JP3455861B2 - Foundation structure and foundation construction method - Google Patents

Foundation structure and foundation construction method

Info

Publication number
JP3455861B2
JP3455861B2 JP04463095A JP4463095A JP3455861B2 JP 3455861 B2 JP3455861 B2 JP 3455861B2 JP 04463095 A JP04463095 A JP 04463095A JP 4463095 A JP4463095 A JP 4463095A JP 3455861 B2 JP3455861 B2 JP 3455861B2
Authority
JP
Japan
Prior art keywords
foundation
existing
building
caisson
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP04463095A
Other languages
Japanese (ja)
Other versions
JPH08239861A (en
Inventor
清 石井
毅芳 福武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP04463095A priority Critical patent/JP3455861B2/en
Publication of JPH08239861A publication Critical patent/JPH08239861A/en
Application granted granted Critical
Publication of JP3455861B2 publication Critical patent/JP3455861B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、既設建物を建て替える
とき等に用いて好適な基礎構造および基礎の構築方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation structure suitable for use in rebuilding an existing building and a foundation construction method.

【0002】[0002]

【従来の技術】ビル等の建物は、地盤中に形成された基
礎と、その上方に形成された上部構造とに概略区分され
る。このような建物の老朽化、あるいはその使用用途を
変更する場合などには、既設の建物を取り壊した後、要
求に対応した新設の建物を建てているが、その建て替え
に際しては、既設の建物を基礎まで取り壊して撤去した
後、ここに新設の建物の基礎および上部構造物を構築す
るのが一般的である。
2. Description of the Related Art A building such as a building is roughly divided into a foundation formed in the ground and a superstructure formed above the foundation. When such a building deteriorates or its usage is changed, the existing building is demolished, and then a new building is built to meet the requirements. After the foundation has been demolished and removed, it is common to build the foundation and superstructure of a new building here.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上述し
たような従来の基礎の構築方法には、以下のような問題
が存在する。まず、言うまでもなく、既設の建物、特に
基礎の解体撤去には、多大な時間とコストが必要であ
る。しかも、基礎は耐久性を重視して設計、施工されて
おり、その品質は長期にわたって安定している。このた
め、建物を建て替えるときに、まだ十分に機能を果たす
ことのできる基礎を取り壊してそこに新規の基礎を構築
することは、いわば「無駄」であり、工期の短縮化、コ
スト削減の妨げの要因となっていた。また、近年、既設
の建物を取り壊すときに発生するコンクリート殻(が
ら)等の廃棄物の量の低減が望まれている。この問題を
回避するために、例えば既設の基礎を地中にそのまま残
置したとしても、これは単にその処理を先延ばししたに
過ぎない。さらには、既設の基礎を取り壊す際には騒
音,振動が発生し、近隣環境へ悪影響を及ぼすことがあ
る。しかも既設の基礎を取り壊すことによって、周囲地
盤のゆるみ,沈下,あるいは変形を招くことがあり、こ
れらに対応するにも多大なコスト、工期を要するという
問題がある。本発明は、以上のような点を考慮してなさ
れたもので、コストの低減,工期の短縮化を図るととも
に、廃棄物発生量を低減させることのできる基礎構造お
よび基礎の構築方法を提供することを目的とする。
However, the above-mentioned conventional method of constructing the foundation has the following problems. First of all, it goes without saying that dismantling and removing existing buildings, especially foundations, requires a great deal of time and cost. Moreover, the foundation is designed and constructed with an emphasis on durability, and its quality is stable over a long period of time. For this reason, when rebuilding a building, it is a waste of time to demolish a foundation that can still fully function and build a new foundation there, which is a waste of time and impedes cost reduction. It was a factor. Further, in recent years, it has been desired to reduce the amount of waste such as concrete shells generated when an existing building is demolished. To avoid this problem, even if the existing foundation is left as it is in the ground, this merely postpones the processing. Furthermore, when the existing foundation is demolished, noise and vibration are generated, which may adversely affect the neighboring environment. In addition, the existing foundation may be loosened, which may cause loosening, subsidence, or deformation of the surrounding ground, which requires a great deal of cost and construction period. The present invention has been made in consideration of the above points, and provides a basic structure and a method of constructing a basic structure capable of reducing the cost, shortening the construction period, and reducing the amount of waste generated. The purpose is to

【0004】[0004]

【課題を解決するための手段】請求項1に係る発明は、
既設建物を建て替える際に適用する基礎の構造であっ
て、地盤中に構築されている既設基礎である第一の基礎
と、該第一の基礎の周囲に基礎杭またはケーソン基礎が
複数配置されて、前記第一の基礎をはさんで対向するこ
れら基礎杭またはケーソン基礎上に基礎梁が架設されて
なる第二の基礎とから構成されていることを特徴として
いる。
The invention according to claim 1 is
It is a basic structure applied when rebuilding an existing building.
And a plurality of foundation piles or caisson foundations are arranged around the first foundation, which is an existing foundation constructed in the ground, and are opposed to each other across the first foundation. It is characterized in that it is composed of a foundation pile or a caisson foundation and a second foundation constructed by laying foundation beams.

【0005】請求項2に係る発明は、請求項1記載の基
礎構造において、前記第一の基礎と前記第二の基礎の前
記基礎梁との間に、弾性部材が介装されていることを特
徴としている。
The invention according to claim 2 is the foundation structure according to claim 1, wherein an elastic member is interposed between the foundation beam of the first foundation and the foundation beam of the second foundation. It has a feature.

【0006】請求項3に係る発明は、既設建物を建て替
える際に適用する基礎の構築方法であって、地盤中に構
築されている既設の基礎である第一の基礎の周囲に、基
礎杭またはケーソン基礎を複数配設した後、前記第一の
基礎上に弾性部材を配するとともに、前記基礎杭または
ケーソン基礎上に基礎梁を架設することによって、前記
基礎梁と前記基礎杭またはケーソン基礎とからなる第二
の基礎を、前記第一の基礎を跨ぐように構築することを
特徴としている。
The invention according to claim 3 rebuilds an existing building.
It is a method of constructing the foundation that is applied when
After arranging a plurality of foundation piles or caisson foundations around the first foundation that is an existing foundation that has been built , an elastic member is arranged on the first foundation, and on the foundation piles or caisson foundation. A second foundation consisting of the foundation beam and the foundation pile or caisson foundation is constructed by straddling the foundation beam on the first foundation.

【0007】請求項4に係る発明は、請求項3記載の基
礎の構築方法において、前記基礎梁を架設するときに、
該基礎梁と前記第一の基礎のいずれか一方あるいは双方
の変位を変位計測手段で計測し、前記第一の基礎にかか
る荷重を調整することを特徴としている。
The invention according to claim 4 is the method for constructing a foundation according to claim 3, wherein when the foundation beam is installed,
Displacement of one or both of the foundation beam and the first foundation is measured by a displacement measuring means, and the load applied to the first foundation is adjusted.

【0008】[0008]

【作用】請求項1記載の発明では、既設建物を建て替え
る際に、その基礎を、第一の基礎と、該第一の基礎の周
囲に複数配置した基礎杭またはケーソン基礎上に基礎梁
を架設してなる第二の基礎とから構成した。これによ
り、このような基礎上に構築する新設建物の上部構造の
荷重を、第一の基礎と第二の基礎とに分担させて支持さ
せることができる。このとき、既設の基礎を第一の基礎
として利用することによって、新たに第二の基礎を構築
するのみで、新設する建物の基礎を構成することが可能
である。
In the invention according to claim 1, the existing building is rebuilt.
In this case, the foundation was composed of a first foundation and a second foundation formed by laying foundation beams on a plurality of foundation piles or caisson foundations arranged around the first foundation. Thereby, the load of the superstructure of the new building constructed on such a foundation can be shared and supported by the first foundation and the second foundation. At this time, by using the existing foundation as the first foundation, it is possible to construct the foundation of the new building only by newly constructing the second foundation.

【0009】請求項2記載の発明では、第一の基礎と第
二の基礎の基礎梁との間に弾性部材を介装する構成とし
た。これによって、第一の基礎と第二の基礎とを別体と
することができ、ダンパー等の付属装置を付加すれば、
地震時等に、第一の基礎から、第二の基礎およびその上
に構築された建物等の上部構造に振動が伝達されるのを
抑さえることができる。
According to the second aspect of the invention, the elastic member is interposed between the first foundation beam and the second foundation beam. With this, the first foundation and the second foundation can be separated, and if an additional device such as a damper is added,
It is possible to suppress the transmission of vibration from the first foundation to the second foundation and the superstructure such as a building constructed on the second foundation during an earthquake or the like.

【0010】請求項3記載の発明では、既設建物を建て
替える際に、既設基礎を第一の基礎として利用し、その
周囲に、基礎杭またはケーソン基礎を複数配設した後、
第一の基礎上に弾性部材を配し、基礎梁を基礎杭または
ケーソン基礎上に架設することによって、第二の基礎を
前記第一の基礎を跨ぐように構築する構成とした。これ
により、第一の基礎と第二の基礎とからなる基礎を構築
することができる。このとき、第一の基礎として、既設
の建物の基礎を用いることから、既設の基礎を取り壊さ
ずにこれをそのまま利用して、新設の建物の基礎の一部
とすることができるので、既設の基礎の取り壊し、及び
新設の基礎の構築の手間を省くことができる。
According to the invention of claim 3, an existing building is built.
When replacing, use the existing foundation as the first foundation,
After arranging multiple foundation piles or caisson foundations around ,
The elastic member is arranged on the first foundation, and the foundation beam is installed on the foundation pile or the caisson foundation, so that the second foundation is constructed so as to straddle the first foundation. As a result, it is possible to build a foundation consisting of the first foundation and the second foundation. At this time, as the first foundation, the existing
Since the foundation of the existing building is used, it can be used as it is without destroying the existing foundation and can be used as a part of the foundation of the new building. Therefore, the existing foundation is demolished and the new foundation is constructed. Can be saved.

【0011】請求項4記載の発明では、基礎梁を架設す
るときに、基礎梁と第一の基礎のいずれか一方あるいは
双方の変位を変位計測手段で計測し、第一の基礎にかか
る荷重を調整する構成とした。これによって、第一の基
礎と第二の基礎との間でバランスのとれた荷重配分とす
ることができる。
In the invention of claim 4, when the foundation beam is installed, the displacement of either or both of the foundation beam and the first foundation is measured by the displacement measuring means, and the load applied to the first foundation is measured. The configuration is adjusted. As a result, a balanced load distribution can be achieved between the first foundation and the second foundation.

【0012】[0012]

【実施例】以下、本発明を図面に示す一実施例を参照し
て説明する。ここでは、本発明に係る基礎構造および基
礎の構築方法を、既設の建物の建て替えに適用する場合
の実施例を用いて説明する。図1は、本発明に係る基礎
構造の一例を示すものである。この図において、符号1
は新設建物、2は新設建物1の上部構造、3は新設建物
1の基礎部を示すものである。新設建物1の基礎部3
は、この場所に以前設けられていた建物(図示なし;以
下「既設建物」と称する)の既設基礎(第一の基礎)4
と、新たに構築した新設基礎(第二の基礎)5とから構
成されている。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to an embodiment shown in the drawings. Here, a foundation structure and a foundation construction method according to the present invention will be described using an example in which the foundation structure and the foundation construction method are applied to rebuilding an existing building. FIG. 1 shows an example of a basic structure according to the present invention. In this figure, reference numeral 1
Is a new building, 2 is a superstructure of the new building 1, and 3 is a foundation of the new building 1. Foundation part 3 of new building 1
Is the existing foundation (first foundation) of the building (not shown; hereinafter referred to as "existing building") that was previously installed in this place. 4
And a newly constructed new foundation (second foundation) 5.

【0013】既設基礎4は、例えば鉄筋コンクリート造
からなる杭基礎であり、所定間隔で地盤G中に埋設され
た基礎杭6,6,…上に、水平面内に位置する基礎版7
が架設された構成からなっている。
The existing foundation 4 is, for example, a pile foundation made of a reinforced concrete structure, and the foundation plate 7 located in a horizontal plane on the foundation piles 6, 6, ...
It has a structure that is erected.

【0014】このような既設基礎4の外周側には、コン
クリート杭あるいは鋼管杭(基礎杭)8,8,…が所定
間隔毎に埋設されている。そして、既設基礎4を挟んで
位置する鋼管杭8,8上には、例えば鉄筋コンクリート
造の基礎梁9が、前記既設基礎4を跨ぐように架設され
ている。これら鋼管杭8,8,…と基礎梁9とから、断
面視略門型の前記新設基礎5が構成されている。
Concrete piles or steel pipe piles (foundation piles) 8, 8, ... Are buried on the outer peripheral side of the existing foundation 4 at predetermined intervals. Then, on the steel pipe piles 8 and 8 which are located across the existing foundation 4, for example, a reinforced concrete foundation beam 9 is installed so as to straddle the existing foundation 4. The steel pipe piles 8, 8, ... And the foundation beams 9 constitute the new foundation 5 having a substantially gate-shaped cross section.

【0015】新設基礎5の各基礎梁9と前記既設基礎4
の基礎版7との間には、例えばゴム製の弾性部材10,
10,…と、図示しないダンパー等の付属装置とが介装
されており、各弾性部材10は基礎杭6の鉛直上方に位
置するよう配置されている。
Each foundation beam 9 of the new foundation 5 and the existing foundation 4
Between the base plate 7 and the elastic plate 10 made of rubber,
, And an accessory device such as a damper (not shown) are interposed, and each elastic member 10 is arranged so as to be positioned vertically above the foundation pile 6.

【0016】上述したような既設基礎4と新設基礎5と
から構成された基礎部3では、上部構造2の荷重は、新
設基礎5だけでなく、その一部が、弾性部材10,1
0,…を介して既設基礎4によっても支持されるように
なっている。このとき、既設基礎4と新設基礎5との間
には弾性部材10,10,…およびダンパー等の付属装
置が介装されているので、地震時等には、これら弾性部
材10およびダンパー等の付属装置によって、振動が、
既設基礎4から新設基礎5および上部構造2に伝達され
るのを抑さえることができるようになっている。これに
よって、新設建物1の基礎部3は免振構造の一形態をな
している。
In the foundation portion 3 composed of the existing foundation 4 and the new foundation 5 as described above, the load of the superstructure 2 is not limited to the new foundation 5 but a part thereof is elastic members 10, 1.
It is also supported by the existing foundation 4 via 0, .... At this time, since the elastic members 10, 10, ... And accessory devices such as dampers are interposed between the existing foundation 4 and the new foundation 5, these elastic members 10 and dampers, etc. are installed in the event of an earthquake. With the attached device, vibration
It is possible to suppress transmission from the existing foundation 4 to the new foundation 5 and the superstructure 2. As a result, the foundation part 3 of the new building 1 forms one form of the vibration isolation structure.

【0017】次に、上記の基礎部3を備えた新設建物1
の構築方法について説明する。これにはまず、既設建物
(図示なし)の上部構造のみを解体・撤去し、既設基礎
4は地盤G中にそのまま残しておく。
Next, a new building 1 having the above-mentioned foundation 3
The construction method of is explained. For this purpose, first, only the upper structure of the existing building (not shown) is dismantled and removed, and the existing foundation 4 is left in the ground G as it is.

【0018】次いで、既設基礎4の外周側の所定位置
に、鋼管杭8,8,…を打ち込む。続いて、既設基礎4
の上面の所定位置に弾性部材10,10,…をセットす
る。この後、基礎梁9を、現場打ちあるいはプレキャス
トコンクリート造等によって、鋼管杭8,8上に架設す
る。
Next, the steel pipe piles 8, 8, ... Are driven into predetermined positions on the outer peripheral side of the existing foundation 4. Next, existing foundation 4
The elastic members 10, 10, ... Are set at predetermined positions on the upper surface of the. After this, the foundation beam 9 is erected on the steel pipe piles 8 and 8 by cast-in-place casting or precast concrete construction.

【0019】このとき、例えば水もり変位計等の変位計
測手段で、既設基礎4および基礎梁9の変位を計測する
ことによって、既設基礎4に配分される支持荷重、およ
び基礎梁9と既設基礎4との離間間隔を調整するように
なっている。
At this time, the displacements of the existing foundation 4 and the foundation beam 9 are measured by a displacement measuring means such as a water beam displacement gauge, so that the supporting load distributed to the existing foundation 4 and the foundation beam 9 and the foundation beam 9 are 4 is adjusted to be separated from each other.

【0020】この後、このようにして構築した基礎部3
上に、上部構造2を構築することによって、新設建物1
が完成する。
After this, the foundation part 3 constructed in this way
New building 1 by building superstructure 2 on top
Is completed.

【0021】上述した基礎部3の構築方法では、既設建
物(図示なし)の上部構造のみを解体撤去した後、既設
基礎4の周囲に鋼管杭8,8,…を配設するとともに、
既設基礎4上に弾性部材10,10,…をセットし、鋼
管杭8,8間に基礎梁9を架設する構成となっている。
これにより、既設建物(図示なし)の既設基礎4を取り
壊すことなくそのまま利用して、新設建物1の基礎部3
を構成することができる。したがって、従来に比較し
て、基礎部3を構築するための工期を大幅に短縮するこ
とができる。また、コスト面についても、基礎部3の施
工コストはもちろんのこと、コンクリート等の資材の使
用量を大幅に削減することができるので、資材コストも
削減することができる。さらには、既設基礎4を取り壊
すことにより生じる廃棄物を削減することができるの
で、その処理にかかる手間、コストも削減することがで
きる。これに加えて、既設基礎4を取り壊さないので、
当然のことながら、これを取り壊すときに発生する騒
音、振動、周囲地盤のゆるみ,沈下,変形等といった問
題も生じることがない。
In the construction method of the foundation part 3 described above, after dismantling and removing only the upper structure of the existing building (not shown), the steel pipe piles 8, 8, ... Are arranged around the existing foundation 4, and
The elastic members 10, 10, ... Are set on the existing foundation 4 and the foundation beam 9 is installed between the steel pipe piles 8, 8.
With this, the existing foundation 4 of the existing building (not shown) can be used as it is without being demolished, and the foundation part 3 of the new building 1 can be used.
Can be configured. Therefore, the construction period for constructing the base portion 3 can be significantly shortened as compared with the conventional case. Further, in terms of cost, not only the construction cost of the base portion 3 but also the amount of use of materials such as concrete can be significantly reduced, so that material costs can also be reduced. Furthermore, since the waste generated by demolishing the existing foundation 4 can be reduced, the labor and cost required for the treatment can be reduced. In addition to this, since the existing foundation 4 is not demolished,
As a matter of course, there is no problem such as noise, vibration, loosening, subsidence, deformation, etc. of the surrounding ground, which occurs when this is demolished.

【0022】また、上述した基礎部3の構築方法では、
基礎梁9を架設するときに、変位計測手段で、既設基礎
4および基礎梁9の変位を計測する構成とした。これに
よって、既設基礎4に配分される支持荷重を最適に調整
することができ、基礎梁9と既設基礎4との間でバラン
スのとれた荷重配分とすることができる。
Further, in the above-mentioned construction method of the base portion 3,
When the foundation beam 9 is installed, the displacement measuring means measures the displacement of the existing foundation 4 and the foundation beam 9. As a result, the supporting load distributed to the existing foundation 4 can be optimally adjusted, and the load distribution can be balanced between the foundation beam 9 and the existing foundation 4.

【0023】なお、上記実施例において、既設基礎4の
水平方向のスパンが大きい場合等には、図2に示すよう
な構成とすればよい。この図に示すように、既設建物
(図示なし)の既設基礎(第一の基礎)11を、複数の
既設基礎11a,11bに分割し、これらの中間部にも
鋼管杭8’を埋設して、基礎梁9’をこれら鋼管杭8,
8,8’上に架設することによって、新設基礎5’が構
築された構成となっている。このような構成からなる新
設建物1’の基礎部3’によっても、上記実施例と同様
の効果を奏することが可能である。
In the above embodiment, when the horizontal span of the existing foundation 4 is large, the structure shown in FIG. 2 may be used. As shown in this figure, an existing foundation (first foundation) 11 of an existing building (not shown) is divided into a plurality of existing foundations 11a and 11b, and a steel pipe pile 8'is buried in the middle portion between them. , The foundation beam 9'to these steel pipe piles 8,
The new foundation 5'is constructed by being erected on 8, 8 '. The same effect as that of the above-described embodiment can be obtained by the base portion 3 ′ of the new building 1 ′ having such a configuration.

【0024】また、基礎部3’の構成は、平面規模が大
きな新設建物1’を構築する場合に、複数の既設建物
(図示なし)の既設基礎11a,11bを利用する場合
にも同様に適用することができる。
Further, the structure of the foundation portion 3'is similarly applied to the case of using the existing foundations 11a and 11b of a plurality of existing buildings (not shown) when constructing the new building 1'having a large plane scale. can do.

【0025】また、上記実施例において、新設基礎5の
構造については、何ら限定するものではなく、鋼管杭8
を、コンクリート杭等の他の杭状基礎としてもよいし、
また、ケーソン基礎などとしてもよい。基礎梁9の構成
についても、鉄筋コンクリート造に限定するものではな
く、鉄骨フレームとその上面に敷設したスラブとからな
る構成など、他の構造としてもよい。
Further, in the above-mentioned embodiment, the structure of the new foundation 5 is not limited at all, and the steel pipe pile 8
May be other pile-shaped foundations such as concrete piles,
It may also be used as a caisson foundation. The structure of the foundation beam 9 is not limited to the reinforced concrete structure, and may be another structure such as a structure including a steel frame and a slab laid on the upper surface thereof.

【0026】さらには、ゴム製の弾性部材10を用いた
が、これを例えば各種バネ等としてもよいし、弾性部材
10に代えて、各種の免振装置やジャッキ装置等、他の
ものを新設基礎5と既設基礎4との間に介装させる構成
としてもよい。例えば、免振装置を介装させれば、新設
建物1の免振性能を大幅に向上させることが可能であ
る。また、ジャッキ装置を採用した場合には、例えば地
盤の不同沈下が生じた場合に、各箇所の沈下量に応じて
ジャッキ装置を伸長させることによって、新設基礎5の
荷重を既設基礎4に確実に伝達させることができ、新設
建物1を不同沈下に対応可能な構造とすることが可能で
ある。また、このジャッキ装置は、施工時に前記免振装
置や弾性部材10を設置するに際して用いることも可能
である。
Further, although the elastic member 10 made of rubber is used, it may be used as various springs, for example. Instead of the elastic member 10, various other vibration isolator, jack device, etc. are newly provided. It may be configured to be interposed between the foundation 5 and the existing foundation 4. For example, if a vibration isolator is provided, the vibration isolation performance of the new building 1 can be significantly improved. Further, when the jack device is adopted, for example, when uneven ground subsidence occurs, the jack device is extended in accordance with the subsidence amount at each location to ensure that the load of the new foundation 5 is applied to the existing foundation 4. Therefore, the new building 1 can have a structure that can cope with uneven settlement. The jack device can also be used when installing the vibration isolator or the elastic member 10 during construction.

【0027】また、新設基礎5と既設基礎4との間だけ
でなく、各鋼管杭8と基礎梁9との間にも弾性部材10
や免振装置を介装させる構成としてもよい。このような
構成とすれば、新設建物1の免振性能をさらに向上させ
ることができる。
The elastic member 10 is provided not only between the new foundation 5 and the existing foundation 4 but also between each steel pipe pile 8 and the foundation beam 9.
Alternatively, a vibration isolator may be interposed. With such a configuration, the vibration isolation performance of the new building 1 can be further improved.

【0028】これに加えて、既設基礎4,11の構造形
式についても、限定するものではなく、あらゆる形式の
基礎構造を用いることが可能である。
In addition to this, the structural types of the existing foundations 4 and 11 are not limited, and any type of basic structure can be used .

【0029】[0029]

【発明の効果】以上説明したように、請求項1に係る基
礎構造によれば、既設建物の建て替える際に、その基礎
を、既設の基礎を第一の基礎とし、該第一の基礎の周囲
に複数配置した基礎杭またはケーソン基礎上に基礎梁を
架設してなる第二の基礎とから構成した。これにより、
基礎上で支持する上部構造の荷重を、第一の基礎と第二
の基礎とで分担して支持させることができる。このと
き、第一の基礎として既設の基礎を利用してこれを基礎
の一部とするので、基礎を構築するためのコストの低
減、工期の短縮、廃棄物の削減といった効果を奏するこ
とが可能である。
As described above, according to the foundation structure of claim 1, when the existing building is rebuilt, the foundation is rebuilt.
Of the existing foundation was used as the first foundation, and a plurality of foundation piles or caisson foundations arranged around the first foundation and a second foundation formed by erection of foundation beams. This allows
The load of the superstructure supported on the foundation can be shared and supported by the first foundation and the second foundation. At this time, use the existing foundation as the first foundation
Therefore, it is possible to achieve the effects of reducing the cost for constructing the foundation, shortening the construction period, and reducing the waste.

【0030】請求項2に係る基礎構造によれば、第一の
基礎と第二の基礎の基礎梁との間に弾性部材を介装する
構成とした。これによって、第一の基礎と第二の基礎と
を別体とすることができ、地震時等に、第一の基礎か
ら、第二の基礎およびその上に構築された建物等の上部
構造に振動が伝達されるのを抑さえることができ、基礎
状に構築した建物等の免振性能を高めることが可能とな
る。
According to the second aspect of the basic structure, the elastic member is interposed between the first foundation beam and the second foundation beam. As a result, the first foundation and the second foundation can be separated, and at the time of an earthquake, etc., the first foundation can be changed to the second foundation and the superstructure such as a building constructed on it. It is possible to suppress the transmission of vibration, and it is possible to enhance the vibration isolation performance of a building or the like constructed in the basic state.

【0031】請求項3に係る基礎の構築方法によれば、
既設建物を建て替える際に、既設基礎を第一の基礎とし
て利用し、その周囲に、基礎杭またはケーソン基礎を複
数配設した後、第一の基礎上に弾性部材を配し、基礎梁
を基礎杭またはケーソン基礎上に架設することによっ
て、第二の基礎を前記第一の基礎を跨ぐように構築する
構成とした。これにより、第一の基礎と第二の基礎とか
らなる、建物等の基礎を構築することができる。このと
き、第一の基礎として既設建物の基礎を用いることか
ら、既設の建物の基礎を取り壊さずにそのまま利用し
て、これを新設の建物の基礎の一部とすることができ
る。したがって、基礎を構築するための工期およびコス
トを大幅に削減することができる。さらには、既設基礎
を取り壊すときに生じる廃棄物を削減するとともに、そ
の処理にかかる手間、コストも削減することができる。
これに加えて、既設基礎を取り壊すときに発生する騒
音、振動、周囲地盤のゆるみ,沈下,変形等も抑さえる
ことができる。
According to the method for constructing a foundation according to claim 3,
When rebuilding an existing building, make the existing foundation the first foundation
After arranging a plurality of foundation piles or caisson foundations around it , elastic members are arranged on the first foundation and the foundation beams are erected on the foundation piles or caisson foundations. The foundation was constructed so as to straddle the first foundation. As a result, it is possible to construct a foundation such as a building that is composed of the first foundation and the second foundation. At this time, whether to use the foundation of the existing building as the first foundation
Et al., Was used as it is without demolished the foundations of the existing building, which can be a part of the foundation of the new building. Therefore, the construction period and cost for constructing the foundation can be significantly reduced. Further, it is possible to reduce the waste generated when the existing foundation is demolished, and also reduce the labor and cost required for the treatment.
In addition to this, it is possible to suppress noise, vibration, loosening, subsidence, deformation, etc. of the surrounding ground that occur when the existing foundation is demolished.

【0032】請求項4に係る基礎の構築方法によれば、
基礎梁を架設するときに、基礎梁と第一の基礎のいずれ
か一方あるいは双方の変位を変位計測手段で計測し、第
一の基礎にかかる荷重を調整する構成とした。これによ
って、第一の基礎と第二の基礎との間でバランスのとれ
た荷重配分とすることができる。
According to the method for constructing a foundation according to claim 4,
When the foundation beam is installed, the displacement of either or both of the foundation beam and the first foundation is measured by the displacement measuring means, and the load applied to the first foundation is adjusted. As a result, a balanced load distribution can be achieved between the first foundation and the second foundation.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る基礎構造および基礎の構築方法を
適用して構築した建物の一例を示す立断面図である。
FIG. 1 is a vertical sectional view showing an example of a building constructed by applying a foundation structure and a foundation construction method according to the present invention.

【図2】本発明に係る基礎構造および基礎の構築方法を
適用して構築した建物の他の一例を示す立断面図であ
る。
FIG. 2 is a vertical sectional view showing another example of a building constructed by applying the foundation structure and the foundation construction method according to the present invention.

【符号の説明】[Explanation of symbols]

3 基礎部(基礎) 4,11 既設基礎(第一の基礎) 5,5’ 新設基礎(第二の基礎) 8,8’ 鋼管杭(基礎杭) 9 基礎梁 10 弾性部材 3 Basic Department (Basic) 4,11 Existing foundation (first foundation) 5,5 'New foundation (second foundation) 8,8 'steel pipe pile (foundation pile) 9 foundation beams 10 Elastic member

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 35/00 ─────────────────────────────────────────────────── ─── Continuation of the front page (58) Fields surveyed (Int.Cl. 7 , DB name) E02D 35/00

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 既設建物を建て替える際に適用する基礎
の構造であって、地盤中に構築されている既設基礎であ
第一の基礎と、該第一の基礎の周囲に基礎杭またはケ
ーソン基礎が複数配置されて、前記第一の基礎をはさん
で対向するこれら基礎杭またはケーソン基礎上に基礎梁
が架設されてなる第二の基礎とから構成されていること
を特徴とする基礎構造。
[Claim 1] Foundation applied when rebuilding an existing building
The existing foundation that is constructed in the ground.
That the first basic, around the said first underlying foundation pile or caisson foundation with a plurality disposed, foundation beams are bridged on these foundation pile or caisson foundation facing across said first basic A basic structure characterized in that it is composed of a second foundation consisting of
【請求項2】 請求項1記載の基礎構造において、前記
第一の基礎と前記第二の基礎の前記基礎梁との間に、弾
性部材が介装されていることを特徴とする基礎構造。
2. The foundation structure according to claim 1, wherein an elastic member is interposed between the foundation beam of the first foundation and the foundation beam of the second foundation.
【請求項3】 既設建物を建て替える際に適用する基礎
の構築方法であって、地盤中に構築されている既設基礎
である第一の基礎の周囲に、基礎杭またはケーソン基礎
を複数配設した後、前記第一の基礎上に弾性部材を配す
るとともに、前記基礎杭またはケーソン基礎上に基礎梁
を架設することによって、前記基礎梁と前記基礎杭また
はケーソン基礎とからなる第二の基礎を、前記第一の基
礎を跨ぐように構築することを特徴とする基礎の構築方
法。
[Claim 3] Foundation to be applied when rebuilding an existing building
The existing foundation that is constructed in the ground
After arranging a plurality of foundation piles or caisson foundations around the first foundation that is , laying elastic members on the first foundations and erection foundation beams on the foundation piles or caisson foundations. The method for constructing a foundation is characterized by constructing a second foundation consisting of the foundation beam and the foundation pile or caisson foundation so as to straddle the first foundation.
【請求項4】 請求項3記載の基礎の構築方法におい
て、前記基礎梁を架設するときに、該基礎梁と前記第一
の基礎のいずれか一方あるいは双方の変位を変位計測手
段で計測し、前記第一の基礎にかかる荷重を調整するこ
とを特徴とする基礎の構築方法。
4. The method of constructing a foundation according to claim 3, wherein when the foundation beam is erected, displacement of one or both of the foundation beam and the first foundation is measured by a displacement measuring means, A method for constructing a foundation, comprising adjusting a load applied to the first foundation.
JP04463095A 1995-03-03 1995-03-03 Foundation structure and foundation construction method Expired - Fee Related JP3455861B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04463095A JP3455861B2 (en) 1995-03-03 1995-03-03 Foundation structure and foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04463095A JP3455861B2 (en) 1995-03-03 1995-03-03 Foundation structure and foundation construction method

Publications (2)

Publication Number Publication Date
JPH08239861A JPH08239861A (en) 1996-09-17
JP3455861B2 true JP3455861B2 (en) 2003-10-14

Family

ID=12696749

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04463095A Expired - Fee Related JP3455861B2 (en) 1995-03-03 1995-03-03 Foundation structure and foundation construction method

Country Status (1)

Country Link
JP (1) JP3455861B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435346A (en) * 2017-08-18 2017-12-05 北京恒祥宏业基础加固技术有限公司 A kind of grouting and reinforcing method for correcting error suitable for high building structure

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3950287B2 (en) * 2000-08-01 2007-07-25 株式会社竹中工務店 Construction method that reuses existing piles at the time of rebuilding and building structure that reuses existing piles
CN100371536C (en) * 2005-05-30 2008-02-27 南京工业大学 Construction process for composite pile of foundation and pile tip displacement regulating device
CN100363564C (en) * 2005-05-30 2008-01-23 南京工业大学 Pile tip displacement regulating device
JP5577677B2 (en) * 2009-11-13 2014-08-27 株式会社大林組 Seismic isolation structure
CN103741729A (en) * 2013-12-27 2014-04-23 陕西大唐新能电力设计有限公司 Foundation beam underpass cable duct processing method
CN108532655B (en) * 2017-01-21 2019-11-29 叶长青 The deviation rectification construction method of brick-concrete building

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107435346A (en) * 2017-08-18 2017-12-05 北京恒祥宏业基础加固技术有限公司 A kind of grouting and reinforcing method for correcting error suitable for high building structure
CN107435346B (en) * 2017-08-18 2020-02-14 北京恒祥宏业基础加固技术有限公司 Grouting reinforcement deviation rectifying method suitable for high-rise building structure

Also Published As

Publication number Publication date
JPH08239861A (en) 1996-09-17

Similar Documents

Publication Publication Date Title
JP3455861B2 (en) Foundation structure and foundation construction method
JP2004162362A (en) Aseismatic reinforcing structure for pile foundation structure
JPH093921A (en) Base-isolated foundation and replacing method for base-isolation device
JP3692805B2 (en) Seismic isolation method for existing buildings
JP2000265574A (en) High floor type steel frame footing beam method
JP2797045B2 (en) Solid foundation method with stabilizer
JP3760304B2 (en) Building foundation construction method
JP3240438B2 (en) Seismic isolation method for seismically isolated buildings and existing buildings
JP4465571B2 (en) Seismic isolation system for existing buildings
JPH09317208A (en) Base isolation construction method for existing wooden house
JP3178390B2 (en) Building seismic isolation foundation
JP3407168B2 (en) Foundation of new building using existing pile foundation
JP3756158B2 (en) Seismic isolation structure
JP6886811B2 (en) Foundation structure and method of constructing foundation structure
JP3109038B2 (en) Underground skeleton structure and construction method
JP2800688B2 (en) Foundation method of building consisting of high-rise building and low-rise building
JPH11350746A (en) Underground structure of building
JPH09170338A (en) Base isolation method for existing building
JPH11172757A (en) Building structure
JP2000027291A (en) Structure of steel framed building
JP7129290B2 (en) Building floor structure for rebuilding
JPH10317486A (en) Bearing structure of floor slab in building structure utilizing pile for column
JPS6043529A (en) Mat foundation and its construction
JPH07279184A (en) Floating underground beam foundation for building
JPS6360327A (en) Earthquake-proof device for housing

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20030603

LAPS Cancellation because of no payment of annual fees