JP3359588B2 - Repair method of existing lining - Google Patents

Repair method of existing lining

Info

Publication number
JP3359588B2
JP3359588B2 JP07907499A JP7907499A JP3359588B2 JP 3359588 B2 JP3359588 B2 JP 3359588B2 JP 07907499 A JP07907499 A JP 07907499A JP 7907499 A JP7907499 A JP 7907499A JP 3359588 B2 JP3359588 B2 JP 3359588B2
Authority
JP
Japan
Prior art keywords
injection
anchor material
pipe
anchor
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP07907499A
Other languages
Japanese (ja)
Other versions
JP2000273862A (en
Inventor
和田  弘
Original Assignee
ライト工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ライト工業株式会社 filed Critical ライト工業株式会社
Priority to JP07907499A priority Critical patent/JP3359588B2/en
Publication of JP2000273862A publication Critical patent/JP2000273862A/en
Application granted granted Critical
Publication of JP3359588B2 publication Critical patent/JP3359588B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、法面、土留め、ト
ンネル、水止め等の補修工法に関する。更に詳しくは、
地山がコンクリート、モルタル等で覆われた既設覆工物
の面を破壊することなく補修する工法に関する。例え
ば、地山の崩壊、法面の風化防止等のためにモルタルま
たはコンクリート(以下、モルタル類という。)による
吹付け工が行われているが、この吹付け工の後の空洞
化、風化、脱落等の生じたコンクリート、モルタル面等
の補修工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for repairing slopes, earth retaining walls, tunnels, water stops, and the like. More specifically,
The present invention relates to a method for repairing the existing lining without covering the ground with concrete, mortar, etc. without destroying the surface. For example, spraying with mortar or concrete (hereinafter referred to as mortar) is performed to prevent collapse of the ground, weathering of a slope, and the like. It relates to a method of repairing concrete, mortar surfaces, etc. that have fallen off.

【0002】[0002]

【従来の技術】地盤を切取りまたは盛土によってできた
人工的な土の傾斜面、すなわち法面が風雨などによって
崩壊することを防ぐために、草木を植えたり、モルタル
を吹き付けたりすることを法面保護工と呼んでいる。こ
の法面保護工の一つのモルタル類による吹き付け工は、
安価で簡便な工法のために広範に施工されている。
2. Description of the Related Art In order to prevent the slope of artificial soil formed by cutting or embankment of the ground, that is, the slope from being collapsed by wind and rain, it is necessary to protect the slope by planting plants or spraying mortar. Called mechanic. One of the slope protection works, mortar spraying,
It is widely used for cheap and simple construction.

【0003】近年このモルタルまたはコンクリート吹付
け工の後の既設法面が、風化し、また地山の土砂の流出
等でひび割れ、崩壊を生じている。このため地山と、吹
付コンクリートの裏面との間に空洞を生じる場合があ
る。このため、モルタルまたはコンクリートを全面的に
又は一部を剥ぎ取り、再度吹付け工等法面保護工を行い
法面の補修を施している。
In recent years, the existing slope after the mortar or concrete spraying work has been weathered, and has been cracked or collapsed due to outflow of earth and sand from the ground. For this reason, a cavity may be formed between the ground and the back surface of the shotcrete. For this reason, mortar or concrete is entirely or partially stripped off, and slope protection is performed again by spraying to repair the slope.

【0004】しかし、かかる従来の工法は、既設覆工物
の補修においては、風化したモルタルまたはコンクリー
トを剥ぎ取る工事がともなうため、落下物を生じのり面
下にある道路を遮断したり、足場を構築するなど大掛り
となる問題がある。
However, in such a conventional method, when repairing an existing lining, work for stripping weathered mortar or concrete is involved, so that falling objects are generated and roads under the slope are cut off or scaffolds are cut off. There are problems such as building.

【0005】本出願人は、かかる問題点を解決すべく、
先の特公平5−22775号において、覆工物を破壊す
ることなく覆工物と背面地山との間の空洞等を計測し、
次いで削孔ドリルにより既設覆工物を貫通して地山内ま
でアンカー孔を削孔した後に、削孔ドリルを引き抜き、
続いてこのアンカー孔にアンカー材を挿入し、このアン
カー材内を通じて、覆工物と背面地山との間の空洞等に
硬化材を充填する方法を提案した。
[0005] In order to solve such a problem, the present applicant has
In Japanese Patent Publication No. 5-22775, the cavity between the lining and the back ground was measured without destroying the lining,
Next, after drilling the anchor hole through the existing lining by drilling the hole to the ground, pull out the drill,
Subsequently, a method was proposed in which an anchor material was inserted into the anchor hole, and a hardening material was filled into the cavity between the lining and the back ground through the anchor material.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、この従
来工法では、削孔ドリルにより既設覆工物を貫通して地
山内までアンカー孔を削孔した後に、削孔ドリルを引き
抜き、続いてこのアンカー孔にアンカー材を挿入してい
たため、削孔とアンカー材挿入とが二度手間となってい
た。
However, in this conventional method, after drilling an anchor hole to the ground by penetrating an existing lining with a drill hole, the drill hole is pulled out, and then the anchor hole is removed. Since the anchor material was inserted into the hole, drilling and inserting the anchor material were bothersome.

【0007】また一般に、既設覆工物の背面地山は雨水
の浸透等により風化し脆弱化していることが多いため、
せっかくアンカー孔を開けてもアンカー挿入時にはそれ
が崩壊しており、アンカー材を円滑に挿入できないこと
がある。その際には、再度アンカー孔を削孔しなおし、
しかる後にアンカー材を挿入するほかなく、手間数が倍
になる。
[0007] Generally, the ground behind the existing lining is often weathered and weakened due to rainwater penetration or the like.
Even when the anchor hole is opened, it may be broken when the anchor is inserted, and the anchor material may not be inserted smoothly. In that case, drill the anchor hole again,
After a while, there is no choice but to insert the anchor material, and the number of labors is doubled.

【0008】そこで、本発明の主たる課題は、既設覆工
物の補修に関し、作業手間数を減らすとともに、アンカ
ー材の挿入を容易かつ円滑に行うことができるように
し、もって作業能率の向上を図ることにある。
Accordingly, a main object of the present invention is to repair an existing lining, reduce the number of working steps, and make it possible to easily and smoothly insert an anchor material, thereby improving the working efficiency. It is in.

【0009】[0009]

【課題を解決するための手段】上記課題を解決した本発
明の第1の発明は、地山を覆う既設覆工物の補修工法に
おいて、先端ビットを備えるとともに、少なくとも先端
側部分および頭部を除く基端側部分に吐出口をそれぞれ
有する管状アンカー材を用い、前記管状アンカー材内の
流路にエア供給用内管を挿入し、かつこのエア供給用内
管を前記先端側部分の吐出口にのみ連通させた状態とし
て、削孔エアを、このエア供給用内管を通して前記先端
部の吐出口のみから吹出させて、前記既設覆工物を貫通
しその背面の地山内まで削孔し、この削孔によってアン
カー材をその頭部を残して前記地山内まで挿入する、管
状アンカー材の自削孔挿入工程と、この削孔挿入した管
状アンカー材を引き抜かずに、硬化材を、その管状アン
カー材内および前記先端側部分の吐出口を通して吐出さ
せて、吐出硬化材を管状アンカー材外面と前記削孔によ
り形成されたアンカー孔内面との隙間における少なくと
も先端側部分に対して注入する、第1の注入工程と、こ
の注入硬化材の硬化により、管状アンカー材の少なくと
も先端側部分を地山に対して定着するとともに、管状ア
ンカー材の頭部を前記既設覆工物表面に対して定着させ
る、管状アンカー材の定着工程と、しかる後に、前記既
設覆工物表面を新たに覆工する、新規覆工工程と、しか
る後に、硬化材を、前記定着されている管状アンカー材
内および前記基端側部分の吐出口を通して、少なくとも
前記既設覆工物背面と地山表面との間の空洞部に対して
注入する、第2の注入工程と、を含むことを特徴とする
既設覆工物の補修工法である。
According to a first aspect of the present invention, there is provided a method of repairing an existing lining covering a ground, comprising a tip bit, and at least a tip portion and a head. Using a tubular anchor material having a discharge port at a base end portion except for the air supply inner pipe inserted into a flow path in the tubular anchor material, and connecting the air supply inner pipe to the discharge port at the distal end portion In a state of being communicated only with the hole, the drilling air is blown out only from the discharge port at the distal end portion through the air supply inner pipe, and penetrates the existing lining to drill into the ground on the back surface thereof, Inserting the anchor material into the ground while leaving the head part by the drilling, the self-cutting hole insertion step of the tubular anchor material, and without pulling out the drilled and inserted tubular anchor material, the hardened material is removed from the tubular material. In and before anchor material A first injection step of discharging through a discharge port of the distal end portion and injecting the discharge hardening material into at least a distal end portion in a gap between the outer surface of the tubular anchor material and the inner surface of the anchor hole formed by the drilling; By curing the injection-hardened material, at least the distal end portion of the tubular anchor material is fixed to the ground, and the head of the tubular anchor material is fixed to the surface of the existing lining. A fixing step, and thereafter, a new lining step of newly lining the surface of the existing lining, and thereafter, a hardening material is discharged into the fixed tubular anchor material and the base end portion. A second injection step of injecting, through an outlet, at least into a cavity between the back surface of the existing lining and the ground surface, and a method of repairing the existing lining.

【0010】第2の発明は、地山を覆う既設覆工物の補
修工法において、先端ビットを備えるとともに、少なく
とも先端側部分および頭部を除く基端側部分に吐出口を
それぞれ有する管状アンカー材を用いて、前記既設覆工
物を貫通しその背面の地山内まで削孔し、この削孔によ
ってアンカー材をその頭部を残して前記地山内まで挿入
する、管状アンカー材の自削孔挿入工程と、この削孔挿
入した管状アンカー材を引き抜かずに、硬化材を、その
管状アンカー材内および前記先端側部分の吐出口を通し
て吐出させて、吐出硬化材を管状アンカー材外面と前記
削孔により形成されたアンカー孔内面との隙間における
少なくとも先端側部分に対して注入する、第1の注入工
程と、前記第1の注入工程以降であって且つ少なくとも
前記第1の注入工程で注入した硬化材が硬化する前に、
圧気を、前記アンカー材内を通して前記基端側部分の吐
出口のみから吹出させる工程と、前記第1の注入工程の
注入硬化材の硬化により、管状アンカー材の少なくとも
先端側部分を地山に対して定着するとともに、管状アン
カー材の頭部を前記既設覆工物表面に対して定着させ
る、管状アンカー材の定着工程と、しかる後に、前記既
設覆工物表面を新たに覆工する、新規覆工工程と、しか
る後に、硬化材を、前記定着されている管状アンカー材
内および前記基端側部分の吐出口を通して、少なくとも
前記既設覆工物背面と地山表面との間の空洞部に対して
注入する、第2の注入工程と、を含むことを特徴とする
既設覆工物の補修工法である。
According to a second aspect of the present invention, there is provided a method of repairing an existing lining covering a ground, wherein a tubular anchor member having a tip bit and having a discharge port at least in a base end portion excluding at least a tip end portion and a head portion. A hole is drilled through the existing lining to the inside of the ground on the back side of the existing lining, and the anchor material is inserted into the ground while leaving the head thereof by the drilling. Without removing the drilled and inserted tubular anchor material, discharging the stiffening material in the tubular anchor material and through the discharge port at the tip side portion, and discharging the hardened material with the outer surface of the tubular anchor material and the drilling hole. Injecting into at least the tip side portion in the gap between the inner surface of the anchor hole formed by the above and the first injecting step after the first injecting step and at least the first injecting step. Before injecting the hardening material is hardened in,
The step of blowing the compressed air through only the discharge port of the base end portion through the anchor material, and the hardening of the injection hardening material in the first injection step causes at least the distal end portion of the tubular anchor material to be grounded. Fixing the head of the tubular anchor material to the surface of the existing lining, and fixing the tubular anchor material, and then newly lining the surface of the existing lining, Work step, and thereafter, the hardening material, through the discharge port of the anchored tubular anchor material and the base end portion, at least to the cavity between the back surface of the existing lining and the ground surface And a second injecting step of injecting the existing lining.

【0012】また硬化材の注入に関し、相対的に大径の
拡径部を先端側部分に有する内管と、前記拡径部より後
方の内管部分を取り囲み且つ内管に対してその長手方向
に沿って前後スライド自在の外管と、この外管と前記内
管拡径部との間の内管部分を取り囲む可撓性パッカー部
材とを含む、注入管部と、前記内管を前記外管に対して
前後スライド移動させる操作手段とを備え、この操作手
段により前記内管を前記外管に対して後へスライド移動
させることによって、前記内管の拡径部と前記外管との
間で前記可撓性パッカー部材を挟み圧縮して側方に張出
させるように構成したパッカー装置を用い;前記第1の
注入工程における硬化材注入および第2の注入工程にお
ける硬化材注入の少なくとも一方に際し、前記パッカー
装置の注入管部を前記アンカー材の内部流路に挿入した
後、前記操作手段により前記可撓性パッカー部材を側方
に張出させ、その張出したパッカー部材により前記アン
カー材内面と前記注入管部の外面との隙間を塞いだ状態
とし、しかる後に、この閉塞状態を保持しつつ、硬化材
を前記パッカー装置の内管内を通して前記アンカー材内
へ供給することにより、前記第1の注入工程における硬
化材注入および第2の注入工程における硬化材注入の少
なくとも一方を行うことを提案する。
[0012] Further, with respect to the injection of the hardening material, an inner tube having a relatively large-diameter enlarged portion at a distal end portion, and an inner tube portion surrounding the inner tube portion behind the enlarged portion and extending in a longitudinal direction with respect to the inner tube. An outer tube slidable back and forth along a flexible piper member surrounding the inner tube portion between the outer tube and the inner tube enlarged-diameter portion. Operating means for sliding back and forth with respect to the pipe, and sliding the inner pipe backward with respect to the outer pipe by means of this operating means, thereby allowing the inner pipe to move between the enlarged portion of the inner pipe and the outer pipe. Using a packer device configured to sandwich and compress the flexible packer member to project laterally; at least one of the hardening material injection in the first injection step and the hardening material injection in the second injection step At the time, the injection pipe part of the packer device is After being inserted into the internal flow path of the anchor material, the operating means causes the flexible packer member to protrude to the side, and the protruding packer member causes a gap between the inner surface of the anchor material and the outer surface of the injection pipe portion. By supplying the hardening material into the anchor material through the inner tube of the packer device while maintaining the closed state, whereby the hardening material injection in the first injection step and the second hardening material injection are performed. It is proposed to perform at least one of the hardening material injection in the injection step of (1).

【0014】これら注入および圧気吹出しに関し、さら
に具体的な例としては、相対的に大径の拡径部を先端側
部分に有する内管と、前記拡径部より後方の内管部分を
隙間をもって取り囲み、且つ内管に対してその長手方向
に沿って前後スライド自在とされ、且つ側面に圧気吹出
口が形成された外管と、この外管と前記内管拡径部との
間の内管部分を取り囲む可撓性パッカー部材とを含む、
注入管部と、前記内管を前記外管に対して前後スライド
移動させる操作手段とを備え、この操作手段により前記
内管を前記外管に対して後へスライド移動させることに
よって、前記内管拡径部と前記外管との間で前記可撓性
パッカー部材を挟み圧縮して側方に張出させるように構
成したパッカー装置を用い;前記第1の注入工程におけ
る硬化材注入および第2の注入工程における硬化材注入
の少なくとも一方に際し、前記パッカー装置の注入管部
を前記アンカー材の内部流路に挿入した後、前記操作手
段により前記可撓性パッカー部材を側方に張出させ、そ
の張出したパッカー部材により前記アンカー材内面と前
記注入管部の外面との隙間を塞いだ状態とし、しかる後
に、この閉塞状態を保持しつつ、硬化材を前記パッカー
装置の内管内を通して前記アンカー材内へ供給すること
により、前記第1の注入工程における硬化材注入および
第2の注入工程における硬化材注入の少なくとも一方を
行うとともに、前記第1の注入工程以降であって且つ少
なくとも前記第1の注入工程で注入した硬化材が硬化す
る前に、圧気を、前記内管と外管との隙間を通して前記
圧気吹出口から前記外管の外面と前記アンカー材の内面
との隙間に吹出させ、この吹出圧気を、更に前記アンカ
ー材基端側部分の吐出口から吹出させることを提案す
る。
Regarding the injection and the blow-out of the compressed air, as a more specific example, an inner pipe having a relatively large-diameter enlarged portion at a distal end portion, and an inner pipe portion behind the enlarged portion are provided with a gap. An outer pipe surrounding and being slidable back and forth with respect to the inner pipe in the longitudinal direction thereof and having a compressed air outlet formed on a side surface; and an inner pipe between the outer pipe and the inner pipe enlarged portion. A flexible packer member surrounding the portion.
An injection pipe portion; and an operating means for sliding the inner pipe back and forth with respect to the outer pipe. The operating means causes the inner pipe to slide backward with respect to the outer pipe, whereby the inner pipe is moved. Using a packer device configured to sandwich and compress the flexible packer member between the enlarged diameter portion and the outer tube so as to protrude laterally; hardening material injection and second injection in the first injection step At least one of the hardening material injection in the injection step of, after inserting the injection pipe portion of the packer device into the internal flow path of the anchor material, the operating means to extend the flexible packer member to the side, The overhanging packer member closes the gap between the inner surface of the anchor material and the outer surface of the injection pipe portion. Thereafter, while keeping this closed state, the hardened material is passed through the inner pipe of the packer device. And supplying at least one of the hardening material in the first injecting step and the hardening material in the second injecting step, and at least after the first injecting step and Before the hardening material injected in the first injection step hardens, pressurized air is passed through the gap between the inner pipe and the outer pipe from the compressed air outlet to the gap between the outer surface of the outer pipe and the inner face of the anchor material. It is proposed that the air is blown out and that the blown-out air is further blown out from a discharge port of the anchor material base end side portion.

【0015】<作用>本発明の主たるポイントは、アン
カー材を自身先端の削孔ビットにより削孔しつつ背面地
山内まで挿入する点にある。すなわち、本発明は、アン
カー挿入とそのアンカー孔の削孔とを同時に行う、自削
孔挿入を特徴事項とするものである。したがって、本発
明では、アンカー挿入に先立って予めアンカー孔を削孔
しなくとも良く、その分手間数を減らすことができる。
また後述するようにアンカー挿入に先立って予めアンカ
ー孔を削孔する場合であっても、その下孔に沿ってアン
カー材を自削孔挿入することで、下孔の一部崩壊等に関
係無く、アンカー材を円滑に挿入できる。
<Operation> The main point of the present invention lies in that the anchor material is drilled by the drill bit at the tip of the anchor material and inserted into the back ground. That is, the present invention is characterized by self-cutting hole insertion in which the anchor insertion and the drilling of the anchor hole are performed simultaneously. Therefore, according to the present invention, it is not necessary to drill the anchor hole before inserting the anchor, and the number of labors can be reduced by that amount.
Also, even when the anchor hole is pre-drilled prior to anchor insertion as described later, by self-drilling the anchor material along the prepared hole, regardless of partial collapse of the prepared hole, etc. , The anchor material can be inserted smoothly.

【0016】[0016]

【発明の実施の形態】以下、本発明の実施の形態につい
て添付図面を参照しつつ詳説する。<空洞部等の検出>
施工に際して初めに、既設覆工物背面のどの箇所に空洞
が生じているかを正確に特定する必要がある。空洞を特
定する公知の手段としては、例えば、超音波の反射波を
利用して検出する方法、空洞と他の箇所との熱放射の違
いを熱赤外線カメラで検出して特定する方法、ハンマー
で覆工物を叩き、その際の音を聞き分けて経験によって
検出する方法等がある。これらはいずれも公知の方法で
あるので、ここでは敢えて説明を略す。空洞の位置が特
定されたならば、その部位に以下に述べるように新規に
アンカーを設ける。
Embodiments of the present invention will be described below in detail with reference to the accompanying drawings. <Detection of cavities etc.>
At the time of construction, it is necessary to accurately identify where on the back of the existing lining the hollow is formed. As a known means for specifying the cavity, for example, a method of detecting using a reflected wave of ultrasonic waves, a method of detecting and specifying the difference in heat radiation between the cavity and other parts by using a thermal infrared camera, a method using a hammer There is a method of hitting a lining, hearing the sound at that time, and detecting it by experience. Since these are all known methods, the explanation is omitted here. Once the location of the cavity has been identified, a new anchor is provided at that location as described below.

【0017】<管状アンカー材の削孔挿入工程> 本発明では、例えば図1に示すような、先端ビット1B
を備えるとともに、この先端ビット1Bの先端面と頭部
1Hを除く基端側部分とに、内外に連通する先端吐出口
PH,…および基端側吐出口BH1〜BH3をそれぞれ
形成した管状アンカー材(以下、単にアンカー材ともい
う)1を新規アンカーとして用いる。頭部1Hは非挿入
部分であり、アンカー材1の挿入深さ等に応じて適宜長
さを定める。また、図示例では、基端側吐出口BH1〜
BH3を長手方向に間隔を空けて複数設けており、これ
らのうちいずれかが次述の挿入後において、既設覆工物
背面と地山表面との間の空洞部と略同じ深さ方向位置に
くるようになっている。
<Step of Inserting Hole into Tubular Anchor Material> In the present invention, for example, as shown in FIG.
... and a tubular anchor member having distal end outlets PH, ... and proximal end outlets BH1 to BH3 formed in the distal end surface of the distal end bit 1B and the proximal end portion excluding the head 1H, respectively. (Hereinafter, also simply referred to as anchor material) 1 is used as a new anchor. The head 1H is a non-insertion portion, and its length is appropriately determined according to the insertion depth of the anchor member 1 and the like. Further, in the illustrated example, the base end side discharge ports BH1 to BH1
A plurality of BH3s are provided at intervals in the longitudinal direction, and one of them is located at the same depth direction position as the cavity between the back surface of the existing lining and the ground surface after the insertion described below. It comes to come.

【0018】そして図3に示すように、かかる管状アン
カー材1により既設覆工物C1を貫通してその背面の地
山BG内まで削孔し、この削孔によって管状アンカー材
1をその頭部1Hを残して地山BG内まで挿入する。図
示例では圧気を先端ビット1Bの先端吐出口から吹出し
て、この吹出しエアに乗せて削孔屑をアンカー材1外面
とアンカー孔壁AH1との隙間S1から既設覆工物C1
表面側へ排出させる、いわゆるエア削孔を採用してい
る。2は削岩機を示している。
As shown in FIG. 3, the tubular anchor 1 penetrates through the existing lining C1 and drills a hole in the ground BG on the back side thereof. Insert into the ground BG leaving 1H. In the illustrated example, compressed air is blown out from the discharge end of the tip bit 1B, and the drilled air is put on the blown air to remove drilling dust from the gap S1 between the outer surface of the anchor material 1 and the anchor hole wall AH1.
The so-called air drilling that discharges to the surface side is adopted. 2 indicates a rock drill.

【0019】かかるエア削孔を行う場合、基端側吐出口
BH1〜BH3からも削孔エアを吹出させてしまうと、
その吹出しエアが削孔屑の排出を妨げるように作用し、
削孔屑の排出が円滑に行われない。そこで、図1および
図2に示すように、管状アンカー材1内にエア供給用内
管3を挿入し、かつこのエア供給用内管3を先端吐出孔
PH,…にのみ連通させた状態として、削孔エアを、こ
のエア供給用内管3の内部流路3Fを通して先端吐出口
PH,…のみから吹出させつつ削孔を行うのが好まし
い。この例ではエア供給用内管3の先端面3aを、先端
ビット1B背面の先端吐出口への入口面1bに突き合わ
せ状態で直接接続しているが、図4に示すように、エア
供給用内管3の先端出口3aを、最先端側の基端側吐出
口BH1と先端吐出口の入口1bとの間のアンカー材1
内に臨ませ、エア供給用内管3の内部流路3Fと先端吐
出口の入口1bとをアンカー材内流路1Fの一部分を介
して間接的に接続することもできる。この場合、エア供
給用内管3の少なくとも先端部30の外周面をアンカー
材内周面に密着させる(図示例では、エア供給用内管3
の先端部30の外周面にシールリングRを巻付けて密着
シールしている)。
When such air drilling is performed, drilling air is also blown from the base end side discharge ports BH1 to BH3.
The blowing air acts to prevent the discharge of drilling debris,
Discharge of drilling debris is not performed smoothly. Therefore, as shown in FIGS. 1 and 2, the air supply inner pipe 3 is inserted into the tubular anchor member 1 and the air supply inner pipe 3 is communicated only with the tip end discharge holes PH,. It is preferable that the drilling is performed while the drilling air is blown out only from the tip discharge ports PH,... Through the internal flow path 3F of the inner pipe 3 for supplying air. In this example, the distal end surface 3a of the air supply inner pipe 3 is directly connected to the inlet surface 1b to the distal end discharge port on the back surface of the distal end bit 1B, but as shown in FIG. The distal end outlet 3a of the pipe 3 is connected to the anchor member 1 between the base end side discharge port BH1 on the foremost side and the front end discharge port entrance 1b.
The internal flow path 3F of the air supply inner pipe 3 and the inlet 1b of the distal end discharge port can be indirectly connected via a part of the anchor material flow path 1F. In this case, the outer peripheral surface of at least the distal end portion 30 of the air supply inner tube 3 is brought into close contact with the anchor material inner peripheral surface (in the illustrated example, the air supply inner tube 3
A seal ring R is wound around the outer peripheral surface of the distal end portion 30 for tight sealing.

【0020】また、図1および図2に示す例のエア供給
内管3の基端部には、アンカー材1と削岩機2とを接続
する接続部4が取付けられている。この接続部4は先端
側にナット部4aを有し、アンカー材1の基端部周面に
形成されたネジ部1Nの外側に螺合するようなってい
る。この接続前の状態が図1に、接続後の状態が図2に
示されている。
A connecting portion 4 for connecting the anchor material 1 and the rock drill 2 is attached to the base end of the air supply inner pipe 3 in the example shown in FIGS. The connection portion 4 has a nut portion 4a on the distal end side, and is screwed to the outside of a thread portion 1N formed on the peripheral surface of the base end portion of the anchor material 1. The state before the connection is shown in FIG. 1, and the state after the connection is shown in FIG.

【0021】削孔挿入が完了したならば、図5に示すよ
うにアンカー材1を引き抜かずに残して、その挿入した
状態のアンカー材1から削岩機2および接続部4を含む
エア供給用内管3を取り外す(図5には取り外した状態
を示している)。
When the drilling is completed, as shown in FIG. 5, the anchor material 1 is left without being pulled out, and the rock drill 2 and the air supply including the connection portion 4 are removed from the anchor material 1 in the inserted state. The inner tube 3 is removed (FIG. 5 shows a state where the inner tube 3 is removed).

【0022】<第1の注入工程> 次に図6に示すように、この削孔挿入した管状アンカー
材1を引き抜かずに、硬化材G1を、その管状アンカー
材1内および先端側部分の吐出口PH,…を通して吐出
させる。この吐出硬化材G1は、管状アンカー材1とア
ンカー孔AHとの隙間S1における少なくとも先端側部
分に対して注入充填する。さらに通常の場合には、図中
G11として示すように注入硬化材は隙間周囲の背面地
山BG内にも浸透する。
<First Injection Step> Next, as shown in FIG. 6, the hardened material G1 is discharged into the tubular anchor material 1 and the distal end portion without pulling out the drilled and inserted tubular anchor material 1. Discharge through outlets PH, ... The discharge hardening material G1 is injected and filled into at least the front end portion in the gap S1 between the tubular anchor material 1 and the anchor hole AH. Further, in a normal case, the injection hardening material also penetrates into the back ground BG around the gap as shown by G11 in the drawing.

【0023】ここで、好適には図7〜9に示す第1のパ
ッカー装置5または図10に示す第2のパッカー装置5
0を用いて注入を行う。先ず両パッカー装置5,50の
共通点について説明すると、それらはいずれも次のよう
な構成を有するものである。
Here, preferably, the first packer device 5 shown in FIGS. 7 to 9 or the second packer device 5 shown in FIG.
Inject using 0. First, the common features of the two packer devices 5 and 50 will be described. Both of them have the following configuration.

【0024】すなわち、相対的に大径の拡径部6aを先
端側部分に有する内管6と、拡径部6aより後方の内管
部分を隙間をもって取り囲み、且つ内管6に対してその
長手方向に沿って前後スライド自在とされた外管7と、
この外管7の先端面と内管拡径部6aの後端面との間の
内管部分を取り囲む筒状の可撓性パッカー部材5Pとを
含む、注入管部8を備えるとともに、内管6を外管7に
対して前後スライド移動させるワンタッチ操作手段9を
備えたものである。
That is, the inner tube 6 having a relatively large-diameter enlarged portion 6a at the distal end portion and the inner tube portion behind the enlarged diameter portion 6a are surrounded with a gap, and the inner tube 6 has a longitudinal direction. An outer tube 7 slidable back and forth along the direction,
An injection pipe portion 8 including a tubular flexible packer member 5P surrounding the inner pipe portion between the front end face of the outer pipe 7 and the rear end face of the inner pipe enlarged portion 6a; Is provided with one-touch operation means 9 for sliding the front and rear with respect to the outer tube 7.

【0025】このワンタッチ操作手段9は、より詳細に
は、外管7に対して取付けられた軸部材周りに揺動する
ハンドル9Hと、このハンドル9Hの揺動に応じて内管
6を外管7に対して前後スライド移動させるリンク機構
部9Rとからなり、ハンドル9Hの揺動によりリンク機
構部9Rを介して内管6を外管7に対して後へスライド
移動させることによって、内管6の拡径部6aの後端面
と外管7の先端面との間で可撓性パッカー部材5Pを挟
み圧縮して側方に膨張させ張出させることができるよう
に構成したものである。
More specifically, the one-touch operation means 9 comprises a handle 9H swinging around a shaft member attached to the outer tube 7 and an inner tube 6 in response to the swing of the handle 9H. And a link mechanism 9R that slides back and forth with respect to the inner tube 6. The inner tube 6 is slid rearward with respect to the outer tube 7 via the link mechanism 9R by swinging of the handle 9H. The flexible packer member 5P is sandwiched between the rear end surface of the enlarged diameter portion 6a and the front end surface of the outer tube 7 so that the flexible packer member 5P can be expanded and laterally expanded.

【0026】かくして、このワンタッチ操作手段9によ
り、図8に示すように内管6を外管7に対して後へスラ
イド移動させることによって、内管6の拡径部6aと外
管7先端面との間で可撓性パッカー部材5Pを挟み圧縮
して側方に膨張させ張出させることができる。
Thus, the one-touch operation means 9 causes the inner pipe 6 to slide backward with respect to the outer pipe 7 as shown in FIG. The flexible packer member 5 </ b> P can be sandwiched and compressed between them to expand and expand laterally.

【0027】このように、両パッカー装置5,50はパ
ッカー部材5Pの張出し機構において異なるところはな
く(相違する構造については後述する。)、双方ともに
ワンタッチでパッカー部材5Pを張出させることができ
るものであるので、ナットを締めつけていくことでパッ
カーを張出させる公知のタイプの装置と比べて格段に迅
速かつ容易にパッカー張出しを行うことができる利点を
有する。しかし、本発明ではもちろん従来のナット締め
タイプのもの(前掲特公平5−22775号の第5図参
照)を用いることもできる。
As described above, there is no difference between the two packer devices 5 and 50 in the extension mechanism of the packer member 5P (a different structure will be described later), and both can extend the packer member 5P with one touch. Therefore, there is an advantage that the packer can be extended much more quickly and easily as compared with a known type device in which the packer is extended by tightening the nut. However, in the present invention, a conventional nut-tightening type (see FIG. 5 of Japanese Patent Publication No. 5-22775) can be used.

【0028】注入に際しては、先ず、可撓性パッカー部
材5Pが側方に張出していない状態で、パッカー装置5
の注入管部8をアンカー材1内に挿入する。この際、パ
ッカー部材5Pの張出状態を示す図9から理解できるよ
うに、注入管部8のパッカー部材5Pが少なくともアン
カー材1の最先端側の基端側吐出口BH1を塞ぎうる位
置、すなわち好ましくは最先端側の基端側吐出口BH1
よりも先端側に位置させる。しかる後、図9に示すよう
に、ワンタッチ操作手段9によりパッカー部材5Pを側
方に張出させ、その張出したパッカー部材5Pによりア
ンカー材1の内面と注入管部8の外面との隙間S2を塞
いだ状態とする。その上で、この閉塞状態を保持しつ
つ、硬化材G1をパッカー装置5の内管6内を通してア
ンカー材1内へ供給する。硬化材G1はアンカー材1内
を通り、先端吐出口PH,…のみから吐出される。
At the time of injection, first, in a state where the flexible packer member 5P does not protrude to the side, the packer device 5P is opened.
Is inserted into the anchor material 1. At this time, as can be understood from FIG. 9 showing the projecting state of the packer member 5P, a position where the packer member 5P of the injection pipe portion 8 can close at least the base end side discharge port BH1 on the most distal end side of the anchor material 1, that is, Preferably, the most proximal side outlet port BH1
More distally. Thereafter, as shown in FIG. 9, the packer member 5P is extended laterally by the one-touch operation means 9, and the gap S2 between the inner surface of the anchor member 1 and the outer surface of the injection pipe portion 8 is formed by the extended packer member 5P. It is in the closed state. Then, the hardening material G1 is supplied into the anchor material 1 through the inner pipe 6 of the packer device 5 while maintaining the closed state. The hardening material G1 passes through the anchor material 1 and is discharged only from the distal end discharge ports PH,.

【0029】かくして、硬化材G1を、アンカー材1内
を介して先端吐出口PH,…のみから吐出させ、アンカ
ー材1外面とアンカー孔内面AH1との隙間S1に対し
て注入充填することができる。
Thus, the hardening material G1 can be discharged from only the distal end discharge ports PH,... Through the inside of the anchor material 1, and can be injected and filled into the gap S1 between the outer surface of the anchor material 1 and the inner surface AH1 of the anchor hole. .

【0030】ところで、かかるアンカー材先端部のみの
硬化材注入において、注入量が多すぎるもしくは注入ス
ピードが速すぎることなどが原因で、注入した硬化材が
アンカー材1の基端側吐出口BH1〜BH3を閉塞して
しまうことがある。これでは、後述する第2の注入工程
において円滑な硬化材注入ができなくなったり、あるい
は注入不能となったりすることが想定される。これに対
して、前述第1のパッカー装置5を用いると、この閉塞
を防止することができる。
In the injection of the hardening material only at the tip of the anchor material, the injected hardening material is too large or the injection speed is too high. BH3 may be blocked. In this case, it is supposed that smooth injection of the hardening material becomes impossible or impossible in the second injection step described later. On the other hand, if the first packer device 5 is used, this blockage can be prevented.

【0031】すなわち図9に詳細に示すように、第1の
パッカー装置5では、第2のパッカー装置50と異な
り、外管7の先端側に圧気吹出口7a,7aを形成する
とともに、この圧気吹出口に対して内管6外面と外管7
内面との隙間S3を介して連通する圧気供給口9aをワ
ンタッチ操作手段9に設けており、少なくとも前述第1
の注入工程以降であって且つその注入硬化材の硬化前
に、好適には第1の注入直後に、圧気を圧気供給口9a
および隙間S3を通して圧気吹出口7a,7aから外管
7外面とアンカー材1内面との隙間S4に吹出させ、こ
の吹出圧気を、更にアンカー材1の基端側吐出口BH1
〜BH3から吹出させて、それら基端側吐出口BH1〜
BH3ならびにこれに連通する隙間S4,S3等を塞い
でいる未硬化の硬化材を吹き飛ばすことができる。かく
して、第1の注入による硬化材G1によりアンカー材1
の基端側吐出口BH1〜BH3への連通路が塞がってし
まうのを防止できる。なお、図6の工程図にはこの第1
のパッカー装置5が示されている。注入後、パッカー装
置5はアンカー材から引き抜かれる。
That is, as shown in detail in FIG. 9, in the first packer device 5, unlike the second packer device 50, compressed air outlets 7a, 7a are formed at the distal end side of the outer tube 7, and the compressed air Outer surface of inner tube 6 and outer tube 7
The one-touch operation means 9 is provided with a compressed air supply port 9a which communicates with the inner surface via a gap S3.
After the injection step and before the injection hardening material is cured, preferably immediately after the first injection, the compressed air is supplied to the compressed air supply port 9a.
And the gap S3 is blown from the compressed air outlets 7a, 7a to the gap S4 between the outer surface of the outer tube 7 and the inner surface of the anchor member 1, and the blown air is further discharged to the base end discharge port BH1 of the anchor member 1.
BH3 to the base end discharge ports BH1 to BH3.
It is possible to blow off the uncured hardening material that blocks the BH3 and the gaps S4, S3, etc. communicating with the BH3. Thus, the anchor material 1 is provided by the hardened material G1 obtained by the first injection.
Can be prevented from blocking the communication path to the base end side discharge ports BH1 to BH3. Note that the process chart of FIG.
Is shown. After injection, the packer device 5 is withdrawn from the anchor material.

【0032】<硬化待ち> 一方、前述の第1の注入工程で注入した硬化材G1の硬
化により、管状アンカー材1の先端側部分が地山に対し
て固定されるのを待つ。
<Wait for Hardening> On the other hand, the hardening of the hardening material G1 injected in the above-described first injection step waits until the distal end portion of the tubular anchor material 1 is fixed to the ground.

【0033】<管状アンカー材の緊張定着工程> 第1の注入による硬化材G1が硬化したならば、図11
に示すように、既設覆工物C1表面から突出する管状ア
ンカー材1の頭部1Hに対して、アンカー挿通孔10a
を有する支圧板10を通し、次いでそのアンカー材頭部
1H周面に形成されたネジ部1N(図11には示してい
ない)にテンションナット11を螺合させ締付ける。こ
れにより、テンションナット11がアンカー材1を介し
て地山BGに反力を取りつつ、支圧板10を既設覆工物
C1表面に圧接させる。かくして、管状アンカー材頭部
1Hを既設覆工物C1表面に対して定着させるととも
に、地山BGと既設覆工物C1とに跨って固定された管
状アンカー材1に作用する緊張力によって、地山BGと
既設覆工物C1とを強固に一体化することができる。
<Tension fixing step of tubular anchor material> When the hardening material G1 is hardened by the first injection, FIG.
As shown in the figure, the anchor insertion hole 10a is inserted into the head 1H of the tubular anchor member 1 protruding from the surface of the existing lining C1.
Then, the tension nut 11 is screwed into a screw portion 1N (not shown in FIG. 11) formed on the peripheral surface of the anchor material head 1H and tightened. As a result, the tension plate 11 presses the support plate 10 against the surface of the existing lining C1 while taking a reaction force against the ground BG via the anchor material 1. Thus, the head 1H of the tubular anchor material is fixed to the surface of the existing lining C1, and the ground acting on the tubular anchor 1 fixed across the ground BG and the existing lining C1 is ground. The mountain BG and the existing lining C1 can be firmly integrated.

【0034】<新規覆工工程> 次に、図12に示すように、既設覆工物C1表面を新た
に覆工し、新規覆工物C2を構築する。新規覆工におい
ては、アンカー材頭部1Hが突出しているのを埋め殺す
ために、図示例のようにモルタル類を用いた吹き付け工
法を採用するのが好ましい。また、特に吹き付けの際に
は、次述する第2の注入のために、管状アンカー材1の
基端面の開口部1Cにキャップ12(ゴム製が好適)を
嵌めておき、このキャップ12の基端部が露出するよう
に、新規吹き付けを行うのが好ましい。しかし他のコン
クリートブロック等による覆工を行っても良い。
<New Covering Step> Next, as shown in FIG. 12, the surface of the existing covering C1 is newly covered to construct a new covering C2. In the new lining, it is preferable to adopt a spraying method using mortars as shown in the illustrated example in order to bury the protrusion of the anchor material head 1H. In particular, at the time of spraying, a cap 12 (preferably made of rubber) is fitted into the opening 1C of the base end surface of the tubular anchor material 1 for the second injection described below. It is preferable to perform a new spray so that the end is exposed. However, lining with another concrete block or the like may be performed.

【0035】<第2の注入工程> 新規覆工が完了したならば、図13に示すように、硬化
材を、緊張定着されている管状アンカー材1内およびア
ンカー材1の基端側部分の吐出口BH1〜BH3を通し
て、既設覆工物C1背面と地山BG表面との間の空洞部
Hに対して注入充填する。
<Second Injection Step> When the new lining is completed, as shown in FIG. 13, the hardened material is removed from the tensioned and fixed tubular anchor material 1 and the base end portion of the anchor material 1. The cavity H between the back surface of the existing lining C1 and the surface of the ground BG is injected and filled through the discharge ports BH1 to BH3.

【0036】図示例では、前述キャップ12を新規覆工
物C2表面側から取り外して、新規覆工物C2表面側か
らその内部に埋め殺されたアンカー材1の基端面開口部
1Cに連通する注入孔13を形成する。しかる後、前述
の第2のパッカー装置50(もちろん、第1のパッカー
装置5を用いても良い。)を用い、その注入管部8を新
規覆工物C2の注入孔13に挿入するとともに、パッカ
ー部材5Pを張出させ注入孔13の口元の隙間を塞いだ
上で硬化材の注入を行う。
In the illustrated example, the cap 12 is removed from the front side of the new lining C2, and the injection is conducted from the front side of the new lining C2 to the base end opening 1C of the anchor material 1 embedded therein. A hole 13 is formed. Then, using the above-mentioned second packer device 50 (of course, the first packer device 5 may be used), the injection pipe portion 8 is inserted into the injection hole 13 of the new lining C2, and After the packer member 5P is extended to close the gap at the mouth of the injection hole 13, the hardening material is injected.

【0037】この際、複数あるアンカー材1の基端側吐
出口BH1〜BH3のいずれか(図示例ではBH3)
が、既設覆工物C1背面と地山BG表面との間の空洞部
Hと略同じ深さ方向位置にくるので、主にその基端側吐
出口BH3から空洞部Hに対して、ならびに主に他の基
端側吐出口BH1,…BH2,…からアンカー材1外面
とアンカー孔内面AH1との隙間S1における前述第1
の注入により注入しなかった残部に対する注入充填が行
われる。またこの際、通常の場合には、図中G22とし
て示すように注入硬化材は隙間S1および空洞部H周囲
の背面地山BG内にも浸透する。
At this time, one of the plurality of base end side discharge ports BH1 to BH3 of the anchor member 1 (BH3 in the illustrated example).
Comes in the same depth direction as the cavity H between the back surface of the existing lining C1 and the surface of the ground BG, and therefore, mainly from the base end side discharge port BH3 to the cavity H. , BH2,..., BH2,... In the gap S1 between the outer surface of the anchor member 1 and the inner surface AH1 of the anchor hole.
Injection filling is performed for the remaining portion that has not been injected by the injection. At this time, in a normal case, the injection hardening material also penetrates into the back ground BG around the gap S1 and the cavity H as indicated by G22 in the drawing.

【0038】<後処理> 必要に応じて、前述第2の注入に際して使用した、新規
覆工物C2表面の前述キャップ12により形成された残
孔13にモルタル類Mを充填し、新規覆工物C2表面が
孔のない平坦な面となるようにコテ仕上げをする。
<Post-treatment> If necessary, mortars M are filled in the residual holes 13 formed by the cap 12 on the surface of the new lining C2 used for the second injection, and the mortar M is filled with the mortar M. Finish ironing so that the C2 surface becomes a flat surface without holes.

【0039】<その他> (イ)他方、本発明では、アンカー材の自削孔挿入に先
だって予備削孔を行い、アンカー予定位置にアンカー下
孔を形成しておくことができる。この場合、アンカー材
による自削孔の削孔径よりも大径の孔を削孔しておくの
が好ましい。
<Others> (A) On the other hand, in the present invention, preliminary drilling is performed prior to insertion of the self-cutting hole of the anchor material, and an anchor pilot hole can be formed at the expected anchor position. In this case, it is preferable to drill a hole larger in diameter than the hole diameter of the self-drilling hole by the anchor material.

【0040】かかる予備削孔を行うと、予備削孔とアン
カー材の自削孔挿入とを行うので二度手間になるもの
の、その後のアンカー材の自削孔による挿入が容易にな
る。また、予備削孔を行ったのに、アンカー材挿入前に
アンカー孔が多少崩壊してしまっていたりすることが良
くあることについては前述したが、本発明ではアンカー
材を自削孔により挿入するので、そのような場合にも従
来例のようにアンカー材を挿入できないことは実質的に
なく、円滑な挿入が可能である。
When the preliminary drilling is performed, the preliminary drilling and the insertion of the self-cutting hole of the anchor material are performed twice, which is troublesome, but the subsequent insertion of the anchor material by the self-cutting hole becomes easy. In addition, although the preliminary drilling was performed, it has been described that the anchor hole is often slightly collapsed before the anchor material is inserted, but in the present invention, the anchor material is inserted by the self-drilling hole. Therefore, even in such a case, there is substantially no possibility that the anchor material cannot be inserted unlike the conventional example, and smooth insertion is possible.

【0041】(ロ)上記例では、アンカー材1の先端部
固定ならびにアンカー材1とアンカー孔AHとの隙間S
1充填のための注入(第1の注入)と、既設覆工物C1
背面の空洞部H充填のための注入(第2の注入)とを二
回に分けて行っている。しかし、本発明はこれに限定さ
れず、例えば前述第1の注入において、先端吐出口P
H,…ならびに基端側吐出口BH1〜BH3の両方から
硬化材を吐出させ、それら両対象部位への注入を同時的
に行い、前述キャップ取付、第2の注入工程、ならびに
後処理を省略することができる。
(B) In the above example, the distal end portion of the anchor member 1 is fixed and the gap S between the anchor member 1 and the anchor hole AH is fixed.
1. Injection for filling (first injection) and existing lining C1
The injection for filling the cavity H on the back surface (second injection) is performed twice. However, the present invention is not limited to this. For example, in the above-described first injection, the tip discharge port P
H,... And the curable material is discharged from both of the base-side discharge ports BH1 to BH3, and simultaneously injected into both target portions, and the cap mounting, the second injection step, and the post-processing are omitted. be able to.

【0042】(ハ)上記例では、アンカー材1先端部の
地山に対する定着を硬化材G1の注入により行うことと
したが、本発明の範囲において他の公知の方法により、
アンカー材先端部を地山に定着させることができる。
(C) In the above example, the fixing of the distal end portion of the anchor material 1 to the ground is performed by injecting the hardening material G1, but within the scope of the present invention, by other known methods,
The tip of the anchor material can be fixed to the ground.

【0043】(ニ)また、上記例ではアンカー材1を緊
張することとしたが、過度の緊張力が既設覆工物C1の
空洞部Hを有する部分に作用すると、当該部分が破壊す
ることが想定される。したがって、テンションナット1
1を締め付け過ぎず、単にアンカー材頭部1Hが既設構
造物C1表面に接する程度でも良い。
(D) In the above example, the anchor member 1 is tensioned. However, if excessive tension acts on the portion having the hollow portion H of the existing lining C1, the portion may break. is assumed. Therefore, tension nut 1
1, the anchor material head 1H may simply be in contact with the surface of the existing structure C1.

【0044】[0044]

【発明の効果】以上のとおり、本発明によれば、作業手
間数が減るとともに、アンカー材の挿入を容易かつ円滑
に行うことができるようになり、もって作業能率の向上
を図ることができる。
As described above, according to the present invention, the number of working steps can be reduced, and the insertion of the anchor member can be performed easily and smoothly, so that the working efficiency can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る、アンカー材およびエア供給用内
管を示す、縦断面図である。
FIG. 1 is a longitudinal sectional view showing an anchor material and an air supply inner pipe according to the present invention.

【図2】アンカー材にエア供給用内管を取付けた状態を
示す、縦断面図である。
FIG. 2 is a longitudinal sectional view showing a state where an air supply inner pipe is attached to an anchor member.

【図3】自削孔工程を示す、一部縦断面図である。FIG. 3 is a partial vertical sectional view showing a self-drilling step.

【図4】エア供給用内管の他の例を示す、縦断面図およ
び要部拡大図である。
FIG. 4 is a longitudinal sectional view and a main part enlarged view showing another example of the air supply inner pipe.

【図5】地削孔工程終了後の状態を示す、一部縦断面図
である。
FIG. 5 is a partial longitudinal sectional view showing a state after a ground drilling step is completed.

【図6】第1の注入工程を示す、一部縦断面図である。FIG. 6 is a partial longitudinal sectional view showing a first injection step.

【図7】第1のパッカー装置を示す、一部縦断面図であ
る。
FIG. 7 is a partial vertical sectional view showing the first packer device.

【図8】そのパッカー膨出状態を示す、一部縦断面図で
ある。
FIG. 8 is a partial longitudinal sectional view showing the packer swelling state.

【図9】図8の要部拡大図である。FIG. 9 is an enlarged view of a main part of FIG. 8;

【図10】第2のパッカー装置を示す、一部縦断面図で
ある。
FIG. 10 is a partial vertical sectional view showing a second packer device.

【図11】管状アンカー材の緊張定着工程を示す、一部
縦断面図である。
FIG. 11 is a partial longitudinal sectional view showing a tension fixing step of the tubular anchor member.

【図12】新規覆工工程を示す、一部縦断面図である。FIG. 12 is a partial longitudinal sectional view showing a new lining process.

【図13】第2の注入工程を示す、一部縦断面図であ
る。
FIG. 13 is a partial longitudinal sectional view showing a second injection step.

【図14】仕上げ工程を示す、一部縦断面図である。FIG. 14 is a partial longitudinal sectional view showing a finishing step.

【符号の説明】[Explanation of symbols]

1…管状アンカー材、BH1〜BH3…基端側吐出口、
PH…先端吐出口、3…エア供給用内管、5…第1のパ
ッカー装置、50…第2のパッカー装置、9…ワンタッ
チ操作手段、C1…既設覆工物、C2…新規覆工物、B
G…地山。
1: tubular anchor material, BH1 to BH3: base end side discharge port,
PH: tip discharge port, 3: inner pipe for air supply, 5: first packer device, 50: second packer device, 9: one-touch operation means, C1: existing lining, C2: new lining, B
G: Ground mountain.

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 5/80 E02D 17/20 104 E21D 20/00 ──────────────────────────────────────────────────続 き Continued on front page (58) Field surveyed (Int.Cl. 7 , DB name) E02D 5/80 E02D 17/20 104 E21D 20/00

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】地山を覆う既設覆工物の補修工法におい
て、 先端ビットを備えるとともに、少なくとも先端側部分お
よび頭部を除く基端側部分に吐出口をそれぞれ有する管
状アンカー材を用い、前記管状アンカー材内の流路にエ
ア供給用内管を挿入し、かつこのエア供給用内管を前記
先端側部分の吐出口にのみ連通させた状態として、削孔
エアを、このエア供給用内管を通して前記先端部の吐出
口のみから吹出させて、前記既設覆工物を貫通しその背
面の地山内まで削孔し、この削孔によってアンカー材を
その頭部を残して前記地山内まで挿入する、管状アンカ
ー材の自削孔挿入工程と、 この削孔挿入した管状アンカー材を引き抜かずに、硬化
材を、その管状アンカー材内および前記先端側部分の吐
出口を通して吐出させて、吐出硬化材を管状アンカー材
外面と前記削孔により形成されたアンカー孔内面との隙
間における少なくとも先端側部分に対して注入する、第
1の注入工程と、 この注入硬化材の硬化により、管状アンカー材の少なく
とも先端側部分を地山に対して定着するとともに、管状
アンカー材の頭部を前記既設覆工物表面に対して定着さ
せる、管状アンカー材の定着工程と、 しかる後に、前記既設覆工物表面を新たに覆工する、新
規覆工工程と、 しかる後に、硬化材を、前記定着されている管状アンカ
ー材内および前記基端側部分の吐出口を通して、少なく
とも前記既設覆工物背面と地山表面との間の空洞部に対
して注入する、第2の注入工程と、 を含むことを特徴とする既設覆工物の補修工法。
1. A method of repairing an existing lining covering a ground, wherein a tubular anchor material having a tip bit and having a discharge port at least in a base end portion excluding a tip end portion and a head portion is used. Insert the air supply inner pipe into the flow path in the tubular anchor material, and place the air supply inner pipe in communication with only the discharge port at the tip side portion, and cut the drilling air into the air supply inner pipe. The pipe is blown out only from the discharge port at the tip portion through a pipe, penetrates the existing lining, and drills a hole in the ground on the back side, and inserts the anchor material into the ground with the drilling leaving the head part. Self-cutting hole insertion process of the tubular anchor material, and discharging the hardening material through the discharge port in the tubular anchor material and the tip side portion without pulling out the drilled and inserted tubular anchor material. Tube material A first injection step of injecting at least a distal end portion in a gap between the outer surface of the anchor material and the inner surface of the anchor hole formed by the drilling, and at least the distal end side of the tubular anchor material by curing the injection hardening material. Fixing the portion to the ground and fixing the head of the tubular anchor material to the surface of the existing lining, and fixing the tubular anchor material, and thereafter, the surface of the existing lining is renewed. Lining, a new lining step, and thereafter, the hardening material is passed through the discharge port in the anchored tubular anchor material and the base end portion, and at least the back surface of the existing lining material and the ground surface A second injecting step of injecting into a cavity between the two. A method of repairing an existing lining, comprising:
【請求項2】地山を覆う既設覆工物の補修工法におい
て、 先端ビットを備えるとともに、少なくとも先端側部分お
よび頭部を除く基端側部分に吐出口をそれぞれ有する管
状アンカー材を用いて、前記既設覆工物を貫通しその背
面の地山内まで削孔し、この削孔によってアンカー材を
その頭部を残して前記地山内まで挿入する、管状アンカ
ー材の自削孔挿入工程と、 この削孔挿入した管状アンカー材を引き抜かずに、硬化
材を、その管状アンカー材内および前記先端側部分の吐
出口を通して吐出させて、吐出硬化材を管状アンカー材
外面と前記削孔により形成されたアンカー孔内面との隙
間における少なくとも先端側部分に対して注入する、第
1の注入工程と、 前記第1の注入工程以降であって且つ少なくとも前記第
1の注入工程で注入した硬化材が硬化する前に、圧気
を、前記アンカー材内を通して前記基端側部分の吐出口
のみから吹出させる工程と、 前記第1の注入工程の注入硬化材の硬化により、管状ア
ンカー材の少なくとも先端側部分を地山に対して定着す
るとともに、管状アンカー材の頭部を前記既設覆工物表
面に対して定着させる、管状アンカー材の定着工程と、 しかる後に、前記既設覆工物表面を新たに覆工する、新
規覆工工程と、 しかる後に、硬化材を、前記定着されている管状アンカ
ー材内および前記基端側部分の吐出口を通して、少なく
とも前記既設覆工物背面と地山表面との間の空洞部に対
して注入する、第2の注入工程と、 を含むことを特徴とする既設覆工物の補修工法。
2. A method for repairing an existing lining material covering a ground, comprising using a tubular anchor material having a tip bit and having a discharge port at least at a base end portion excluding a tip end portion and a head portion, Self-cutting hole insertion process of a tubular anchor material, which penetrates the existing lining and drills a hole in the ground on the back surface thereof, and inserts the anchor material into the ground while leaving the head thereof by the drilling; Without pulling out the drilled and inserted tubular anchor material, the stiffening material was discharged through the discharge port in the tubular anchor material and the tip side portion, and the discharged stiffening material was formed by the outer surface of the tubular anchor material and the drilled hole. A first injecting step of injecting at least a tip side portion in a gap between the inner surface of the anchor hole and an injecting step after the first injecting step and at least in the first injecting step Before the curing material is cured, a step of blowing compressed air through only the discharge port of the base end portion through the anchor material, and by curing the injection-cured material in the first injection step, at least the tubular anchor material Fixing the tip side portion to the ground, fixing the head of the tubular anchor material to the surface of the existing lining, and fixing the tubular anchor material. A new lining step for newly lining; and thereafter, a hardening material is passed through at least the back of the existing lining and the ground surface through the discharge port in the fixed tubular anchor material and the base end portion. A second injection step of injecting into the cavity between the steps (a) and (b).
【請求項3】相対的に大径の拡径部を先端側部分に有す
る内管と、前記拡径部より後方の内管部分を取り囲み且
つ内管に対してその長手方向に沿って前後スライド自在
の外管と、この外管と前記内管拡径部との間の内管部分
を取り囲む可撓性パッカー部材とを含む、注入管部と、 前記内管を前記外管に対して前後スライド移動させる操
作手段とを備え、 この操作手段により前記内管を前記外管に対して後へス
ライド移動させることによって、前記内管の拡径部と前
記外管との間で前記可撓性パッカー部材を挟み圧縮して
側方に張出させるように構成したパッカー装置を用い; 前記第1の注入工程における硬化材注入および第2の注
入工程における硬化材注入の少なくとも一方に際し、前
記パッカー装置の注入管部を前記アンカー材の内部流路
に挿入した後、前記操作手段により前記可撓性パッカー
部材を側方に張出させ、その張出したパッカー部材によ
り前記アンカー材内面と前記注入管部の外面との隙間を
塞いだ状態とし、 しかる後に、この閉塞状態を保持しつつ、硬化材を前記
パッカー装置の内管内を通して前記アンカー材内へ供給
することにより、前記第1の注入工程における硬化材注
入および第2の注入工程における硬化材注入の少なくと
も一方を行う、請求項1または2記載の既設覆工物の補
修工法。
3. An inner tube having a relatively large-diameter enlarged portion at a distal end portion, and an inner tube portion surrounding the inner tube portion behind the enlarged portion and sliding back and forth along the longitudinal direction with respect to the inner tube. An infusion tube section including a free outer tube, and a flexible packer member surrounding the inner tube portion between the outer tube and the inner tube enlarged portion; Operating means for slidably moving the inner pipe backward with respect to the outer pipe by means of the operating means, whereby the flexibility between the enlarged diameter portion of the inner pipe and the outer pipe is increased. A packer device configured to sandwich and compress the packer member so as to protrude laterally; at least one of the hardening material injection in the first injection process and the hardening material injection in the second injection process, the packer device Flow through the injection pipe section After that, the flexible packer member is extended laterally by the operating means, and the extended packer member closes the gap between the inner surface of the anchor material and the outer surface of the injection pipe portion. Then, while maintaining the closed state, the hardening material is supplied into the anchor material through the inner pipe of the packer device, so that the hardening material is injected in the first injection process and the hardening material injection in the second injection process. The method for repairing an existing lining according to claim 1 or 2, wherein at least one of the following is performed.
【請求項4】相対的に大径の拡径部を先端側部分に有す
る内管と、前記拡径部より後方の内管部分を隙間をもっ
て取り囲み、且つ内管に対してその長手方向に沿って前
後スライド自在とされ、且つ側面に圧気吹出口が形成さ
れた外管と、この外管と前記内管拡径部との間の内管部
分を取り囲む可撓性パッカー部材とを含む、注入管部
と、 前記内管を前記外管に対して前後スライド移動させる操
作手段とを備え、 この操作手段により前記内管を前記外管に対して後へス
ライド移動させることによって、前記内管拡径部と前記
外管との間で前記可撓性パッカー部材を挟み圧縮して側
方に張出させるように構成したパッカー装置を用い; 前記第1の注入工程における硬化材注入および第2の注
入工程における硬化材注入の少なくとも一方に際し、前
記パッカー装置の注入管部を前記アンカー材の内部流路
に挿入した後、前記操作手段により前記可撓性パッカー
部材を側方に張出させ、その張出したパッカー部材によ
り前記アンカー材内面と前記注入管部の外面との隙間を
塞いだ状態とし、 しかる後に、この閉塞状態を保持しつつ、硬化材を前記
パッカー装置の内管内を通して前記アンカー材内へ供給
することにより、前記第1の注入工程における硬化材注
入および第2の注入工程における硬化材注入の少なくと
も一方を行うとともに、 前記第1の注入工程以降であって且つ少なくとも前記第
1の注入工程で注入した硬化材が硬化する前に、圧気
を、前記内管と外管との隙間を通して前記圧気吹出口か
ら前記外管の外面と前記アンカー材の内面との隙間に吹
出させ、この吹出圧気を、更に前記アンカー材基端側部
分の吐出口から吹出させる、請求項1または2記載の既
設覆工物の補修工法。
4. An inner tube having a relatively large-diameter enlarged portion at a distal end portion and an inner tube portion behind the enlarged portion with a gap therebetween, and extending along the longitudinal direction with respect to the inner tube. Including an outer tube slidable back and forth and having a compressed air outlet on a side surface, and a flexible packer member surrounding an inner tube portion between the outer tube and the inner tube enlarged portion. A pipe portion; and operating means for sliding the inner pipe back and forth with respect to the outer pipe. The operating means causes the inner pipe to slide backward with respect to the outer pipe, thereby expanding the inner pipe. Using a packer device configured to sandwich and compress the flexible packer member between a diameter portion and the outer tube so as to protrude laterally; hardening material injection in the first injection step and second At least one of the hardening material injection in the injection step, After inserting the injection pipe portion of the packing device into the internal flow path of the anchor material, the flexible packer member is extended laterally by the operation means, and the anchor material inner surface and the anchor material are extended by the extended packing member. The first injection is performed by supplying a hardening material into the anchor material through the inner pipe of the packer device while keeping the closed state with the gap between the outer surface of the injection pipe portion and the closed state. Performing at least one of the hardening material injection in the step and the hardening material injection in the second injecting step, and before the hardening material injected in the first injecting step is hardened after the first injecting step. The compressed air is blown out from the compressed air outlet through the gap between the inner pipe and the outer pipe into the gap between the outer surface of the outer pipe and the inner surface of the anchor material. The method for repairing an existing lining according to claim 1 or 2, wherein the lining is blown out from a discharge port at a base end side portion of the anchor material.
JP07907499A 1999-03-24 1999-03-24 Repair method of existing lining Expired - Lifetime JP3359588B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07907499A JP3359588B2 (en) 1999-03-24 1999-03-24 Repair method of existing lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07907499A JP3359588B2 (en) 1999-03-24 1999-03-24 Repair method of existing lining

Publications (2)

Publication Number Publication Date
JP2000273862A JP2000273862A (en) 2000-10-03
JP3359588B2 true JP3359588B2 (en) 2002-12-24

Family

ID=13679755

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07907499A Expired - Lifetime JP3359588B2 (en) 1999-03-24 1999-03-24 Repair method of existing lining

Country Status (1)

Country Link
JP (1) JP3359588B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6895842B2 (en) * 2017-07-31 2021-06-30 大成建設株式会社 Ground improvement method
JP7497254B2 (en) * 2020-09-02 2024-06-10 株式会社イノアック住環境 How to repair slopes

Also Published As

Publication number Publication date
JP2000273862A (en) 2000-10-03

Similar Documents

Publication Publication Date Title
KR100919821B1 (en) Ground enhansing apparatus with anchor rod and method thereof
KR100852724B1 (en) Supporting tube assembly for tunnel grouting including plastic extension tube with cutting grooove and friction resistance enriched surface and tunnel supporting method of using thereof
JP3359588B2 (en) Repair method of existing lining
JP3493014B2 (en) Tunnel widening method
JP3347685B2 (en) Packer equipment
KR100616359B1 (en) Support-pipe using method of soil nailing
KR100498536B1 (en) Method for costructing anchors under the ground using high pressure grouting
KR100756536B1 (en) Grout same time injection apparatus and a method of construction type reinforcement steel pipe
JP3382873B2 (en) How to insert the tube
KR20050008343A (en) Multistage grouting apparatus and method using casing and packer
JP3851590B2 (en) Preceding ground mountain consolidation method using self-drilling bolt and FRP bolt
KR200263955Y1 (en) Nailing device that use spiral style pipe
JPH11172667A (en) High-pressure injection ground-improvement method
JPH11200750A (en) Excavation bit for winding hole and execution method using it
JP2842236B2 (en) Grout injection method into back of underground continuous wall and its injection device
JP2005105776A (en) Enlarged excavating bit in pile installation by inner excavation
JPH01131715A (en) Ground improving work by horizontal injection of chemical grout
JP7311894B2 (en) Ground reinforcement method
KR100472059B1 (en) Mortar full-filling method reformed with a reinforced protective umbrella method
JP2001182496A (en) Water leakage measure of tunnel
JP2004183444A (en) Slope reinforcing method
KR102368274B1 (en) grouting device with packer cover device
JP3125052B2 (en) Crack injection aid
KR200331999Y1 (en) Multistage grouting apparatus using casing and packer
JP4414844B2 (en) Reinforcement method of natural ground

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081011

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091011

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101011

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111011

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111011

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121011

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121011

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131011

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141011

Year of fee payment: 12

EXPY Cancellation because of completion of term