JP3797733B2 - Construction girder and electric switch rail direct connection device - Google Patents
Construction girder and electric switch rail direct connection device Download PDFInfo
- Publication number
- JP3797733B2 JP3797733B2 JP00229497A JP229497A JP3797733B2 JP 3797733 B2 JP3797733 B2 JP 3797733B2 JP 00229497 A JP00229497 A JP 00229497A JP 229497 A JP229497 A JP 229497A JP 3797733 B2 JP3797733 B2 JP 3797733B2
- Authority
- JP
- Japan
- Prior art keywords
- girder
- electric switch
- construction
- cross beam
- cross
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Description
【0001】
【発明の属する技術分野】
本発明は、分岐器を有する既設橋を取り壊して新設橋を構築する際に用いる工事桁、及びこの工事桁の主桁の上面に搭載される電気転てつ機と枕木上に敷設されるレールとを直結する電気転てつ機レール直結装置に関する。
【0002】
【従来の技術、及び、発明が解決しようとする課題】
一般に、工事桁は、営業線で列車を走行させながら線路下を掘削し、構造物を構築する場合の軌道の仮受けに広く利用されている。しかし、用いる工事桁がその現場の状況に適しているかどうかが、その工事の難易に大きく影響する。従って、工事桁はその工事に適合したものを選ぶと同時にその機能が十分発揮できるように工夫して設計されなければならない。
【0003】
従来、図10(a)〜(c)に示すように、分岐器や転てつ装置を有する既設橋42を取り壊して新設橋46を構築する際に用いる工事桁としては、下路プレートガーダ形式の工事桁110が知られている。
この工事桁110は、横断面(K−K断面)を図10(c)に示すように、1対のH鋼主桁111、111と、その主桁111、111間に入り込むようにして支持された複数のH鋼横桁120と、その横桁120上に載せられたプレート125とを備えている。このプレート125の裏面には強度アップを目的として複数のリブ126が設けられている。
【0004】
しかしながら、工事現場によっては既設橋42の上面UからレールレベルRLまでの高さが十分でない(例えば50〜60cm)場合があり、この場合には上記工事桁110では、横桁120の最下端からレールレベルRLまでの間隔dが[横桁の高さ]+[枕木の高さ]+[レールの高さ]となるため、横桁120の最下端と既設橋42の上面Uとの間隔が著しく狭くなる。このため、既設橋42の取り壊し作業を行ったり、新設橋46の構築作業を行ったりするスペースが十分でなく、作業が困難になるという問題があった。
【0005】
また、上記工事桁110では、分岐器や転てつ装置を備える必要があるため高い剛性が要求されるが、既設橋42の上面UからレールレベルRLまでの高さが低い場合には横桁120の高さを十分高くできないため横桁120一本あたりの剛性が十分高くすることができない。このため、要求される剛性を満足させるには、枕木1本に対して例えば2本以上の横桁を設けなければならず(即ち枕木間隔以上に横桁を設置しなければならず)、施工作業が煩雑になる等の問題があった。
【0006】
一方、分岐器や転てつ装置を有する既設橋を取り壊して新設橋を構築する期間中、転てつ装置を構成する電気転てつ機161を作動させる必要があるが、この電気転てつ機161は一般に営業線では枕木141の上に設置されるため、工事期間中もこれと同様に枕木141の上に設置している(図10(c)参照)。
【0007】
また、電気転てつ機161は、図11に示すように、通常、ポイントの転換を確実に行うために、列車の振動等により電気転てつ機161とレールRBとの関係がずれてしまうことのないよう、両者を2本の直線棒状のゲージタイ175、175(「電気転てつ機レール直結装置」ともいう、なお図11では一方のみ図示した)により直結されている。
【0008】
しかしながら、電気転てつ機161を枕木141の上に設置するには、横桁120の幅方向の長さを長くする必要があるため、結果として主桁111、111同士の間隔が広くなる。しかし、主桁111、111同士の間隔を広く設定できない場合(例えば隣合う線路同士の間隔が狭い場合)もあり、この場合には枕木141の上に電気転てつ機161を設置できないという問題があった。
【0009】
本発明は上記課題に鑑みなされたものであり、その目的は、既設橋の上面からレールレベルまでの高さが低い場合であっても十分な作業スペースを確保でき、しかも分岐器や転てつ装置を保持するのに要求される高剛性に十分応えることのできる工事桁を提供することにある。
【0010】
また、別の目的は、隣合う線路同士の間隔が狭い場合でも電気転てつ機を搭載することのできる工事桁を提供することにある。
更に、別の目的は、本発明の工事桁の主桁の上面に搭載される電気転てつ機と枕木上に敷設されるレールとを直結するのに適した電気転てつ機レール直結装置を提供することにある。
【0011】
【課題を解決するための手段及び発明の効果】
上記課題を解決するため、請求項1記載の発明は、分岐器や転てつ装置を有する既設橋を取り壊して新設橋を構築する際に用いる工事桁であって、各枕木を抱き込んだ状態で保持する複数の横桁と、前記横桁を前記既設橋の上面から持ち上げた状態で前記横桁の両端を支持する1対の主桁とを備え、前記主桁はその上面に電気転てつ機を搭載可能な搭載部を備え、該搭載部は他の箇所に比べて高さが低く幅が広い形状に形成されていることを特徴とする。
【0012】
分岐器とは1つの線路を2つの線路に振り分ける線路設備のことをいい、トングレールなどを含む。また、転てつ装置とは分岐器を動かす装置をいい、モータ等を含む電気転てつ機や、電気転てつ機から発生する転換力をトングレールに伝えてポイントを転換するスイッチアジャスタなどを含む。
【0013】
かかる工事桁では、レールは横桁に抱き込まれた枕木に敷設されることになる。ここで、横桁の最下端からレールレベル(レールは枕木に敷設される)までの間隔は、横桁が枕木を抱き込んでいるため、ほぼ[枕木の高さ]+[レールの高さ]となる。即ち、従来の下路プレートガーダ形式の工事桁のように横桁の上に枕木を載せてその枕木にレールを敷設した場合に比べて、[横桁の高さ]分だけ小さくなる。また、主桁は横桁を既設橋の上面から持ち上げた状態で支持している。この結果、既設橋の上面から横桁の最下端までの間隔は、従来に比べて[横桁の高さ]分だけ広くなる。
【0014】
また、分岐器や転てつ装置によるポイント転換が確実に行われる必要があることから、本発明の工事桁は高い剛性が要求される。この点に関し、従来の下路プレートガーダ形式の工事桁では、既設橋の上面からレールレベルまでの高さが低い場合には横桁の高さを十分高くすることができないため、要求される剛性を満足するには例えば枕木1本あたり2本以上の横桁を設けなければならず、施工作業が煩雑になる等の問題があった。これに対して、本発明の工事桁は抱き込み形式であるため、枕木1本あたり1本の横桁を設ければよく、施工作業が容易になる。
【0015】
以上述べたように、本発明の工事桁によれば、既設橋の上面から横桁の最下端までの間隔が広くなった分、既設橋の取り壊し作業や新設橋の構築作業を容易に行うことができるという効果が得られる。また、分岐器等を有する工事桁に要求される高剛性につき従来の下路プレートガーダ形式に比して容易な施工で実現できるという効果も得られる。
【0016】
かかる工事桁では、ポイントの転換を行うための電気転てつ機を搭載する必要がある。仮に電気転てつ機を横桁の上あるいは横桁に保持される枕木の上に搭載する場合には、横桁あるいは枕木には電気転てつ機を搭載するためのスペースが別途必要となるため、横桁あるいは枕木が長くなる。すると主桁同士の間隔が広がってしまうので隣合う線路同士の間隔が狭いときには実使用できないという問題がある。この点に関し、主桁の上面をスペース的に有効に利用するとの観点から本発明の工事桁ではこの主桁の上面に電気転てつ機を搭載したものであり、これにより上記問題は解消されるという効果が得られる。また、搭載部は他の箇所に比べて高さが低いため、電気転てつ機を搭載したとしても列車の建築限界(列車が通過するために確保された領域)を侵すおそれはない。更に、この搭載部は他の箇所に比べて幅が広いため、電気転てつ機を搭載するに十分な剛性を実現できる。
【0017】
請求項2記載の発明は、請求項1記載の工事桁であって、前記横桁のうち、前記搭載部に搭載された前記電気転てつ機を構成する部材と干渉する位置にある横桁は、枕木の略下半分のみを保持する形状であることを特徴とする。
【0018】
電気転てつ機を構成する部材のうち横桁と干渉するおそれのあるものとしては、例えば、スイッチアジャスタの調整具(スイッチアジャスタによりポイントが転換されたとき、トングレールが基本レールに密着するように調整するための調整具)、ロック機構の調整具(ポイント転換後に転てつ装置を鎖錠するためのロック機構の鎖錠位置の狂いを調整するための調整具)、ゲージタイの調整具(電気転てつ機とレールとの位置のずれを防止するためのゲージタイを調整するための調整具)等がある。
【0019】
電気転てつ機を構成する部材と干渉する位置にある横桁につき、枕木の両側面の全面及び底面を覆う形状とした場合には、例えばナットなどの調整具をスパナなどの調整用治具で調整しようとしても、横桁の側面部分が邪魔になって調整できないおそれがあるが、本発明ではこのような横桁は枕木の略下半分のみを保持する形状としたため、調整用具での調整の邪魔になることはなくスムーズに調整できるという効果が得られる。
【0020】
請求項3記載の発明は、請求項1または請求項2に記載の工事桁の前記主桁の上面に搭載される電気転てつ機と前記枕木上に敷設されるレールとを直結する電気転てつ機レール直結装置であって、前記横桁同士の間にて該横桁と略平行に延び、上段と下段を有するクランク状に形成されたゲージタイとして構成され、該ゲージタイの上段は前記主桁上面に搭載された電気転てつ機に固定され、下段は前記枕木上に敷設されたレールに固定されていることを特徴とする。
【0021】
かかる電気転てつ機レール直結装置では、電気転てつ機は主桁の上面に搭載されているため、電気転てつ機の下部とレールの下部とを直線的に結合しようとしても電気転てつ機の下方に主桁が存在していることから困難である。
そこで、本発明ではゲージタイをクランク状とし、この主桁の上面に搭載された電気転てつ機をゲージタイの上段で固定し、枕木上に敷設されたレールをゲージタイの下段で固定することで、電気転てつ機の下方に主桁が存在しても容易に電気転てつ機とレールとを直結できるようにした。
【0022】
【発明の実施の形態】
以下に、本発明の好適な実施例を図面に基づいて説明する。尚、本発明の実施の形態は、下記の実施例に何ら限定されるものではなく、本発明の技術的範囲に属する限り種々の形態を採り得ることはいうまでもない。
【0023】
図1は本実施例の工事桁の平面図である。本実施例の工事桁10は、図1に示すように、1対の主桁11、11と、この主桁11、11間に架け渡される横桁(通常部用横桁20及び搭載部用横桁30)とを備えている。
図2は主桁の説明図であり、(a)は平面図、(b)は正面図、(c)はA−A断面図である。主桁11は、いわゆるH鋼であり、上面11a、底面11b及び縦板11cを備えている。また、主桁11には、電気転てつ機を搭載しない通常部12と、電気転てつ機を搭載する搭載部13が設けられている。
【0024】
通常部12は高さ(底面11bから上面11aまで)がH1、幅がW1であるのに対して、搭載部13は高さがH2(<H1)、幅がW2(>W1)であり、通常部12から搭載部13に至る部分は、上面11aの高さが徐々に低くなるようにまた幅が徐々に広くなるように変化していく異形断面となっている。また、通常部12の高さは図3(b)に示すように主桁11が建築限界(列車が通過するために確保された領域)を侵すことのないように設定され、搭載部13の高さは図4(b)及び図5(b)に示すように電気転てつ機が搭載されたときに電気転てつ機が建築限界を侵すことのないように設定されている。
【0025】
また、搭載部13のうち電気転てつ機のロック機構である鎖錠かん71を配置する箇所には切欠13aが設けられている。主桁11のうち、長手方向に延びる溝15には横桁の端部を受けるためのプレート状の受け台16とその受け台16を支持するための複数の受け台リブ17とが設けられている。尚、受け台16は、搭載部13においては通常部12よりも幅が広くなるように形成され、また後述する第2横桁36を受ける箇所(本実施例では3カ所)には四角状の切欠16aが形成されている。
【0026】
横桁には図1に示すように通常部用横桁20と搭載部用横桁30があり、更に搭載部用横桁30には第1横桁31と第2横桁36の2種類が存在する。
図3は通常部用横桁の説明図であり、(a)は平面図、(b)はB−B断面図、(c)はC−C断面図である。通常部用横桁20は、1対の主桁11、11の通常部12、12を架け渡すための横桁であり、底面20a及び両側面20b、20bからなる断面略凹状に形成され、枕木41を抱き込んだ状態で保持可能な凹部22を有している。
【0027】
この通常部用横桁20の両側面20b、20bには長手方向に沿って補強用リブ23、23が設けられている。このため剛性が高く撓みが少ない構造となっている。また、通常部用横桁20の各端部は主桁11に設けられた受け台16上に例えばボルトナット等の締結具により固着されている。このため通常部用横桁20は主桁11の底面11bから持ち上げられた状態で支持されている。
【0028】
図4は第1横桁の説明図であり、(a)は平面図、(b)はD−D断面図、(c)はE−E断面図である。搭載部用横桁30のうち第1横桁31は、搭載部13に搭載された電気転てつ機を構成する部材(例えば後述のスイッチアジャスタ66の調整ナット69や鎖錠かん71の調整金具73やゲージタイ75の調整ナット76など)とは干渉しない位置を架け渡すための横桁である。
【0029】
この第1横桁31は、底面31a及び両側面31b、31bからなる断面略凹状に形成され、枕木41を抱き込んだ状態で保持可能な凹部32を有している。また、第1横桁31の両側面31b、31bには通常部用横桁20と同様、補強用リブ33、33が設けられている。
【0030】
この第1横桁31の各端部は主桁11の上面11aと受け台16との隙間に入り込めるよう高さが低く形成され、主桁11に設けられた受け台16上に例えばボルトナット等の締結具により固着されている。このため第1横桁31は主桁11の底面11bから持ち上げられた状態で支持されている。
【0031】
図5は第2横桁の説明図であり、(a)は平面図、(b)はF−F断面図、(c)はG−G断面図である。第2横桁36は、主桁11の搭載部13に搭載された電気転てつ機を構成する部材(例示は既述ずみ)と干渉する位置(図7に示す3カ所)を架け渡すための横桁である。
【0032】
この第2横桁36は、底面36a及び両側面36b、36bからなる断面略H状に形成された部材であり、枕木41を抱き込んだ状態で保持可能な凹部37を有している。この第2横桁36は両側面36b、36bが底面36aから更に下方に延びる形状を採用したのは剛性を高くするためである。
【0033】
凹部37は通常部用横桁20や第1横桁31に比べて浅いため、枕木41のうち略下半分だけを保持しうる。なお、この第2横桁36には補強リブを設けていない。これは、後述する電気転てつ機を構成する部材と補強用リブが干渉するのを避けるためであるが、特にこれらの部材と干渉しなければ補強用リブを設けてもよい。
【0034】
この第2横桁36の各端部は断面略H状ではなく断面略凹状に形成され、主桁11の上面11aと受け台16との隙間に入り込めるように形成されている。この第2横桁36の各端部のうち両側面36b、36bが底面36aから下方に延びている部分は、受け台16に設けた切欠16a内に配置されている。このようにして受け台16上に載置された第2横桁36の各端部は、例えばボルトナット等の締結具により受け台16に固着されている。このため第2横桁36は主桁11の底面11bから持ち上げられた状態で支持されている。
【0035】
次に、この工事桁10を用いて、分岐器及び転てつ装置を有する既設橋を取り壊して新設橋を構築する際の工法を図6に基づいて概説する。図6は工事の概略工程図である。まず、図6(a)に示すように、既設の架道橋42の両側に仮橋台43、43を設置し、工事桁10が既設の架道橋42の上方を架け渡すように仮橋台43、43上に架設する。そして、図6(b)に示すように、既設の架道橋42を取り壊しつつ、その取り壊した範囲に仮受支柱44を設け、橋台45と仮受支柱44との間に新設の架道橋46を構築するためのH鋼埋込桁を架設する、という作業サイクルを繰り返す。そして、新設の架道橋46が完成した後、バラストを新設の架道橋46上に撒く。このとき、工事桁10において隣合う横桁と横桁の間は空いているため、工事桁10の上から新設の架道橋46にバラストを撒くことができ、作業性がよい。これに対して、従来の下路プレートガーダ形式(図10参照)では横桁の上をプレートが覆っているため、バラストを撒く作業を容易に行うことができない。その後、残っている仮受支柱44等を撤去し、工事桁10を撤去して営業線を元通りに戻し、全作業を終了する。
【0036】
次に、工事期間中における工事桁10の役割について説明する。
仮橋台43、43に架設した工事桁10につき、横桁(通常部用横桁20、第1横桁31、第2横桁36)の凹部22、32、37にそれぞれ枕木41を保持させ、これら枕木41上にレールRを敷設する(図3(b)、図4(b)、図5(b)参照)。このとき、各横桁は枕木41を抱き込むように保持するため、各横桁の最下端からレールレベル(レールRの上面)までの間隔はほぼ[枕木41の高さ]+[レールRの高さ]となる。
【0037】
このため、図10に示す従来の下路プレートガーダ形式の工事桁のように横桁の上に枕木を載せてその枕木にレールを敷設した場合に比べて、[横桁の高さ]分だけ小さくなる。
したがって、既設の架道橋42の上面からレールレベルまでの距離が50〜60cmと狭い場合であっても、本実施例の工事桁10によれば既設の架道橋42の上面と各横桁の底面との間で新設の架道橋46を構築するのに十分なスペースを確保することができる。この結果、既設橋の取り壊し作業やこの部分にH鋼埋込桁を施工する作業を容易に行うことができるという効果が得られる。
【0038】
尚、第2横桁36は両側面36b、36bが底面36aの下方に延びる形状であるため既設橋42の上面との間隔が狭くなっているが、第2横桁36は数カ所(本実施例では3カ所)にのみ用いること、また底面36aと既設橋42の上面との間隔は広いためこのスペースを利用できること、等から特に問題になることはない。但し、作業性をより向上させる観点から、両側面36b、36bのうち下方に延びる部分をカットしてもよい。
【0039】
図7は工事期間中の分岐器先端付近の工事桁の平面図である。この図7に示すように枕木41上にはトングレール51や基本レールRB等を含む分岐器50が設置され、主桁11の搭載部13には転てつ装置60が取り付けられている。
ここで、分岐器50及び転てつ装置60によるポイント転換が確実に行われる必要があることから、工事桁10には高い剛性が要求される。この点に関し、従来の下路プレートガーダ形式の工事桁では、この要求に応えるためには枕木1本あたり例えば2本以上の横桁を設けなければならず、施工作業が煩雑になる等の問題があったが、本実施例の工事桁10は抱き込み形式であるため、枕木1本あたり1本の横桁を設ければよく、施工作業が容易になるという効果が得られる。
【0040】
ここで、転てつ装置60について図7〜図9に基づいて説明する。図7は工事期間中の分岐器先端付近の工事桁の平面図、図8はゲージタイ周辺の断面図、図9は図7のJ−J断面図である。
転てつ装置60は、電気転てつ機61、動作かん63、スイッチアジャスタ66、鎖錠かん71、ゲージタイ75(「電気転てつ機レール直結装置」ともいう)などから構成されている。
【0041】
電気転てつ機61は、モータ62や、このモータ62の駆動力を動作かん63に伝達する例えばギア等からなる図示しない伝達機構などを備えている。この電気転てつ機61は、主桁11の搭載部13上に絶縁板64及び敷板65を介して搭載されている。このように主桁11上に電気転てつ機61を搭載するため、枕木上に搭載する場合に比べて1対の主桁11、11の幅が狭くできる。特にこの構造は、隣合う線路同士の間隔が小さい場合に有効である。
【0042】
また、この搭載部13は他の箇所に比べて高さが低いため、電気転てつ機61を搭載したとしても列車の建築限界を侵すおそれはない。更に、この搭載部13は他の箇所に比べて幅が広いため、電気転てつ機61を搭載するに十分な剛性を有するばかりでなく、ポイント転換を確実に行う上で要求される剛性も実現できる。
【0043】
動作かん63は、スイッチアジャスタ66のロッド66aに連結されている。このため、動作かん63が移動するのに伴ってスイッチアジャスタ66も同方向に移動する。
スイッチアジャスタ66は、電気転てつ機61から発生する転換力を転てつ棒67を介してトングレール51に伝え、ポイントを転換し、トングレール51を基本レールRBに密着させるものである。スイッチアジャスタ66のロッド66aと転てつ棒67とは略T字状の腕金具68を介して連結されている。そしてこの腕金具68の両側から調整ナット69、69により位置決めされている。
【0044】
即ち、この調整ナット69、69を適宜回転することによりロッド66aと転てつ棒67の位置関係を調整することができる。このため、ポイント転換の際に1対のトングレール51、51のいずれかが1対の基本レールRB、RBのいずれかに密着するように調整することができる。尚、この調整ナット69、69には回転を阻止するための回り止め70が被せられている。
【0045】
鎖錠かん71は、トングレール51、51に直結された略コの字状のフロントロッド72に接続されている。この鎖錠かん71及び前記動作かん63は、電気転てつ機61の内部に設けられたロックピース(図示せず)との噛み合いによって鎖錠されるものである。即ち、ポイントの転換は1対のトングレール51、51のうちいずれかを基本レールRB,RBのいずれかに密着させることにより行われるが、このように密着した状態を確実に保持すべく鎖錠を行うのである。
【0046】
この鎖錠かん71は列車通過で鎖錠位置が微妙に狂うこともあるので、フロントロッド72の調整金具73の両側にある調整ナット73a、73aによって調整を行う。なお、この鎖錠かん71は電気転てつ機61から主桁11の切欠13aを経て基本レールRBの下方を通過するように形成されている。
【0047】
2本のゲージタイ75、75は、基本レールRBと電気転てつ機61の位置のずれを防止して鎖錠や密着(トングレール51と基本レールRBとの密着)の狂いを防ぐものであり、本実施例ではクランク状に形成されている。このクランク状のゲージタイ75の上段75aは、図7及び図8に示すように主桁11の搭載部13に搭載された電気転てつ機61に固定され、下段は枕木41上に敷設された基本レールRB、RBの下部に固定されている。このゲージタイ75は各基本レールRBの両側に設けた調整ナット76、76により固定位置を調整可能である。
【0048】
もし仮に図11に示すような直線棒状のゲージタイを用いるとすれば、H鋼の主桁に穴を開ける等の作業が必要になるが、本実施例ではクランク状のゲージタイ75を用いたため、そのような作業は不要であり、容易に電気転てつ機61と基本レールRB、RBとを直結することができる。
【0049】
このように設置された転てつ装置60の動作について簡単に説明する。ポイント転換の必要がある場合には、電気転てつ機61のモータ62を駆動させる。すると、その駆動力が動作かん63に伝達され、この動作かん63がスイッチアジャスタ66を移動させ、トングレール51と基本レールRBを密着させる。このとき、動作かん63及び鎖錠かん71は図示しないロックピースにより鎖錠される。このようにしてポイント転換が行われる。
【0050】
本実施例によれば、図8に示すように、主桁11の搭載部13には第2横桁36が3カ所に架設されており、このためゲージタイ75の調整ナット76、フロントロッド72の調整ナット73a、スイッチアジャスタ66の調整ナット69をスパナ等の調整用具によって調整する際に横桁が邪魔になるおそれがないという効果が得られる。
【0051】
尚、上記実施例では主桁11に断面略H状の鋼材を用いたが、工事桁10に要求される主桁の剛性を満足すれば特にこの形状でなくてもよい。また、1対の主桁11、11のうち電気転てつ機61を搭載しない側の主桁11には搭載部13を設けなくてもよい。
【図面の簡単な説明】
【図1】 本実施例の工事桁の平面図である。
【図2】 主桁の説明図であり、(a)は平面図、(b)は正面図、(c)はA−A断面図である。
【図3】 通常部用横桁の説明図であり、(a)は平面図、(b)はB−B断面図、(c)はC−C断面図である。
【図4】 第1横桁の説明図であり、(a)は平面図、(b)はD−D断面図、(c)はE−E断面図である。
【図5】 第2横桁の説明図であり、(a)は平面図、(b)はF−F断面図、(c)はG−G断面図である。
【図6】 架設橋を取り壊し新設橋を構築するときの工事の概略工程図である。
【図7】 工事期間中の分岐器先端付近の工事桁の平面図である。
【図8】 ゲージタイ周辺の断面図である。
【図9】 図7のJ−J断面図である。
【図10】 従来の工事桁の説明図であり、(a)は工事桁の使用説明図、(b)は(a)の円形部分の拡大破断面図、(c)はK−K断面図である。
【図11】 従来のゲージタイ周辺の断面図である。
【符号の説明】
10・・・工事桁、11・・・主桁、12・・・通常部、13・・・搭載部、16・・・受け台、17・・・受け台リブ、20・・・通常部用横桁、22・・・凹部、23・・・補強用リブ、30・・・搭載部用横桁、31・・・第1横桁、32・・・凹部、33・・・補強用リブ、36・・・第2横桁、37・・・凹部、41・・・枕木、42・・・既設の架道橋、43・・・仮橋台、44・・・仮受支柱、45・・・橋台、46・・・新設の架道橋、50・・・分岐器、51・・・トングレール、60・・・転てつ装置、61・・・電気転てつ機、63・・・動作かん、66・・・スイッチアジャスタ、67・・・転てつ棒、68・・・腕金具、69・・・調整ナット、70・・・回り止め、71・・・鎖錠かん、72・・・フロントロッド、73・・・調整金具、75・・・ゲージタイ、76・・・調整ナット。[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a work girder used when a new bridge is constructed by demolishing an existing bridge having a turnout, and an electric switch mounted on the upper surface of the main girder of this construction girder and a rail laid on sleepers The present invention relates to an electric switch rail direct connection device.
[0002]
[Background Art and Problems to be Solved by the Invention]
In general, a construction girder is widely used for temporary receiving of a track when excavating under a railway line while constructing a structure while running a train on a business line. However, whether or not the construction girder used is suitable for the situation at the site greatly affects the difficulty of the construction. Therefore, the construction girder must be designed so that it can be fully used at the same time as selecting a construction girder suitable for the construction.
[0003]
Conventionally, as shown in FIGS. 10 (a) to 10 (c), as a construction girder used when constructing a
As shown in FIG. 10 (c), the
[0004]
However, depending on the construction site, the height from the upper surface U of the existing
[0005]
The
[0006]
On the other hand, it is necessary to operate the
[0007]
In addition, as shown in FIG. 11, in the
[0008]
However, in order to install the
[0009]
The present invention has been made in view of the above problems, and its purpose is to secure a sufficient work space even when the height from the upper surface of the existing bridge to the rail level is low, and to prevent a branching device or a turnover. An object of the present invention is to provide a construction girder that can sufficiently meet the high rigidity required to hold the device.
[0010]
Another object is to provide a construction girder that can be equipped with an electric switch even when the distance between adjacent tracks is narrow.
Furthermore, another object is to provide an electric switch rail direct connection device suitable for directly connecting an electric switch mounted on the upper surface of the main beam of the construction beam of the present invention and a rail laid on a sleeper. Is to provide.
[0011]
[Means for Solving the Problems and Effects of the Invention]
In order to solve the above-mentioned problem, the invention according to claim 1 is a construction girder used when a new bridge is constructed by demolishing an existing bridge having a branching device and a switch device, and each sleeper is embraced And a pair of main girders that support both ends of the cross beam in a state where the cross beam is lifted from the upper surface of the existing bridge. The main girder has a mounting portion on the upper surface on which an electric switch can be mounted, and the mounting portion is formed in a shape that is lower in height and wider than other portions. It is characterized by that.
[0012]
A branching device refers to a line facility that distributes one line to two lines, and includes a tongrail. In addition, a switch device is a device that moves a branching device, such as an electric switch machine that includes a motor, etc., a switch adjuster that changes the point by transmitting the conversion force generated by the electric switch machine to the Tongler. including.
[0013]
In such construction girders, the rails are laid on sleepers held in the horizontal girders. Here, the distance from the lowest end of the cross beam to the rail level (the rail is laid on the sleeper) is almost [the height of the sleeper] + [the height of the rail] because the cross beam holds the sleeper. It becomes. That is, as compared with the case where a sleeper is placed on a horizontal beam and a rail is laid on the sleeper as in a conventional lower plate girder-type construction beam, it is reduced by [the height of the horizontal beam]. The main girder supports the horizontal girder in a state where it is lifted from the upper surface of the existing bridge. As a result, the distance from the upper surface of the existing bridge to the lowest end of the cross beam is widened by [the height of the cross beam] compared to the conventional case.
[0014]
In addition, since the point change by the branching device or the turning device must be performed reliably, the construction girder of the present invention is required to have high rigidity. In this regard, with the conventional lower plate girder type construction girders, if the height from the upper surface of the existing bridge to the rail level is low, the height of the cross girders cannot be made sufficiently high, so the required rigidity In order to satisfy the above, for example, two or more cross girders must be provided for each sleeper, and there is a problem that the construction work becomes complicated. On the other hand, since the construction girder according to the present invention is a holding type, it is sufficient to provide one horizontal girder per sleeper, and the construction work is facilitated.
[0015]
As described above, according to the construction girder of the present invention, the existing bridge can be easily demolished or the new bridge can be constructed by increasing the distance from the upper surface of the existing bridge to the lowest end of the horizontal girder. The effect of being able to be obtained. In addition, the high rigidity required for a construction girder having a branching device or the like can be realized by an easy construction as compared with the conventional lower plate girder type.
[0016]
Or In such a construction girder, it is necessary to install an electric switch for changing points. If the electric switch is mounted on a cross beam or on a sleeper that is held by the cross beam, a space for mounting the electric switch is required on the cross beam or sleeper. For this reason, the cross beams or sleepers become longer. Then, since the interval between the main girders widens, there is a problem that it cannot be actually used when the interval between adjacent lines is narrow. In this regard, from the viewpoint of effectively using the upper surface of the main girder, the construction girder of the present invention is equipped with an electric switch on the upper surface of the main girder, thereby eliminating the above problem. The effect is obtained. Moreover, since the mounting portion is lower in height than other places, even if an electric switch is mounted, there is no risk of violating the construction limit of the train (the area secured for the train to pass). Furthermore, since this mounting part is wider than other parts, it is possible to realize sufficient rigidity to mount the electric switch.
[0017]
[0018]
Among the members constituting the electric switch, there is a possibility of interference with the cross beam. For example, a switch adjuster adjuster (when the point is changed by the switch adjuster, the Tongleil adheres to the basic rail. Adjustment tool for adjusting the lock mechanism (adjustment tool for adjusting the locking mechanism lock position to lock the locking mechanism after the point change), gauge tie adjustment tool ( And an adjustment tool for adjusting a gauge tie for preventing displacement between the electric switch and the rail.
[0019]
In the case of a shape that covers the entire and bottom surfaces of both sides of the sleeper for the cross beam in a position that interferes with the members constituting the electric switch, for example, an adjustment tool such as a spanner is used as an adjustment tool such as a spanner. Even if you try to adjust it, the side part of the cross beam may be in the way, and in the present invention, such a cross beam has a shape that only holds the lower half of the sleeper, so adjustment with the adjustment tool The effect of being able to adjust smoothly without getting in the way is obtained.
[0020]
Claim 3 The described invention Claim 1 or
[0021]
In such an electric switch rail direct coupling device, since the electric switch is mounted on the upper surface of the main girder, even if it is attempted to linearly connect the lower part of the electric switch and the lower part of the rail, It is difficult because there is a main girder below the lever.
Therefore, in the present invention, the gauge tie is crank-shaped, and the electric switch mounted on the upper surface of the main girder is fixed at the upper stage of the gauge tie, and the rail laid on the sleepers is fixed at the lower stage of the gauge tie, Even if there is a main girder below the electric switch, the electric switch and rail can be easily connected directly.
[0022]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, preferred embodiments of the present invention will be described with reference to the drawings. The embodiments of the present invention are not limited to the following examples, and it goes without saying that various forms can be adopted as long as they belong to the technical scope of the present invention.
[0023]
FIG. 1 is a plan view of a construction girder according to the present embodiment. As shown in FIG. 1, the
2A and 2B are explanatory diagrams of the main girder, in which FIG. 2A is a plan view, FIG. 2B is a front view, and FIG. The
[0024]
The
[0025]
Moreover, the
[0026]
As shown in FIG. 1, there are two types of horizontal girders: a
FIGS. 3A and 3B are explanatory diagrams of the normal part cross beam, wherein FIG. 3A is a plan view, FIG. 3B is a cross-sectional view along BB, and FIG. 3C is a cross-sectional view along CC. The normal
[0027]
Reinforcing
[0028]
4A and 4B are explanatory views of the first cross beam, in which FIG. 4A is a plan view, FIG. 4B is a DD cross-sectional view, and FIG. 4C is a EE cross-sectional view. The
[0029]
The
[0030]
Each end portion of the
[0031]
5A and 5B are explanatory views of the second cross beam, in which FIG. 5A is a plan view, FIG. 5B is a cross-sectional view taken along line FF, and FIG. 5C is a cross-sectional view taken along line GG. The second
[0032]
The
[0033]
Since the
[0034]
Each end portion of the
[0035]
Next, an outline of a construction method for constructing a new bridge by demolishing an existing bridge having a branching device and a switch using the
[0036]
Next, the role of the
For the
[0037]
For this reason, compared with the case where a sleeper is placed on a horizontal girder and a rail is laid on the sleeper as in the conventional lower plate girder-type construction girder shown in FIG. Get smaller.
Therefore, even if the distance from the upper surface of the existing
[0038]
The
[0039]
FIG. 7 is a plan view of a construction girder near the tip of the turnout during the construction period. As shown in FIG. 7, a branching
Here, since the point change by the branching
[0040]
Here, the rolling
The
[0041]
The
[0042]
Moreover, since this mounting
[0043]
The
The
[0044]
That is, the positional relationship between the
[0045]
The lock can 71 is connected to a substantially U-shaped front rod 72 directly connected to the
[0046]
Since the lock position of the lock can 71 may be slightly changed when the train passes, adjustment is performed by adjusting nuts 73a and 73a on both sides of the adjustment fitting 73 of the front rod 72. This lock can 71 is formed so as to pass from the
[0047]
The two
[0048]
If a straight rod-shaped gauge tie as shown in FIG. 11 is used, an operation such as drilling a hole in the main girder of H steel is required. However, in this embodiment, a crank-shaped
[0049]
The operation of the
[0050]
According to the present embodiment, as shown in FIG. 8, the mounting
[0051]
In the above embodiment, a steel material having a substantially H-shaped cross section is used for the
[Brief description of the drawings]
FIG. 1 is a plan view of a construction girder according to the present embodiment.
FIGS. 2A and 2B are explanatory views of a main girder, in which FIG. 2A is a plan view, FIG. 2B is a front view, and FIG.
3A and 3B are explanatory diagrams of a normal part cross beam, in which FIG. 3A is a plan view, FIG. 3B is a cross-sectional view taken along the line BB, and FIG.
4A and 4B are explanatory diagrams of a first cross beam, in which FIG. 4A is a plan view, FIG. 4B is a DD cross-sectional view, and FIG. 4C is an EE cross-sectional view.
5A and 5B are explanatory diagrams of a second cross beam, in which FIG. 5A is a plan view, FIG. 5B is a cross-sectional view taken along line FF, and FIG.
FIG. 6 is a schematic process diagram of the construction when a bridge is demolished and a new bridge is constructed.
FIG. 7 is a plan view of a construction girder near the tip of a turnout unit during construction.
FIG. 8 is a cross-sectional view around a gauge tie.
9 is a cross-sectional view taken along line JJ in FIG.
FIGS. 10A and 10B are explanatory diagrams of a conventional construction girder, where FIG. 10A is a diagram illustrating the use of a construction girder, FIG. 10B is an enlarged sectional view of a circular portion of FIG. It is.
FIG. 11 is a sectional view around a conventional gauge tie.
[Explanation of symbols]
DESCRIPTION OF
Claims (3)
各枕木を抱き込んだ状態で保持する複数の横桁と、
前記横桁を前記既設橋の上面から持ち上げた状態で前記横桁の両端を支持する1対の主桁とを備え、
前記主桁はその上面に前記転てつ装置の一構成物である電気転てつ機を搭載可能な搭載部を備え、
該搭載部は他の箇所に比べて高さが低く幅が広い形状に形成されていることを特徴とする工事桁。It is a construction girder used when building a new bridge by demolishing an existing bridge embankment with a branching device and a tipping device,
A plurality of cross beams to hold each sleeper in a state of being held,
A pair of main girders that support both ends of the cross beam in a state where the cross beam is lifted from the upper surface of the existing bridge ,
The main girder includes a mounting portion on the upper surface of which an electric turning machine that is a component of the turning device can be mounted.
The construction girder characterized in that the mounting portion is formed in a shape that is lower in height and wider than other portions .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP00229497A JP3797733B2 (en) | 1997-01-09 | 1997-01-09 | Construction girder and electric switch rail direct connection device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP00229497A JP3797733B2 (en) | 1997-01-09 | 1997-01-09 | Construction girder and electric switch rail direct connection device |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10195806A JPH10195806A (en) | 1998-07-28 |
JP3797733B2 true JP3797733B2 (en) | 2006-07-19 |
Family
ID=11525359
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP00229497A Expired - Lifetime JP3797733B2 (en) | 1997-01-09 | 1997-01-09 | Construction girder and electric switch rail direct connection device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3797733B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103741565A (en) * | 2014-01-21 | 2014-04-23 | 唐山金山腾宇科技有限公司 | Waste alloy steel frog repairing process |
-
1997
- 1997-01-09 JP JP00229497A patent/JP3797733B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103741565A (en) * | 2014-01-21 | 2014-04-23 | 唐山金山腾宇科技有限公司 | Waste alloy steel frog repairing process |
CN103741565B (en) * | 2014-01-21 | 2015-12-09 | 唐山金山腾宇科技有限公司 | The renovation technique of waste alloy steel frog |
Also Published As
Publication number | Publication date |
---|---|
JPH10195806A (en) | 1998-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100757958B1 (en) | Insert reclamation apparatus for construction of linear induction motor panel in linear induction motor | |
JP4090157B2 (en) | Assembly method of fixed track line | |
CA1336424C (en) | Railroad roadway for high speed rail-mounted vehicles | |
AU2007211764B2 (en) | Ballastless track for railway vehicles | |
JP4540632B2 (en) | Erection girder | |
JPH0438841B2 (en) | ||
KR101399839B1 (en) | Transition track structure of railway bridge deck end and Construction method | |
JP3797733B2 (en) | Construction girder and electric switch rail direct connection device | |
KR102003695B1 (en) | Rail Track Assembly For Steel Railway Bridge | |
JP4650255B2 (en) | Steel slab reinforcement structure and existing steel slab reinforcement method | |
JP5276801B2 (en) | Labor-saving track reinforcement method | |
JP4162291B2 (en) | Railway work girder cradle and rail work girder cradle construction method | |
KR101270942B1 (en) | Sleeper having shear fixing apparatus for asphalt roadbed, and constructing method for the same | |
JP4148607B2 (en) | Construction method of underground structure using floor girder for construction girder | |
JP2903003B2 (en) | Railway station platform | |
KR20150138625A (en) | Transition track structure of railway bridge deck end and Construction method | |
JP4359731B2 (en) | Method of replacing concrete floor slab bridge with steel slab and structure of replacing concrete floor slab bridge with steel slab | |
JP2006112086A (en) | Structure of bridge and method for rebuilding bridge | |
WO2005085528A1 (en) | Railway rail, elongate rail support therefor and method of construction | |
CN110857544B (en) | High-speed railway safety protection structure and construction method thereof | |
JP4627383B2 (en) | Replaced steel deck bridge | |
JP3396051B2 (en) | Simple girder guard girder device | |
TWI653375B (en) | Track, travel path forming portion, method of laying rails, and method of repairing rails | |
JP3830004B2 (en) | Bifurcation sleeper right angle spacing prevention device | |
JP5400868B2 (en) | Solid track road with continuous laying floor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050829 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050906 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051107 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060328 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060418 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090428 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100428 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110428 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110428 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120428 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130428 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |