JP3771871B2 - Steel pipe pile foundation and steel pipe pile foundation construction method - Google Patents
Steel pipe pile foundation and steel pipe pile foundation construction method Download PDFInfo
- Publication number
- JP3771871B2 JP3771871B2 JP2002151205A JP2002151205A JP3771871B2 JP 3771871 B2 JP3771871 B2 JP 3771871B2 JP 2002151205 A JP2002151205 A JP 2002151205A JP 2002151205 A JP2002151205 A JP 2002151205A JP 3771871 B2 JP3771871 B2 JP 3771871B2
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe pile
- filler
- pile foundation
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、鋼管杭基礎および鋼管杭基礎施工方法に関し、特に水底地盤上に構築される橋梁基礎に用いる鋼管杭基礎および鋼管杭基礎施工方法に関するものである。
【0002】
【従来の技術】
図8は橋梁における鋼管杭基礎10を示す斜視図であり、この鋼管杭基礎10は、従来の剛構造であるケーソン式基礎とは異なり、橋梁の主要部を構成する主塔1と、その下部を囲むように設けられたジャケットレグ2とを備えたジャケット型基礎3が水底地盤4上に据え付けられ、このジャケットレグ2の複数のレグ5,5,・・・をガイドとして複数の鋼管杭6,6,・・・が水底地盤4に打設して構成されたものである。
この橋梁における鋼管杭基礎10では、鋼管杭6を打設する際の鋼管杭6とレグ5との接合部におけるシール性(止水性)が重要になる。
というのは、作業者が鋼管杭6の切断作業や、プラグ溶接作業のためにこのレグ5内に入らなければならないからである。
【0003】
図9は、従来の鋼管杭基礎10の鋼管杭6とレグ5との接合部を示す断面図であり、鋼管杭6とレグ5の下端との間にゴムシール材7が装着され、前記レグ5のゴムシール材7よりわずかに上方の位置にはグラウト圧送管8が設けられている。そして、このグラウト圧送管8により鋼管杭6とレグ5との隙間に所定の高さまでグラウト(第三の充填材)9が注入されている。この接合部においては、ゴムシール材7により鋼管杭6とレグ5との接合部を止水するとともに、グラウト9注入時の漏洩防止を図っている。
【0004】
【発明が解決しようとする課題】
ところで、上述した従来の鋼管杭6とレグ5との接合部においては、ゴムシール材7により止水およびグラウト9注入時の漏洩防止を図っているが、ゴムシール材7は硬質ゴム等により構成されているために、鋼管杭6を打ち込む際の衝撃により摩耗等が生じやすく、シール材としての耐久性が不十分で、十分な止水性が得られないという問題点があった。
【0005】
また、この鋼管杭6とレグ5との接合部が水面下に位置した場合においては、ゴムシール材7ではシール材としての耐久性が不十分で、十分な止水性が得られないために、グラウト9を注入する際の止水性が不十分でグラウト9が漏洩してしまうという問題点があった。
【0006】
本発明は、上記の事情に鑑みてなされたもので、鋼管杭とレグとの接合部における止水性を向上させることができ、グラウト注入時におけるグラウトの漏洩を防止することができる鋼管杭基礎および鋼管杭基礎施工方法を提供することを目的としている。
【0007】
【課題を解決するための手段】
本発明の鋼管杭基礎および鋼管杭基礎施工方法では、上記課題を解決するため、以下の手段を採用した。
すなわち、請求項1記載の鋼管杭基礎によれば、筒状のレグと、該レグに挿通される鋼管杭との間の接合部に装着され、弾性を有するとともに環状に形成されており、かつその外側端部が前記レグの内周面と接しているとともに、その内側端部が前記鋼管杭の外周面と接している少なくとも2つのシール部材と、これらシール部材とシール部材との間に形成された充填材室と連通するとともに、該充填材室の内部に充填材を充填するための充填材圧送管と、前記充填材室と別途連通するとともに、該充填材室の内部への充填材の充填により前記充填材室の内部の水を外部に排出するための排水管と、前記排水管を介して排出された前記充填材室の内部の水を受ける排水受けと、を具備することを特徴とする。
【0008】
この鋼管杭基礎においては、シール部材とシール部材との間に充填材室が形成され、かつレグには充填材室と連通する充填材圧送管と排水管とが設けられているので、充填材圧送管を介して充填材を充填材室に充填していくと、この充填材室にあった水が排水管を介して充填材室から排出されるようになっている。
【0009】
請求項2記載の鋼管杭基礎によれば、請求項1に記載の鋼管杭基礎において、前記充填材室内への前記充填材の充填圧力は、前記シール部材が位置する場所における水圧の1.0〜1.1倍であることを特徴とする。
【0010】
この鋼管杭基礎においては、シール部材が位置する場所における水圧の1.0〜1.1倍で充填材が充填材室に充填されることとなる。
【0011】
請求項3記載の鋼管杭基礎によれば、請求項1または2に記載の鋼管杭基礎において、前記シール部材はブラシ型シールからなり、かつこれらブラシ型シールの内部には、止水性を有する第二の充填材が予め塗布されていることを特徴とする。
【0012】
この鋼管杭基礎においては、シール部材としてブラシ型シールが適用され、かつこれらブラシ型シールの内部に止水性を有する第二の充填材が予め塗布されている。
【0013】
請求項4記載の鋼管杭基礎によれば、請求項3に記載の鋼管杭基礎において、前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記後板は前記前板よりも長いことを特徴とする。
【0014】
この鋼管杭基礎においては、水底側に位置する後板が水面側に位置する前板よりも長くなるよう、すなわち後板の受圧面積が前板の受圧面積よりも大きくなるように設定されている。言い換えれば、後板にかかる水圧が前板にかかる水圧よりも大きくなる。
【0015】
請求項5記載の鋼管杭基礎によれば、請求項3に記載の鋼管杭基礎において、前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記前板の板厚は前記後板の板厚よりも厚いことを特徴とする。
【0016】
この鋼管杭基礎においては、前板の板厚が後板の板厚よりも厚くなるよう、すなわち前板の剛性が後板の剛性よりも高くなるように設定されている。
したがって、前板にかかるたとえばグラウトやグリースによる圧力に対して前板が十分な抗力を有することとなる。
【0017】
請求項6記載の鋼管杭基礎によれば、請求項3に記載の鋼管杭基礎において、前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記後板の背面と前記レグの内周面との間には支持部材が設けられていることを特徴とする。
【0018】
この鋼管杭基礎においては、たとえばグラウトやグリースが充填されることにより後板がレグ内周面側へ移動しようとしても、支持部材によりその移動が抑制され、シール部材の内側端部と鋼管杭の外周面との接触が保たれるようになっている。
【0019】
請求項7記載の鋼管杭基礎によれば、請求項3に記載の鋼管杭基礎において、前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記メッシュ部材は前記前板および前記後板よりも長いことを特徴とする。
【0020】
この鋼管杭基礎においては、メッシュ部材の内側端部が前板および後板よりも広い面積で鋼管杭の外周面と接触するようになっている。
【0021】
請求項8記載の鋼管杭基礎によれば、請求項3に記載の鋼管杭基礎において、前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつその外側端部と前記レグの内周面との間には嵩上げ部材が設けられていることを特徴とする。
【0022】
この鋼管杭基礎においては、ブラシ型シールの外側端部とレグの内周面との間に嵩上げ部材が設けられており、この嵩上げ部材の高さを変えることによりブラシ型シールの内側端部と鋼管杭の外周面との間の間隙、すなわちブラシ型シールの内側端部と鋼管杭の外周面との間の接触圧力を自由に選択できるようになっている。
【0023】
請求項9記載の鋼管杭基礎施工方法によれば、筒状のレグと、該レグに挿通される鋼管杭との間の接合部に装着され、弾性を有するとともに環状に形成されており、かつその外側端部が前記レグの内周面と接しているとともに、その内側端部が前記鋼管杭の外周面と接している少なくとも2つのシール部材と、これらシール部材とシール部材との間に形成された充填材室と、前記充填材室と連通するとともに、該充填材室の内部への充填材の充填により前記充填材室の内部の水を外部に排出するための排水管と、前記排水管を介して排出された前記充填材室の内部の水を受ける排水受けと、を具備する鋼管杭基礎を施工する際の鋼管杭基礎施工方法であって、前記充填材室に充填材を充填する段階と、前記充填材の充填により前記充填材室に存在していた水を、前記排水管を介して前記排水受けに排出する段階と、を具備していることを特徴とする。
【0024】
この鋼管杭基礎施工方法においては、シール部材とシール部材との間に形成された充填材室の内部に充填材を充填していくと、この充填材室の内部にあった水が充填材室から排出されることとなる。
【0025】
請求項10記載の鋼管杭基礎施工方法によれば、請求項9に記載の鋼管杭基礎施工方法において、前記充填材室内へ前記充填材を充填する段階の充填圧力は、前記シール部材が位置する場所における水圧の1.0〜1.1倍であることを特徴とする。
【0026】
この鋼管杭基礎施工方法においては、シール部材が位置する場所における水圧の1.0〜1.1倍で充填材が充填材室に充填されることとなる。
【0027】
請求項11記載の鋼管杭基礎施工方法によれば、請求項9または10に記載の鋼管杭基礎施工方法において、前記シール部材はブラシ型シールからなり、かつこれらブラシ型シールの内部に、止水性を有する第二の充填材を予め塗布しておくことを特徴とする。
【0028】
この鋼管杭基礎施工方法においては、シール部材としてブラシ型シールが適用され、かつこれらブラシ型シールの内部に止水性を有する第二の充填材が予め塗布されている。
【0029】
請求項12記載の鋼管杭基礎施工方法によれば、請求項9に記載の鋼管杭基礎施工方法において、前記充填材室に前記充填材が充填されるとともに、該充填材室内に存在していた水が排出された後、前記充填材室の上方に位置し、かつ前記レグの内周面と前記鋼管杭の外周面との間に存在する水を抜き取る段階と、前記レグの内周面と前記鋼管杭の外周面との間に第三の充填材を充填する段階とを具備していることを特徴とする。
【0030】
この鋼管杭基礎施工方法においては、充填材室の上方に位置し、かつレグの内周面と鋼管杭の外周面との間に存在する水が取り除かれた後、その部分にグラウトが充填される。実際の施工では水を抜き、止水位置よりも上の位置で杭を切断し、その位置に荷重伝達用のプラグを溶接施工した後にグラウトが充填される。
【0031】
【発明の実施の形態】
以下、本発明の一実施の形態について、図1および図2を参照しながら説明する。なお、従来と同一の部材には同一の符号を付している。
図1は本発明による鋼管杭基礎100のレグ5と鋼管杭6との間の接合部を示す側断面である。
【0032】
図1に示すように、鋼管杭基礎100は、レグ5と、鋼管杭6と、たとえば2つのシール部材11,12と、充填材圧送管13と、排水管14とを主たる要素として構成されたものである。
【0033】
シール部材11,12はブラシ型シールと呼ばれるものであり、1.96MPa(20kgf/cm2)程度の水圧に対しても十分な止水性を有するものである。
これらシール部材11,12は、図2に示すように、バネ鋼11a,11b,12a,12b、ワイヤブラシ11c,11c’,12c,12c’、ステンレス製のメッシュ金網11d,11d’,12d,12d’が組み合わされた構造を有するもので、レグ5の内周面5aに沿って環状に配置される上部材11e,12eと、この上部材11e,12eの下端から下方に漸次縮径するように延びて鋼管杭6の外周面6aに沿って巻回する略漏斗状の下部材11f,12fとにより構成されており、鋼管杭6とレグ5との間のズレには十分対応できる追従性を有したものである。
すなわち、シール部材11,12の弾力性により、鋼管杭6とレグ5との間にズレが生じても即座に対応可能とされている。
また、打設される鋼管杭6程度の杭長であれば、鋼管杭6の打設される際の打撃に伴う摩擦等によるシール性の低下に対しても十分な耐久性を有し、水深数十m下での止水性も十分備えている。
【0034】
前述したバネ鋼(前板)11a,12aとワイヤブラシ11c,12cとの間、メッシュ金網11d,12dとメッシュ金網11d’,12d’との間、ワイヤブラシ11c’,12c’とバネ鋼(後板)11b,12bとの間に、止水性に優れたグリース(第二の充填材)が予め塗布されていればさらに有利である。このグリースは、たとえば繊維が含有されたグリースであり、一例としては「日石三菱シールノックグリース(商品名)」が挙げられる。
【0035】
図1に示すように、充填材圧送管13は、充填材注入用ポンプ20と、シール部材11、12間に形成された充填材室21とを連通するとともに、充填材注入用ポンプ20から吐出されてきた充填材22を充填材室21内に導くためのものである。この場合の充填材22としては、特に圧送性に優れたグリースが好適である。
【0036】
このように、充填材圧送管13の一端は充填材注入用ポンプ20に接続されているとともに、その他端は充填材室21が位置するところのレグ5に接続されている。
【0037】
なお、充填材室21に充填される充填材22は、圧送性に優れたグリースに限定されるものではなく、たとえば膨潤性の高いベントナイト系の粘土モルタルや、発泡ウレタン、あるいは砂モルタルなどを充填材22として充填することもできる。
このようなモルタル材やウレタン材を充填材22として充填材室21に充填する場合、図3に示すような構成が必要となる。
図3の鋼管杭基礎200は、図1の鋼管杭基礎100に設けられた充填材圧送管13および充填材注入用ポンプ20の代わりに、充填材圧送管71、充填材注入用ポンプ72、薬剤圧送管73、薬剤注入用ポンプ74、ミキシングノズル75、および導入管76が設けられたものである。したがって、この部分以外の構成要素は図1に示すものと同じであるのでここではその説明を省略する。
【0038】
充填材圧送管71は、充填材注入用ポンプ72と、充填材室21の入口近傍に配置されたミキシングノズル75とを連通するとともに、充填材注入用ポンプ72から吐出されてきた充填材をミキシングノズル75内に導くためのものである。充填材としては、たとえばモルタルやウレタンなどである。
また、薬剤圧送管73は、薬剤注入用ポンプ74と、ミキシングノズル75とを連通するとともに、薬剤注入用ポンプ74から吐出されてきた薬剤をミキシングノズル75内に導くためのものである。薬剤としては、たとえばゲル化剤などである。
ミキシングノズル75は、充填材圧送管71を介して充填材注入用ポンプ72から吐出されてきた充填材と、薬剤圧送管73を介して薬剤注入用ポンプ74から吐出されてきた薬剤とを均一に混合するものである。
ミキシングノズル75で混ぜ合わせられた充填材22は、導入管76を介して充填材室21内に導かれるようになっている。
【0039】
このように、充填材室21内に粘土モルタルや、発泡ウレタン、あるいは砂モルタルなどのモルタル材やウレタン材を充填材22として充填することにより、この部分のレグ5と鋼管杭6との接合部を剛な材料で充填することができ、止水性を向上させることができる。
【0040】
排水管14は、充填材室21と、たとえば水面上に設置された排水受け23とを連通するとともに、充填材室21から導出された水を排水受け23に導くためのものである。
すなわち、排水管14の一端は充填材室21が位置するところのレグ5に接続されているとともに、その他端は排水受け23に接続されている。
【0041】
つぎに、この鋼管杭基礎100を施工する際の鋼管杭基礎施工方法について説明する。
まず、予めシール部材11,12の上部材11e,12eを、レグ5の内周面5aの接合部に当たる部分に装着しておく。
ついで、レグ5をガイドとして鋼管杭6をこのレグ5に挿入する。この際、シール部材11,12の下部材11f,12fは軸心に向かって延出しているので、挿入される鋼管杭6によって押し広げられて、その弾性力により鋼管杭6に圧接される。
【0042】
つづいて、この鋼管杭6を水底地盤に打設する。打設完了後、充填材圧送管13を介して充填材注入用ポンプ20から充填材室21内に充填材22を圧送するとともに、充填材室21内に充満していた水が圧送されてきた充填材22により押し出され、排水管14を介して排水受け23に排出されることとなる。
このようにして充填材室21が充填材22で充満されれば、止水が完全に行われたことになる。
また、充填材22の充填圧力としては、これらシール部材11,12が位置する場所における水圧の1.0倍〜1.1倍が特に好適である。水圧の検知方法としては、たとえばこれらシール部材11,12が位置する場所の水深から求めることもできるし、これらシール部材11,12が位置する場所のレグ5の外周面に設けられた圧力センサなどによって求めることができる。
【0043】
そしてつぎに、充填材室21の上側に位置するとともに、レグ5の内周面5aと鋼管杭6の外周面6aとの間に介在している水を、たとえば汲み上げポンプ(図示せず)およびこの汲み上げポンプに接続されたホース(図示せず)などを用いて外部に排出する。
【0044】
そして、充填材室21よりも上方のレグ5と鋼管杭6との隙間に所定高さまでグラウト(第三の充填材)9を注入する。
【0045】
このような鋼管杭基礎100および鋼管杭基礎施工方法によれば、シール部材11,12のそれぞれの弾性、および充填材室21に充填された充填材22により止水性を格段に向上させることができる。したがって、シール部材11,12によりグラウト9の漏洩が防止されるので、グラウト9が外部に漏洩するおそれがない。
【0046】
以上説明したように、本実施形態によれば、レグ5と鋼管杭6との間の接合部に少なくとも2つのシール部材11,12を装着し、これらシール部材11,12の間に形成される充填材室21に充填材22を導くための充填材圧送管13と、充填材室21内の水を外部に導くための排水管14とをレグ5に設けることにより、レグ5と鋼管杭6との間の止水性を大幅に向上させることができる。
【0047】
さて、図4に示すように、図2を用いて説明したシール部材11,12の、下側(水底側)に位置するバネ鋼11b,12bの長さが、上側(水面側)に位置するバネ鋼11a,12aの長さよりも長くなるように設定されていればさらに有利である。
すなわち、バネ鋼11a,12a、ワイヤブラシ11c,12c、メッシュ金網11d,12d、メッシュ金網11d’,12d’、ワイヤブラシ11c’,12c’、バネ鋼11b,12bの長さは、上側から下側にいくにしたがって、徐々に長くなり、これらの先端がすべて鋼管杭6の外周面6aと密着(あるいは接触)するように構成されている。
【0048】
このような構成により、シール部材11,12の内側端部(先端部)と鋼管杭6の外周面6aとの接触面積がより大きくなり、この部分のシール性(止水性)をさらに向上させることができる。
また、バネ鋼11b,12bの受圧面積がバネ鋼11a,12aの受圧面積よりも大きくなる、すなわちバネ鋼11b,12bにかかる水圧がバネ鋼11a,12aにかかる水圧よりも大きくなるため、たとえばシール部材11,12の上側にグリースやグラウトが充填されたとしても、これらの充填圧力に対して抗力を有することとなる。
これにより、これらグリースやグラウトがシール部材11,12の内側端部(先端部)と鋼管杭6の外周面6aとの間から下側に漏れ出すことを防止することもできる。
【0049】
シール部材11,12の内側端部(先端部)と鋼管杭6の外周面6aとの接触面積をさらに大きくするには、ワイヤブラシ11c,11c’,12c,12c’の本数を増やして、このワイヤブラシ11c,11c’,12c,12c’の部分の厚みを厚くしてやればよい。
一方、このようにワイヤブラシワイヤブラシ11c,11c’,12c,12c’の本数を増やすことにより、このワイヤブラシ11c,11c’,12c,12c’の部分の剛性が高められる。
この部分の剛性が高められることにより、たとえばシール部材11,12の上側にグリースやグラウトが充填されたとしても、これらの充填圧力に対して十分な抗力を有することとなる。
したがって、これらグリースやグラウトがシール部材11,12の内側端部(先端部)と鋼管杭6の外周面6aとの間から下側に漏れ出すことを防止することができる。
【0050】
ワイヤブラシワイヤブラシ11c,11c’,12c,12c’の本数を増やしてワイヤブラシ11c,11c’,12c,12c’の部分の剛性を高める代わりに、バネ鋼11a,12aおよび/またはバネ鋼11b,12bの板厚を厚くしてバネ鋼11a,12aおよび/またはバネ鋼11b,12b自体の剛性を高めるようにしても同様の効果を得ることができる。
この場合、シール部材11,12の内側端部(先端部)と鋼管杭6の外周面6aとの接触面積は図4に示すものと同じになってしまうが、これらシール部材11,12の上側に充填された充填材による充填圧力に対しては十分な抗力を有するようになる。
【0051】
シール部材11,12の上側に充填された充填材による充填圧力に対する抗力を増加させる構成としては図5に示すようなものもある。
図5は、図4に示すシール部材11,12のバネ鋼11b,12bの背面(水底側の面)とレグ5の内周面5aとの間にバックアップ部材(支持部材)50を設けた状態を示す図である。
バックアップ部材50は、支持部51と固定部52とから構成されたもので、断面T字形状を有する部材であって、レグ5の内周面5aに沿ってシール部材11,12と略平行に配置されたものである。
支持部51はバネ鋼11b,12bの背面を支持する板状部材で、その表面全体がバネ鋼11b,12bの背面と接するように構成されている。
固定部52はレグ5の内周面5aと支持部51とを連結するものであって、基端部がレグ5の内周面5aに溶接固定されるとともに、他端部が支持部51の背面に溶接固定されたものである。
【0052】
このような構成により、バネ鋼11b,12bのレグ5の内周面5a側への移動が制止されるとともに、バネ鋼11a,12a、ワイヤブラシ11c,12c、メッシュ金網11d,12d、メッシュ金網11d’,12d’、ワイヤブラシ11c’,12c’のレグ5の内周面5a側への移動も抑制される。
すなわち、シール部材11,12の上側に充填された充填材による充填圧力に対する抗力が増加されることとなる。
【0053】
さらに、シール部材11,12と鋼管杭6の外周面6aとの接触面積を大きくする構成として、メッシュ金網11d,11d’,12d,12d’の長さを、バネ鋼11b,11b’,12b,12b’の長さよりも長くして、これらメッシュ金網11d,11d’,12d,12d’の先端部が鋼管杭6の外周面6aと面で接触するようにするとさらに有利である。
メッシュ金網11d,11d’,12d,12d’の長さとしては、図6に示すように、鋼管杭6が打ち込まれる(打ち込まれた)状態で、メッシュ金網11d,11d’,12d,12d’の先端部がバネ鋼11b,12bの先端よりも下側に延在していれば好適である。
このようにメッシュ金網11d,11d’,12d,12d’の先端部がバネ鋼11b,12bの先端よりも下側に延在していることにより、メッシュ金網11d,11d’,12d,12d’の先端部が鋼管杭6の外周面6aと広い範囲にわたって面で接触するようになるとともに、バネ鋼11b,12bの先端と鋼管杭6の外周面6aとの間に位置するメッシュ金網11d,11d’,12d,12d’が、バネ鋼11b,12bの先端により鋼管杭6の外周面6aの側に押しつけられることとなる。
【0054】
このような構成により、この部分のシール性(止水性)をより向上させることができる。
また、これらメッシュ金網11d,11d’,12d,12d’の網目に、前述した止水性に優れたグリース(第二の充填材)を予め塗布しておけばさらに好適である。
これによりメッシュ金網11d,11d’,12d,12d’の先端部が鋼管杭6の外周面6aと広い範囲にわたって密着するようになり、止水性をさらに向上させることができる。
【0055】
また、メッシュ金網11d,11d’,12d,12d’の一方あるいは両方を、バネ鋼11a,12aとワイヤブラシ11c,12cとの間、すなわちバネ鋼11a,12aに接触させて設けるようにすることもできる。
これによりメッシュ金網11d,11d’,12d,12d’の一方あるいは両方が、鋼管杭6の外周面6aと最も広い範囲で接触するようになるとともに、バネ鋼11a,12aと鋼管杭6の外周面6aとの隙間をメッシュ金網が塞ぐようになるので、止水性をさらに向上させることができる。
【0056】
図7に示すように、シール部材11,12が嵩上げ部材70を介してレグ5の内周面5aに取り付けられるようにしても良い。
嵩上げ部材70はシール部材11,12と同様、レグ5の内周面5aに沿って環状に配置されたものであり、レグ5の内周面5aに溶接固定されたものである。
嵩上げ部材70とレグ5の内周面5aとの間、嵩上げ部材70と上部材11e,12eとの間には、隙間が生じないようになっている。
このような嵩上げ部材70により、嵩上げ部材70の上面70aと鋼管杭6の外周面6aとの間隙を、たとえば70mm程度にすると有利である。
【0057】
このように、嵩上げ部材70の上面70aと鋼管杭6の外周面6aとの間隙を狭めることにより、シール部材11,12の下部材11f,12fが鋼管杭6の外周面6aに押しつけられながら接触するようになり、接触面積が増加して止水性を向上させることができる。
また、シール部材11,12の下部材11f,12fが鋼管杭6の外周面6aに十分押しつけられながら接触させられるため、下部材11f,12fが元の形に戻ろうとする復元力が高められ、これによりシール部材11,12の上側に充填された充填材による充填圧力に対する抗力も高められることとなる。
【0058】
なお、図2、図4ないし図7を用いて説明してきた内容およびこれに付随して説明した内容は、必要に応じて適宜組み合わせることができる。
【0059】
以上、本発明の鋼管杭基礎および鋼管杭基礎施工方法について図面に基づいて説明してきたが、具体的な構成は本実施形態に限定されるものではなく、本発明の要旨を逸脱しない範囲内で変形・変更実施可能である。
たとえば、シール部材はブラシ型シールに限定されるものではなく、同様の機能を有するものであればどのようなものであっても良い。
【0060】
また、本発明ではシール部材を接合部に2つ配置したものを一例として説明してきたが、これに限定されるものではなく、3つ以上配置することももちろん可能である。ただしこの際、シール部材とシール部材との間に形成される各充填材室に対して充填材圧送管および排水管を設けるようにすることが望ましい。
【0061】
なお、今回の施工試験では、シール部材11とシール部材12との距離(ブラシピッチ)、すなわち上部材11eの上端面11gと上部材12eの上端面12gとの距離を365mm、ワイヤブラシの最大長さを300mm、バネ鋼(後板)11a’,12a’とレグ5の内周面5aとのなす角θを50゜、レグ5の内周面5aと鋼管杭6の外周面6aとの間隙を150mmとして実施し、極めて良好な止水性を確認することができた。
【0062】
【発明の効果】
本発明の鋼管杭基礎および鋼管杭基礎施工方法によれば、以下の効果を奏する。
請求項1記載の鋼管杭基礎によれば、シール部材とシール部材との間に充填材室が形成され、かつレグには充填材室と連通する充填材圧送管と排水管とが設けられているので、充填材圧送管を介して充填材を充填材室に充填していくと、この充填材室にあった水が排水管を介して充填材室から排出されるようになっており、充填材の水中への漏洩を防止することができ、止水性を格段に向上させることができるとともに、この止水性の向上によりグラウトの充填室内への漏洩を防止し、後に続く杭の切断作業やプラグの溶接作業をドライなエリアで作業することができる。
【0063】
請求項2記載の鋼管杭基礎によれば、シール部材が位置する場所における水圧の1.0〜1.1倍で充填材が充填材室に充填されることとなるので、水が充填材室の内部に浸入することを確実に防止することができる。
【0064】
請求項3記載の鋼管杭基礎によれば、シール部材としてブラシ型シールが適用され、かつこれらブラシ型シールの内部に止水性を有する第二の充填材が予め塗布されているので、充填材室内への水の浸入、充填材室外への水および/または充填材の漏洩を確実に防止することができて、止水性をさらに向上させることができる。
【0065】
請求項4記載の鋼管杭基礎によれば、水底側に位置する後板が水面側に位置する前板よりも長くなるよう、すなわち後板の受圧面積が前板の受圧面積よりも大きくなるように設定されているので、充填材の充填圧力に対する抗力が高められ、シール部材の内側端部(先端部)と鋼管杭の外周面との間から下側に充填材が漏れ出すことを防止することができる。
【0066】
請求項5記載の鋼管杭基礎によれば、前板の板厚が後板の板厚よりも厚くなるよう、すなわち前板の剛性が後板の剛性よりも高くなるように設定されているので、前板によって充填材の充填圧力を受け止めることができて、シール部材の内側端部(先端部)と鋼管杭の外周面との間から下側に充填材が漏れ出すことを防止することができる。
【0067】
請求項6記載の鋼管杭基礎によれば、充填材が充填されることにより後板がレグ内周面側へ移動しようとしても、支持部材によりその移動が抑制され、シール部材の内側端部と鋼管杭の外周面との接触が保たれるようになっているので、止水性を向上させることができる。
【0068】
請求項7記載の鋼管杭基礎によれば、メッシュ部材の内側端部が前板および後板よりも広い面積で鋼管杭の外周面と接触するようになっているので、止水性をさらに向上させることができる。
【0069】
請求項8記載の鋼管杭基礎によれば、ブラシ型シールの外側端部とレグの内周面との間に嵩上げ部材が設けられており、この嵩上げ部材の高さを変えることによりブラシ型シールの内側端部と鋼管杭の外周面との間の間隙、すなわちブラシ型シールの内側端部と鋼管杭の外周面との間の接触圧力を自由に選択できるようになっているので、必要に応じて所望の接触圧力を得ることができ、止水を確実に行うことができる。
【0070】
請求項9記載の鋼管杭基礎施工方法によれば、シール部材とシール部材との間に形成された充填材室の内部に充填材を充填していくと、この充填材室の内部にあった水が充填材室から排出されることとなるので、充填材の水中への漏洩を防止することができ、止水性を格段に向上させることができるとともに、この止水性の向上によりグラウトの充填室内への漏洩を防止することができる。
【0071】
請求項10記載の鋼管杭基礎施工方法によれば、シール部材が位置する場所における水圧の1.0〜1.1倍で充填材が充填材室に充填されることとなるので、水が充填材室の内部に浸入することを確実に防止することができる。
【0072】
請求項11記載の鋼管杭基礎施工方法によれば、シール部材としてブラシ型シールが適用され、かつこれらブラシ型シールの内部に止水性を有する第二の充填材が予め塗布されているので、充填材室内への水の浸入、充填材室外への水および/または充填材の漏洩を確実に防止することができて、止水性をさらに向上させることができる。
【0073】
請求項12記載の鋼管杭基礎施工方法によれば、充填材室の上方に位置し、かつレグの内周面と鋼管杭の外周面との間に存在する水が取り除かれた後、杭を切断し、プラグの溶接作業を行うことから作業エリアをドライに保つことができる上、その部分にグラウトが充填されることとなるので、グラウトの性能を最大限発揮させることができて、十分な強度を有する基礎を構築することができる。
【図面の簡単な説明】
【図1】 本発明による鋼管杭基礎の鋼管杭とレグとの接合部の一実施形態を示す側断面図である。
【図2】 図1におけるシール部材の一つを拡大した拡大図である。
【図3】 本発明による鋼管杭基礎の鋼管杭とレグとの接合部の他の実施形態を示す側断面図である。
【図4】 本発明による鋼管杭基礎の別の実施形態を示す図であって、図2同様、シール部材の一つを拡大した拡大図である。
【図5】 本発明による鋼管杭基礎のさらに別の実施形態を示す図であって、図2同様、シール部材の一つを拡大した拡大図である。
【図6】 本発明による鋼管杭基礎のさらに別の実施形態を示す図であって、図2同様、シール部材の一つを拡大した拡大図である。
【図7】 本発明による鋼管杭基礎のさらに別の実施形態を示す図であって、図2同様、シール部材の一つを拡大した拡大図である。
【図8】 橋梁における鋼管杭基礎を示す斜視図である。
【図9】 従来の鋼管杭基礎の鋼管杭とレグとの接合部を示す側断面図である。
【符号の説明】
5 レグ
5a 内周面
6 鋼管杭
6a 外周面
9 グラウト(第三の充填材)
10 鋼管杭基礎
11 シール部材
11a バネ鋼(前板)
11b バネ鋼(後板)
11c ワイヤブラシ(ブラシ)
11c’ワイヤブラシ(ブラシ)
11d メッシュ金網(メッシュ部材)
11d’メッシュ金網(メッシュ部材)
12 シール部材
12a バネ鋼(前板)
12b バネ鋼(後板)
12c ワイヤブラシ(ブラシ)
12c’ワイヤブラシ(ブラシ)
12d メッシュ金網(メッシュ部材)
12d’メッシュ金網(メッシュ部材)
13 充填材圧送管
14 排水管
21 充填材室
22 充填材
50 バックアップ部材(支持部材)
70 嵩上げ部材
100 鋼管杭基礎
200 鋼管杭基礎[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a steel pipe pile foundation and a steel pipe pile foundation construction method, and more particularly to a steel pipe pile foundation and a steel pipe pile foundation construction method used for a bridge foundation constructed on a submerged ground.
[0002]
[Prior art]
FIG. 8 is a perspective view showing a steel
In the steel
This is because an operator must enter the
[0003]
FIG. 9 is a cross-sectional view showing a joint portion between the
[0004]
[Problems to be solved by the invention]
By the way, in the junction part of the conventional
[0005]
Further, when the joint between the
[0006]
The present invention has been made in view of the above circumstances, and can improve the water stoppage at the joint between the steel pipe pile and the leg, and can prevent the leakage of the grout at the time of grout injection. It aims at providing the steel pipe pile foundation construction method.
[0007]
[Means for Solving the Problems]
In the steel pipe pile foundation and the steel pipe pile foundation construction method of the present invention, the following means are adopted in order to solve the above problems.
That is, according to the steel pipe pile foundation according to claim 1, the steel pipe pile foundation is attached to a joint portion between the cylindrical leg and the steel pipe pile inserted through the leg, has elasticity and is formed in an annular shape, and At least two seal members whose outer end portions are in contact with the inner peripheral surface of the leg and whose inner end portions are in contact with the outer peripheral surface of the steel pipe pile, and formed between these seal members and the seal member And a filler pressure feed pipe for filling the inside of the filler material chamber with a filler, and a separate material communicating with the filler material chamber, and a filler material inside the filler material chamber. A drain pipe for discharging water inside the filler chamber to the outside by filling A drain receiver for receiving the water inside the filler chamber discharged through the drain pipe; It is characterized by comprising.
[0008]
In this steel pipe pile foundation, a filler material chamber is formed between the seal member and the seal member, and the leg is provided with a filler pressure feeding tube and a drain pipe communicating with the filler material chamber. When the filler material is filled into the filler material chamber via the pressure feed pipe, the water in the filler material chamber is discharged from the filler material chamber via the drain tube.
[0009]
According to the steel pipe pile foundation according to
[0010]
In this steel pipe pile foundation, the filler is filled in the filler chamber at 1.0 to 1.1 times the water pressure at the place where the seal member is located.
[0011]
According to the steel pipe pile foundation according to
[0012]
In this steel pipe pile foundation, a brush-type seal is applied as a seal member, and a second filler having a water-stopping property is applied in advance inside the brush-type seal.
[0013]
According to the steel pipe pile foundation according to claim 4, in the steel pipe pile foundation according to
[0014]
In this steel pipe pile foundation, the rear plate located on the water bottom side is set to be longer than the front plate located on the water surface side, that is, the pressure receiving area of the rear plate is set to be larger than the pressure receiving area of the front plate. . In other words, the water pressure applied to the rear plate is larger than the water pressure applied to the front plate.
[0015]
According to the steel pipe pile foundation according to
[0016]
In this steel pipe pile foundation, the thickness of the front plate is set to be thicker than the thickness of the rear plate, that is, the rigidity of the front plate is set to be higher than the rigidity of the rear plate.
Therefore, for example, the front plate has a sufficient resistance against pressure caused by grout or grease applied to the front plate.
[0017]
According to the steel pipe pile foundation according to
[0018]
In this steel pipe pile foundation, for example, even if the rear plate tries to move toward the inner periphery of the leg by filling with grout or grease, the movement is suppressed by the support member, and the inner end of the seal member and the steel pipe pile Contact with the outer peripheral surface is maintained.
[0019]
According to the steel pipe pile foundation according to
[0020]
In this steel pipe pile foundation, the inner end of the mesh member comes into contact with the outer peripheral surface of the steel pipe pile over a larger area than the front plate and the rear plate.
[0021]
According to the steel pipe pile foundation according to
[0022]
In this steel pipe pile foundation, a raising member is provided between the outer end portion of the brush-type seal and the inner peripheral surface of the leg, and the inner end portion of the brush-type seal is changed by changing the height of the raising member. The gap between the outer peripheral surface of the steel pipe pile, that is, the contact pressure between the inner end of the brush-type seal and the outer peripheral surface of the steel pipe pile can be freely selected.
[0023]
According to the steel pipe pile foundation construction method according to
[0024]
In this steel pipe pile foundation construction method, when the filler is filled in the filler chamber formed between the seal members, the water inside the filler chamber is filled with the filler chamber. It will be discharged from.
[0025]
According to the steel pipe pile foundation construction method according to
[0026]
In this steel pipe pile foundation construction method, the filler is filled into the filler chamber at 1.0 to 1.1 times the water pressure at the place where the seal member is located.
[0027]
According to the steel pipe pile foundation construction method according to
[0028]
In this steel pipe pile foundation construction method, a brush-type seal is applied as a seal member, and a second filler having a water-stopping property is applied in advance inside the brush-type seal.
[0029]
According to the steel pipe pile foundation construction method according to
[0030]
In this steel pipe pile foundation construction method, the water located between the inner peripheral surface of the leg and the outer peripheral surface of the steel pipe pile is removed, and then that portion is filled with grout. The In actual construction, water is drained, the pile is cut at a position above the water stop position, and a load transmission plug is welded to that position, and then the grout is filled.
[0031]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to FIG. 1 and FIG. In addition, the same code | symbol is attached | subjected to the member same as the past.
FIG. 1 is a side cross-section showing a joint between a
[0032]
As shown in FIG. 1, the steel
[0033]
The
As shown in FIG. 2, the
That is, due to the elasticity of the
In addition, if the pile length is about the
[0034]
Between the aforementioned spring steel (front plate) 11a, 12a and the
[0035]
As shown in FIG. 1, the filler
[0036]
In this way, one end of the
[0037]
The filling
When filling such a mortar material or urethane material into the
The steel
[0038]
The
The
The mixing
The
[0039]
Thus, by filling the
[0040]
The
That is, one end of the
[0041]
Below, the steel pipe pile foundation construction method at the time of constructing this steel
First, the
Next, the
[0042]
Subsequently, this
If the
Further, the filling pressure of the
[0043]
Next, water located between the inner
[0044]
Then, a grout (third filler) 9 is poured into the gap between the
[0045]
According to the steel
[0046]
As described above, according to the present embodiment, at least two
[0047]
Now, as shown in FIG. 4, the lengths of the spring steels 11b and 12b located on the lower side (water bottom side) of the
That is, the lengths of the spring steels 11a and 12a, the
[0048]
With such a configuration, the contact area between the inner ends (tips) of the
Further, since the pressure receiving areas of the spring steels 11b and 12b are larger than the pressure receiving areas of the spring steels 11a and 12a, that is, the water pressure applied to the spring steels 11b and 12b is larger than the water pressure applied to the spring steels 11a and 12a. Even if grease or grout is filled on the upper side of the
Thereby, it is also possible to prevent the grease and grout from leaking downward from between the inner end portions (tip portions) of the
[0049]
In order to further increase the contact area between the inner ends (tips) of the
On the other hand, by increasing the number of wire
By increasing the rigidity of this portion, for example, even if grease or grout is filled on the upper side of the
Therefore, these greases and grouts can be prevented from leaking downward from between the inner end portions (tip portions) of the
[0050]
Instead of increasing the number of
In this case, the contact area between the inner ends (tips) of the
[0051]
As a configuration for increasing the resistance against the filling pressure by the filler filled on the upper side of the
FIG. 5 shows a state in which a backup member (support member) 50 is provided between the back surface (water bottom side surface) of the
The
The
The fixing
[0052]
With such a configuration, the movement of the spring steels 11b and 12b to the inner
That is, the resistance against the filling pressure by the filler filled on the upper side of the
[0053]
Furthermore, as a configuration for increasing the contact area between the
As shown in FIG. 6, the lengths of the mesh wire meshes 11d, 11d ′, 12d, and 12d ′ are those of the mesh wire meshes 11d, 11d ′, 12d, and 12d ′ in a state in which the
Thus, the
[0054]
With such a configuration, the sealability (waterstop) of this portion can be further improved.
Further, it is more preferable that the above-described grease (second filler) excellent in water-stopping properties is applied in advance to the mesh of the
Thereby, the front-end | tip part of mesh metal-
[0055]
Further, one or both of the mesh wire meshes 11d, 11d ′, 12d, and 12d ′ may be provided between the spring steels 11a and 12a and the
As a result, one or both of the mesh wire meshes 11d, 11d ′, 12d, and 12d ′ come into contact with the outer
[0056]
As shown in FIG. 7, the
Like the sealing
There is no gap between the raising
With such a raising
[0057]
In this way, by narrowing the gap between the
Moreover, since the
[0058]
Note that the content described with reference to FIGS. 2 and 4 to 7 and the content described accompanying this can be combined as appropriate.
[0059]
As mentioned above, although the steel pipe pile foundation of this invention and the steel pipe pile foundation construction method have been demonstrated based on drawing, a specific structure is not limited to this embodiment, In the range which does not deviate from the summary of this invention. Modifications and changes can be made.
For example, the seal member is not limited to a brush-type seal, and may be any member as long as it has a similar function.
[0060]
In the present invention, the case where two seal members are arranged at the joint has been described as an example. However, the present invention is not limited to this example, and it is of course possible to arrange three or more. However, at this time, it is desirable to provide a filler pressure feeding pipe and a drain pipe for each filler chamber formed between the seal member and the seal member.
[0061]
In this construction test, the distance (brush pitch) between the
[0062]
【The invention's effect】
The steel pipe pile foundation and the steel pipe pile foundation construction method of the present invention have the following effects.
According to the steel pipe pile foundation of claim 1, the filler chamber is formed between the seal member and the seal member, and the leg is provided with the filler pumping tube and the drain pipe communicating with the filler chamber. Therefore, when the filler is filled into the filler chamber via the filler pumping pipe, the water in the filler chamber is discharged from the filler chamber via the drain pipe, The leakage of the filler into the water can be prevented, and the water stoppage can be remarkably improved. In addition, the improvement of the water stoppage prevents leakage of the grout into the filling chamber, and the subsequent pile cutting work and Plug welding work can be done in a dry area.
[0063]
According to the steel pipe pile foundation according to
[0064]
According to the steel pipe pile foundation according to
[0065]
According to the steel pipe pile foundation according to claim 4, the rear plate located on the water bottom side is longer than the front plate located on the water surface side, that is, the pressure receiving area of the rear plate is larger than the pressure receiving area of the front plate. Therefore, the resistance against the filling pressure of the filler is increased, and the filler is prevented from leaking downward from between the inner end (tip) of the seal member and the outer peripheral surface of the steel pipe pile. be able to.
[0066]
According to the steel pipe pile foundation of
[0067]
According to the steel pipe pile foundation according to
[0068]
According to the steel pipe pile foundation of
[0069]
According to the steel pipe pile foundation of
[0070]
According to the steel pipe pile foundation construction method of
[0071]
According to the steel pipe pile foundation construction method of
[0072]
According to the steel pipe pile foundation construction method of
[0073]
According to the steel pipe pile foundation construction method according to
[Brief description of the drawings]
FIG. 1 is a side sectional view showing an embodiment of a joint between a steel pipe pile and a leg of a steel pipe pile foundation according to the present invention.
FIG. 2 is an enlarged view of one of the seal members in FIG.
FIG. 3 is a side sectional view showing another embodiment of a joint portion between a steel pipe pile and a leg of a steel pipe pile foundation according to the present invention.
FIG. 4 is a view showing another embodiment of the steel pipe pile foundation according to the present invention, and is an enlarged view of one of the seal members as in FIG.
5 is a view showing still another embodiment of the steel pipe pile foundation according to the present invention, and is an enlarged view of one of the seal members as in FIG. 2. FIG.
6 is a view showing still another embodiment of the steel pipe pile foundation according to the present invention, and is an enlarged view of one of the seal members as in FIG.
7 is a view showing still another embodiment of the steel pipe pile foundation according to the present invention, and is an enlarged view of one of the seal members as in FIG. 2. FIG.
FIG. 8 is a perspective view showing a steel pipe pile foundation in a bridge.
FIG. 9 is a side sectional view showing a joint portion between a steel pipe pile and a leg of a conventional steel pipe pile foundation.
[Explanation of symbols]
5 legs
5a Inner peripheral surface
6 Steel pipe pile
6a outer peripheral surface
9 Grout (third filler)
10 Steel pipe pile foundation
11 Seal member
11a Spring steel (front plate)
11b Spring steel (rear plate)
11c Wire brush (brush)
11c 'wire brush (brush)
11d mesh wire mesh (mesh member)
11d 'mesh wire mesh (mesh member)
12 Seal member
12a Spring steel (front plate)
12b Spring steel (rear plate)
12c Wire brush (brush)
12c 'wire brush (brush)
12d mesh wire (mesh member)
12d 'mesh wire mesh (mesh member)
13 Filler pressure feeding tube
14 Drain pipe
21 Filling material chamber
22 Filler
50 Backup member (support member)
70 Raising member
100 steel pipe pile foundation
200 Steel pipe pile foundation
Claims (12)
これらシール部材とシール部材との間に形成された充填材室と連通するとともに、該充填材室の内部に充填材を充填するための充填材圧送管と、
前記充填材室と別途連通するとともに、該充填材室の内部への充填材の充填により前記充填材室の内部の水を外部に排出するための排水管と、
前記排水管を介して排出された前記充填材室の内部の水を受ける排水受けと、を具備することを特徴とする鋼管杭基礎。It is attached to the joint between the cylindrical leg and the steel pipe pile inserted through the leg, has elasticity and is formed in an annular shape, and its outer end is in contact with the inner peripheral surface of the leg And at least two sealing members whose inner ends are in contact with the outer peripheral surface of the steel pipe pile,
A filler pumping tube for communicating with the filler chamber formed between the seal member and the seal member, and for filling the filler into the filler chamber;
A drain pipe for communicating with the filler chamber separately, and for discharging water inside the filler chamber to the outside by filling the filler chamber with the filler;
A steel pipe pile foundation comprising: a drain receiver that receives the water inside the filler chamber discharged through the drain pipe .
前記充填材室内への前記充填材の充填圧力は、前記シール部材が位置する場所における水圧の1.0〜1.1倍であることを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 1,
The steel pipe pile foundation characterized in that the filling pressure of the filling material into the filling material chamber is 1.0 to 1.1 times the water pressure at the place where the seal member is located.
前記シール部材はブラシ型シールからなり、かつこれらブラシ型シールの内部には、止水性を有する第二の充填材が予め塗布されていることを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 1 or 2,
The steel pipe pile foundation characterized in that the seal member comprises a brush-type seal, and a second filler having a water-stopping property is applied in advance inside the brush-type seal.
前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記後板は前記前板よりも長いことを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 3,
The brush type seal includes a front plate located on the water surface side into which the steel pipe pile is inserted, a rear plate located on the water bottom side, and a plurality of brushes provided between the front plate and the rear plate. And a plate-like mesh member provided in the brush and extending substantially parallel to the front plate and the rear plate, and the rear plate is longer than the front plate. Steel pipe pile foundation.
前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記前板の板厚は前記後板の板厚よりも厚いことを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 3,
The brush type seal includes a front plate located on the water surface side into which the steel pipe pile is inserted, a rear plate located on the water bottom side, and a plurality of brushes provided between the front plate and the rear plate. A plate-like mesh member provided in the brush and extending substantially parallel to the front plate and the rear plate, and the thickness of the front plate is larger than the thickness of the rear plate. Steel pipe pile foundation characterized by being thick.
前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記後板の背面と前記レグの内周面との間には支持部材が設けられていることを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 3,
The brush type seal includes a front plate located on the water surface side into which the steel pipe pile is inserted, a rear plate located on the water bottom side, and a plurality of brushes provided between the front plate and the rear plate. A plate-like mesh member provided in the brush and extending substantially parallel to the front plate and the rear plate, and between the rear surface of the rear plate and the inner peripheral surface of the leg. A steel pipe pile foundation characterized by having a support member.
前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつ前記メッシュ部材は前記前板および前記後板よりも長いことを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 3,
The brush type seal includes a front plate located on the water surface side into which the steel pipe pile is inserted, a rear plate located on the water bottom side, and a plurality of brushes provided between the front plate and the rear plate. A plate-like mesh member provided in the brush and extending substantially parallel to the front plate and the rear plate, and the mesh member is longer than the front plate and the rear plate Steel pipe pile foundation characterized by.
前記ブラシ型シールは、前記鋼管杭が挿入されてくる水面側に位置する前板と、水底側に位置する後板と、これら前板と後板との間に設けられた多数本のブラシと、該ブラシ内に設けられるとともに前記前板および前記後板に対して略平行に延在する板状のメッシュ部材とを具備し、かつその外側端部と前記レグの内周面との間には嵩上げ部材が設けられていることを特徴とする鋼管杭基礎。In the steel pipe pile foundation according to claim 3,
The brush type seal includes a front plate located on the water surface side into which the steel pipe pile is inserted, a rear plate located on the water bottom side, and a plurality of brushes provided between the front plate and the rear plate. A plate-like mesh member provided in the brush and extending substantially parallel to the front plate and the rear plate, and between the outer end portion and the inner peripheral surface of the leg. Is a steel pipe pile foundation characterized in that a raising member is provided.
これらシール部材とシール部材との間に形成された充填材室と、
前記充填材室と連通するとともに、該充填材室の内部への充填材の充填により前記充填材室の内部の水を外部に排出するための排水管と、
前記排水管を介して排出された前記充填材室の内部の水を受ける排水受けと、を具備する鋼管杭基礎を施工する際の鋼管杭基礎施工方法であって、
前記充填材室に充填材を充填する段階と、
前記充填材の充填により前記充填材室に存在していた水を、前記排水管を介して前記排水受けに排出する段階と、を具備していることを特徴とする鋼管杭基礎施工方法。It is attached to the joint between the cylindrical leg and the steel pipe pile inserted through the leg, has elasticity and is formed in an annular shape, and its outer end is in contact with the inner peripheral surface of the leg And at least two sealing members whose inner ends are in contact with the outer peripheral surface of the steel pipe pile,
A filler chamber formed between the seal member and the seal member;
A drain pipe for communicating with the filler chamber and for discharging water inside the filler chamber to the outside by filling the filler chamber with the filler;
A steel pipe pile foundation construction method for constructing a steel pipe pile foundation comprising a drain receiver that receives water inside the filler chamber discharged through the drain pipe ,
Filling the filler chamber with a filler;
Discharging the water existing in the filler chamber by filling the filler into the drain receptacle through the drain pipe, and a steel pipe pile foundation construction method.
前記充填材室内へ前記充填材を充填する段階の充填圧力は、前記シール部材が位置する場所における水圧の1.0〜1.1倍であることを特徴とする鋼管杭基礎施工方法。In the steel pipe pile foundation construction method according to claim 9,
The steel pipe pile foundation construction method, wherein a filling pressure at a stage of filling the filler into the filler chamber is 1.0 to 1.1 times a water pressure at a place where the seal member is located.
前記シール部材はブラシ型シールからなり、かつこれらブラシ型シールの内部に、止水性を有する第二の充填材を予め塗布しておくことを特徴とする鋼管杭基礎施工方法。In the steel pipe pile foundation construction method according to claim 9 or 10,
The steel pipe pile foundation construction method, wherein the seal member is made of a brush-type seal, and a second filler having a water-stopping property is previously applied to the inside of the brush-type seal.
前記充填材室に前記充填材が充填されるとともに、該充填材室内に存在していた水が排出された後、前記充填材室の上方に位置し、かつ前記レグの内周面と前記鋼管杭の外周面との間に存在する水を抜き取る段階と、
前記レグの内周面と前記鋼管杭の外周面との間に第三の充填材を充填する段階とを具備していることを特徴とする鋼管杭基礎施工方法。In the steel pipe pile foundation construction method according to claim 9,
The filler material is filled in the filler material chamber, and after the water existing in the filler material material chamber is discharged, the inner peripheral surface of the leg and the steel pipe are located above the filler material material chamber. Extracting water existing between the outer peripheral surfaces of the piles;
A steel pipe pile foundation construction method comprising the step of filling a third filler between the inner peripheral surface of the leg and the outer peripheral surface of the steel pipe pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002151205A JP3771871B2 (en) | 2002-03-15 | 2002-05-24 | Steel pipe pile foundation and steel pipe pile foundation construction method |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002073021 | 2002-03-15 | ||
JP2002-73021 | 2002-03-15 | ||
JP2002151205A JP3771871B2 (en) | 2002-03-15 | 2002-05-24 | Steel pipe pile foundation and steel pipe pile foundation construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003336270A JP2003336270A (en) | 2003-11-28 |
JP3771871B2 true JP3771871B2 (en) | 2006-04-26 |
Family
ID=29714248
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002151205A Expired - Fee Related JP3771871B2 (en) | 2002-03-15 | 2002-05-24 | Steel pipe pile foundation and steel pipe pile foundation construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3771871B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102392445A (en) * | 2011-10-21 | 2012-03-28 | 中铁十七局集团第六工程有限公司 | Construction method of prestressed pipe pile with vertical water discharge grooves |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4565882B2 (en) * | 2004-04-22 | 2010-10-20 | 日鉄トピーブリッジ株式会社 | Sealing member for preventing grouting outflow between pile and sheath tube |
GB2433540A (en) * | 2005-12-22 | 2007-06-27 | Martin Hardy | Brush seal for grouting annuli |
JP2013147813A (en) * | 2012-01-18 | 2013-08-01 | Nippon Steel & Sumikin Engineering Co Ltd | Seal material for grouting between pile and sheath pipe and seal structure of the same |
JP2015040448A (en) * | 2013-08-23 | 2015-03-02 | 株式会社大本組 | Decompression construction method of pneumatic caisson |
CN104131556B (en) * | 2014-07-22 | 2016-03-30 | 杭州江润科技有限公司 | The construction method of the mutual foundation drainage pile for prestressed pipe of a kind of soft or hard interlayer |
-
2002
- 2002-05-24 JP JP2002151205A patent/JP3771871B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102392445A (en) * | 2011-10-21 | 2012-03-28 | 中铁十七局集团第六工程有限公司 | Construction method of prestressed pipe pile with vertical water discharge grooves |
CN102392445B (en) * | 2011-10-21 | 2013-10-30 | 中铁十七局集团第六工程有限公司 | Construction method of prestressed pipe pile with vertical water discharge grooves |
Also Published As
Publication number | Publication date |
---|---|
JP2003336270A (en) | 2003-11-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2016089404A (en) | Grout method for cast-in-place concrete pile | |
JP3771871B2 (en) | Steel pipe pile foundation and steel pipe pile foundation construction method | |
CN110424518B (en) | Construction method of geotechnical engineering drain pipe | |
JPH09189133A (en) | Repairing method of concrete wall | |
JP3771868B2 (en) | Pile foundation and pile foundation construction method | |
JP3676086B2 (en) | Steel pipe pile foundation | |
US11603760B2 (en) | Shield method | |
JPH08199154A (en) | Injection grouting material and water-stopping for joint of vertical steel pipe sheathing | |
JP2001073369A (en) | Press-in erection method for piles | |
KR101435489B1 (en) | Helical pile and it's construction method | |
JPH04146398A (en) | Laying of pipeline through embankment | |
JP3647798B2 (en) | Construction method of mountain retaining work and bag body therefor | |
CN215518781U (en) | Sectional type high-pressure post-grouting device for underwater concrete cast-in-place pile | |
KR102518440B1 (en) | Steel pipe reinforcing grouting method using simultaneous injection steel pipe and grout | |
CN211898480U (en) | Hole digging pile shaft wall water stopping system | |
JP3444488B2 (en) | How to lay pipes that penetrate the embankment without excavation | |
JP4194453B2 (en) | Water stop method for steel sheet pile joints | |
JP2887170B2 (en) | Combined backfill injection water stop method | |
CN216405402U (en) | Plugging structure applied to leakage stoppage of anchor cable | |
JP2005273170A (en) | Starting pit mouth wall | |
JP3801229B2 (en) | Underground bending member and its construction method | |
JPS60181497A (en) | Drilling method and apparatus for covering pipeline wall by water impermeable film | |
JP2008240424A (en) | Water stop liquid filling tool and water stop liquid filling device | |
JPH10176483A (en) | Reinforcement and reinforcing pipe, and reinforcing and repairing method for embedded body in underground by use of the pipe | |
JP2016211158A (en) | Joint water shielding method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040528 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20051025 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051208 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060117 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060210 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100217 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100217 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110217 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110217 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120217 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120217 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130217 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |