JP4111285B2 - Laying a temporary track for tunnel construction - Google Patents
Laying a temporary track for tunnel construction Download PDFInfo
- Publication number
- JP4111285B2 JP4111285B2 JP14259098A JP14259098A JP4111285B2 JP 4111285 B2 JP4111285 B2 JP 4111285B2 JP 14259098 A JP14259098 A JP 14259098A JP 14259098 A JP14259098 A JP 14259098A JP 4111285 B2 JP4111285 B2 JP 4111285B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- rail
- track
- primary lining
- lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、シールド機に連行される後続台車やズリ鋼車、セグメント運搬車、機関車等の坑内運搬車等を走行させるために一次覆工セグメントの底部に設置されるトンネル工事用仮設軌道の敷設方法に関する。
【0002】
【従来の技術】
たとえば、シールドトンネル等の工事においては、シールド機に連行される後続台車やズリ鋼車、セグメント運搬車、機関車等の坑内運搬車等を走行させるために、一次覆工用セグメントの構築後、直ちに枕木をトンネル幅方向に渡すとともに、この枕木上にトンネル長手方向に沿って前記後続台車および坑内運搬車用の軌条を敷設している。
【0003】
小断面トンネルの場合には、図3に示されるように、坑内運搬車7が走行するために左右一対の2本の軌条1,1と、シールド機に連行されるシールド動力および付帯設備類、ズリ出し設備等のための後続台車6の軌条2との合計3本の軌条1〜2が敷設され、前記坑内運搬車用軌条1,1の内側に歩廊用足場板8がトンネル長手方向に沿って敷設される。なお、前記後続台車6の軌条2は、モノレールであるため、一次覆工セグメント10の側面に取り付けられたブラケット20上のガイドレールによって支えられている。
【0004】
【発明が解決しようとする課題】
前述のように、狭いトンネル内に3本の軌条を設置し、坑内運搬車7と後続台車6とが並列的に走行し得るようにするためには、枕木3の設置高さをある程度の高さにせざるを得ず、その結果作業員が歩廊用足場8を歩く際には、中腰状態での歩行を強いられ、長距離の歩行には大変な苦痛を伴うなどの問題があった。
【0005】
また、トンネルが水道トンネル等の場合には、一次覆工が完了した後、一次覆工セグメント10よりも一回りほど小径となる水道管を搬入しなければならないが、前記一次覆工時の枕木高さでは水道管が搬入できないため、一次覆工完了後に、全線に亘って低い高さ位置に二次覆工用の軌道を敷設し直さなければならないなどの問題が生じていた。
【0006】
他方、前述の歩行時の姿勢負担の問題に鑑み、実公平7−8639号公報においては、図12に示されるように、トンネル内面に沿う円弧状に湾曲した当て板50上に、レール55,56を敷設するためのレール載せ部51,51を設けるとともに、このレール載せ部51,51よりも低い位置に歩行用足場板を載せる足場載せ部52を設け、さらにこの足場載せ部52に補助レール54を載せるための台53が移動自在となっているトンネル内レール仮設用枕木が提案されている。この仮設用枕木によれば、レール敷設面よりも一段低い部分を歩行面とするため、作業員は中腰のままの歩行を強いられるようなことが無くなり、歩行時の負担が大幅に軽減されるようになる。しかしながら、前記水道管を搬入する場合には、新たに二次覆工用の軌道を敷設し直さなければならないなどの問題が同様に生じてしまうとともに、特殊製作の枕木となるため、製作コストが嵩み、材料費負担が大きくなるなどの問題、さらに補助レールへ軌道を盛替えた後、軌道センターがトンネル中心よりも偏心することになるため、セグメントのローリングを防止するために留め金を別途取り付けなければならないなどの問題があった。
【0007】
そこで本発明の主たる課題は、先ず第1に歩行面からの内空高さを高くして作業員が楽に歩けるようにし、歩行時の姿勢負担を解消すること、第2に一次覆工後に直ちに大径の下水管を搬入できるようにして作業の効率化および施工期間の短縮を図ること、第3に軌条偏心によるローリングを防止するようにすること、等の問題を一挙に解決し得るトンネル工事用仮設軌道の敷設方法を提供することにある。
【0008】
【課題を解決するための手段】
前記課題を解決するための本発明に係るトンネル工事用仮設軌道の敷設方法は、シールド機によるトンネル掘削に併行して、設置が完了した一次覆工セグメント内に、少なくとも前記シールド機の後方側に連行される後続台車とトンネル坑内を走行する運搬車とが並列的に走行可能な高さ位置に一次覆工時用枕木を設置するとともに、前記後続台車および運搬車が走行する軌条を敷設する一方、トンネル掘削中に、トンネル後方側においてシールド機と共に前進する前記後続台車が通過し終えたところから順に、前記一次覆工時用枕木及び前記後続台車および運搬車が走行する軌条を撤去し、この一次覆工時用枕木より相対的に低い高さ位置に二次覆工時用枕木を設置するとともに、前記運搬車が走行する軌条のみを敷設し直すとともに、シールド機側の前記一次覆工時用枕木に設置された運搬車が走行する軌条と連結することを特徴とするものである。
【0009】
この場合において、前記二次覆工時用枕木に設置された運搬車が走行する軌条の軌条中心をトンネル中心に一致させて敷設するようにすればセグメントのローリングを同時に防止できるようになる。
【0010】
上記本発明法においては、シールド機によるトンネル掘削時には、通常通りの方法に従って仮設軌道を所定の高さ位置に敷設するが、前記後続台車が通り終えたところから順に、低い軌道へ順次盛替えを行うようにする。したがって、後続台車が配置される区間以外のほとんどのトンネル区間において、内空高さを高く設定することができ、作業員はたとえば立坑と切羽との行き来に際して、中腰とならずに歩行することができるようになる。
【0011】
しかも、一次覆工時、すなわちトンネル掘削に併行して軌道の盛替えを完了させることにより、二次覆工作業の開始と同時に、大径の水道管をトンネル内に搬入できるようになる。従来であれば、一次覆工完了と二次覆工開始との間に全線に亘る軌道盛替えが行われ、これにかなりの期間を要していたが、この期間を省略することができるようになり、大幅な施工期間の短縮が図れるようになる。
【0012】
【発明の実施の形態】
以下、本発明の実施の形態について図面を参照しながら詳述する。
【0013】
本発明について概説すると、トンネル掘削中、すなわちシールド機による掘削と共に、一次覆工セグメントの設置を行う際には、通常通り、シールド機と共に連行する後続台車用軌条と並んで、セグメント運搬やズリ搬出等のための運搬車用の軌条を設置するが、前記後続台車がシールド機の掘進に伴って前進したならば、後続台車用軌条が不要になったところから順に、相対的に低い高さ位置に軌道の盛替えを行うものである。
【0014】
以下、具体的に詳述すると、図1に示されるように、工事中のトンネルTにおいて、坑内の先端部(切羽)にはシールド機Sが定位しており、地盤掘削に伴って前進している。このシールド機Sのすぐ後方側には、所定の区間に亘って、本例では約60mの区間に亘って、掘削、覆工、裏込注入作業の材料、機械器具およびシールド動力、付帯設備類、ズリ出し設備等のための後続台車6,6…が続いている。
【0015】
この後続台車配置区間Aの軌条構造は、図3に示されるように、一次覆工セグメント10の底部に対し、周方向のセグメントリブ10a、10aを利用して移動不能にH鋼型材よりなる一次覆工用枕木3が横架され、この一次覆工用枕木3の上面側に、坑内運搬車7が走行するための左右一対の軌条1,1(以下、運搬車軌条という)と、前記後続台車6用のモノ軌条2(以下、後続台車軌条という)との合計3本の軌条1,1,2がトンネル長手方向に沿って敷設されている。前記一次覆工用枕木3は、本例では前記後続台車6と坑内運搬車7とが並列的に走行可能となる高さ位置(RL)に設置され、前記運搬車軌条1,1の内側には、歩廊用足場板8がトンネル長手方向に沿って敷設されている。なお、前述の軌条構造は一般的な小径シールドにおいて、ごく一般的に採用されている軌条構造である。
【0016】
他方、前記後続台車6,6…が配置された区間より後方側の区間(以下、軌条盛替え完了区間Cという。)では、前記運搬車軌条1,1は、斜路区間Bを間に介して前記後続台車配置区間Aの軌道水準よりもhだけ低くした状態で軌道が盛り替えられている。具体的には、図4に示されるように、前記後続台車配置区間Aの一次覆工用枕木3の設置高さからh分だけ低い位置(RL−h)に二次覆工用枕木5,5…がトンネル長手方向に所定の間隔で設置され、この二次覆工用枕木5,5…上には、トンネル縦中心線を境に対象配置にそれぞれ前記運搬車軌条1,1が敷設されている。なお、軌条盛替え完了区間Cの枕木高さは、作業員の歩行のし易さ、二次覆工時に搬入される水道管の搬入等を総合的に考慮した上で決定される。
【0017】
前記後続台車配置区間Aと軌条盛替え完了区間Cとの間に設けられた、すりつけ区間としての斜路区間Bでは、運搬車軌条1を傾斜させて敷設するため、上面フランジのみを傾斜させた特殊形状の斜路枕木4,4を用い、かつ軌条盛替え完了区間Cでは軌道中心をトンネル中心に一致させているため、平面的にS字状にカーブさせながら両区間の軌条を連結している。この斜路区間は、前記坑内運搬車7がスムーズに走行できるように、出来るだけ区間長を長くし傾斜勾配を緩やかにするのがよい。
【0018】
前記二次覆工用枕木5は、具体的には図5に示されるように、溝形鋼を枕木本体とし、その両端部において、端縁より部材長手方向に沿って2条の切込み線5b,5bを設けるとともに、これら切込み線5b,5bに挟まれた部分5a(以下、切起し片)を上方側に折曲げたものである。なお、この切起し片5aは、切り起こした後、坑内運搬車7の走行等の邪魔にならない長さに切断される。
【0019】
前記一次覆工用枕木5の設置に当たっては、図6に示されるように、前記切起し片5aによって形成されたスリット溝Pを一次覆工セグメント10のセグメントリブ10aに対して嵌合させながら、かつ一次覆工セグメント10の内面に対して両端下部を接地させた状態で移動不能に固定される。
【0020】
前記切起し片5aは、前記スリット溝Pの形成のためと同時に、運搬車軌条1,1の片側位置を規制する側縁ストッパーとして使用される。図8に示されるように、運搬車軌条1の外側縁を前記切起し片5aに対して当接させた状態とする一方、軌条1の内側縁については、二次覆工用枕木5の下面側よりネジ部だけをボルト孔より上方に突出させたボルト13と、前記ネジ部に螺合されるナット14とによりレールクリップ12を締結し固定する。この場合、前記ボルト13については、ボルト孔にネジ部を挿通させた状態で二次覆工用枕木5に対してボルト頭部を溶接により固定しておくようにすれば、挿通手間が無くなり締結作業の効率化が図れるようになる。
【0021】
前記切起し片5aについては、最低限の機能として前記運搬車軌条1の片側位置を規制するストッパーとしての機能が必要であるが、図9に示されるように、運搬車軌条1のベースフランジ1aに沿うように逆L字状に屈曲させ側方に開口するスリット状の開口溝を形成し、この開口溝に運搬車軌条1のベースフランジ1aの側縁を嵌合させて固定するようにしてもよい。この場合には、運搬車軌条1の浮き上がりについても同時に防止することができるようになる。
【0022】
軌道レールの盛替えについては、たとえば図10に示される要領に従って行われる。なお、本例では、約1ヶ月毎に軌条の盛替えを行うこととしたため、1月当たりの掘進距離である約200mが一回の盛替え区間として設定される。
【0023】
図10(A)に示される、掘削中のある段階での軌道敷設状態から掘進に伴いシールド機Sが前進すると、シールド機Sに牽引されながら、または自走により、シールド機Sの進行に合わせながら後続台車6,6…が前進する。約1ヶ月の経過の後、シールド機Sおよび後続台車6,6…が、図10(B)に示されるように、約200m前進したならば、この段階で後続台車6,6…の後尾から斜路区間までの区間(約200m)が二次覆工用枕木5に盛り替えられる。枕木の盛替えが完了し、運搬車軌条1を敷設し直した状態が図10(C)の状態である。
【0024】
上記軌道盛替えを繰り返し、その後、一次覆工が完了したならば、既に低レベル側に盛替えが完了している運搬車軌条1,1を利用して、水道管15の搬入が行われる。二次覆工作業は、図11に示されるように、前記運搬車軌条1,1を走行する管運搬車7’に水道管15を搭載し、トンネル内の所定の位置まで運搬し、トンネルの中心位置に据え付けたならば、前記水道管15と一次覆工セグメント10との間にコンクリートを打設することにより二次覆工が施工される。
【0025】
【発明の効果】
以上詳説のとおり、本発明による軌道敷設方法によれば、トンネル掘削中に、後続台車軌条が不要になったところから順に低い位置へ軌道の盛替えを行うようにしたため、後続台車が配置される区間以外のほとんどのトンネル区間において、内空高さを高く設定することができ、作業員が中腰とならずに楽に歩けるようになる。また、一次覆工中に二次覆工用の軌道へ盛替えを行っているため、一次覆工後に直ちに大径の下水管を搬入できるようになるため、作業の効率化および施工期間の短縮が図れるようになる。さらに、盛替え後の軌道をトンネル中心とすれば、トンネル中心への盛替えが早い時期に完了していることから運搬車による偏心載荷が無くなり、ローリングを容易に防止できるようになる。
【図面の簡単な説明】
【図1】 本発明法における仮設軌道の概略を示す側面図である。
【図2】 その要部拡大平面図である。
【図3】 図1のIII−III線矢視図である。
【図4】 図1のIV−IV線矢視図である。
【図5】 二次覆工用枕木5の端部構造を示す要部斜視図である。
【図6】 二次覆工用枕木5の設置状態正面図である。
【図7】 その平面図である。
【図8】 軌条固定部の拡大図である。
【図9】 他の固定方法に係る軌条固定部の拡大図である。
【図10】 軌道盛替え手順図である。
【図11】 水道管運搬状態を示す正面図である。
【図12】 従来の仮設軌道用枕木の正面図である。
【符号の説明】
1…運搬車軌条、2…後続台車軌条、3…一次覆工用枕木、4…斜路枕木、5…二次覆工用枕木、5a…切起し片、6…後続台車、7…坑内運搬車、8…歩廊用足場、10…一次覆工セグメント、10a…セグメントリブ、15…水道管[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a temporary track for tunnel construction that is installed at the bottom of a primary lining segment in order to run a trolley car, a follower truck, a scrap steel car, a segment carrier car, a locomotive, etc. about the laying how.
[0002]
[Prior art]
For example, in the construction of shield tunnels, etc., after the construction of the primary lining segment in order to run the following carriages, shear steel cars, segment transport vehicles, locomotives, etc. The sleepers are immediately passed in the tunnel width direction, and the rails for the subsequent carriage and the underground transport vehicle are laid on the sleepers along the longitudinal direction of the tunnel.
[0003]
In the case of a small cross-section tunnel, as shown in FIG. 3, a pair of left and
[0004]
[Problems to be solved by the invention]
As described above, in order to install the three rails in the narrow tunnel and allow the
[0005]
When the tunnel is a water tunnel or the like, after completion of the primary lining, a water pipe having a diameter smaller than that of the
[0006]
On the other hand, in view of the above-mentioned problem of posture burden during walking, in Japanese Utility Model Publication No. 7-8639, as shown in FIG. 12,
[0007]
Therefore, the main problems of the present invention are to firstly increase the height of the sky from the walking surface so that workers can walk easily, to eliminate the posture burden during walking, and secondly immediately after the primary lining. Tunnel construction that can solve large-scale sewage pipes in order to improve work efficiency and shorten the construction period, and thirdly to prevent rolling due to rail eccentricity. It is to provide a method for laying a temporary track.
[0008]
[Means for Solving the Problems]
A method for laying a temporary track for tunnel construction according to the present invention for solving the above-described problem is provided in parallel with tunnel excavation by a shield machine, in the primary lining segment where installation is completed, at least on the rear side of the shield machine. A sleeper for primary lining is installed at a height position where a follower cart and a transport vehicle traveling in the tunnel mine can travel in parallel, and a rail for traveling the follower cart and the transport vehicle is installed. In the tunnel excavation, in order from the point where the succeeding carriage moving forward with the shield machine on the rear side of the tunnel has passed, the sleepers for primary lining and the rails on which the succeeding carriage and the carriage travel are removed, with installing sleepers for the time of a secondary lining into a primary lining at a relatively lower height than the sleepers position, the re-laying only rail of the truck is traveling, shea It is characterized in that the field-side of the primary lining during sleepers the installed carrier vehicle in joins with a rail traveling.
[0009]
In this case, the segment rolling can be prevented at the same time if the rail center of the rail on which the transport vehicle installed on the sleeper for secondary lining travels coincides with the tunnel center.
[0010]
In the above-described method of the present invention, when tunneling with a shield machine, a temporary track is laid at a predetermined height position according to a normal method. To do. Therefore, in most tunnel sections other than the section where the following carriage is placed, the height of the inner space can be set high, so that workers can walk without going back and forth when going up and down, for example, between a shaft and a face. become able to.
[0011]
Moreover, at the time of the primary lining, that is, along with the tunnel excavation, the refilling of the track is completed, so that a large-diameter water pipe can be carried into the tunnel simultaneously with the start of the secondary lining work. Conventionally, track reshuffling over the entire line was performed between the completion of the primary lining and the start of the secondary lining, which took a considerable period of time, but this period can be omitted. As a result, the construction period can be greatly shortened.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
[0013]
Outline of the present invention is as follows. During tunnel excavation, that is, when excavating with a shield machine and installing a primary lining segment, as usual, along with the rail for the following carriage that is accompanied with the shield machine, segment transportation and slip-out For example, if the trailer moves forward with the shield machine, the trailer for the trailer is no longer necessary. In this case, the trajectory is changed.
[0014]
In more detail below, as shown in FIG. 1, in the tunnel T under construction, the shield machine S is positioned at the tip (face) in the mine, and moves forward with the excavation of the ground. Yes. Immediately behind this shield machine S is a material for excavation, lining, backfilling work, machinery and equipment, shield power, and auxiliary equipment over a predetermined section, in this example, over a section of about 60 m. , Followed by the following
[0015]
As shown in FIG. 3, the rail structure of the subsequent carriage arrangement section A is a primary made of an H steel mold material that cannot move with respect to the bottom of the
[0016]
On the other hand, in the section on the rear side of the section where the succeeding
[0017]
In the ramp section B as a rubbing section provided between the succeeding carriage arrangement section A and the rail refilling completion section C, a special construction in which only the upper surface flange is inclined in order to lay the
[0018]
Specifically, as shown in FIG. 5, the
[0019]
When installing the
[0020]
The cut and raised
[0021]
The cut-and-raised
[0022]
The refilling of the track rail is performed, for example, according to the procedure shown in FIG. In this example, since the rail refilling is performed about every month, about 200 m, which is the digging distance per month, is set as one refilling section.
[0023]
When the shield machine S moves forward with excavation from the track laying state at a certain stage during excavation shown in FIG. 10 (A), the shield machine S is pulled by the shield machine S or by self-running to match the progress of the shield machine S. However, the following
[0024]
If the above-mentioned track re-sampling is repeated and then the primary lining is completed, the
[0025]
【The invention's effect】
As described above in detail, according to the track laying method according to the present invention, during the tunnel excavation, the track is rearranged to a lower position in order from the point where the subsequent cart rail is no longer necessary, so the subsequent cart is arranged. In most tunnel sections other than the section, the height of the inner sky can be set high, so that workers can walk easily without being in the middle. In addition, because the secondary lining track is replaced during the primary lining, it becomes possible to carry in a large-diameter sewer pipe immediately after the primary lining, thus improving work efficiency and shortening the construction period. Can be planned. Furthermore, if the track after refilling is used as the center of the tunnel, since the refilling to the tunnel center is completed at an early stage, there is no eccentric loading by the transport vehicle, and rolling can be easily prevented.
[Brief description of the drawings]
FIG. 1 is a side view showing an outline of a temporary track in the method of the present invention.
FIG. 2 is an enlarged plan view of a main part thereof.
FIG. 3 is a view taken along the line III-III in FIG. 1;
4 is a view taken in the direction of arrows IV-IV in FIG. 1;
FIG. 5 is a main part perspective view showing an end structure of a
FIG. 6 is a front view of an installed state of a
FIG. 7 is a plan view thereof.
FIG. 8 is an enlarged view of a rail fixing part.
FIG. 9 is an enlarged view of a rail fixing portion according to another fixing method.
FIG. 10 is a trajectory replacement procedure diagram.
FIG. 11 is a front view showing a water pipe carrying state.
FIG. 12 is a front view of a conventional temporary track sleeper.
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14259098A JP4111285B2 (en) | 1998-05-25 | 1998-05-25 | Laying a temporary track for tunnel construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14259098A JP4111285B2 (en) | 1998-05-25 | 1998-05-25 | Laying a temporary track for tunnel construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11336500A JPH11336500A (en) | 1999-12-07 |
JP4111285B2 true JP4111285B2 (en) | 2008-07-02 |
Family
ID=15318854
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14259098A Expired - Fee Related JP4111285B2 (en) | 1998-05-25 | 1998-05-25 | Laying a temporary track for tunnel construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4111285B2 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4823040B2 (en) * | 2006-12-08 | 2011-11-24 | 株式会社奥村組 | Segment transport system |
JP5156523B2 (en) * | 2008-07-29 | 2013-03-06 | 大成建設株式会社 | Transport system in shield tunnel. |
CN107435558A (en) * | 2017-09-22 | 2017-12-05 | 中国水利水电第四工程局有限公司 | A kind of narrow-bore tunnel excavation construction transport establishment and construction method |
CN108944627A (en) * | 2018-08-06 | 2018-12-07 | 济南重工股份有限公司 | A kind of shield machine trailer configuration |
CN109026038B (en) * | 2018-09-28 | 2019-09-24 | 中国葛洲坝集团第一工程有限公司 | TBM shield body is anti-to sidewinder walking support device and application method |
CN110055835A (en) * | 2019-04-17 | 2019-07-26 | 中铁上海工程局集团有限公司 | Subway is laid a railway track by-pass temporary transition device and construction method |
-
1998
- 1998-05-25 JP JP14259098A patent/JP4111285B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH11336500A (en) | 1999-12-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107031663B (en) | Walking platform and walking method of shield machine marshalling train and matched trailer behind shield machine | |
CN103711499A (en) | Shield tunneling machine split starting construction method | |
CN105626088B (en) | T-shaped bored tunnel shield machine is gone into the well shift method | |
JP4111285B2 (en) | Laying a temporary track for tunnel construction | |
CN108590745B (en) | Transportation method and transportation structure for shield tunnel construction | |
JP2006342574A (en) | Sleeper | |
CN201284653Y (en) | Arrangement structure for steel form plate trolley and belt conveyer in tunnel construction by TBM method | |
CN201317902Y (en) | Unballasted track lathe long rail bar paving machine set | |
JP2899880B1 (en) | Tunnel construction equipment | |
US4396313A (en) | Method of forming flooring in tunnels | |
CN110500104B (en) | Propelling method for shield tunneling machine to pass through shallow-buried underground excavation tunnel | |
JP2002285800A (en) | Rail and wide truck for tunnel driving work | |
CN209908510U (en) | Tire type tunnel operation vehicle | |
JP3051568B2 (en) | Traveling equipment for subsequent equipment of a tunnel excavator | |
CN209854462U (en) | Track for TBM equipment walking of vehicle with rear matching | |
JP2022001704A (en) | Method for arranging succeeding bogie of shield machine and succeeding bogie | |
JP2873818B1 (en) | Continuous belt conveyor support mechanism in tunnel excavation | |
US3754505A (en) | Method and apparatus for replacing a pair of rails | |
JPH0860997A (en) | Constructing method for tunnel and tunnel construction member | |
JP3422749B2 (en) | A shearing-out method and a shearing-out device enabling double track in a small section tunnel | |
JP4024967B2 (en) | The bottom structure of the shaft | |
JP3579783B2 (en) | Rail extension structure | |
JP4022081B2 (en) | Temporary track for shield tunnel construction | |
JP2014224351A (en) | Tunnel interior transfer system in shield tunnel | |
CN210622804U (en) | Shield constructs quick-witted shallow propulsion structure who buries undercut tunnel that buries |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050518 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071031 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071221 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080326 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080402 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110418 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120418 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120418 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130418 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130418 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140418 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |