JP3754698B1 - Steel tower basic structure - Google Patents

Steel tower basic structure Download PDF

Info

Publication number
JP3754698B1
JP3754698B1 JP2004271161A JP2004271161A JP3754698B1 JP 3754698 B1 JP3754698 B1 JP 3754698B1 JP 2004271161 A JP2004271161 A JP 2004271161A JP 2004271161 A JP2004271161 A JP 2004271161A JP 3754698 B1 JP3754698 B1 JP 3754698B1
Authority
JP
Japan
Prior art keywords
tower
concrete
steel tower
steel
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2004271161A
Other languages
Japanese (ja)
Other versions
JP2006083641A (en
Inventor
成 田邉
敏 松尾
正浩 吉本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2004271161A priority Critical patent/JP3754698B1/en
Priority to PCT/JP2005/017144 priority patent/WO2006030893A1/en
Priority to CNB200580029551XA priority patent/CN100567659C/en
Application granted granted Critical
Publication of JP3754698B1 publication Critical patent/JP3754698B1/en
Publication of JP2006083641A publication Critical patent/JP2006083641A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

【課題】地盤中に比較的口径の小さい杭体を複数設置した基礎構造形式において、基礎の小規模化を可能とすることにより、施工時間の短縮、掘削量の低減、コンクリート打設量の縮小等を図り得る鉄塔の基礎構造を提供する。
【解決手段】地盤中に打設された複数本の杭体1,1…と、鉄塔の主脚柱2をコンクリート構造体3を介して接合した鉄塔の基礎構造において、前記コンクリート構造体3は、内壁面に、周方向に沿って固設されたズレ止め用リブ4,4…を上下方向に複数段に亘って有する鋼管5内にコンクリート6を打設することによって造成された構造体とし、前記コンクリート構造体3の下部側に、前記地盤中に打設された複数本の杭体1,1…の頂部が接合され、かつ前記鉄塔主脚柱2の下部外面に複数段に亘り支圧板7,7…が設けられ、支圧板7,7…が配設された主脚柱部分Kがコンクリート構造体3に埋設されている構造とする。
【選択図】図1
[PROBLEMS] To reduce the construction time, reduce the amount of excavation, and reduce the amount of concrete placement by enabling the foundation to be scaled down in a foundation structure with multiple piles with relatively small diameters installed in the ground. To provide a foundation structure of a steel tower that can be used.
In a foundation structure of a steel tower in which a plurality of pile bodies 1, 1... Placed in the ground and a main pillar 2 of the steel tower are joined via a concrete structure 3, the concrete structure 3 is A structure formed by placing concrete 6 in a steel pipe 5 having a plurality of steps in the vertical direction, with ribs 4, 4... The tops of a plurality of piles 1, 1... Placed in the ground are joined to the lower side of the concrete structure 3, and the lower main surface of the tower main pedestal 2 is supported in multiple steps. It is assumed that the main pedestal column portion K provided with the pressure plates 7, 7... Is embedded in the concrete structure 3.
[Selection] Figure 1

Description

本発明は、地盤中に打設した複数の杭体と、鉄塔の主脚柱とをコンクリート構造体を介して接合した鉄塔の基礎構造に関する。   The present invention relates to a steel tower foundation structure in which a plurality of pile bodies placed in the ground and a main pillar of a steel tower are joined via a concrete structure.

前記鉄塔の主脚柱を支持する基礎構造として、比較的支持層が深い場合には、図6に示されるように、地盤に比較的口径の小さい複数の杭体50,50…を打設した後、これら杭体50,50…の頂部と連結するように鉄筋コンクリートによってフーチング51を造成し、このフーチング51と鉄塔の主脚柱52とを接続する方式が一般的となっている(下記特許文献1等参照)。   As a foundation structure for supporting the main pedestal of the steel tower, when the support layer is relatively deep, as shown in FIG. 6, a plurality of pile bodies 50, 50. Thereafter, a footing 51 is formed of reinforced concrete so as to be connected to the tops of these piles 50, 50... And a method of connecting the footing 51 and the main pedestal 52 of the steel tower is generally used (the following patent document). 1 etc.).

また、前記フーチング51と主脚柱52との定着構造に関しては、大別すると、ボルト定着方式、いかり材定着方式、支圧板定着方式などが存在する。ボルト定着方式は、図6に示されるように、主脚柱52の底面に設けられたベースプレート53を複数本のアンカーボルト54,54…によって定着する方式であり、前記いかり材定着方式は、図7(A)〜(C)に示されるように、フーチング51に埋設される主脚柱の下部周面に取付板56を溶接等によって固設し、この取付板56を挟んで左右対のアングル57,57をボルト接合したものを周囲に複数箇所設けた定着方式であり、前記支圧板定着方式は、図8に示されるように、フーチング51に埋設される主脚柱52の底面及び/又は外面に外方に突出するように設けたリング状等の支圧板58,58…によって定着する方式である。
一方、フーチングと杭頭部との接合方式は、図9(A)に示されるように、フーチング51内に没入させた杭頭部の外面に、外方に突出するように設けたリング状等の支圧板59,59…によって定着する支圧板接合方式や、図9(B)に示されるように、杭頭部とフーチング51とに跨るように複数本の鉄筋60,60…を配設して接合する鉄筋接合方式などが採用されている。
The fixing structure between the footing 51 and the main pedestal 52 is roughly divided into a bolt fixing method, a contact material fixing method, and a pressure plate fixing method. As shown in FIG. 6, the bolt fixing method is a method in which a base plate 53 provided on the bottom surface of the main pedestal 52 is fixed by a plurality of anchor bolts 54, 54... 7 (A) to (C), a mounting plate 56 is fixed to the lower peripheral surface of the main pedestal embedded in the footing 51 by welding or the like, and a pair of left and right angles sandwiching the mounting plate 56 A fixing method in which a plurality of bolts 57 and 57 are joined to each other at a plurality of locations around the periphery, and the support plate fixing method includes the bottom surface of the main pedestal 52 embedded in the footing 51 and / or the support plate fixing method as shown in FIG. In this method, fixing is performed by ring-shaped pressure bearing plates 58, 58,... Provided on the outer surface so as to protrude outward.
On the other hand, as shown in FIG. 9 (A), the jointing method between the footing and the pile head is a ring shape provided so as to protrude outward on the outer surface of the pile head immersed in the footing 51. The bearing plates are fixed by the bearing plates 59, 59, and a plurality of reinforcing bars 60, 60 are disposed so as to straddle the pile head and the footing 51 as shown in FIG. 9B. Reinforcing bar joining method is used.

一方で、基礎構造の簡略化を図るために、下記特許文献2では、下端に杭径より大径な掘削羽根を有する回転圧入用鋼管杭70、70…を、地中に斜め方向に圧入して設置し、回転圧入用鋼管杭70、70…の上端に鉄塔脚部71の下端部に連結固定してなる鉄塔基礎構造において、地中に斜め方向に設置された回転圧入用鋼管杭70と上方に伸びる鉄塔脚部71とが直線状になるように構成した鉄塔用基礎構造が提案されている。
特開平9−3882号公報 特開2003−166254号公報
On the other hand, in order to simplify the foundation structure, in Patent Document 2 below, steel pipe piles 70, 70... For rotary press-fit having excavation blades larger than the pile diameter at the lower end are pressed into the ground in an oblique direction. In the steel tower foundation structure that is connected and fixed to the lower end of the steel tower leg 71 at the upper end of the steel pipe piles 70, 70 for rotary press fitting, the steel pipe pile 70 for rotary press fitting installed in the ground in an oblique direction; A steel tower foundation structure has been proposed in which the steel tower legs 71 extending upward are linear.
Japanese Patent Laid-Open No. 9-3882 JP 2003-166254 A

前記送電用鉄塔の基礎においては、図11に示されるように、鉄塔の自重、電線の自重の影響よりも、電線の延線張力や、台風や季節風などによる風荷重の影響を強く受けることになる。その結果、転倒モーメントが他の要因による全圧縮荷重に比べて大きくなるため、風下側の鉄塔脚部には圧縮加重が作用する一方で、風上側の鉄塔脚部には圧縮荷重(押込み力)の約7割に及ぶ引揚荷重(引抜き力)が作用する。また、前記押込み力と引抜き力による偶力によって曲げモーメントが作用するとともに、水平力が作用することになる。   In the foundation of the power transmission tower, as shown in FIG. 11, it is more strongly affected by the wire tension, the typhoon, the seasonal wind and the like than the influence of the weight of the tower and the weight of the wire. Become. As a result, the overturning moment becomes larger than the total compressive load due to other factors, so compression load acts on the leeward steel tower legs, while compressive load (pushing force) acts on the leeward steel tower legs. About 70% of the lifting load (pullout force) is applied. Further, a bending moment is applied by a couple of forces due to the pushing force and the pulling force, and a horizontal force is applied.

従って、鉄塔脚部を支持する基礎(フーチング)では、図12に示されるように、主脚柱52とフーチング51の定着部において、フーチングが浅くなり過ぎると、主脚柱52の基部を中心としたコーン状の剪断ひび割れ61が発生し定着部破壊を引き起こすことがある。また、図13に示されるように、杭体50がフーチング51の外縁に近すぎる場合には定着部から外側に割裂ひび割れ状の剪断ひび割れ62,62…が発生し、定着部破壊が起こることがある。さらに、フーチングが薄くなり過ぎると、同図に示されるように、杭体50を中心としてコーン状の剪断ひび割れ61が発生することがあるなどの問題があった。
従って、これらの押込み力、引抜き力、曲げモーメント、水平力に対して十分な耐力を有し、ひび割れを起こさないようにフーチング51を設計すると、フーチング規模が大型化してしまうとともに、フーチングが大規模となった分、掘削量が多くなるとともに、コンクリート打設量が多くなるなどの問題も発生し、施工に多くの時間と手間が掛かっていた。
Therefore, in the foundation (footing) for supporting the tower leg, as shown in FIG. 12, if the footing becomes too shallow in the fixing portion of the main pedestal 52 and the footing 51, the base of the main pedestal 52 is centered. The corn-like shear crack 61 may be generated and the fixing portion may be destroyed. As shown in FIG. 13, when the pile body 50 is too close to the outer edge of the footing 51, split crack-like shear cracks 62, 62,... is there. Furthermore, when the footing is too thin, there is a problem that a cone-shaped shear crack 61 may occur around the pile body 50 as shown in FIG.
Therefore, if the footing 51 is designed so as to have sufficient proof strength against these pushing force, pulling force, bending moment, and horizontal force so as not to cause cracks, the footing scale becomes large and the footing becomes large. As a result, the amount of excavation increased and the amount of concrete placement increased, which caused much time and labor for the construction.

一方、前記特許文献2記載の基礎構造の場合は、フーチングを有しないため、前述した問題点が解消されるようになるけれども、大口径の鋼管杭70を地盤中に打設するためには大型の重機類が必要となり、特に山岳地帯での鉄塔基礎の構築には採用することができない、或いは困難であるなどの問題があった。   On the other hand, in the case of the foundation structure described in Patent Document 2, since there is no footing, the above-mentioned problems will be solved. However, in order to place a large-diameter steel pipe pile 70 in the ground, a large size is required. Heavy machinery is necessary, and there is a problem that it cannot be adopted or is difficult to construct a steel tower foundation particularly in a mountainous area.

そこで本発明の主たる課題は、地盤中に比較的口径の小さい杭体を複数設置した基礎構造形式において、基礎の小規模化を可能とすることにより、施工時間の短縮、掘削量の低減、コンクリート打設量の縮小などを図った鉄塔の基礎構造を提供することにある。   Therefore, the main problem of the present invention is to reduce the construction time, reduce the amount of excavation, and reduce the amount of excavation by making the foundation smaller in the foundation structure type in which a plurality of pile bodies with relatively small diameters are installed in the ground. The purpose is to provide a foundation structure for a steel tower that reduces the amount of casting.

前記課題を解決するために請求項1に係る本発明として、地盤中に打設された複数本の杭体と、鉄塔の主脚柱とをコンクリート構造体を介して接合した鉄塔の基礎構造において、
前記コンクリート構造体は、内壁面に、周方向に沿って固設されたズレ止め用リブを上下方向に複数段に亘って有する鋼管内にコンクリートを打設することによって造成された構造体とし、前記コンクリート構造体の下部側に、前記地盤中に打設された複数本の杭体の頂部が接合され、かつ前記鉄塔主脚柱の下部に定着部材が設けられ、前記定着部材が設けられた主脚柱部分が前記コンクリート構造体に埋設されていることを特徴とする鉄塔の基礎構造が提供される。
In order to solve the above-mentioned problem, as the present invention according to claim 1, in a foundation structure of a steel tower in which a plurality of pile bodies placed in the ground and a main pedestal of a steel tower are joined via a concrete structure. ,
The concrete structure is a structure formed by placing concrete in a steel pipe having a plurality of steps in the vertical direction with a rib for fixing a slippage fixed on the inner wall surface along the circumferential direction, A top portion of a plurality of pile bodies placed in the ground is joined to the lower side of the concrete structure, and a fixing member is provided at a lower portion of the main tower pillar, and the fixing member is provided. A foundation structure of a steel tower is provided in which a main pedestal column portion is embedded in the concrete structure.

上記請求項1記載の本発明においては、先ず地盤中に打設された複数本の杭体と、鉄塔の主脚柱とを接合するコンクリート構造体として、内壁面に、周方向に沿って固設されたズレ止め用リブを上下方向に複数段に亘って有する鋼管内にコンクリートを打設することによって造成された構造体とする。
従来は、鉄塔主脚柱の定着部の設計は、コンクリートの許容引張応力度や許容剪断応力度に基づいた定着耐力により補強が成されていたが、安全性の検知から十分でないと予測される場合があり、一層の定着耐力向上のために、経験則に基づく補強が成されていたため、過剰補強が成されることがあった。本出願人はこのような状況に鑑み、効率的な基礎の設計及び補強について鋭意検討を行った結果、特開2000-345571号公報において開示するように、主脚柱に継続的な応力が作用すると、コンクリートに水平のひび割れや垂直のひび割れ(割裂ひび割れ)が発生する。そして、支圧定着方式の場合には、前記割裂ひび割れの発生による影響を大きく受け、この割裂ひび割れが発生した時は、その内の一つでも基礎表面にまで至ると破壊が生じるとの知見を得るに至った。なお、本願発明者等は、割裂ひび割れに直交する方向、すなわち主脚柱の周方向を鋼管により補強し、コンクリートの拘束を向上させて割裂破壊を抑制することにより、定着耐力を飛躍的に向上できることを十数体の模型実験や数値解析から得ている。
In the present invention described in claim 1, first, as a concrete structure for joining a plurality of pile bodies placed in the ground and a main pedestal of a steel tower, the inner wall surface is fixed along the circumferential direction. It is set as the structure formed by placing concrete in the steel pipe which has the rib for ribs provided in multiple steps in the up-down direction.
Conventionally, the design of the anchoring part of the tower main pedestal was reinforced by the anchoring strength based on the allowable tensile stress and allowable shear stress of the concrete, but it is predicted that it will not be sufficient from safety detection. In some cases, in order to further improve the fixing strength, reinforcement based on empirical rules has been made, and thus over-reinforcement was sometimes made. In view of this situation, the present applicant has conducted extensive studies on efficient foundation design and reinforcement. As a result, as disclosed in JP 2000-345571 A, continuous stress acts on the main pedestal. Then, horizontal cracks and vertical cracks (split cracks) occur in the concrete. And in the case of the support pressure fixing method, it is greatly affected by the occurrence of the above-mentioned split crack, and when this split crack occurs, the knowledge that even if one of them reaches the foundation surface, it will break down. I came to get. In addition, the inventors of the present application dramatically improve the fixing strength by reinforcing the direction perpendicular to the split crack, that is, the circumferential direction of the main pedestal with a steel pipe, and improving the restraint of the concrete to suppress split fracture. What we can do is gained from a dozen model experiment and numerical analysis.

従って、割裂ひび割れをできる限り抑制することができれば、定着耐力が向上し、接合部(基礎部分)が縮小化できるとの考えの下、上記構造のコンクリート構造体とし、その下部側に、前記地盤中に打設された複数本の杭体の頂部が接合され、かつ前記鉄塔主脚柱の下部に定着部材が設けられ、前記定着部材が設けられた主脚柱部分が前記コンクリート構造体に埋設されている基礎構造とした。   Accordingly, if it is possible to suppress the split crack as much as possible, the fixing strength can be improved and the joint portion (foundation portion) can be reduced, so that a concrete structure having the above structure is formed. The tops of a plurality of pile bodies placed inside are joined, a fixing member is provided at the lower part of the main tower pillar, and the main pillar part provided with the fixing member is embedded in the concrete structure The basic structure is the same.

その結果、前記鋼管が打設されたコンクリートを外部(周囲)から拘束することにより割裂ひび割れが防止され、コンクリート構造体の定着耐力を大幅に向上できるようになるとともに、杭体は鋼管内の内壁面近傍に近接して配置することができるようになるため、コンクリート構造体の規模を大幅に縮小化できるようになる。また、コンクリート構造体の規模を縮小化できることにより、施工時間の短縮、掘削量の低減、コンクリート打設量の縮小などが図れるようになる。   As a result, by constraining the concrete on which the steel pipe is placed from the outside (periphery), split cracks can be prevented, and the anchoring strength of the concrete structure can be greatly improved. Since it can be arranged close to the wall surface, the scale of the concrete structure can be greatly reduced. In addition, since the scale of the concrete structure can be reduced, the construction time can be shortened, the excavation amount can be reduced, and the concrete placement amount can be reduced.

さらに、前記鋼管とコンクリートとからなるコンクリート構造体とすることにより、複数本の杭を容易に設置することが可能であるとともに、主杭や副杭の施工誤差を容易に吸収することが可能になる。   Furthermore, by using a concrete structure composed of the steel pipe and concrete, it is possible to easily install a plurality of piles and to easily absorb construction errors of main piles and sub-piles. Become.

請求項2に係る本発明として、前記複数本の杭体は、口径が400φmm以下又は口径が前記鋼管径の1/6以下の小口径杭とする請求項1記載の鉄塔の基礎構造が提供される。杭体としては、大口径杭よりも口径が400φmm以下又は口径が前記鋼管径の1/6以下の小口径杭を複数本、好ましくは4〜6本程度配置するのが望ましい。特に山岳地帯では大型重機を持ち込めないため、小型の削孔機械によって小口径杭を必要本数だけ地盤に造成するのがよい。小口径杭としては、詳細には後述するが、場所打ち杭や鋼管杭などとすることができる。   As the present invention according to claim 2, the foundation structure of the steel tower according to claim 1, wherein the plurality of pile bodies are small-diameter piles having a diameter of 400 mm or less or a diameter of 1/6 or less of the steel pipe diameter. The As the pile body, it is desirable to arrange a plurality of, preferably 4 to 6, small-diameter piles having a diameter of 400 mm or less or a diameter of 1/6 or less of the steel pipe diameter as compared with the large-diameter pile. Especially in mountainous areas, large heavy machinery cannot be brought in. Therefore, it is recommended to create as many small-diameter piles as necessary on the ground using a small drilling machine. The small-diameter pile may be a cast-in-place pile or a steel pipe pile, which will be described in detail later.

請求項3に係る本発明として、前記ズレ止め用リブは、前記鉄塔主脚柱の支圧板配設部位を境に、その上部側及び下部側に夫々配設してある請求項1、2いずれかに記載の鉄塔の基礎構造が提供される。   As a third aspect of the present invention, the rib for preventing misalignment is disposed on the upper side and the lower side, respectively, with respect to the bearing plate arrangement portion of the main tower pillar. A foundation structure of the steel tower is provided.

上記請求項3記載の本発明においては、前記ズレ止め用リブは、前記鉄塔主脚柱の埋設部の支圧板配設部位を境に、その上部側及び下部側に夫々配設するようにするものである。コンクリート構造体に作用する主脚柱からの荷重は、風荷重や地震荷重の方向によって押込み力、引抜き力の双方のケースがあるため、これらの荷重の両者に対して、前記ズレ止め用リブを効果的に機能させるには、支圧板配設部位を境に、その上部側及び下部側に夫々配設するようにするのが良い。   In the present invention described in claim 3, the misalignment prevention ribs are arranged on the upper side and the lower side, respectively, with the bearing plate arrangement part of the buried part of the main tower pillar as a boundary. Is. The load from the main pedestal acting on the concrete structure has both cases of indentation force and pull-out force depending on the direction of wind load and seismic load. In order to function effectively, it is preferable that the support plate is disposed on the upper side and the lower side of the support plate placement site.

請求項4に係る本発明として、前記コンクリート構造体は、その大部分が地盤に埋設されている請求項1〜3いずれかに記載の鉄塔の基礎構造が提供される。   As the present invention according to claim 4, the foundation structure of the steel tower according to any one of claims 1 to 3, wherein most of the concrete structure is embedded in the ground.

前記コンクリート構造体は、地上に載置するような形態で築造することもできるが、基礎の変位などを抑制するにはフーチングを同様に、地中に埋設し土圧抵抗によって変位を抑制し得る状態で築造するのが望ましい。   The concrete structure can be built in a form to be placed on the ground. However, in order to suppress the displacement of the foundation, a footing can be embedded in the ground and the displacement can be suppressed by earth pressure resistance. It is desirable to build in state.

請求項5に係る本発明として、前記鉄塔主脚柱の径をφ、前記鉄塔主脚柱における支圧板の配設区間長をL、前記鋼管の内径をDとするとき、L/φ=2〜5であり、かつD/φ=2〜10の条件を満足している請求項1〜4いずれかに記載の鉄塔の基礎構造が提供される。   In the present invention according to claim 5, when the diameter of the tower main pedestal column is φ, the section length of the bearing plate in the tower main pedestal column is L, and the inner diameter of the steel pipe is D, L / φ = 2. It is -5, and the basic structure of the steel tower in any one of Claims 1-4 which satisfy | fills the conditions of D / phi = 2-10 is provided.

請求項6に係る本発明として、前記コンクリート構造体の鋼管周壁部より斜め下方向に沿って打設された斜杭を備える請求項1〜5いずれかに記載の鉄塔の基礎構造が提供される。   As the present invention according to claim 6, there is provided the foundation structure of the steel tower according to any one of claims 1 to 5, further comprising a diagonal pile driven in a diagonally downward direction from a steel pipe peripheral wall portion of the concrete structure. .

上記請求項6記載の本発明においては、前記コンクリート構造体の鋼管周壁部より斜め下方向に向けて打設された斜杭を備えるようにするものである。斜杭を設けることにより、特に引抜き耐力を大幅に向上できるようになる。   In this invention of the said Claim 6, it is made to equip with the slant pile put toward the diagonally downward direction from the steel pipe surrounding wall part of the said concrete structure. By providing the inclined piles, the pulling strength can be greatly improved.

請求項7に係る本発明として、前記隣接する鉄塔主脚柱のコンクリート構造体同士を連結する連結梁を備える請求項1〜5いずれかに記載の鉄塔の基礎構造が提供される。
上記請求項7記載の本発明においては、隣接する鉄塔主脚柱のコンクリート構造体同士を結合する連結梁を設けるようにするものである。コンクリート構造体を連結梁で連結しておくことにより、基礎の変位を大幅に抑制することが可能となる。
As this invention which concerns on Claim 7, the foundation structure of the tower in any one of Claims 1-5 provided with the connection beam which connects the concrete structures of the said adjacent tower main pedestal pillar is provided.
In the present invention according to the seventh aspect, a connecting beam for connecting the concrete structures of adjacent main tower pillars is provided. By connecting the concrete structures with connecting beams, the displacement of the foundation can be greatly suppressed.

請求項8に係る本発明として、前記鉄塔主脚柱の本数を2乃至4本とする請求項1〜5いずれかに記載の鉄塔の基礎構造が提供される。大きな鋼管柱の代わりに、トラス構造の支柱を2乃至4本有する上部構造にも使用することができ、小さな規模の鉄塔の場合は、1つの前記鋼管の中に4本の主脚柱をすべて定着することができる。   As the present invention according to claim 8, there is provided the foundation structure of a steel tower according to any one of claims 1 to 5, wherein the number of the main tower pillars is 2 to 4. Instead of a large steel pipe column, it can also be used in an upper structure with 2 to 4 truss structure columns. In the case of a small-scale steel tower, all four main pedestal columns are placed in one steel pipe. It can be fixed.

以上詳説のとおり本発明によれば、地盤中に比較的口径の小さい杭体を複数設置した基礎構造形式において、コンクリート構造体として、内壁面に、周方向に沿って固設されたズレ止め用リブを上下方向に複数段に亘って有する鋼管内にコンクリートを打設することによって造成された構造体を採用するため、定着耐力を飛躍的に向上させることができ、基礎部分を小規模化できるようになる。その結果、施工時間の短縮、掘削量の低減、コンクリート打設量の縮小などを図り得るようになる。   As described above in detail, according to the present invention, in the foundation structure type in which a plurality of piles having a relatively small diameter are installed in the ground, as a concrete structure, for the displacement prevention fixed to the inner wall surface along the circumferential direction. Adopting a structure created by placing concrete in a steel pipe with multiple ribs in the vertical direction, the fixing strength can be drastically improved, and the foundation part can be scaled down It becomes like this. As a result, it is possible to shorten the construction time, the excavation amount, the concrete placement amount, and the like.

以下、本発明の実施の形態について図面を参照しながら詳述する。
〔第1形態例〕
図1に示されるように、本発明に係る鉄塔基礎構造は、地盤中に打設された複数本の杭体1,1…と、鉄塔の主脚柱2とをコンクリート構造体3を介して接合するに当たり、前記コンクリート構造体3として、内壁面に、周方向に沿って固設されたズレ止め用リブ4,4…を上下方向に複数段に亘って有する鋼管5内にコンクリート6を打設することによって造成された構造体とし、前記コンクリート構造体3の下部側に、前記地盤中に打設された複数本の杭体1,1…の頂部が接合され、かつ前記鉄塔主脚柱2の下部外面に複数段に亘り支圧板7,7…が設けられ、前記支圧板7,7…が配設された主脚柱部分Kが前記コンクリート構造体3に埋設されている構造とするものである。
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
[First embodiment]
As shown in FIG. 1, the steel tower foundation structure according to the present invention includes a plurality of pile bodies 1, 1... Placed in the ground and a main pedestal 2 of the steel tower via a concrete structure 3. In joining, the concrete structure 3 is struck with concrete 6 in a steel pipe 5 having a plurality of vertically extending ribs 4, 4... Fixed on the inner wall surface along the circumferential direction. A top of the plurality of pile bodies 1, 1... Placed in the ground is joined to the lower side of the concrete structure 3, and the main tower pillar Are provided in a plurality of stages on the outer surface of the lower part 2, and the main pedestal column portion K on which the bearing plates 7, 7... Are disposed is embedded in the concrete structure 3. Is.

以下、より具体的に詳述すると、
前記コンクリート構造体3としては、例えば径が1000〜5000mm程度、厚みは約20〜30mm程度の厚肉鋼管が好適に使用される。内壁面に固設されるズレ止め用リブ4,4…としては、打設されるコンクリート6との間で確実に滑りを防止し得る突起形状であれば如何なる断面形状のものであってもよい。例えば、図5(A)に示されるように、鉄筋/鋼棒4aを鋼管5の内壁面に沿って溶接によって固設してもよいし、図5(B)に示されるように、角鋼材4bを用いても良いし、図5(C)に示されるようにフラットバー4cなどを用いてもよい。
In more detail below,
As the concrete structure 3, for example, a thick steel pipe having a diameter of about 1000 to 5000 mm and a thickness of about 20 to 30 mm is preferably used. The misalignment prevention ribs 4, 4... Fixed to the inner wall surface may have any cross-sectional shape as long as it is a protrusion shape that can reliably prevent slippage with the concrete 6 to be placed. . For example, as shown in FIG. 5 (A), the rebar / steel bar 4a may be fixed by welding along the inner wall surface of the steel pipe 5, or as shown in FIG. 5 (B), a square steel material. 4b may be used, or a flat bar 4c may be used as shown in FIG.

なお、図示の例では前記鋼管5として、鋼製の円形管としたが、角管や多角形管などの鋼製管を用いることもできる。また、前記コンクリート構造体3は、地上に載置するような形態で築造することもできるが、土圧抵抗による変位量の低減を図るため、大部分が地盤に埋設されている状態で築造するのが望ましい。
前記主脚柱2には、前述したように、風荷重等の方向によって、押込み力又は引抜き力の双方が作用することになるため、押込み力と引抜き力との両者に対応可能とするため、前記ズレ止め用リブ4は、前記鉄塔主脚柱2の支圧板配設部位Kを境に、その上部側及び下部側のそれぞれに配設するようにするのが望ましい。実際には、前記鋼管5の上下方向にほぼ均等の間隔で配置するのが望ましい。
In the illustrated example, the steel pipe 5 is a steel circular pipe, but a steel pipe such as a square pipe or a polygonal pipe may be used. In addition, the concrete structure 3 can be built in such a form that it is placed on the ground, but in order to reduce the displacement due to earth pressure resistance, the concrete structure 3 is mostly built in a state where it is buried in the ground. Is desirable.
As described above, both the pushing force and the pulling force act on the main pedestal 2 depending on the direction of wind load, etc., so that both the pushing force and the pulling force can be handled. The misalignment prevention ribs 4 are preferably arranged on the upper side and the lower side of the support main plate 2 of the tower main pedestal 2 as a boundary. Actually, it is desirable that the steel pipes 5 are arranged at almost equal intervals in the vertical direction.

前記主脚柱2は、その下部外面に複数段に亘り、図示例では3段に亘り支圧板7,7…が設けられ、この支圧板配設部位Kが前記コンクリート構造体3のほぼ中央に位置するように、コンクリート構造体3に埋設されている。前記主脚柱2の断面寸法は特に限定はないが、概ね300〜3000mm程度とされる。前記支圧板7としては、リング板を前記主脚柱2の周囲に溶接等によって固設した構造としたが、支圧板7の平面形状は多角形状等であってもよい。また、本形態例では、前記主脚柱2の定着方式として支圧板方式を採用したが、図7に示される、いかり材定着方式を採用することもできる。   The main pedestal column 2 is provided with a plurality of steps on the outer surface of the lower part thereof, and in the example shown in the figure, the support plates 7, 7... Are provided, and the support plate disposition site K is substantially at the center of the concrete structure 3. It is embed | buried in the concrete structure 3 so that it may be located. The cross-sectional dimension of the main pedestal 2 is not particularly limited, but is approximately 300 to 3000 mm. The bearing plate 7 has a structure in which a ring plate is fixed around the main pedestal 2 by welding or the like, but the planar shape of the bearing plate 7 may be a polygonal shape or the like. In this embodiment, the pressure plate method is adopted as the fixing method of the main pedestal 2. However, the anchor material fixing method shown in FIG. 7 can also be adopted.

さらに、図示例では鉄塔主脚柱2として、鋼管柱の例を示したが、主脚柱2としては例えば、主脚柱2としては例えば山形鋼とすることもでき、また、図4に示されるように、主脚柱2の数を2乃至4本とし、これらを複数の斜材2a、2a…で連結した組立て柱2’などを対象とすることもできる。   Further, in the illustrated example, an example of a steel pipe column is shown as the steel tower main pedestal 2, but the main pedestal 2 can be, for example, angle steel, for example, as shown in FIG. 4. As described above, the number of the main leg pillars 2 may be two to four, and the assembly pillars 2 ′ or the like in which these are connected by a plurality of diagonal members 2a, 2a.

前記杭体1としては、杭種は問わず、鋼管杭、場所打ち杭、或いは既製杭などのいずれかとすることができる。前記杭体1は、前記鋼管5内に少なくとも2本以上、好ましくは4〜6本程度均等配置できる径とすることが望ましいが、好ましくは施工性の点から、口径が400φmm以下又は口径が前記鋼管5の径の1/6以下の小口径杭とするのが望ましい。前記小口径杭の施工は、例えば削孔により地盤中に穿孔を行ったならば、この穿孔内に鋼管又は既製杭を挿入し、周囲にグラウト材又はコンクリート、高流動性コンクリートなどの固化材を充填し固定するようにしてもよいし、穿孔内に組立筋を挿入し、コンクリート又は高流動性コンクリートを充填することにより場所打ち杭として造成したものとすることができる。前記地盤の穿孔は、地盤が弱い場合にはロータリー式などを用い、岩盤か途中に岩盤層が介在するような地盤の場合には回転打撃式のダウンザホールハンマー(商標名)などを好適に使用することができる。   The pile body 1 can be any one of steel pipe piles, cast-in-place piles, ready-made piles, etc., regardless of the pile type. It is desirable that the pile body 1 has a diameter that allows at least two or more, preferably about 4-6, to be evenly arranged in the steel pipe 5, but preferably has a diameter of 400 mm or less or a diameter of the above-described diameter from the viewpoint of workability. It is desirable to use a small-diameter pile having a diameter of 1/6 or less of the diameter of the steel pipe 5. For the construction of the small-diameter pile, for example, if a hole is drilled in the ground by drilling, a steel pipe or a ready-made pile is inserted into the hole, and a solidified material such as grout material or concrete or high-fluidity concrete is placed around the hole. It may be configured to be filled and fixed, or can be constructed as a cast-in-place pile by inserting an assembly bar into the perforation and filling concrete or high-fluidity concrete. For the drilling of the ground, a rotary type or the like is used when the ground is weak, and a rotary hitting down-the-hole hammer (trade name) or the like is suitably used when the ground is a bedrock or a bedrock layer in the middle. be able to.

前記杭体1とコンクリート構造物3との接合は、図示例では両者間に跨る定着鉄筋8,8…を配設する鉄筋定着方式を採用しているが、鋼管杭の場合にはコンクリート構造体3内に挿入した杭頭部の外面に、外方に突出するように設けたリング状等の支圧板によって定着を図る支圧板接合方式を採用してもよい。   In the illustrated example, the pile body 1 and the concrete structure 3 are joined using a reinforcing bar fixing system in which fixed reinforcing bars 8, 8,... A bearing plate joining method may be employed in which fixing is performed on the outer surface of the pile head inserted into the ring 3 by a bearing plate such as a ring provided so as to protrude outward.

以上詳述した基礎構造の施工は、先ず最初に、コンクリート構造体3の施工部を地盤掘削したならば鋼管5を設置し、次いで杭体1,1…のための穿孔を行い杭体1、1…を地盤中に造成する。その後、定着筋8,8…を設置するとともに、主脚柱2の基部を鋼管5内の所定の位置に位置決めし、仮固定部材(図示せず)によって固定を図るとともに、鋼管5内に所定の鉄筋を配筋し、すべての配筋作業を終えたならば、コンクリートを打設する。   The construction of the foundation structure detailed above is as follows. First, if the construction part of the concrete structure 3 is excavated, the steel pipe 5 is installed, and then the pile body 1, 1. Create 1 ... in the ground. Thereafter, the fixing bars 8, 8... Are installed, the base portion of the main pedestal 2 is positioned at a predetermined position in the steel pipe 5, and fixed by a temporary fixing member (not shown). After all the reinforcement work has been completed, concrete is placed.

〔第2形態例〕
次いで、図2に示される第2形態例に係る基礎構造は、前記コンクリート構造体3の鋼管5周壁部より斜め下方向に向けて打設された斜杭10を設けるものである。斜杭10をコンクリート構造体3に対して一体的に備えることにより、押込み力の向上はもちろんであるが、それ以上に引抜き耐力を大幅に向上できるようになる。なお、前記斜杭10は図示例は1本としたが、複数設けるようにしてもよい。
施工は、先ず最初に、コンクリート構造体3の施工部を地盤掘削したならば、掘削部の壁面より穿孔を行い斜杭10を打設した後、鋼管5を設置する。鋼管5の壁面には、予め前記斜杭10との一体化を図るために定着筋11の挿入口5aが形成されている。
[Second embodiment]
Next, the foundation structure according to the second embodiment shown in FIG. 2 is provided with a diagonal pile 10 that is driven obliquely downward from the peripheral wall portion of the steel pipe 5 of the concrete structure 3. By providing the slant pile 10 integrally with the concrete structure 3, not only the pushing force is improved, but also the pulling strength can be greatly improved. In addition, although the said example of the diagonal pile 10 was made into the example of illustration, you may make it provide multiple.
In the construction, first, if the construction part of the concrete structure 3 is excavated in the ground, the steel pipe 5 is installed after drilling from the wall surface of the excavation part and placing the slant pile 10. In the wall surface of the steel pipe 5, an insertion port 5 a for the fixing bar 11 is formed in advance for integration with the oblique pile 10.

次いで、杭体1,1…のための穿孔を行い杭体1、1…を地盤中に造成する。その後、定着筋8,8…を設置するとともに、主脚柱2の基部を鋼管5内の所定の位置に位置決めし、仮固定部材(図示せず)によって固定するとともに、鋼管5内に所定の鉄筋を配筋し、かつ鋼管5の挿入口5aから定着筋11を挿入し、すべての配筋作業を終えたならば、コンクリートを打設する。
また、前記鋼管5の挿入口5aの外側部分にも、コンクリートを打設し、斜杭10の頭部を固定し、コンクリート構造体3との一体化を図るようにする。
Next, the pile bodies 1, 1... Are drilled to form the pile bodies 1, 1. After that, the fixing muscles 8, 8... Are installed, the base portion of the main pedestal 2 is positioned at a predetermined position in the steel pipe 5 and fixed by a temporary fixing member (not shown), and the predetermined portion in the steel pipe 5 is set. When reinforcing bars are placed and the fixing bars 11 are inserted from the insertion port 5a of the steel pipe 5 and all the placing work is completed, concrete is placed.
In addition, concrete is also cast on the outer portion of the insertion port 5 a of the steel pipe 5, and the head of the oblique pile 10 is fixed so as to be integrated with the concrete structure 3.

〔第3形態例〕
次いで、図3に示される第3形態例に係る基礎構造は、隣接する鉄塔主脚柱2のコンクリート構造体3,3同士を結合するように連結梁12を設けるものである。コンクリート構造体3,3を連結梁12によって相互に連結することにより、基礎の変位を大幅に抑制できるようになる。
[Third embodiment]
Next, the foundation structure according to the third embodiment shown in FIG. 3 is provided with connecting beams 12 so as to connect the concrete structures 3 and 3 of the adjacent tower main pedestal columns 2. By connecting the concrete structures 3 and 3 to each other by the connecting beam 12, the displacement of the foundation can be greatly suppressed.

施工は、先ず最初に、コンクリート構造体3の施工部を地盤掘削したならば、掘削部の壁面より水平穿孔を行い連結梁12を設置するための通孔を形成するか、比較的浅い場合にはオープン掘削により連結梁設置部分に溝を形成し、連結梁12を造成した後、鋼管5を設置する。なお、鋼管5の壁面には、予め前記連結梁12との一体化を図るために定着筋11の挿入口5aが形成されている。   First of all, if the construction part of the concrete structure 3 is excavated in the ground, if the drilling part forms a through hole for installing the connecting beam 12 by horizontal drilling from the wall surface of the excavation part, or if it is relatively shallow Forms a groove in the connecting beam installation portion by open excavation, and after forming the connecting beam 12, the steel pipe 5 is installed. An insertion port 5a for the fixing bar 11 is formed in advance on the wall surface of the steel pipe 5 so as to be integrated with the connecting beam 12 in advance.

次いで、杭体1,1…のための穿孔を行い杭体1、1…を地盤中に造成する。その後、定着筋8,8…を設置するとともに、主脚柱2の基部を鋼管5内の所定の位置に位置決めし、仮固定部材(図示せず)によって固定するとともに、鋼管5内に所定の鉄筋を配筋し、かつ鋼管5の挿入口5aから定着筋11を挿入し、すべての配筋作業を終えたならば、コンクリートを打設する。   Next, the pile bodies 1, 1... Are drilled to form the pile bodies 1, 1. After that, the fixing muscles 8, 8... Are installed, the base portion of the main pedestal 2 is positioned at a predetermined position in the steel pipe 5 and fixed by a temporary fixing member (not shown), and the predetermined portion in the steel pipe 5 is set. When reinforcing bars are placed and the fixing bars 11 are inserted from the insertion port 5a of the steel pipe 5 and all the placing work is completed, concrete is placed.

また、前記鋼管5の挿入口5aの外側部分にも、コンクリートを打設し、連結梁12の端部を固定し、コンクリート構造体3との一体化を図るようにする。   Further, concrete is also cast on the outer portion of the insertion port 5 a of the steel pipe 5 to fix the end of the connecting beam 12 so as to be integrated with the concrete structure 3.

〔本定着方式による定着耐力の設計〕
次に、本発明に係る鉄塔基礎の設計方法について説明する。
この設計方法は、割裂破壊を防止した上での破壊形態(鋼管5の降伏耐力、支圧板周囲のコンクリートの付着耐力、ズレ止め用リブ4の耐力)を終局耐力としているため合理的な設計となる。
[Design of fixing strength by this fixing method]
Next, a method for designing a steel tower foundation according to the present invention will be described.
This design method has a reasonable design because the ultimate strength is the fracture mode (yield strength of the steel pipe 5, the adhesion strength of the concrete around the bearing plate, the strength of the rib 4 for slippage prevention) after preventing the split fracture. Become.

本接合方式による定着耐力の設計は、以下の事項を考慮し、下記に示す式に基づいて設計することができる。
(1)コンクリートを拘束する前記鋼管5の降伏耐力(応力)は、次式(1)にて決定する。

Figure 0003754698
(2)支圧板7周囲のコンクリート付着耐力(応力度)は、次式(2)によって決定する。
Figure 0003754698
(3)前記ズレ止め用リブ4の耐力を検討するために、ズレ止め用リブ4の溶接部のせん断応力度は次式(3)にて決定する。
Figure 0003754698
(4)前記ズレ止め用リブ4に接するコンクリートの支圧応力度は、次式(4)にて決定する。
Figure 0003754698
(5)前記ズレ止め用リブ4の内周に接するコンクリートのせん断応力度は、次式(5)にて決定する。
Figure 0003754698
The fixing strength design by this joining method can be designed based on the following formula in consideration of the following matters.
(1) The yield strength (stress) of the steel pipe 5 that restrains the concrete is determined by the following equation (1).
Figure 0003754698
(2) The concrete adhesion strength (stress level) around the bearing plate 7 is determined by the following equation (2).
Figure 0003754698
(3) In order to examine the proof stress of the misalignment prevention rib 4, the shear stress degree of the welded portion of the misalignment prevention rib 4 is determined by the following equation (3).
Figure 0003754698
(4) The bearing stress level of the concrete in contact with the misalignment prevention rib 4 is determined by the following equation (4).
Figure 0003754698
(5) The degree of shear stress of the concrete in contact with the inner periphery of the displacement preventing rib 4 is determined by the following equation (5).
Figure 0003754698

第1形態例に係る鉄塔の基礎構造を示す、(A)は縦断面図、(B)は横断面図である。The basic structure of the steel tower which concerns on a 1st form example is shown, (A) is a longitudinal cross-sectional view, (B) is a cross-sectional view. 第2形態例に係る鉄塔の基礎構造を示す、(A)は縦断面図、(B)は右側面図、(C)は横断面図である。The basic structure of the steel tower which concerns on a 2nd form example is shown, (A) is a longitudinal cross-sectional view, (B) is a right view, (C) is a cross-sectional view. 第3形態例に係る鉄塔の基礎構造を示す縦断面図である。It is a longitudinal cross-sectional view which shows the basic structure of the steel tower which concerns on a 3rd form example. 主脚柱2の変形例を示す縦断面図である。FIG. 6 is a longitudinal sectional view showing a modification of the main pedestal 2. ズレ止め用リブ4の形態例図(A)〜(C)である。FIG. 4 is a view showing an example of the misalignment prevention rib 4 (A) to (C). 従来の鉄塔の基礎構造を示す、(A)は縦断面図、(B)は横断面図である。The basic structure of the conventional steel tower is shown, (A) is a longitudinal sectional view, and (B) is a transverse sectional view. 主脚柱52のいかり材定着方式を示す、(A)はフーチング縦断面図、(B)はいかり材の平面図、(C)はいかり材の側面図である。The anchoring material fixing method of the main pedestal 52 is shown, (A) is a footing longitudinal section, (B) is a plan view of the anchoring material, and (C) is a side view of the anchoring material. 主脚柱52の支圧板定着方式を示す、(A)は縦断面図、(B)は横断面図である。FIG. 5A is a longitudinal sectional view and FIG. 5B is a transverse sectional view showing a pressure plate fixing method of the main pedestal 52. (A)は杭体50の支圧板定着方式を示す図であり、(B)は鉄筋定着方式を示す図である。(A) is a figure which shows the bearing plate fixing system of the pile body 50, (B) is a figure which shows a reinforcing bar fixing system. 従来例に係る簡易な鉄塔の基礎構造を示す側面図である。It is a side view which shows the basic structure of the simple steel tower which concerns on a prior art example. 鉄塔基礎に対する風荷重による外力作用状態図である。It is an external-force action state figure by the wind load with respect to a steel tower foundation. フーチングの破壊形態(その1)を示す図である。It is a figure which shows the destruction form (the 1) of a footing. フーチングの破壊形態(その2)を示す図である。It is a figure which shows the destruction form (the 2) of a footing.

符号の説明Explanation of symbols

1…杭体、2…主脚柱、3…コンクリート構造体、4・4a〜4c…ズレ止め用リブ、5…鋼管、6…コンクリート、7…支圧板、8・11…定着筋、10…斜杭、12…連結梁   DESCRIPTION OF SYMBOLS 1 ... Pile body, 2 ... Main pedestal column, 3 ... Concrete structure, 4 * 4a-4c ... Rib for rib prevention, 5 ... Steel pipe, 6 ... Concrete, 7 ... Supporting plate, 8.11 ... Fixing reinforcement, 10 ... Diagonal piles, 12 ... connected beams

Claims (8)

地盤中に打設された複数本の杭体と、鉄塔の主脚柱とをコンクリート構造体を介して接合した鉄塔の基礎構造において、
前記コンクリート構造体は、内壁面に、周方向に沿って固設されたズレ止め用リブを上下方向に複数段に亘って有する鋼管内にコンクリートを打設することによって造成された構造体とし、前記コンクリート構造体の下部側に、前記地盤中に打設された複数本の杭体の頂部が接合され、かつ前記鉄塔主脚柱の下部に定着部材が設けられ、前記定着部材が設けられた主脚柱部分が前記コンクリート構造体に埋設されていることを特徴とする鉄塔の基礎構造。
In the foundation structure of a steel tower in which multiple piles placed in the ground and the main pedestal of the steel tower are joined via a concrete structure,
The concrete structure is a structure formed by placing concrete in a steel pipe having a plurality of steps in the vertical direction with a rib for fixing a slippage fixed on the inner wall surface along the circumferential direction, A top portion of a plurality of pile bodies placed in the ground is joined to the lower side of the concrete structure, and a fixing member is provided at a lower portion of the main tower pillar, and the fixing member is provided. A foundation structure of a steel tower, wherein a main pillar portion is embedded in the concrete structure.
前記複数本の杭体は、口径が400φmm以下又は口径が前記鋼管径の1/6以下の小口径杭とする請求項1記載の鉄塔の基礎構造。   The foundation structure of a steel tower according to claim 1, wherein the plurality of pile bodies are small-diameter piles having a diameter of 400 mm or less or a diameter of 1/6 or less of the steel pipe diameter. 前記ズレ止め用リブは、前記鉄塔主脚柱の支圧板配設部位を境に、その上部側及び下部側に夫々配設してある請求項1、2いずれかに記載の鉄塔の基礎構造。   The steel tower foundation structure according to any one of claims 1 and 2, wherein the misalignment prevention ribs are arranged on an upper side and a lower side, respectively, with a bearing plate arrangement portion of the main tower pillar as a boundary. 前記コンクリート構造体は、その大部分が地盤に埋設されている請求項1〜3いずれかに記載の鉄塔の基礎構造。   The said concrete structure is the foundation structure of the steel tower in any one of Claims 1-3 by which most is embed | buried under the ground. 前記鉄塔主脚柱の径をφ、前記鉄塔主脚柱における支圧板の配設区間長をL、前記鋼管の内径をDとするとき、L/φ=2〜5であり、かつD/φ=2〜10の条件を満足している請求項1〜4いずれかに記載の鉄塔の基礎構造。   When the diameter of the tower main pedestal column is φ, the section length of the bearing plate in the tower main pedestal column is L, and the inner diameter of the steel pipe is D, L / φ = 2 to 5 and D / φ The foundation structure of the steel tower in any one of Claims 1-4 which satisfy | fills the conditions of = 2-10. 前記コンクリート構造体の鋼管周壁部より斜め下方向に向けて打設された斜杭を備える請求項1〜5いずれかに記載の鉄塔の基礎構造。   The foundation structure of the steel tower in any one of Claims 1-5 provided with the diagonal pile cast toward diagonally downward from the steel pipe surrounding wall part of the said concrete structure. 前記隣接する鉄塔主脚柱のコンクリート構造体同士を結合する連結梁を備える請求項1〜5いずれかに記載の鉄塔の基礎構造。   The foundation structure of the steel tower in any one of Claims 1-5 provided with the connection beam which connects the concrete structures of the said adjacent steel tower main pedestal column. 前記鉄塔主脚柱の本数を2乃至4本とする請求項1〜5いずれかに記載の鉄塔の基礎構造。
The foundation structure of the steel tower according to any one of claims 1 to 5, wherein the number of the main tower pillars is 2 to 4.
JP2004271161A 2004-09-17 2004-09-17 Steel tower basic structure Expired - Lifetime JP3754698B1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP2004271161A JP3754698B1 (en) 2004-09-17 2004-09-17 Steel tower basic structure
PCT/JP2005/017144 WO2006030893A1 (en) 2004-09-17 2005-09-16 Foundation structure of tower
CNB200580029551XA CN100567659C (en) 2004-09-17 2005-09-16 The base configuration of iron tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004271161A JP3754698B1 (en) 2004-09-17 2004-09-17 Steel tower basic structure

Publications (2)

Publication Number Publication Date
JP3754698B1 true JP3754698B1 (en) 2006-03-15
JP2006083641A JP2006083641A (en) 2006-03-30

Family

ID=36060140

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004271161A Expired - Lifetime JP3754698B1 (en) 2004-09-17 2004-09-17 Steel tower basic structure

Country Status (3)

Country Link
JP (1) JP3754698B1 (en)
CN (1) CN100567659C (en)
WO (1) WO2006030893A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049521A (en) * 2016-06-23 2016-10-26 中国电力工程顾问集团中南电力设计院有限公司 Cross cantilever beam single-column self-balance foundation of power transmission line and construction method thereof
CN115419103A (en) * 2022-10-19 2022-12-02 四川省送变电建设有限责任公司 Power transmission line engineering foundation structure and construction method thereof

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4783746B2 (en) * 2007-01-29 2011-09-28 公益財団法人鉄道総合技術研究所 Joint structure of slant pile and foundation
CN101871217B (en) * 2009-04-23 2013-12-18 润弘精密工程事业股份有限公司 Method for connecting precast pile cap structure and connected structure thereof
WO2011090055A1 (en) * 2010-01-19 2011-07-28 新日本製鐵株式会社 Steel pipe pile
JP5563512B2 (en) * 2011-04-12 2014-07-30 レンドリース・ジャパン株式会社 Columnar structure and installation method of columnar structure
CN103174162A (en) * 2011-12-21 2013-06-26 上海市电力公司 Composite pile structure for iron tower of electric transmission line
CN102767189B (en) * 2012-07-31 2014-06-25 中铁第五勘察设计院集团有限公司 Set bearing platform foundations and construction method thereof
CN104790423B (en) * 2015-03-12 2017-03-01 中国能源建设集团浙江省电力设计院有限公司 A kind of large-scale transmission tower is combined and expands top bored concrete pile foundation
JP2017197984A (en) * 2016-04-28 2017-11-02 清水建設株式会社 Joining structure of phc pile and steel column
CN106381881B (en) * 2016-09-14 2018-06-22 中国海洋大学 A kind of gravity type single-pile foundation
CN106223356B (en) * 2016-09-21 2018-11-06 成都九十度工业产品设计有限公司 A kind of swelling column foot of Fast Installation
CN106968159A (en) * 2017-04-01 2017-07-21 徐冲 A kind of bridge structure of town airbus
JP7263671B2 (en) * 2018-08-09 2023-04-25 株式会社竹中工務店 pile foundation structure
JP7449880B2 (en) * 2021-01-18 2024-03-14 大成建設株式会社 Steel pipe column base structure
CN113914701A (en) * 2021-11-01 2022-01-11 峻江建设有限公司 Anti-toppling iron tower capable of being applied to soft soil

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5498009A (en) * 1978-01-19 1979-08-02 Kubota Ltd Method of building foundation for pylon on mountain
JP2000355938A (en) * 1999-06-17 2000-12-26 Nippon Steel Corp Connection structure of pile head and column, and drawing resistance structure of the pile head and footing
JP4576067B2 (en) * 2001-04-13 2010-11-04 新日本製鐵株式会社 Joint structure of pile head and steel underground beam
JP2003082689A (en) * 2001-09-11 2003-03-19 Chubu Electric Power Co Inc Execution method for foundation of steel pipe pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049521A (en) * 2016-06-23 2016-10-26 中国电力工程顾问集团中南电力设计院有限公司 Cross cantilever beam single-column self-balance foundation of power transmission line and construction method thereof
CN115419103A (en) * 2022-10-19 2022-12-02 四川省送变电建设有限责任公司 Power transmission line engineering foundation structure and construction method thereof

Also Published As

Publication number Publication date
CN100567659C (en) 2009-12-09
WO2006030893A1 (en) 2006-03-23
CN101010465A (en) 2007-08-01
JP2006083641A (en) 2006-03-30

Similar Documents

Publication Publication Date Title
WO2006030893A1 (en) Foundation structure of tower
JP4800899B2 (en) Pile head joint structure and construction method
JP5955108B2 (en) Pile reinforcement structure of existing building and its construction method
KR101827846B1 (en) Joint structure for steel bridge pier and concrete pile foundation
JP3764729B2 (en) Construction method of steel tower foundation using concrete restraint joint member
JP4691690B2 (en) Joint structure and joining method of pedestal
JP5456626B2 (en) Connection structure and method of connection between pile and steel column
WO2006030894A1 (en) Foundation structure of tower
JP3680294B2 (en) Mountain retaining method using braided piles consisting of diagonal piles
JP4448592B2 (en) Reinforcement pile fixture
JP5207108B2 (en) Structure and method for joining pier and footing
JP6102010B2 (en) Pile reinforcement structure of existing building and its construction method
KR101448145B1 (en) Column Integrated Footing
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP2010077656A (en) Structure and method for seismically strengthening column
CN114482071A (en) Device for improving rock-socketed depth of large-diameter cast-in-place pile
JP2002129583A (en) Building construction method and stress transmission device
JP6977688B2 (en) Precast footing for embankments and embankments
JP5551943B2 (en) Foundation structure using ground improvement body
KR20100004125U (en) A pile head reinforcement structure of concrete pile
JP3753632B2 (en) Construction method of existing seismic isolation piles and cast-in-place piles
CN220768081U (en) Combined inclined pile support foundation pit supporting structure
JP7406102B2 (en) Pile foundation structure and construction method of structure foundation
JP7499382B1 (en) Earthquake-resistant reinforcement structure

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051212

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051216

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3754698

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091222

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101222

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101222

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121222

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131222

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350