JP3291502B2 - Embankment - Google Patents

Embankment

Info

Publication number
JP3291502B2
JP3291502B2 JP10044593A JP10044593A JP3291502B2 JP 3291502 B2 JP3291502 B2 JP 3291502B2 JP 10044593 A JP10044593 A JP 10044593A JP 10044593 A JP10044593 A JP 10044593A JP 3291502 B2 JP3291502 B2 JP 3291502B2
Authority
JP
Japan
Prior art keywords
embankment
girder
hook
rod
horizontal line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP10044593A
Other languages
Japanese (ja)
Other versions
JPH06287956A (en
Inventor
恭一 生駒
良信 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takiron Co Ltd
Original Assignee
Takiron Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=14274128&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=JP3291502(B2) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Takiron Co Ltd filed Critical Takiron Co Ltd
Priority to JP10044593A priority Critical patent/JP3291502B2/en
Publication of JPH06287956A publication Critical patent/JPH06287956A/en
Application granted granted Critical
Publication of JP3291502B2 publication Critical patent/JP3291502B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、盛土、特に急勾配の法
面を備えた盛土の施工に用いられる盛土用法枠に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an embankment, and more particularly to an embankment embankment used for embankment having a steep slope.

【0002】[0002]

【従来の技術】特開昭59−52024号公報による
と、従来、急勾配の法面を有する盛土を施工するとき
に、盛土施工場所に天然繊維や化繊で作った前後に長い
ネットを敷き、そのネットの前端部に近い前後方向の中
間部に、土や砂を袋に詰めた土嚢を所定高さに積み上
げ、積み上げた土嚢を上記ネットの前端部側で包み込ん
でその前端部を土嚢の後方に折り返すと共に、土嚢の後
方空間を土で埋めて1段目の土層を形成し、次に、1段
目の土層の上に別のネットを敷き、そのネットの上に土
嚢を積み上げ、積み上げた土嚢を上記ネットの前端部側
で包み込んでその前端部を土嚢の後方に折り返すと共
に、土嚢の後方空間を土で埋めて2段目の土層を形成
し、この後、同じ作業を繰り返すという施工方法が知ら
れている。
2. Description of the Related Art According to JP-A-59-52024, conventionally, when embankment having a steep slope is constructed, a long net is laid before and after the embankment construction site, made of natural fiber or synthetic fiber. At the middle part in the front-rear direction near the front end of the net, sandbags filled with bags of soil and sand are piled up to a predetermined height, the stacked sandbags are wrapped around the front end of the net, and the front end is placed behind the sandbag. At the same time, the back space of the sandbag is filled with soil to form the first layer of soil layer, and then another net is laid on the first layer of soil layer, and the sandbag is stacked on the net. The piled sandbags are wrapped around the front end of the net and the front end is turned back to the back of the sandbags, and the space behind the sandbags is filled with soil to form a second layer of soil layer, and thereafter, the same operation is repeated. The construction method is known.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、土嚢と
ネットとを用いた従来の施工方法を採用すると、土嚢の
運搬や積上げに多くの人手と労力を必要とし、また、ネ
ットでその上に置いた土嚢を包み込むといった作業に熟
練と長時間を要するという問題があった。
However, when the conventional construction method using a sandbag and a net is adopted, a large amount of manpower and labor is required for transporting and stacking the sandbag, and the sandbag is placed on the net. There has been a problem that it takes skill and a long time to wrap the sandbag.

【0004】本発明は以上の状況の下でなされたもので
あり、土嚢を用いる必要性を無くし、しかも運搬が容易
で、施工後には法面を確実に補強してその崩壊事故を起
こりにくくすることのできる盛土用法枠を提供すること
を目的とする。
[0004] The present invention has been made under the above circumstances, eliminates the need for using sandbags, is easy to transport, and reliably reinforces the slope after construction to prevent collapse accidents. The purpose of the present invention is to provide an embankment legal framework that can be used.

【0005】[0005]

【課題を解決するための手段】請求項1の発明による盛
土用法枠は、盛土中に略水平に埋設される桁材と、桁材
に対して傾倒自在に軸支されかつ桁材の先端部から立ち
上げられて盛土の法面に配備される桟部材と、桁材と桟
部材との間に亘って介在されて桁材に対する桟部材の立
上り角度を規制しかつ盛土中に埋設される支杆と、を備
えていると共に、支杆の一端部に桁材の適所に対する掛
止部が設けられ、支杆の他端部に、縦線と横線を溶接し
た溶接金網よりなる上記桟部材の一本の横線を上下に跨
ぎかつ相隣接する2本の縦線を左右に跨ぐ状態でそれら
の横線と縦線とに巻き付いて係止する係合部が設けられ
ているものである。
According to a first aspect of the present invention, there is provided a method for embankment embankment, comprising: a girder buried substantially horizontally in the embankment; And a support member interposed between the girder members and the girder member for regulating the rising angle of the birth member with respect to the girder member and being buried in the embankment. A rod is provided, and at one end of the support rod, a hook is provided at an appropriate position of the girder member. At the other end of the support rod, the bar member is formed of a welding wire mesh formed by welding a vertical line and a horizontal line. An engaging portion is provided which wraps around a horizontal line and a vertical line so as to straddle one horizontal line vertically and straddle two adjacent vertical lines right and left and straddle the adjacent vertical lines.

【0006】請求項2の発明による盛土用法枠は、請求
項1に記載したものにおいて、桁材の先端部と桟部材の
下端部とに、水平に配備される連結棒に対して掛止可能
な鉤形部がそれぞれ設けられ、これらの鉤形部を上記連
結棒に掛止することによって桁材と桟部材とが傾倒自在
に軸支されており、桟部材の上端部に、上段側に配備さ
れる桟部材の下端部と共働して水平に配備される別の連
結棒を保持する鉤形係合部が設けられているものであ
る。
The embankment frame according to the second aspect of the present invention is the embankment frame according to the first aspect, which can be hooked to a connecting rod horizontally disposed at a tip end of a girder member and a lower end of a beam member. Hook-shaped portions are provided, and the beam members and the bar member are pivotally supported by tilting by hooking these hook-shaped portions on the connecting rod, and at the upper end side of the bar member, A hook-shaped engaging portion for holding another connecting rod horizontally disposed in cooperation with the lower end of the beam member to be disposed is provided.

【0007】[0007]

【作用】請求項1に記載した発明による盛土用法枠によ
ると、支杆の長さを変えるか、あるいは支杆の掛止部と
桁材との掛止箇所や支杆の係合部と桟部材の係止箇所を
適宜選択することにより桁材に対する桟部材の立上り角
度を調節すれば、桁材の傾きを法面の傾斜に合わせるこ
とが可能である。このため、法面が急勾配であっても緩
勾配であっても適用することが可能である。そして、盛
土の滑り落ちに対しては桁材がそれに対抗し、盛土の滑
り落ちに伴う法面の迫り出しに対しては桟部材がそれに
対抗する。
According to the embankment fill frame according to the first aspect of the present invention, the length of the support rod is changed, or the position where the support portion of the support rod is engaged with the girder material, or the engagement portion of the support rod and the crosspiece are connected. By adjusting the rising angle of the cross member with respect to the beam by appropriately selecting the locking position of the member, the inclination of the beam can be adjusted to the inclination of the slope. For this reason, the present invention can be applied whether the slope is steep or gentle. The girder member opposes the sliding of the embankment, and the bar member opposes the approach of the slope due to the sliding of the embankment.

【0008】請求項2に記載した発明による盛土用法枠
によると、桁材と桟部材と支杆とを分解した状態で運搬
することが可能である。
According to the embankment frame according to the second aspect of the invention, it is possible to transport the beam, the crosspiece and the support rod in a disassembled state.

【0009】[0009]

【実施例】図1は本発明の実施例による盛土用法枠Aの
施工状態を示す部分断面図である。この法枠Aは同図の
ように上下多段に配設されるものであって、盛土中に略
水平に埋設される桁材1と、桁材1に対して傾倒自在に
軸支されかつ桁材1の先端部から立ち上げられて盛土G
の法面Sに配備される桟部材2と、桁材1と桟部材2と
の間に亘って介在されて桁材1に対する桟部材2の立上
り角度を規制しかつ盛土中に埋設される支杆3と、を備
えている。
FIG. 1 is a partial sectional view showing an embankment embankment A according to an embodiment of the present invention. The frame A is arranged in multiple stages in the vertical direction as shown in the figure, and includes a girder 1 buried substantially horizontally in an embankment, Embankment G started from the tip of timber 1
And a support member interposed between the girder member 1 and the girder member 2 to regulate the rising angle of the girder member 2 with respect to the girder member 1 and to be embedded in the embankment. And a rod 3.

【0010】図2〜図6のいずれかから類推できるよう
に、桁材1は比較的太い縦線11と横線12とを溶接し
て接合することにより形成された溶接金網でなり、その
先端部すなわち各縦線11の先端部に鉤形に屈曲された
鉤形部13が設けられ、また、その後端部すなわち各縦
線11の後端部に折返し状に屈曲された係合保持部14
が設けられている。他方、桟部材2も縦線21と横線2
2とを溶接して接合することにより形成された溶接金網
でなり、その下端部すなわち各縦線21の下端部に鉤形
に屈曲された鉤形部23が設けられ、また、桟部材2の
上端部すなわち各縦線21の上端部に鉤形に屈曲された
鉤形係合部24が設けられている。そして、桁材1およ
び桟部材2のそれぞれの鉤形部13,23を、水平に配
備された連結棒4に掛止することによって桁材1と桟部
材2とが傾倒自在に軸支されている。
As can be inferred from any of FIGS. 2 to 6, the girder 1 is a welded wire mesh formed by welding and joining a relatively thick vertical line 11 and a horizontal line 12, and the leading end thereof That is, a hook-shaped portion 13 bent in a hook shape is provided at a front end portion of each vertical line 11, and an engagement holding portion 14 bent in a folded shape at a rear end portion, that is, a rear end portion of each vertical line 11.
Is provided. On the other hand, the cross member 2 also has a vertical line 21 and a horizontal line 2.
2 is formed by welding and joining, and a hook-shaped portion 23 bent in a hook shape is provided at a lower end portion thereof, that is, a lower end portion of each vertical wire 21. At the upper end, that is, at the upper end of each vertical line 21, a hook-shaped engaging portion 24 bent in a hook shape is provided. The hooks 13 and 23 of the beam 1 and the bar 2 are hooked on the connecting rod 4 disposed horizontally so that the beam 1 and the bar 2 are pivotally supported so as to be tiltable. I have.

【0011】図4および図5に詳細に示したように、支
杆3はその一端部がU字形に折り曲げられて掛止部31
となされ、また、その他端部が正面視形状が波形をなす
ように折り曲げられた係合部32となされている。そし
て、支杆3の係合部32が図4のように桟部材2におけ
る所定の縦線21と所定の横線22とに巻付き状に掛止
されているのに対し、支杆3の掛止部31が図5のよう
に桁材1の所定の横線12に掛止されている。図4で判
るように、支杆3の係合部32は、桟部材2の一本の横
線22aを上下に跨ぐ状態でその横線22aに巻き付い
ていると共に、相隣接する2本の縦線21a,21aの
それぞれを左右に跨ぐ状態でその縦線21a,21aに
巻き付いている。したがって、桟部材2と支杆3とは支
杆3の係合部32を介して上下左右に動かないように連
結されている。また、支杆3の掛止部31は図5のよう
に桁材1の所定の横線12に下方から係合されている。
As shown in detail in FIGS. 4 and 5, one end of the support rod 3 is bent into a U-shape, and
The other end portion is formed as an engaging portion 32 which is bent so that the shape in a front view forms a waveform. 4, while the engaging portion 32 of the support rod 3 is wound around a predetermined vertical line 21 and a predetermined horizontal line 22 of the cross member 2 as shown in FIG. The stop part 31 is hooked on the predetermined horizontal line 12 of the beam 1 as shown in FIG. As can be seen in FIG. 4, the engaging portion 32 of the support rod 3 is wound around the horizontal line 22a in a state of straddling one horizontal line 22a of the cross member 2 up and down, and two adjacent vertical lines 21a. , 21a are wound around the vertical lines 21a, 21a in a state of straddling each of the right and left sides. Therefore, the crosspiece 2 and the support rod 3 are connected via the engaging portion 32 of the support rod 3 so as not to move up, down, left and right. The engaging portion 31 of the support rod 3 is engaged with a predetermined horizontal line 12 of the beam 1 from below as shown in FIG.

【0012】上記支杆3は盛土中に埋設されているの
で、上記のようにして支杆3により桁材1と桟部材2と
が連結されていると、桁材1に対する桟部材2の立上り
角度が支杆3により規制される。ここで、支杆3の掛止
部31を桁材1におけるより前側の横線12に掛止させ
たり、支杆3の係合部32を桟部材2におけるより下側
で縦線21や横線22に係合させたりすると、桁材1に
対する桟部材2の立上り角度が大きくなり、その逆に、
支杆3の掛止部31を桁材1におけるより後側の横線1
2に掛止させたり、支杆3の係合部32を桟部材2にお
けるより上側で縦線21や横線22に係合させたりする
と、桁材1に対する桟部材2の立上り角度が小さくな
る。また、桟部材2の立上り角度は支杆3として長さの
異なるものを用いることによっても変更することができ
る。これらの方法を適宜採用して桟部材2の立上り角度
を調節することにより、桟部材2の傾きを法面Sの傾き
に合わせることが可能である。
Since the supporting rod 3 is buried in the embankment, when the beam 1 and the beam 2 are connected by the supporting rod 3 as described above, the rise of the beam 2 with respect to the beam 1 The angle is regulated by the support rod 3. Here, the engaging portion 31 of the support rod 3 is engaged with the horizontal line 12 on the front side of the girder member 1, and the engaging portion 32 of the support rod 3 is connected to the vertical line 21 or the horizontal line 22 below the bar member 2. , The rising angle of the cross member 2 with respect to the girder 1 increases, and conversely,
The hooking portion 31 of the support rod 3 is connected to the horizontal line 1
2, or when the engaging portion 32 of the support rod 3 is engaged with the vertical line 21 or the horizontal line 22 above the bar member 2, the rising angle of the bar member 2 with respect to the girder member 1 decreases. Further, the rising angle of the crosspiece member 2 can be changed by using the supporting rods 3 having different lengths. By adjusting the rising angle of the beam member 2 by appropriately employing these methods, the inclination of the beam member 2 can be adjusted to the inclination of the slope S.

【0013】また、図1〜図3のように、桟部材2の鉤
形係合部24は、上段側に配備された桟部材2の下端部
と共働して、水平または略水平に配備された別の連結棒
5を挾んで保持している。ここで、図2や図3によく示
されているように、下段側の桟部材2における鉤形係合
部24と上段側の桟部材2における鉤形部23とはあた
かも算用数字の8字を形作るように交差しており、しか
も上段側の桁材1と桟部材2とを結合している連結棒4
と上記連結棒5とがその8字の2つの孔の中に各別に挿
入された形態になっている。その上、連結棒4が桁材1
の鉤形部13と前後方向(図2に矢符Xで示してある)
で掛止されていると共に、上段側の桟部材2における鉤
形部23によって滑り落ちないように下側から支持され
ているので、下段側の桟部材2が滑り落ちることはな
い。
As shown in FIGS. 1 to 3, the hook-shaped engaging portion 24 of the crosspiece 2 is horizontally or substantially horizontally cooperated with the lower end of the crosspiece 2 disposed on the upper side. The other connecting rod 5 is held therebetween. Here, as is well shown in FIGS. 2 and 3, the hook-shaped engaging portion 24 of the lower bar member 2 and the hook-shaped portion 23 of the upper bar member 2 are as if each of the numerals 8 Connecting rods 4 which intersect so as to form a character, and which connect the upper girder 1 and the crosspiece 2
And the connecting rod 5 are separately inserted into the two figures of eight. In addition, the connecting rod 4 is the girder 1
And the front and rear direction (indicated by an arrow X in FIG. 2)
And is supported from below by the hook-shaped portion 23 of the upper bar member 2 so as not to slide down, so that the lower bar member 2 does not slide down.

【0014】図8のように、同一段で横に並べて配設さ
れる桟部材2,2はそれらの左右方向の端部に位置する
縦線21同士が適所で連結金具6により連結されてい
る。桁材1についても同様である。
As shown in FIG. 8, in the cross members 2, 2 arranged side by side in the same step, the vertical lines 21 located at the ends in the left-right direction thereof are connected to each other by the connecting fitting 6 at an appropriate position. . The same applies to the beam 1.

【0015】図1、図2および図6のように、桁材1に
おける係合保持部14には、合成樹脂製のネット7の端
部を巻き付けて保持させたフラットバー8が嵌め込まれ
て保持されている。そして、このフラットバー8から後
方に上記ネット7が導出されている。このネット7は引
張強度の大きな合成樹脂繊維の撚り線を編み組みしたも
のである。なお、左右方向に並設されるネット7同士は
図示していない連結具を用いて連結されている。
As shown in FIG. 1, FIG. 2 and FIG. 6, a flat bar 8 in which an end of a net 7 made of synthetic resin is wound and held in the engagement holding portion 14 of the girder 1 is held. Have been. The net 7 is led out from the flat bar 8 to the rear. The net 7 is formed by braiding a stranded wire of a synthetic resin fiber having a large tensile strength. It should be noted that the nets 7 arranged side by side in the left-right direction are connected using a connecting tool (not shown).

【0016】次に、上記盛土用法枠Aを用いた盛土の施
工手順の一例を図1を参照して説明する。なお、盛土施
工場所へは、必要数の桁材1、桟部材2、支杆3、フラ
ットバー8およびネット7などが互いに組み付けられて
いないばらばらの状態で搬入される。また、盛土施工場
所は平坦な土面G1を持つようにあらかじめ整地され
る。
Next, an example of an embankment construction procedure using the embankment frame A will be described with reference to FIG. In addition, the required number of girder members 1, crosspieces 2, supporting rods 3, flat bars 8, nets 7, and the like are carried into the embankment construction site in a state where they are not assembled together. The embankment construction site is previously leveled so as to have a flat soil surface G1.

【0017】整地された土面G1に、最下段の桁材1を
設置した後、最下段の連結棒4と桟部材2とを配置する
ことにより、桟部材2を連結棒4を介して桁材1に傾倒
自在に軸支する。そして、支杆3を配設して桁材1に対
する桟部材2の立上り角度を定めることと、フラットバ
ー8を用いて最下段のネット7を桁材1の後方に導出す
ることと、ネット7が敷設された土面G1の上に土を積
み上げてネット7や支杆3や桁材1を埋めることとを行
う。この際、土を投入する途中で適宜土の転圧を行う。
そして、積み上げた土の上面を最下段の桟部材2の上端
部付近にレベル合わせする。
After the lowermost girder 1 is installed on the leveled soil surface G1, the lowermost connecting rod 4 and the crosspiece 2 are arranged, so that the crosspiece 2 is connected via the connecting rod 4. It is pivotably supported on the material 1. Then, the support rod 3 is arranged to determine the rising angle of the cross member 2 with respect to the girder 1, the lowermost net 7 is led out behind the girder 1 using the flat bar 8, Is piled up on the soil surface G1 on which is laid, and the net 7, the support rod 3, and the girder 1 are buried. At this time, the soil is compacted appropriately during the charging of the soil.
Then, the level of the upper surface of the piled soil is adjusted to the vicinity of the upper end of the crosspiece member 2 at the bottom.

【0018】こうして形成した1段目の積上げ土の土面
に、上述したところと同じ要領で桁材1やネット7を配
設すると共に、その桁材1に連結棒4を介して桟部材2
を連結し、さらに支杆3によって桟部材の2の立上り角
度を定める。また、このときに、連結棒5を用いて下段
側の桟部材2と上段側の桟部材2とを連結する。この
後、土を積み上げ、その積上げ土を転圧する。以後は、
同様の作業を繰り返して所定高さの盛土を構築する。
The girder 1 and the net 7 are arranged on the soil surface of the first-stage pile thus formed in the same manner as described above, and the beam 2 is connected to the girder 1 via the connecting rod 4.
And the support rod 3 determines the rising angle of the crosspiece 2. At this time, the connecting member 5 is used to connect the lower bar member 2 and the upper bar member 2. Thereafter, the soil is piled up and the piled soil is compacted. After that,
The same operation is repeated to construct an embankment of a predetermined height.

【0019】以上のようにして構築された盛土において
は、各段の積上げ土の重みが各段の桁材1…に加わるこ
と、各段の積上げ土の土が各段のネット7の網目を埋め
ていること、などによって桁材1…やネット7が盛土と
強固に一体化しており、しかも、盛土Gの法面Sが、各
段の桟部材2…により押さえられ、盛土Gの滑り落ちに
対しては桁材1…がそれに対抗し、盛土Gの滑り落ちに
伴う法面Sの迫り出しに対しては桟部材2…がそれに対
抗するので、きわめて崩壊しにくい法面Sが形成され
る。
In the embankment constructed as described above, the weight of the stacked soil of each step is added to the girder members 1... Of each step, and the soil of the stacked soil of each step forms the mesh of the net 7 of each step. The girder 1 and the net 7 are firmly integrated with the embankment by being buried, and the slope S of the embankment G is pressed down by the bar members 2 of each step, and the embankment G slides down. Against the girder members 1 and against the overhang of the slope S due to the sliding down of the embankment G, the cross members 2. You.

【0020】図1および図2に示した実施例において
は、盛土施工後の植生を促すために、植物の種子や養分
などを保持させた植生マット9を各段の桟部材2…の裏
面側に設けてある。こうしておけば、施工後に植物が法
面S上に茂って桟部材2が目立たなくなる。なお、植生
を行うためには、施工後に種子と土を法面S上に吹き付
けるという方法を採用することも可能である。
In the embodiment shown in FIGS. 1 and 2, in order to promote vegetation after embankment, a vegetation mat 9 holding plant seeds, nutrients, and the like is placed on the back side of the cross members 2. It is provided in. If it does in this way, the plant will grow on the slope S after construction, and the crosspiece 2 will become inconspicuous. In addition, in order to perform vegetation, it is also possible to adopt a method of spraying seeds and soil on the slope S after construction.

【0021】この実施例では、図1や図2で判るよう
に、各段の桟部材2の立上り角度を定めるのに長短2種
類の支杆3…を用いている。これは、一つの桟部材2の
高さが高いことによっており、こうしておけば、背高の
桟部材2を上端部付近と中間部とで支えられるので法面
Sの保持作用が向上する。なお、桟部材2の高さがそれ
ほど高くないときは、図8のように1種類の支杆3で桟
部材2の上端部付近だけを支持させておけばよい。
In this embodiment, as can be seen from FIGS. 1 and 2, two types of long and short support rods 3 are used to determine the rising angle of the crosspiece member 2 at each stage. This is because the height of one crosspiece member 2 is high, and in this case, the tall crosspiece member 2 is supported by the vicinity of the upper end portion and the intermediate portion, so that the holding action of the slope S is improved. When the height of the cross member 2 is not so high, only the vicinity of the upper end portion of the cross member 2 may be supported by one kind of support rod 3 as shown in FIG.

【0022】また、支杆3の係合部32の形状は図4に
示した形状に限定されない。すなわち、この係合部32
は、その形の如何を問わず、桟部材2に具備された横線
22を上下に跨ぎかつ縦線21を左右に跨ぐ状態でそれ
らの横線22と縦線21とに係止可能な形状であればよ
い。
The shape of the engaging portion 32 of the support rod 3 is not limited to the shape shown in FIG. That is, the engagement portion 32
Whatever the shape, any shape can be used to straddle the horizontal line 22 and the vertical line 21 in a state of straddling the horizontal line 22 provided on the crosspiece member 2 vertically and straddling the vertical line 21 left and right. I just need.

【0023】[0023]

【発明の効果】本発明による盛土用法枠によると、土嚢
を用いる必要がないことなどにより短時間で簡便に施工
することが可能になり、そのことが省力化を促進するこ
とに有用であるという効果がある。また、法面が急勾配
であっても緩勾配であっても適用することができ、施工
後には盛土の滑り落ちや法面の迫り出しが防止されて法
面の崩壊が生じにくくなり、さらに施工後の仕上がりが
良好になって外観が美しく保たれるという効果もある。
According to the embankment method according to the present invention, since it is not necessary to use sandbags, it is possible to carry out the construction in a short time and simply, which is useful for promoting labor saving. effective. In addition, it can be applied whether the slope is steep or gentle, and after construction, the embankment is prevented from sliding down and the slope is prevented from protruding, and the slope is less likely to collapse. There is also an effect that the finish after construction is improved and the appearance is kept beautiful.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例による盛土用法枠の施工状態を
示す部分断面図である。
FIG. 1 is a partial cross-sectional view showing a construction state of an embankment frame according to an embodiment of the present invention.

【図2】図1の要部を拡大した断面図である。FIG. 2 is an enlarged sectional view of a main part of FIG.

【図3】図2のIII部を拡大して示す斜視図である。FIG. 3 is an enlarged perspective view showing a part III in FIG. 2;

【図4】図2のIV部を拡大して示す斜視図である。FIG. 4 is an enlarged perspective view showing an IV section of FIG. 2;

【図5】図2のV部を拡大して示す斜視図である。FIG. 5 is an enlarged perspective view showing a portion V in FIG. 2;

【図6】図2のVI部を拡大して示す斜視図である。FIG. 6 is an enlarged perspective view showing a VI section in FIG. 2;

【図7】桟部材などを示す概略正面図である。FIG. 7 is a schematic front view showing a cross member and the like.

【図8】変形例による桟部座などを示す概略正面図であ
る。
FIG. 8 is a schematic front view showing a crosspiece seat and the like according to a modified example.

【符号の説明】[Explanation of symbols]

A 法枠 G 盛土 S 法面 1 桁材 2 桟部材 3 支杆 4 連結棒 5 連結棒 13 桁材の鉤形部 21 桟部材の縦線 22 桟部材の横線 23 桟部材の鉤形部 24 桟部材の鉤形係合部 31 支杆の掛止部 32 支杆の係合部 A Law frame G Embankment S Slope 1 Girder member 2 Beam member 3 Support rod 4 Connection rod 5 Connection rod 13 Hook-shaped portion of girder 21 Vertical line of beam member 22 Horizontal line of bar member 23 Hook-shaped portion of beam member 24 Beam Hook-shaped engaging part of member 31 Latch part of supporting rod 32 Engaging part of supporting rod

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 17/18 ──────────────────────────────────────────────────続 き Continued on the front page (58) Field surveyed (Int.Cl. 7 , DB name) E02D 17/18

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 盛土中に略水平に埋設される桁材と、桁
材に対して傾倒自在に軸支されかつ桁材の先端部から立
ち上げられて盛土の法面に配備される桟部材と、桁材と
桟部材との間に亘って介在されて桁材に対する桟部材の
立上り角度を規制しかつ盛土中に埋設される支杆と、を
備えていると共に、支杆の一端部に桁材の適所に対する
掛止部が設けられ、支杆の他端部に、縦線と横線を溶接
した溶接金網よりなる上記桟部材の一本の横線を上下に
跨ぎかつ相隣接する2本の縦線を左右に跨ぐ状態でそれ
らの横線と縦線とに巻き付いて係止する係合部が設けら
れていることを特徴とする盛土用法枠。
1. A girder material buried substantially horizontally in an embankment, and a beam member rotatably supported on the girder material and raised from a tip end of the girder material and disposed on a slope of the embankment. And a rod interposed between the girder member and the bar member to regulate the rising angle of the bar member with respect to the girder member and buried in the embankment, and at one end of the rod. A hook portion is provided for an appropriate position of the girder material, and at the other end of the supporting rod, one horizontal line of the cross member made of a welding wire mesh formed by welding a vertical line and a horizontal line is vertically straddled and two adjacent ones are adjacent to each other. An embankment frame, comprising an engaging portion which is wound around a horizontal line and a vertical line so as to be engaged with the vertical line so as to straddle the left and right sides.
【請求項2】 桁材の先端部と桟部材の下端部とに、水
平に配備される連結棒に対して掛止可能な鉤形部がそれ
ぞれ設けられ、これらの鉤形部を上記連結棒に掛止する
ことによって桁材と桟部材とが傾倒自在に軸支されてお
り、桟部材の上端部に、上段側に配備される桟部材の下
端部と共働して水平に配備される別の連結棒を保持する
鉤形係合部が設けられている請求項1に記載の盛土用法
枠。
2. A hook which can be hooked to a horizontally disposed connecting rod is provided at a tip end of the beam member and a lower end of the cross member, respectively, and these hooks are connected to the connecting rod. The girder member and the beam member are pivotally supported by being tilted by being hooked on the shaft member, and are horizontally disposed at the upper end of the beam member in cooperation with the lower end portion of the beam member provided on the upper stage side. The method according to claim 1, further comprising a hook-shaped engaging portion for holding another connecting rod.
JP10044593A 1993-04-02 1993-04-02 Embankment Expired - Fee Related JP3291502B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10044593A JP3291502B2 (en) 1993-04-02 1993-04-02 Embankment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10044593A JP3291502B2 (en) 1993-04-02 1993-04-02 Embankment

Publications (2)

Publication Number Publication Date
JPH06287956A JPH06287956A (en) 1994-10-11
JP3291502B2 true JP3291502B2 (en) 2002-06-10

Family

ID=14274128

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10044593A Expired - Fee Related JP3291502B2 (en) 1993-04-02 1993-04-02 Embankment

Country Status (1)

Country Link
JP (1) JP3291502B2 (en)

Also Published As

Publication number Publication date
JPH06287956A (en) 1994-10-11

Similar Documents

Publication Publication Date Title
US6345934B1 (en) Earth structure and method for constructing with supports having rearwardly located portions
KR100698669B1 (en) An element for forming ground covering, restraining and reinforcing structures, and retaining walls
JPH08511590A (en) Module block retaining wall structure and components
US6595726B1 (en) Retaining wall system and method of making retaining wall
JP2001512796A (en) System and method for connecting retaining wall panels to a buried mesh
WO2005012652A1 (en) Composite form for stabilizing earthen embankments
JP3291502B2 (en) Embankment
KR100874961B1 (en) Reinforced earth retaining wall wire mesh
KR20100047485A (en) Slope reinforcement structure with reinforce frame of dividing
GB2295180A (en) Facing panel for earth structures
JP2000199214A (en) Civil engineering construction and construction method therefor
KR100419883B1 (en) Method for constructing green reinforcement slope; R, S Green
KR100794669B1 (en) Wire net for reinforced earth retaining wall and method of constructing the reinforced earth retaining wall utilizing the wire net
JP2529977Y2 (en) Embankment frame
JPH05171644A (en) Banking structure, construction method thereof and construction material
JP2750363B2 (en) Steep embankment
JP2000080654A (en) Reinforced earth work method
JP3056926B2 (en) Slope forming method and slope mold
KR100430245B1 (en) Method for constructing green reinforcement slope R, S Green
KR100847022B1 (en) wire mat for reinforced earth retaining wall
JP3871988B2 (en) Earth retaining frame and earth retaining method using the same
JPH0354184Y2 (en)
JP5986967B2 (en) Divided wall construction wall unit
JPH0533350A (en) Slope frame and filling construction using same
JPH0359220A (en) Steep slope banking and retaining member therefor

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20011211

LAPS Cancellation because of no payment of annual fees