JP3895143B2 - Assembly and dismantling method for work lifting scaffolds in tower tanks - Google Patents
Assembly and dismantling method for work lifting scaffolds in tower tanks Download PDFInfo
- Publication number
- JP3895143B2 JP3895143B2 JP2001287694A JP2001287694A JP3895143B2 JP 3895143 B2 JP3895143 B2 JP 3895143B2 JP 2001287694 A JP2001287694 A JP 2001287694A JP 2001287694 A JP2001287694 A JP 2001287694A JP 3895143 B2 JP3895143 B2 JP 3895143B2
- Authority
- JP
- Japan
- Prior art keywords
- mast
- stage
- scaffold
- elevating
- assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Movable Scaffolding (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は塔槽類内の点検、修繕、清掃等を行う際に用いる作業用昇降式足場の組立・解体工法に関する。
【0002】
【従来の技術】
煙突、蒸発釜、タンク等の塔槽類(以下塔槽類と云う)においては、内部の点検、修繕、清掃等を行うために、定期的、不定期的に運転を停止する。塔槽類の運転を停止し、かつ内部を水洗した後、内部に足場を組み、内部の点検、修繕、清掃等を行う。
【0003】
一般に塔槽類は本体を気密に保ち、被流体を処理し、上部から系外に排出する等を行っている。
【0004】
例えば、クラフトパルプの蒸解に用いられる連続式蒸発釜は、高さが約50mの塔状体である。上記蒸解は耐圧蒸発釜で木材チップに蒸解液を加え、加熱用蒸気を上中下部に吹き込んで、170度前後で数時間行われる。木材チップは蒸解液を浸透して蒸解しながら下降し、ブローダウンにより、下端からパルプが回収される。
【0005】
蒸発釜は一般に形状が円筒体で内壁が平滑であり、蒸発釜の上部、下部に反応又は蒸解を促進させるために、攪拌機等が備えられている。
【0006】
攪拌機等は攪拌を円滑に持続させるために、定期的又は不定期的に点検、修繕、更には清掃を行う必要がある。その場合、蒸発釜内に足場の仮設が必要である。
【0007】
しかるに、蒸発釜は、気密性が要求されることから、釜内への出入口が少なく、通常は、軸方向に設けた3〜4箇所程度のマンホールを利用してパイプ等の足場資材を挿入し、仮設足場を組んで点検、修繕、更には清掃を行っている。
【0008】
従って、狭い場所での足場資材の搬出入作業が繁雑であり、仮設足場を組むのに時間を要していた。通常は、蒸発釜の操業計画からみて、長く停止することができないために、点検等の実施日を年当たり2〜3回に分けて行う場合が生じていた。また、上部までの足場の仮設は高所作業であり、熟練度が要求される。
【0009】
【発明が解決しようとする課題】
前述した蒸発釜に示すように、一般に塔槽類は本体を気密に保ち、被流体を処理するために、内部の点検、修繕、清掃等を行うための仮設足場を組立・解体することが煩雑で時間を要する。そのために、塔槽類の操業に支障を生じ易い。また、上部までの足場の仮設は高所作業であり、熟練度が要求される。
【0010】
特開平8−218620号公報には、煙突等の塔状構造物を建設する際に使用される足場装置が開示されている。上記塔状構造物を建設する際には、躯体形成用に複数段の型枠を組み、その中にコンクリートを流し込んで凝固させた後、型枠を順次取り外し、一ブロックずつ順次積み重ねていく形で躯体形成作業が進められる。
【0011】
即ち、基礎面上に、マストを構成するマストブロックを積み重ねて行く躯体形成作業であり、同時に躯体形成作業を行うための足場装置が使用される。
【0012】
足場装置は、マストブロック昇降装置とマストブロック搬出入装置と、該昇降装置を用いて継足しにより立設されたマストの上端に固定した上部固定足場と、上部固定足場の下方に所要間隔を開けて、固定した下部固定足場と、上部固定足場と下部固定足場との間に昇降可能に配設された移動踊場とから構成されている。
【0013】
しかしながら、特開平8−218620号公報に開示された足場装置は、シリンダを利用してマストブロックを押し上げる装置であり、そのまま塔槽類の点検等の昇降足場に適用することは困難である。
【0014】
本発明は、上記のような問題点の解決を図ったものであり、高所作業を激減し、揺動しない、部品数を削減した軽量で、迅速に組立・解体して工期短縮ができる、作業用足場の組立・解体工法を提供することを目的とする。
【0015】
【課題を解決するための手段】
参考発明1は、塔槽類内に組立・解体される作業用昇降式足場(以下昇降式足場と云う)であって、前記昇降式足場は塔槽類内に仮設する作業床と、該作業床に着脱可能に設置する継足しマストからなる集合マストと、該集合マストの軸方向に昇降させる昇降ステージと、該昇降ステージを取付けそれをラックピニオン式機構で昇降させる駆動装置を各継足しマスト毎に備えた駆動フレームと、制御装置から構成されたことを特徴とする塔槽類内の昇降式足場である。
【0016】
参考発明2は、参考発明1において、集合マストの継足しマストの繋ぎが一定間隔をおいて内側に三角形状に枠組されたフレームで構成されたことを特徴とする。
【0017】
参考発明3は、参考発明1において、集合マストの継足しマストの繋ぎが一定間隔をおいて外側にリング状に枠組されたフレームで構成されたことを特徴とする。
【0018】
参考発明4は、参考発明1、2又は3において、集合マストの頂部に、昇降ステージで組立て・解体される固定ステージを設けたことを特徴とする。
【0019】
本発明によれば、上記した作業床と、該作業床に設置する継足しマストからなる集合マストと、該集合マストの軸方向に昇降させる昇降ステージと、該昇降ステージを取付けそれをラックピニオン式機構で昇降させる駆動装置を各継足しマスト毎に備えた駆動フレームと、制御装置から構成されているので、壁繋ぎができない塔槽類内であっても、昇降式足場の組立をすることができ、また、昇降ステージにより組立てた固定ステージを集合マストの頂部に取付ける組立をすることもでき、昇降式足場の組立てを完了し、昇降式足場による作業を終了した後、固定ステージを昇降ステージにより解体し、昇降ステージを下降させて継足しマストを順次取外して昇降式足場を解体することができる。
【0020】
請求項1の発明は、塔槽類内における作業用昇降式足場の組立・解体工法であって、前記塔槽類内に仮設した作業床に継足しマストを着脱可能に設置し、それらの継足しマストにラックピニオン式の昇降機構を有する駆動装置を備えた駆動フレームを取付け、該フレームにブラケットを介して昇降ステージを取付け、ラックピニオン式の昇降機構により昇降ステージを継足しマストの軸方向に上昇させ、継足しマストを順次継足しながら所定高さの集合マストを設置し、該昇降ステージにより組立てた固定ステージを集合マストの頂部に取付けて、昇降式足場の組立てを完了し、昇降式足場による作業を終了した後、固定ステージを昇降ステージにより解体し、昇降ステージを下降させて継足しマストを順次取外して昇降式足場を解体することを特徴とする塔槽類内の作業用昇降式足場の組立・解体工法である。
【0021】
以上のように、本発明によれば、壁繋ぎができない塔槽類内であっても、昇降式足場を昇降させながら、マストの継足し、取外しを行い、昇降式足場を迅速に組立・解体することができるので、高所作業を激減し、且つ全体の工期を短縮できる。
【0022】
【発明の実施の形態】
以下に、本発明の実施の形態を図によって詳述する。
【0023】
図1は本発明の一実施の形態を示す縦断面図であり、図2は図1による点線Pで示す要部拡大図、図3は図1によるA−A線矢視の下部作業床を示す一部切欠きを有する図、図4は継足しマスト単体によるマストベースへの取付け状態を示す側面図、図5は図4のD−D線矢視による横断面図、図6は本発明による継足しマストと駆動フレームの取付け状態を示す平面図、図7は図1によるB−B線矢視の昇降ステージを示す一部切欠きを有する図、図8は図1によるE−E線矢視の中継ぎを示す図、図9は図1によるC−C線矢視の上部全面床を示す一部切欠きを有する図である。
【0024】
本発明の作業用昇降式足場を二点鎖線で示す連続式蒸発釜(以下蒸発釜と云う)に用いた場合について詳述する。
【0025】
以下に本発明の特徴を順次詳述する。
【0026】
図1に示すように、蒸発釜1内に昇降式足場4が仮設されている。昇降式足場4は蒸発釜1の下部に設置した作業床5と、作業床5に設置された継足しマスト6からなる集合マスト16と、集合マスト16の軸方向に昇降させる昇降ステージ7と、昇降ステージ7をラックピニオン式で昇降させる駆動装置9aと制御装置9bを各継足しマスト毎に備えた駆動フレーム8から構成されている。
【0027】
昇降式足場4は、蒸発釜1を停止し、内部を水洗等により被溶液を流した後に仮設されたものである。
【0028】
作業床5、継足しマスト6、昇降ステージ7、駆動装置9aと制御装置9bを備えた駆動フレーム8はいずれもボルト・ナット等によって着脱可能に組立又は取付けられている。
【0029】
昇降式足場4を仮設するにあたり、作業床5が蒸発釜1の底部に設置される。
【0030】
蒸発釜1内に作業床5等を組立又は取付けるために、足場資材等が図2に示すように、従来の既設マンホール3aを改良した角型マンホール3bから搬入され、更には解体後に足場資材等がそこから搬出される。
【0031】
蒸発釜1の底部に設けられている下部の攪拌機2は停止状態にして、その空間を縫って主梁10が設けられる。主梁10はジャッキベース11によって支持され、更に主梁10の下側に交差させて補助梁12が設けられる。そして作業床5が主梁10の上に設置される。これらはいずれもボルト・ナット等によって着脱自在に組立てられる。
【0032】
作業床5は図3に示すように、鋼製足場による床面5aを形成し、床面5aの周端部にチェッカープレート14が取付けられる。
【0033】
また、床面5aには3箇所にマストベース受枠15aを設け、主梁10に固定された3個のマストベース13に、継足しマスト6がマストベース受枠15aを介して設置される。継足しマスト6は、後述する中継ぎ部材を取付けることができるように、軸芯を結ぶ線が正三角形になるように配置される。
【0034】
なお、符号15bは、開口部で既設の攪拌機2の一部が突き出ている。また、符号15cはハッチで床下点検時等の出入口である。
【0035】
継足しマスト6は図4,図5、図6に示すように、4本のマスト部材6aを補強材17で接続しながら間隔をおいて略四角形に配置し、マスト骨郭を形成している。継足しマスト6はラックピニオン式機構を構成するラック18を取付けている。
【0036】
継足しマスト6は下端にベース板20を取付け、ボルト22によりマストベース13に着脱可能に設置する。また、ガイド19により継足しマスト6の設置を容易にしている。
【0037】
継足しマスト6の上端には同様にベース板20を取付け、次の継足しマスト6の下端に取付けたベース板20との間でボルト22により継足しされる。
【0038】
これらの継足しマスト6の継足し操作は順次繰り返されて所定高さの継足しマスト6が形成される。所定高さまで形成された継足しマスト6は集合マスト16として取扱われる。
【0039】
昇降ステージ7は、図7に示すように、各継足しマスト6に昇降できるように取付けられた駆動フレーム8と、各駆動フレーム8に取付けられたブラケット25と、ブラケット25を介してドウナツ状に取付けられたステージ26から構成されている。ステージ26には安全性を保持するために手摺り23が取付けられている。昇降ステージ7の昇降は図6に示すように継足しマスト6を構成するラック18と駆動フレーム8のピニヨン27が噛合っており、駆動装置9aを駆動させて、駆動装置9aと一体的に接続されている制御装置9bで制御しながら、ラックピニオン式機構によって水平位置を保持しながら昇降する。
【0040】
この際、継足しマスト6間に、マスト中継ぎ部材24が設けられて、繋留めして偏りを生じないようにしている。そのために、駆動フレーム8の軸芯方向側が開放されている。開放割合は継足しマスト6の軸芯間を結ぶ線が二点鎖線で示すような正三角形21になるようにしている。
【0041】
昇降ステージ7は蒸発釜1内の点検、修繕、清掃等の作業を行う際の作業用足場であり、作業者とともに、作業に必要な機器、道具等が載置される。また、昇降ステージ7には継足しマスト6を組立てるのに必要な資材、資材の吊揚げ装置等が載置されており、継足しマスト6は昇降ステージ7内で組立てられる。制御装置9bも昇降ステージ7に設置される。
【0042】
従って、昇降ステージ7はそれらのものを載置して作業ができる広さを有する。しかし、不足のものは昇降を繰り返して簡単に補完することができるが、昇降ステージ7の広さにも限界があるので、例えば継足しマスト6は人手で搬出入できる長さとして1.5m程度のマスト部材6aを用いて継足される。
また、昇降ステージ7の周りには安全性を維持するために手摺り23が設置されている。
【0043】
集合マスト16は昇降ステージ7が継足しマスト6の軸方向に円滑に昇降できるように、所定の間隔をおいて、図8に示すように、継足しマスト6を繋留めするマスト中継ぎ部材24を設けている。中継ぎ部材24は昇降ステージ7の昇降に影響しないように、前記した二点鎖線で示す正三角形21内に入る大きさの正三角形状のフレームによる枠組みをしている。
【0044】
固定ステージを集合マスト16の頂部に設けることは、本発明の特徴の一つであり、ここでは、上部全面床28として、集合マスト16の頂部に設けている。上部全面床28は昇降ステージ7内で組立て・解体される。
【0045】
次に、図1〜図9により、蒸発釜内における作業用昇降式足場の組立・解体工法について詳述する。
【0046】
蒸発釜1内に足場資材等が角型マンホール3bを介して搬入され、作業床5が仮設される。作業床5は床面5aにマストベース受枠15aを設けて、マストベース13が固定される。
【0047】
継足しマスト6がマストベース13にボルト・ナット22によって着脱可能に設置される。それらの継足しマスト6にラックピニオン式の昇降機構を有する駆動装置9aと制御装置9bを備えた駆動フレーム8が取付けられ、駆動フレーム8にブラケット25を介して昇降ステージ7が取付けられる。
【0048】
昇降ステージ7はラックピニオン式の昇降機構を駆動させて、継足しマストの軸方向に上昇させ、継足しマスト6を順次継足しながら所定高さの集合マスト16を設置する。
【0049】
昇降ステージ7を作業床5まで下降させて、昇降ステージ7内で、上部全面床28の主な構造が組立てられる。
【0050】
図9に示すように、上部全面床28は骨格フレーム28aによって、後組み部分30と先組み部分31に大別される。後組み部分30には継足しマスト6からなる集合マスト16と中継ぎ部材24が配置されている。
【0051】
上部全面床28は下降した昇降ステージ7内で、先組み部分31が鋼製足場板32で床面を取付けられ、チェッカープレート33が取付けられる。
【0052】
その後、上部全面床28は昇降ステージ7の上昇により集合マスト16の頂部を超える位置まで運ばれる。上部全面床28は固定用フレーム34を移動させて、各集合マスト16の上端に位置される。これによって、上部全面床28は昇降ステージ7から独立して、集合マスト16の上に固定される。
【0053】
その後、後組み部分30に設けたハッチ35を開けて、そこから鋼製足場板29を運び、後組み部分30の床面を形成する。これによって、昇降式足場4の組立てが完了する。
【0054】
昇降式足場4を用いて点検等の作業を終了した後、組立の手順と逆の手順によって、上部全面床28を昇降ステージ7内で解体し、上部全面床28を解体した後、昇降ステージ7を下降させて継足しマスト6を順次取外して昇降式足場4を解体する。
【0055】
以上のように、上記した実施の形態によれば、壁繋ぎのできない蒸発釜1でも、簡単な構造の中継ぎ部材24を用いて、継足しマスト6間を連結して、昇降ステージ7の偏りを皆無にして、系外で用意された部材を釜内に搬入して、昇降式足場4の組立・解体作業を迅速、簡単且つ安全に行うことができる。
【0056】
上記昇降式足場4によれば、蒸発釜1においては、昇降式足場4の組立・解体作業が各一日以内で行うことができるので、蒸発釜1の操業に支障を生じない。また、上部までの足場の仮設は高所作業を激減し、熟練度を必要としない。
【0057】
上記実施の形態では、蒸発釜の場合について詳述したが、他の塔槽類内で昇降式足場を組立・解体する場合も同様の効果が得られる。
【0058】
図10は本発明による昇降ステージの他の例を示す横断面図である。
【0059】
図7と共通する箇所は同じ符号を付けて、説明の一部を省略した。
【0060】
昇降ステージ36の取付け構造に特徴を有する。
【0061】
集合マスト16を構成する継足しマスト6を繋ぐために、継足しマスト6の外側にリングフレーム37を設け、各継足しマスト6の外側に駆動フレーム8の開口部を設けてそこから中継ぎ部材38をリングフレーム37に接続させている。
【0062】
従って駆動フレーム8から軸芯方向にブラケット39を設け、ブラケット39の先端部にリング状のステージフレーム40を設け、ステージフレーム40を介して継足しマスト6と継足すマスト6の間にステージ40a、40bを形成している。
【0063】
昇降ステージ36は外側にリングフレーム37を設けることによって、径の小さい塔槽類の昇降式足場の組立、解体に適している。効果については、前述した昇降ステージ4と同様の効果を有する。
【0064】
【発明の効果】
以上のように、本発明は塔槽類内に仮設する作業床と、該作業床に着脱可能に設置する継足しマストからなる集合マストと、該集合マストの軸方向に昇降させる昇降ステージと、該昇降ステージを取付けそれをラックピニオン式機構で昇降させる駆動装置を各継足しマスト毎に備えた駆動フレームと、制御装置から構成した簡単な昇降式足場構造によって、昇降式足場を昇降させながら、マストの継足し、取外しを行い、壁繋ぎのできない場合でも、昇降式足場を迅速に組立・解体することができ、高所作業を激減し、且つ全体の工期を短縮できる。
【図面の簡単な説明】
【図1】本発明の一実施の形態を示す縦断面図である。
【図2】図1による点線Pで示す要部拡大図である。
【図3】図1によるA−A線矢視の下部作業床を示す一部切欠きを有する図である。
【図4】継足しマスト単体によるマストベースへの取付け状態を示す側面図である。
【図5】図4のD−D線矢視による横断面図である。
【図6】本発明による継足しマストと駆動フレームの取付け状態を示す平面図である。
【図7】図1によるB−B線矢視の昇降ステージを示す一部切欠きを有する図である。
【図8】図1によるE−E線矢視の中継ぎを示す図である。
【図9】図1によるC−C線矢視の上部全面床を示す一部切欠きを有する図である。
【図10】本発明による他の実施の形態を示す一部切欠きを有する横断面図である。
【符号の説明】
1 蒸発釜
2 攪拌機等
3a マンホール
3b 角型マンホール
4 昇降式足場
5 作業床
5 床面
6 継足しマスト
6a マスト部材
7 昇降ステージ
8 駆動フレーム
9a 駆動装置
9b 制御装置
10 主梁
11 ジャッキベース
12 補助梁
13 マストベース
14、33 チェッカープレート
15a マストベース受枠
15b 開口部
15c ハッチ
16 集合マスト
17 補強材
18 ラック
19 ガイド
20 ベース板
21 正三角形
22 ボルト
23 手摺り
24 マスト中継ぎ部材
25 ブラケット
26 ステージ
27 ピニヨン
28 上部全面床
28a 骨格フレーム
29、32 鋼製足場板
30 後組み部分
31 先組み部分
34 固定用フレーム
35 ハッチ
36 昇降ステージ(リングフレーム型)
37 リングフレーム
38 中継ぎ部材(リングフレーム型)
39 ブラケット(リングフレーム型)
40 ステージフレーム
40a、40b ステージ[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for assembling / disassembling a working lifting scaffold used when checking, repairing, cleaning, and the like in tower tanks.
[0002]
[Prior art]
Tower tanks such as chimneys, evaporators and tanks (hereinafter referred to as tower tanks) are periodically and irregularly stopped for internal inspection, repair, cleaning, etc. After stopping the operation of the towers and tanks and washing the interior with water, assemble a scaffolding inside and inspect, repair, and clean the interior.
[0003]
In general, tower tanks keep the main body airtight, process the fluid, and discharge the system from the top.
[0004]
For example, a continuous evaporator used for cooking kraft pulp is a tower having a height of about 50 m. The above cooking is carried out for several hours at around 170 degrees by adding a cooking solution to wood chips in a pressure-resistant evaporation kettle and blowing heating steam into the upper, middle and lower parts. The wood chip descends while permeating the cooking liquor, and the pulp is recovered from the lower end by blowdown.
[0005]
The evaporating kettle is generally cylindrical in shape and has a smooth inner wall, and a stirring machine or the like is provided at the upper and lower parts of the evaporating kettle to promote reaction or cooking.
[0006]
A stirrer or the like needs to be inspected, repaired, and cleaned regularly or irregularly in order to keep stirring smoothly. In that case, a temporary scaffold is required in the evaporation pot.
[0007]
However, since the evaporating kettle is required to be airtight, there are few entrances into the kettle, and usually, scaffolding materials such as pipes are inserted using about 3 to 4 manholes provided in the axial direction. In addition, the temporary scaffolding is inspected, repaired, and cleaned.
[0008]
Therefore, the work of loading and unloading scaffolding materials in a narrow place is complicated, and it takes time to build a temporary scaffold. Usually, in view of the operation plan of the evaporating kettle, since it cannot be stopped for a long time, there are cases where the inspection date is divided into two or three times per year. Moreover, the temporary construction of the scaffolding up to the upper part is a work at a high place, and skill is required.
[0009]
[Problems to be solved by the invention]
As shown in the evaporating kettle described above, it is generally complicated to assemble and dismantle temporary scaffolds for internal inspection, repair, cleaning, etc. in order to keep the main body airtight and to treat the fluid. Takes time. Therefore, it is easy to cause trouble in the operation of tower tanks. Moreover, the temporary construction of the scaffolding up to the upper part is a work at a high place, and skill is required.
[0010]
Japanese Patent Application Laid-Open No. 8-218620 discloses a scaffold device used when building a tower-like structure such as a chimney. When constructing the above tower-like structure, form a multi-stage formwork to form a frame, cast concrete into it and solidify it, then remove the formwork one after another and stack one block at a time. The building formation work proceeds.
[0011]
That is, a scaffold forming operation for stacking mast blocks constituting a mast on a basic surface, and simultaneously using a scaffold device for performing the chassis forming operation.
[0012]
The scaffold device includes a mast block lifting device, a mast block loading / unloading device, an upper fixed scaffold fixed to the upper end of a mast erected by using the lifting device, and a predetermined interval below the upper fixed scaffold. The fixed lower fixed scaffold, and the movable landing that is arranged to be movable up and down between the upper fixed scaffold and the lower fixed scaffold.
[0013]
However, the scaffold device disclosed in Japanese Patent Application Laid-Open No. 8-218620 is a device that pushes up the mast block using a cylinder, and it is difficult to apply the scaffold device as it is to a lifting scaffold such as inspection of tower tanks.
[0014]
The present invention is intended to solve the above-mentioned problems, drastically reduces work at height, does not swing, is lightweight with a reduced number of parts, and can be quickly assembled and disassembled to shorten the work period. The purpose is to provide a method for assembling and dismantling work scaffolds.
[0015]
[Means for Solving the Problems]
[0016]
The
[0017]
The reference invention 3 is characterized in that, in the
[0018]
The reference invention 4 is characterized in that, in the
[0019]
According to the present invention, the above-described work floor, a collective mast composed of an additional mast installed on the work floor, a lift stage that moves up and down in the axial direction of the collective mast, and the lift stage is attached to the rack and pinion type Because it is composed of a drive frame that is equipped with a drive device that moves up and down with a mechanism for each mast, and a control device, it is possible to assemble a lifting scaffold even in tower tanks that can not be connected to the wall It is also possible to assemble the fixed stage assembled by the lifting stage to the top of the collective mast.After the assembly of the lifting scaffold is completed and the work by the lifting scaffold is completed, the fixed stage is moved by the lifting stage. It can be dismantled, the elevating stage can be lowered and added, and the mast can be removed sequentially to dismantle the elevating scaffold.
[0020]
The invention of
[0021]
As described above, according to the present invention, even in a tower tank that cannot be connected to the wall, the mast is added and removed while raising and lowering the lifting platform, and the lifting platform is quickly assembled and disassembled. Therefore, it is possible to drastically reduce the work at high places and shorten the overall construction period.
[0022]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described in detail below with reference to the drawings.
[0023]
FIG. 1 is a longitudinal sectional view showing an embodiment of the present invention, FIG. 2 is an enlarged view of a main part indicated by a dotted line P in FIG. 1, and FIG. 3 is a lower work floor as viewed in the direction of arrows AA in FIG. FIG. 4 is a side view showing a state in which the additional mast is attached to the mast base, FIG. 5 is a cross-sectional view taken along line DD of FIG. 4, and FIG. 7 is a plan view showing a mounting state of the additional mast and the drive frame according to FIG. 7, FIG. 7 is a view having a partially cut-out showing the lifting stage as viewed from the line B-B in FIG. 1, and FIG. 8 is a line EE in FIG. FIG. 9 is a view having a partially cutout showing the upper entire floor of the CC line arrow view according to FIG. 1.
[0024]
The case where the working lifting scaffold of the present invention is used in a continuous evaporation pot (hereinafter referred to as an evaporation pot) indicated by a two-dot chain line will be described in detail.
[0025]
The features of the present invention will be described in detail below.
[0026]
As shown in FIG. 1, an elevating scaffold 4 is temporarily installed in the
[0027]
The elevating scaffold 4 is temporarily installed after the evaporating
[0028]
The
[0029]
In temporarily installing the elevating scaffold 4, the
[0030]
In order to assemble or attach the
[0031]
The
[0032]
As shown in FIG. 3, the
[0033]
Further, mast
[0034]
In addition, the code |
[0035]
4, 5, and 6, the
[0036]
The
[0037]
Similarly, a
[0038]
These addition operations of the
[0039]
As shown in FIG. 7, the elevating
[0040]
At this time, a mast
[0041]
The elevating
[0042]
Therefore, the elevating
Further, a
[0043]
As shown in FIG. 8, the
[0044]
Providing the fixed stage on the top of the
[0045]
Next, with reference to FIGS. 1 to 9, the assembly / disassembly method of the working lifting scaffold in the evaporation pot will be described in detail.
[0046]
Scaffolding materials and the like are carried into the evaporating
[0047]
The
[0048]
The elevating
[0049]
The elevating
[0050]
As shown in FIG. 9, the upper
[0051]
The upper
[0052]
Thereafter, the upper
[0053]
Thereafter, the
[0054]
After completion of the inspection and the like using the lifting / lowering scaffold 4, the upper
[0055]
As described above, according to the embodiment described above, even in the evaporating
[0056]
According to the lifting / lowering scaffold 4, in the evaporating
[0057]
In the above embodiment, the case of the evaporating kettle has been described in detail, but the same effect can be obtained when the lifting and lowering scaffold is assembled and disassembled in other tower tanks.
[0058]
FIG. 10 is a cross-sectional view showing another example of the lifting stage according to the present invention.
[0059]
Portions common to those in FIG. 7 are denoted by the same reference numerals, and a part of the description is omitted.
[0060]
The mounting structure of the lifting / lowering
[0061]
In order to connect the
[0062]
Accordingly, the
[0063]
The elevating
[0064]
【The invention's effect】
As described above, the present invention is a work floor temporarily installed in the towers, a collective mast composed of an additional mast that is detachably installed on the work floor, a lifting stage that moves up and down in the axial direction of the collective mast, While installing the lifting stage and driving it up and down with a rack and pinion mechanism, the driving frame provided for each mast and a simple lifting type scaffolding structure composed of a control unit, while raising and lowering the lifting type scaffold, Even when the mast is added and removed, and the walls cannot be connected, the lifting and lowering scaffold can be quickly assembled and disassembled, and the work at a high place can be drastically reduced and the entire construction period can be shortened.
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional view showing an embodiment of the present invention.
FIG. 2 is an enlarged view of a main part indicated by a dotted line P in FIG.
FIG. 3 is a view having a partially cutaway showing a lower work floor as viewed in the direction of arrows AA in FIG. 1;
FIG. 4 is a side view showing a state of attachment to a mast base by an additional mast alone.
5 is a cross-sectional view taken along line DD in FIG.
FIG. 6 is a plan view showing an attachment state of an extension mast and a drive frame according to the present invention.
7 is a view having a partially cutaway showing the lifting stage as viewed in the direction of arrows BB according to FIG. 1;
FIG. 8 is a view showing a joint as viewed in the direction of arrows EE according to FIG. 1;
FIG. 9 is a view having a partial cut-out showing the entire upper floor of the line CC in FIG. 1;
FIG. 10 is a cross-sectional view with a partial cutaway showing another embodiment according to the present invention.
[Explanation of symbols]
DESCRIPTION OF
37
39 Bracket (Ring frame type)
40
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001287694A JP3895143B2 (en) | 2001-09-20 | 2001-09-20 | Assembly and dismantling method for work lifting scaffolds in tower tanks |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001287694A JP3895143B2 (en) | 2001-09-20 | 2001-09-20 | Assembly and dismantling method for work lifting scaffolds in tower tanks |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003097045A JP2003097045A (en) | 2003-04-03 |
JP3895143B2 true JP3895143B2 (en) | 2007-03-22 |
Family
ID=19110463
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001287694A Expired - Lifetime JP3895143B2 (en) | 2001-09-20 | 2001-09-20 | Assembly and dismantling method for work lifting scaffolds in tower tanks |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3895143B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2428230A (en) * | 2005-07-08 | 2007-01-24 | Michael E Kavanagh | Surveyor's elevator and staging |
JP5654398B2 (en) * | 2011-03-25 | 2015-01-14 | 太平電業株式会社 | Chimney dismantling method |
JP5635163B1 (en) * | 2013-07-29 | 2014-12-03 | 太平電業株式会社 | How to build a scaffold in a boiler |
-
2001
- 2001-09-20 JP JP2001287694A patent/JP3895143B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2003097045A (en) | 2003-04-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH1018589A (en) | Construction device for concrete structure | |
JP3895143B2 (en) | Assembly and dismantling method for work lifting scaffolds in tower tanks | |
JP2007205043A (en) | Construction method and dismantling method of scaffolding for high-rise building | |
JP4952014B2 (en) | Building demolition method and maintenance method, curing scaffold descent device | |
JP3028071B2 (en) | Top removal method and scaffold for removal work of ultra-high tubular structure | |
CN210508326U (en) | Liftable well operation platform | |
KR102061110B1 (en) | Method and module for the installation of equipment on a ship | |
JPH09195497A (en) | Elevatable scaffold | |
CN113585087B (en) | A easily install and easily remove template supporting platform for tie beam construction | |
JPH11303421A (en) | Demolition method for steel tower type high-rise chimney | |
JPH0886037A (en) | Plant building, constructing method therefor, and structure for its construction | |
JP2718188B2 (en) | Building exterior wall mounting method | |
JPH0445628B2 (en) | ||
JPH10184037A (en) | Construction method of water-containing type gas holder | |
JPH08218620A (en) | Scaffold device for constructing towerlike structure | |
US4272465A (en) | Method for multi-storied concrete construction and apparatus therefor | |
RU19033U1 (en) | SELF-LIFTING WORK AREA | |
JPH1018595A (en) | Tower-shaped carrying device | |
JPH0445629B2 (en) | ||
KR960013586B1 (en) | Method for constructing huge modules, and a module fabricated by the method | |
CN113622317A (en) | Construction method of tie beam | |
JP2016130439A (en) | Vent assembly device, and assembly method for connected body of vents | |
JP2000064598A (en) | Scaffolding device for constructing tower-shaped structure | |
CN115217318A (en) | Material lifting device for installing and detaching floor scaffold of plate buckle and construction method | |
CN115215253A (en) | Material lifting device for installing and detaching disc buckle supporting frame and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040409 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060309 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060314 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060428 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20060808 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060928 |
|
A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20061030 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061121 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061213 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3895143 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101222 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101222 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121222 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131222 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |