JP3662470B2 - Suspended mobile pile embedding device and pile embedding method using the same - Google Patents

Suspended mobile pile embedding device and pile embedding method using the same Download PDF

Info

Publication number
JP3662470B2
JP3662470B2 JP2000107387A JP2000107387A JP3662470B2 JP 3662470 B2 JP3662470 B2 JP 3662470B2 JP 2000107387 A JP2000107387 A JP 2000107387A JP 2000107387 A JP2000107387 A JP 2000107387A JP 3662470 B2 JP3662470 B2 JP 3662470B2
Authority
JP
Japan
Prior art keywords
pile
reaction force
suspended
embedding
base beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2000107387A
Other languages
Japanese (ja)
Other versions
JP2001248375A (en
Inventor
正壽 大久保
英宣 野呂
Original Assignee
株式会社モリセン
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社モリセン filed Critical 株式会社モリセン
Priority to JP2000107387A priority Critical patent/JP3662470B2/en
Publication of JP2001248375A publication Critical patent/JP2001248375A/en
Application granted granted Critical
Publication of JP3662470B2 publication Critical patent/JP3662470B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Earth Drilling (AREA)

Description

【0001】
【発明の目的】
この発明は、構造物用基礎地盤を強化するための杭埋込み作業に係わるものであって、特に、杭埋込み対象地盤箇所が、従前からのクローラ杭埋込み機や移動式クレーン等大型建設機械の持ち込みを不可能とする箇所、例えば町中の狭小な施工現場や、高低さがある箇所で高低何れか側にしか接近できず、接近できる側ではない箇所となる施工現場等の杭埋込み作業が実施可能となるようにする新規な構造からなる吊下移動式杭埋込装置と、それを使用した新規な杭埋込方法とを提供しようとするものである。
【0002】
【従来の技術】
ビルディングや橋梁、広告塔、防音壁、防雪柵等々、我々を取り巻く各種構造物は、その自重は勿論のこと、その構造物に加わる外部荷重、例えば人や荷物、車両等といった各種積載物による荷重から、地震や強風等自然エネルギーに起因した荷重にまで耐え得るだけの十分な構造強度を有していて、安全に自立しておられるように設計されていなければならいが、いくら構造物自体を頑強に造り上げたとしても、それを支える基礎地盤の支持耐力が十分に確保されていなければ、頑強な筈の構造物も極めて簡単に破損、倒壊してしまうことになり、人々の平穏な日常生活が脅かされてしまうことになる。
【0003】
そのため、各種構造物は、その規模や公共性、立地条件等に応じ、建設計画段階に十分な地質調査を実施して地盤の状態を把握した上、それに応じた地盤強化策、例えばケーソン工法や杭埋込み工法等が検討され、公害規制等の法的配慮もなされた上で最適な工法が採用、実施に移され、確実な地盤強化を施してからその上に設計どおりの構造物を建設していくことになる。
【0004】
従前からこの地盤強化策として最も繁用されてきている工法の一つに、主として地盤との間の摩擦抵抗を反力として構造物を支えるようにした杭埋込み工法があり、杭の打ち込み方によって分類される各種工法がこれまでにも多く開発、実用化されてきており、その代表的な工法として、伝統的な振動工法や打撃工法の外にも、プレボーリング工法や中掘り工法等も広く知られるところのものとなっている。
【0005】
伝統的な振動工法や打撃工法の場合、バイブロハンマーやディーゼルパイルハンマーを使って直接的に杭に衝撃を加え、地盤中に杭を強力に差し込んでいく工法であり、その機構、構造が単純であって、しかも期待どおりの杭埋込み作業を実施できることから、長年に渡って杭埋込み工法の主流をなしてきていたが、近年では、周辺住民に及ぼす騒音や振動が社会問題となり、市街地から十分離れた山間僻地や海岸、海上等一定地域以外での使用が騒音防止条例によって規制されるところになり、この騒音防止条例制定以降では、低振動、低騒音の施工を可能にするプレボーリング工法や中掘り工法等が杭埋込み工法の中心をなすようになってきており、それらについても各社各様に改良、開発した工法が実施されてきている。
【0006】
例えば、代表的なプレボーリング工法を見てみると、クローラ杭埋込み機Kのリーダにミルク注入部を兼用するオーガを装着し、ミルク注入部を通じてオーガヘッドの先端側から掘削液を噴出させながら、同オーガを回転駆動することによって地盤を掘削し、回転するオーガの螺旋状翼部に沿って掘削した土砂や掘削液を上昇、排出し、掘削孔内から地表部へ土砂を排出させ、所定深さまで掘削した後、ミルク注入部を通じて同掘削孔中にセメントミルクを注入しながらオーガを抜き去り、同掘削孔内に所定の既成杭を挿入、埋設するようにした工事によるものとなるが、この工法に使用するクローラ杭埋込み機Kは、移動式クレーン車のクレーンでガイドポストK1を支持する構造となつていて、極めて大型の建設機械に頼る工法の一つということができる。
【0007】
また、従来からの中掘り工法も、大型クローラに直接リーダー下端を支持した上、二本の控えビームK2とで固定してなる移動式直結三点支持機を使い、リーダーに添わせて立設した中空先端開放杭を、その中空部に配したアースオーガの回転、掘削によって杭孔を先行しながら押し込んでいき、所定深度にまで杭が押し込まれた後、アースオーガを引き上げて内部にセメントミルクを注入、固化するようにした工事によるものであって、やはり、前記したプレボーリング工法同様に大型建設機械によるものとなっている上、直接この移動式直結三点支持機のリーダーが望む位置での杭埋込みしかできず、更に小回りが利かないという制約も受けてしまうものとなっている。
【0008】
これら伝統的な振動工法や打撃工法に代わって登場してきたプレボーリング工法や中掘り工法は、確かに騒音公害もなく確実に杭埋込み工事が遂行できるという点において秀れた工法とすることができるものの、上述の如く、何れも大型建設機械であるがために、混み入った市街地で各種構造物が林立しているような建設現場や、丘陵地帯を切り開いて建設が進む高速道路等で、法面の上に防音壁等各種構造物を建設する際のような高低差の著しい建設現場等においては、必要とされる建設機械の導入が不可能となって折角の秀れた工法も実質的に採用することができないという問題を抱えるものとなっていた。
【0009】
この発明は、秀れた工法として知られるプレボーリング工法や中掘り工法の上記したとおりの問題に対処すべく、長年に渡って建設業に携わるものの一人として逸早くその開発、研究に着手し、様々な試行錯誤と試作実験とを繰り返してきた結果、遂に茲にきてそれら従前からの工法では果たすことができなかった杭埋込みを可能にする新規な削孔方法、およびそれに使用する新規な構成からなる吊下移動式削孔装置の実現化に成功したものであり、以下では、具体的な実施例と共にその構成を詳述していくこととする。
【0010】
【発明の構成】
この発明の吊下移動式杭埋込装置は、基本的に次のとおりの構成を要旨とするものである。
即ち、レベリングジャッキと反力アンカー装着部とが両端側に夫々一体形成されてなるベースビームに対し、その長さ方向略中央から、上端に吊下部が形成されたリーダーを立設、一体化した上、該リーダーの上端近傍で前記吊下部形成箇所に重複しない箇所には、2本のワイヤーを巻き掛け可能とするシーブを両端近傍夫々に配してなるトップビームが、当該リーダー軸芯に交叉状配置となる如く一体化されたものとして装置骨格体となす一方、該装置骨格体ベースビーム部分の、リーダー取着部側近には上下に貫通状とした杭ガイド部が、また、杭ガイド部から離れた箇所には電動オーガ昇降用ウインチおよび杭装着用ウインチが夫々配設されてなるものとした吊下移動式杭埋込装置である。
【0011】
この基本的な構成の吊下移動式杭埋込装置は、より具体的な構成によるものとすれば、レベリングジャッキを近接配置してなる反力アンカー装着部が両端夫々に一体形成されると共に、少なくとも何れか一方の反力アンカー装着部の外側には、既設杭への仮着部を併設してなる十分な長さと構造強度とを有するベースビームに対し、その長さ方向略中央から、杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端に吊下部が形成されてなるリーダーを立設、一体化した上、該リーダーの上端近傍で前記吊下部形成箇所に重複しない箇所には、2本のワイヤーを巻き掛け可能とするシーブを両端近傍夫々に配してなるトップビームが、当該リーダー軸芯に交叉状配置であって、前記ベースビームに略平行状となる如く一体化されたものとして装置骨格体となす一方、該装置骨格体トップビームの、一方のシーブの略真下に相当するベースビーム部分には、上下に貫通状とした杭ガイド部が設けられ、同他方のシーブの真下からやや端部側にずらした箇所のベースビーム部分には、電動オーガ昇降用ウインチと杭装着用ウインチとが配設された上、当該電動オーガ昇降用ウインチから両シーブを経由して導出したワイヤーに電動オーガ装置部を昇降自在に吊下すると共に、他方杭装着用ウインチから両シーブを経由して導出したワイヤー先端に杭吊り込み金具を取着してなるものとした構成を要旨とする吊下移動式杭埋込装置ということができる。
【0012】
また、前記した基本的な構成からなるこの発明の吊下移動式杭埋込装置には、レベリングジャッキを近接配置してなる反力アンカー装着部が両端夫々に一体形成されると共に、少なくとも何れか一方の反力アンカー装着部の外側には、既設杭への仮着部を併設してなる十分な長さと構造強度とを有するベースビームに対し、その長さ方向略中央から、杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端に吊下部が形成されてなるリーダーを立設、一体化した上、該リーダーの上端近傍で前記吊下部形成箇所に重複しない箇所には、2本のワイヤーを巻き掛け可能とするシーブを両端近傍夫々に配してなるトップビームが、当該リーダー軸芯に交叉状配置であって、前記ベースビームに略平行状となる如く一体化されたものとして装置骨格体となす一方、該装置骨格体トップビームの、一方のシーブの略真下に相当するベースビーム部分には、上下に貫通状とした杭ガイド部が設けられ、同他方のシーブの真下からやや端部側にずらした箇所のベースビーム部分には、電動オーガ昇降用ウインチと杭装着用ウインチとが配設された上、当該電動オーガ昇降用ウインチから両シーブを経由して導出したワイヤーに電動オーガ装置部を昇降自在に吊下すると共に、他方杭装着用ウインチから両シーブを経由して導出したワイヤー先端に杭吊り込み金具を取着してなるものとした構成を要旨とする吊下移動式杭埋込装置も包含されている。
【0013】
装置骨格体は、杭埋込過程における削孔反力を装置骨格体自身で打ち消しながら削孔ならびに杭埋込を実施可能とする機能が果たし得るものとして形成されると共に、クローラクレーンのブームから吊り下げたワイヤーに係止され、ブームの傾斜、旋回範囲内での所望する杭埋込箇所まで自在に何回でも吊り下げ移動された上、各杭埋込箇所における立設姿勢は、当該クレーンのワイヤーを緊張したままとすることによって維持されるようにしたものに形成される必要がある。
【0014】
したがって、この装置骨格体は、削孔ならびに杭埋込機能分担用の電動オーガを案内すると共に、この装置自体を吊り下げ、移動する際に背骨的機能を果たすことになるリーダーと、該リーダー下端を支持した上、リーダーに加わる削孔反力を杭埋込箇所の地盤と共に負担するベースビームと、電動オーガの昇降作動、操作すると共に、杭の吊り込み操作するため、ベースビーム適所に配するウインチからのワイヤーがリーダー上端を経由できるようにしているワイヤー誘導機構、即ちシーブ等組込み用としてのトップビームとによって構成されるものであって、何れも十分な強度を有する鋼材から形成され、リーダー下端はベースビームの略中央部分に、またリーダー上端側でクレーン吊りのための吊下部を残した辺りにトップビームが、夫々熔着等公知の手段で堅固に一体化されてなるものとする。
【0015】
ベースビームは、上述の如く、装置骨格体の一部をなしてリーダーに加わる削孔反力を杭埋込箇所の地盤に伝える機能を果たすと共に、リーダーの鉛直性を確保する機能も果たすことになるため、十分な長さ、例えば後述する実施例に取り上げているもののように、長さ10メートルのリーダーとすれば7〜8メートル程度の長さのものとする等固定的な長さのものに形成するか、あるいは、埋込むべき杭の長さや地盤の状態その他の要因によって長さを適宜調節可能とし得るよう、ベースビームを、例えばリーダーを取着する主杆と、その両側の反力アンカー装着部形成側とする副杆とか、リーダーおよび両反力アンカー装着部を取着、形成する主杆と、既設杭への仮着部形成側とする副杆とに分離、形成し、当該主杆に副杆が適宜公知の手段によって伸縮自在に連結されるようにした構造のもの、例えば主杆に対して副杆を差込み構造、添え板添設構造、雇い杆仲介構造等強度有る連結構造で接続するようにした上、油圧手段やボルト締め等によって相互の接続位置を固定できるようにしたものとすることも可能であり、何れもこの発明に包含されている。
【0016】
そして、このベースビームの両端には、夫々レベリングジャッキを近接配置してなる反力アンカー装着部が一体的に形成されてなるものとし、望ましくは少なくとも何れか一方の反力アンカー装着部の外側に、既設杭への仮着部を併設し、二本目以降の杭を埋め込む作業に際しては、その仮着部の併設された側の反力アンカー装着部に反力アンカーを装着する代わりに同仮着部を既設杭に装着し、削孔反力の一部を既設杭によって負担するようにしたものとし、作業の効率化を図ると共に、より安全な反力負担が実現されるようにしたものとする。
【0017】
また、このベースビームには、リーダー下端取着部分に近接した箇所であってトップビームに組み込んだワイヤー誘導機構としての一方のシーブの略真下に相当する箇所に、上下に貫通状とした杭ガイド部を設け、その貫通部分を案内にして、埋め込むべき杭が所定の箇所に正しく位置させられるようにしたものとしなければならず、また、同他方のシーブの真下からやや端部側にずらした箇所には、電動オーガ昇降用ウインチと杭装着用ウインチとが配設され、各ウインチからのワイヤーが、トップビームにワイヤー誘導機構として組み込んである一対のシーブを夫々経由して、一方は電動オーガ上端に組み込んである滑車に巻回され、他方はその先端に杭吊り込み用のフックが装着されてなるものとする。
【0018】
なお、これら装置骨格体を構成するリーダー、ベースビーム、トップビームの組合せ構造(一体化する際の相互の位置関係等)や、ベースビームに組み込む反力アンカー装着部、仮着部、レベリングジャッキ、両ウインチの配置具合は、リーダー上端の吊下部をクレーンで吊り上げたときのバランスを考慮して最適な配置関係となるようにすべきである。
【0019】
【関連する発明】
上記のとおりの構成を要旨とする吊下移動式杭埋込装置に関連し、この発明には、その吊下移動式杭埋込装置を使用した次のような基本的な構成を要旨とする杭埋込み方法が包含される。
即ち、杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端には吊下部およびワイヤー巻回機構の組み込まれたトップビームが一体に配されてなるリーダーの下端を、両端夫々に反力アンカー装着部が一体形成され、十分な長さと構造強度とを有するベースビームに一体化したものとしてなる装置骨格体を、移動式クレーンによって吊り下げて昇降移動させ、所定箇所においてその都度起立状に保持したまま、当該ベースビームのレベル調整と共に、両反力アンカー装着部に夫々反力アンカーを装着、打ち込みをなし、ベースビームが削孔箇所の地盤に支持されるようした上、電動オーガ装置部に連結したオーガスクリューを内装状とするようにして先端開放中空杭を杭装着用ウインチから導出したワイヤーで吊り込むと共に、その下端側を杭ガイド部に挿通してから、該電動オーガ装置部を作動し、削孔反力は装置骨格体自身で打ち消しながら削孔することによって先端開放中空杭を所定深度にまで埋込んだ後、電動オーガ昇降用ウインチから導出したワイヤーでオーガスクリューだけを引き上げ、所定箇所の地中に残置した先端開放中空杭の中空部に土砂等を埋め戻し、填圧するようにしてなる一連の作業工程により、所定箇所における杭埋込み作業を終えた後、引き続き、装置骨格体全体を移動式クレーンで吊り上げ、移動式クレーン作業圏内であって、移動式クレーンからは離れた複数の杭埋込箇所において、移動式クレーンの移動、接近をすることなく、先の一連の作業工程を順次繰り返していくようにした杭埋込方法である。
【0020】
更に、この発明には、近接する二本目以降の杭埋込みに有利になる杭埋込方法として、杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端には吊下部およびワイヤー巻回機構の組み込まれたトップビームが一体に配されてなるリーダーの下端を、両端夫々に反力アンカー装着部が一体形成され、十分な長さと構造強度とを有するベースビームに一体化したものとしてなる装置骨格体を、移動式クレーンによって吊り下げ、昇降移動させ、移動箇所においてその都度起立状に保持したまま、当該ベースビームのレベル調整と共に、何れか一方の反力アンカー装着部側に既設の杭の仮着、他方の反力アンカー装着部に反力アンカーの装着、打ち込みをなし、ベースビームが削孔箇所の地盤に支持されるようした上、電動オーガ装置部に連結したオーガスクリューを内装状とするようにして先端開放中空杭を杭装着用ウインチから導出したワイヤーで吊り込むと共に、その下端側を杭ガイド部に挿通してから、該電動オーガ装置部を作動させ、削孔反力は装置骨格体自身で打ち消しながら削孔することによって先端開放中空杭を所定深度にまで埋込んだ後、電動オーガ昇降用ウインチから導出したワイヤーでオーガスクリューだけを引き上げ、所定箇所の地中に残置した先端開放中空杭の中空部に土砂等を埋め戻し、填圧するようにしてなる一連の作業工程により、所定箇所における杭埋込み作業を終えた後、引き続き、装置骨格体全体を移動式クレーンで吊り上げ、移動式クレーン作業圏内であって、移動式クレーンからは離れた複数の杭埋込箇所において、移動式クレーンの移動、接近をすることなく、先の一連の作業工程を順次繰り返していくようにした構成を要旨とする杭埋込み方法も包含されている。
【0021】
装置骨格体は、リーダーをガイドとして昇降自在となる電動オーガ装置部(即ち、騒音公害に対処可能な構成を有する公知の削孔装置を代表するものであって、その他、今後開発されるであろう同種の各種削孔装置が包含される。以下、同様。)が組み込まれ、同オーガスクリューの回転作動(その他各種削孔装置に応じた削孔機能を含む。以下、同様。)によって削孔する能力を有すると共に、オーガスクリュー削孔反力を自らで打ち消しながら削孔できるようにしたものに形成されていなければならず、公知の各種移動式クレーンによって適宜所望する削孔、杭埋込み箇所まで吊り下げ、昇降移動された上、同所における起立状態を移動式クレーンの吊り下げワイヤーの緊張によって支持されるようにするが、移動式クレーン側には削孔反力に抗するための負荷が掛かるようなことはない。なお、移動式クレーンの作動圏内では、該移動式クレーン自体の移動なしで装置骨格体の移動、削孔を繰り返していくことになる。
【0022】
移動式クレーンによって適宜所望する削孔箇所まで吊り下げ、昇降移動された装置骨格体は、削孔作業に先んじ、リーダーの鉛直性を実現するために削孔箇所においてレベル調整がなされなければならず、その後、自らにおいて削孔反力を打ち消すことができるようにするための工程として、削孔箇所における地盤に対し、削孔反力が直接掛かるリーダーが安定して連結されるようにした作業を実施する。
【0023】
そのため、当該リーダーの下端には、十分な長さと構造強度とを有し、両端夫々に反力アンカー装着部の形成されてなるベースビームが強固に一体化されてなる構造のものとして装置骨格体を構成し、該ベースビームの両反力アンカー装着部に夫々反力アンカーを装着した上、それら反力アンカーを強固に地盤に打ち込んで一体化を図り(必要があればその後にレベル調節するようにしたり、再度レベル調節の必要があれば実施する)、これら反力アンカーによって地盤に連結されたベースビームを介して、間接的にリーダーの削孔反力が打ち消される削孔作業の実施を可能にするものである。その際、反力アンカー装着部間の距離が調節可能なベースビームを採用したものについては、削孔箇所における地盤地耐力や削孔深度に応じ、ベースビーム全長を調節して削孔反力の打ち消しが確実に達成されるようにすると極めて好都合のものとなる。
【0024】
なお、所望する箇所における最初の削孔作業に引き続き、二本目以降の削孔作業については、一本目と同様に、ベースビームの両反力アンカー装着部に夫々反力アンカーを装着した上、それら反力アンカーを強固に地盤に打ち込んで一体化を図る上記したとおりの工程を繰り返していっても勿論差し支えはないが、予め、少なくとも何れか一方の反力アンカー装着部側に、それよりも外側部分を、既設の杭(即ち、削孔作業を終えた杭孔に埋込まれた状態となっている杭)への適宜仮着手段、例えばベルト状金具による挟着構造、リング状金具による嵌合構造等各種公知の手段が講じられたものに形成しておき、当該仮着手段によってベースビームの少なくとも一端側だけは、反力アンカーではなく、既設の杭によって地盤への連結、支持がなされるようにした工程を採用するようにし、二本の反力アンカーをその都度打ち込む工程を一本で済まして簡略化できるようにしたものとすることもできる。
【0025】
こうして、装置骨格体が、移動式クレーンによって起立状に保持され、レベル調整を終えた段階で、当該装置骨格体に予め組み込まれている電動オーガ装置部の作動により、オーガスクリューを回転させ、所定箇所の地盤をオーガーヘッドで削孔し、所定の杭を徐々に沈降させる杭埋込み工程に移行するが、その際のオーガーヘッドからオーガスクリュー、電動オーガ装置部を通じて装置骨格体に加わる削孔反力は、地盤に支持された装置骨格体自身で打ち消すことができることになり、装置骨格体を起立状とする移動式クレーン側に負荷を掛けてしまうことはない。
【0026】
杭埋込み工程は、従前からの中掘り工法と略同様の過程を経て実施されれば足りるものであって、所定深度への埋込みを実現した杭だけを地盤中に残置したまま、電動オーガ昇降用ウインチから導出したワイヤーでオーガスクリューを引き上げ、土砂や砕石の埋め戻し、填圧も従前どおりに進め、所定箇所における杭埋込みを完了したところで、装置骨格体全体を移動式クレーンで吊り上げてしまってからは、それまでの一連の作業工程を、移動式クレーン作業圏内であって、移動式クレーンからは離れた複数の杭埋込箇所において、移動式クレーンの移動、接近させないで、順次繰り返し実施していき、移動式クレーン作業圏内での複数の杭埋込み作業を終えてしまった段階で、はじめて次の複数の杭埋込み作業を必要とする範囲を作業圏内とする場所で、走行可能な場所にまで移動式クレーンを移動させるものである。
以下では、これまでに詳述してきたこの発明の吊下移動式削孔装置、およびそれを使用した杭埋込方法についての構成が、より一層明確なものとなるよう、この発明を代表する具体的な実施例を取り上げ、それらについて説明を加えていくことにする。
【0027】
【実施例1】
図1は、この発明の代表的な構成を具備し、起立状に支持してなる吊下移動式削孔装置の全体側面図、図2は、移動式クレーンによる吊り下げ態様を示した概略的に示した側面図、図3ないし8図は、この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の使用態様を概略的に示す側面図である。
【0028】
図1の全体側面図からも明確に把握できるとおり、この実施例のための吊下移動式削孔装置は、全長を約10.5m程度とし、一辺を400mmとする箱型肉厚中空断面の鋼材からなり、上端には吊下部11を形成してなるリーダー1に対し、その下端には、該リーダー1と略同様の素材断面で、全長を約7m程度としたベースビーム2の略中央部分を相互が直交状配置となるように熔着、一体化すると共に、同上端側で前記吊下部11形成箇所に重複しない箇所には、当該リーダー1の軸芯に交叉状配置であって、前記ベースビーム2に略平行状となる如くして、長さが約2m程度、巾300m程度とした2枚の厚板鋼板を両側から添設、熔着してトップビーム3とすることにより、側面形で概略縦長エの字状構造となるようにした装置骨格体を有している。
【0029】
この装置骨格体トップビーム3には、後述する電動オーガ昇降用ウインチ4および杭装着用ウインチ5夫々から導出される2本のワイヤー41,51を、夫々別々の巻き掛け経路となるようにしてトップビーム3の一端側から他端側に誘導するワイヤー誘導機構として、夫々対をなすシーブ31,32が両端近傍に配されている。
【0030】
一方、ベースビーム2は、両端側に反力アンカー装着部21,21が夫々一体形成されると共に、各反力アンカー装着部21,21よりも内側で、各反力アンカー装着部21,21の近傍にレベリングジャッキ22,22が併設されてなる構造とされ、また、各反力アンカー装着部21,21には、ベースビーム2を夫々上下方向に貫通して反力アンカー21a,21aを挿入し、適宜手段で地中に打設できるものに形成されると共に、何れか一方、この実施例ではリーダー1に対して杭ガイド部24形成側にある反力アンカー装着部21の更に外側に仮着部23が形成されてなるものとし、両反力アンカー装着部21,21に反力アンカー21a,21aを挿入、打設する代わりに、仮着部23を既設の杭に連結するようにして、一方の反力アンカー21aの挿入、打設工程を省略して作業の簡略化を図ると共に、より一層安定した状態で該ベースビーム2を地盤に連結し、実質的に装置骨格体全体が削孔箇所の地盤に支持され、削孔反力を打ち消すことができる構造のものとなるようにしており、また、レベリングジャッキ22,22の調節によってベースビーム2の水平化をして、実質的にリーダー1の鉛直性が確保できるようにしてある。
【0031】
更に、このベースビーム2には、先のトップビーム3にワイヤー誘導機構として組み込まれた一方のシーブ32の略真下に相当する部分に、上下に貫通状とした杭ガイド部24が設けられ、同他方のシーブ31の真下からやや端部側にずらした箇所には、電動オーガ昇降用ウインチ4と杭装着用ウインチ5とが配設されており、当該電動オーガ昇降用ウインチ4から両シーブ31,32を経由して導出したワイヤー41に電動オーガ装置部6を昇降自在に吊下すると共に、他方杭装着用ウインチ5から両シーブ31,32を経由して導出したワイヤー51先端に杭吊り込み金具52を取着してなるものとしてある。
【0032】
以上のようにして形成されたこの発明の代表的な構造からなる吊下移動式削孔装置は、例えば、山岳地帯を切り開いて造成した団地等が存在し、その造成地よりも低い位置を高速道路が開通し、高速道路路面よりも高い位置となる造成地際に防音壁を設置する必要がある場合のように、高低さがある箇所であって、構造物を設置する側が住宅地で大形建設機械の投入が適わず、低い側の高速道路路面側からしか接近できないような箇所を施工現場とする際に、高速道路側に移動式クレーンCを投入し、その吊り下げフックC2で、装置骨格体リーダー2上端の吊下部11を吊り上げた上、ブームC1を旋回、傾斜操作して道路法面上端の所望する造成地際に移動し、当該移動式クレーンCの作業圏内であって、移動式クレーンCからは離れた複数の削孔箇所を、該移動式クレーンCの移動、接近をすることなく順次削孔、杭埋込みをする工事等の杭埋込み方法に使用することになる。
【0033】
先ず、当該移動式クレーンCにより、吊り下げ状にして装置骨格体を所望する削孔、埋込み箇所まで移動し、ベースビーム2の杭ガイド部24中心を削孔箇所の杭埋込み中心に合致するようにしながら、降下、接地させ、レベリングジャッキ22,22を操作してベースビーム2の水平化を図ると共に、反力アンカー装着部21,21には夫々反力アンカー21a,21aを挿入、打設し、実質的にリーダー1の鉛直性が確保されるようにした上、予め削孔箇所の近くに用意しておいた先端開放中空鋼管杭8を、杭装着用ウインチ5から両シーブ31,32を経由して導出したワイヤー51先端の杭吊り込み金具52で吊り上げ、電動オーガ装置部6下端に排土アダプター9を介し、接続ロッドで連結してあるオーガースクリュー7を内装状となるようにすると共に、その下端をベースビーム2の杭ガイド部24に上方から挿入、設置させてから、杭吊り込み金具52を先端開放中空鋼管杭8から外してしまう。
【0034】
続いて、電動オーガ装置部6を作動、降下させていくことにより、オーガースクリュー7先端のオーガーヘッド71の回転、掘削によって先端開放中空鋼管杭8下端の地面を掘り下げ、先端開放中空鋼管杭8を所定深度に達するまで削孔作業を継続し、その過程で発生する削土は、オーガースクリュー7の螺旋翼で先端開放中空鋼管杭8を上昇させた上、排土アダプター9から地上部に排出、堆積状にしておき、先端開放中空鋼管杭8が所定深度にまで沈降した段階で、電動オーガ装置部6を停止させるか、逆転作動しながら、電動オーガ昇降用ウインチ4によって電動オーガ装置部6毎オーガースクリュー7だけを引き上げ、先端開放中空鋼管杭8だけを地中に残置したままとなし、その後、堆積してあった土砂や砕石を埋め戻し、填圧して先端開放中空鋼管杭8を所定箇所に埋込む工程を終えてから、今度は移動式クレーンCの作動により、装置骨格体全体を同地点から吊り上げて引き離し、移動式クレーンCのブームC1の作動圏内にある他の杭埋込み箇所にまで旋回、移動し、以降、同様に装置骨格体の据付け、削孔、杭埋設となる一連の杭埋込方法を順次繰り返すことにより、移動式クレーンC作業圏内であって、移動式クレーンCからは離れた複数の杭埋込箇所において、移動式クレーンCの移動、接近させる必要のない杭埋込方法を完了するものである。
【0035】
なお、この一連の杭埋込み過程において、同所における二本目以降の杭埋込方法では、反力アンカー装着部21,21の中の一方への反力アンカー21a,の挿入、打設工程を省略してしまい、作業の簡略化と共に、より一層の安定した地盤への連結を図るようにした工程を採用するようにすることができると共に、この実施例においては採用していないが、必要があれば、ベースビーム2を長さ調節可能な構造のものとしておき、削孔箇所の地盤状況や杭長等の要因に応じ、装置骨格体据付け工程前の段階に、最適な長さのベースビーム2わ実現した上、以降の工程が実施されるようにすることも可能である。
【0036】
【作用効果】
以上のような構成からなるこの発明の吊下移動式杭埋込装置、およびそれを使用した杭埋込方法は、吊下移動式杭埋込装置は極めて簡潔な構造のものとして製造可能であって、従前からの杭打ち専用大型建設機械に比較し、遥かに安価な機械装置とすることができ、しかも、移動式クレーンの用意ができさえすれば、当該移動式クレーンを所望する削孔箇所まで直接近付ける必要もなく、その作業圏内での杭埋込み作業を効率的にこなすことができるものになることから、特に従前からの大型建設機械の投入の難しい施工現場での杭埋込み作業を、非常に経済的且つ安全、迅速に実施可能ならしめるという極めて大きな特徴を発揮することができるものとなる。
【0037】
特に、実施例に取り上げたこの発明を代表する構造からなる吊下移動式杭埋込装置は、それらの特徴を如何なく発揮することができるものとして実現されており、したがって、それを使った杭埋込方法も期待どおりに円滑且つ確実に実施可能にするものとなっており、この種箇所における杭埋込作業に大いに役立つ、極めて実用的なものになるという秀れた作用効果が期待できるものとなっている。
【0038】
叙述の如く、この発明の吊下移動式杭埋込装置、およびそれを使用した杭埋込方法は、特徴ある新規な構成によって普く所期の目的を達成可能にするものであって、市街地化が進む一方で、高速交通網の整備、拡大が進み、居住空間と各種構造物の建設現場とが錯綜する機会が益々増加する中で、人々の生活に支障を来す騒音公害や危険性をもたらすことなく、所望する構造物の建設を可能にする秀れた技術として建設業界はもとよりのこと、関係各方面から高い評価がなされ、広く採用、普及していくものになることが予想される。
【図面の簡単な説明】
図面は、この発明を代表する一実施例を示したものである。
【図1】 この発明の代表的な構成を具備し、起立状に支持してなる吊下移動式削孔装置の全体側面図である。
【図2】 移動式クレーンによる吊り下げ態様を示した概略的に示した側面図である。
【図3】 この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の、図2に続く使用態様を概略的に示す側面図である。
【図4】 この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の、図3に続く使用態様を概略的に示す側面図である。
【図5】 この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の、図4に続く使用態様を概略的に示す側面図である。
【図6】 この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の、図5に続く使用態様を概略的に示す側面図である。
【図7】 この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の、図6に続く使用態様を概略的に示す側面図である。
【図8】 この発明の杭埋め込み方法を実施する過程における吊下移動式削孔装置の、図7に続く使用態様を概略的に示す側面図である。
【図9】 従前からの大型専用杭打ち機の概略を示す側面図である。
【符号の説明】
1 リーダー
11 同 吊下部
2 ベースビーム
21 同 反力アンカー装着部
21a 同 反力アンカー
22 同 レベリングジャッキ
23 同 仮着部
24 同 杭ガイド部
3 トップビーム
31 同 シーブ
32 同 シーブ
4 電動オーガ昇降用ウインチ
41 同 ワイヤー
5 杭装着用ウインチ
51 同 ワイヤー
52 同 吊込み金具
6 電動オーガ装置部
7 オーガースクリュー
71 同 オーガーヘッド
8 先端開放中空鋼管杭
9 排土アダプター
C 移動式クレーン
K クローラー杭埋込機
K1 同 ガイドポスト
K2 同 控えポスト
M オーガ
[0001]
OBJECT OF THE INVENTION
The present invention relates to pile embedding work for strengthening the foundation ground for structures. In particular, the ground target area for pile embedding is a large-scale construction machine such as a crawler pile embedding machine or a mobile crane. Pile embedding work at places where it is impossible to access, for example, narrow construction sites in town, places where there are heights and only accessible to either the high or low side, and places that are not accessible It is an object of the present invention to provide a suspended moving type pile embedding device having a novel structure that can be made possible and a novel pile embedding method using the same.
[0002]
[Prior art]
Various structures surrounding us, such as buildings, bridges, advertising towers, sound barriers, snow fences, etc., as well as their own weight, external loads applied to the structures, such as loads from various loads such as people, luggage, vehicles, etc. To a load caused by natural energy such as earthquakes and strong winds, and it must be designed to be safe and self-supporting. Even if it is stubbornly built, if the supporting strength of the foundation ground that supports it is not sufficiently secured, the structure of the rugged ridge can be damaged and collapsed very easily, and people can enjoy a peaceful daily life. Will be threatened.
[0003]
Therefore, according to the size, public nature, location conditions, etc. of various structures, a sufficient geological survey is conducted at the construction planning stage to grasp the ground condition, and ground reinforcement measures corresponding to it, such as the caisson method, The pile embedding method, etc. was studied, and after considering legal considerations such as pollution control, the optimum method was adopted and implemented, and after a solid ground reinforcement, a structure as designed was built on it. It will follow.
[0004]
One of the most commonly used methods for strengthening the ground has been the pile embedding method that mainly supports the structure by using the frictional resistance with the ground as a reaction force, depending on how the pile is driven. Many types of construction methods that have been classified have been developed and put to practical use. Typical examples of construction methods include pre-boring methods and digging methods in addition to traditional vibration methods and hammering methods. It has become known.
[0005]
In the case of the traditional vibration method or hammering method, the pile is strongly impacted directly using a vibro hammer or a diesel pile hammer, and the pile is strongly inserted into the ground, and its mechanism and structure are simple. In addition, the pile embedding method has been the mainstream for many years because it can carry out the pile embedding work as expected, but in recent years noise and vibration on the surrounding residents have become social problems and are far away from the urban area. Use outside of certain areas such as mountainous areas, coasts, and oceans is regulated by the Noise Prevention Ordinance, and after the establishment of this Noise Prevention Ordinance, pre-boring methods and medium The digging method has become the center of the pile embedding method, and improved and developed methods have been implemented for each company.
[0006]
For example, when looking at a typical pre-boring method, an auger that also serves as a milk injection part is attached to the leader of the crawler pile embedding machine K, and the drilling liquid is ejected from the tip side of the auger head through the milk injection part. The auger is driven to rotate to excavate the ground, and the excavated soil and drilling fluid along the spiral wings of the rotating auger are raised and discharged, and the sediment is discharged from the borehole to the ground surface. After the excavation, the auger is pulled out while injecting cement milk into the excavation hole through the milk injection part, and a predetermined pre-built pile is inserted and buried in the excavation hole. The crawler pile embedding machine K used in the construction method has a structure that supports the guide post K1 with a crane of a mobile crane vehicle, and is one of the construction methods that rely on extremely large construction machines. Ukoto can.
[0007]
In addition, the conventional digging method also supports the lower end of the leader directly on a large crawler, and uses a mobile three-point support machine that is fixed with two stand-off beams K2, and stands along with the leader. The hollow open end pile was pushed in by rotating the earth auger placed in the hollow part while leading the pile hole, and after the pile was pushed to a predetermined depth, the earth auger was pulled up and cement milk inside This is due to the construction of injecting and solidifying, and it is also due to the construction of a large construction machine like the pre-boring method described above, and at the position desired by the leader of this mobile direct-coupled three-point support machine. It is only possible to embed a pile of stakes, and it is also subject to the restriction that it does not work well.
[0008]
The pre-boring method and the digging method that have appeared instead of these traditional vibration methods and hammering methods can be excellent in that they can reliably carry out pile embedding without noise pollution. However, as mentioned above, because they are large construction machines, they are legally used in construction sites where various structures are forested in crowded urban areas, and highways where construction is performed by opening up hills. In construction sites where there are significant differences in height, such as when building various structures such as soundproof walls on the surface, it is impossible to introduce the necessary construction machines and the construction method with excellent corners is also substantial. It was a problem that could not be adopted.
[0009]
This invention has quickly started its development and research as one of those who have been involved in the construction industry for many years in order to deal with the above-mentioned problems of pre-boring method and digging method known as excellent methods. As a result of repeated trial and error and trial production, we finally came up with a new drilling method that enables embedding piles that could not be achieved by conventional methods, and a new configuration used for it. In the following, the configuration of the suspended mobile drilling device will be described in detail along with specific examples.
[0010]
[Structure of the invention]
The suspended mobile pile embedding device of the present invention basically has the following configuration.
That is, with respect to the base beam in which the leveling jack and the reaction force anchor mounting portion are integrally formed on both ends, a leader having a suspended portion formed on the upper end is erected and integrated from substantially the center in the length direction. In addition, a top beam formed by arranging a sheave capable of winding two wires in the vicinity of both ends in the vicinity of the upper end of the leader that does not overlap with the suspended portion forming portion crosses the leader axis. The device skeleton body is integrated so as to be in the shape of the arrangement, while the device frame base beam portion has a pile guide portion vertically penetrating in the vicinity of the leader attachment portion, and the pile guide portion. This is a suspended mobile pile embedding device in which an electric auger raising / lowering winch and a pile mounting winch are respectively disposed at locations away from the vehicle.
[0011]
If the suspension mobile pile embedding device of this basic configuration is based on a more specific configuration, the reaction force anchor mounting portion formed by closely arranging the leveling jack is integrally formed on both ends, At least one of the reaction force anchors on the outside of the base beam having a sufficient length and structural strength with a temporary attachment to the existing pile, from the center in the longitudinal direction, A leader having a predetermined length necessary for embedding and sufficient structural strength and having a suspended portion formed at the upper end is erected and integrated, and does not overlap with the suspended portion forming portion in the vicinity of the upper end of the leader. The top beam formed by arranging sheaves capable of winding two wires in the vicinity of both ends is arranged in a cross manner on the leader axis and is substantially parallel to the base beam. Integrated The base beam portion of the device skeleton top beam, which is substantially directly below one sheave, is provided with a pile guide portion that penetrates vertically, and directly below the other sheave. An electric auger lifting winch and a pile mounting winch are arranged on the base beam portion shifted slightly from the end side, and the wire led out from the electric auger lifting winch through both sheaves Suspension is based on a structure in which the electric auger device is suspended in a vertically movable manner and a pile hanging bracket is attached to the tip of the wire led out from the other pile mounting winch via both sheaves. It can be called a lower movable pile embedding device.
[0012]
Further, in the suspended mobile pile embedding device according to the present invention having the above-described basic structure, reaction force anchor mounting portions each having a leveling jack arranged close to each other are integrally formed at both ends, and at least any one of them. Necessary for embedding piles from the center in the longitudinal direction of a base beam with sufficient length and structural strength that is provided with a temporary attachment to an existing pile on the outside of one reaction force anchor mounting part In a place that has a predetermined length and sufficient structural strength and has a leader with a suspended portion formed at the upper end, integrated, and does not overlap with the suspended portion forming position in the vicinity of the upper end of the leader A top beam formed by arranging sheaves capable of winding two wires in the vicinity of both ends is arranged in a cross manner on the leader axis and integrated so as to be substantially parallel to the base beam. As On the other hand, the base beam portion of the device frame top beam, which is substantially directly below one sheave, is provided with a pile guide portion that penetrates vertically, from the bottom of the other sheave. An electric auger lifting winch and a pile mounting winch are arranged on the base beam part slightly shifted to the end side, and the wire led out from the electric auger lifting winch via both sheaves Suspension of the electric auger unit that can be moved up and down and suspended by attaching a pile hanging bracket to the tip of the wire led out from the other pile mounting winch via both sheaves A mobile pile embedding device is also included.
[0013]
The device skeleton is formed so that it can perform the function of enabling drilling and pile embedding while canceling the drilling reaction force in the pile embedding process itself, and suspended from the crawler crane boom. Locked by the lowered wire, the boom is tilted and freely suspended and moved to the desired pile embedding location within the swivel range, and the standing posture at each pile embedding location is It needs to be formed into something that would be maintained by keeping the wire taut.
[0014]
Therefore, the device skeleton body guides the electric auger for sharing the drilling holes and pile embedding functions, and also suspends the device itself and performs a spine function when moving, and the lower end of the leader The base beam that bears the drilling reaction force applied to the leader with the ground where the pile is embedded, and the electric auger up and down operation, as well as the pile lifting operation, are placed at the appropriate base beam location It is composed of a wire guiding mechanism that allows the wire from the winch to pass through the upper end of the leader, that is, a top beam for incorporation such as a sheave, both of which are formed from a steel material having sufficient strength, and the leader The top beam is located at the bottom of the base beam at the center of the base beam. And it made rigidly integral with people 熔着 like known means.
[0015]
As mentioned above, the base beam functions to transmit the drilling reaction force applied to the leader as a part of the device skeleton to the ground of the pile embedding location, and also to ensure the verticality of the leader. Therefore, it is of a fixed length, such as a length of about 7 to 8 meters if it is a sufficient length, for example, a leader of 10 meters in length, as in the examples described later. The base beam can be adjusted appropriately according to the length of the pile to be embedded, the condition of the ground, and other factors. Separated and formed into a secondary hook on the anchor mounting portion forming side, a main rod to which the leader and both reaction force anchor mounting portions are attached and formed, and a secondary rod on the temporary mounting portion forming side to the existing pile. The vice-basket is appropriately known With a structure that is connected to be stretchable by a step, for example, a secondary hook is inserted into the main pole, connected with a strong connecting structure such as an insertion structure, an attached plate attachment structure, an hiring anchor intermediation structure, It is also possible to fix the connecting positions by hydraulic means, bolting, or the like, both of which are included in the present invention.
[0016]
Then, reaction force anchor mounting portions each having leveling jacks arranged close to each other are integrally formed at both ends of the base beam, and preferably at least one of the reaction force anchor mounting portions is outside the reaction beam anchor mounting portion. When attaching a temporary attachment part to an existing pile and embedding the second and subsequent piles, instead of attaching a reaction force anchor to the reaction force anchor attachment part on the side of the temporary attachment part, the temporary attachment The part was attached to the existing pile, and a part of the drilling reaction force was to be borne by the existing pile, so that the work efficiency was improved and a safer reaction force load was realized. To do.
[0017]
Also, this base beam has a pile guide that is vertically penetrated at a location close to the leader lower end attachment portion and substantially below one sheave as a wire guiding mechanism incorporated in the top beam. It was necessary to provide a part and guide the penetrating part so that the pile to be embedded was correctly positioned at a predetermined location, and shifted slightly from the bottom of the other sheave to the end side. In the place, a winch for raising and lowering the electric auger and a winch for mounting the pile are arranged, and the wire from each winch passes through a pair of sheaves incorporated as a wire guiding mechanism in the top beam, respectively, and one is an electric auger. It is wound around a pulley incorporated at the upper end, and the other is provided with a hook for hanging a pile at its tip.
[0018]
It should be noted that the reader, base beam, top beam combination structure (mutual positional relationship etc. when integrating), reaction force anchor mounting portion incorporated in the base beam, temporary attachment portion, leveling jack, The arrangement of both winches should be in an optimum arrangement relationship in consideration of the balance when the suspension at the upper end of the leader is lifted by a crane.
[0019]
[Related invention]
The present invention relates to a suspended mobile pile embedding device having the configuration as described above, and the present invention includes the following basic configuration using the suspended mobile pile embedding device. Pile embedding methods are included.
That is, it has a predetermined length necessary for pile embedding and sufficient structural strength, and the lower end of the leader in which the top beam incorporating the suspended portion and the wire winding mechanism is integrally arranged on the upper end, The device skeleton, which is integrated with a base beam having a sufficient length and structural strength, is integrally lifted up and down by a mobile crane and moved up and down each time at a predetermined location. While maintaining the upright position, adjust the level of the base beam, attach reaction force anchors to both reaction force anchor mounting parts, and drive them in, so that the base beam is supported by the ground at the drilling location, and electric The auger screw connected to the auger device is made into an interior shape, and the open-ended hollow pile is suspended with a wire led out from the pile mounting winch. After the lower end side is inserted into the pile guide portion, the electric auger device portion is operated, and the drilling reaction force is drilled while canceling with the device skeleton itself to embed the open-ended hollow pile to a predetermined depth. After that, a series of work steps consisting of pulling up only the auger screw with the wire derived from the electric auger lifting winch, filling the hollow part of the open-ended hollow pile left in the ground at a predetermined location, and filling it with pressure Then, after finishing the pile embedding work at a predetermined location, the entire device skeleton is lifted with a mobile crane, and within the mobile crane work area, a plurality of pile embedding locations away from the mobile crane, This is a pile embedding method in which a series of work steps are sequentially repeated without moving and approaching the mobile crane.
[0020]
Furthermore, this invention has a predetermined length and sufficient structural strength required for pile embedding as a pile embedding method that is advantageous for embedding the second and subsequent piles close to each other, and has a suspended portion and a wire at the upper end. The bottom beam of the leader, which is integrated with the top beam with a winding mechanism, is integrated with the base beam with a sufficient length and structural strength. The equipment frame is suspended by a mobile crane, moved up and down, and is installed on either reaction force anchor mounting part side while adjusting the level of the base beam while holding it upright at each moving point. Attaching the reaction force anchor to the other reaction force anchor attachment part, driving in, and making the base beam supported by the ground at the drilling location, the electric auger device part With the connected auger screw as an interior, the open-ended hollow pile is suspended with a wire led out from the pile mounting winch, and the lower end side is inserted into the pile guide portion, and then the electric auger device is activated. After drilling the drilling hole while canceling with the device skeleton itself, the hollow pile with the open end is embedded to a predetermined depth, and then only the auger screw is pulled up with the wire led out from the electric auger lifting winch. After completing the pile embedding work in a predetermined place by a series of work processes that backfill and fill the hollow part of the open-ended hollow pile left in the ground of the place, continue the entire device skeleton body Is lifted by a mobile crane. Moving, without the approach, piles embedding method according to summary the configuration as repeated sequentially previous series of working steps are also included.
[0021]
The device skeleton body represents an electric auger device section that can be raised and lowered with a leader as a guide (that is, a known drilling device having a configuration capable of dealing with noise pollution, and will be developed in the future) Various types of drilling devices of the same type are included, and the same shall apply hereinafter), and drilling is performed by rotating the auger screw (including other drilling functions according to various other drilling devices. The same applies hereinafter). It has to be capable of drilling while canceling the auger screw drilling reaction force by itself, and it can be appropriately drilled and piled up by various known mobile cranes. It is suspended and moved up and down, and the standing state in the same place is supported by the tension of the hanging wire of the mobile crane. It is not such thing as load is applied to resist the force. In addition, within the operating range of the mobile crane, the movement of the device skeleton and the drilling are repeated without moving the mobile crane itself.
[0022]
Prior to drilling work, the level of the machine skeleton that is suspended and moved up and down by a mobile crane to the desired drilling spot must be adjusted at the drilling spot in order to realize the verticality of the leader. After that, as a process for making it possible to cancel the drilling reaction force on its own, the work is performed so that the leader that directly applies the drilling reaction force is stably connected to the ground at the drilling location. carry out.
[0023]
Therefore, the apparatus skeleton body has a structure in which a base beam having a sufficient length and structural strength is formed at the lower end of the leader and a reaction force anchor mounting portion is formed at each of both ends is firmly integrated. The reaction beam anchors are attached to the reaction beam anchor mounting portions of the base beam, and the reaction force anchors are firmly driven into the ground for integration (if necessary, the level is adjusted thereafter. Drilling work that can counteract the drilling reaction force of the leader indirectly through the base beam connected to the ground by these reaction force anchors. It is to make. At that time, for those using a base beam that can adjust the distance between the reaction force anchors, adjust the total length of the base beam according to the ground strength and depth of the drilling location. It can be very advantageous to ensure that cancellation is achieved.
[0024]
Following the first drilling operation at the desired location, for the second and subsequent drilling operations, as with the first drilling, the reaction force anchors were mounted on the reaction beam anchor mounting portions of the base beam, respectively. Of course, there is no problem even if the steps as described above are repeated so that the reaction anchor is firmly driven into the ground and integrated. However, at least one of the reaction force anchors on the side of the anchor is installed in advance. Appropriate temporary attachment means to the existing pile (that is, the pile embedded in the pile hole that has been drilled), for example, a sandwich structure with a belt-like metal fitting, a fitting with a ring-like metal fitting It is formed in a structure in which various known means such as a combined structure are taken, and at least one end side of the base beam is not a reaction force anchor but is connected to and supported by the existing pile by the temporary attachment means. It is the way the process so as to adopt may be those to be simplified spoofing by one upon each typing process the reaction force anchor two.
[0025]
Thus, when the device skeleton is held upright by the mobile crane and the level adjustment is completed, the auger screw is rotated by the operation of the electric auger device portion incorporated in advance in the device skeleton, The ground is drilled with an auger head, and the process proceeds to a pile embedding process in which a predetermined pile is gradually settled. The drilling reaction force applied from the auger head to the device frame through the auger screw and electric auger unit Can be canceled by the device skeleton itself supported by the ground, and a load is not applied to the mobile crane side in which the device skeleton is raised.
[0026]
The pile embedding process needs only to be carried out through a process similar to that of the conventional digging method, and it is sufficient to lift and lower the electric auger while leaving only the pile that has been embedded to the specified depth. Pull up the auger screw with the wire derived from the winch, backfill the earth and sand and crushed stone, proceed with filling as usual, and when the pile embedding at the predetermined place is completed, the entire device skeleton is lifted with a mobile crane Repeats the sequence of work steps up to that point in a mobile crane work area, without moving or approaching the mobile crane at multiple pile embedding locations away from the mobile crane. At the stage where multiple pile embedding work has been completed within the mobile crane work area, the work area where the next multiple pile embedding work is required for the first time In place of the one in which moving the mobile crane to the travelable place.
In the following, the suspension moving type drilling device of the present invention, which has been described in detail so far, and the configuration of the pile embedding method using the same will be described in a more specific manner. Specific examples will be taken and explained.
[0027]
[Example 1]
FIG. 1 is an overall side view of a suspended mobile drilling device having a typical configuration according to the present invention and supported in an upright shape, and FIG. 2 is a schematic view showing a suspended state by a mobile crane. 3 to 8 are side views schematically showing how the suspended mobile drilling device is used in the process of carrying out the pile embedding method of the present invention.
[0028]
As can be clearly seen from the overall side view of FIG. 1, the suspended mobile drilling device for this embodiment has a box-type thick hollow section with a total length of about 10.5 m and a side of 400 mm. Compared to the leader 1 made of steel and having a suspended portion 11 at the upper end, the lower end of the leader 1 is substantially the same section as the leader 1 and has a substantially central portion of the base beam 2 having a total length of about 7 m. Are welded and integrated so that they are in an orthogonal arrangement, and at the same upper end side, the portion that does not overlap with the portion where the hanging portion 11 is formed is an intersection arrangement on the axis of the leader 1, By attaching and welding two thick steel plates with a length of about 2 m and a width of about 300 m from both sides so as to be substantially parallel to the base beam 2, a top beam 3 is obtained. A device bone that is shaped like a roughly vertical letter-shaped structure. And it has a body.
[0029]
The apparatus skeleton top beam 3 is provided with two wires 41 and 51 led out from an electric auger lifting winch 4 and a pile mounting winch 5, which will be described later, respectively, so as to form separate winding paths. As a wire guiding mechanism for guiding the beam 3 from one end side to the other end side, a pair of sheaves 31 and 32 are arranged near both ends.
[0030]
On the other hand, the base beam 2 has reaction force anchor mounting portions 21 and 21 integrally formed at both end sides, and inside the reaction force anchor mounting portions 21 and 21, each of the reaction force anchor mounting portions 21 and 21. Leveling jacks 22 and 22 are provided adjacent to each other, and reaction force anchors 21a and 21a are inserted into the reaction force anchor mounting portions 21 and 21 through the base beam 2 in the vertical direction, respectively. It is formed so that it can be placed in the ground by appropriate means, and in either case, in this embodiment, it is temporarily attached to the outer side of the reaction force anchor mounting portion 21 on the pile guide portion 24 forming side with respect to the leader 1. It is assumed that the portion 23 is formed, and instead of inserting and driving the reaction force anchors 21a and 21a into both reaction force anchor mounting portions 21 and 21, the temporary attachment portion 23 is connected to an existing pile, The other side The insertion and placement process of the anchor 21a is omitted to simplify the work, and the base beam 2 is connected to the ground in a more stable state, so that the entire device skeleton is substantially grounded at the ground of the drilling location. The structure is such that it is supported and can counteract the drilling reaction force, and the base beam 2 is leveled by adjusting the leveling jacks 22 and 22, so that the verticality of the leader 1 is substantially improved. Can be secured.
[0031]
Further, the base beam 2 is provided with a pile guide portion 24 vertically penetrating in a portion substantially corresponding to a portion of one sheave 32 incorporated as a wire guiding mechanism in the top beam 3. An electric auger elevating winch 4 and a pile mounting winch 5 are disposed at a position slightly shifted from the position immediately below the other sheave 31 to the end side. The electric auger device section 6 is suspended from the wire 41 led out through the wire 32 so as to be movable up and down, and the pile hanging bracket is attached to the tip of the wire 51 led out from the other pile mounting winch 5 through the sheaves 31 and 32. 52 is attached.
[0032]
The suspended mobile drilling device having the typical structure of the present invention formed as described above has, for example, a housing complex formed by opening up a mountainous area, and a position lower than the constructed land is high-speed. As in the case where it is necessary to install a soundproof wall when the road is open and is higher than the expressway road surface, it is a place with a height and the side where the structure is installed is large in a residential area When the construction site is a site where the construction machine is not suitable and can only be accessed from the highway road surface on the lower side, the mobile crane C is inserted on the highway side, and its hanging hook C2 After lifting the suspension part 11 at the upper end of the apparatus skeleton body leader 2, the boom C1 is swiveled and tilted to move to the desired construction site at the upper end of the road slope, and within the working range of the mobile crane C, Away from mobile crane C The drilling point number, the movement of the mobile crane C, will be used to sequentially drilling, pile embedding method of construction, etc. of the pile buried without the approach.
[0033]
First, the mobile crane C is suspended to move the device skeleton to the desired drilling and embedding location, so that the center of the pile guide portion 24 of the base beam 2 coincides with the pile embedding center of the drilling location. At the same time, the base beam 2 is leveled by lowering and grounding and operating the leveling jacks 22 and 22, and the reaction force anchors 21a and 21a are inserted and driven in the reaction force anchor mounting portions 21 and 21, respectively. In addition, the verticality of the leader 1 is substantially secured, and the open-ended hollow steel pipe pile 8 prepared in the vicinity of the drilling hole is attached to the sheaves 31 and 32 from the pile mounting winch 5. An auger screw 7 that is lifted by a pile hanging metal fitting 52 at the tip of the wire 51 that is led out and connected to a lower end of the electric auger device 6 by a connecting rod via a soil removal adapter 9 So as thereby to insert the lower end from above into the pile guide unit 24 of the base beam 2, were allowed to set up, thus removing the bracket 52 hanging pile from the open ended hollow steel pipe pile 8.
[0034]
Subsequently, by operating and lowering the electric auger device section 6, the auger head 71 at the tip of the auger screw 7 is rotated and excavated to dig down the ground at the lower end of the open-ended hollow steel pipe pile 8, The drilling operation is continued until the predetermined depth is reached, and the soil generated in the process is discharged from the soil removal adapter 9 to the ground, after the open-ended hollow steel pipe pile 8 is lifted by the spiral blade of the auger screw 7 When the hollow steel pipe pile 8 with the open end is settled down to a predetermined depth, the electric auger device unit 6 is stopped or reversely operated while the electric auger device unit 6 is operated by the electric auger lifting / lowering winch 4. Pull up only the auger screw 7 and leave only the open-ended hollow steel pipe pile 8 in the ground, and then backfill and fill the sediment and crushed stone that have accumulated. After completing the process of embedding the hollow steel pipe pile 8 with the open end at the predetermined location, the mobile crane C is now lifted away from the same point by operating the mobile crane C, and the operating range of the boom C1 of the mobile crane C is within the operating range. Rotate and move to other pile embedding locations in the area, and then repeat a series of pile embedding methods that are similarly installed, drilling, and pile embedding in the mobile crane C work area. Thus, the pile embedding method that does not require the mobile crane C to move and approach at a plurality of pile embedding locations away from the mobile crane C is completed.
[0035]
In this series of pile embedding processes, in the second and subsequent pile embedding methods in the same place, the insertion of the reaction force anchor 21a in one of the reaction force anchor mounting portions 21, 21 and the placing step are omitted. In addition to simplification of work, it is possible to adopt a process that is intended to achieve a more stable connection to the ground, and it is not necessary in this embodiment, but it is necessary. For example, the base beam 2 should have a structure that can be adjusted in length, and the base beam 2 of the optimum length can be used at the stage prior to the equipment frame installation process, depending on factors such as the ground conditions at the drilling location and the pile length. In addition, it is possible to carry out the subsequent steps.
[0036]
[Function and effect]
The suspended mobile pile embedding device and the pile embedding method using the suspended mobile pile embedding device of the present invention configured as described above can be manufactured with an extremely simple structure. Compared to conventional large-scale construction machines dedicated to pile driving, if the machine can be made much cheaper and a mobile crane can be prepared, the desired drilling location of the mobile crane can be obtained. Pile embedding work within the work area can be done efficiently, so pile embedding work at construction sites where it is difficult to put in large construction machines from the past It is possible to exhibit an extremely great feature that it can be implemented economically, safely and quickly.
[0037]
In particular, the suspended mobile pile embedding device having a structure representative of the present invention taken up in the embodiments is realized as being able to demonstrate their features without any problems, and therefore a pile using the same. The embedding method can be carried out smoothly and reliably as expected, and it can be expected to have the excellent effect of becoming extremely practical, which is very useful for pile embedding work in this kind of place It has become.
[0038]
As described above, the suspended mobile pile embedding apparatus of the present invention and the pile embedding method using the same make it possible to achieve the intended purpose by a characteristic new structure, However, as the development and expansion of the high-speed transportation network progresses and the opportunities to mix the living space with the construction sites of various structures increase more and more, noise pollution and hazards that hinder people's lives As a superior technology that enables the construction of the desired structure without bringing about a high level of appreciation, it is expected that it will be widely adopted and popularized not only in the construction industry, but also in various fields. The
[Brief description of the drawings]
The drawings show one embodiment representative of the present invention.
FIG. 1 is an overall side view of a suspended mobile drilling device having a typical configuration according to the present invention and supported upright.
FIG. 2 is a side view schematically showing a hanging manner by a mobile crane.
FIG. 3 is a side view schematically showing a usage mode following the FIG. 2 of the suspended mobile drilling device in the process of implementing the pile embedding method of the present invention.
FIG. 4 is a side view schematically showing a usage mode following FIG. 3 of the suspended mobile drilling device in the process of carrying out the pile embedding method of the present invention.
FIG. 5 is a side view schematically showing a usage mode following the FIG. 4 of the suspended mobile drilling device in the process of carrying out the pile embedding method of the present invention.
FIG. 6 is a side view schematically showing a usage mode following FIG. 5 of the suspended mobile drilling device in the process of implementing the pile embedding method of the present invention.
FIG. 7 is a side view schematically showing a usage mode following the FIG. 6 of the suspended mobile drilling device in the process of carrying out the pile embedding method of the present invention.
FIG. 8 is a side view schematically showing a usage mode following the FIG. 7 of the suspended mobile drilling device in the process of implementing the pile embedding method of the present invention.
FIG. 9 is a side view showing an outline of a conventional large-sized pile driver.
[Explanation of symbols]
1 leader
11 Same hanging part
2 Base beam
21 Reaction force anchor mounting part
21a Same reaction force anchor
22 Same leveling jack
23 Same temporary wear
24 Same pile guide
3 Top beam
31 Same Sheave
32 Same Sheave
4 Electric auger lifting winch
41 Same wire
5 Pinch mounting winch
51 Same wire
52 Same hanging bracket
6 Electric auger unit
7 Auger screw
71 Same Auger Head
8 Hollow steel pipe pile with open end
9 Earth removal adapter
C Mobile crane
K crawler pile embedding machine
K1 Guide post
K2 same post
M Ogre

Claims (7)

レベリングジャッキを近接配置してなる反力アンカー装着部が両端夫々に一体形成されてなる十分な長さと構造強度とを有するベースビームに対し、その長さ方向略中央から、杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端に吊下部が形成されてなるリーダーを立設、一体化した上、該リーダーの上端近傍で前記吊下部形成箇所に重複しない箇所には、2本のワイヤーを巻き掛け可能とするシーブを両端近傍夫々に配してなるトップビームが、当該リーダー軸芯に交叉状配置であって、前記ベースビームに略平行状となる如く一体化されたものとして装置骨格体となす一方、該装置骨格体トップビームの、一方のシーブの略真下に相当するベースビーム部分には、上下に貫通状とした杭ガイド部が設けられ、同他方のシーブの真下からやや端部側にずらした箇所のベースビーム部分には、電動オーガ昇降用ウインチと杭装着用ウインチとが配設された上、当該電動オーガ昇降用ウインチから両シーブを経由して導出したワイヤーに電動オーガ装置部を昇降自在に吊下すると共に、他方杭装着用ウインチから両シーブを経由して導出したワイヤー先端に杭吊り込み金具を取着してなるものとしたことを特徴とする吊下移動式杭埋込装置。  Necessary for embedding piles from a substantially central position in the longitudinal direction of a base beam having a sufficient length and structural strength in which reaction force anchor mounting parts formed by placing leveling jacks in close proximity are integrally formed at both ends. A leader having a predetermined length and sufficient structural strength and having a suspended portion formed at the upper end is erected and integrated, and there are 2 in the vicinity of the upper end of the leader that does not overlap the suspended portion forming portion. A top beam in which sheaves capable of winding a wire are arranged in the vicinity of both ends are arranged so as to cross the leader axis and integrated so as to be substantially parallel to the base beam. The base beam portion of the device skeleton top beam, which is substantially directly below one of the sheaves, is provided with a pile guide portion that penetrates in the vertical direction. An electric auger lifting winch and a pile mounting winch are arranged at the base beam portion shifted slightly from the bottom to the end side, and are derived from the electric auger lifting winch via both sheaves. The electric auger device is suspended from the wire so that it can be raised and lowered, and a pile hanging bracket is attached to the tip of the wire led out from the other pile mounting winch via both sheaves. Suspended mobile pile embedding device. レベリングジャッキを近接配置してなる反力アンカー装着部が両端夫々に一体形成されると共に、少なくとも何れか一方の反力アンカー装着部の外側には、既設杭への仮着部を併設してなる十分な長さと構造強度とを有するベースビームに対し、その長さ方向略中央から、杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端に吊下部が形成されてなるリーダーを立設、一体化した上、該リーダーの上端近傍で前記吊下部形成箇所に重複しない箇所には、2本のワイヤーを巻き掛け可能とするシーブを両端近傍夫々に配してなるトップビームが、当該リーダー軸芯に交叉状配置であって、前記ベースビームに略平行状となる如く一体化されたものとして装置骨格体となす一方、該装置骨格体トップビームの、一方のシーブの略真下に相当するベースビーム部分には、上下に貫通状とした杭ガイド部が設けられ、同他方のシーブの真下からやや端部側にずらした箇所のベースビーム部分には、電動オーガ昇降用ウインチと杭装着用ウインチとが配設された上、当該電動オーガ昇降用ウインチから両シーブを経由して導出したワイヤーに電動オーガ装置部を昇降自在に吊下すると共に、他方杭装着用ウインチから両シーブを経由して導出したワイヤー先端に杭吊り込み金具を取着してなるものとしたことを特徴とする吊下移動式杭埋込装置。  A reaction force anchor mounting portion in which leveling jacks are arranged close to each other is integrally formed on both ends, and at least one of the reaction force anchor mounting portions is provided with a temporary attachment portion to an existing pile. A leader having a predetermined length required for pile embedding and a sufficient structural strength from the center in the longitudinal direction of the base beam having a sufficient length and structural strength, and having a suspended portion at the upper end. The top beam is formed by arranging sheaves capable of winding two wires in the vicinity of both ends near the upper end of the leader and not overlapping with the hanging part forming part. The device skeleton is integrated with the leader axis so as to be substantially parallel to the base beam, and the device skeleton top beam is substantially directly below one sheave. The corresponding base beam part is provided with a pile guide part that penetrates up and down, and the base beam part that is shifted slightly from the bottom of the other sheave to the end side has an electric auger lifting winch and pile. A mounting winch is provided, and the electric auger device is suspended from the electric auger lifting winch via the both sheaves so that the electric auger device can be lifted and lowered. A suspended mobile pile embedding device characterized in that a pile hanging metal fitting is attached to a wire tip led out via the wire. ベースビームが、両反力アンカー装着部を形成した両端部分とその間の主要部分とに分割、形成された上、双方を差込み構造、添設構造、添え板構造その他の適宜手段で連結可能なものに形成し、両反力アンカー装着部間の距離が適宜調節可能となるようにした、請求項1または2何れか記載の吊下移動式杭埋込装置。  The base beam is divided and formed into both end portions where both reaction force anchor mounting portions are formed and the main portion between them, and both can be connected by an appropriate structure such as an insertion structure, an attachment structure, an attachment structure, etc. The suspended mobile pile embedding device according to claim 1 or 2, wherein the distance between both reaction force anchor mounting portions can be appropriately adjusted. 少なくとも何れか一方の反力アンカー装着部と、その外側に形成される既設杭への仮着部とが分割、形成された上、双方を差込み構造、添設構造、添え板構造その他の適宜手段で連結可能なものに形成し、他方の反力アンカー装着部と既設杭への仮着部との距離が適宜調節可能となるようにした、請求項2記載の吊下移動式杭哩込装置。  At least one of the reaction force anchor mounting portion and the temporary attachment portion to the existing pile formed on the outside thereof is divided and formed, and both are inserted, the attachment structure, the attachment plate structure, and other appropriate means 3. The suspended mobile pile driving device according to claim 2, wherein the distance between the other reaction force anchor mounting portion and the temporary attachment portion to the existing pile can be adjusted as appropriate. . 杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端には吊下部およびワイヤー巻回機構の組み込まれたトップビームが一体に配されてなるリーダーの下端を、両端夫々に反力アンカー装着部が一体形成され、十分な長さと構造強度とを有するベースビームに一体化したものとしてなる装置骨格体を、移動式クレーンによって吊り下げて昇降移動させ、所定箇所においてそ
の都度起立状に保持したまま、当該ベースビームのレベル調整と共に、両反力アンカー装着部に夫々反力アンカーを装着、打ち込みをなし、ベースビームが削孔箇所の地盤に支持されるようした上、電動オーガ装置部に連結したオーガスクリューを内装状とするようにして先端開放中空杭を杭装着用ウインチから導出したワイヤーで吊り込むと共に、その下端側を杭ガイド部に挿通してから、該電動
オーガ装置部を作動し、削孔反力は装置骨格体自身で打ち消しながら削孔することによって先端開放中空杭を所定深度にまで埋込んだ後、電動オーガ昇降用ウインチから導出したワイヤーでオーガスクリューだけを引き上げ、所定箇所の地中に残置した先端開放中空杭の中空部に土砂等を埋め戻し、填圧するようにしてなる一連の作業工程により、所定箇所における杭埋込み作業を終えた後、引き続
き、装置骨格体全体を移動式クレーンで吊り上げ、移動式クレーン作業圏内であって、移動式クレーンからは離れた複数の杭埋込箇所において、移動式クレーンの移動、接近をすることなく、先の一連の作業工程を順次繰り返していくようにしたことを特徴とする、請求項1ないし4何れか記載の吊下移動式杭埋込装置を使用した杭埋込方法。
It has a predetermined length required for pile embedding and sufficient structural strength, and the upper end of the leader is integrated with a suspended beam and a top beam incorporating a wire winding mechanism. The device skeleton, which is integrated with a base beam with a sufficient length and structural strength, is integrated with a force anchor mounting part, and is suspended and moved up and down by a mobile crane. In addition to adjusting the level of the base beam, the reaction beam anchors are mounted on both reaction force anchor mounting parts, driven in, and the base beam is supported by the ground at the drilling location. The auger screw connected to the part is made into an interior shape, and the open-ended hollow pile is suspended with a wire derived from the pile mounting winch, and its lower end After inserting the hollow guide pile to a predetermined depth by operating the electric auger device part and then drilling while counteracting the drilling reaction force with the device skeleton itself, By pulling up only the auger screw with the wire led out from the electric auger lifting winch, backfilling the earth and sand etc. in the hollow part of the open-ended hollow pile left in the ground at a predetermined location, and by filling a series of work steps, After completing the pile embedding work at a predetermined location, the entire device skeleton body is subsequently lifted by a mobile crane, and the mobile crane work area is located within a plurality of pile embedding locations away from the mobile crane. The suspension transfer according to any one of claims 1 to 4, wherein the series of work steps are sequentially repeated without moving or approaching the crane. Pile embedding method using the Shikikui implant device.
杭埋込みに必要となる所定長さと十分な構造強度とを有し、上端には吊下部およびワイヤー巻回機構の組み込まれたトップビームが一体に配されてなるリーダーの下端を、両端夫々に反力アンカー装着部が一体形成され、十分な長さと構造強度とを有するベースビームに一体化したものとしてなる装置骨格体を、移動式クレーンによって吊り下げ、昇降移動させ、移動箇所においてそ
の都度起立状に保持したまま、当該ベースビームのレベル調整と共に、何れか一方の反力アンカー装着部側に既設の杭の仮着、他方の反力アンカー装着部に反力アンカーの装着、打ち込みをなし、ベースビームが削孔箇所の地盤に支持されるようした上、電動オーガ装置部に連結したオーガスクリューを内装状とするようにして先端開放中空杭を杭装着用ウインチから導出したワイヤーで吊り込むと共
に、その下端側を杭ガイド部に挿通してから、該電動オーガ装置部を作動させ、削孔反力は装置骨格体自身で打ち消しながら削孔することによって先端開放中空杭を所定深度にまで埋込んだ後、電動オーガ昇降用ウインチから導出したワイヤーでオーガスクリューだけを引き上げ、所定箇所の地中に残置した先端開放中空杭の中空部に土砂等を埋め戻し、填圧するようにしてなる一連の作業工程により、所定箇所における杭埋込み作業を終えた後、引き続き、装置骨格体全体を移動式クレーンで吊り上げ、移動式クレーン作業圏内であって、移動式クレーンからは離れた複数の杭埋込箇所において、移動式クレーンの移動、接近をすることなく、先の一連の作業工程を順次繰り返していくようにしたことを特徴とする、請求項1ないし4何れか記載の吊下移動式杭埋込装置を使用した杭埋込方法。
It has a predetermined length required for pile embedding and sufficient structural strength, and the upper end of the leader is integrated with a suspended beam and a top beam incorporating a wire winding mechanism. The device skeleton, which is integrated with a base beam with a sufficient length and structural strength, integrated with a force anchor mounting part, is suspended by a mobile crane, moved up and down, and raised at each moving point. While holding the base beam, adjust the level of the base beam, temporarily attach the existing pile to one of the reaction force anchor mounting parts, and attach and drive the reaction force anchor to the other reaction force anchor mounting part. The beam is supported by the ground at the drilling location, and the auger screw connected to the electric auger device is made into an interior, and the open-ended hollow pile is attached to the pile mounting window. Hang it with the wire led out from the hose and insert the lower end side into the pile guide part, then operate the electric auger device part, and drill the hole reaction while counteracting the drilling reaction force with the device skeleton itself After embedding the open hollow pile to a predetermined depth, pull up only the auger screw with the wire derived from the electric auger lifting winch, and backfill the hollow part of the open hollow pile left in the ground at the predetermined location. Then, after completing the pile embedding work in a predetermined place by a series of work steps to be filled, the entire device skeleton body is lifted with a mobile crane, within the mobile crane work area, from the mobile crane Now repeats the above series of work steps sequentially without moving or approaching the mobile crane at multiple remote pile embedding locations. DOO characterized, piles embedding method using the down-type pile implantable device hanging as set forth in any one of claims 1 to 4.
ベースビームの全長が可変となる構造に形成された装置骨格体を使用し、削孔箇所の地盤地耐力に合わせてベースビーム全長を調節することにより、最適な状態で削孔反力を装置骨格体自身で打ち消しながらの削孔が可能となるようにする、請求項5または6何れか記載の杭埋込方法。  By using an equipment skeleton that has a variable base beam length, and adjusting the overall length of the base beam according to the ground strength of the drilling location, the drilling reaction force is optimally applied to the equipment skeleton. The pile embedding method according to claim 5 or 6, wherein drilling is possible while canceling with the body itself.
JP2000107387A 2000-03-03 2000-03-03 Suspended mobile pile embedding device and pile embedding method using the same Expired - Lifetime JP3662470B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000107387A JP3662470B2 (en) 2000-03-03 2000-03-03 Suspended mobile pile embedding device and pile embedding method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000107387A JP3662470B2 (en) 2000-03-03 2000-03-03 Suspended mobile pile embedding device and pile embedding method using the same

Publications (2)

Publication Number Publication Date
JP2001248375A JP2001248375A (en) 2001-09-14
JP3662470B2 true JP3662470B2 (en) 2005-06-22

Family

ID=18620387

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000107387A Expired - Lifetime JP3662470B2 (en) 2000-03-03 2000-03-03 Suspended mobile pile embedding device and pile embedding method using the same

Country Status (1)

Country Link
JP (1) JP3662470B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4920352B2 (en) * 2006-09-04 2012-04-18 有限会社ジオ技研 Drilling rig
JP5426424B2 (en) * 2010-02-15 2014-02-26 大和ハウス工業株式会社 Method for placing ground reinforcing pile and rod for preceding excavation and casting apparatus used therefor
CN101963046B (en) * 2010-09-11 2015-03-18 张宝有 Top driving slippery insert type folding guide rail plate
CN107724957B (en) * 2017-10-21 2019-04-23 佛山市平石深基坑工程有限公司 A kind of centering type intelligence pile digger device people
JP7061526B2 (en) * 2018-07-02 2022-04-28 鹿島建設株式会社 Excavation method and excavation equipment
CN108746760A (en) * 2018-07-19 2018-11-06 上海建工七建集团有限公司 A kind of simple punching device and its construction method
CN109403953B (en) * 2018-11-16 2022-10-14 中铁三局集团有限公司 Device and method for quickly and accurately measuring perpendicularity of drilled pile body
CN113186923B (en) * 2021-04-09 2024-02-02 安徽恒坤地基基础工程有限公司 Pile hanging method
CN114734404B (en) * 2022-04-12 2023-06-30 交通运输部上海打捞局 Horizontal splitting method for end plate top beam and arc beam assembly of sunken ship integral salvaging equipment

Also Published As

Publication number Publication date
JP2001248375A (en) 2001-09-14

Similar Documents

Publication Publication Date Title
US5733068A (en) Metal foundation push-it and installation apparatus and method
JP3662470B2 (en) Suspended mobile pile embedding device and pile embedding method using the same
JP6865518B1 (en) Mountain retaining wall and its formation method
CN210288383U (en) Rotary drilling and piling integrated machine
JP6761556B1 (en) Mountain retaining wall formation method
CN206987509U (en) Supply line's electric pole plants lever apparatus
CN110258627A (en) Combined type anchor draws road shoulder retaining wall and its construction method
KR100474184B1 (en) Hitting machine to drive sheet pile deeply using auger
CN114991165A (en) Construction method for subway deep foundation pit adjacent to railway business line
CN111851510B (en) Earth rock foundation pit blasting excavation system and construction method applying same
JP2913630B2 (en) Pile driver
JP3451275B2 (en) Deep foundation excavator
CN211312225U (en) Pile-column integrated structure based on bridge transformed from existing road surface
JP2006083673A (en) Installation method for pile in vehicle traveling area and method of constructing artificial ground using the same
JP3910135B2 (en) Building construction method and beam member used therefor
JP5027752B2 (en) Construction method of underground floor pillar and underground floor pillar
CN114687356B (en) Construction method for deep foundation pit excavation of building
JP2858997B2 (en) Temporary support column used for reverse driving method
JP3681883B2 (en) Long-cut soil slope reduction method
JP7337343B2 (en) Strut construction device and strut construction method for protective fence
JP4112921B2 (en) Temporary gantry used for work between tracks
JP2540639Y2 (en) Utility pole installation tool
CN221194939U (en) Environment-friendly vertical shaft guide well impact well forming device
CN214940114U (en) Piling and hole guiding device for bridge erecting pile driver
CN212956547U (en) Foundation ditch support tower crane basis integral type structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041025

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041116

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050117

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050215

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050323

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3662470

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090401

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090401

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100401

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100401

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110401

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120401

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120401

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130401

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140401

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term