JP4032711B2 - Foundation pile construction method and foundation pile constructed by this method - Google Patents

Foundation pile construction method and foundation pile constructed by this method Download PDF

Info

Publication number
JP4032711B2
JP4032711B2 JP2001357583A JP2001357583A JP4032711B2 JP 4032711 B2 JP4032711 B2 JP 4032711B2 JP 2001357583 A JP2001357583 A JP 2001357583A JP 2001357583 A JP2001357583 A JP 2001357583A JP 4032711 B2 JP4032711 B2 JP 4032711B2
Authority
JP
Japan
Prior art keywords
pile
foundation pile
foundation
pile head
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001357583A
Other languages
Japanese (ja)
Other versions
JP2003155756A (en
Inventor
政人 伊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2001357583A priority Critical patent/JP4032711B2/en
Publication of JP2003155756A publication Critical patent/JP2003155756A/en
Application granted granted Critical
Publication of JP4032711B2 publication Critical patent/JP4032711B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、基礎杭の施工方法とそれにより施工される基礎杭に関し、特に、基礎杭が支持対象となる構造物を支持する以前に載荷を行う技術に関する。
【0002】
【従来の技術】
軟弱地盤など、直接基礎等では良好な支持が得られにくい地盤においては、上部構造物の重量を的確に下層地盤に伝達して良好な支持力を確保できる杭基礎が施工される場合が多い。この杭基礎を設計するにあたり、例えば杭先端面が担う支持力や杭の周面摩擦が担う支持力といった鉛直支持力を杭毎に考慮して許容支持力を算定する。そしてこの許容支持力に応じて、一つの構造物に必要な杭の本数や配置パターン等を決定している。この場合、前記の構造物の完成後荷重に由来して生じる沈下が当該構造物に損傷等を与えないよう、前記鉛直支持力の極限値(極限支持力)を2〜3の安全率でもって除した値を許容支持力として設計に用いることが多い。こうして設計された杭は打撃、振動、圧入、プレボーリングなどの工法でもって地盤中に打ち込まれ、或いは場所打ち工法でもって地盤中に構築されることになる。
【0003】
【発明が解決しようとする課題】
しかし、前記構造物完成後において基礎杭が常時負担する荷重は、極限支持力の1/3程度にとどまるから、実際には基礎杭の先端まで荷重が伝達されている状況は少ない。言い換えれば、基礎杭が本来備える支持能力を十分に発揮することが少なく、過大な設計をされた杭基礎がそのまま施工されていたのである。他方、特開平3−90706号公報に示すように、杭の周面摩擦力を反力にとる載荷ジャッキを基礎杭先端に設けておき、これに硬化性圧力流体を圧入することで、当該基礎杭に鉛直下方の載荷を予め行い支持力増加や設計の適正化を図るといった手法も案出されている。しかし実際の施工状況を想定するに、前記載荷ジャッキを杭打設前の打設孔底に予め設置する必要があり、場所打ち工法やプレボーリング工法以外の工法には適用しにくく、また圧力流体を扱う手間やコストが少なからずかかるといった点で改善する余地が存在した。
【0004】
本発明はこのような事情に鑑みてなされたものであって、過大設計を抑制して経済的かつ効率的な設計施工を実現すると共に、良好な支持力を発現可能な基礎杭施工方法およびこの方法により施工される基礎杭を提供することを目的とする。
【0005】
【課題を解決するための手段】
この発明は上記目的を達成するためになされたもので、第1の発明は、盤中に打込まれた若しくは構築された基礎杭の杭頭に設置したジャッキ装置により、当該基礎杭が支持する構造物に反力をとって、当該基礎杭に対し載荷を行う基礎杭施工方法であって、前記基礎杭の杭頭に固設され杭頭端面より上方に突出する棒状体コネクタのうち前記杭頭端面からの突出部位をサヤ管に収め、前記ジャッキ装置の稼動に先立って前記構造物に接続することを特徴とする。
【0006】
第2の発明は、第1の発明において、前記基礎杭に対し、前記構造物の完成後荷重以上の載荷を行うことを特徴とする。
【0007】
第3の発明は、第1又は第2の発明に用いられる基礎杭であって、基礎杭の杭頭に固設され杭頭端面より上方に突出すると共にこの杭頭端面からの突出部位をサヤ管に収めた棒状体コネクタと、前記杭頭に設置されるジャッキ装置とを備えたことを特徴とする。
【0008】
【発明の実施の形態】
図1は本発明の基礎杭施工方法における施工状況を示す図であり、図2は本発明の基礎杭の杭頭付近の構造を示す図であり、(a)はジャッキ載荷前、(b)はジャッキ載荷後の状態を示す。以下、本発明の基礎杭施工方法およびこの方法により施工される基礎杭につき図面を参照しつつ詳細に説明する。本実施形態における状況として、例えば、橋梁10の建設工事に伴って橋脚躯体11が構築される状況を想定でき、この状況下で地盤20の状態に合わせて杭基礎30の施工が選択されたとする。
【0009】
杭基礎の施工手順としては、支持層や地下水位の位置等の地質状況や地盤強度など地盤20の状態を見極めた上で、既製杭を貫入させるのか場所打ち杭を打設するのか決定する。(a)図で示す基礎杭31が場所打ち杭であるとすれば、例えばアースドリル等の削孔重機でもって地盤20に杭打設孔を穿ち、この杭打設孔に鉄筋籠を建て込んでコンクリートを打設することで形成されるのである。他方、打撃工法、圧入工法および中堀工法などを採用して既製杭を地盤20に貫入させるとしても勿論よい。以下、場所打ち杭を打設した場合や既製杭を貫入させた場合も含めて、基礎杭は地盤20に「構築される」ものとする。
【0010】
こうして地盤20中に構築された基礎杭31の杭頭には油圧ジャッキ40とシアコネクター41が設置されている。この設置は基礎杭構築の前後や既製杭の製造前後を問わず、状況に合わせて行うとすればよい。いずれにしても、基礎杭31が地盤20に構築された時点から以降、本発明における“完成荷重以上の載荷”を基礎杭31に加える以前に設置がなされていればよいのである。前記油圧ジャッキ(ジャッキ装置)40は、図2で示すように例えば杭頭32の端面33にベースを埋込固定するものとし、基礎杭31の長さ方向、つまり鉛直下方に向けて適宜延伸する動作を行う。他に、基礎杭31の杭頭32および橋脚躯体11下面におけるコンクリートとの付着性を高める定着鉄筋などの手段を適宜用いることが好ましい。この定着鉄筋は、杭頭32および橋脚躯体11の少なくとも一方との定着に用いると好適だが、施工状況に応じて採用せずともよい。また、シアコネクター(棒状体コネクタ)41は水平力を基礎杭31に伝える役割を担うものであって、基礎杭31の杭頭32に一端を固設され、他端が杭頭端面33より上方に突出すると共にこの杭頭端面33からの突出部位42をサヤ管43に収めた鋼棒等の棒状体である。
【0011】
以上のように基礎杭31の構築と、その杭頭32における油圧ジャッキ40等の設置が完了したならば、サヤ管43に収まった前記突出部位42を、前記橋脚躯体11におけるフーチング12の構築に伴い、これに接続する。あるいはこの接続処理を省略して、前記油圧ジャッキ40による載荷処理を開始する。この載荷処理では、油圧ジャッキ40の反力盤40aをフーチング12に当接若しくは固定し、当該基礎杭31が支持する橋梁10(含む橋脚躯体11等)に反力をとって、当該基礎杭31に対し前記橋脚躯体11を含む橋梁10の完成後荷重以上の載荷を行う。図2に示すように、(a)図のジャッキ載荷前の状態では、フーチング12の下面と油圧ジャッキ40の反力盤40aの下面とは基礎杭31の杭頭端面33に一致している。一方、(b)図のジャッキ載荷後の状態では、杭頭端面33は、フーチング12の下面および反力盤40aの下面より下方に押し下げられている。つまり、油圧ジャッキ40の鉛直下方への延伸により基礎杭31が地盤20中へより貫入したと言える。この時、前記サヤ管43内の突出部位42は、基礎杭31の下降に伴いサヤ管43内をスライドしている。
【0012】
図3は杭にかかる荷重と沈下量との関係について示したグラフであり、(a)は従来方法、(b)は本発明の施工方法の場合を示す。従来の施工方法によれば、(a)図に示すとおり、設計荷重(上記許容支持力に対応する)は、基礎杭31がもともと対応可能である極限荷重の1/3程度となっていた。一方、本発明においては、フーチング12や橋脚躯体11といった構築済み躯体の荷重に加えて、完成後荷重以上の荷重を基礎杭31に載荷することで、構造物完成後に生じるであろう沈下を予め生じさせた上で設計荷重を設定することが可能である。よって、極限荷重に近い荷重値を設計荷重とすることができる。もちろんその結果、構造物(橋梁10)完成後の沈下量が抑制されることにつながる。
【0013】
【発明の効果】
以上詳細に説明したように、本発明の基礎杭施工方法およびこの方法により施工される基礎杭によれば、基礎杭が本来備えている支持能力を限界近くまで発揮させる形で十分な支持力を確保可能な施工を行うことができる上に、この施工に先立つ設計時においても過大設計を抑制する効果を奏する。また、場所打ち工法やプレボーリング工法といった杭打設孔を予め設ける工法だけでなく、打撃工法などの既成杭を地盤に貫入させる工法においても本発明は適用可能であり、幅広い施工状況に確実に対応することが出来る。加えて、本発明の基礎杭を構成するジャッキ装置や棒状体コネクタは杭頭に設けるものであるから、施工の手間がさほどかからずコストも低廉に出来るのである。
【0014】
しかして、過大設計を抑制して経済的かつ効率的な設計施工を実現すると共に、良好な支持力を発現可能な基礎杭施工方法およびこの方法により施工される基礎杭を提供可能となる。
【図面の簡単な説明】
【図1】本発明の基礎杭施工方法における施工状況を示す図である。
【図2】本発明の基礎杭の杭頭付近の構造を示す図であり、(a)はジャッキ載荷前、(b)はジャッキ載荷後の状態を示す。
【図3】杭にかかる荷重と沈下量との関係について示したグラフであり、(a)は従来方法、(b)は本発明の施工方法の場合を示す。
【符号の説明】
10 構造物(橋梁)
20 地盤
31 基礎杭
32 杭頭
40 ジャッキ装置(油圧ジャッキ)
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a foundation pile construction method and a foundation pile constructed thereby, and more particularly, to a technology for loading before the foundation pile supports a structure to be supported.
[0002]
[Prior art]
In the case of ground where it is difficult to obtain good support with a direct foundation such as soft ground, pile foundations that can transmit the weight of the upper structure to the lower ground accurately to ensure good support are often constructed. In designing this pile foundation, for example, the allowable bearing force is calculated by taking into consideration the vertical bearing force such as the bearing force borne by the pile tip surface and the bearing force borne by the circumferential friction of the pile for each pile. And according to this permissible bearing capacity, the number of piles required for one structure, arrangement pattern, etc. are determined. In this case, the limit value (extreme support force) of the vertical support force is set to a safety factor of 2 to 3 so that the settlement caused by the load after completion of the structure does not damage the structure. The value divided is often used in the design as the allowable bearing force. The pile thus designed is driven into the ground by a method such as hammering, vibration, press-fitting, or pre-boring, or is constructed in the ground by a cast-in-place method.
[0003]
[Problems to be solved by the invention]
However, since the load that the foundation pile always bears after completion of the structure is only about 1/3 of the ultimate bearing capacity, there are few situations where the load is actually transmitted to the tip of the foundation pile. In other words, the pile foundation that was originally designed was rarely fully exhibited, and the pile foundation with an excessively large design was constructed as it was. On the other hand, as shown in Japanese Patent Laid-Open No. 3-90706, a loading jack that takes the circumferential frictional force of the pile as a reaction force is provided at the tip of the foundation pile, and a curable pressure fluid is press-fitted into the foundation pile, thereby A method has also been devised in which the pile is loaded in the vertical direction in advance to increase the bearing capacity and optimize the design. However, in order to assume the actual construction situation, it is necessary to install the load jack described above at the bottom of the placement hole before placing the pile, which is difficult to apply to construction methods other than the cast-in-place method and the pre-boring method. There was room for improvement in that it took a lot of labor and cost to handle the.
[0004]
The present invention has been made in view of such circumstances, and realizes an economical and efficient design and construction by suppressing an excessive design, and a foundation pile construction method capable of expressing a good bearing force, and this It aims at providing the foundation pile constructed by the method.
[0005]
[Means for Solving the Problems]
The present invention has been made in order to achieve the above object, a first aspect of the present invention, by installing the jack device in the pile head of the implanted or constructed foundation pile in the ground plate, the foundation pile is supported to construct taking reaction force, the foundation pile to pair with loading a row cormorants group Ishizuekui construction method, the rod-shaped body which projects upward from the pile head is fixed to the pile head end face of said foundation pile Of the connector, a protruding portion from the end face of the pile head is housed in a sheath pipe and connected to the structure prior to operation of the jack device .
[0006]
The second invention is characterized in that, in the first invention, the foundation pile is loaded more than the load after completion of the structure .
[0007]
3rd invention is the foundation pile used for 1st or 2nd invention, Comprising: It is fixed to the pile head of a foundation pile, and it protrudes upwards from a pile head end surface, and the protrusion site | part from this pile head end surface is a shear. A rod-shaped body connector housed in a pipe and a jack device installed on the pile head are provided.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
FIG. 1 is a diagram showing the construction status in the foundation pile construction method of the present invention, FIG. 2 is a diagram showing the structure near the pile head of the foundation pile of the present invention, (a) before jack loading, (b) Indicates the state after the jack is loaded. Hereinafter, the foundation pile construction method of the present invention and the foundation pile constructed by this method will be described in detail with reference to the drawings. As a situation in the present embodiment, for example, a situation can be assumed in which the pier frame 11 is constructed along with the construction work of the bridge 10, and under this situation, the construction of the pile foundation 30 is selected in accordance with the state of the ground 20. .
[0009]
As the construction procedure of the pile foundation, after determining the geological condition such as the position of the support layer and the groundwater level and the condition of the ground 20 such as the ground strength, it is determined whether the ready-made pile is to be penetrated or the cast-in-place pile is to be placed. (A) If the foundation pile 31 shown in the figure is a cast-in-place pile, for example, a pile driving hole is drilled in the ground 20 with a drilling heavy machine such as an earth drill, and a reinforcing bar is built in the pile driving hole. It is formed by casting concrete. On the other hand, it is a matter of course that a ready-made pile may be penetrated into the ground 20 by adopting a hitting method, a press-fitting method, a Nakabori method or the like. Hereinafter, it is assumed that the foundation pile is “constructed” on the ground 20 including a case where a cast-in-place pile is placed and a case where a ready-made pile is inserted.
[0010]
A hydraulic jack 40 and a shear connector 41 are installed on the pile head of the foundation pile 31 thus constructed in the ground 20. This installation may be performed according to the situation before and after foundation pile construction and before and after production of ready-made piles. In any case, after the foundation pile 31 is constructed on the ground 20, it is sufficient that the installation is made before adding “loading more than the completed load” in the present invention to the foundation pile 31. As shown in FIG. 2, the hydraulic jack (jack device) 40 has a base embedded and fixed to, for example, an end surface 33 of the pile head 32, and extends appropriately in the length direction of the foundation pile 31, that is, vertically downward. Perform the action. In addition, it is preferable to appropriately use means such as fixing reinforcing bars for improving the adhesion between the pile head 32 of the foundation pile 31 and the concrete on the lower surface of the pier frame 11. This fixing reinforcing bar is preferably used for fixing with at least one of the pile head 32 and the pier frame 11, but may not be used depending on the construction situation. The shear connector (rod-shaped body connector) 41 plays a role of transmitting a horizontal force to the foundation pile 31, and one end is fixed to the pile head 32 of the foundation pile 31, and the other end is above the pile head end surface 33. It is a rod-shaped body such as a steel rod that protrudes from the pile head end surface 33 and accommodates the protruding portion 42 in the sheath pipe 43.
[0011]
When the construction of the foundation pile 31 and the installation of the hydraulic jack 40 and the like at the pile head 32 are completed as described above, the protruding portion 42 that is housed in the sheath pipe 43 is used to construct the footing 12 in the pier frame 11. Connect with this. Or this connection process is abbreviate | omitted and the loading process by the said hydraulic jack 40 is started. In this loading process, the reaction force plate 40a of the hydraulic jack 40 abuts or is fixed to the footing 12, taking the reaction force bridge 10 a person the foundation pile 31 is supported (including pier building frame 11, etc.), the foundation pile 31 is loaded more than the post-completion load of the bridge 10 including the pier housing 11. As shown in FIG. 2, the bottom surface of the footing 12 and the bottom surface of the reaction force board 40 a of the hydraulic jack 40 coincide with the pile head end surface 33 of the foundation pile 31 in the state before the jack loading in FIG. On the other hand, in the state after jack loading of (b) figure, the pile head end surface 33 is pushed down from the lower surface of the footing 12, and the lower surface of the reaction force board 40a. That is, it can be said that the foundation pile 31 has penetrated more into the ground 20 by extending the hydraulic jack 40 vertically downward. At this time, the protruding portion 42 in the sheath pipe 43 slides in the sheath pipe 43 as the foundation pile 31 descends.
[0012]
FIG. 3 is a graph showing the relationship between the load applied to the pile and the amount of settlement, where (a) shows the case of the conventional method and (b) shows the case of the construction method of the present invention. According to the conventional construction method, as shown in FIG. 5A, the design load (corresponding to the allowable support force) is about 1/3 of the ultimate load that the foundation pile 31 can originally handle. On the other hand, in the present invention, in addition to the load of the built frame such as the footing 12 and the pier frame 11, a load higher than the post-completion load is loaded on the foundation pile 31 to prevent the settlement that will occur after the structure is completed in advance. It is possible to set the design load after it is generated. Therefore, a load value close to the ultimate load can be used as the design load. Of course, as a result, the amount of settlement after the structure (bridge 10) is completed is suppressed.
[0013]
【The invention's effect】
As explained in detail above, according to the foundation pile construction method of the present invention and the foundation pile constructed by this method, sufficient support force is provided in such a manner that the support ability of the foundation pile is provided to the limit. In addition to being able to perform construction that can be secured, there is an effect of suppressing excessive design even at the time of design prior to this construction. Moreover, the present invention can be applied not only to a method in which a pile driving hole such as a cast-in-place method or a pre-boring method is provided in advance, but also to a method in which an existing pile such as a batting method is inserted into the ground, and is surely applicable to a wide range of construction situations Can respond. In addition, since the jack device and the rod-shaped body connector that constitute the foundation pile of the present invention are provided on the pile head, it does not require much labor for construction, and the cost can be reduced.
[0014]
Thus, it is possible to provide an economical and efficient design and construction by suppressing an excessive design, and to provide a foundation pile construction method capable of expressing a good bearing force and a foundation pile constructed by this method.
[Brief description of the drawings]
FIG. 1 is a diagram showing a construction status in a foundation pile construction method of the present invention.
FIGS. 2A and 2B are diagrams showing a structure near a pile head of a foundation pile according to the present invention, in which FIG. 2A shows a state before jack loading, and FIG. 2B shows a state after jack loading.
FIG. 3 is a graph showing a relationship between a load applied to a pile and a subsidence amount, where (a) shows a conventional method and (b) shows a case of the construction method of the present invention.
[Explanation of symbols]
10 Structure (Bridge)
20 Ground 31 Foundation pile 32 Pile head 40 Jack device (hydraulic jack)

Claims (3)

盤中に打込まれた若しくは構築された基礎杭の杭頭に設置したジャッキ装置により、当該基礎杭が支持する構造物に反力をとって、当該基礎杭に対し載荷を行う基礎杭施工方法であって、
前記基礎杭の杭頭に固設され杭頭端面より上方に突出する棒状体コネクタのうち前記杭頭端面からの突出部位をサヤ管に収め、前記ジャッキ装置の稼動に先立って前記構造物に接続することを特徴とする基礎杭施工方法
By installing the jack device in the pile head of the implanted or constructed foundation pile in the ground plate, taking a reaction force to the structure to which the foundation pile is supported, intends row a load placement against to the foundation pile a group Ishizuekui construction methods,
Of the rod-shaped connector fixed to the pile head of the foundation pile and projecting upward from the end face of the pile head, the projecting part from the end face of the pile head is housed in a sheath tube and connected to the structure prior to the operation of the jack device. A foundation pile construction method characterized by:
前記基礎杭に対し、前記構造物の完成後荷重以上の載荷を行うことを特徴とする請求項1記載の基礎杭施工方法 The foundation pile construction method according to claim 1, wherein the foundation pile is loaded more than a load after completion of the structure . 請求項1又は2に記載の方法に用いられる基礎杭であって、基礎杭の杭頭に固設され杭頭端面より上方に突出すると共にこの杭頭端面からの突出部位をサヤ管に収めた棒状体コネクタと、前記杭頭に設置されるジャッキ装置とを備えたことを特徴とする基礎杭。It is the foundation pile used for the method of Claim 1 or 2, Comprising: It fixed to the pile head of the foundation pile, and it protruded upwards from the pile head end surface, and the protrusion site | part from this pile head end surface was stored in the Saya pipe. A foundation pile comprising a rod-shaped body connector and a jack device installed on the pile head.
JP2001357583A 2001-11-22 2001-11-22 Foundation pile construction method and foundation pile constructed by this method Expired - Fee Related JP4032711B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001357583A JP4032711B2 (en) 2001-11-22 2001-11-22 Foundation pile construction method and foundation pile constructed by this method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001357583A JP4032711B2 (en) 2001-11-22 2001-11-22 Foundation pile construction method and foundation pile constructed by this method

Publications (2)

Publication Number Publication Date
JP2003155756A JP2003155756A (en) 2003-05-30
JP4032711B2 true JP4032711B2 (en) 2008-01-16

Family

ID=19168908

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001357583A Expired - Fee Related JP4032711B2 (en) 2001-11-22 2001-11-22 Foundation pile construction method and foundation pile constructed by this method

Country Status (1)

Country Link
JP (1) JP4032711B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970958A (en) * 2016-05-27 2016-09-28 王继忠 Monitoring and protecting method for pre-cast pile construction

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4365238B2 (en) * 2004-02-24 2009-11-18 Jfeスチール株式会社 Foundation reinforcement method for structures
CN103266637B (en) * 2013-06-04 2015-05-20 天津大学 In-situ measurement device and method for end resistance and frictional resistance of skirtboard foundation in penetration process
CN103266636B (en) * 2013-06-04 2015-05-20 天津大学 In-situ measurement device and method for end resistance and frictional resistance of barrel type foundation in penetration process
KR101652837B1 (en) * 2016-02-23 2016-09-01 주식회사 한국지오콘 Pre-loading apparatus for construction pile and method for constructing the pile using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970958A (en) * 2016-05-27 2016-09-28 王继忠 Monitoring and protecting method for pre-cast pile construction

Also Published As

Publication number Publication date
JP2003155756A (en) 2003-05-30

Similar Documents

Publication Publication Date Title
US6074133A (en) Adjustable foundation piering system
WO2006030893A1 (en) Foundation structure of tower
KR101519111B1 (en) jacking method for pile
US20070048095A1 (en) Supported Underpinning Piers
JP4032711B2 (en) Foundation pile construction method and foundation pile constructed by this method
US7044686B2 (en) Apparatus and method for supporting a structure with a pier
JP2009121114A (en) Construction bearing structure, method of constructing underground construction, and method of replacing bearing of foundation load
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
JP3690495B2 (en) Building construction method and building
JP5036775B2 (en) Construction method of cast-in-place concrete pile or cylindrical ground improvement body
CN212656218U (en) Heavy pile machine load underpinning structure
JP3488454B1 (en) H-shaped steel pile for temporary work
JP3778069B2 (en) Construction method of foundation pile with seismic isolation effect
JP3963326B2 (en) Seismic reinforcement structure for bridge pier and its construction method
JP2001303592A (en) Method for installing and fixing block
KR20100123576A (en) Method for carrying out improved pile
JP4968676B2 (en) Pile foundation reinforcement method using increased piles
JP4837618B2 (en) Caisson press-in method
JP3293796B2 (en) Pile driver
KR102215027B1 (en) Construction method of structure using ground bearing capacity
JP3773134B2 (en) Seismic isolation method for structures using micropile
JP2003268785A (en) Pile foundation
JPH10140583A (en) Aseismatic reinforcing method of existing structure foundation by micropile
EP4187018A1 (en) Pile foundation and method for installing a pile foundation

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20040927

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041111

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20041111

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20041111

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061122

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061205

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070201

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070508

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070706

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071002

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071015

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101102

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101102

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111102

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121102

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131102

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees