JP3729607B2 - Roof structure of outdoor assembly stairs and its construction method - Google Patents
Roof structure of outdoor assembly stairs and its construction method Download PDFInfo
- Publication number
- JP3729607B2 JP3729607B2 JP17975397A JP17975397A JP3729607B2 JP 3729607 B2 JP3729607 B2 JP 3729607B2 JP 17975397 A JP17975397 A JP 17975397A JP 17975397 A JP17975397 A JP 17975397A JP 3729607 B2 JP3729607 B2 JP 3729607B2
- Authority
- JP
- Japan
- Prior art keywords
- roof
- plate
- top surface
- column wall
- roof structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Steps, Ramps, And Handrails (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は屋外用組立階段の屋根構造およびその構築工法に関するものである。
【0002】
【従来の技術】
近年、マンションなどの集合住宅の屋外階段はプレキャストコンクリート製の組立階段が構築されるようになっている。この屋外階段の屋根を鉄筋コンクリートで構築する場合は、型枠が必要であったために外部足場を組んでいた。
【0003】
【発明が解決しようとする課題】
しかし、上記のように屋根を鉄筋コンクリートで構築する場合は、型枠や外部足場を必要としていたため、大がかりな工事となり、かつ危険を伴う工事であった。
【0004】
本発明はこれらの問題に鑑みてなされたものであり、その目的は、短期間でかつ安全に施工できる屋外用組立階段の屋根構造およびその構築工法を提供することである。
【0005】
【課題を解決するための手段】
以上の課題を解決するための屋外用組立階段の屋根構造は、両側に段板が組み付けられた柱壁の頂面に、適宜大きさのプレキャストコンクリート板からなる屋根板が取り付けられ、該屋根板は中央の開口部が柱壁の頂面に位置するように設置され、前記開口部の内周面に突設された連結プレートが柱壁の頂面から突設したアンカーボルトに固定されたことを特徴とする。また屋根板は1枚または2枚のプレキャストコンクリート板で形成されたことを含む。また屋根板上面の周縁に沿って適宜高さの突起部が設けられたことを含む。また屋根板は全体が上側に湾曲したことを含むものである。
また屋外用組立階段の屋根構造の構築工法は、両側に段板が組み付けられた柱壁の頂面に、適宜大きさのプレキャストコンクリート板からなる屋根板を中央の開口部が柱壁の頂面に位置するように設置し、前記開口部の内周面に突設された連結プレートを柱壁の頂面から突設したアンカーボルトに固定した後、前記柱壁の頂面と開口部とで形成された空隙部にコンクリートを打設することを特徴とする。また屋根板は1枚または2枚のプレキャストコンクリート板で形成されたことを含むものである。
また屋外用組立階段の屋根構造の構築工法は、両側に段板が組み付けられた柱壁の頂面に、適宜大きさのプレキャストコンクリート板からなる屋根板を中央の開口部が柱壁の頂面に位置するように設置し、前記開口部の内周面に突設された連結プレートを柱壁の頂面から突設したアンカーボルトに固定するとともに、前記頂面から突設した鉄筋を屋根板上面に形成された欠き込み部に折り曲げ配筋した後、前記柱壁の頂面と開口部とで形成された空隙部と、前記欠き込み部とにコンクリートを打設することを特徴とする。また屋根板は1枚または2枚のプレキャストコンクリート板で形成されたことを含むものである。
【0006】
柱壁や段板などと同じプレキャストコンクリート板で屋根板が形成され、該屋根板が連結プレートで柱壁の頂面に突設したアンカーボルトに固定されたことにより、屋根板の自重やその他の荷重による曲げ応力が、前記の連結プレートおよびアンカーボルトを通じて柱壁に伝達される。
【0007】
屋根板がプレキャストコンクリート板を使用して構築されたことにより、型枠や外部足場を必要とせずに、屋外用組立階段の屋根構造が短期間でかつ安全に構築できる。
【0008】
地上において屋根板に組立階段の最上部の柱壁を組み付けた後に、これを既に建て込まれた柱壁に接合したことにより、高所での組立作業が容易かつ簡潔になる。
【0009】
【発明の実施の形態】
以下、本発明の屋外用組立階段の屋根構造(以下屋根構造)の実施の形態を図面に基づいて説明する。図1は屋根構造の断面図、図2は屋根板の分解平面図、図3は屋根板の取り付け状態を示す平面図、図4は図3のA−A線断面図、図5の(1)は図3のB−B線断面図、(2)は同C−C線断面図である。
【0010】
図1は屋根構造1を示し、プレキャストコンクリート製の柱壁2と、該柱壁2に組み付けられた段板3と、最上部の柱壁の頂面2aに設けた屋板板4とから構成されている。
【0011】
屋根板4は、図2に示すように、2枚のプレキャストコンクリート板5が接続片5cで接合して構成されている。プレキャストコンクリート板5は建物側および先端側の水平板5aと、これらを結ぶ斜板5bとで構成され、建物側の水平板5aには接続筋6が突出されている。
【0012】
プレキャストコンクリート板5の接合辺を除く周縁には所定の高さの突起7が突設されているとともに、前記接合辺には凹溝8が形成され、この内面には連結プレート9が突設されている。また凹溝8の上面には、所定の大きさの欠き込み部10が形成され、ここには連結筋11が適宜間隔ごとに配筋され、その先端部が凹溝8まで臨んでいる。
【0013】
このプレキャストコンクリート板5が接合された屋根板4には凹溝8による開口部13が形成され、ここに連結プレート9が配設されている。また開口部13には連結筋11の先端部が僅かな間隔をもって突き合わせ配筋されている。
【0014】
図3および図4は、屋根板4を柱壁2に固定したものであり、プレキャストコンクリート板5の接合辺の一端部が柱壁の頂面2aに設置されている。また連結プレート9に柱壁の頂面2aのアンカーボルト14が挿入されてナット15で固定されているとともに、アンカーボルト14に取り付けた補強板19が連結プレート9に溶接されている。また突合せ配筋された連結筋11が添え筋16で溶接接合されて、連結筋11間に補強筋17が配筋されている。
【0015】
この屋根板4は、柱壁の頂面2aと開口部13から形成された空隙部18と、欠き込み部10とに打設されたコンクリート(図示せず)で柱壁2に固定されるとともに、水平板5aが接続筋6で建物12に接合されている。
【0016】
図6は他の屋根板20の平面図を示したものであり、(1)はプレキャストコンクリート板21の接合辺の上面全部にわたって欠き込み部22が設けられた構成と、欠き込み部22全体に連結筋23が配筋された構成とを除いては、前記の屋根板4と同一の構成である。また(2)は図2の屋根板4を1枚のプレキャストコンクリート板で形成した屋根板4を示したものであり、その他の構成は図2の屋根板4と同一である。
【0017】
以下に、上記の屋根構造の構築工法を説明する。まず、図2に示すような、プレキャストコンクリート板5を工場で製造して現場に搬送し、これらを地上で接合して屋根板4を形成する。この屋根板4には凹溝8による開口部13が形成され、ここに連結プレート9が配設されるとともに、連結筋11もわずかな間隔をもって突合せ配筋されている。
【0018】
このような屋根板4をクレーンで吊り上げて、既に組み立てられた柱壁の頂面2aに設置するとともに、連結プレート9にアンカーボルト14を挿入してナット15で固定する。またアンカーボルト14に取り付けた補強板19を連結プレート9に溶接する。そして突合せ配筋された連結筋11を添え筋16で接合して、連結筋11間に補強筋17が配筋されるようにする。
【0019】
次に、柱壁の頂面2aと開口部13で形成された空隙部18と、欠き込み部10と、接続筋が配筋された建物12の上面とに現場打ちコンクリート(図示せず)を打設して屋根構造1を構築する。このように屋根板4をプレキャストコンクリート板5で形成したことにより、屋根構造1が型枠や外部足場を必要とせずに構築できる。
【0020】
また図6(1)の屋根板20を使用する場合も、前記と同様に屋根板20を連結プレート24で柱壁2に固定するとともに、欠き込み部22全体に配筋した連結筋23を添え筋(図示せず)で溶接接合した後に、開口部25および欠き込み部22全体に現場打ちコンクリート(図示せず)を打設する。また同図の(2)の屋根板4を使用する場合も同様の方法で構築する。
【0021】
図7は上側に湾曲したプレキャストコンクリート板26を使用した屋根板27であり、上側に湾曲した構成を除いて、上記の屋根構造1と同一の構成である。
【0022】
この屋根構造28の構築工法は、地上において2枚のプレキャストコンクリート板26を突合せ接合して、図8に示すような屋根板27を形成し、これをクレーンで吊り上げて柱壁の頂面2aに設置する。そして開口部29の連結プレート30にアンカーボルト14を挿入してナット15で固定するとともに、アンカーボルト14に取り付けた補強板31を連結プレート30に溶接する。
【0023】
次に、図9に示すように、柱壁の頂面2aから突出した鉄筋32を折り曲げて反対側のプレキャストコンクリート板26の欠き込み部33に配筋するとともに、該欠き込み部33に配筋された連結筋34に添え筋35を重ね配筋する。そして柱壁の頂面2aと開口部29で形成された空隙部36と、欠き込み部33と、接続筋37が配筋された建物12の上面とに現場打ちコンクリート(図示せず)を打設する(図10および図11)。
【0024】
また図12は、地上において、組立階段における最上部の柱壁材2bに屋根板38を組み付けたものであり、これをクレーンで吊り上げて、既に建て込まれた柱壁2の最上部に接合して屋根構造を構築する。このように地上において柱壁材2bに屋根板38を組み付けたことにより、高所での組立作業が容易かつ簡潔となる。
【0025】
【発明の効果】
柱壁や段板などと同じプレキャストコンクリート板で屋根板が形成されたことにより、簡単な作業で屋根構造が構築できる。
【0026】
屋根板が連結プレートで柱壁の頂面に突設したアンカーボルトにネジ止めされたことにより、屋根板の自重やその他の荷重による曲げ応力が、前記の連結プレートおよびアンカーボルトを通じて柱壁に伝達できる。
【0027】
屋根板がプレキャストコンクリート板を使用して構築されたことにより、型枠や外部足場を必要とせずに屋根構造が構築できる。
【0028】
屋根板の上面の周縁に突設された適宜高さの突起により、雨水を所定の箇所に排水できる。
【0029】
屋根板が上側に湾曲したことにより、組立階段の景観およびグレードを高めることができる。
【0030】
適宜大きさのプレキャストコンクリート板からなる屋根板を、組立階段の最上部の柱壁に連結プレートで固定した後に、該固定部にコンクリートを打設して屋根構造を構築したことにより、屋根構造が外部足場を必要とせずに、短期間でかつ安全に構築できる。
【0031】
屋根板に組立階段の最上部の柱壁を地上において組み付けた後に、これを既に建て込まれた柱壁に接合したことにより、高所での組立作業が容易かつ簡潔になる。
【0032】
1枚のプレキャストコンクリート板で屋根板を形成したことにより、屋根構造が短期間でかつ簡単に構築できる。
【図面の簡単な説明】
【図1】屋根構造の断面図である。
【図2】屋根板の平面図である。
【図3】屋根板を取り付けた平面図である。
【図4】図3のA−A線断面図である。
【図5】(1)は図3のB−B線断面図、(2)は同C−C線断面図である。
【図6】(1)および(2)は他の屋根板の平面図である。
【図7】他の屋根構造の断面図である。
【図8】屋根板の平面図である。
【図9】図10のD−D線断面図である。
【図10】屋根板を取り付けた平面図である。
【図11】図10の断面図である。
【図12】最上部の柱壁を組み付けた屋根板の断面図である。
【符号の説明】
1、28 屋根構造
2 柱壁
2a 柱壁の頂面
3 段板
4、20、27、38 屋根板
5、26 プレキャストコンクリート板
6、37 接続筋
7 突起
8 凹溝
9、23、30 連結プレート
10、21、33 欠き込み部
11、22、34 連結筋
12 建物
13、25、29 開口部
14 アンカーボルト
15 ナット
16、24、35 添え筋
17 補強筋
18、36 空隙部
19、31 補強板[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a roof structure of an outdoor assembly staircase and a construction method thereof.
[0002]
[Prior art]
In recent years, precast concrete assembly stairs have been constructed for outdoor stairs in apartment buildings such as condominiums. When constructing the roof of this outdoor staircase with reinforced concrete, a formwork was required, so an external scaffold was built.
[0003]
[Problems to be solved by the invention]
However, when the roof is constructed of reinforced concrete as described above, a formwork and an external scaffold are required, which is a large-scale construction and a construction that involves danger.
[0004]
The present invention has been made in view of these problems, and an object thereof is to provide a roof structure for an outdoor assembly staircase that can be safely constructed in a short period of time and a construction method thereof.
[0005]
[Means for Solving the Problems]
The roof structure of the outdoor assembly staircase for solving the above-mentioned problem is that a roof plate made of a precast concrete plate of an appropriate size is attached to the top surface of a column wall having step plates assembled on both sides. Was installed so that the central opening was located on the top surface of the column wall, and the connecting plate protruding on the inner peripheral surface of the opening was fixed to the anchor bolt protruding from the top surface of the column wall It is characterized by. Moreover, the roof board includes that it is formed of one or two precast concrete boards. Moreover, it includes that a protrusion having an appropriate height is provided along the periphery of the upper surface of the roof plate. Further, the roof plate includes that the whole is curved upward.
In addition, the construction method of the roof structure of outdoor assembly stairs is the top surface of the column wall with stepped plates on both sides, the roof plate made of precast concrete plate of appropriate size, and the central opening is the top surface of the column wall After fixing the connecting plate protruding on the inner peripheral surface of the opening to the anchor bolt protruding from the top surface of the column wall, the top surface of the column wall and the opening It is characterized in that concrete is placed in the formed gap. Moreover, the roof board includes that it is formed of one or two precast concrete boards.
In addition, the construction method of the roof structure of outdoor assembly stairs is the top surface of the column wall with stepped plates on both sides, the roof plate made of precast concrete plate of appropriate size, and the central opening is the top surface of the column wall The connecting plate protruding from the inner peripheral surface of the opening is fixed to the anchor bolt protruding from the top surface of the column wall, and the reinforcing bar protruding from the top surface is fixed to the roof plate. After bending and arranging in the notch formed on the upper surface, concrete is placed in the gap formed by the top surface of the column wall and the opening and the notch . Or shingles are those comprising formed by one or two precast concrete plate.
[0006]
A roof plate is formed of the same precast concrete plate as a column wall or a corrugated plate, and the roof plate is fixed to an anchor bolt protruding from the top surface of the column wall with a connecting plate. The bending stress due to the load is transmitted to the column wall through the connection plate and the anchor bolt.
[0007]
Since the roof plate is constructed using a precast concrete plate, the roof structure of the outdoor assembly stair can be constructed safely in a short period of time without the need for a formwork or an external scaffold.
[0008]
After assembling the uppermost column wall of the assembly staircase on the roof plate on the ground, this is joined to the already built column wall, making assembly work at high places easy and simple.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments of a roof structure (hereinafter referred to as a roof structure) for an outdoor assembly staircase of the present invention will be described with reference to the drawings. 1 is a cross-sectional view of the roof structure, FIG. 2 is an exploded plan view of the roof plate, FIG. 3 is a plan view showing the state of attachment of the roof plate, FIG. 4 is a cross-sectional view taken along line AA in FIG. ) Is a cross-sectional view taken along line BB in FIG. 3, and (2) is a cross-sectional view taken along line CC.
[0010]
FIG. 1 shows a
[0011]
As shown in FIG. 2, the
[0012]
A
[0013]
The
[0014]
3 and 4 show the
[0015]
The
[0016]
FIG. 6 shows a plan view of another
[0017]
Below, the construction method of said roof structure is demonstrated. First, the
[0018]
Such a
[0019]
Next, cast-in-place concrete (not shown) is applied to the
[0020]
6 (1), when the
[0021]
FIG. 7 shows a
[0022]
In the construction method of the
[0023]
Next, as shown in FIG. 9, the reinforcing
[0024]
FIG. 12 shows the roof plate 38 assembled to the uppermost
[0025]
【The invention's effect】
The roof structure can be constructed with a simple operation by forming the roof panel with the same precast concrete plate as the column wall and corrugated board.
[0026]
Because the roof plate is screwed to the anchor bolt protruding from the top surface of the column wall with a connecting plate, the bending stress due to the roof plate's own weight and other loads is transmitted to the column wall through the connecting plate and anchor bolt. it can.
[0027]
Since the roof board is constructed using precast concrete boards, the roof structure can be constructed without the need for formwork or external scaffolding.
[0028]
Rainwater can be drained to a predetermined location by a protrusion having an appropriate height protruding from the periphery of the upper surface of the roof panel.
[0029]
The scenery and grade of an assembly staircase can be enhanced by the roof board being curved upward.
[0030]
After fixing the roof plate made of precast concrete plate of appropriate size to the column wall at the top of the assembly staircase with the connecting plate, concrete was placed on the fixed portion to construct the roof structure, so that the roof structure It can be constructed quickly and safely without the need for an external scaffold.
[0031]
By assembling the top column wall of the assembly staircase on the roof plate on the ground, and then joining it to the already built column wall, the assembly work at a high place becomes easy and simple.
[0032]
By forming the roof board with a single precast concrete board, the roof structure can be easily constructed in a short period of time.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of a roof structure.
FIG. 2 is a plan view of a roof plate.
FIG. 3 is a plan view with a roof plate attached.
4 is a cross-sectional view taken along line AA in FIG.
5 is a cross-sectional view taken along line BB in FIG. 3, and (2) is a cross-sectional view taken along line CC in FIG.
FIGS. 6A and 6B are plan views of other roof boards. FIGS.
FIG. 7 is a cross-sectional view of another roof structure.
FIG. 8 is a plan view of a roof plate.
9 is a cross-sectional view taken along the line DD of FIG.
FIG. 10 is a plan view with a roof plate attached.
11 is a cross-sectional view of FIG.
FIG. 12 is a cross-sectional view of a roof plate assembled with the uppermost column wall.
[Explanation of symbols]
DESCRIPTION OF
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17975397A JP3729607B2 (en) | 1997-07-04 | 1997-07-04 | Roof structure of outdoor assembly stairs and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17975397A JP3729607B2 (en) | 1997-07-04 | 1997-07-04 | Roof structure of outdoor assembly stairs and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1122093A JPH1122093A (en) | 1999-01-26 |
JP3729607B2 true JP3729607B2 (en) | 2005-12-21 |
Family
ID=16071286
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP17975397A Expired - Lifetime JP3729607B2 (en) | 1997-07-04 | 1997-07-04 | Roof structure of outdoor assembly stairs and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3729607B2 (en) |
-
1997
- 1997-07-04 JP JP17975397A patent/JP3729607B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH1122093A (en) | 1999-01-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA1331830C (en) | Space frame structure | |
EA006995B1 (en) | Method and apparatus for precast and framed block element construction | |
KR100211534B1 (en) | The coupling structure between pc wall and pc slab, and the method thereof | |
KR200414349Y1 (en) | Connection structure of precast concrete structure | |
JP3881135B2 (en) | Connecting structure of floor slabs using concrete truss with concrete slab in bridge girder | |
JPH04269229A (en) | Space frame structural body | |
JP3729607B2 (en) | Roof structure of outdoor assembly stairs and its construction method | |
JPS6314937A (en) | Reinforcing bar composite pillar | |
JPH03132532A (en) | Construction method of precast reinforced concrete column and beam | |
JP2897663B2 (en) | How to build underground structures | |
JP2654935B2 (en) | Construction method of ribbed slab and spacer for rib reinforcement | |
JP3116767B2 (en) | Existing building seismic isolation structuring method | |
JP3233531B2 (en) | Assembly stairs | |
JP2817591B2 (en) | Construction method of steel reinforced concrete building | |
JP3028297B2 (en) | Half precast slab and floor structure using the same | |
JP3944870B2 (en) | Method for constructing staircase with staircase and unit staircase used in this construction method | |
JPH0334963Y2 (en) | ||
JPH0681315A (en) | Construction method for concrete main tower | |
JP3830627B2 (en) | Joint structure of reinforced concrete columns and beams | |
JP2673235B2 (en) | Parallel string reinforcement truss frame structure of building | |
JP2586994B2 (en) | Assembly stairs | |
JPH0781355B2 (en) | Construction method of joist slab using precast concrete girder | |
JP2683878B2 (en) | Precast staircase structure | |
JP2642598B2 (en) | PC foundation for wall columns of assembly stairs | |
JP2558889Y2 (en) | garage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050224 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050302 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050418 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20050704 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050712 |
|
A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20050817 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050920 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20051004 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081014 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111014 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111014 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121014 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121014 Year of fee payment: 7 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121014 Year of fee payment: 7 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121014 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131014 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |