JP3774157B2 - Medium push jack handling device - Google Patents

Medium push jack handling device Download PDF

Info

Publication number
JP3774157B2
JP3774157B2 JP2002055585A JP2002055585A JP3774157B2 JP 3774157 B2 JP3774157 B2 JP 3774157B2 JP 2002055585 A JP2002055585 A JP 2002055585A JP 2002055585 A JP2002055585 A JP 2002055585A JP 3774157 B2 JP3774157 B2 JP 3774157B2
Authority
JP
Japan
Prior art keywords
jack
telescopic boom
tube
push
intermediate push
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002055585A
Other languages
Japanese (ja)
Other versions
JP2003253985A (en
Inventor
強 宮原
脩 野辺
Original Assignee
栗本コンクリート工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 栗本コンクリート工業株式会社 filed Critical 栗本コンクリート工業株式会社
Priority to JP2002055585A priority Critical patent/JP3774157B2/en
Publication of JP2003253985A publication Critical patent/JP2003253985A/en
Application granted granted Critical
Publication of JP3774157B2 publication Critical patent/JP3774157B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、推進工法により地中に管路を構築する場合に用いられる中押しジャッキの取扱い装置に関するものである。
【0002】
【従来の技術】
推進工法により地中に管路を構築する場合、推進距離が一定以上に長くなったり、カーブ部分があったりする場合には、元押し側の推進力の不足を補うために推進管路の途中に中押し管を介在し、その中押し管に中押しジャッキを取り付け、その中押しジャッキによる推進、いわゆる中押しが行われる。
【0003】
前記の中押しジャッキは、1カ所の中押し管当たり、標準的な径の場合で、最大14本使用され、通常は地上において中押し管の内周面に中押しジャッキを取り付けておき、推進を行いながら適宜な位置で推進管と推進管との間にその中押し管を介在させるようにしている。前記の中押し管とそれに取り付けた中押しジャッキは、通常は、管路の構築が完了した後においても除去することなく、中押し管の内周面に充填されるモルタル中に埋め込まれる。
【0004】
しかしながら、前記の中押し管とそれに取り付けられた中押しジャッキは、施工現場の種々の事情により使用されないことがしばしばあり、工事のコストに対する影響が問題となる。
【0005】
この対策として、中押しジャッキを取り付けることなく、その取り付け部のみを設けた中押し管を所定位置に介在させて推進を行い、実際に中押しを行う必要が生じた場合には、推進管内に中押しジャッキを搬入し、その中押しジャッキを簡単な工具を用いた作業者の手作業により取り付け、工事の完了後にはこれを撤去することにより、工事のコストの低減を図る方法がとられている。
【0006】
【発明が解決しようとする課題】
しかしながら、狭い推進管の内部で100キログラム弱の中押しジャッキを中押し管内壁に取り付ける作業、特にその天井部に取り付ける作業は危険で難渋な作業である。また、その撤去作業についても同様のことがいえる。
【0007】
そこで、この発明は、前記の中押しジャッキの取り付け作業と撤去作業が、容易かつ安全に行える中押しジャッキ取扱い装置を提供することを課題とする。
【0008】
【課題を解決するための手段】
上記の課題を解決するために、この発明にかかる中押しジャッキ取扱い装置は、伸縮ブームと、その先端部に設けられたジャッキ把持部と、前記伸縮ブームの回転支持部と、前記伸縮ブームの揺動装置とからなり、前記回転支持部を中押し管の内壁低位置に固定し、該回転支持部に前記伸縮ブーム後端を前記中押し管の中心線方向と平行のヒンジピンにより揺動自在に連結してなり、前記ジャッキ把持部により把持した中押しジャッキを前記伸縮ブームの伸縮と前記揺動装置の駆動とにより、該中押しジャッキを前記中押し管内壁の所定位置に持ち上げるようにしたものである。
【0009】
前記の装置を用いると、伸縮ブームの先端部のジャッキ把持部で把持した中押しジャッキを、伸縮装置と揺動装置の作動により中押し管の高所に容易に持ち上げることができる。
【0010】
前記の中押し管の内壁面低位置にジャッキ仮置き台を設置してなる構成をとることができる。このような仮置き台を設けると、中押しジャッキを一時的にこれに載置できる便利さがある。
【0011】
なお、前記の揺動装置は、前記の伸縮ブームの一部に取り付けたワイヤーと、前記中押し管内壁面高位置に取り付けた滑車と、前記中押し管内壁面の適宜位置に取り付けた巻取り引装置とからなり、前記ワイヤーを前記滑車を経て前記巻取り装置で巻き取るようにした構成をとることができる。
【0012】
【発明の実施の形態】
以下、この発明の実施形態を図1及び図2に基づいて説明する。まず中押し管1について説明する。中押し管1は、中押し外管2と中押し内管3との組み合わせからなる。中押し外管2は推進方向(矢印A参照)の前部に配置され、中押し内管3は中押し外管2の後部からその内径面に嵌合される。
【0013】
中押し外管2は鋼鈑製の金属管部4とその前端に同芯・同一外径に形成され一体化されたコンクリート管部5とにより構成される。金属管部4の内径面においてその前端部に近い位置に内つば6が設けられ、その内つば6の外面と金属管部4の内径面に前記のコンクリート管部5の後端部が一体化される。
【0014】
前記の内つば6の後面に、ボルト7により当て輪8が着脱可能に取り付けられている。ボルト7はコンクリート管部5に埋設されたナット9に螺合される。前記の当て輪8はチャンネル状の鋼製リングにより構成され、全周にわたり内側に多数のリブ11が設けられる。
【0015】
なお、前記のコンクリート管部5の先端部は、前位の推進管10の後端部に差し込まれる。
【0016】
一方、前記の中押し内管3は、図1に示すように、鋼鈑製の金属管部12の後端部に断面L字形の差し口用リング13を接合一体化したものである。その差し口用リング13に後位の推進管14の先端部が差し込まれる。また、前記差し口用リング13と対向して金属管部12の内径面に内つば15が設けられ、その内つば15と差し口用リング13との間に多数の補強リブ16が設けられる。
【0017】
さらに、金属管部12の先端に内向きの先端つば17が設けられ、前記の内つば15と先端つば17の間には、周方向に等間隔をおいて14本の補強リブ20が長さ方向に設けられる(図2参照)。これらの各補強リブ20の間が中押しジャッキ18の取付け部19となり、各取付け部19ごとに先端つば17の内周縁には中押しジャッキ18の先端部の位置決め凹所21が設けられる。
【0018】
以上述べた中押し管1の内部に中押しジャッキ取扱い装置22が取り付けられる。この中押しジャッキ取扱い装置22を構成する伸縮ブーム23は、図2に示すように、角筒状のケーシング24の内部に自動伸縮アーム25、その自動伸縮アーム25内に手動伸縮アーム26を順に入れ子式に収納したものである。自動伸縮アーム25はケーシング24の外側に取り付けた油圧シリンダー27のピストンロッド28にブラケット29を介して連結される。また、手動伸縮アーム26は、前記のブラケット29を経て自動伸縮アーム25の部分に抜き差し自在に挿入したピン31を手動伸縮アーム26に設けた所定のピン孔26aに通すことにより位置めされる。また、手動伸縮アーム26の先端にジャッキ把持部32が設けられる。
【0019】
ジャッキ把持部32は、中押しジャッキ18の胴部を受け入れる大きさに開放されたコの字形の枠部材により構成され、その先端部の左右に上下一対の把持用ボルト33、33が開口部の内側に突出するように螺入されている。
【0020】
前記伸縮ブーム23のケーシング24の後端部は、中押し管1の中心線方向と平行のヒンジピン34を介して回転支持部35に揺動自在に連結される。回転支持部35は前記の補強リブ20のうち比較的低位置(図示の場合は、中間高さの補強リブ20から1つ下がった位置)のものにボルト36で固定された部材により構成される。
【0021】
前記の伸縮ブーム23を前記ヒンジピン34を中心として揺動させる揺動装置37は、前記のケーシング24の先端上部に固着されたブラケット38と、そのブラケット38に一端部が連結されたワイヤー39、前記中押し管1の補強リブ20のうち比較的高位置(図示の場合は、頂部の補強リブ20から前記支持部35側へ1つ片寄った位置)のものに支持金具41を介して取り付けられた滑車42、及び前記回転支持部35近辺の補強リブ20に支持金具43を介して取り付けられた巻取り装置44とにより構成される。前記のワイヤー39は滑車42に掛けられ巻取り装置44に巻き取られる。
【0022】
前記の中押し管1の内周面において、前記支持部35とほぼ同じ高さで対向した補強リブ20に左右一対のジャッキ仮置き台45,45(図1参照)がボルト46で固定される。
【0023】
実施形態の中押しジャッキ取扱い装置22は以上のようなものであり、推進工法の実施に際しては、中押しジャッキ18を取り付けていない中押し管1を所定間隔で前位の推進管10と後位の推進管14との間に介在させて推進を行う。推進の途中で中押しの必要が生じた場合は、その必要が生じた部分の中押し管1の部分にジャッキ取扱い装置22の構成部材を搬入し組立を行う。
【0024】
その組立は、支持部35の固定、滑車42、巻取り装置44の取り付け、ジャッキ仮置き台45の固定等を行い、次に伸縮ブーム23を前記の支持部35に連結し、さらにワイヤー39を掛け通す。また、油圧シリンダー27への油圧供給の準備を行う。
【0025】
このような準備作業を終えたのち、搬入された中押しジャッキ18を一旦ジャッキ仮置き台45上に置き、伸縮ブーム23の手動伸縮アーム26をピン31により所定長さに伸ばして中押しジャッキ18をジャッキ把持部32の開口内に入れ、把持用ボルト33を螺入する。これにより中押しジャッキ18が把持される。
【0026】
次に、巻取り装置44を手動で駆動してワイヤー39を所定量巻き取ると、伸縮ブーム23が所定角度起き上がる。そこで、油圧シリンダー27を駆動させた自動伸縮アーム25を伸張させるとジャッキ把持部32が中押し管1の内周壁まで伸び、その先端部が取付け部19の位置決め凹所21に嵌合される(図2の一点鎖線参照)。この状態にまで持ち上げられ位置決めされた中押しジャッキ18の胴部2カ所に作業者が締め付けバンド47を巻き、中押し管1の内壁面にボルト48により固定する。以下同様の作業を繰り返して中押しジャッキ18を頂部まで取り付ける。
【0027】
次に、前記のジャッキ取扱い装置22を左右対称位置に付け替え、反対側の内壁面の各取付け部19に前記と同様の作業により中押しジャッキ18を取り付ける。
【0028】
なお、伸縮ブーム23より低い位置においては、中押しジャッキ18を持ち上げる必要はないので、直接所定の取付け部19に取り付ける。
【0029】
前記の中押しジャッキ取扱い装置22は、取り外すことなく推進が継続され、推進完了後にその装置22を用いて中押しジャッキ18を取り外す。その取り外し作業は、前述の取り付け作業と逆の手順により行われる。取り外し作業の完了後、該ジャッキ取扱い装置22も取り外される。
【0030】
【発明の効果】
以上のように、この発明は中押し管の内周面に中押しジャッキを取り付ける作業及び取り外す作業において、ジャッキ把持部を有する伸縮ブームを適宜揺動・伸縮させて中押しジャッキを高所に持ち上げ、また高所から降ろすことが出きるので、作業者の労力が著しく軽減され、作業性と安全性を向上することができる。
【図面の簡単な説明】
【図1】実施形態の断面図
【図2】同上の図1におけるII−II線の断面図
【符号の説明】
1 中押し管
2 中押し外管
3 中押し内管
4 金属管部
5 コンクリート管部
6 内つば
7 ボルト
8 当て輪
9 ナット
10 推進管
11 リブ
12 金属管部
13 差し口用リング
14 推進管
15 内つば
16 補助リブ
17 先端つば
18 中押しジャッキ
19 取付け部
20 補強リブ
21 位置決め凹所
22 中押しジャッキ取扱い装置
23 伸縮ブーム
24 ケーシング
25 自動伸縮アーム
26 手動伸縮アーム
26a ピン孔
27 油圧シリンダー
28 ピストンロッド
29 ブラケット
31 ピン
32 ジャッキ把持部
33 把持用ボルト
34 ヒンジピン
35 回転支持部
36 ボルト
37 揺動装置
38 ブラケット
39 ワイヤー
41 支持金具
42 滑車
43 支持金具
44 巻取り装置
45 ジャッキ仮置き台
46 ボルト
47 締め付けバンド
48 ボルト
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a handling device for an intermediate jack used for constructing a pipeline in the ground by a propulsion method.
[0002]
[Prior art]
When constructing a pipeline in the ground by the propulsion method, if the propulsion distance is longer than a certain length or there is a curved part, it is necessary to make a midway along the propulsion pipeline to make up for the lack of propulsive force on the main push side. An intermediate pusher tube is interposed between the intermediate pusher tube and an intermediate pusher jack is attached to the intermediate pusher tube.
[0003]
In the case of a standard diameter, a maximum of 14 middle push jacks are used per one middle push pipe. Usually, the middle push jack is attached to the inner peripheral surface of the middle push pipe on the ground and propelled as needed. The intermediate pusher tube is interposed between the propulsion tube and the propulsion tube at various positions. The middle pusher tube and the middle pusher jack attached to the middle pusher tube are normally embedded in a mortar filled on the inner peripheral surface of the middle pusher tube without being removed even after the construction of the pipeline is completed.
[0004]
However, the above-mentioned middle push pipe and the middle push jack attached thereto are often not used due to various circumstances at the construction site, and the influence on the construction cost becomes a problem.
[0005]
As a countermeasure against this, when it is necessary to carry out propulsion with an intermediate push pipe provided with only its attachment section in place, without attaching the intermediate push jack, and when it becomes necessary to actually push the middle push jack, There is a method of reducing the cost of construction by carrying in, attaching the jack jack by manual operation of an operator using a simple tool, and removing the jack after completion of the construction.
[0006]
[Problems to be solved by the invention]
However, the work of attaching an intermediate push jack of less than 100 kilograms to the inner wall of the intermediate push pipe inside the narrow propulsion pipe, particularly the work of attaching it to the ceiling, is a dangerous and difficult work. The same is true for the removal work.
[0007]
Then, this invention makes it a subject to provide the intermediate push jack handling apparatus which can perform the attachment operation | work and removal operation | work of the said intermediate push jack easily and safely.
[0008]
[Means for Solving the Problems]
In order to solve the above-described problems, an intermediate push jack handling device according to the present invention includes an extendable boom, a jack grip provided at a tip portion thereof, a rotation support portion of the extendable boom, and a swing of the extendable boom. The rotation support part is fixed to the lower position of the inner wall of the intermediate push pipe, and the rear end of the telescopic boom is connected to the rotation support part so as to be swingable by a hinge pin parallel to the center line direction of the intermediate push pipe. Thus, the intermediate push jack grasped by the jack grasping portion is lifted to a predetermined position on the inner wall of the intermediate push pipe by expansion and contraction of the telescopic boom and driving of the swinging device.
[0009]
If the said apparatus is used, the intermediate push jack hold | gripped with the jack holding | grip part of the front-end | tip part of an expansion-contraction boom can be easily lifted to the height of a center push pipe by the action | operation of an expansion-contraction apparatus and a rocking | swiveling device.
[0010]
A configuration in which a jack temporary table is installed at a low position on the inner wall surface of the intermediate push tube can be employed. Providing such a temporary placement stand has the convenience of temporarily placing the intermediate push jack on it.
[0011]
The swing device includes: a wire attached to a part of the telescopic boom; a pulley attached at a high position on the inner wall surface of the intermediate push tube; and a winding / removal device attached at an appropriate position on the inner wall surface of the intermediate push tube. Thus, the wire can be taken up by the winding device through the pulley.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to FIGS. 1 and 2. First, the intermediate push tube 1 will be described. The intermediate push tube 1 is composed of a combination of an intermediate push outer tube 2 and an intermediate push inner tube 3. The intermediate push outer tube 2 is disposed at the front portion in the propulsion direction (see arrow A), and the intermediate push inner tube 3 is fitted to the inner diameter surface from the rear portion of the intermediate push outer tube 2.
[0013]
The intermediately pressed outer tube 2 is composed of a steel tube-made metal tube portion 4 and a concrete tube portion 5 formed concentrically and at the same outer diameter at the front end thereof. An inner collar 6 is provided at a position near the front end of the inner diameter surface of the metal tube portion 4, and the rear end portion of the concrete tube portion 5 is integrated with the outer surface of the inner collar 6 and the inner diameter surface of the metal tube portion 4. Is done.
[0014]
A contact wheel 8 is detachably attached to the rear surface of the inner collar 6 by a bolt 7. The bolt 7 is screwed into a nut 9 embedded in the concrete pipe portion 5. The abutment ring 8 is constituted by a channel-shaped steel ring, and a large number of ribs 11 are provided on the inner side over the entire circumference.
[0015]
In addition, the front-end | tip part of the said concrete pipe part 5 is inserted in the rear-end part of the front propulsion pipe 10. FIG.
[0016]
On the other hand, as shown in FIG. 1, the inner press-in inner tube 3 is formed by joining and integrating an L-shaped insertion ring 13 with a rear end portion of a steel tube-made metal tube portion 12. The tip of the rear propulsion pipe 14 is inserted into the insertion ring 13. Further, an inner collar 15 is provided on the inner surface of the metal tube portion 12 so as to face the insertion ring 13, and a plurality of reinforcing ribs 16 are provided between the inner collar 15 and the insertion ring 13.
[0017]
Further, an inward leading end collar 17 is provided at the leading end of the metal tube portion 12, and 14 reinforcing ribs 20 have a length between the inner collar 15 and the leading end collar 17 at equal intervals in the circumferential direction. (See FIG. 2). Between each of these reinforcing ribs 20 is an attachment portion 19 of the intermediate push jack 18, and a positioning recess 21 at the distal end portion of the intermediate push jack 18 is provided on the inner peripheral edge of the distal end collar 17 for each attachment portion 19.
[0018]
The intermediate push jack handling device 22 is attached to the inside of the intermediate push tube 1 described above. As shown in FIG. 2, the telescopic boom 23 constituting the intermediate push jack handling device 22 includes an automatic telescopic arm 25 in a rectangular tubular casing 24 and a manual telescopic arm 26 in the automatic telescopic arm 25 in this order. It is what was stored in. The automatic telescopic arm 25 is connected via a bracket 29 to a piston rod 28 of a hydraulic cylinder 27 attached to the outside of the casing 24. The manual telescopic arm 26 is positioned by passing a pin 31, which is removably inserted into the automatic telescopic arm 25 through the bracket 29, through a predetermined pin hole 26 a provided in the manual telescopic arm 26. A jack grip 32 is provided at the tip of the manual extendable arm 26.
[0019]
The jack grip 32 is formed by a U-shaped frame member that is opened to receive the body of the intermediate push jack 18, and a pair of upper and lower grip bolts 33, 33 are provided on the inner side of the opening. It is screwed so that it may protrude.
[0020]
A rear end portion of the casing 24 of the telescopic boom 23 is swingably connected to a rotation support portion 35 via a hinge pin 34 parallel to the center line direction of the intermediate pusher tube 1. The rotation support portion 35 is constituted by a member fixed by a bolt 36 at a relatively low position (in the illustrated case, one position lower than the intermediate height reinforcing rib 20) of the reinforcing ribs 20. .
[0021]
The swinging device 37 for swinging the telescopic boom 23 around the hinge pin 34 includes a bracket 38 fixed to the upper end of the casing 24, a wire 39 having one end connected to the bracket 38, A pulley attached to a relatively high position of the reinforcing ribs 20 of the intermediate pusher tube 1 (in the illustrated case, one position shifted from the top reinforcing rib 20 toward the supporting portion 35) via a support fitting 41. 42 and a winding device 44 attached to the reinforcing rib 20 in the vicinity of the rotation support portion 35 via a support fitting 43. The wire 39 is hung on a pulley 42 and wound on a winding device 44.
[0022]
On the inner peripheral surface of the intermediate pusher tube 1, a pair of left and right jack temporary holders 45 and 45 (see FIG. 1) are fixed to the reinforcing rib 20 facing the support portion 35 at substantially the same height with bolts 46.
[0023]
The intermediate push jack handling device 22 of the embodiment is as described above. When carrying out the propulsion method, the front push pipe 10 and the rear push pipe are arranged at predetermined intervals with the middle push pipe 1 to which the middle push jack 18 is not attached. 14 and propulsion is performed. When the need for intermediate pressing occurs during the propulsion, the components of the jack handling device 22 are carried into the portion of the intermediate pressing tube 1 where the necessity has occurred and assembled.
[0024]
The assembly includes fixing the support portion 35, attaching the pulley 42 and the take-up device 44, fixing the jack temporary table 45, etc., and then connecting the telescopic boom 23 to the support portion 35, and further connecting the wire 39. Run through. In addition, preparation for supplying hydraulic pressure to the hydraulic cylinder 27 is performed.
[0025]
After completing such preparatory work, the loaded intermediate pushing jack 18 is temporarily placed on the temporary jacking table 45, the manual telescopic arm 26 of the telescopic boom 23 is extended to a predetermined length by the pin 31, and the intermediate pushing jack 18 is jacked. A gripping bolt 33 is screwed into the opening of the gripping portion 32. As a result, the intermediate push jack 18 is gripped.
[0026]
Next, when the winding device 44 is manually driven to wind the wire 39 by a predetermined amount, the telescopic boom 23 rises by a predetermined angle. Therefore, when the automatic telescopic arm 25 that has driven the hydraulic cylinder 27 is extended, the jack gripping portion 32 extends to the inner peripheral wall of the intermediate pusher tube 1, and its distal end is fitted into the positioning recess 21 of the mounting portion 19 (see FIG. 2 dash-dot line). The operator wraps the fastening band 47 around the two body portions of the intermediate push jack 18 which is lifted and positioned in this state, and is fixed to the inner wall surface of the intermediate push tube 1 with the bolts 48. Thereafter, the same operation is repeated to attach the intermediate push jack 18 to the top.
[0027]
Next, the jack handling device 22 is changed to a symmetrical position, and the intermediate push jack 18 is attached to each attachment portion 19 on the opposite inner wall surface by the same operation as described above.
[0028]
Since the intermediate push jack 18 does not need to be lifted at a position lower than the telescopic boom 23, it is directly attached to the predetermined attachment portion 19.
[0029]
Propulsion is continued without removing the intermediate push jack handling device 22, and the intermediate push jack 18 is removed using the device 22 after completion of the propulsion. The removal operation is performed in the reverse order of the above-described attachment operation. After the removal operation is completed, the jack handling device 22 is also removed.
[0030]
【The invention's effect】
As described above, according to the present invention, in the work of attaching and removing the intermediate push jack to the inner peripheral surface of the intermediate push pipe, the telescopic boom having the jack gripping portion is appropriately swung and extended to lift the intermediate push jack to a high place. Therefore, the labor of the operator can be remarkably reduced, and workability and safety can be improved.
[Brief description of the drawings]
FIG. 1 is a sectional view of an embodiment. FIG. 2 is a sectional view taken along line II-II in FIG.
DESCRIPTION OF SYMBOLS 1 Middle push pipe 2 Middle push outer pipe 3 Middle push inner pipe 4 Metal pipe part 5 Concrete pipe part 6 Inner collar 7 Bolt 8 Bearing ring 9 Nut 10 Propulsion pipe 11 Rib 12 Metal pipe part 13 Feeding ring 14 Propulsion pipe 15 Inner collar 16 Auxiliary rib 17 End collar 18 Middle push jack 19 Mounting portion 20 Reinforcement rib 21 Positioning recess 22 Middle push jack handling device 23 Telescopic boom 24 Casing 25 Automatic telescopic arm 26 Manual telescopic arm 26a Pin hole 27 Hydraulic cylinder 28 Piston rod 29 Bracket 31 Pin 32 Jack gripping portion 33 Grasping bolt 34 Hinge pin 35 Rotation support portion 36 Bolt 37 Oscillating device 38 Bracket 39 Wire 41 Support bracket 42 Pulley 43 Support bracket 44 Winding device 45 Jack temporary holder 46 Bolt 47 Tightening band 48 Bolt

Claims (3)

伸縮ブームと、その先端部に設けられたジャッキ把持部と、前記伸縮ブームの回転支持部と、前記伸縮ブームの揺動装置とからなり、前記回転支持部を中押し管の内壁低位置に固定し、該回転支持部に前記伸縮ブーム後端を前記中押し管の中心線方向と平行のヒンジピンにより揺動自在に連結してなり、前記ジャッキ把持部により把持した中押しジャッキを前記伸縮ブームの伸縮と前記揺動装置の駆動とにより、該中押しジャッキを前記中押し管内壁の所定位置に持ち上げるようにした中押しジャッキ取扱い装置。The telescopic boom is composed of a telescopic boom, a jack grip provided at the tip of the telescopic boom, a rotational support unit of the telescopic boom, and a swinging device for the telescopic boom, and the rotational support unit is fixed to a low position on the inner wall of the intermediate push tube. The rear end of the telescopic boom is pivotally connected to the rotation support portion by a hinge pin parallel to the center line direction of the middle push tube, and the middle push jack gripped by the jack grip portion is extended and retracted from the telescopic boom. A middle push jack handling device configured to lift the middle push jack to a predetermined position on the inner wall of the middle push pipe by driving a swinging device. 前記の中押し管の内壁面低位置にジャッキ仮置き台を設置してなる請求項1に記載の中押しジャッキ取扱い装置。The intermediate push jack handling device according to claim 1, wherein a temporary jack stand is installed at a low position on the inner wall surface of the intermediate push tube. 前記の揺動装置は、前記の伸縮ブームの一部に取り付けたワイヤーと、前記中押し管内壁面高位置に取り付けた滑車と、前記中押し管内壁面の適宜位置に取り付けた巻取り引装置とからなり、前記ワイヤーを前記滑車を経て前記巻取り装置で巻き取るようにした請求項1又は2に記載の中押しジャッキ取扱い装置。The swing device comprises a wire attached to a part of the telescopic boom, a pulley attached at a high position on the inner wall surface of the intermediate push tube, and a winding / unloading device attached at an appropriate position on the inner wall surface of the intermediate push tube, The intermediate push jack handling device according to claim 1 or 2, wherein the wire is wound up by the winding device through the pulley.
JP2002055585A 2002-03-01 2002-03-01 Medium push jack handling device Expired - Fee Related JP3774157B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002055585A JP3774157B2 (en) 2002-03-01 2002-03-01 Medium push jack handling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002055585A JP3774157B2 (en) 2002-03-01 2002-03-01 Medium push jack handling device

Publications (2)

Publication Number Publication Date
JP2003253985A JP2003253985A (en) 2003-09-10
JP3774157B2 true JP3774157B2 (en) 2006-05-10

Family

ID=28666384

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002055585A Expired - Fee Related JP3774157B2 (en) 2002-03-01 2002-03-01 Medium push jack handling device

Country Status (1)

Country Link
JP (1) JP3774157B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013108318A (en) * 2011-11-24 2013-06-06 Kidoh Construction Co Ltd Middle pushing device

Also Published As

Publication number Publication date
JP2003253985A (en) 2003-09-10

Similar Documents

Publication Publication Date Title
JP2009286610A (en) Pipe body hanging gripping device
JP3774157B2 (en) Medium push jack handling device
FI72949C (en) ROERLAEGGNINGSREDSKAP.
EP4164980B1 (en) Mobile telescopic hydraulic crane
CN111572294A (en) Tire dismounting device
CN210732333U (en) Movable pneumatic sleeve thread protection dismounting device
JP6998791B2 (en) Heavy object fixing jig and heavy object fixing method using it
JP2922496B1 (en) Ground access removal method and tools for communication lines
CN218253691U (en) Welding jig equipment that overhead tank made
CN206928917U (en) Well head helps pipe device
JP2002135932A (en) Pipe connecting device, and pipe connecting method
CN111056422A (en) Lifting appliance for mounting large flywheel and using method thereof
JP3238248B2 (en) Propulsion device
JPH08269958A (en) Elevation device for working platform for pile constructing machine
JP2000282686A (en) Pipe supporting device for concrete pump
CN114542127B (en) Tunnel support machine with wide application range
JP2509231Y2 (en) Hydraulic excavator with crane device
JPS63171219A (en) Bend straightening machine
JPS5953985B2 (en) Hose guide device in fluid transfer equipment
JP2553027B2 (en) Pile driver using circular pit
JP3377810B2 (en) Pipe joining equipment
CN116985169A (en) Mechanical arm auxiliary grabbing structure suitable for construction of root piles of all-sleeve pipe-following tree
FR3123909A1 (en) On-board pole-laying crane
KR200178593Y1 (en) Device for constructing fume pipe
JPH017668Y2 (en)

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20051101

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060131

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060216

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120224

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120224

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130224

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130224

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140224

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees