management unit 182 of the usage processing unit 180 performs processing necessary for registering the owner (electric power supplier) of the power supply device 202, and information on the power supplier, the power supply device 202 of this power supplier. ID (to be described later with reference to FIG. 10 and the like), information required for authentication of the power supply device 202 (supplier), etc. (these are also collectively referred to as power supplier information) Store and manage in DB188.
The supply time management unit 184 aggregates the power usage time stored in the user DB 178, and calculates the time (power supply time) when the power supply device 202 of each power supplier supplies power to the power usage device 302. The power supply time obtained as a result of the aggregation is stored in the supplier DB 188 and managed.

返還処理部186は、供給者DB188に記憶された電力供給者情報、および、その電力供給時間を処理して、電力料金を算出し、電力供給者に返還され、あるいは、支払われるべき金額を算出するために必要な処理を行う。
返還処理部186は、例えば、各電力供給者に返還などされるべき金額を、予め設定される単位時間(例えば1分)あたりの単価と、電力供給時間とを乗算することにより算出する。
The return processing unit 186 processes the power supplier information stored in the supplier DB 188 and its power supply time, calculates a power fee, and calculates the amount to be returned or paid to the power supplier. To perform the necessary processing.
For example, the return processing unit 186 calculates the amount of money to be returned to each power supplier by multiplying a preset unit price per unit time (for example, 1 minute) and the power supply time.

[電力供給システム1の動作]
以下、電力供給システム1の動作を説明する。
[Operation of power supply system 1]
Hereinafter, the operation of the power supply system 1 will be described.

[電力利用者登録]
図7は、図1に示した電力供給システム1の全体的な動作を示す第1の通信シーケンス図であって、課金サーバ12に対する電力利用者登録のための処理(S10)を示す。
図8は、図7に示したS100の処理により課金サーバ12から電気機器100(図1)にダウンロードされる登録用画像を例示する図である。
図7に示すように、ステップ100(S100)において、電力利用者は、ネットワーク104を介して課金サーバ12に接続された電気機器100(PC)から、課金サーバ12にアクセスし、図8に示すような登録用画像をダウンロードする。
[Power User Registration]
FIG. 7 is a first communication sequence diagram showing the overall operation of the power supply system 1 shown in FIG. 1, and shows a process for power user registration (S 10) with respect to the accounting server 12.
FIG. 8 is a diagram exemplifying a registration image downloaded from the accounting server 12 to the electrical device 100 (FIG. 1) by the process of S100 shown in FIG.
As shown in FIG. 7, in step 100 (S100), the power user accesses the billing server 12 from the electrical device 100 (PC) connected to the billing server 12 via the network 104, as shown in FIG. Download an image for registration.

ステップ102(S102)において、電気機器100は、その表示装置に、課金サーバ12からダウンロードされた登録用画像を表示する。
ステップ104(S104)において、電力利用者は、表示された登録用画像に対して操作を行い、電力利用者情報の全部または一部の項目(必要項目)を入力する。
なお、図8には、必要項目として、電力利用者に、利用者名、利用者メールアドレスおよび利用者IDの入力が求められる場合が例示されている。
In step 102 (S102), the electric device 100 displays the registration image downloaded from the billing server 12 on the display device.
In step 104 (S104), the power user operates the displayed registration image and inputs all or a part of the power user information (necessary items).
FIG. 8 illustrates a case where the power user is requested to input a user name, a user email address, and a user ID as necessary items.

ステップ106(S106)において、電気機器100は、課金サーバ12に対して、入力された必要項目の情報を含む登録要求を送信する。
ステップ108(S108)において、課金サーバ12は、電気機器100からの登録要求を受信する。
ステップ110(S110)において、課金サーバ12は、電気機器100からの登録要求に含まれる必要項目の情報を、データベース(利用者DB178;図6)に記憶する。
In step 106 (S106), the electric device 100 transmits a registration request including information on the input necessary items to the billing server 12.
In step 108 (S108), the accounting server 12 receives the registration request from the electrical device 100.
In step 110 (S110), the billing server 12 stores information on necessary items included in the registration request from the electric device 100 in the database (user DB 178; FIG. 6).

ステップ112,114(S112,S114)において、課金サーバ12は、電気機器100に対して、登録完了通知を送信する処理を行う。
ステップ116(S116)において、電気機器100は、課金サーバ12からの登録完了通知を行う。
ステップ118(S118)において、電気機器100は、必要に応じて、接続された電力利用装置302の利用アダプタ32のリセットを行い、利用アダプタ32に対して、利用者IDを設定する。
In steps 112 and 114 (S112 and S114), the accounting server 12 performs a process of transmitting a registration completion notification to the electrical device 100.
In step 116 (S116), the electric device 100 issues a registration completion notification from the billing server 12.
In step 118 (S118), the electric device 100 resets the usage adapter 32 of the connected power usage device 302 as necessary, and sets a user ID for the usage adapter 32.

[電力供給者登録]
図9は、図1に示した電力供給システム1の全体的な動作を示す第2の通信シーケンス図であって、課金サーバ12に対する電力供給者登録のための処理(S14)を示す。
図10は、図9に示したS142の処理により課金サーバ12からPC204(図1)にダウンロードされる登録用画像を例示する図である。
図9に示すように、ステップ140(S140)において、電力供給者は、ネットワーク104を介して課金サーバ12に接続されたPC204から、課金サーバ12にアクセスし、図9に示すような登録用画像をダウンロードする。
[Power supplier registration]
FIG. 9 is a second communication sequence diagram showing the overall operation of the power supply system 1 shown in FIG. 1, and shows the process (S14) for registering the power supplier to the billing server 12.
FIG. 10 is a diagram illustrating a registration image downloaded from the billing server 12 to the PC 204 (FIG. 1) by the process of S142 shown in FIG.
As shown in FIG. 9, in step 140 (S140), the power supplier accesses the charging server 12 from the PC 204 connected to the charging server 12 via the network 104, and the registration image as shown in FIG. Download.

ステップ142(S142)において、PC204は、その表示装置に、課金サーバ12からダウンロードされた登録用画像を表示する。
ステップ144(S144)において、電力供給者は、表示された登録用画像に対して操作を行い、電力供給者情報の全部または一部の項目(必要項目)を入力する。
なお、図10には、必要項目として、電力供給者に、供給者名、供給者メールアドレス、供給者IDおよび課金単価の入力が求められる場合が例示されている。
In step 142 (S142), the PC 204 displays the registration image downloaded from the accounting server 12 on the display device.
In step 144 (S144), the power supplier operates the displayed registration image and inputs all or a part of the power supplier information (necessary items).
FIG. 10 illustrates a case where the power supplier is requested to input a supplier name, a supplier email address, a supplier ID, and a charge unit price as necessary items.

ステップ146(S146)において、PC204は、課金サーバ12に対して、入力された必要項目の情報を含む登録要求を送信する。
ステップ148(S148)において、課金サーバ12は、PC204からの登録要求を受信する。
ステップ150(S150)において、課金サーバ12は、PC204からの登録要求に含まれる必要項目の情報を、データベース(供給者DB188;図6)に記憶する。
In step 146 (S146), the PC 204 transmits a registration request including information on the input necessary items to the accounting server 12.
In step 148 (S148), the accounting server 12 receives a registration request from the PC 204.
In step 150 (S150), the accounting server 12 stores information on necessary items included in the registration request from the PC 204 in the database (supplier DB 188; FIG. 6).

ステップ152,154(S152,S154)において、課金サーバ12は、PC204に対して、登録完了通知を送信する処理を行う。
ステップ156(S156)において、PC204は、課金サーバ12からの登録完了通知を行う。
ステップ158(S158)において、PC204は、必要に応じて、接続された電力供給装置202の供給アダプタ22のリセットを行い、供給アダプタ22に対して、供給者IDを設定する。
In steps 152 and 154 (S152 and S154), the accounting server 12 performs a process of transmitting a registration completion notification to the PC 204.
In step 156 (S156), the PC 204 issues a registration completion notification from the accounting server 12.
In step 158 (S158), the PC 204 resets the supply adapter 22 of the connected power supply apparatus 202 as necessary, and sets a supplier ID for the supply adapter 22.

[電力利用開始]
図11は、図1に示した電力供給システム1の全体的な動作を示す第3の通信シーケンス図であって、電力利用装置302が、電力利用を開始するための処理(S18)を示す。
図11に示すように、ステップ180(S180)において、電力利用者は、電力供給装置202の供給アダプタ22の専用コンセント206(図1,図2(A))と、電力利用装置302の利用アダプタ32の専用プラグ306(図2(B))とを接続し、利用アダプタ32の操作ボタン322(図5)に対して、電力の利用を開始するための操作を行う。
ステップ182(S182)において、電力利用装置302は、専用コンセント206および電力用電極308を介して、電力供給装置202から、供給者IDを取得する。
ステップ184(S184)において、電力利用装置302は、供給者IDを受信する。
[Start using electricity]
FIG. 11 is a third communication sequence diagram showing the overall operation of the power supply system 1 shown in FIG. 1, and shows a process (S18) for the power usage apparatus 302 to start using the power.
As shown in FIG. 11, in step 180 (S <b> 180), the power user uses the dedicated outlet 206 (FIG. 1, FIG. 2A) of the supply adapter 22 of the power supply apparatus 202 and the utilization adapter of the power utilization apparatus 302. 32 dedicated plugs 306 (FIG. 2B) are connected, and an operation for starting the use of power is performed on the operation button 322 (FIG. 5) of the usage adapter 32.
In step 182 (S 182), the power utilization apparatus 302 acquires a supplier ID from the power supply apparatus 202 via the dedicated outlet 206 and the power electrode 308.
In step 184 (S184), the power usage apparatus 302 receives the supplier ID.

ステップ186,188(S186,S188)において、電力利用装置302は、課金サーバ12に対して、利用者情報、電力供給装置202および電力利用装置302(供給者IDおよび利用者)の認証のための情報などを含む利用開始要求を送信する。
ステップ190(S190)において、課金サーバ12は、電力利用装置302からの利用開始要求を受信する。
ステップ192(S192)において、課金サーバ12は、電力利用装置302の認証を行う。
ステップ194(S194)において、課金サーバ12は、電力利用装置302を認証したときには、認証通知を、電力利用装置302に対して送信する。
In steps 186 and 188 (S186 and S188), the power usage apparatus 302 authenticates the user information, the power supply apparatus 202, and the power usage apparatus 302 (supplier ID and user) to the billing server 12. A usage start request including information etc. is transmitted.
In step 190 (S190), the accounting server 12 receives the usage start request from the power usage apparatus 302.
In step 192 (S192), the billing server 12 authenticates the power usage apparatus 302.
In step 194 (S 194), when the charging server 12 authenticates the power usage device 302, the charging server 12 transmits an authentication notification to the power usage device 302.

ステップ196(S196)において、課金サーバ12は、認証した電力利用装置302の利用開始のための処理を行う。
ステップ198(S198)において、電力利用装置302は、認証通知を受信する。
ステップ200(S200)において、電力利用装置302は、電力の利用を開始するための処理を行い、電気機器100に対する電力の供給を開始する。
ステップ202(S202)において、電力利用装置302は、課金サーバ12に対して、利用開始を通知する。
ステップ204(S204)において、電力利用装置302の利用アダプタ32は、動作確認ランプ324を点灯させ、電気機器100に電力が供給されていることを、電力利用者に示す。
In step 196 (S196), the billing server 12 performs processing for starting use of the authenticated power usage apparatus 302.
In step 198 (S198), the power usage apparatus 302 receives the authentication notification.
In step 200 (S200), the power usage apparatus 302 performs processing for starting the use of power, and starts supplying power to the electrical device 100.
In step 202 (S202), the power usage apparatus 302 notifies the charging server 12 of the start of usage.
In step 204 (S204), the use adapter 32 of the power use apparatus 302 turns on the operation check lamp 324 to indicate to the power user that power is being supplied to the electrical device 100.

[電力利用終了]
図12は、図1に示した電力供給システム1の全体的な動作を示す第4の通信シーケンス図であって、電力利用装置302が、電力利用を終了するための処理(S22)を示す。
ステップ220,222(S220,S222)において、電力利用者が、電力利用装置302の利用アダプタ32の操作ボタン322(図5)に対して、電力の利用を終了するための操作を行ったときに、電力利用装置302は、電力利用を終了するための処理を行う。
[End of power use]
FIG. 12 is a fourth communication sequence diagram showing the overall operation of the power supply system 1 shown in FIG. 1, and shows a process (S22) for the power usage apparatus 302 to end the power usage.
In steps 220 and 222 (S220 and S222), when the power user performs an operation to end the use of power on the operation button 322 (FIG. 5) of the usage adapter 32 of the power usage device 302. The power usage device 302 performs a process for terminating the power usage.

ステップ224(S224)において、電力利用装置302は、課金サーバ12に対して電力利用終了を通知する。
ステップ226(S226)において、課金サーバ12は、電力利用終了の通知を受信する。
ステップ228(S228)において、課金サーバ12は、電力利用終了を通知した電力利用装置302の認証を行う。
ステップ230(S230)において、電力利用装置302が認証されたときには、課金サーバ12は、電力利用終了のための処理(電力利用時間測定の停止など)を行う。
In step 224 (S224), the power usage apparatus 302 notifies the charging server 12 of the end of power usage.
In step 226 (S226), billing server 12 receives the notification of the end of power use.
In step 228 (S228), the billing server 12 authenticates the power usage apparatus 302 that has notified the end of power usage.
In step 230 (S230), when the power usage apparatus 302 is authenticated, the billing server 12 performs a process for ending the power usage (stopping power usage time measurement, etc.).

ステップ232(S232)において、課金サーバ12は、電力利用装置302に対して利用終了を通知する。
ステップ234(S234)において、電力利用装置302は、利用終了通知を受信する。
ステップ236(S236)において、電力利用装置302の利用アダプタ32は、動作確認ランプ324を消灯する。
ステップ238(S238)において、電力利用装置302は、電気機器100に対する電力の供給を停止する。
なお、図12に示した利用停止のための処理は、電気機器100に対する電力の供給が停止してから、一定時間が経過したときにも行われ、このときには、電力供給装置202と電力利用装置302との間のデータ伝送は、適宜、省略される。
In step 232 (S232), the accounting server 12 notifies the power usage apparatus 302 of the end of usage.
In step 234 (S234), the power usage apparatus 302 receives a usage end notification.
In step 236 (S236), the utilization adapter 32 of the power utilization apparatus 302 turns off the operation confirmation lamp 324.
In step 238 (S238), the power usage apparatus 302 stops supplying power to the electrical device 100.
The process for stopping use shown in FIG. 12 is also performed when a certain time has elapsed after the supply of power to the electric device 100 is stopped. At this time, the power supply apparatus 202 and the power use apparatus Data transmission to and from 302 is omitted as appropriate.

[第2の電力供給システム2]
以上説明した第1の電力供給システム1においては、電力利用装置側が主な処理を行い、電気機器100に対する電力の供給が行われる場合が例示されたが、以下、電力供給装置側が主な処理を行って、電気機器100に対する電力の供給を行う第2の電力供給システム2を説明する。
[Second power supply system 2]
In the first power supply system 1 described above, the case where the power usage apparatus side performs the main processing and the power supply to the electric device 100 is illustrated, but the power supply apparatus side performs the main processing hereinafter. The second power supply system 2 that performs the power supply to the electric device 100 will be described.

図13は、本発明にかかる電力供給方法が適用される第2の電力供給システム2の構成を例示する図である。
図13に示すように、第2の電力供給システム2は、図1に示した第1の電力供給システム1の第1の電力利用装置302を、第2の電力利用装置314に置換し、第1の電力供給装置202を、第2の電力供給装置214に置換した構成をとる。
第2の電力供給装置214は、第1の電力供給装置202の第1の供給アダプタ22を、第2の供給アダプタ24に置換した構成をとり、第2の電力利用装置314は、第1の電力利用装置302の利用アダプタ32を、第2の利用アダプタ36に置換した構成をとる。
これらの構成部分により、第2の電力供給システム2は、第1の電力供給システム1と同様に、電気機器100に対する電力の供給、電力利用者に対する電力利用時間に応じた課金、および、電力供給者に対する電力利用時間に応じた電力料金の払い戻しなどを行う。
FIG. 13 is a diagram illustrating the configuration of the second power supply system 2 to which the power supply method according to the present invention is applied.
As shown in FIG. 13, the second power supply system 2 replaces the first power usage device 302 of the first power supply system 1 shown in FIG. The first power supply apparatus 202 is replaced with the second power supply apparatus 214.
The second power supply device 214 has a configuration in which the first supply adapter 22 of the first power supply device 202 is replaced with the second supply adapter 24, and the second power utilization device 314 has the first power supply device 314. The configuration is such that the usage adapter 32 of the power usage device 302 is replaced with the second usage adapter 36.
With these components, the second power supply system 2 supplies power to the electrical device 100, charges according to the power usage time for the power user, and power supply in the same manner as the first power supply system 1. Refund of electricity charges according to the power usage time for the person.

[ハードウエア]
図14は、図13に示した第2の供給アダプタ24のハードウエア構成を示す図である。
図14に示すように、供給アダプタ24は、UI部240、CPU122、メモリ124、無線通信装置246、スイッチ制御部250、タイマ部254、データIF部248およびPC−IF部256が、バスを介して接続されて構成される。
さらに、UI部240には、操作ボタン242および動作確認ランプ244が接続され、スイッチ制御部250には、スイッチ252が接続され、データIF部248には、専用コンセント206(図13,図2(A))のデータ用受け口210が接続される。
[Hardware]
FIG. 14 is a diagram showing a hardware configuration of the second supply adapter 24 shown in FIG.
As shown in FIG. 14, the supply adapter 24 includes a UI unit 240, a CPU 122, a memory 124, a wireless communication device 246, a switch control unit 250, a timer unit 254, a data IF unit 248, and a PC-IF unit 256 via a bus. Connected and configured.
Further, an operation button 242 and an operation confirmation lamp 244 are connected to the UI unit 240, a switch 252 is connected to the switch control unit 250, and a dedicated outlet 206 (FIGS. 13 and 2 (2) is connected to the data IF unit 248. The data receiving port 210 of A)) is connected.

供給アダプタ24は、電力システム142から供給される電力により動作し、供給アダプタ24のメモリ124には、供給プログラム26が、ROMなどに記憶されてロードされ、ロードされた供給プログラム26は、CPU122により実行される。
実行された供給プログラム26の制御に従って、供給アダプタ24の各構成部分は、第2の利用アダプタ36に対して電力を供給し、利用アダプタ36に接続された電気機器100による電力利用を可能とする。
The supply adapter 24 is operated by the power supplied from the power system 142, and the supply program 26 is stored and loaded in the ROM 124 or the like in the memory 124 of the supply adapter 24. The loaded supply program 26 is loaded by the CPU 122. Executed.
In accordance with the control of the executed supply program 26, each component of the supply adapter 24 supplies power to the second usage adapter 36 and enables the electric equipment 100 connected to the usage adapter 36 to use the power. .

UI部240は、供給アダプタ24の所有者(電力供給者)による操作ボタン242に対する電力供給の開始および終了のための操作を受け入れて、この操作を示すデータを、CPU122などに対して出力する。
また、CPU122などから設定されるデータに従って、UI部240は、動作確認ランプ244の点灯および消灯を行い、供給アダプタ24の動作状態を利用者に示す。
無線通信装置246は、ネットワーク104、基地局106および無線通信回線108(図13)を介した課金サーバ12との間の通信のために必要な機能を実現する。
The UI unit 240 accepts operations for starting and ending power supply to the operation buttons 242 by the owner (power supplier) of the supply adapter 24 and outputs data indicating the operations to the CPU 122 and the like.
Further, the UI unit 240 turns on and off the operation check lamp 244 according to data set by the CPU 122 and the like, and indicates the operating state of the supply adapter 24 to the user.
The wireless communication device 246 realizes functions necessary for communication with the accounting server 12 via the network 104, the base station 106, and the wireless communication line 108 (FIG. 13).

スイッチ制御部250は、CPU122により設定されるデータに従って、スイッチ252を制御し、利用アダプタ36に対する電力の供給および供給の停止を行う機能を実現する。
また、スイッチ制御部250は、スイッチ252を介して、利用アダプタ36に対する電力の供給を監視し、電力の供給が行われているか否かを示すデータを、CPU122などに対して通知するための機能を実現する。
また、スイッチ制御部250は、スイッチ252を介して、利用アダプタ36の接続を監視し、利用アダプタ36が供給アダプタ24に接続されているか否かを示すデータを、CPU122などに対して通知するための機能を実現する。
The switch control unit 250 controls the switch 252 in accordance with the data set by the CPU 122 to realize a function of supplying power to the usage adapter 36 and stopping the supply.
The switch control unit 250 also functions to monitor the power supply to the usage adapter 36 via the switch 252 and notify the CPU 122 and the like of data indicating whether or not the power supply is performed. Is realized.
The switch control unit 250 also monitors the connection of the usage adapter 36 via the switch 252 and notifies the CPU 122 and the like of data indicating whether or not the usage adapter 36 is connected to the supply adapter 24. Realize the function.

スイッチ252は、スイッチ制御部250の制御に従って、利用アダプタ36に対する電力の接続および切断を行う。
なお、スイッチ252は、上述したスイッチとしての機能の他に、例えば、通過する電流が1Aを超えたときに、電流を遮断するブレーカとしての機能を有し、時間に応じた課金により、電力供給者に損失が生じることを防いでいる。
タイマ部254は、供給アダプタ24において用いられるクロック信号を計数し、データ・電力ケーブル212(図2(A),(B))の接続が外れたなどの原因で、利用アダプタ36に対する電力供給がなくなってから、一定時間が経過したなどのタイミングで、図17などを参照して後述する利用終了処理を起動するための機能を実現する。
The switch 252 connects and disconnects power to the usage adapter 36 according to the control of the switch control unit 250.
The switch 252 has a function as a breaker that cuts off the current when the passing current exceeds 1 A, for example, in addition to the function as the switch described above. It is preventing the loss to the person.
The timer unit 254 counts the clock signal used in the supply adapter 24, and the power supply to the usage adapter 36 is caused by the disconnection of the data / power cable 212 (FIGS. 2A and 2B). A function for starting a use end process, which will be described later with reference to FIG.

データIF部248は、CPU122により設定されたデータを、専用コンセント206を介して利用アダプタ36に対して出力するための機能、および、利用アダプタ36から入力されるデータを受けて、CPU122などに対して出力するための機能を実現する。
PC−IF部256は、PC204から入力されるデータを受けて、CPU122などに対して出力するための機能、および、CPU122から設定されたデータを、PC204に対して出力するための機能を実現する。
The data IF unit 248 receives a function for outputting the data set by the CPU 122 to the usage adapter 36 via the dedicated outlet 206 and data input from the usage adapter 36, and sends the data to the CPU 122 and the like. Realizes the function to output.
The PC-IF unit 256 realizes a function for receiving data input from the PC 204 and outputting it to the CPU 122 and the like, and a function for outputting data set from the CPU 122 to the PC 204. .

図15は、図13に示した第2の利用アダプタ36のハードウエア構成を示す図である。
図15に示すように、利用アダプタ36は、バスで接続されたCPU122、メモリ124、UI部320(図5)、操作ボタン322、データIF部334およびPC−IF部336、および、電気機器100への電力ケーブルに接続され、供給アダプタ24からの電力が供給されている間、点灯する動作確認ランプ324から構成される。
つまり、第2の利用アダプタ36は、第1の利用アダプタ32から、不要な構成部分を取り去り、動作確認ランプ324を、電源ケーブルに接続した構成をとる。
FIG. 15 is a diagram illustrating a hardware configuration of the second usage adapter 36 illustrated in FIG. 13.
As illustrated in FIG. 15, the usage adapter 36 includes a CPU 122, a memory 124, a UI unit 320 (FIG. 5), an operation button 322, a data IF unit 334, a PC-IF unit 336, and the electric device 100 connected via a bus. The operation check lamp 324 is connected to the power cable and is turned on while the power from the supply adapter 24 is supplied.
That is, the second usage adapter 36 has a configuration in which unnecessary components are removed from the first usage adapter 32 and the operation check lamp 324 is connected to the power cable.

利用アダプタ36は、供給アダプタ24から供給される電力で動作し、利用アダプタ36のメモリ124には、利用プログラム38がロードされ、ロードされた利用プログラム38は、CPU122により実行される。
実行された利用プログラム38に従って、利用アダプタ36の各構成部分は、第2の利用アダプタ36から供給された電力を、電気機器100に対して供給し、電気機器100による電力利用を可能とする。
The usage adapter 36 operates with the power supplied from the supply adapter 24, and the usage program 38 is loaded into the memory 124 of the usage adapter 36, and the loaded usage program 38 is executed by the CPU 122.
In accordance with the executed usage program 38, each component of the usage adapter 36 supplies the electric device 100 with the electric power supplied from the second usage adapter 36, enabling the electric device 100 to use the electric power.

[第2の電力供給システム2の動作]
以下、図13に示した電力供給システム2の動作を説明する。
第1の電力供給システム2においても、第1の電力供給システム1について、図7〜10を参照して説明した電力利用者および電力供給者の登録が行われる。
[Operation of Second Power Supply System 2]
Hereinafter, the operation of the power supply system 2 shown in FIG. 13 will be described.
Also in the 1st electric power supply system 2, the electric power user and electric power supplier which were demonstrated with reference to FIGS. 7-10 about the 1st electric power supply system 1 are registered.

[電力利用開始]
図16は、図13に示した電力供給システム2の全体的な動作を示す第1の通信シーケンス図であって、電力供給装置214が、電力利用を開始するための処理(S26)を示す。
図16に示すように、ステップ260(S260)において、電力利用者は、電力供給装置214の供給アダプタ24の専用コンセント206(図13,図2(A))と、電力利用装置314の利用アダプタ36の専用プラグ306(図2(B))とを接続し、電力供給装置214の操作ボタン242(図14)に対して、電力の利用を開始するための操作を行う。
[Start using electricity]
FIG. 16 is a first communication sequence diagram showing the overall operation of the power supply system 2 shown in FIG. 13, and shows a process (S26) for the power supply device 214 to start using power.
As shown in FIG. 16, in step 260 (S <b> 260), the power user uses the dedicated outlet 206 (FIG. 13, FIG. 2A) of the supply adapter 24 of the power supply device 214 and the use adapter of the power use device 314. 36 dedicated plugs 306 (FIG. 2B) are connected, and an operation for starting the use of power is performed on the operation button 242 (FIG. 14) of the power supply device 214.

ステップ262(S262)において、電力供給装置214は、電力利用装置314の利用アダプタ36の接続を検出し、利用アダプタ36の起動のために用いるタイマを起動する。
ステップ264(S264)において、電力利用装置314は、S262において起動されたタイマが示す時間、電力利用装置314の利用アダプタ36に電力を供給し、利用アダプタ36を起動する。
In step 262 (S262), the power supply device 214 detects the connection of the usage adapter 36 of the power usage device 314, and starts a timer used for starting the usage adapter 36.
In step 264 (S264), the power usage apparatus 314 supplies power to the usage adapter 36 of the power usage apparatus 314 for the time indicated by the timer activated in S262, and activates the usage adapter 36.

ステップ266〜272(S266〜S272)において、電力供給装置214は、利用者ID取得処理を行い、電力利用装置314の利用アダプタ36に対して、利用開始要求を送信し、この要求に応じて返された利用者IDを取得する。
ステップ274,276(S274,S276)において、電力供給装置214は、課金サーバ12に対して、利用者ID、供給者ID、および、電力供給装置214および電力利用装置314(供給者および利用者)の認証のための情報などを含む利用開始要求を送信する。
In steps 266 to 272 (S266 to S272), the power supply device 214 performs a user ID acquisition process, transmits a use start request to the use adapter 36 of the power use device 314, and returns in response to this request. The obtained user ID is acquired.
In steps 274 and 276 (S274 and S276), the power supply device 214 provides the user ID, the supplier ID, and the power supply device 214 and the power use device 314 (supplier and user) to the billing server 12. A usage start request including information for authentication is transmitted.

ステップ278(S278)において、課金サーバ12は、電力供給装置214からの利用開始要求を受信する。
ステップ280(S280)において、課金サーバ12は、電力供給装置214の認証を行う。
ステップ282(S282)において、課金サーバ12は、電力供給装置214を認証したときには、認証通知を、電力供給装置214に対して送信する。
ステップ284(S284)において、課金サーバ12は、認証した電力利用装置302の利用開始のための処理を行う。
In step 278 (S278), the accounting server 12 receives the use start request from the power supply apparatus 214.
In step 280 (S280), the accounting server 12 authenticates the power supply device 214.
In step 282 (S282), when the charging server 12 authenticates the power supply device 214, the billing server 12 transmits an authentication notification to the power supply device 214.
In step 284 (S284), the billing server 12 performs a process for starting the use of the authenticated power usage apparatus 302.

ステップ286,288(S286,S288)において、電力供給装置214は、課金サーバ12からの認証通知を受信し、供給アダプタ24の動作確認ランプ244の点灯など、電力利用開始のための処理を行う。
ステップ290(S290)において、電力供給装置214は、課金サーバ12に対して、利用開始を通知する。
ステップ292(S292)において、課金サーバ12は、利用開始通知を受信する。
ステップ294(S294)において、課金サーバ12は、電力利用装置314に接続された電気機器100による電力利用時間の測定などの処理を行う。
In steps 286 and 288 (S286 and S288), the power supply device 214 receives the authentication notification from the billing server 12, and performs processing for starting the use of power, such as lighting the operation check lamp 244 of the supply adapter 24.
In step 290 (S290), the power supply device 214 notifies the charging server 12 of the start of use.
In step 292 (S292), the accounting server 12 receives the usage start notification.
In step 294 (S294), the billing server 12 performs processing such as measurement of power usage time by the electric device 100 connected to the power usage device 314.

[電力利用終了]
図17は、図13に示した電力供給システム2の全体的な動作を示す第2の通信シーケンス図であって、電力供給装置214が、電力利用を終了するための処理(S34)を示す。
ステップ340,342(S340,S342)において、電力利用者が、電力利用装置314の利用アダプタ36の操作ボタン322(図15)に対して、電力の利用を終了するための操作を行ったときに、電力利用装置302は、電力利用を終了するための処理を行う。
[End of power use]
FIG. 17 is a second communication sequence diagram showing the overall operation of the power supply system 2 shown in FIG. 13, and shows a process (S34) for the power supply apparatus 214 to end the use of power.
In steps 340 and 342 (S340 and S342), when the power user performs an operation to end the use of power on the operation button 322 (FIG. 15) of the use adapter 36 of the power use device 314. The power usage device 302 performs a process for terminating the power usage.

ステップ344(S344)において、電力利用装置302は、電力供給装置214に対して電力利用終了を要求する。
ステップ346,348(S346,348)において、電力供給装置214は、課金サーバ12に対して、電力利用終了を要求する。
ステップ350(S350)において、課金サーバ12は、電力利用終了の要求を受信する。
In step 344 (S344), the power usage apparatus 302 requests the power supply apparatus 214 to end power usage.
In steps 346 and 348 (S346 and 348), the power supply device 214 requests the billing server 12 to end the use of power.
In step 350 (S350), billing server 12 receives a request for termination of power use.

ステップ352(S352)において、課金サーバ12は、電力利用終了を通知した電力供給装置214の認証を行う。
ステップ354(S354)において、電力供給装置214が認証されたときには、課金サーバ12は、電力利用終了のための処理(電力利用時間測定(課金)の停止など)を行う。
ステップ356(S356)において、課金サーバ12は、電力利用終了を、電力供給装置214に対して通知する。
In step 352 (S352), the billing server 12 authenticates the power supply device 214 that has notified the end of power use.
In step 354 (S354), when the power supply device 214 is authenticated, the billing server 12 performs processing for terminating power use (such as stopping power use time measurement (billing)).
In step 356 (S356), the billing server 12 notifies the power supply device 214 of the end of power use.

ステップ358(S358)において、電力供給装置214は、電力利用終了通知を受信する。
ステップ360(S360)において、電力供給装置214は、供給アダプタ24の動作確認ランプ244の消灯など、利用終了のための処理を行う。
ステップ362(S362)において、電力供給装置214から電力利用装置314への電力供給が停止される。
なお、図17に示した利用停止のための処理は、電気機器100に対する電力の供給が停止してから、一定時間が経過したときにも行われ、このときには、電力供給装置214と電力利用装置314との間のデータ伝送は、適宜、省略される。
In step 358 (S358), the power supply apparatus 214 receives the power use end notification.
In step 360 (S360), the power supply device 214 performs processing for terminating the use, such as turning off the operation check lamp 244 of the supply adapter 24.
In step 362 (S362), power supply from the power supply device 214 to the power utilization device 314 is stopped.
The process for stopping use shown in FIG. 17 is also performed when a certain time has elapsed after the supply of power to the electric device 100 is stopped. At this time, the power supply apparatus 214 and the power use apparatus Data transmission to and from 314 is omitted as appropriate.

本発明は、電気機器に電力を供給し、電力の供給について課金を行うために利用可能である。   The present invention can be used to supply electric power to an electric device and charge for the supply of electric power.

本発明にかかる電力供給方法が適用される第1の電力供給システムの構成を例示する図である。It is a figure which illustrates the composition of the 1st power supply system to which the power supply method concerning the present invention is applied. (A),(B)は、図1に示した専用コンセントおよび専用プラグの構成を例示する図である。(A), (B) is a figure which illustrates the structure of the exclusive outlet and exclusive plug shown in FIG. 図1に示した課金サーバ、電気機器およびPCのハードウエア構成を例示する図である。It is a figure which illustrates the hardware constitutions of the accounting server shown in FIG. 1, an electric equipment, and PC. 図1に示した第1の供給アダプタのハードウエア構成を示す図である。It is a figure which shows the hardware constitutions of the 1st supply adapter shown in FIG. 図1に示した第1の利用アダプタのハードウエア構成を示す図である。It is a figure which shows the hardware constitutions of the 1st utilization adapter shown in FIG. 図1に示した課金サーバにおいて実行される課金プログラムの構成を示す図である。It is a figure which shows the structure of the charging program run in the charging server shown in FIG. 図1に示した電力供給システムの全体的な動作を示す第1の通信シーケンス図であって、課金サーバに対する電力利用者登録のための処理(S10)を示す。FIG. 3 is a first communication sequence diagram showing the overall operation of the power supply system shown in FIG. 1, and shows a process (S 10) for power user registration with a billing server. 図7に示したS100の処理により課金サーバから電気機器(図1)にダウンロードされる登録用画像を例示する図である。It is a figure which illustrates the image for registration downloaded to an electric equipment (Drawing 1) from a billing server by processing of S100 shown in Drawing 7. 図1に示した電力供給システムの全体的な動作を示す第2の通信シーケンス図であって、課金サーバに対する電力供給者登録のための処理(S14)を示す。FIG. 5 is a second communication sequence diagram showing the overall operation of the power supply system shown in FIG. 1, and shows a process (S14) for registering a power supplier with a billing server. 図9に示したS142の処理により課金サーバからPC(図1)にダウンロードされる登録用画像を例示する図である。It is a figure which illustrates the image for registration downloaded to PC (FIG. 1) from the accounting server by the process of S142 shown in FIG. 図1に示した電力供給システムの全体的な動作を示す第3の通信シーケンス図であって、電力利用装置が、電力利用を開始するための処理(S18)を示す。FIG. 6 is a third communication sequence diagram showing the overall operation of the power supply system shown in FIG. 1, and shows a process (S 18) for the power usage apparatus to start using the power. 図1に示した電力供給システムの全体的な動作を示す第4の通信シーケンス図であって、電力利用装置が、電力利用を終了するための処理(S22)を示す。FIG. 10 is a fourth communication sequence diagram illustrating an overall operation of the power supply system illustrated in FIG. 1, and shows a process (S22) for the power usage apparatus to end the power usage. 本発明にかかる電力供給方法が適用される第2の電力供給システムの構成を例示する図である。It is a figure which illustrates the composition of the 2nd power supply system to which the power supply method concerning the present invention is applied. 図13に示した第2の供給アダプタのハードウエア構成を示す図である。It is a figure which shows the hardware constitutions of the 2nd supply adapter shown in FIG. 図13に示した第2の利用アダプタのハードウエア構成を示す図である。It is a figure which shows the hardware constitutions of the 2nd utilization adapter shown in FIG. 図13に示した電力供給システムの全体的な動作を示す第1の通信シーケンス図であって、電力供給装置が、電力利用を開始するための処理(S26)を示す。FIG. 14 is a first communication sequence diagram showing an overall operation of the power supply system shown in FIG. 13, and shows a process (S 26) for the power supply apparatus to start using power. 図13に示した電力供給システムの全体的な動作を示す第2の通信シーケンス図であって、電力供給装置が、電力利用を終了するための処理(S34)を示す。FIG. 14 is a second communication sequence diagram showing the overall operation of the power supply system shown in FIG. 13, showing a process (S 34) for the power supply apparatus to end the use of power.

符号の説明Explanation of symbols

1,2・・・電力供給システム,
100・・・電気機器,
102・・・通信システム,
104・・・ネットワーク,
106・・・基地局,
108・・・無線通信回線,
12・・・課金サーバ,
120・・・本体,
122・・・CPU,
124・・・メモリ,
126・・・タイマ,
128・・・入出力装置,
130・・・通信・IF装置,
132・・・記録装置,
134・・・記録媒体,
16・・・課金プログラム,
160・・・通信制御部,
162・・・UI部,
164・・・認証部,
170・・・利用処理部,
172・・・利用者管理部,
174・・・利用時間管理部,
176・・・課金処理部,
178・・・利用者DB,
180・・・供給処理部,
182・・・供給者管理部,
184・・・供給者管理部,
186・・・返還処理部,
188・・・供給者DB,
140・・・電力事業者システム,
142・・・電力システム,
144・・・汎用プラグ,
146・・・汎用コンセント,
202,214・・・電力供給装置,
204・・・PC,
206・・・専用コンセント,
208・・・電力用受け口,
210・・・データ用受け口,
212・・・データ・電力ケーブル,
22,24・・・供給アダプタ,
220・・・データIF部,
222・・・ID記憶部,
224・・・PC−IF部,
240・・・UI部,
242・・・操作ボタン,
244・・・動作確認ランプ,
246・・・無線通信装置,
248・・・データIF部,
250・・・スイッチ制御部,
252・・・スイッチ,
254・・・タイマ部,
256・・・PC−IF部,
26・・・供給プログラム,
302,314・・・電力利用装置,
306・・・専用プラグ,
308・・・電力用電極,
310・・・データ用電極,
32,36・・・利用アダプタ,
320・・・UI部,
322・・・操作ボタン,
324・・・動作確認ランプ,
326・・・無線通信装置,
328・・・スイッチ制御部,
330・・・スイッチ,
332・・・タイマ部,
334・・・データIF部,
336・・・PC−IF部,
34,38・・・利用プログラム,
1, 2 ... Power supply system,
100 ... electric equipment,
102 ... Communication system,
104 ... network,
106 ... base station,
108: wireless communication line,
12 ... billing server,
120 ... main body,
122... CPU
124 ... memory,
126... Timer
128 ... I / O device,
130: Communication / IF device,
132... Recording device,
134... Recording medium,
16 ... Billing program,
160 ... communication control unit,
162 ... UI part,
164: Authentication unit,
170 ... use processing unit,
172 ... User management department,
174: Usage time management unit,
176 ... billing processing unit,
178 ... User DB,
180... Supply processing unit,
182: Supplier management department,
184 ... Supplier management department,
186 ... Return processing department,
188 ... supplier DB,
140: Electric power company system,
142 ... electric power system,
144: General purpose plug,
146 ... General purpose outlet,
202, 214 ... power supply device,
204 ... PC,
206: Dedicated outlet,
208: Power receptacle,
210: Data receiving port,
212 ... Data / power cable,
22, 24 ... Supply adapter,
220: Data IF section,
222... ID storage unit,
224... PC-IF unit,
240 ... UI part,
242 ... operation buttons,
244 ... Operation check lamp,
246: Wireless communication device,
248 ... Data IF section,
250... Switch control unit,
252 ... switch,
254 ... Timer part,
256 ... PC-IF section,
26 ... supply program,
302, 314 ... power utilization device,
306 ... Dedicated plug,
308 ... Power electrode,
310 ... Data electrode,
32, 36 ... Adapter used,
320 ... UI unit,
322 ... operation buttons,
324 ... operation check lamp,
326... Wireless communication device,
328... Switch control unit,
330 ... switch,
332: Timer part,
334: Data IF section,
336 ... PC-IF section,
34, 38 ... use program,

Claims (8)

固有の供給識別子が付され、所定の電力システムに接続されて電力の供給を受ける電力供給装置と、
利用者を識別する固有の利用識別子が付され、接続された前記電力供給装置から電力の供給を受け、供給された電力を外部に対して供給する電力利用装置と、
前記電力利用装置を利用して前記電力供給装置から電力の供給を受けた電力利用時間に従って、電力利用料金の課金を行う課金装置と
を有する電力供給システムであって、
前記電力供給装置は、
供給接続手段を有し、
前記電力利用装置は、
前記供給接続手段のみに適合し、前記供給接続手段を介して、前記電力供給装置から、電力と、前記供給識別子を含むデータとが伝えられるよう前記供給接続手段と接続される利用接続手段と、
外部に対する電力供給の開始および終了の操作を受ける操作手段と、
前記付された利用識別子と、前記利用接続手段に接続された前記供給接続手段を介して伝えられたデータに含まれる供給識別子と、前記電力供給の開始および終了とを、前記課金装置に通知する通知手段と
を有し、
前記課金装置は、
前記通知された供給識別子が付された電力供給装置から電力の供給を受けた利用時間、および、前記通知された供給識別子が付された電力供給装置の課金単価に従って、前記通知された利用識別子に対応する利用者に対して、電力利用料金の課金を行う
電力供給システム。
A power supply device with a unique supply identifier and connected to a predetermined power system to receive power supply;
A power usage device that is provided with a unique usage identifier for identifying a user, receives power from the connected power supply device, and supplies the supplied power to the outside;
A power supply system comprising: a charging device that charges a power usage fee according to a power usage time when power is supplied from the power supply device using the power usage device;
The power supply device
Having supply connection means,
The power usage device is:
Use connection means adapted to only the supply connection means, and connected to the supply connection means so that power and data including the supply identifier are transmitted from the power supply device via the supply connection means,
Operating means for receiving an operation of starting and ending power supply to the outside;
The charging device is notified of the attached usage identifier, the supply identifier included in the data transmitted via the supply connection unit connected to the usage connection unit, and the start and end of the power supply. have a notification means,
The charging device is
The notified usage identifier is set according to the usage time when power is supplied from the power supply apparatus to which the notified supply identifier is attached, and the charging unit price of the power supply apparatus to which the notified supply identifier is attached. A power supply system that charges a corresponding user for a power usage fee .
前記電力利用装置と、前記課金装置とは、無線通信回線を介して接続される
請求項1に記載の電力供給システム。
The power supply system according to claim 1, wherein the power usage apparatus and the billing apparatus are connected via a wireless communication line.
固有の供給識別子が付され、所定の電力システムに接続されて電力の供給を受ける電力供給装置と、
利用者を識別する固有の利用識別子が付され、接続された前記電力供給装置から電力の供給を受け、供給された電力を外部に対して供給する電力利用装置と、
課金装置と
を有する電力供給システムであって、
前記課金装置は、
前記電力供給装置から通知される供給識別子と、利用識別子と、電力供給の開始および終了との通知に応じて、前記電力利用装置を利用して前記通知された供給識別子が付された電力供給装置から電力の供給を受けた電力利用時間、および、前記通知された供給識別子が付された電力供給装置の課金単価に従って、前記通知された利用識別子に対応する利用者に対して、電力利用料金の課金を行う課金手段と、
前記電力供給装置から通知される電力供給の開始および終了の通知に応じて、前記電力供給装置から前記電力利用装置への電力供給の開始および終了を制御する供給制御手段と
を有し、
前記電力利用装置は、
利用接続手段と、
外部に対する電力供給の開始および終了の操作を受ける操作手段と、
前記利用接続手段を介して、前記付された利用識別子と、前記電力供給の開始および終了とを、前記電力供給装置に対して通知する通知手段と
を有し、
前記電力供給装置は、
前記利用接続手段のみに適合し、前記利用接続手段を介して、前記電力利用装置から、前記利用識別子を含むデータが伝えられるよう前記利用接続手段と接続される供給接続手段と、
前記供給接続手段に接続された前記利用接続手段を介して伝えられたデータに含まれる利用識別子と、前記付された供給識別子と、前記電力供給の開始および終了とを、前記課金装置に通知する通知手段と、
前記課金装置からの制御に従って、前記電力利用装置への電力供給を開始および終了する供給スイッチ手段と
を有する
電力供給システム。
A power supply device with a unique supply identifier and connected to a predetermined power system to receive power supply;
A power usage device that is provided with a unique usage identifier for identifying a user, receives power from the connected power supply device, and supplies the supplied power to the outside;
A power supply system having a billing device,
The charging device is
The power supply apparatus to which the supply identifier notified using the power utilization apparatus is attached in response to the notification of the supply identifier, the usage identifier, and the start and end of power supply notified from the power supply apparatus Power usage fee for the user corresponding to the notified usage identifier in accordance with the power usage time when the power supply is received from and the unit price of the power supply device to which the notified supply identifier is attached . A billing means for charging;
Supply control means for controlling start and end of power supply from the power supply device to the power utilization device in response to notification of start and end of power supply notified from the power supply device,
The power usage device is:
Use connection means,
Operating means for receiving an operation of starting and ending power supply to the outside;
A notification means for notifying the power supply device of the attached usage identifier and the start and end of the power supply via the use connection means;
The power supply device
Supply connection means adapted to only the usage connection means, and connected to the usage connection means so that data including the usage identifier is transmitted from the power usage device via the usage connection means,
Notifying the billing device of a usage identifier included in data transmitted through the usage connection means connected to the supply connection means, the attached supply identifier, and the start and end of the power supply Notification means;
A power supply system comprising: supply switch means for starting and ending power supply to the power usage device in accordance with control from the billing device.
前記電力供給装置と、前記課金装置とは、無線通信回線を介して接続される
請求項3に記載の電力供給システム。
The power supply system according to claim 3, wherein the power supply device and the billing device are connected via a wireless communication line.
利用者を識別する固有の利用識別子が付され、所定の電力システムから電力の供給を受ける電力供給装置に接続されて電力の供給を受ける電力利用装置であって、供給された電力を外部に対して供給する電力利用装置であって、前記所定の電力システムが有する課金装置により、前記電力利用装置を利用して前記電力供給装置から電力の供給を受けた電力利用時間に従って、電力利用料金の課金が、電力供給の開始および終了の通知に応じて、前記利用識別子および前記電力供給装置に固有に付された供給識別子を用いて行なわれ、
前記電力供給装置は、
供給接続手段を有し、
前記電力利用装置は、
前記供給接続手段のみに適合し、前記供給接続手段を介して、前記電力供給装置から、電力と、前記供給識別子を含むデータとが伝えられるよう前記供給接続手段と接続される利用接続手段と、
外部に対する電力供給の開始および終了の操作を受ける操作手段と、
前記課金のために、前記付された利用識別子と、前記利用接続手段に接続された前記供給接続手段を介して伝えられたデータに含まれる供給識別子と、前記電力供給の開始および終了とを、前記課金装置に対して通知する通知手段と
を有し、
前記課金装置は、
前記通知された供給識別子が付された電力供給装置から電力の供給を受けた利用時間、および、前記通知された供給識別子が付された電力供給装置の課金単価に従って、前記通知された利用識別子に対応する利用者に対して、電力利用料金の課金を行う
電力利用装置。
A power usage apparatus that receives a power supply by being connected to a power supply apparatus that receives a power supply from a predetermined power system with a unique usage identifier that identifies the user, and that supplies the supplied power to the outside A power usage fee that is supplied in accordance with a power usage time when power is supplied from the power supply device using the power usage device by a charging device included in the predetermined power system. Is performed using the use identifier and the supply identifier uniquely given to the power supply device in response to the notification of the start and end of power supply,
The power supply device
Having supply connection means,
The power usage device is:
Use connection means adapted to only the supply connection means, and connected to the supply connection means so that power and data including the supply identifier are transmitted from the power supply device via the supply connection means,
Operating means for receiving an operation of starting and ending power supply to the outside;
For the accounting, the attached usage identifier, the supply identifier included in the data transmitted via the supply connection means connected to the usage connection means, and the start and end of the power supply, have a notification means for notifying to the charging device,
The charging device is
The notified usage identifier is set according to the usage time when power is supplied from the power supply apparatus to which the notified supply identifier is attached, and the charging unit price of the power supply apparatus to which the notified supply identifier is attached. A power usage device that charges a corresponding user for a power usage fee .
前記課金装置により、前記電力利用装置を利用して前記電力供給装置から電力の供給を受けた電力利用時間に従った電力利用料金の課金に応じて、前記課金装置に対して通知された供給識別子を用いて電力料金が払い戻される
請求項5に記載の電力利用装置。
The supply identifier notified to the charging device according to the charging of the power usage fee according to the power usage time when the power usage device receives power supply from the power supply device using the power usage device The power usage apparatus according to claim 5, wherein the power charge is reimbursed using.
固有の供給識別子が付され、所定の電力システムに接続されて電力の供給を受け、受けた電力を電力利用装置に供給する電力供給装置であって、
前記所定の電力システムが有する課金装置により、前記電力供給装置から通知される利用者を識別する利用識別子と、前記付された供給識別子と、電力供給の開始および終了との通知に応じて、前記電力利用装置を利用して前記通知された供給識別子が付された電力供給装置から電力の供給を受けた電力利用時間、および、前記通知された供給識別子が付された電力供給装置の課金単価に従って、前記通知された利用識別子に対応する利用者に対して、電力利用料金の課金が行なわれ、
前記電力供給装置から通知される電力供給の開始および終了との通知に応じて、前記課金装置により、前記電力供給装置から前記電力利用装置への電力供給の開始および終了が制御され、
前記電力利用装置は、
利用接続手段を有し、
固有の利用識別子が付され、接続された前記電力供給装置から電力の供給を受け、供給された電力を外部に対して供給し、
前記利用接続手段を介して、前記付された利用識別子と、前記電力供給の開始および終了とを、前記電力供給装置に対して通知し、
前記電力供給装置は、
前記利用接続手段のみに適合し、前記利用接続手段を介して、前記電力利用装置から、前記利用識別子を含むデータが伝えられるよう前記利用接続手段と接続される供給接続手段と、
前記課金のために、前記供給接続手段に接続された前記利用接続手段を介して伝えられたデータに含まれる利用識別子と、前記付された供給識別子と、前記電力供給の開始および終了とを、前記課金装置に通知する通知手段と、
前記課金装置からの制御に従って、前記電力利用装置への電力供給を開始および終了する供給スイッチ手段と
を有する電力供給装置。
A power supply device with a unique supply identifier, connected to a predetermined power system and receiving power supply, and supplying the received power to a power utilization device,
In accordance with the notification of the usage identifier for identifying the user notified from the power supply device, the attached supply identifier, and the start and end of power supply by the charging device of the predetermined power system, According to the power usage time when power is supplied from the power supply apparatus to which the notified supply identifier is attached using the power utilization apparatus, and the charging unit price of the power supply apparatus to which the notified supply identifier is attached The user corresponding to the notified usage identifier is charged for the power usage fee,
In response to the notification of the start and end of power supply notified from the power supply device, the charging device controls the start and end of power supply from the power supply device to the power utilization device,
The power usage device is:
Use connection means,
A unique usage identifier is attached, and power is supplied from the connected power supply device, and the supplied power is supplied to the outside.
Via the use connection means, the attached use identifier and the start and end of the power supply are notified to the power supply device,
The power supply device
Supply connection means adapted to only the usage connection means, and connected to the usage connection means so that data including the usage identifier is transmitted from the power usage device via the usage connection means,
For the billing, a usage identifier included in data transmitted through the usage connection means connected to the supply connection means, the attached supply identifier, and the start and end of the power supply, Notification means for notifying the charging device;
A power supply device comprising: supply switch means for starting and ending power supply to the power usage device in accordance with control from the billing device.
前記課金装置により、前記電力利用装置を利用して前記電力供給装置から電力の供給を受けた電力利用時間に従った電力利用料金の課金に応じて、前記課金装置に対して通知された供給識別子を用いて電力料金が払い戻される
請求項7に記載の電力供給装置。
The supply identifier notified to the charging device according to the charging of the power usage fee according to the power usage time when the power usage device receives power supply from the power supply device using the power usage device The power supply apparatus according to claim 7, wherein the electric power charge is refunded using.
JP2005367863A 2005-12-21 2005-12-21 Power supply system Active JP4848182B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005367863A JP4848182B2 (en) 2005-12-21 2005-12-21 Power supply system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005367863A JP4848182B2 (en) 2005-12-21 2005-12-21 Power supply system

Publications (2)

Publication Number Publication Date
JP2007172220A JP2007172220A (en) 2007-07-05
JP4848182B2 true JP4848182B2 (en) 2011-12-28

Family

ID=38298715

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005367863A Active JP4848182B2 (en) 2005-12-21 2005-12-21 Power supply system

Country Status (1)

Country Link
JP (1) JP4848182B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014164696A (en) * 2013-02-27 2014-09-08 Softbank Mobile Corp Power supply system
US10176539B2 (en) 2013-02-27 2019-01-08 Softbank Corp. Power supply system

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010154635A (en) * 2008-12-25 2010-07-08 Chubu Electric Power Co Inc Charging management system for vehicle
JP2012098798A (en) * 2010-10-29 2012-05-24 Toko Electric Corp Charging system
JPWO2015145926A1 (en) * 2014-03-24 2017-04-13 日本電気株式会社 Power supply system, control device, power receiving device, terminal device, power control method and program
JP6346601B2 (en) * 2015-12-22 2018-06-20 ソフトバンク株式会社 Power management system, power relay device, power management program, and power management method
JP2022031014A (en) * 2020-08-07 2022-02-18 トヨタ自動車株式会社 Information processing device, information processing system, information processing method, and power supply device

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002117183A (en) * 2000-10-11 2002-04-19 Mitsubishi Electric Corp Device and method for service related to consumption of resources
JP2002279572A (en) * 2001-03-22 2002-09-27 Osaka Gas Co Ltd Utility use quantity measurement system and method
JP3922936B2 (en) * 2002-01-07 2007-05-30 四国電力株式会社 Electrical equipment status information collection system
JP4105923B2 (en) * 2002-09-26 2008-06-25 大崎電気工業株式会社 Electricity sales system equipment
JP2004135084A (en) * 2002-10-10 2004-04-30 Ricoh Co Ltd Electric and electronic device, charging device, charging method and charging program
JP3925411B2 (en) * 2003-01-10 2007-06-06 享久 笠茂 Power management system and power measuring device
JP2004234117A (en) * 2003-01-28 2004-08-19 Hitachi Information Technology Co Ltd Power supply charging system and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014164696A (en) * 2013-02-27 2014-09-08 Softbank Mobile Corp Power supply system
US10176539B2 (en) 2013-02-27 2019-01-08 Softbank Corp. Power supply system

Also Published As

Publication number Publication date
JP2007172220A (en) 2007-07-05

Similar Documents

Publication Publication Date Title
JP4848182B2 (en) Power supply system
US10354301B2 (en) Mobile power source and method of use
JP5487994B2 (en) Power management apparatus and display method
US9688155B2 (en) Authentication and pairing of a mobile device to an external power source
CN102104262A (en) Electric vehicle, taxing server, charging apparatus and drive management method
JP2016514445A (en) System and method for managing a distributed wireless power transfer network for electrical devices
JP2011155712A (en) Electronic appliance, power management apparatus, and method of identifying appliance
JP5905286B2 (en) Power network access control apparatus and power network access control method
CN108422887B (en) Vehicle-mounted alternating-current charging and discharging machine charging and discharging interface, method, charging pile and electronic equipment
CN107316224A (en) Portable power source leasing method and system
Kim et al. Toward interoperability of smart grids
CN113706312A (en) Photovoltaic electricity transaction method and device based on block chain
JP5794603B2 (en) Power management system, control device, management server, power management method, and program
CN114449024B (en) Power equipment control method, device, equipment and storage medium based on Internet of things
ES2904848T3 (en) Maintenance equipment management method and server, and computer-readable storage medium
TW202040490A (en) Systems and methods for charging management of charging devices
US9363756B2 (en) Electric-power supplying apparatus, method, and program
CN116315179A (en) Battery pack output control method, battery pack, and storage medium
JP2010039800A (en) Electricity usage control system
US20170061554A1 (en) Device for powering an electrical appliance
TWI652877B (en) Switching power supply identification system and charging method thereof
JP2008065617A (en) Power transaction system, program of power transaction system, and consumer terminal and supplier terminal for use in power transaction system
US9230248B2 (en) Physical-quantity receiving device and physical-quantity supplying device with payment receiving feature
JP2021077124A (en) Notification system, notification method, and program
CN109076109B (en) Equipment management method, equipment management device and mobile terminal

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071219

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100625

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100917

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20110401

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110726

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20110801

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111006

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111017

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141021

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4848182

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250