JP3957390B2 - Intermediate stage structure - Google Patents
Intermediate stage structure Download PDFInfo
- Publication number
- JP3957390B2 JP3957390B2 JP07151998A JP7151998A JP3957390B2 JP 3957390 B2 JP3957390 B2 JP 3957390B2 JP 07151998 A JP07151998 A JP 07151998A JP 7151998 A JP7151998 A JP 7151998A JP 3957390 B2 JP3957390 B2 JP 3957390B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- stage
- building
- intermediate stage
- structural
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Residential Or Office Buildings (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、建物の1階から上階への吹き抜け部に配置される中間ステージ構造に関するものである。
【0002】
【従来の技術】
従来の中低層住宅における中間ステージ(以下、「スキップフロア」という)構造は建物の構造躯体の一部として設計されるのが一般であり、その構造の一例を図3を用いて説明する。図3はスキップフロアの構造の一例を示す模式図である。
【0003】
図3において、スキップフロアSは建物の普通の1、2階の柱51よりも短い柱52と、該スキップフロアSの梁53を中間部で支持すると共に普通の1、2階の柱51と同じ長さを有する柱54とにより支持され、該スキップフロアSの梁53の上部に普通の1、2階の柱51よりも長い柱55を配置してこの柱55と普通の2階の柱51とにより普通の2階の梁56が支持されて建物の構造躯体の一部を構成する。
【0004】
また、柱52,55の夫々の間には建物の構造躯体の耐震性能を確保するためのブレース57,58が取り付けられ、スキップフロアSと建物の普通の1、2階の床との間に夫々図示しない階段が取り付けられる。
【0005】
【発明が解決しようとする課題】
しかしながら、前述の従来例では、スキップフロアSの梁53及び該梁53を支持する柱52,54、普通の2階の梁56を支持する柱55及びスキップフロアSと普通の1、2階の床との間に設けられる階段が建物の構造躯体の一部として設計されるため構造計算が複雑であり、使用される構造部材の形状が制限されたり強度を確保するために部品点数が増大し、施工に手間がかかって工期が長くなるという問題がある。
【0006】
また、長さの異なる柱51,52,55や梁53を中間で支持する柱54が必要となるので使用する柱の種類が増大し、これに伴って長さの異なるブレース57,58が必要となるので使用するブレースの種類も増大する。また、柱52,55の長さに合わせた外壁材や、内装の下地材或いは窓枠が必要となるのでこれ等の種類も増大する。また、スキップフロアSの床上げレベルを数種類設定すれば、更に上記の各部材の種類が増大して製造及び管理コストがかかるという問題がある。
【0007】
また、最近では生活環境をより豊かにするために採光が良く、通風の良い居住スペースのニーズが高まっており、天井が高く大きな窓のある広い居住スペースの確保が望まれている。
【0008】
本発明は前記課題を解決するものであり、その目的とするところは、天井が高く大きな窓のある広い居住スペースを確保するために建物の1階から上階への吹き抜け部に配置される中間ステージ構造に着目し、建物の構造躯体から独立してステージ部を設けることで建物の構造計算が簡単で使用される構造部材の形状の自由度が増し、部品点数及び部品の種類を削減して施工が容易な中間ステージ構造を提供せんとするものである。
【0009】
【課題を解決するための手段】
前記目的を達成するための本発明に係る中間ステージ構造は、建物の1階から上階への吹き抜け部に配置される中間ステージ構造であって、建物の構造躯体から独立して1階の床上に配置される支持部と、該支持部に支持され、建物の構造躯体から独立したステージ部と、該ステージ部から下階に延長する下階段及び/または該ステージ部から上階に延長する上階段を備えていることを特徴とする。
【0010】
本発明は、上述の如く構成したので、建物の構造躯体から独立して1階の床上に配置された支持部によりステージ部が支持されるので中間ステージ構造を建物の構造計算に算入する必要がなく構造設計が簡単に出来る。
【0011】
また、ステージ部を建物の構造躯体となる普通階の柱や梁で支持する必要がないので普通階の柱や梁の種類が低減出来ると共に使用される構造部材の部品点数を削減して施工が容易に出来、該構造部材の形状の自由度を増大することが出来る。また、普通階の梁や柱の種類に関係なくステージ部のレベル高さを自由に設定出来る。
【0012】
また、ステージ部から下階に延長する下階段及び/または該ステージ部から上階に延長する上階段を備えたことでステージ部への昇り降りが上下階段或いは梯子により容易に出来る。
【0013】
また、前記ステージ部の下側を室空間として構成した場合には、該ステージ部の下側スペースを居住空間や収納スペース或いは機械室等として有効利用することが出来る。
【0014】
また、前記ステージ部の下側の室空間を半地下に配置した場合には地面を少し掘るだけでステージ部の下側の室空間を居住空間や収納スペース或いは機械室等として有効利用することが出来る。
【0015】
【発明の実施の形態】
図により本発明に係る中間ステージ構造の一実施形態を具体的に説明する。図1は本発明に係る中間ステージ構造を有する2階建て住宅の一例を示す断面説明図、図2は本発明に係る中間ステージ構造の周辺の構成を示す斜視図である。
【0016】
本発明に係る中間ステージ構造は建物の1階から上階への吹き抜け部に配置されるものであり、本実施形態では特に中低層住宅に好適な中間ステージ(以下、「スキップフロア」という)構造について説明する。
【0017】
図1において、Aは住宅の1階部分、Bは2階部分、Cは屋上部分、Dは地階部分を夫々示す。1は地面2上に設けられた床であり、3は1階と2階との間の梁、4は屋上の梁である。この住宅の構造躯体は上記床1、普通階の梁3,4及び図示しない普通階の柱等により構成され、これ等の部材に基づいて構造計算が行われる。
【0018】
図1の住宅の右側部は地階部分Dから屋上部分Cに亘って吹き抜け部Eとして構成されており、その天井屋根部5には天窓6が設けられている。また吹き抜け部Eの図1の右側の外壁部7には開口部(窓)8が設けられている。
【0019】
上記地階部分Dから3階部分Cに亘って設けられた吹き抜け部Eは天井が高く天井屋根部5に設けられた天窓6や外壁部7に設けられた開口部(窓)8により大きな窓のある広い居住スペースを確保することが出来るものであり、これにより、採光が良く、通風の良い居住スペースのニーズに対応して生活環境をより豊かにすることが出来る住宅を提供するものである。
【0020】
前記吹き抜け部Eの1階部分Aに中2階となるスキップフロアSが配置されている。スキップフロアSは建物の柱や梁等からなる構造躯体から独立してスキップフロアSの下階となる地階部分Dの床9上に配置される支持部となる柱10と、該柱10に支持されたステージ部11を有しており、更に該ステージ部11にはステージ部11から下階となる1階部分Aに延長する下階段12と、該ステージ部11から上階となる2階部分Bに延長する上階段13を備えて構成されている。
【0021】
上階段13は2階部分Bの廊下や部屋の入口部分等の床に固定され、下階段12も同様に1階部分Aの廊下や部屋の入口部分等の床に固定されている。尚、上下階段13,12は1、2階部分A,Bの床に固定しなくても床に載置されるか若しくは所定間隔浮いている梯子であっても良い。
【0022】
スキップフロアSのステージ部11のレベル高さは柱10の高さ及び上下階段13,12の段数を調節することで容易に調整することが出来るので普通階の梁や柱の種類に関係なくステージ部11のレベル高さを自由に設定出来、有利である。
【0023】
また、スキップフロアSのステージ部11が柱10により支持されるのみで住宅の構造躯体から独立した構造であるので住宅本体に荷重をかけないため中間ステージとなるスキップフロアSの構造を建物の構造計算に算入する必要がなく構造設計が簡単に出来、有利である。
【0024】
また、ステージ部11を建物の構造躯体である普通階の柱や梁で支持する必要がないので普通階の柱や梁の種類が低減出来ると共に使用される構造部材の部品点数を削減して施工が容易に出来、該構造部材の形状の自由度を増大することが出来る。
【0025】
また、ステージ部11から下階に延長する下階段12及び該ステージ部11から上階に延長する上階段13を備えたことでステージ部11への昇り降りが上下階段13,12により容易に出来る。また、ステージ部11からの階段は下階段12或いは上階段13のみからなる場合でも良く、夫々梯子により構成しても良い。
【0026】
本実施形態では、ステージ部11は少なくとも子供が遊ぶことの出来る広さを有すると共に間仕切りやドアなしで上下階段13,12に連絡出来るようになっている。
【0027】
また、ステージ部11及び柱10等は各部品を室内に搬入して組み立てることが出来るようになっており、住宅が出来上がった状態であってもスキップフロアSを容易に構築することが出来るものである。
【0028】
また、ステージ部11の下側には半地下に配置された室空間14が設けられており、1階部分Aの廊下や部屋の入口部分等の床から室空間14の地階部分Dの床9に地下階段15が連絡している。
【0029】
このように、ステージ部11の下側を室空間14として構成したことで該室空間14を居住空間や収納スペース或いは機械室等として有効利用することが出来る。
【0030】
また、ステージ部11の下階が1階であり、該ステージ部11の下側の室空間14を半地下に配置した場合には地面2を少し掘るだけでステージ部11の下側の室空間14を居住空間や収納スペース或いは機械室等として有効利用することが出来るので好ましい。
【0031】
尚、前記実施形態では、スキップフロアSを建物の構造躯体外に設けた場合について説明したが、建物の構造躯体内に設けることも可能である。また、住宅以外のオフィス等の建物にも適宜適用出来るものである。
【0032】
【発明の効果】
本発明は、上述の如き構成と作用とを有するので、建物の構造躯体から独立してステージ部を設けることで建物の構造計算が簡単で使用される構造部材の形状の自由度が増し、部品点数及び部品の種類を削減して施工が容易な中間ステージ構造を提供することが出来る。
【0033】
即ち、建物の構造躯体から独立して1階の床上に配置された支持部にステージ部が支持されるので中間ステージ構造を建物の構造計算に算入する必要がなく構造設計が簡単に出来る。
【0034】
また、ステージ部を建物の構造躯体である普通階の柱や梁で支持する必要がないので普通階の柱や梁の種類が低減出来ると共に使用される構造部材の部品点数を削減して施工が容易に出来、該構造部材の形状の自由度を増大することが出来る。また、普通階の梁や柱の種類に関係なくステージ部のレベル高さを自由に設定出来る。
【0035】
また、ステージ部から下階に延長する下階段及び/または該ステージ部から上階に延長する上階段を備えたことでステージ部への昇り降りが上下階段或いは梯子により容易に出来る。
【0036】
また、ステージ部の下側を室空間として構成した場合には、該ステージ部の下側スペースを居住空間や収納スペース或いは機械室等として有効利用することが出来る。
【0037】
また、ステージ部の下側の室空間を半地下に配置した場合には地面を少し掘るだけでステージ部の下側の室空間を居住空間や収納スペース或いは機械室等として有効利用することが出来る。
【図面の簡単な説明】
【図1】 本発明に係る中間ステージ構造を有する2階建て住宅の一例を示す断面説明図である。
【図2】 本発明に係る中間ステージ構造の周辺の構成を示す斜視図である。
【図3】 従来例の課題を説明する図である。
【符号の説明】
A…1階部分
B…2階部分
C…屋上部分
D…地階部分
E…吹き抜け部
S…スキップフロア
1…床
2…地面
3,4…梁
5…天井屋根部
6…天窓
7…外壁部
8…開口部
9…床
10…柱
11…ステージ部
12…下階段
13…上階段
14…室空間
15…地下階段[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an intermediate stage structure that is arranged in a hollow portion from the first floor to the upper floor of a building.
[0002]
[Prior art]
A conventional intermediate stage (hereinafter referred to as “skip floor”) structure in a middle- and low-rise house is generally designed as a part of a structural frame of a building, and an example of the structure will be described with reference to FIG. FIG. 3 is a schematic diagram showing an example of the structure of the skip floor.
[0003]
In FIG. 3, the skip floor S includes a
[0004]
In addition,
[0005]
[Problems to be solved by the invention]
However, in the above-described conventional example, the
[0006]
In addition, since
[0007]
Recently, in order to enrich the living environment, there is a growing need for a well-lit and well-ventilated living space, and it is desired to secure a large living space with a high ceiling and large windows.
[0008]
The present invention solves the above-mentioned problems, and its object is to provide an intermediate space arranged in the atrium from the first floor to the upper floor of the building in order to secure a large living space with a high ceiling and large windows. Focusing on the stage structure, providing the stage part independently from the building structural frame increases the degree of freedom in the shape of the structural members that are easy to use, and reduces the number of parts and types of parts. It is intended to provide an intermediate stage structure that is easy to construct.
[0009]
[Means for Solving the Problems]
In order to achieve the above object, an intermediate stage structure according to the present invention is an intermediate stage structure that is arranged in an atrium from the first floor to the upper floor of a building, and is provided on the floor of the first floor independently of the structural frame of the building. A support part disposed on the stage , a stage part supported by the support part and independent of the structural frame of the building, a lower staircase extending from the stage part to the lower floor, and / or extending from the stage part to the upper floor It is characterized by having an upper staircase.
[0010]
Since the present invention is configured as described above, the stage part is supported by the support part arranged on the floor of the first floor independently of the building structural frame. Therefore, it is necessary to include the intermediate stage structure in the structural calculation of the building. The structure design can be done easily.
[0011]
In addition, since it is not necessary to support the stage with pillars and beams on the ordinary floor that will be the structural frame of the building, the number of types of pillars and beams on the ordinary floor can be reduced and the number of structural members used can be reduced. This can be easily performed, and the degree of freedom of the shape of the structural member can be increased. In addition, the level height of the stage can be freely set regardless of the types of beams and columns on the normal floor.
[0012]
Further, by providing the lower stairs extending from the stage part to the lower floor and / or the upper stairs extending from the stage part to the upper floor, the ascending and descending to the stage part can be easily performed by the upper and lower stairs or the ladder.
[0013]
Further, when the lower side of the stage portion is configured as a room space, the lower space of the stage portion can be effectively used as a living space, a storage space, a machine room, or the like.
[0014]
Also, effectively utilized as only the stage portion below the chamber space living space and storage space or machine room or the like digging a little ground in the case of arranging the lower chamber space before kissing stage portion in a semi-underground I can do it.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
An embodiment of the intermediate stage structure according to the present invention will be specifically described with reference to the drawings. FIG. 1 is a cross-sectional explanatory view showing an example of a two-story house having an intermediate stage structure according to the present invention, and FIG. 2 is a perspective view showing a configuration around the intermediate stage structure according to the present invention.
[0016]
The intermediate stage structure according to the present invention is arranged in the atrium from the first floor to the upper floor of the building, and in the present embodiment, an intermediate stage (hereinafter referred to as “skip floor”) structure particularly suitable for middle- and low-rise houses. Will be described.
[0017]
In FIG. 1, A is the first floor portion of the house, B is the second floor portion, C is the rooftop portion, and D is the basement portion. 1 is a floor provided on the
[0018]
The right side portion of the house in FIG. 1 is configured as an atrium portion E extending from the basement portion D to the rooftop portion C, and the
[0019]
The atrium E provided from the basement part D to the third floor part C has a high ceiling and has a large window formed by a
[0020]
A skip floor S serving as a middle second floor is disposed in the first floor portion A of the atrium portion E. The skip floor S is a
[0021]
The
[0022]
The level height of the
[0023]
In addition, since the
[0024]
In addition, it is not necessary to support the
[0025]
In addition, by having a
[0026]
In the present embodiment, the
[0027]
In addition, the
[0028]
In addition, a room space 14 disposed in the semi-basement is provided below the
[0029]
Thus, by configuring the lower side of the
[0030]
In addition, when the lower floor of the
[0031]
In addition, although the said embodiment demonstrated the case where the skip floor S was provided outside the structural frame of a building, it is also possible to provide in the structural frame of a building. Moreover, it can be applied to buildings such as offices other than houses as appropriate.
[0032]
【The invention's effect】
Since the present invention has the above-described configuration and operation, providing the stage portion independently of the building structural frame increases the degree of freedom in the shape of the structural members that can be easily used for the structural calculation of the building, and the parts. It is possible to provide an intermediate stage structure that is easy to construct by reducing the number of points and the types of parts.
[0033]
That is, since the stage portion is supported by the support portion arranged on the first floor independently of the building structural frame, it is not necessary to include the intermediate stage structure in the structural calculation of the building, thereby simplifying the structural design.
[0034]
In addition, since it is not necessary to support the stage part with ordinary floor pillars and beams, which are the structural frame of the building, the number of types of pillars and beams on the ordinary floor can be reduced and the number of structural members used can be reduced. This can be easily performed, and the degree of freedom of the shape of the structural member can be increased. In addition, the level height of the stage can be freely set regardless of the types of beams and columns on the normal floor.
[0035]
Further, by providing the lower stairs extending from the stage part to the lower floor and / or the upper stairs extending from the stage part to the upper floor, the ascending and descending to the stage part can be easily performed by the upper and lower stairs or the ladder.
[0036]
Further, when the lower side of the stage unit is configured as a room space, the lower space of the stage unit can be effectively used as a living space, a storage space, a machine room, or the like.
[0037]
In addition, it is possible to effectively use only the lower chamber space of the stage as living space and storage space or mechanical room or the like in the dig a little ground in the case of arranging the lower side of the chamber space of the stages part in a semi-underground I can do it.
[Brief description of the drawings]
FIG. 1 is an explanatory cross-sectional view showing an example of a two-story house having an intermediate stage structure according to the present invention.
FIG. 2 is a perspective view showing a peripheral configuration of an intermediate stage structure according to the present invention.
FIG. 3 is a diagram illustrating a problem of a conventional example.
[Explanation of symbols]
A ... 1st floor part B ... 2nd floor part C ... Rooftop part D ... Basement part E ... Blow-through part S ... Skip floor 1 ...
10 ... pillar
11 ... Stage
12… Lower staircase
13… Upstairs
14 ... Room space
15 ... Underground staircase
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP07151998A JP3957390B2 (en) | 1998-03-20 | 1998-03-20 | Intermediate stage structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP07151998A JP3957390B2 (en) | 1998-03-20 | 1998-03-20 | Intermediate stage structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11270040A JPH11270040A (en) | 1999-10-05 |
JP3957390B2 true JP3957390B2 (en) | 2007-08-15 |
Family
ID=13463060
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP07151998A Expired - Lifetime JP3957390B2 (en) | 1998-03-20 | 1998-03-20 | Intermediate stage structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3957390B2 (en) |
-
1998
- 1998-03-20 JP JP07151998A patent/JP3957390B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH11270040A (en) | 1999-10-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4648736B2 (en) | Unit building | |
JP3987392B2 (en) | building | |
JP3957390B2 (en) | Intermediate stage structure | |
US4676037A (en) | Building and method of construction | |
JP4036858B2 (en) | building | |
JP3686732B2 (en) | Unit building | |
JP4097645B2 (en) | building | |
JP3952397B2 (en) | Seismic reinforcement extension method of house and building extended by this method | |
JP3571089B2 (en) | Unit building | |
JP5066354B2 (en) | Building units and unit buildings | |
JPH10131522A (en) | Dwelling | |
JP3012498B2 (en) | Residential floor plan | |
JP2843287B2 (en) | Building | |
JPH10196138A (en) | Attic space structure of building | |
JP2547483B2 (en) | Housing unit for setback of unit housing | |
JPH07331895A (en) | Planer structure of building | |
JPH0874428A (en) | Industrialized dwelling house | |
JPH0657971A (en) | Double-loaded corridor type wide opening collective housing | |
JP3339701B2 (en) | Multi-storey building structure | |
JPH11222939A (en) | Unit type building | |
JP3924050B2 (en) | Unit building | |
JP2738599B2 (en) | Structure of middle and high rise building and construction method | |
JP2618111B2 (en) | Dwelling unit | |
JP4007953B2 (en) | Building construction method | |
JPH0762900A (en) | Building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050318 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070129 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070206 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070327 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070508 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070508 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110518 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110518 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120518 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120518 Year of fee payment: 5 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120518 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120518 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130518 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130518 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140518 Year of fee payment: 7 |
|
EXPY | Cancellation because of completion of term |